Wind Farm Project Management isEasy..Right?
John ConnollyManager Wind Farm Development & Construction
-
7/28/2019 National Wind Energy Conference
2/39
Presentation Contents
Introduction to ESBI Engineering Services Provided Total Solution
Need for Project Management
Case Studies
Project Delivery Model
Questions
-
7/28/2019 National Wind Energy Conference
3/39
ESBI Engineering
ESBs largest engineering resource
Working in a diverse range of Disciplines
Over 500 professional engineering and technical staff Engineering Design
Project management
Asset Management Support
Commissioning
Construction Management
Safety Management
Overhaul Management
Etc.
Atrackrecordindeliver
inghighlycomplex
utilityp
rojects
-
7/28/2019 National Wind Energy Conference
4/39
Wind Farm Concept
- Wind Farm Optimisation
- EIA and Planning Support- Grid Connections
Wind Farm Development Support
Programme & Financial Model
Tendering & Procurement
Financial Close
Wind Farm Construction
Project Execution
Wind Farm O&M
Technical Services to operator/owner
Services Provided
-
7/28/2019 National Wind Energy Conference
5/39
Black Banks
10.2MW
Carnsore
11.9MW
Derrybrien 59.5MW
Crokahenny
5MW
Carrane Hill
3.4MW
Mountain Lodge
31.5MW
Mount Eagle
6.8 MW
West Durham
24 MW
8 Commercial Operation 152MW
Hunters Hill
20 MW
Garvagh Glebe
26 MW
Tullynahaw
22 MW
Crockagarran
15 MW
4 Operational Dec 2010 83MW
Betws
44 MW
Cappawhite
44 MW
Carrickatane
22.5 MW
Grouse Lodge
15 MW
Curryfree
15 MW
3 In Construction 96MW
Fullabrook
66 MW
4 In Development 109MW
18 in SEM Pipeline 600+MW
Woodhouse
20 MW
-
7/28/2019 National Wind Energy Conference
6/39
Importance and Role of PM
Windfarm Projects are Complex Commercially Driven Projects
Role of PM is key
Interface & Stakeholder Management People Deliver Projects
-
7/28/2019 National Wind Energy Conference
7/39
1
PROJ ECT DELIVERY MOD EL
Case Study 1
The Millennium DomeThe UK Government White Elephant
Constructed to celebrate the Millennium
Completed on schedule for opening
ceremony 31st
December 1999 Initial estimate 250m
Final cost 750m and 2 Governmentminister resignations
Visitor numbers only 50% of forecast
Closed after 1 year and redundant until
reopened as O2 Arena
Meeting fixed schedules can cost a lot of money
Scope Management and definition of the scope and WBS has to be undertaken asearly as possible
Massive failure of stakeholder management
Lessons Learned
-
7/28/2019 National Wind Energy Conference
8/39
2
PROJECT DELIVERY MODEL
Case Study 2
New Signage System For Dublin
Inner and outer orbital routes
Lesson Learned
Identify key stakeholders. Ignore them at your peril
Design & launched by Dublin Corporation
10% of the signs erected Key stakeholder, Transport Minister Seamus
Brennan not managed.
Plans published 22 August
Project halted by Minister 28 August.
Expected cost of failed project: in excess of10,000s
-
7/28/2019 National Wind Energy Conference
9/39
3
PROJECT DELIVERY MODEL
Case Study 3 - Heathrow Terminal 5
Lessons Learned includes
People are the most important part of any project
majority of issues were people not technology
20 years i n the making first design
milestone - 1989
Construction phase started in 2002 18
ma jor projects
4.3 B illion Budget
260 hectares , 60 Aircraft Stands, C ontrol
Towe r - 87m ..
Over 5km of road & water tunnels.
On ti me & on budget best pra ctice
project
27th March 2008 - Chaos
Avoid Big Bang launches if at all possible; trial days had 2,000; opening day 40,000 passengers
If it can go wrong, it will who was managing the risk log? Were staff, baggage handling, security& car parks on it?
-
7/28/2019 National Wind Energy Conference
10/39
Case Study 4 Lets Get Real
Garvagh Glebe is a 13 WTG Wind Farm in Co. Leitrim Tullynahaw is an 11 WTG Wind Farm in Co. Roscommon
20kV Overhead Interconnector
110kV Overhead Connection to Corderry 110kV Substation
GG was a JV between ESB & Coillte
Both are Peat sites (different depths and slopes)
Managed as a single Project
Construction started in August 2008 Finished..its a long story
-
7/28/2019 National Wind Energy Conference
11/39
-
7/28/2019 National Wind Energy Conference
12/39
Interfaces
-
7/28/2019 National Wind Energy Conference
13/39
Challenges
Planning Grid Connection 110kV & 20kV
Ground Conditions
Stakeholder Management
Programme & Cost
-
7/28/2019 National Wind Energy Conference
14/39
Planning
GG Received Planning in August 2003 / TW in June 2004
CER Grid Moratorium both required extensions
Area of GG was designated NHA post Planning
Bird Breeding Season different in Roscommon & Leitrim
110kV OHL and Substation were 1st Project to SIA
Micro Siting not allowed flexibility
Corderry 110kV Substation
-
7/28/2019 National Wind Energy Conference
15/39
Grid Connection
Critical Path
Contestable Connection
5.7km of 110kV OHL SC
First SIA Minor Modification Major Risk
WTGs erected with no Grid
6.7km 20kV OHL
NHA
Fibre Wrap Material Issues poles & hardware
Weather
-
7/28/2019 National Wind Energy Conference
16/39
January Weather
-
7/28/2019 National Wind Energy Conference
17/39
20kV Interconnector
Designed for radial ice & high wind but.
Greater snow, ice and wind than expected
-
7/28/2019 National Wind Energy Conference
18/39
-
7/28/2019 National Wind Energy Conference
19/39
20kV Interconnector
Designed for radial ice & high wind but.
Greater snow, ice and wind than expected
New design
More material problems
FO & Construction Crew
-
7/28/2019 National Wind Energy Conference
20/39
Ground Conditions
Deep Peat with 5-7 Deg slope - unusual
Peat Slip
Completely new approach to Peat Sites
Developed a Zonal Peat Stability Assessment (ZPSA)
Manage Peat
Lease Agreements
Planning
Long Term
-
7/28/2019 National Wind Energy Conference
21/39
-
7/28/2019 National Wind Energy Conference
22/39
-
7/28/2019 National Wind Energy Conference
23/39
Stakeholder Management
Public Client
Local Media / County Council / Politicians
Our Insurers
Contractors
ManageContin
uouslyN
otJustin
Crisis
-
7/28/2019 National Wind Energy Conference
24/39
Costs & Programme
Known Unknowns
Manage Expectations
Know what your options areKnow the consequences of eachKnow the cost of each
Make
Informe
dDecisions&
GetB
uy-in
-
7/28/2019 National Wind Energy Conference
25/39
-
7/28/2019 National Wind Energy Conference
26/39
Still a Success
Despite the Challenges
3rd Party Issues
Project Delivered to revised Schedule & Budget
Good news
Met Every Challenge
Restored Confidence
-
7/28/2019 National Wind Energy Conference
27/39
-
7/28/2019 National Wind Energy Conference
28/39
The Foundation
-
7/28/2019 National Wind Energy Conference
29/39
-
7/28/2019 National Wind Energy Conference
30/39
-
7/28/2019 National Wind Energy Conference
31/39
-
7/28/2019 National Wind Energy Conference
32/39
-
7/28/2019 National Wind Energy Conference
33/39
-
7/28/2019 National Wind Energy Conference
34/39
-
7/28/2019 National Wind Energy Conference
35/39
-
7/28/2019 National Wind Energy Conference
36/39
Project Delivery Methodology
Enables repeatable, best in classproject delivery
Combines the vast project deliveryexperiences of the
organisation and our people,
with international best practice
Supports our strategy to continueto invest in large scale
generation capital projects
-
7/28/2019 National Wind Energy Conference
37/39
-
7/28/2019 National Wind Energy Conference
38/39
In Conclusion
Spend as much time Planning as Doing
Know who your Stakeholders are manage them
Understand the Commercial Context of Decisions
Keep the Project Moving Forward
Dont Panic!
-