New 230 kV Transmission Line for Thurston County 230 kV Transmission Line for Thurston County ......
Transcript of New 230 kV Transmission Line for Thurston County 230 kV Transmission Line for Thurston County ......
New 230 kV Transmission Linefor Thurston County
Leslie Wright, PMPProject Manager
October 15, 2009
2
Presentation overview
Fundamentals of Electric Systems Electric System Planning Standards Thurston County Transmission Infrastructure Thurston/Pierce Electric System Thurston County Project Need Completed and Planned Transmission Projects Alternative Solutions Increased Capacity Description- New 230 KV
Transmission Line 230 kV Transmission Line Route Selection Overview Public Involvement Request
3
Fundamentals of Electric SystemsHow Power Gets To You
4
Electric System Planning StandardsNERC Regional Councils
5
Thurston County Transmission InfrastructureHow Power gets to Thurston County
6
Thurston/Pierce Electric SystemThurston and Pierce Counties
7
Thurston County Project Need
Demand for power is growing
Not enough transmission to move the power to residences and business in Thurston County
NERC reliability Without additional
transmission capacity, the delivery system will reach NERC non-compliant limits
8
Thurston County Project NeedDec 15 2008 Peak Load - Pierce/Thurston Load Trend
1050 MW Limit
1005 MW Peak
Thurston County Load
Pierce / Thurston Combined Load
9
Completed and Planned Transmission ProjectsTransmission Projects in Thurston County
Completed Projects Olympia Cut-over
Voltage upgrade to 115 kV Loss savings of 220 MWh/year Upgrade of 5 substations Re-build of 2 substations
Planned Projects Thurston / St. Clair 230 kV St. Clair – Yelm 115 kV Olympia Bus Improvements Spurgeon Creek Substation Hoffman Substation
10
Completed and Planned Transmission ProjectsTransmission Projects in Pierce County
Completed Projects Planned Projects
Woodland-St. Clair Phase I Conversion from 55 kV to 115 kV Precursor to the Olympia Cut-over Project
White River 230 kV Bus Upgrade
Alderton Transmission Station Add a new 230 kV tie to AldertonSubstation Expand Alderton Substation into a 230 kV Transmission Station
11
Alternative SolutionsTwo Paths
There are two paths to resolving the electric load requirement for Thurston County Increase capacity - Add Infrastructure Reduce demand - Increase Energy Efficiency and
Conservation
12
Alternative SolutionsIncreased Capacity Alternatives Summary
-This is an interim stop-gap solution
- May defer the larger St. Clair project by 3-5 years.
Replace existing smaller 230 kV transformer with larger capacity
Install a third 115 kV line PSE transmission in BPA Olympia
Upgrade Bulk Power Capacity in BPA Olympia
PSE has indefinitely deferred since route options are very limited …
- Resolves PSE THU capacity limitations
- Acquire about 30 miles of new 230 kV transmission route.
Complete the 230 kV White River –St. Clair project (40 miles) and install
a 230-115 kV transformer
Install 230-115 kV transformer at St. Clair
-Resolves PSE THU capacity limitations
-Not desirable since it limits the robustness of power supply into Thurston county
Construct / upgrade several PSE transmission systems
Install a 3rd 230-115 kV Bank in BPA Olympia
Install a 3rd 230-115 kV transformer at BPA Olympia
Need to Acquire about 5 miles of 100-125 ft new 230 kV transmission route
- Resolves PSE THU capacity limitations-Provides a reliable looped transmission-
Loop BPA 230 kV (about 5 miles) to St. Clair and install 230-115 kV
transformer.
Install 230-115 kV transformer at St. Clair
Route Options / ChallengesPerformance / Local PSE loadProject DescriptionOptions
13
Alternative SolutionsEnergy Efficiency and Conservation
Florescent lighting
Weatherization
High-efficiency heating and cooling
ENERGY STAR®
appliances
14
Increased Capacity DescriptionNew 230 KV Transmission Line from St. Clair Substation
15
230 kV Transmission Line Route Selection Process Overview
Identify study area Identify criteria (built environment, natural environment, and co-
location/engineering/cost) Get public input Data collection – Web Data and Field Observations Criteria weighting Process Identify route segments & candidate routes Computer Model of data, criteria and weights Quantitative and Qualitative Evaluation Selection of preferred and/or alternative routes Public Involvement Selection of preferred route
16
Route Selection Process Overview Typical Evaluation Criteria
Built Environment
• Residential dwellings• Future residential land use• Parcels• Community facilities and recreation
areas • Archaeological resource sites• Historic resource sites• Major land developments
Natural Environment
• Natural resource lands• Protected species and priority
habitats• Forest areas• Forested wetland areas• Non-forested wetlands areas• Aquifer recharge areas• Special management areas• 100-year floodplain • Shorelines• Geological hazard areas
17
Route Selection Process Overview Qualitative Evaluation
Step 2GIS Spatial Analysis of each route segment to compare route segments using
criteria.
Step 1Determine which factors have the highest priority to the project team by
summing all of the pair-wise comparisons for each criterion evaluated in the analysis.
Step 3Run model for each route segment and candidate route to produce resource
value data for the candidate route for each criterion. Apply weighting to yield preferred routes.
Routes with lowest scores have least impact. Consider other non-quantitative factors and their effect.
18
Public Involvement Request
PSE Would Appreciate Your Help To:
Identify Key Issues We Should Consider for Resolving the Thurston County Reliability Situation
Identify and Prioritize Key Factors for Corridor Siting Provide Suggestions Regarding the Public Involvement Process