MPWSP Overview Schedule Update2015/08/26  · Updated August 18, 2015 July Aug Sept Oct Nov Dec Jan...

15
MPWSP Overview Schedule & Update Presented to: MPWSP Governance Committee Presented by: Cal Am Date: August 24, 2015 1

Transcript of MPWSP Overview Schedule Update2015/08/26  · Updated August 18, 2015 July Aug Sept Oct Nov Dec Jan...

Page 1: MPWSP Overview Schedule Update2015/08/26  · Updated August 18, 2015 July Aug Sept Oct Nov Dec Jan # GC Meeting Dates 24 16 21 18 1 1 11 9/25 RFP & Draft Contract Released RFP docs,

MPWSP Overview Schedule & Update

Presented to: MPWSP Governance CommitteePresented by: Cal AmDate: August 24, 2015

1

Page 2: MPWSP Overview Schedule Update2015/08/26  · Updated August 18, 2015 July Aug Sept Oct Nov Dec Jan # GC Meeting Dates 24 16 21 18 1 1 11 9/25 RFP & Draft Contract Released RFP docs,
Page 3: MPWSP Overview Schedule Update2015/08/26  · Updated August 18, 2015 July Aug Sept Oct Nov Dec Jan # GC Meeting Dates 24 16 21 18 1 1 11 9/25 RFP & Draft Contract Released RFP docs,

3

MW1

MW3

MW4

Page 4: MPWSP Overview Schedule Update2015/08/26  · Updated August 18, 2015 July Aug Sept Oct Nov Dec Jan # GC Meeting Dates 24 16 21 18 1 1 11 9/25 RFP & Draft Contract Released RFP docs,

4

ShallowMedium

Deep

-1’-1.5’

-4’

Page 5: MPWSP Overview Schedule Update2015/08/26  · Updated August 18, 2015 July Aug Sept Oct Nov Dec Jan # GC Meeting Dates 24 16 21 18 1 1 11 9/25 RFP & Draft Contract Released RFP docs,

MPWSP Conveyance Facilities RFQ Results & RFP Schedule

5

Page 6: MPWSP Overview Schedule Update2015/08/26  · Updated August 18, 2015 July Aug Sept Oct Nov Dec Jan # GC Meeting Dates 24 16 21 18 1 1 11 9/25 RFP & Draft Contract Released RFP docs,

6

Conveyance Facilities RFQ Summary• Seven SOQ’s received on July 2 from:

Garney ConstructionGranite Construction Mountain CascadeMonterey Peninsula EngineeringSteve P. RadosRanger PipelinesW.A. Rasic Construction

• CAW Selection Committee evaluated and scored the SOQ’s based on the technical (70%) and financial criteria (30%) identified in the RFQ.

Page 7: MPWSP Overview Schedule Update2015/08/26  · Updated August 18, 2015 July Aug Sept Oct Nov Dec Jan # GC Meeting Dates 24 16 21 18 1 1 11 9/25 RFP & Draft Contract Released RFP docs,

7

Conveyance Facilities RFQ/RFP

• All seven contractors qualified for RFP stage

• Experienced contractors

• RFP distributed on August 17

• Proposals due October 16

Page 8: MPWSP Overview Schedule Update2015/08/26  · Updated August 18, 2015 July Aug Sept Oct Nov Dec Jan # GC Meeting Dates 24 16 21 18 1 1 11 9/25 RFP & Draft Contract Released RFP docs,

MPWSP Conveyance Facilities Procurement Schedule

8

Page 9: MPWSP Overview Schedule Update2015/08/26  · Updated August 18, 2015 July Aug Sept Oct Nov Dec Jan # GC Meeting Dates 24 16 21 18 1 1 11 9/25 RFP & Draft Contract Released RFP docs,

MPWSP Anticipated Schedule

Updated August 18, 2015

June July August Sept Oct Nov DecGC Meeting Dates#

CANRFP

22

RFQ ReleasedSOQ’s

dueJuly 2

SOQ’sEvaluation

&Qualified

Firms Listed

1724 27 24 16 21 18

9

27

8/17

RFP & Draft ContractReleased

RFP docs, draft contracts, technical specs & drawings finalized

RFP

9/3

Pre-proposalMeeting

9/15

Proposer Comments

Due on Draft

Contract

9/30

Revised ContractIssued

10/16

ProposalsDue

10/30

Notificationof Preferred Proposer

CANContract

13

11/13 2016

23

Contract Executed

Late 2015/Early

2016VE Session 2016

RFQ

CANDraft

Contract

GC Input on Draft 

Contract

GC Input onContract

Page 10: MPWSP Overview Schedule Update2015/08/26  · Updated August 18, 2015 July Aug Sept Oct Nov Dec Jan # GC Meeting Dates 24 16 21 18 1 1 11 9/25 RFP & Draft Contract Released RFP docs,

MPWSP Production WellsProcurement Schedule

10

Page 11: MPWSP Overview Schedule Update2015/08/26  · Updated August 18, 2015 July Aug Sept Oct Nov Dec Jan # GC Meeting Dates 24 16 21 18 1 1 11 9/25 RFP & Draft Contract Released RFP docs,

MPWSP Anticipated Schedule

Updated August 18, 2015

July Aug Sept Oct Nov Dec JanGC Meeting Dates#

24 16 21 18

11

11

9/25

RFP & Draft ContractReleased

RFP docs, draft contracts, technical specs & drawings 

finalized10/23

ProposalsDue

Notificationof Preferred Proposer

11/13 2016

Contract Executed Early Jan

2016

Input onDraft 

Contract

2116

8

GCInput oncontract

CAN RFP CAN Contract

18

Page 12: MPWSP Overview Schedule Update2015/08/26  · Updated August 18, 2015 July Aug Sept Oct Nov Dec Jan # GC Meeting Dates 24 16 21 18 1 1 11 9/25 RFP & Draft Contract Released RFP docs,

MPWSP Alternate Pipeline Overview

12

Page 13: MPWSP Overview Schedule Update2015/08/26  · Updated August 18, 2015 July Aug Sept Oct Nov Dec Jan # GC Meeting Dates 24 16 21 18 1 1 11 9/25 RFP & Draft Contract Released RFP docs,

MPWSP Anticipated Schedule

Blue dots are demand centers.

DEIR Proposed mains each end at Eardley Pump Sta. in PG and use existing main to route to ex. 15 MG storage tanks at Forest Lake in PB.

Alternate Main proceeds over Crest and proceeds to existing main in Carmel Valley and also ends at 15 MG storage tanks at Forest Lake in PB.

Page 14: MPWSP Overview Schedule Update2015/08/26  · Updated August 18, 2015 July Aug Sept Oct Nov Dec Jan # GC Meeting Dates 24 16 21 18 1 1 11 9/25 RFP & Draft Contract Released RFP docs,

MPWSP Anticipated Schedule

0

100

200

300

400

500

600

0 2 4 6 8 10 12 14 16 18 20 22 24

Elevation (feet)

Length (miles)

Profiles of Various MPWSP Pipeline Alignments

DEIR Org. Proposed DEIR Alt Route Alternate Route

HGL‐DEIR Alt HGL‐Alternate Route HGL Org. Proposed

Page 15: MPWSP Overview Schedule Update2015/08/26  · Updated August 18, 2015 July Aug Sept Oct Nov Dec Jan # GC Meeting Dates 24 16 21 18 1 1 11 9/25 RFP & Draft Contract Released RFP docs,

15

Pipe Profile Summary

• Existing Pipe (Age, Hydraulics)

• Power Increase

• Leakage

• ASR Injection