MICE Target Status Chris Booth Sheffield 10 th May 2006.

24
MICE Target Status Chris Booth Sheffield 10 th May 2006
  • date post

    21-Dec-2015
  • Category

    Documents

  • view

    216
  • download

    0

Transcript of MICE Target Status Chris Booth Sheffield 10 th May 2006.

MICE Target Status

Chris Booth

Sheffield

10th May 2006

Chris Booth University of Sheffield 2

• Focus of recent work has been assembly tests at RAL 24th-28th April.

– Review of components

– Results of tests

– Preliminary follow-up plans

Chris Booth University of Sheffield 3

Components• Stator body

• Ceramic tube

• Glass readout tube

• Target shuttle

• Ceramic bearings

• Electronics

• Frame, jack, bellows, gate-valve

Chris Booth University of Sheffield 4

Stator• Micro-surgery on

Manchester body has allowed insertion of ceramic tube!

• Tolerances around ceramic slightly tight.

• We have learned how to make all components for future stators in house.

Chris Booth University of Sheffield 5

Ceramic tube• Test flanges &

dummy stator built at RAL.

• Indium vacuum seals tested.

• Pronounced satisfactory!

Chris Booth University of Sheffield 6

Optical readout enclosure

• Quartz glass tube and flange procured.

• Flange machined, tube fixed with cryostat cement.

Chris Booth University of Sheffield 7

Shuttle• Oxford agreed to assemble shaft, target,

alignment fin, stop, magnets, readout vane (see picture) – many thanks!

• Magnets, readout vane supplied by Sheffield.

• For prototype, shaft produced from steel tube rather than titanium.

• Assembly cleaned in Oxford, delivered direct to RAL.

Chris Booth University of Sheffield 8

Titanium target

Steel shaft

Alignment fin

Stop

Magnets

Optical readout vane

Chris Booth University of Sheffield 9

Ceramic bearings

Slot for alignment fin

Hole for alignment pin

Chris Booth University of Sheffield 10

Control electronics• Cards now rack-

mounted.

• Extensive tests with prototype drive. Several hours pulsing at 0.3 Hz (10 A).

• Some reliability & noise problems to be addressed.

Chris Booth University of Sheffield 11

Bellows

Chris Booth University of Sheffield 12

Chris Booth University of Sheffield 13

Indium seals

Ceramic bearings

Chris Booth University of Sheffield 14

Beam pipe

Gate valve

Bellows

Drive mechanism

Support frame

Chris Booth University of Sheffield 15

Assembly test: 24-28 April• First time many parts came together:

– Stator first connected to electronics 20th

– Glass readout tube assembled 21st

– Target shuttle finished morning of 24th

– Some RAL parts and flanges not previously assembled.

Chris Booth University of Sheffield 16

What did we learn?1. Glass tube is very fragile!

– Broken near metal flange.

– Ground down and re-glued – vacuum tested ok.

– New crack when tightened down onto full assembly.

– Covered in epoxy! Amazingly, this appeared to seal ok!

Chris Booth University of Sheffield 17

2. Target shuttle was distorted– Slot cut along thin-walled tube to take

alignment vane caused shaft to distort.

– Vane was twisted and slightly off-axis at one end.

– Would not pass through ceramic bearing.

– Slot & hole in bearing machined out to allow shaft and vane to pass.

– Some play and roughness, but movement satisfactory.

Chris Booth University of Sheffield 18

3. Indium seals did not work!– Despite success with test pieces, could not

pump down below 310–3 mbar.

– Flanges found to have too large diameter and chamfer; rebates incorrect so inadequate closure of seal.

– Attempts to seal with extra indium.

– Only partial improvement.

– Prevented vacuum quality checks with mass spectrometer.

Chris Booth University of Sheffield 19

4. Temperature sensitivity– Operation of drive (power-off to park

position) caused deterioration in vacuum.

– Chilled water cooling (12°C) also worsened vacuum.

– Partial recovery on return to ambient temperature.

– Movement of ceramic tube disturbing (imperfect) seal?

Chris Booth University of Sheffield 20

5. Optical readout block did not fit– Insufficient space for readout block around

glass tube when drive in raised position.

– Large guide flange removed – appears not to be necessary.

– Flange could also be machined down to allow space.

6. Extremely difficult to align optics– Higher refractive index of quartz tube?

– RAL restrictions on use of laser in hall.

Chris Booth University of Sheffield 21

Solutions1 & 6 Replace glass tube with steel plus flat

glass windows– Robust, much simpler optics.

– Redesign optical mounts to allow off-line alignment.

3 & 4 Flanges for indium seals to be re-ground or re-made

– Vacuum and temperature tests will be performed at RAL.

Chris Booth University of Sheffield 22

2 Oxford redesigned target shuttle– Target, shaft, stop, alignment fin machined

out of single piece of titanium.

– Cross-shaped cross-section.

– Strong, no tendency to twist.

– Only magnets and readout fin to be added.

– New (or modified) ceramic bearings will be required – design to allow insertion of shaft through lower bearing for easier assembly.

Chris Booth University of Sheffield 23

Conclusions(1)Still digesting results of week before last!

Despite problems, a lot was learned.• Practical details of assembly tested for first

time.• Learned what does, what doesn’t work.• Improved design of major components (optical

windows & readout mount, target shuttle).• No proper vacuum tests.• No reliability or vibration tests.• Review (with ISIS) 23rd May.

Chris Booth University of Sheffield 24

Conclusions(2)• Parts (flanges etc) now in Sheffield for full

system tests under vacuum.• Will repeat assembly in hall.• Will conduct reliability tests in Sheffield, then

in assembly hall.• Will not be able to install in ISIS for June –

must perform thorough off-line checks to demonstrate readiness for October access.

• High-current driver electronics should be ready mid-summer (was not planned for June).