MIT1_040s09_lec23

download MIT1_040s09_lec23

of 25

Transcript of MIT1_040s09_lec23

  • 8/12/2019 MIT1_040s09_lec23

    1/25

    MIT OpenCourseWarehttp://ocw.mit.edu

    1.040 Project ManagementSpring 2009

    For information about citing these materials or our Terms of Use, visit: http://ocw.mit.edu/terms .

    http://ocw.mit.edu/http://ocw.mit.edu/termshttp://ocw.mit.edu/termshttp://ocw.mit.edu/
  • 8/12/2019 MIT1_040s09_lec23

    2/25

    Presentation by:Professor Fred Moavenzadeh

  • 8/12/2019 MIT1_040s09_lec23

    3/25

    Managing Construction Risk1. An Integrated Approach2. Identifying Project Risks3. Allocation of Risk

    4. Economical Solutions to Risk

  • 8/12/2019 MIT1_040s09_lec23

    4/25

  • 8/12/2019 MIT1_040s09_lec23

    5/25

    Integrated Project Risk Management

    Risk Financing Self Funded Owner Control

    Incentive Bonus

    Loss Prevention Risk Identification Contract Formation Scheduling

    Dispute Resolution On-Site Resolution Mediation/Arbitration Contractual

  • 8/12/2019 MIT1_040s09_lec23

    6/25

    Integrated Project Risk Management

    Builders Risk

    Risk Financing Owner Buys? Cont. Buys? Build Risk?

    Delay of Opening Force Majeure

    Loss Prevention Risk ID Contract Wording Site Security Disaster Planning

    Dispute Resolution Allocation ofDeductible How Does Claim GetResolved?

  • 8/12/2019 MIT1_040s09_lec23

    7/25

    Key Point #2

    Identifying Project Risks

  • 8/12/2019 MIT1_040s09_lec23

    8/25

    Risk Identificationy Project Type & Sitey Project Participantsy Project Delivery Methody Budget & Financingy Schedulingy Legaly Political

  • 8/12/2019 MIT1_040s09_lec23

    9/25

    CM or PM

    Owner

    ContractorA/E

    Sub Subub

    Owner

    At Risk CM or PM/E

    Sububub

    Owner

    Contractor/E

    Owner

    Design Builder

    A/E Subcontractors

    By Project Delivery Methods

    CM or PM

    Owner

    Contractor A/E

    Sub SubSub

    Agency CM or PM

    Owner

    At Risk CM or PM A/E

    SubSubSub

    At-Risk CM or PM

    Owner

    Contractor A/E

    Design-Bid-Build

    Owner

    Design - Builder

    A/E Subcontractors

    Design-Build

  • 8/12/2019 MIT1_040s09_lec23

    10/25

    Key Point #3

    Choice in Risk Allocation

  • 8/12/2019 MIT1_040s09_lec23

    11/25

    Responsibility for Risk

    By ContractRisk ShiftingInsurance

    By DefaultDenial of Responsibility Acceptance of Responsibility

    By Law StatutesRegulations

    Common Law

  • 8/12/2019 MIT1_040s09_lec23

    12/25

    Fair Allocation of Risk

    9 Which Party can best control risk9 Which party can best finance the risk9 Which party can best manage the risk9 Which party can more easily accept the

    consequence of risk

  • 8/12/2019 MIT1_040s09_lec23

    13/25

    Risk MatrixRisks Owner Architect/Engineer

    Contractor Subcontractor

    Injury to General Liability Professional Workers General Liability

    contractors or owners liability or compensationemployees protective general liability

    Injury to General liability or Professional General liability Workerssubcontractors owners protective liability or compensationemployees general liability

    Injury to general General liability or Professional General liability General liabilitypublic owners protective liability or

    general liability

    Physical damage to Builders risk Professional Builders risk Builders Riskproject during liability orconstruction general liability

    Physical damage to Property policy Professional General liability General liabilityproject after liability (completed (completedconstruction operations) operations

  • 8/12/2019 MIT1_040s09_lec23

    14/25

    Approaches to Avoidand Reduce Claims

    y Realistic Contractual Allocation of Risksy Match Risk Allocation to Compensation

    y Dispute Prevention through Incentive Programs

    y Use Integrated Programs to Protect all Parties

  • 8/12/2019 MIT1_040s09_lec23

    15/25

    Key Point #4

    Economical Solutions forConstruction Risks

  • 8/12/2019 MIT1_040s09_lec23

    16/25

    Allocation of Insurance-RelatedRisks & Costs: Strategies

    Construction Industry Institute Study (1993)

    y Invest in Loss Control and Safety Programs

    y Limited Indemnity by Contractors

    y Less Insurance, More Risk Management

    y Controlled Insurance Programs Not New.

    What is New is increasing Utilization

  • 8/12/2019 MIT1_040s09_lec23

    17/25

    Key Point #5

    Controlled Insurance Programs(CIPs)

  • 8/12/2019 MIT1_040s09_lec23

    18/25

  • 8/12/2019 MIT1_040s09_lec23

    19/25

    Owner- or Contractor-ControlledInsurance Program

    y Wrap-up Advantagesy Cost Savings

    y Controly Public Relations

  • 8/12/2019 MIT1_040s09_lec23

    20/25

    Wrap-up Feasibility

    $5MM

    $1.5-3MM

    $2-3.5MM

    Construction Hard Costs$100,000,000

    Bid Reductions

    Wrap UpCost Wrap-Up vs.Conventional

    Cost Savings

  • 8/12/2019 MIT1_040s09_lec23

    21/25

    Key Point #6

    Project ProfessionalPolicies

  • 8/12/2019 MIT1_040s09_lec23

    22/25

    Pitfalls in ProfessionalLiability Insurance

    y Problems Low, Aggregated Limits

    y Solutions

    y

    Good certificate of insurance backed by contractrequirements

    y

    Buy project professional insurance on larger projectsy Buy owners protective insurance

  • 8/12/2019 MIT1_040s09_lec23

    23/25

    Owners Protective ProfessionalLiability: Sample Program

    Typical Professional

    Liability Limits

    D e s i g n

    F i r m

    P r i m a r y L i m i t s

    Project No. 1 Project No. 2

  • 8/12/2019 MIT1_040s09_lec23

    24/25

    Owners Protective Professional

    D e s i g n F i r m

    P r i m a r y

    L i m i t s

    Liability Sample Program

    $0

    $2

    $4

    $6

    $8

    $10

    $12

    $14

    $16

    Arch.#1 Soils Eng. #2 Interiors #3 Arch. #4 Eng. #5 Landscape #6

    $10M aggregate limit excess ofEach individual underlying policy

    Project No. 1 Project No. 2

  • 8/12/2019 MIT1_040s09_lec23

    25/25

    Political Risk ModelingP8P9

    P11

    P10

    P7P6

    P5

    P4

    P1

    P2

    P3

    No compensation

    CompensationExpropriation

    No Expropriation

    No Expropriation

    Expropriation Compensation

    No compensation

    Coup Ideology A

    Coup Ideology B

    Stability

    Probability of Expropriation without compensation = P1xP4xP9 + P2xP6xP11