MIT1_040s09_lec23
Transcript of MIT1_040s09_lec23
-
8/12/2019 MIT1_040s09_lec23
1/25
MIT OpenCourseWarehttp://ocw.mit.edu
1.040 Project ManagementSpring 2009
For information about citing these materials or our Terms of Use, visit: http://ocw.mit.edu/terms .
http://ocw.mit.edu/http://ocw.mit.edu/termshttp://ocw.mit.edu/termshttp://ocw.mit.edu/ -
8/12/2019 MIT1_040s09_lec23
2/25
Presentation by:Professor Fred Moavenzadeh
-
8/12/2019 MIT1_040s09_lec23
3/25
Managing Construction Risk1. An Integrated Approach2. Identifying Project Risks3. Allocation of Risk
4. Economical Solutions to Risk
-
8/12/2019 MIT1_040s09_lec23
4/25
-
8/12/2019 MIT1_040s09_lec23
5/25
Integrated Project Risk Management
Risk Financing Self Funded Owner Control
Incentive Bonus
Loss Prevention Risk Identification Contract Formation Scheduling
Dispute Resolution On-Site Resolution Mediation/Arbitration Contractual
-
8/12/2019 MIT1_040s09_lec23
6/25
Integrated Project Risk Management
Builders Risk
Risk Financing Owner Buys? Cont. Buys? Build Risk?
Delay of Opening Force Majeure
Loss Prevention Risk ID Contract Wording Site Security Disaster Planning
Dispute Resolution Allocation ofDeductible How Does Claim GetResolved?
-
8/12/2019 MIT1_040s09_lec23
7/25
Key Point #2
Identifying Project Risks
-
8/12/2019 MIT1_040s09_lec23
8/25
Risk Identificationy Project Type & Sitey Project Participantsy Project Delivery Methody Budget & Financingy Schedulingy Legaly Political
-
8/12/2019 MIT1_040s09_lec23
9/25
CM or PM
Owner
ContractorA/E
Sub Subub
Owner
At Risk CM or PM/E
Sububub
Owner
Contractor/E
Owner
Design Builder
A/E Subcontractors
By Project Delivery Methods
CM or PM
Owner
Contractor A/E
Sub SubSub
Agency CM or PM
Owner
At Risk CM or PM A/E
SubSubSub
At-Risk CM or PM
Owner
Contractor A/E
Design-Bid-Build
Owner
Design - Builder
A/E Subcontractors
Design-Build
-
8/12/2019 MIT1_040s09_lec23
10/25
Key Point #3
Choice in Risk Allocation
-
8/12/2019 MIT1_040s09_lec23
11/25
Responsibility for Risk
By ContractRisk ShiftingInsurance
By DefaultDenial of Responsibility Acceptance of Responsibility
By Law StatutesRegulations
Common Law
-
8/12/2019 MIT1_040s09_lec23
12/25
Fair Allocation of Risk
9 Which Party can best control risk9 Which party can best finance the risk9 Which party can best manage the risk9 Which party can more easily accept the
consequence of risk
-
8/12/2019 MIT1_040s09_lec23
13/25
Risk MatrixRisks Owner Architect/Engineer
Contractor Subcontractor
Injury to General Liability Professional Workers General Liability
contractors or owners liability or compensationemployees protective general liability
Injury to General liability or Professional General liability Workerssubcontractors owners protective liability or compensationemployees general liability
Injury to general General liability or Professional General liability General liabilitypublic owners protective liability or
general liability
Physical damage to Builders risk Professional Builders risk Builders Riskproject during liability orconstruction general liability
Physical damage to Property policy Professional General liability General liabilityproject after liability (completed (completedconstruction operations) operations
-
8/12/2019 MIT1_040s09_lec23
14/25
Approaches to Avoidand Reduce Claims
y Realistic Contractual Allocation of Risksy Match Risk Allocation to Compensation
y Dispute Prevention through Incentive Programs
y Use Integrated Programs to Protect all Parties
-
8/12/2019 MIT1_040s09_lec23
15/25
Key Point #4
Economical Solutions forConstruction Risks
-
8/12/2019 MIT1_040s09_lec23
16/25
Allocation of Insurance-RelatedRisks & Costs: Strategies
Construction Industry Institute Study (1993)
y Invest in Loss Control and Safety Programs
y Limited Indemnity by Contractors
y Less Insurance, More Risk Management
y Controlled Insurance Programs Not New.
What is New is increasing Utilization
-
8/12/2019 MIT1_040s09_lec23
17/25
Key Point #5
Controlled Insurance Programs(CIPs)
-
8/12/2019 MIT1_040s09_lec23
18/25
-
8/12/2019 MIT1_040s09_lec23
19/25
Owner- or Contractor-ControlledInsurance Program
y Wrap-up Advantagesy Cost Savings
y Controly Public Relations
-
8/12/2019 MIT1_040s09_lec23
20/25
Wrap-up Feasibility
$5MM
$1.5-3MM
$2-3.5MM
Construction Hard Costs$100,000,000
Bid Reductions
Wrap UpCost Wrap-Up vs.Conventional
Cost Savings
-
8/12/2019 MIT1_040s09_lec23
21/25
Key Point #6
Project ProfessionalPolicies
-
8/12/2019 MIT1_040s09_lec23
22/25
Pitfalls in ProfessionalLiability Insurance
y Problems Low, Aggregated Limits
y Solutions
y
Good certificate of insurance backed by contractrequirements
y
Buy project professional insurance on larger projectsy Buy owners protective insurance
-
8/12/2019 MIT1_040s09_lec23
23/25
Owners Protective ProfessionalLiability: Sample Program
Typical Professional
Liability Limits
D e s i g n
F i r m
P r i m a r y L i m i t s
Project No. 1 Project No. 2
-
8/12/2019 MIT1_040s09_lec23
24/25
Owners Protective Professional
D e s i g n F i r m
P r i m a r y
L i m i t s
Liability Sample Program
$0
$2
$4
$6
$8
$10
$12
$14
$16
Arch.#1 Soils Eng. #2 Interiors #3 Arch. #4 Eng. #5 Landscape #6
$10M aggregate limit excess ofEach individual underlying policy
Project No. 1 Project No. 2
-
8/12/2019 MIT1_040s09_lec23
25/25
Political Risk ModelingP8P9
P11
P10
P7P6
P5
P4
P1
P2
P3
No compensation
CompensationExpropriation
No Expropriation
No Expropriation
Expropriation Compensation
No compensation
Coup Ideology A
Coup Ideology B
Stability
Probability of Expropriation without compensation = P1xP4xP9 + P2xP6xP11