RFP No. 23900-RFP-ES860 GENERAL ENGINEERING & TECHNICAL SERVICES September 22, 2008 Pre-Bid Meeting

Transcript of RFP No. 23900-RFP-ES860

Page 1: RFP No. 23900-RFP-ES860

RFP No. 23900-RFP-ES860

GENERAL ENGINEERING & TECHNICAL SERVICES

September 22, 2008

Pre-Bid Meeting

Page 2: RFP No. 23900-RFP-ES860

Request for Proposal 23900-RFP-ES860

✦ Questions and Answers❖ 3 x 5 Card - Written.❖ Only written questions will be responded to

by BJC (Submit to Cindy Hart).❖ RFP can only be changed by Amendment.❖ Final Questions due on or before October 1,

2008.❖ Questions and answers will be posted on the

web at www.bechteljacobs.com.

Page 3: RFP No. 23900-RFP-ES860

Request for Proposal 23900-RFP-ES860

✦ Preparation❖ Use only forms provided in Exhibit C. ❖ Read RFP, Information, and Instructions❖ Examine All Documents Completely❖ Penalty for False Statements❖ Award to the most responsible proposal

through a best value evaluation ❖ Conditional Award - Submittals❖ Proposal Submission Format❖ Exceptions

Page 4: RFP No. 23900-RFP-ES860

Request for Proposal 23900-RFP-ES860

✦ Proposal Evaluation Criteria

Technical ProposalKey PersonnelBusiness Mgmt. Proposal

✦ Target Award Date December 1, 2008

Page 5: RFP No. 23900-RFP-ES860

Request for Proposal 23900-RFP-ES860

✦ Amendment Process

❖ Terms and Conditions

❖ Definition

❖ Offerors must acknowledge

◆ Submission of a signed copy w/proposal.

◆ Acknowledgement Form.

◆ Acknowledgement received with proposal.

◆ Can be cause for proposal rejection.

Page 6: RFP No. 23900-RFP-ES860

Request for Proposal 23900-RFP-ES860

✦ Exhibit C Forms

❖ Volume 1 - Technical Proposal

❖ Form C - Subcontractor/Vendor List

❖ Form C-1 - Lower-Tier Experience Statement

❖Form H - Résumés of Key Personnel

❖ Form J - Technical Data

❖Form I – Project Organization Descriptions

❖Form K – Commercial Data

❖Form Q- Experience Statement

Page 7: RFP No. 23900-RFP-ES860

Request for Proposal 23900-RFP-ES860

✦Exhibit C Forms

❖ Volume 2 - Business Management Proposal

❖Form A-1 - Schedule of Lump Sum and/or Unit Prices

❖ Form P - Representations & Certifications (with Attachments)

Page 8: RFP No. 23900-RFP-ES860

✦ Staff Augmentation & Independent Performance❖ Engineering Analyses

◆ Value Engineering ◆ Estimating

❖ Design Preparation◆ Conceptual Design◆ Detailed Design◆ Specification Preparation◆ Independent Engineering Reviews ◆ Construction Support Activities

Project Scope of Work

Page 9: RFP No. 23900-RFP-ES860

◆ Construction Support Activities◆ Risk Analyses Studies◆ Engineering Alternative Analysis (Trade Studies) ◆ Configuration Management Activities◆ Document Production.◆ Scope Of Work Preparation◆ General CERCLA Support◆ Development of Decision Documents◆ Tech Support ( (Hydrogeology And Other Sciences, Data Collection, Risk Assessment, other)◆ Environmental Fate And Transport Modeling◆ Analytical Data Validation And Screening◆ Document Production

Project Scope of Work

Page 10: RFP No. 23900-RFP-ES860

Quality Assurance

◆ Exhibit K of the Subcontract outlines the requirements for the Project Quality Assurance Program and addresses the implementation of the ten quality assurance criteria included in 10 CFR 830.122.

◆ Addresses three primary areas:

❖ Management

❖ Performance

❖ Assessment

Page 11: RFP No. 23900-RFP-ES860

◆ Subcontractor may either develop procedures to implement the requirements of Exhibit K or develop their own project specific Quality Assurance Plan (QAP) that

meets the requirements described therein.

Quality Assurance

Page 12: RFP No. 23900-RFP-ES860

Management Assessments

◆ Subcontractor shall conduct Management Assessments to evaluate the adequacy and effectiveness of implementation of procedures and the requirements of this Subcontract.

◆ The minimum frequency of such ongoing assessments is one per month.

◆ Performed to verify conformance to applicable requirements and identify opportunities to improve performance and cost-effectiveness.

Page 13: RFP No. 23900-RFP-ES860

Eric Benedict

(Safety Representative)

Environmental Safety & Health

Page 14: RFP No. 23900-RFP-ES860

Zero Accident Performance

Bechtel Jacobs is dedicated to the concept that all accidents are preventable.

◆ Accordingly, the company is committed to achieving and sustaining “Zero Accident Performance” through continuous improvement practices.

Page 15: RFP No. 23900-RFP-ES860

✦ Strive to eliminate all injuries and illnesses.✦ Spread ownership for ES&H to all

employees.✦ Educate all employees on our ES&H

principles that help Zero Accidents become a reality.

✦ Encourage all employees to become active participants in ES&H performance.

✦ Continuously improve processes, procedures, and techniques.

Zero Accident Objectives

Page 16: RFP No. 23900-RFP-ES860

The Integrated Safety Management System (ISMS) Description reflects the approach from Bechtel Jacobs Company LLC (BJC) for integrating safety into all aspects of work planning and execution for the ETTP Accelerated Closure Project. The ISMS description serves as a road map to the ISMS implementing mechanisms.

ISMS Description BJC-GM-1400

Page 17: RFP No. 23900-RFP-ES860

ISMS-What it Means to You

✦ Your involvement in:❖ Planning the work or defining the scope.

❖ Identifying and analyzing the hazards.

❖ Implementing hazard controls.

❖ Performing the work to your plan and controls.

❖ Providing feedback, concerns, and lessons learned.

❖ The authority, without fear of reprisals, to stop the work when you believe to be unsafe, or you do not fully understand the task you are about to perform.

Page 18: RFP No. 23900-RFP-ES860

Feedback/Improvement

◆Collect feedback information◆Identify improvement

opportunities◆Make changes to improve◆Oversight and enforcement

Define Scope of Work

◆Translate mission into work◆Set expectations◆Prioritize tasks and allocate resources

Analyze Hazards

◆Identify and analyze hazards

◆Categorize hazards

Perform Work

◆Confirm readiness◆Perform work safely

Develop/Implement Controls

◆Identify standards and requirements◆Identify controls to prevent/mitigate

hazards◆Establish safety controls◆Implement controls

PerformWorkSafely

1

2

4

5

3

Integrated Safety Management System

Page 19: RFP No. 23900-RFP-ES860

Integrated Safety Management Principles

✦ Line management responsibility for safety.

✦ Clear roles and responsibilities.

✦ Competence commensurate with responsibility.

✦ Balanced priorities.

✦ Identification of safety standards and requirements.

✦ Hazard control tailored to work being performed.

✦ Operations authorization.

Worker Involvement

Page 20: RFP No. 23900-RFP-ES860

Exhibit G

✦ Flows down Environmental, Safety, and Health requirements.

Page 21: RFP No. 23900-RFP-ES860

Worker Safety and Health Program DescriptionBJC/OR-1745

✦ Standard for all new subcontracts.✦ Subcontract flow down.✦ Applicability matrix delineates what

sections apply to this RFP.✦ Specific requirements may require

subcontractor to develop other plans.

Page 22: RFP No. 23900-RFP-ES860

✦Pre-Employment Background Check✦Badges (Issuance and Termination)✦ Clearances (Requesting and

Termination)

Site Considerations & Access

Page 23: RFP No. 23900-RFP-ES860

Access and Work Areas

✦ Site access requires a photo badge, temporary badge, or visitor badge.

✦ Routine access inside the Classified Area fence requires L-clearance.

Page 24: RFP No. 23900-RFP-ES860

Request for Proposal 23900-RFP-ES860

PROPOSAL DUE DATE

October 10, 2008

3:00 p.m.

Local Prevailing Time