K. Long, 14 October 2003 MICE-UK: progress report Progress: WP1: B&I: Target u/g (Sheffield) … PD...
-
Upload
preston-holland -
Category
Documents
-
view
215 -
download
3
Transcript of K. Long, 14 October 2003 MICE-UK: progress report Progress: WP1: B&I: Target u/g (Sheffield) … PD...
K. Long, 14 October 2003
MICE-UK: progress report Progress:
WP1: B&I: Target u/g (Sheffield) … PD Focus coil assembly Spectrometer Software
Issues: Scientific approval Formal connections with iMICE Continuity of funding Scenarios for UK funding for MICE
WP2: Focus coil assembly - Oxford/RALNew design of magnet and absorber
Absorber now slides inside magnetIntegration much easierMore modular for hydrogen safetySimplified magnet designReduces costs
Quench analysis complete
Magnet specifications written, guide prices from companies and Oxford University.
Ongoing analysis of forces
Preparing for iMICE safety review (Dec03)
Current designsimplified integration
WP2: Focus coil assembly
Magnetic Analyses
OPERA calculations
Forces, torques and stresses on coils
Quench analysis
Currents, forces and heating
WP2: Focus coil assembly
Mechanical Analysis
~ 200 tons internal force between coils ~ 80 tons external 2D & 3D FEA analyses of coil support tube
WP2: Focus coil assembly
Simulations
ICOOL simulation of muons in MICE lattice
Specify construction tolerances & magnetic field errors
Perfect
5o tilt
WP3: Spectrometer instrumentn
- Brunel, Edinburgh, Imperial, LiverpoolPrototype:
All three stations shipped to FNAL
WP3: Spectrometer instrumentn
- FNALD0 test stand:
Trigger etc. ready, assembly in progress
RF test done: effect << 1 pe (i.e. OK for MICE)
WP3: Spectrometer instrumentn
Preparations for technology choice 30Oct-02Nov: Have proved construction/collaboration Jp/UK/US Setting up to measure light yield, cross talk etc. RF measurement performed Tight but possible!
Updated costing: Mechanical: revised costing ~prepared. Shows saving
and is based on experience with prototype A. Bross (FNAL) updating electronics costing:
‘Borrow’ D0 spares? Implies negotiation with D0 … Build new VLPC cassettes … cost being evaluated
Schedule: Mechanical: revised following experience with prototype Electronics: being revised by A. Bross (D0 experience)
WP4: MICE software
Present focus: simulation/reconstruction adequate for comparison of SciFi and TPG Gridification: Done: Rapid generation of large data sets RF background generator: under test SciFi simulation: updated: under test SciFi reconstruction: updated: under test
Schedule to provide results for collaboration meeting is tight … but probably will be met
- Brunel, Edinburgh, Imperial
Issues Scientific approval
Discussions with Dan Kaplan and Alain Blondel: Need clear statement such as:
… The MICE project has been fully peer reviewed at both national and international level. The science case has been strongly endorsed in each peer-review process. CCLRC therefore approves the project subject to a satisfactory outcome of the Gateway process. …
Issues: Formal connections with iMICE:
Collaboration meeting: Initiate dialogue CCLRC/iMICE at collaboration board Informal dialogue UK funding agency/iMICE at
collaboration dinner … precursor to more formal meeting?
Project Management Board (chair KJP) Has not yet met … Membership is UK leadership plus iMICE
spokesperson(s) Important to hold first meeting to tie iMICE into
development of financial, managerial and operational cases/activities
Issues: Continuity of funding:
Seed-corn funding provided by CCLRC/PPARC following PPRP review have allowed significant progress to be made on all fronts
Essential to ensure continuity 2003/04 2004/05 2006/07 2008/09 … i.e. beyond the SR2002 period
Sources: OST: £7.5M (via Gateway) PPARC: £2.5M (‘penciled in’) CCLRC: ?
Issues:£21M PSI replacement + contribution to experiment
£7.5M PSI Infrastructure contribution to experiment
<7.0M Quads
7.5M +Tracker
10M +F.Coils (1.5?) +FC Cryo (0.3?)
11.5M PSI+PSI Cryo
12.5M +Beam Line Coils ? UK
Unresolved MICE Items:RF £2M+vat…Track Sol 1.5M+?Cryogenics£1M + Extra Design ?Beam Line Coils £1M?
~1M* Saves
~700k - does this include vat & contingency?
~2M*
~0.5M*
~1M*
~0.5M*
~1M*
UK loses:DAQ & S’Ware ~2.1MTravel ~0.9MConsumables ~0.3MMisc ~0.3M(RF ~1.6M)** * = vat + contingency – no inflation
** this is ~0.6M above UK commitment in proposal