Transcript of Mfg WIP Advisor Webcast 2013 1204
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
1/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.1
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
2/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.2
Oracle Advisor Webcast Program
Current schedule
Archived recordings
Doc ID 740966.1
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
3/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.3
Future Advisor Webcasts
VOICE STREAMING ENABLED
Teleconference Access:US & Canada: 866- 627-3315
Toll Number: +1-706-758-7972
Global Toll-Free: 1148600.1
Password: Oracle FLOW
WIP Webcast Calendar/ArchiveDoc ID 1319827.1
All Webcast Calendar/ArchiveDoc ID 740966.1
Upcoming live webcasts and recent recordings:
What advisor webcast topics do YOU want to see prese
In Process and Flow Manufacturing My Oracle Support
let us know.
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
4/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.4
The following is intended to outline our general producdirection. It is intended for information purposes only, a
may not be incorporated into any contract. It is not a
commitment to deliver any material, code, or functiona
and should not be relied upon in making purchasing de
The development, release, and timing of any features
functionality described for Oracles products remains a
sole discretion of Oracle.
Safe Harbor Statement
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
5/83
Oracle Advisor Webcast
Flow Manufacturing: An End to End Flow
Zar Ahmed
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
6/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.6
Objectives
To understand the basicconcepts of FlowManufacturing (FLM)
Explain the required setups
To provide details of thebasic process flow of FLM
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
7/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.7
Agenda
Overview
Basic Setup Steps
Process Flow using screenshot demo
Basic Technical Details APIs, Tables.
Q&A
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
8/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.8
Overview
FLM (also called LEAN Manufacturing) is a manuapproach that aligns production with customer de
employs Just-In-Time (JIT) concepts such as : Manufacturing to demand (vs. forecast),
Production lines for families of products (vs. playout),
Pull material using kanbans (vs. push materia
Backflush material and costs upon completionoperation), and so on.
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
9/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.9
Overview
Key principles of FLM are : Decrease Inventory. Eliminate waste the more stocking points you create, increases waste.
Continuous Production Line concept : so if you need to store your productcome off the production line, it is not really FLM. No idle resources.
FLM products repetitive tasks, same product produced (in discrete mfg, more tailored to specific customer needs).
Optimize machine utilization Reduce response time to customer needs Simplify shop floor activities. Production without use of work orders. Only one final product typically produced on the line. Raw Materials and sub-assemblies are added at different operations. Lower skill levels typically then in discrete manufacturing. Long production lines mean lower costs.
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
10/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.10
Mixed-Mode ExecutionComplete Manufacturing Operations Management
Flow
Manufacturing
Shop
Manag
Best for
Flexible andConfigurable
Manufacturing
Execution
Capabilities
Make to order demand flowtechnology or lean mfg linesor cells in a low-to-mediumproduction volume, highproduct mix environment
Lot / serial conitems that requduring entire pLow volume devolume interfac
Oracle MES / MOC plus
Configurable work lists Paperless work instructions via graphically rich Streamlined transactions Supervisor dashboard to monitor shop floor stat Integrated quality data collection Product genealogy tracking Label printing (product identifiers, packaging, etc
Traditional manufacturersin a low-to-mediumproduction volume, highproduct mix environment
Production
Assembly
Mobile Supply Chain Applications
Discrete and Process Mfg
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
11/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.11
Oracle Flow Manufacturing Solution
Holistic planning with consensus forecachannel order capture with global ATP
Accurately Plan andCapture Demand
Intuitive UI for paperless work instructioquality management and reporting
Execute in Real-Timewith Built-In
Quality Management
Support for mixed model production, grfor flow line design and balancing
Design for BalancedOperations
Schedule andSequence for
Efficient Production
User-definable scheduling and sequencwith integrated feeder line and supplier
Plan & ExecuteKanban Material
Movement
Complete Kanban management with pusequencing, Kanban planning and exec
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
12/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.12
Flow Manufacturing Definition
Benefits:
Lean processes that are sustainable and repeatable on a global s
Speeds the introduction of new products to the Flow Mfg process
Supports continuous improvement in manufacturing processes
Integrated software that directly supports lean mfg / lean supply c
Lack of formalized, sustainablelean processes Lack of Lean Mfg integration
with core ERP data(e.g., cost accounting andorder management)
Demand-driven manufacturers in any industry
What Does it Do
Who is i t For?
Framework to document flow mfg
Simulates and calculates flow line Designs material replenishment p Sequences demand directly to pro Simulates daily demand for resou Provides line performance metrics
What Problems Does it Solve?
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
13/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.13
REQUIRED SETUPS
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
14/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.14
Summary of Setups
1. Define your items.2. Define your flow lines. These are manufacturing work areas where you p
assembly. Can manufacture multiple items on a flow line simultaneously.
your resources and departments.3. Product Synchronization : Define the products Process Flow using Flow
the processes and activities (events) and the line operations). Use GrapWorkbench for this.
4. Balance Flow Lines (balance resources and events) : Mixed Model Workused to do this. Calculates process times and required resources to do th
5. Create Pull Sequences for every item : FLM uses Kanban replenishmentmaterial requirements and pull material from demand sources.Pull Sequence = definition of the item, where it is used and where it is su
6. Setup Kanban Planning. Graphical Kanban Workbench : Kanban setup , define pull sequences, planning simulation , kanban transactions.
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
15/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.15
Summary of Setups
7. Define Scheduling rules : Purpose of line scheduling is to synchronise prcustomer demand. Use Line Scheduling Workbench to achieve this.Define the scheduling rules that will be used for this.
8. Setup Sequencing Constraints : Sequencing is used to consider your demdetermine a sequence for building assembly items
9. Setup Flow Execution Workstation : This is used to meet daily production(flow line transactions, track work flow, complete assemblies, view comporesource information.
10. Enable profile FLM : Enable Flow Sequencing.
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
16/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.16
Setup 1:Define Your Items
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
17/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.17
Setup 1:Optional : Product Famil ies
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
18/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.18
Setup 2 : Define Flow Lines
.Mfg Work Area where the assembly is produced.
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
19/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.19
Setup 3 : Product Synchronization
Define a Flow Routing
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
20/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.20
Setup 3 : Product Synchronization
Add Events, processes and Line operations
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
21/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.21
Setup 3 : Product Synchronization
Events : Detailed Work Content of the Line
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
22/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.22
Setup 3 : Product Synchronization
Processes : Optional. Discrete Grouping of the EventsUsed to look at balance of the shop using MMW before mov
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
23/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.23
Setup 3 : Product Synchronization
Operations : Grouping events into your line workstations.
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
24/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.24
Setup 4 : Balance Flow Lines (MMW) Line Balancing : Process of defining balanced production lines by including productsperformed and materials and resources consumed at each step. The idea of line balancing is simply to meet the required demand in the quickest tim MMW : Used to balance lines against specific demand and calculate process volum
requirements, TAKT times and in-process-kanban (IPK) requirements. TAKT = rate at which products must be produced to meet schedules.
S 4 B l Fl Li (MMW)
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
25/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.25
Setup 4 : Balance Flow Lines (MMW)Amend assignments; simulate ; balance.Actions used to balance lines include : reduce or remove non-value added work, grousmaller or larger units, increasing resource, increasing in-process inventory, adding add
Line Design and Balancing
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
26/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.26
Line Design and BalancingSimplify Production Modeling
Li
MixeW
Define processesDefine and associate processes with productfamilies, items, or configurable models
Model pr imary & alternateproduction paths
Link operations together as primary, feeder and /or rework processes
Assign workcontent times
For each process, create a detailed sequence ofevents, or estimate time
Share processes & eventsbetween assemblies
Define standard processes and standard events,or common product family synchronizations
Perform mixedmodel calculations
Calculate line and operation takt, and reqdresources; highlight imbalances
Balance lineDefine balanced operations, add IPKs,add resources
S t 5 KANBAN SETUP
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
27/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.27
Setup 5 : KANBAN SETUP
S t 5 D fi P ll S
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
28/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.28
Setup 5 : Define Pull Sequences
Pull Replenishment : To signal Material requirements.
S t 6 K b S t D fi d L
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
29/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.29
Setup 6 :Kanban Setup Define and Lau
Define your planLaunch Plan creates the Kanban cards based on parametAuto-trigger pull demand, pick requests & start / completion
Set p Step 6 Update Prod ction
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
30/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.30
Setup Step 6 :Update Production
Update production to reflect changes in production plan and
Setup Step 6 :Kanban Cards
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
31/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.31
Setup Step 6 :Kanban Cards
Kanban Card a signal that there is a product shortageClick Replenish to replenish the component.
Integrated Kanban Management
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
32/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.32
Integrated Kanban ManagementImprove Inventory Turns and Labor Efficiency
Inventory
Point of Supply Poin
Production
Supplier
PullSequence KanbanPlanning
KanbanExecution
Flexible Pull Sequencedefinition supporting singlecard, dual card, and non-replenishable kanbans
AutomaticaltransactionsSchedule, M
Simulate and compare multipledemand scenarios
Generate new Kanban cards andautomatically cancel outdated cards
Pull Plan Exe
Signal via electronic visual cues
Feeder Plant
Setup 6 : Component Pick Release (op
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
33/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.33
Setup 6 : Component Pick Release (op
FML uses Kanban for Component replenishment.Can use CPR for slow moving or randomly used componenalternative.
Setup 7: Define Scheduling Rules
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
34/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.34
Setup 7: Define Scheduling Rules
Used by Line Scheduling Workbench (see later).
Setup 8 : Setup Sequencing Constraint
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
35/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.35
Setup 8 : Setup Sequencing Constraint Sequencing is used to consider your demands and determine a sequence for building assembly items. Define attribute
them into rules for the assigned production line. Attribute = characteristic of your demand Constraint = restriction enforced on an attribute. E.g Colour. Red first and then black. Sequence assemblies based on Rule = grouping of prioritized constraints for the attributes.
Setup 9 : Setup Flow Exec Workstation
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
36/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.36
Setup 9 : Setup Flow Exec Workstation Sequencing attributes, sequencing rules. Assign the sequencing rule to the production line Define the workstation parameters /preferences for look and feel and for available options HTML and Forms versions of Flow Workstation exist. We will focus on HTML version.
PROCESS FLOW : 1 : Demand
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
37/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.37
PROCESS FLOW : 1 : Demand
Sales orders and/or Planned Orders from ASCP. SO : 6664
PROCESS FLOW : 2 : Create Flow Sch
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
38/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.38
PROCESS FLOW : 2 : Create Flow Sch
Open the Line Scheduling Workbench ; Enter criteria, Create Flow
PROCESS FLOW : 2 : Create Flow Sch
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
39/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.39
PROCESS FLOW : 2 : Create Flow Sch
Flow Schedules have been created. Click Details.
PROCESS FLOW : 2 : Create Flow Sch
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
40/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.40
PROCESS FLOW : 2 : Create Flow Sch
Note the individual flow schedules and the link to SO 66646 The flow schedules take into account the sequencing rules/
PROCESS FLOW : 2 : Create Flow Sch
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
41/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.41
PROCESS FLOW : 2 : Create Flow Sch
Can check component availability against the flow schedule
PROCESS FLOW : 2 : Create Flow Sch
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
42/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.42
PROCESS FLOW : 2 : Create Flow Sch
Sequencing tasks can be used to create flow schedules als A concurrent program creates the flow schedules on submi Uses the defined sequencing rules and constraints Options : Resequence existing schedules or create new sc
PROCESS FLOW : 3 : Initialize Workst
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
43/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.43
PROCESS FLOW : 3 : Initialize Workst
Select org, line and op and specify any optional selection c Note : This assembly has 5 line ops : MBRD, CASE, DRV, T
PROCESS FLOW : 4 : View Schedules
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
44/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.44
PROCESS FLOW : 4 : View Schedules
Schedules can be seen in work queue mode as below or u(scanned or entered). Controlled by the preferences defined
PROCESS FLOW : 4 : View Schedule D
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
45/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.45
Drill into Schedule Number to see details - events tab sho
PROCESS FLOW : 4 : View Schedule D
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
46/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.46
Click on Event Seq Number to see the event details..
PROCESS FLOW : 4 : View Schedule D
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
47/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.47
Drilling into Events also shows detailed instructions, diagra
PROCESS FLOW : 4 : View Schedule D
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
48/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.48
Instructions tab shown below. Details of instructions, diagrams, specifications etc
PROCESS FLOW : 4 : View Schedule D
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
49/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.49
Components tab shown below. Shows components for all th
PROCESS FLOW : 4 : View Schedule D
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
50/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.50
Resource Tab shows resources linked to the events for thoperation and schedule.
PROCESS FLOW : 4 : View Schedule D
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
51/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.51
General details for the line schedule
PROCESS FLOW : 4 : View Schedule D
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
52/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.52
View any custom parameters used for the line schedule.
PROCESS FLOW : 5 : Update Schedul
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
53/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.53
Update any details if required.
PROCESS FLOW : 6 : Complete Line O
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
54/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.54
Click on Express Complete Line Operation Button for flow sDJ877265, op MBRD (1stop)
PROCESS FLOW : 6 : Complete Line O
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
55/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.55
This line op requires some mandatory quality data to be up Mandatory quality collection data can be specified for any o
PROCESS FLOW : 6 : Complete Line O
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
56/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.56
Enter the quality data where required.
PROCESS FLOW : 6 : Complete Line O
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
57/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.57
Now click on apply after quality data entered.
PROCESS FLOW : 6 : Complete Line O
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
58/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.58
Note the completion message and the updated work queue. The assembly has been moved to the NEXT operation. NO material trans When you complete the LAST operation, you have option to complete the
PROCESS FLOW : 6 : Complete Line O
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
59/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.59
To see impact of the op completion, query the next OP - CA
PROCESS FLOW : 6 : Complete Line O
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
60/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.60
The assembly has been moved to the next op as can be se Note : can set parameters to display different buttons for ea
PROCESS FLOW : 7 : Process All Ope
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
61/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.61
Complete Line op CASE moves assembly to Op DRV.
PROCESS FLOW : 7 : Process All Ope
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
62/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.62
Complete Line op DRV moves assembly to Op TEST.
PROCESS FLOW : 7 : Process All Ope
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
63/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.63
Complete Line op TEST moves assembly to final Op PACK
PROCESS FLOW : 8 : Complete Sched
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
64/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.64
There are 2 options for Assembly Completion :- Complete Schedule : Info or review required (html version of work orde- Express Complete Schedule: Automatic completion using defaults
PROCESS FLOW : 8 : Complete Sched
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
65/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.65
Stage 1 :Select complete schedule option. Options to amend qty and specify alternate routings at this
PROCESS FLOW : 8 : Complete SchedSt 2 E t lit d t d if l t d i l b f l t d i l
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
66/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.66
Stage 2 : Enter quality data and specify any lot and serial numbers for lot and serial cCan subsitute, remove components. l removed some components for ease of use.
PROCESS FLOW : 8 : Complete Sched
St 3 T ti l t d li ki fi i h C
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
67/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.67
Stage 3 : Transaction completed on clicking finish.Componbackflushed. Assembly completed into inventory. Flow Scheremoved from work queue. DJ877265 no longer seen here.
PROCESS FLOW : 8 : Complete Sched
C th bl l ti t ti b l
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
68/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.68
Can see the assembly completion transaction below.
PROCESS FLOW : 8 : Complete Sched
Note that you can go to complete schedule directly for the flow schedule a
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
69/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.69
Note that you can go to complete schedule directly for the flow schedule aassembly through all the operations.
PROCESS FLOW : 8 : Complete Sched
C f i f W k d L C l ti l
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
70/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.70
Can use forms version of Workorder Less Completion also
PROCESS FLOW : 9 : Scrap Assemblie
Can add option to scrap assemblies via the parameters
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
71/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.71
Can add option to scrap assemblies via the parameters This follows same process as work orderless completion
Technical Information:Q1: Is there a public api for completing flow schedules?
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
72/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.72
Q1: Is there a public api for completing flow schedules?
A1: Insert records in MTL_TRANSACTIONS_INTERFACE and set transaction source to flow schedThen run inventory manager to process the completion. Will mimic work orderless completion acomponents.
Q2: How do we display additional details for completing the work in the custom property region of FWorkbench?
A2: Use the following:Package Name: FLM_EXECUTION_UTILProcedure Name : GET_ATTRIBUTES
Q3: Is there an API to import Flow Routing, Standard Line Operations, Standard Events & Events R
A3: No. Enter manually or use dataloaders. There is an ER to create api for this:Bug 5460084: CREATE RESOURCES, STD OPERATION, ROUTING EXTERNALLY USING A
Technical Information:Q4: What table is used to store Flow schedules ?
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
73/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.73
Q4: What table is used to store Flow schedules ?
A4: WIP_FLOW_SCHEDULES.
Here are other important tables :FLM_KANBAN_SUMMARY summary of kanbansFLM_MMM_PLANS - Mixed Model Map PlansFLM_MMM_LINES - Mixed Model Map LinesFLM_MMM_OPERATIONS - Mixed Model Map OperationsFLM_SEQ_RULES Sequencing rulesMRP_AD_FLOW_SCHDS stores details about deleted wip flow schedules
Technical Information:Q5: What apis are available for FLM?
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
74/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.74
p
A5: There are 3 apis :
1. Custom Kanban Quantity Calculation API : used to calculate kanban size and qtyPackage Name: MRP_CUSTOM_LINE_SCHEDULEProcedure Name: CUSTOM_SCHEDULE
2. Custom Schedule API : for extending the available line scheduling algorithms.Package Name: MRP_CUSTOM_LINE_SCHEDULEProcedure Name: CUSTOM_SCHEDULE
3. Flow Schedule API : create, update, delete, retrieve, lock, schedule and unlink order lines oPackage Name: MRP_FLOW_SCHEDULE_PUB
Procedure Name: PROCESS_FLOW_SCHEDULE
SummaryWhat we covered today
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
75/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.75
Looked at concepts of FLM.
Looked at how to setup FLM.
Looked at the basic process flow
using screenshots.
Considered basic apis and tables.
Flow ManufacturingSupport Lean Practices to Reduce Cycle Time & Waste
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
76/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.76
ValueStreamMapping
Define and associatestandard processes w/configurable models
Add alternate pathsand rework loops
Add standard events,associate with options
Identify TQC andvalue-add events
Associate workinstructions withoptional events
LineDesign
Calculate line andoperation takt andrequired resources
Highlight imbalancesbased on optionsplanning percentages
Reorganize events intobalanced operations
LeanPlanning
Kanban planningbased on optionplanning percentages
Demand leveling andsmoothing by line rate
Order promising byline rate
Collaborative planningfor VMI and consigned
Inventory optimizationfor postponement
LeaExe
Ka
Cosecoatt
Fesyjus
co
Opdeins
To ask a qphone line
your phon
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
77/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.77
Questions & Answers
your phon
To ask a q
use the Q
top.
Your ques
aloud in th
received.
Question
asked on
Support C
Top Articles and Community Links
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
78/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.78
Work In Process Information Center [ID
1417725.2].
Work In Process & Flow ManufacturingAdvisor Webcast Calendar And Archive[ID1319827.1]
All Advisor Webcasts[ID 1455888.1].
Continue the Discussion on the Work InProcess & Flow Manufacturing My OracleSupport Community.
My Oracle Support Community
C ll b t ith l t k f i d t t f i l
https://support.oracle.com/rs?type=doc&id=1417725.2https://support.oracle.com/rs?type=doc&id=1417725.2https://support.oracle.com/rs?type=doc&id=1319827.1https://support.oracle.com/rs?type=doc&id=1319827.1https://support.oracle.com/rs?type=doc&id=1319827.1https://support.oracle.com/rs?type=doc&id=1319827.1https://support.oracle.com/rs?type=doc&id=1455888.1https://support.oracle.com/rs?type=doc&id=1455888.1https://communities.oracle.com/portal/server.pt/community/work_in_process___flow_manufacturing/478https://communities.oracle.com/portal/server.pt/community/work_in_process___flow_manufacturing/478https://communities.oracle.com/portal/server.pt/community/work_in_process___flow_manufacturing/478https://communities.oracle.com/portal/server.pt/community/work_in_process___flow_manufacturing/478https://communities.oracle.com/portal/server.pt/community/work_in_process___flow_manufacturing/478https://communities.oracle.com/portal/server.pt/community/work_in_process___flow_manufacturing/478https://support.oracle.com/rs?type=doc&id=1455888.1https://support.oracle.com/rs?type=doc&id=1455888.1https://support.oracle.com/rs?type=doc&id=1319827.1https://support.oracle.com/rs?type=doc&id=1319827.1https://support.oracle.com/rs?type=doc&id=1319827.1https://support.oracle.com/rs?type=doc&id=1319827.1https://support.oracle.com/rs?type=doc&id=1417725.2https://support.oracle.com/rs?type=doc&id=1417725.2 -
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
79/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.79
Collaborate with a large network of your industry peers, support professionalsexperts to exchange information, ask questions & get answers.
Visit the My Oracle SupportCommunity now!!
1. Log into My Oracle Support.
2. Select the Community tab.
3. Start typing the community
name in the Find aCommunity Quick Find field.
Advisor Webcast Program
https://metalink.oracle.com/https://metalink.oracle.com/ -
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
80/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.80
Register for upcoming live advisorwebcasts.
Access past webcast recordingsand presentation material.
Continue the discussion on aspecific webcast topic.
Let us know what topics you would
like presented in the communities orin the post webcast survey.
Doc Id 740966.1
Learn MoreAvailable References and Resources to Get Proactive
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
81/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.81
About Oracle Support Best Practices
www.oracle.com/goto/proactivesupport
Get Proactive in My Oracle Supporthttps://support. oracle.com| Doc ID: 432.1
Get Proactive Bloghttps://blogs.oracle.com/getproactive/
Ask the Get Proactive [email protected]
http://www.oracle.com/goto/proactivesupporthttps://support.us.oracle.com/https://blogs.oracle.com/getproactive/mailto:[email protected]:[email protected]:[email protected]:[email protected]://blogs.oracle.com/getproactive/https://support.us.oracle.com/http://www.oracle.com/goto/proactivesupport -
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
82/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.82
THANK YOU
-
7/26/2019 Mfg WIP Advisor Webcast 2013 1204
83/83
Copyright 2013, Oracle and/or its affili ates. All rights reserved.83