Menindee Lakes Water Savings Project Business Case
Transcript of Menindee Lakes Water Savings Project Business Case
DISCLAIMER:
This is a preliminary business case, used to inform decision-making by the Murray-
Darling Basin Ministerial Council and Basin Officials’ Committee on sustainable
diversion limit adjustment mechanism projects.
The document represents the Business case for Menindee Lakes Water Savings
Project at June 2017.
The NSW Department of Industry is currently developing project summary documents
that will summarise project details, and will be progressively published on the
Department of Industry website.
Detailed costings and personal information has been redacted from the original
business case to protect privacy and future tenders that will be undertaken to deliver
these projects.
Menindee Lakes Notification - Attachment A
Menindee Lakes
Water Savings Project
Phase 2 Business Case J
une 2017
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
COMMERCIAL IN CONFIDENCE PAGE 2
Blackwatch Consulting Pty Ltd
37 Avenue Rd Mosman NSW 2088
0409164566
The document may only be used for the purpose for which it was commissioned and in accordance with the Terms of Engagement for the commission. Unauthorised
use of this document in any form whatsoever is prohibited.
Document Status
Status Version Date Author Review Date Approval
Preliminary draft for internal review 2.1 23 May 2017 BT BWC team 23-31 May 2017
Draft Business Case for submission to client 2.43 8 June 2017 BWC Team DPI 8 June 2017
Final Business Case for submission to BOC 2.5 9 June 2017 BWC Team DPI 9 June 2017
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
COMMERCIAL IN CONFIDENCE PAGE 3
LIST OF FIGURES .................................................................................................................................................. 5
LIST OF TABLES ................................................................................................................................................... 6
GLOSSARY OF TERMS AND ACRONYMS ............................................................................................................... 7
1 PROJECT SYNOPSIS .................................................................................................................................. 8
Key Features of this Proposal ..................................................................................................................................... 8 1.1
1.2 Project Purpose ........................................................................................................................................................... 8
1.3 Project Background ............................................................................................................................................................. 9
1.4 Proposed Works Measures ....................................................................................................................................... 10
1.5 Preliminary Project Costs and Benefits ..................................................................................................................................... 14
1.6 Stakeholder and Community Consultation ................................................................................................................ 15
1.7 Project Delivery ............................................................................................................................................................................ 16
1.8 Legislative and Regulatory Frameworks ................................................................................................................... 18
1.9 Next steps .................................................................................................................................................................. 18
2 BACKGROUND - MENINDEE LAKES & THE LOWER DARLING RIVER ............................................... 19
Lower Darling & Menindee Lakes ........................................................................................................................................... 19 2.1
2.2 Development of a regulated river system .................................................................................................................. 20
2.3 Storage Capacities .................................................................................................................................................... 23
2.4 The Lower Darling Regulated River System ............................................................................................................. 24
2.5 The Great Darling Anabranch .................................................................................................................................... 24
3 MENINDEE LAKES AND LOWER DARLING SYSTEM ECOLOGY ......................................................... 27
3.1 Menindee Lakes ........................................................................................................................................................ 27
3.2 Lower Darling and Great Darling Anabranch ............................................................................................................ 30
4 MENINDEE LAKES OPERATIONAL ARRANGEMENTS ........................................................................... 31
4.1 Operating Objectives ................................................................................................................................................. 31
4.2 Current Operating Strategy........................................................................................................................................ 31
4.3 Drought Operations ........................................................................................................................................................... 32
4.4 Flood Operations ....................................................................................................................................................... 32
4.5 “Harmony Operation” with Lake Victoria ................................................................................................................................... 33
5 OVERVIEW OF PROPOSED WORKS AND MEASURES ....................................................................... 34
6 PROPOSED INFRASTRUCTURE MEASURES ........................................................................................ 36
Measure 1 – Enlarged Menindee Regulator Outlet ................................................................................................... 37 6.1
6.2 Measure 2 – Lake Menindee Drainage Channel ....................................................................................................... 39
6.3 Measure 3 – Morton-Boolka Regulator ..................................................................................................................................... 41
6.4 Measure 4 – Old Menindee Town Weir removal ..................................................................................................................... 43
6.5 Measure 5&6 – Lower Darling Channel Capacity (Yartla & Emu Lakes) ............................................................................. 44
6.6 Measure 7 – Cawndilla Creek Regulator ................................................................................................................... 46
6.7 Measure 8,9&11 – Anabranch Offtake Regulators, Dam 183 regulator ................................................................... 48
6.8 Measure 10 – Menindee Main Weir Fish Passage .................................................................................................... 52
6.9 Measure 12 – Flood Protection - Menindee residents .............................................................................................. 53
6.10 Measure 13 – Lower Darling Constraints Mitigation Works ................................................................................................... 55
7 PROPOSED STRUCTURAL ADJUSTMENT MEASURES ...................................................................... 57
7.1 Measure 14 – Acquisition of Lower Darling & Webster Ltd. (Tandou) entitlements ........................................................... 57
8 PROPOSED INSTITUTIONAL ARRANGEMENTS / OPERATING RULES .............................................. 59
Measure 15 - Menindee System Control Transfer & Storage Drawdown ............................................................................ 59 8.1
8.2 Measure 16 - Broken Hill Entitlement........................................................................................................................................ 60
8.3 Measure 17 - Cawndilla Additional E-flows .............................................................................................................................. 61
8.4 Measure 18 - River Murray Improved Operations ................................................................................................................... 63
8.5 Measure 19 - Lake Wetherell (floodplain) drying cycle ........................................................................................................... 63
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
COMMERCIAL IN CONFIDENCE PAGE 4
9 CONCURRENT MEASURES .................................................................................................................... 64
9.1 Measure 20 - Broken Hill TWS Alternate Supply ..................................................................................................................... 64
10 OTHER MEASURES ............................................................................................................................ 66
10.1 Measure 21 - Northern Basin Inflows ................................................................................................................................. 66
10.2 Measure 22 - Lower Darling Temporary Trade ................................................................................................................. 66
11 KEY STAKEHOLDERS AND THE BROADER COMMUNITY .............................................................. 67
12 ENVIRONMENT AND HERITAGE ........................................................................................................... 71
12.1 Environmental Impacts ....................................................................................................................................... 71
12.2 Cultural Heritage ................................................................................................................................................................... 73
13 RISKS AND ISSUES ............................................................................................................................ 76
13.1 Assessment Process .................................................................................................................................... 76
13.2 Risk and Issues – Inherent Heat Map (before mitigation) ................................................................................. 79
13.3 Risk and Issues – Residual Heat Map (after mitigation) .................................................................................... 81
14 PROJECT COSTS ................................................................................................................................. 83
14.1 Infrastructure Costs .................................................................................................................................................... 83
14.2 Non-Construction Project Costs ......................................................................................................................... 84
14.3 Contingencies ...................................................................................................................................................... 87
14.4 Structural Adjustment Costs ................................................................................................................................................ 88
14.5 Funding Requirements - Timings ....................................................................................................................... 89
14.6 Price Escalation ................................................................................................................................................... 89
14.7 Operating and Maintenance Costs ...................................................................................................................... 89
15 PROJECT DELIVERY.......................................................................................................................... 92
15.1 Project Management Plan ................................................................................................................................... 92
15.2 Project Schedule .................................................................................................................................................. 93
15.3 Procurement Strategy .......................................................................................................................................... 95
15.4 Quality Assurance ............................................................................................................................................... 95
16 PROJECT GOVERNANCE .................................................................................................................. 96
16.1 Governance Overview ........................................................................................................................................ 96
17 LEGISLATIVE AND REGULATORY FRAMEWORK FOR MENINDEE LAKES ...................................... 98
REFERENCES ..................................................................................................................................................... 102
APPENDIX 1 – MENINDEE LAKES INTER-JURISDICTIONAL WORKING GROUP ....................................... 103
APPENDIX 2 – MENINDEE LAKES INTER-AGENCY WORKING GROUP ...................................................... 105
APPENDIX 3 – RISKS AND ISSUES – RISK REGISTER ................................................................................. 107
APPENDIX 4 – EIS REQUEST FOR TENDER – (DRAFT REQUIREMENTS) ................................................. 115
APPENDIX 5 – MENINDEE PROJECT COSTINGS .......................................................................................... 128
APPENDIX 6 – ENGINEERING CONCEPT DESIGN DRAWINGS AND SPECIFICATIONS ........................... 141
APPENDIX 7 – ENVIRONMENTAL WATER NEEDS AND WATER MGMT ARRANGEMENTS .................... 147
APPENDIX 8 – DETAILED PROJECT SCHEDULE .............................................................................................. 148
APPENDIX 9 – PROCUREMENT PLAN ............................................................................................................ 149
APPENDIX 10 – INTERIM PROJECT PROPOSAL – APRIL 2017 ................................................................... 151
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
COMMERCIAL IN CONFIDENCE PAGE 5
LIST OF FIGURES
Figure 1: Menindee Lakes and Lower Darling Catchment (Green et al. 2012) ........................................................... 19
Figure 2: Average Monthly Rainfall (Menindee) and Evaporation (Broken Hill) .......................................................... 20
Figure 3: Schematic diagram showing regulating structures in Menindee Lakes system ............................................ 21
Figure 4: Location Map Darling Anabranch (Source Earth Tech 2004) ...................................................................... 25
Figure 5: Proposed Location of Infrastructure Works in Scope .................................................................................. 35
Figure 6: Measure 1 - Enlarged Menindee Regulator .................................................................................................. 38
Figure 7: Measure 7 - Cawndilla Creek inundation mapping ...................................................................................... 47
Figure 8: Measure 8 – Approximate Locality of anabranch regulator ......................................................................... 50
Figure 9: Measure 8 – Proposed anabranch offtake regulator ..................................................................................... 51
Figure 10: Menindee Township Inundation Map at 25,000ML/day ............................................................................ 54
Figure 11: Licence Entitlements – High Security ........................................................................................................ 58
Figure 12: Broken Hill Water Supply - Schematic ...................................................................................................... 65
Figure 13: Project Cost Breakdown ............................................................................................................................. 83
Figure 14: Projected Project Expenditure by Year ...................................................................................................... 89
Figure 15: Key Milestones for Project ......................................................................................................................... 93
Figure 16: Early Estimates of FTE requirements ........................................................................................................ 94
Figure 17: Overview of Proposed works ................................................................................................................... 116
Figure 18: Measure 1 – Menindee Regulator – Aerial View ..........................................................................................141
Figure 19: Measure 1 – Menindee Regulator – Side View ........................................................................................ 142
Figure 20: Measure 2 – Menindee Channel – Cross Sections 1 ............................................................................. 143
Figure 21: Measure 2 – Menindee Channel – Cross Sections 2 ............................................................................. 144
Figure 22: Measure 3 – Morton-Boolka Regulator .................................................................................................... 145
Figure 23: Measure 8 – Darling Anabranch Offtake regulator .................................................................................. 146
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
COMMERCIAL IN CONFIDENCE PAGE 6
LIST OF TABLES
Table 1: Summary of Works and Measures ............................................................................................................... 11
Table 2: Project capital costs (draft) ........................................................................................................................... 14
Table 3: Operating & maintenance costs (draft) ........................................................................................................ 14
Table 4: Phased Delivery of Menindee Water Savings project .................................................................................. 17
Table 5: Maximum Release Rates of main regulating structures in the Menindee Lakes system ............................ 23
Table 6: Storage Capacities ......................................................................................................................................... 23
Table 7: Vegetation Communities Identified ............................................................................................................... 28
Table 8: Listed wetland flora species from the Menindee Lakes ............................................................................... 29
Table 9: Licence numbers by category in lower darling ............................................................................................. 55
Table 10: Licences ...................................................................................................................................................... 58
Table 11: Licence Entitlements (Volumes) ................................................................................................................. 58
Table 12: Stakeholder Matrix ...................................................................................................................................... 68
Table 13: Likely approvals process for the Menindee Lakes project ......................................................................... 72
Table 14: Registered aboriginal sites within the study area .......................................................................................... 74
Table 15: Issues Summary. ........................................................................................................................................ 75
Table 16: Risk Matrix .................................................................................................................................................. 76
Table 17: Consequence Matrix. .................................................................................................................................... 77
Table 18: Inherent Risk Heat MAp. ............................................................................................................................ 79
Table 19: Residual Risk Heatmap .............................................................................................................................. 81
Table 20: Infrastructure Costs (Total Prime Costs) .................................................................................................... 84
Table 21: Non-Construction project costs .................................................................................................................. 85
Table 22: Structural adjustment provisions ................................................................................................................ 88
Table 23: Operating and Maintenance Costs ............................................................................................................... 91
Table 24: Estimated project milestones ..................................................................................................................... 93
Table 26: Comparison of the current prosed Menindee project with the 2013 proposal ......................................... 117
Table 27: Measure 1 – Enlarged Menindee regulator (prime costs) ....................................................................... 128
Table 28: Measure 2 – Menindee Drainage Channel (prime costs) ........................................................................ 129
Table 29: Measure 3 – Morton-Boolka Regulator (prime costs) .............................................................................. 130
Table 30: Measure 4 – Old Menindee town weir removal (prime costs) ................................................................. 131
Table 31: Measure 5 – Emu Lake offtake regulator (prime costs) ........................................................................... 132
Table 32: Measure 6 – Yartla Lake offtake regulator ............................................................................................... 133
Table 33: Measure 7 – Cawndilla creek regulator (prime costs) ............................................................................. 134
Table 34: Measure 8 – Darling anabranch offtake regulator (prime costs) ............................................................. 135
Table 35: Measure 9 – Darling anabranch e-flow regulator (prime costs) ............................................................... 136
Table 36: Measure 10 – main weir fishway (prime costs) ........................................................................................... 137
Table 37: Measure 11 – 183 Dam Regulator, Road Bridge & Fishway (prime costs) ............................................. 138
Table 38: Measure 12 – Menindee Town Flood Protection works (prime costs) .................................................... 139
Table 39: Measure 13 – Lower Darling constraints mitigation works (prime costs) ................................................ 140
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
COMMERCIAL IN CONFIDENCE PAGE 7
GLOSSARY OF TERMS AND ACRONYMS
ANZECC Australian and New Zealand Environment and Conservation Council.
AHD Australian Height Datum
AHIP Aboriginal Heritage Impact Permit
BOC Basin Officials Committee
BSMS Basin Salinity Management Strategy
DOC Dissolved Organic Carbon
DN Diameter Nominal (internal diameter of a pipe)
EC Electrical Conductivity – a measure of salinity
EIS Environmental Impact Statement
Environmental
watering
Provision of water, authorised by an access entitlement, to a location for the
achievement of ecological targets and objectives.
EP&A Act Environmental Planning and Assessment Act 1979 (NSW)
IAWG Interagency Working Group
IJWG Interjurisdictional Working Group.
GL Gigalitres
mg/L Milligram per Litre
MinCo Ministerial Council
ML Megalitres
ML/day Megalitres per Day
Murray Darling Basin
(MDB)
Comprises the catchment of the Murray and Darling Rivers and their many
tributaries, extending from north of Roma in Queensland to Goolwa in South
Australia.
Murray Darling Basin
Agreement Commonwealth Water Act (2007) : Schedule 1 Murray Darling Basin Agreement
Murray Darling Basin
Authority (MDBA)
The authority responsible for managing the Basin’s water resources in the national
interest, in cooperation with state authorities, with the aim of ensuring reliable water
supplies for all users. (Formerly Murray Darling Basin Commission – MDBC)
NOW NSW DPI Water
OEH Office of Environment & Heritage (NSW).
ppm Parts per Million
RL Reference Level
SDL Sustainable Diversion Limits
SDLAM Sustainable Diversion Limits Adjustment Mechanism
TWS Town Water Supply
Water Year An accounting period from 1 July to 30 June, seasonally aligned and corresponding
to water allocation policy in the River Murray system.
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
COMMERCIAL IN CONFIDENCE PAGE 8
1 PROJECT SYNOPSIS
The Menindee Lakes Water Savings Project Business Case is submitted as part of Phase 2 requirements
for proposed Supply Measures under the Murray Darling Basin Plan.
The Business Case confirms that Menindee is capable of making a valuable contribution to Basin Plan
outcomes. It draws upon the current state of knowledge and issues, which in some cases has evolved
over many years of investigations and consultation in a highly variable and sometimes controversial
operating environment.
Where insufficient information is currently available the Business Case provides details of work underway
to fill knowledge gaps, ahead of the final Phase 3 submission in November 2017.
The NSW Government is pleased to have reached this important milestone for such an important project.
1.1 1 Key Featu res of thi s Pro posal
The Menindee Project (the Menindee Project) plan, costings and schedule have been completed
in concept form and the MDBA modelling of expected water savings is underway as part of the
Sustainable Diversion Limit Adjustment Mechanism.
The project includes five key categories of co-dependent works and measures, including
infrastructure works estimated to cost approximately $152 million.
The schedule indicates that the works and measures can be completed before the 2024 target
date with a modest margin, provided:
o that there are no undue delays from the approvals process or significant inundation of the
Lakes.
o that some activities are undertaken in parallel with the approvals process.
The project risk analysis indicates that all identified inherent risks can be reduced to manageable
levels with the right controls in place.
Commercial discussions have commenced with landholders in relation to structural adjustment,
for which a successful outcome is critical to the Project’s success.
The Project will create environmental and socio-economic benefits at the local level as well
making significant contributions to Basin Plan outcomes.
1.2 2 Project Pu rp o se
The Menindee Project is a multi-faceted suite of works and measures contributing to water savings,
improved river operations, and environmental improvements, both locally and across the Murray Darling
Basin.
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
COMMERCIAL IN CONFIDENCE PAGE 9
1.3 3 Pr oject Ba ckgr ound
The Menindee Project is being developed as part of the Murray Darling Basin Plan (the Plan). The Basin
Plan sets out Sustainable Diversion Limits (SDL) across the Basin that represent an overall reduction
of 2,750 GL in extractions, based on existing permitted use, as at June 2009. The SDL Adjustment
Mechanism (SDLAM) provides an opportunity to account for the equivalent environmental outcomes
achieved from the improved management of the Lake system and more efficient use of water by
environmental water holders.
Projects to be considered under the SDLAM for this purpose are referred to as supply measures (which
enable equivalent environmental outcomes to be achieved with less water); the SDLAM also allows for
efficiency measures (which increase the volume of water available for environmental use by improving
the efficiency with which water is used for consumptive purposes). In addition, a suite of works and
measures are being developed to overcome known system constraints which limit the potential for
higher river flows and environmental benefits.
Detailed studies between 2006 and 2013 considered a range of potential schemes to provide water
savings at Menindee. In 2013, the Commonwealth and NSW governments agreed to further investigate
a scope of infrastructure works and potential changes to the Murray-Darling Basin Agreement aimed at
realising evaporative water savings, whilst recognising the water supply benefits to Basin States, the
natural environmental values of the Lakes, and the recreational and social amenity the Lakes provide
for the region.
The Commonwealth has reserved funding of $156 million for a Menindee water savings project. The
NSW Government has also committed to a solution for water security for Broken Hill, with $500 million
available for this purpose. Together these commitments recognise the ongoing importance of improving
water management of Menindee Lakes for the Basin and the local region.
The Menindee Project seeks to achieve significant evaporative water savings by:
a. allowing operation of Lake Menindee independently of Lake Cawndilla, and
decommissioning Lake Cawndilla for the purposes of water storage in all but the wettest
years;
b. removing high security irrigation and town water supply demands from the Lakes through a
combination of infrastructure works and structural adjustment mechanisms;
c. allowing faster drawdown of water in Lake Menindee, including access to residual water;
d. by enlarging the outlet structure and constructing a drainage feeder channel in the bed of
the Lake; and
e. accommodating higher managed flows in the Lower Darling through works which aim to:
o limit breakouts onto the floodplain and into dry Lakes and anabranches, and
o protect private infrastructure from being impacted by higher flows, including changed
operational rules to complement the structural works.
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
COMMERCIAL IN CONFIDENCE PAGE 10
As a consequence of the proposed works and measures, the project will also make significant
contributions to overcoming system constraints and improve the ability for operators to achieve higher
flow events in the Lower Murray.
1.4 4 Pr opose d Works Me asures
The package includes five categories of works and measures: -
1. Infrastructure works
2. Structural Adjustment measures
3. Changes to institutional arrangements and operating rules
4. Concurrent measures
5. Other measures
Section 6 details the objectives of each measure in the package. Whilst individual elements each bring
their own specific benefits and costs to the project, there are critical dependencies between the elements
of the package which may in some cases render the project unviable if one or more elements are not
pursued as part of the package.
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
COMMERICAL IN CONFIDENCE PAGE 11
TABLE 1: SUMMARY OF WORKS AND MEASURES
Measure 1 Menindee outlet regulator capacity increased
from 5,000ML/day.
Measure 2 Lake Menindee drainage channel to feed
outlet and improve discharge
Morton-Boolka transfer regulator to control
Works to increase up to 14,000ML/day SDL supply measure, and
Constraints Management
Drainage channel up to 14,000ML/day SDLsupply measure
Up to 14,000ML/day regulator SDLsupply measure
Measure 3 releases to and from Menindee and
Cawndilla
Measure 4 Old Menindee Town Weir removal Removal of redundant Menindee town weir to improve
Menindee outlet regulator flows by reducing downstream
head
Constraints Management
Measure 5, 6 &
11
Increased Lower Darling channel capacity to
take higher Menindee discharge – offtake
regulators at Emu Lake and Yarta Lake
Two regulators to prevent escape flows into Yartla Lake
and Emu Lake + bridge at Charlie Stone Crossing
SDL supply measure, and
Constraints Management
Measure 7 Cawndilla Creek Regulator Up to 14,000ML/day regulator Environmental mitigation
Measure 8 & 9 Anabranch offtake regulators constructed New Anabranch diversion regulator #1 to control up to
14,000ML/day
SDL supply measure, and
Constraints Management
Measure 10 Works to facilitate fish passage at Menindee
Main Weir
New Anabranch environmental Regulator #2 to control up
to 1,000ML/day, and Dam183 road bridge, regulator, and
fishway
No change to hydrology but fishway on Main Weir included
in costings
Environmental mitigation
Lake Nearie Nature Reserve
Measure 12 Flood protection measures for Menindee
residents
Construction of Menindee town high flow levee bank Constraints Management
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
COMMERICAL IN CONFIDENCE PAGE 12
Measure 13 Lower Darling constraints mitigation -
landholders stock and domestic & some
irrigation pump infrastructure.
Assumption holds. Works now protect and maintain
capacity of pumps during high flow events (ie : floating
suctions, on farm storage and / or groundwater options)
Constraints Management
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
COMMERICAL IN CONFIDENCE PAGE 13
Feature Details Basin Plan
Outcomes St
ruct
ura
l
Ad
just
men
t M
easu
res
Measure 14
Acquisition of Lower Darling and Tandou
water entitlements
Purchase all Tandou entitlements and purchase or convert
Lower Darling HS entitlement.
Structural adjustment
mechanism
nges to
Opera
tin
g R
ule
s an
d A
gre
em
ents
Measure 15
Menindee System control transfer rule
(between NSW and the MDBA) and storage drawdown sequencing
No control transfer in place – MDBA to assume full control
of Menindee on understanding 80GL Wetherell reserve is retained for riparian demands to end of following year.
SDL supply measure
Measure 16
Broken Hill Entitlement
10,000M TWS entitlement shifted to Murray upstream
SDL supply measure
Wentworth.
Measure 17 Capacity for additional E-flows into Lake
Cawndilla
Potential use of Environmental account water to inundate
key assets in addition to natural events. Environmental mitigation
Measure 18
Improved operations of the River Murray
connected system
Proposed recalibration of the SDL Projects Pack OPLOSS
regression equation to better reflect current operating
environment
SDL supply measure
Cha
Measure 19
Lake Wetherell drying cycle
Hardwired drying cycle for Wetherell floodplain
Environmental mitigation
Measure 20 Broken Hill TWS system – alternate supply Pipeline from Murray River @ Wentworth SDL supply measure
COMMERICAL IN CONFIDENCE PAGE 14
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Feature Details Basin Plan Outcomes
W
ork
s &
Mea
sure
s
O
the
r M
easu
res
Rem
ov
ed f
rom
Sco
pe
Measure 21 Recognition of additional Northern basin
inflows to Menindee Lakes from Basin Plan
environmental recovery
Formally recognise the additional inflow and make callable
from a separate account
Supply measure
Measure 22 Limited temporary general security trade to
the Lower Darling subject to resource
assessment
Will be reflected in water planning rules
Basin Plan dealing rules
Deleted
Lake Pamamaroo Drainage channel to
capture dead storage
N/A – works removed from scope
N/A
Deleted
Penellco Channel increased capacity to
service Tandou
N/A - Works removed from scope
N/A
MeMneinndienedLeaekeLsaNkeotsificWataiotenr- SAattavcinhmgsenPt rAoject
COMMERICAL IN CONFIDENCE PAGE 14
1.5 P rel imina ry Pro jec t Costs a n d Benef i ts
1.5.1 Costs
The total cost of works and measures, excluding the structural adjustment package, is estimated at
approximately $152 million, based on preliminary concept designs by NSW Public Works. Table 2 summarises
the estimated capital costs based on construction in the “dry”. Further discussion and detail of capital costs is
provided in Section 14.
The 30% allowance for contingency at this preliminary stage reflects the uncertainty in project scope ahead of field
investigations, approvals and detailed design.
TABLE 2: PROJECT CAPITAL COSTS (DRAFT)
NSW Public Works has also provided an initial estimate of the on-going operations and maintenance costs of the
works. These estimates have not yet been peer reviewed and as such are considered preliminary in nature.
Further consultation and refinement will take place over coming months in preparation of the Phase 3
submission.
TABLE 3: OPERATING & MAINTENANCE COSTS (DRAFT)
1.5.2 Benefits
Previous modelling of earlier versions of the Menindee Project indicated average annual water savings in the
order of 72GL. Whilst the expectation is that this enhanced proposal will increase the level of water savings,
detailed hydrologic modelling is not yet complete following submission of the final modelling brief to the MDBA in
April 2017. The results of the SDLAM modelling will be provided to Ministerial Council as part of the SDL Adjustment
process.
In addition, the Lower Darling has been identified by the MDBA as one of seven priority areas where relaxation of
physical flow constraints will provide significant environmental benefits. The primary constraint to targeting higher
river flows in the Lower Darling is the discharge capacity at Menindee Lakes, and particularly the Lake Menindee
Outlet.
MeMneinndienedLeaekeLsaNkeotsificWataiotenr- SAattavcinhmgsenPt rAoject
COMMERICAL IN CONFIDENCE PAGE 15
Flood Mitigation will also be improved through works around Menindee township to protect residences close to the
Darling River. This will also deliver the added benefit of providing some level of protection from natural flood events,
reducing the need to evacuate these residences during times of flooding, and provide greater flexibility in
managing flood events as they pass through the Menindee Lakes system.
Besides fish passage the benefits to the local environment will revolve around the greater flexibility provided to
the management of the Lakes, the Lower Darling and the Darling Anabranch supply pathways. Under existing
arrangements, reserves must be set aside to provide for Stock and Domestic and Local Water Utility in a repeat
of the worst drought, but this is not required for the High Security or recommended minimum flows. In practice, the
reserve volume required to ensure supply to Broken Hill is around 200GL and most of this is lost to evaporation.
In dry years NSW typically allows continued access by High Security water users around the Lakes due to the
small volumes involved, and meets downstream demands for riparian, High Security and Pooncarrie with a
reduced minimum flow target.
Existing water management decisions at Menindee Lakes are dominated by the need to provide for high reliability
supply to a volumetrically small amount of end user demand. The original selection of a NSW control threshold at
640/480GL was made on the basis of providing a reliable supply to NSW water users, in essence, a 480GL reserve
was created to support a total of 51GL of regulated delivery entitlement. This is clearly inefficient in the current
context.
NSW has been working with the Commonwealth Government to develop opportunities for amending system
management requirements, to avoid the continuation of the need for a large operational reserve, for the
purpose of delivering a small volume. The Commonwealth investment in the Menindee Lakes project is not simply
the purchase of water entitlements, but rather enabling the reserve reduction from 275GL to around 80GL.
The economic value of the purchase should be determined against the increased yield from the Menindee proposal
compared to the intermediate “Run 35”, which would become the default option if the strategic purchase does not
proceed.
NSW has in place an Aboriginal Participation In Construction (APIC) policy, to support greater participation
by Aboriginal people in government construction projects across NSW. Obligations under this policy are determined
by the total construction costs of the project. With this project falling with Category 2 (project value exceeds
$10million), at least 1.5% of the total estimated value of the contract must support direct and indirect Aboriginal
participation.
As part of a package of concurrent measures, NSW has committed significant funding towards the construction
of an alternate town water supply for Broken Hill. This project is currently in mid-stages of tendering for construction.
1.6 S ta k eh ol der a n d Com mun ity Co nsul tati on
Community consultation in regards to the Menindee Lakes project has been hampered over the past five years
due to the complexity of issues involved, including extreme and prolonged periods of drought and Broken Hill
water security issues.
Consultation was undertaken during the development of the options analysis by the NSW Government between
2006 and 2013. During this process, and in the early stages of business case investigations, key stakeholders
indicated concerns regarding:
MeMneinndienedLeaekeLsaNkeotsificWataiotenr- SAattavcinhmgsenPt rAoject
COMMERICAL IN CONFIDENCE PAGE 16
security of supply being further impacted and made worse;
loss of amenity at the Lakes, which are a key asset for the regional community;
the environmental values that have developed around current Lakes operations being
negatively impacted through the proposed changes;
evaporation occurring elsewhere in the basin is not being addressed, and that Menindee Lakes is being
unfairly targeted;
the perception that more water in the Lakes means more employment potential locally whether tourism,
fishing, or irrigation, which will be impacted under the proposed changes;
impacts on Broken Hill’s other recreation areas, which may potentially be drier – Copi Hollow, Sunset Strip
Kinchega National Park – under the proposed management arrangements;
Menindee town and economy of the region will be permanently depressed due to the proposed changes;
and
Concern that the environment of the Lower Darling, the Lakes and the Darling Anabranch will be less
valued than downstream environments.
Additionally, local Indigenous people and Traditional Owners expressed concern that the environment upon which
their culture is based will be impacted for the worse, with concerns that irrevocable damage will occur to
special areas and cultural heritage.
The reinvigoration of this project provides an opportunity to re-engage with the key stakeholders to ensure issues
are brought to the table and appropriately addressed.
At the time of preparation of this draft Business Case, stakeholder and community consultation is focused on
commercial negotiations with directly affected parties, as a precursor to the development of a structural adjustment
package. Broader community consultation is expected to commence in the last quarter of 2017 when commercial
discussions are more advanced. This Business Case also outlines proposed arrangements for Inter-Agency
and Inter-Jurisdictional engagement, which have already commenced informally and will be more formally
established from July 2017.
1.7 P r oje ct D el i ve r y
The Lake Menindee project will be delivered over a six year time frame, with an expectation that scheduled
works will be completed in 2023 prior to commissioning in the same year. Some parallel activities are required
to achieve completion in the time available. This has implications for project costs and in particular the risk of
rework and/or “regrets” expenditure.
Timeframes are highly dependent on the two key schedule risks, namely delays associated with environment
and heritage approvals and construction risks associated with lake inundation. In regard to the latter, wet weather
delivery options have been separately scoped and costed by NSW Public Works.
A project schedule has been prepared for the entire project and included at Appendix 8. The schedule decreases
in detail at the point of transition to the Execution phase, in consideration of increased uncertainty over scope
pending the outcomes of the EIS process. Section 15 provides detail around this schedule.
MeMneinndienedLeaekeLsaNkeotsificWataiotenr- SAattavcinhmgsenPt rAoject
COMMERICAL IN CONFIDENCE PAGE 17
The table below summarises the proposed project delivery plan, involving five phases:
TABLE 4: PHASED DELIVERY OF MENINDEE WATER SAVINGS PROJECT
Project Phase Description Completion
Phase 1
Phase 2a
Draft Business Case – Options Report
Concept design outlining the basic suite of works and
management rule changes
August 2016
Interim Project Proposal Project scope definition and modelling requirements
April 2017
Phase 2b
Preliminary Business Case
Phase 2 submission
June 2017
(this submission)
Phase 3
Final Business Case Phase Residual Phase 2 information and Phase 3 requirements
November 2017
Phase 4a
Project Initiation, Planning and Approvals All activities required to take the project to the point of
December 2021^
Phase 4b
construction/implementation.
Project Execution and Completion Implementation of all construction works and other measures
^ (excluding structural
adjustment processes)
September 2023
through to commissioning and handover
MeMneinndienedLeaekeLsaNkeotsificWataiotenr- SAattavcinhmgsenPt rAoject
COMMERICAL IN CONFIDENCE PAGE 18
1.8 L e gi sl a ti ve an d R eg ul a tor y F r a m ew or k s
The ownership, operations and maintenance of the Menindee Lakes sits within a complex suite of independent
but interrelated legislative, regulatory and commercial instruments and agreements. The changes contemplated
in this Business Case will necessitate changes to these guiding documents. Whilst a detailed legal review is
yet to be undertaken, provision has been made in both time and cost to undertake such a review as part of the
Phase 3 final submission.
Section 17 provides further details in regard to institutional arrangements.
1.9 Nex t steps
On the basis that the Phase 2 Preliminary Business Case is accepted and notified as part of the SDLAM
package by the Basin Officials Committee, the next steps to progressing the business case to Phase 3 Final
Submission will focus on further developing stakeholder engagement and communications plans as well as
confirming, updating and coordinating matters identified in the Phase 2 preliminary business case prior to the
submission of the Phase 3 documentation to MinCo for final approval.
The specific Phase 3 activity currently identified includes;
Stakeholder Engagement / Communications
o Developing stakeholder engagement strategy;
o Developing communications strategy / plan;
o Coordinating and supporting to IAWG;
o Coordinating and supporting to IJWG; and
o Re-engaging with Community representatives.
Confirming, Updating and Coordinating
o Governance arrangements;
o Funding needs and peer review of costs undertaken;
o SDL modelling;
o Links to supply measures;
o Final Advice on E-water delivery;
o Final Advice on risks & 3rd Party Impacts; o
Legal & legislative changes required; and o All
approvals in train.
Preparing and submitting updated Phase 3 business case to Basins Officials Committee for
confirmation.
Additionally, to meet the timelines currently proposed there are additional Phase 4 activities that will need to be
undertaken in parallel with the submission of the Final Phase 3 business case. These activities include;
Confirming Phase 4 Project Plan & Procurement Strategy,
Commencing procurement of EIS scoping study.
MeMneinndienedLeaekeLsaNkeotsificWataiotenr- SAattavcinhmgsenPt rAoject
COMMERICAL IN CONFIDENCE PAGE 19
2 BACKGROUND - MENINDEE LAKES & THE LOWER DARLING RIVER
2.1 1 L ow er D arl i n g & M eni nd ee L ak es
The Lower Darling River System is located in South-Western New South Wales and comprises the portion of
the Darling River that is regulated by releases from the Menindee Lakes System. The three main features
of the study area are:
The Menindee Lakes - a series of once intermittent, shallow wetlands that have been formally used for
water storage since the 1960s.
The Lower Darling River - 530 km of main channel from the Menindee Lakes to the confluence with the
Murray River at Wentworth.
The Great Darling Anabranch - a former channel of the Darling River and associated floodplain wetlands.
FIGURE 1: MENINDEE LAKES AND LOWER DARLING CATCHMENT (GREEN ET AL. 2012)
MeMneinndienedLeaekeLsaNkeotsificWataiotenr- SAattavcinhmgsenPt rAoject
COMMERICAL IN CONFIDENCE PAGE 20
The climate is semi-arid, characterised by low rainfall (average annual rainfall of approximately 300 mm) and
high evaporation (average annual evaporation of 2,700 mm) (Figure 2).
Rainfall Evapora on
450
400
350
300
250
200
150
100
50
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
FIGURE 2: AVERAGE MONTHLY RAINFALL (MENINDEE) AND EVAPORATION (BROKEN HILL) 1
The Menindee Lakes are a key storage in the Murray-Darling system, supplying towns and irrigation along the
Murray and Lower Darling rivers. They are also an area of significant environmental importance, and provide
recreational amenity and tourism opportunities for the region.
The Lakes area is also rich in cultural history. Aboriginal people have occupied the Menindee region for at least
47,000 years (Balme and Hope, 1990); and in 2015, the Barkandji people were granted native title over lands
and waters extending from Wilcannia to Wentworth. The Lakes and the Lower Darling and Darling Anabranch
continue to be important to the wider Aboriginal community as resources and places of significance.
2.2 2 Deve lo pm e nt of a re gula ted rive r syste m
In the 1960s the Menindee Lakes were modified to act as a water resource storage to supply Broken Hill, users
in the Lower Darling, and the Lower Murray Region. A series of weirs, regulators, channels and levees were
constructed to store large upstream events.
The townships of Menindee, Broken Hill, Silverton and Pooncarie are all supplied with water from the Lower
Darling system. There are also a number of private irrigators located south of Menindee Lakes who extract water
directly from the river.
The regulated storage system consists of four main interconnected Lakes. Of these, three are modified
natural depressions (Lakes Pamamaroo, Menindee and Cawndilla), while the fourth (Lake Wetherell) is an
artificial lake along the main river channel, formed by the construction of Main Weir. A channel was built to connect
Lakes Pamamaroo and Menindee (via Copi Hollow), while the other
1 1995 - 2017 (DATA FROM THE BUREAU OF METEOROLOGY CLIMATE DATA ONLINE)
Avera
ge
month
ly (
mm
)
MeMneinndienedLeaekeLsaNkeotsificWataiotenr- SAattavcinhmgsenPt rAoject
COMMERICAL IN CONFIDENCE PAGE 21
interconnections are modified natural channels. In total, there are seven main regulating structures, as shown
in Figure 3.
FIGURE 3: SCHEMATIC DIAGRAM SHOWING REGULATING STRUCTURES IN MENINDEE LAKES SYSTEM
Total releases from Menindee Lakes to the Darling River are measured at Weir 32, located downstream
of all lake outlet locations Figure 3. Weir 32 was constructed in 1958 to provide additional security for the
Broken Hill and Menindee town water supplies, and has a capacity of approximately 4 GL.
The structures in Figure 2 and further detailed in Table 5 allow water to be transferred both between the Lakes
and to the main Darling River channel. Releases to the River can be made independently from Lakes Wetherell,
Pamamaroo and Menindee — water cannot be released directly from Lake Cawndilla to the Darling River,
instead it must first pass through Lake Menindee, otherwise Lake Cawndilla may only be diverted down the
Great Darling Anabranch from the Lake Cawndilla outlet regulator. This water passes via Cawndilla channel to
Tandou Creek, where it’s contained by a block bank and regulator at Packers Crossing. From this point, water
is diverted to Lake Tandou for irrigation by Tandou Limited, or released downstream to Redbank Creek and
then into the main channel of the Great Darling Anabranch.
The maximum release rates listed in
MeMneinndienedLeaekeLsaNkeotsificWataiotenr- SAattavcinhmgsenPt rAoject
COMMERICAL IN CONFIDENCE PAGE 22
Table 5 for Lakes Wetherell, Pamamaroo and Menindee are available when storage levels are high and the
Darling River level is low. At other times, the available release rates are lower.
MeMneinndienedLeaekeLsaNkeotsificWataiotenr- SAattavcinhmgsenPt rAoject
COMMERICAL IN CONFIDENCE PAGE 23
TABLE 5: MAXIMUM RELEASE RATES OF MAIN REGULATING STRUCTURES IN THE MENINDEE LAKES SYSTEM
Regulator Max Release Rate (ML/day)
Main Weir (and associated levees) (Main Weir gates) 70,000
(Main Weir spillway) 110,000
Lake Wetherell outlet 5,000
Lake Pamamaroo inlet 33,000
Lake Pamamaroo outlet 5,000
Lake Menindee inlet 25,000
Lake Menindee outlet 4,000
Lake Cawndilla outlet 2,000
Weir 32 (Fixed Crest) Drowned at 8,000
Note: actual rate of release dependent on lake levels at any given time.
2.3 3 S to ra ge Ca pa ci ti e s
The four major Lakes (Pamamaroo, Menindee, Cawndilla and Wetherell) have a nominal full supply volume of
1,731GL and can be surcharged to hold up to 2,050GL during floods. However, the Lakes are located in a hot,
windy, semi-arid environment, with a combined surface area of 457.3 km2, making them relatively shallow
and prone to average annual evaporation losses of over 420GL of water per annum, which is significantly
higher than other storages throughout the Murray–Darling Basin.
TABLE 6: STORAGE CAPACITIES
Lake Full Supply
level
(m AHD)
Full Supply
Volume
(GL)
Maximum
Surcharge
Level
(m AHD)
Maximum
Surcharge
Volume
(GL)
Dead
Storage
(m AHD)
Dead
Storage
Volume
(GL)
Wetherell 61.67 193.0 62.30 262.2 52.50 0.5
Pamamaroo 60.45 277.7 61.50 353.0 56.00 10.9
Menindee 59.84 629.5 60.45 729.0 55.90 60.0
Cawndilla 59.84 631.0 60.45 705.0 54.00 48.0
TOTAL 1,731.2 2,049.2 119.4
Copi Hollow only 61.50 12.2 58.30 2.7
Lake Tandure only 61.67 77.4 57.80 9.4
The nominal full supply levels and maximum surcharge levels presented in Table 6 are lower than the original
design capacity of 2,400GL. These lower levels have been adopted to minimise risks to a number of structures.
Reduced surcharge levels and lower operating levels also minimise lake foreshore erosion, particularly
erosion of the sensitive lunettes, and subsequent impacts on the indigenous archaeology contained in the
sediments surrounding the Lakes.
MeMneinndienedLeaekeLsaNkeotsificWataiotenr- SAattavcinhmgsenPt rAoject
COMMERICAL IN CONFIDENCE PAGE 24
Each lake contains a percentage of “dead storage” that is unable to be accessed for consumptive use and
is referred to as the “residual pool”. The estimated size of the residual pools for each lake is summarised in
Table 6.
Regulation of the Lakes has increased the rate of sedimentation, particularly in key lake channels, such as
Menindee Creek (within the lake). This has reduced the ability of water to drain from the Lakes, particularly at
lower lake levels. Although some of this water may still be accessible through the existing gravity channels and
regulators, the volume and quality of water able to be accessed at low levels is generally only suitable for drought
emergency measures.
2.4 4 The Lo w er D ar l i ng R egul ate d R i ve r S yste m
The characteristics of overbank flow events in this region have been greatly altered through the development
of the Menindee Lakes as storage capacity for the Murray-Darling system, and the frequency of freshes has
significantly decreased. Furthermore, the frequency and volume of inundation events in the Great Darling
Anabranch have both reduced as a result of upstream regulation and extraction (MDBA 2012).
A number of ecological targets relating to flow regime for the Lower Darling Floodplain have been established
for sustaining native vegetation, supporting habitat of water birds and supporting ecosystem functions. Some
targets are limited by existing operational constraints – including regulator capacities, channel capacity,
inundation of private land creating access issues, operational policy and ensuring reliability of water supply to
Broken Hill and Menindee townships. The issues relating to Broken Hill are currently being addressed by
WaterNSW with the development of the replacement pipeline and supply being sourced from the Murray.
2.5 The G rea t D arli ng A na bra nch
The Great Darling Anabranch (Anabranch) is a high level effluent stream that receives flows whenever
flows in the Darling River exceed approximately 9,000ML/day. The Anabranch extends approximately 460 km
from its difluence with the Darling River, South of Menindee Lakes, to its confluence with the Murray River,
approximately 20 km downstream of Wentworth.
There are 11 large lakes and several lesser lakes and wetlands which are connected at various levels of
flow to the Anabranch, and these have varying natural flooding patterns. Under natural conditions, the
Anabranch flowed about every two years out of three in the upper reaches and less frequently downstream
(Irish 1992). About every two and a half years flows reached half way down the system (Withers 1994; GHD
2013)
MeMneinndienedLeaekeLsaNkeotsificWataiotenr- SAattavcinhmgsenPt rAoject
COMMERICAL IN CONFIDENCE PAGE 25
FIGURE 4: LOCATION MAP DARLING ANABRANCH (SOURCE EARTH TECH 2004)
Following construction of the Menindee Lakes scheme, an annual replenishment flow for stock and domestic
purposes of 50GL was provided if there were no natural high flows. The replenishments were provided from
an outlet at the southern end of Lake Cawndilla, which also supplies irrigation water to Lake Tandou.
MeMneinndienedLeaekeLsaNkeotsificWataiotenr- SAattavcinhmgsenPt rAoject
COMMERICAL IN CONFIDENCE PAGE 26
Over time, a large number of block banks were constructed to create pools of water that would extend
access to water after flows had ceased. The block banks have now been removed as part of the stock and
domestic project finalised in 2006.
The long-standing practice to limit regulated releases from Menindee Lakes to 9,000ML/day to the Lower Darling
River when possible is based on the commence-to-flow threshold for the natural offtake point to the
Anabranch, a flow greater than this rate would result in water passing into the Anabranch. Therefore,
increasing the release rate would not produce a proportional increase in flows to the Murray River. Due to the
commence-to-flow levels, only a small fraction of the increased water entering the anabranch would reach the
Lower Murray system until the anabranch has been wetted up.
MeMneinndienedLeaekeLsaNkeotsificWataiotenr- SAattavcinhmgsenPt rAoject
COMMERICAL IN CONFIDENCE PAGE 27
3 MENINDEE LAKES AND LOWER DARLING SYSTEM ECOLOGY
3.1 1 M eni n dee Lak es
3.1.1 Flora
The Menindee Lakes system contains a broad diversity of both terrestrial and aquatic habitats. The vegetation
/ habitat types present within the Menindee Lakes system at any given time are a product of current and antecedent
conditions, with water levels being the dominant influencing factor. Typically the Lakes are surrounded by a low
woodland, with the lake bed and littoral zone comprising emergent macrophytes or herb / grass lands dependent
on water levels. Several of the wetlands contain standing dead trees, which have drowned as a result of
prolonged inundation.
Five broad categories of inundation dependent vegetation/habitat types have been described in the Menindee
Lakes system (Biosis 2001):
1. Floodplain woodland - dominated by Black Box (Eucalyptus largiflorens) and / or River Red Gum (E.
camaldulensis) with or without Tangled Lignum (Dura florulenta) and variable understories.
2. Shrubland - chenopod shrubland dominated by Nitre Goosefoot (Chenopodium nitrariaceum) with scattered
Black Box.
3. Herb/grass/sedge - occurs on dried out lake beds with vegetation (native and introduced) colonizing
exposed sediments.
4. Wetlands - shallow freshwater marsh with emergent and floating vegetation, often with a canopy of
dead trees.
5. Unvegetated - open water with or without dead trees, exposed unvegetated sediments.
These were divided into 24 separate inundation dependent vegetation communities based on conditions
observed in 2014 (GHD 2015; Table 7).
MeMneinndienedLeaekeLsaNkeotsificWataiotenr- SAattavcinhmgsenPt rAoject
COMMERICAL IN CONFIDENCE PAGE 28
TABLE 7: VEGETATION COMMUNITIES IDENTIFIEDi 2
Group Vegetation Community Lake Lake
Pamamaroo Cawndilla
Lake
Menindee
Lake
Wetherell
Darling
Anabranch
Floodplain
woodland
Coolibah - Black Box Community
(EPBC Listed)
X
Floodplain Woodland (Black Box) X X X X X
Floodplain Woodland (Red Gum) X X X X X
Rarely Flooded Woodland
X
Woodland with Lignum
X
Shrubland Chenopod Shrubland
X X
Hop-bush / Senna / Turpentine Shrubland
Low Chenopod/Blue Bush Shrubland
Herb / grass
/ sedge Cane Grass Shrubland
X
Dry Lake-bed Herbfield/Grassland/Sedgeland
X X X X
Sandy Lake Fringe
X X X
Wetland Dead Trees with Persicaria and or Lignum
X
X
Lake Fringe herbland (Live & Dead Trees)
X X
Lignum Swamp
X X X
Shallow Freshwater Marsh X X X X
Shallow Freshwater Marsh with Dead trees
X
Unvegetated Dry Floodplain Woodland (Dead Trees)
X
Dry Lake Bed (Dead Trees)
X X X X
Introduced species
X
Open Water Channel
X X X X
Open Water Lake X X X X X
Open Water Lake (Dead Trees) X X X X
Recently Exposed Lake-bed
X X X
Inflow - Outflow channel
X
The Menindee Lakes and surrounding habitats are known to provide habitat for a large number of threatened
species listed under Commonwealth (EPBC Act) and State (NSW TSC Act) Legislation.
2 Taylor-Wood et al. 2001identiified vegetation in Pamamaroo in 2001, GHD provided detail for all other lakes in 2015.
MeMneinndienedLeaekeLsaNkeotsificWataiotenr- SAattavcinhmgsenPt rAoject
COMMERICAL IN CONFIDENCE PAGE 29
Some species are likely to be dependent on the regulated water regime of the Lakes, but other species are found
at higher elevations in areas unlikely to be dependent on flooding. URS (2005) reported seven listed flora
species that are likely to be wetland / inundation dependent known to occur at the Menindee Lakes (Table 7). In
addition, the EPBC listed endangered ecological community Coolibah
- Black Box Woodlands of the Darling Riverine Plains and the Brigalow Belt South Bioregions is known to occur in the
region and has been recorded around Lake Wetherell (GHD 2015).
TABLE 8: LISTED WETLAND FLORA SPECIES FROM THE MENINDEE LAKES3
Scientific Name Common Name IUCN EPBC TSC
Atriplex infequens
V V V
Brachyscome papillosa Mossgiel Daisy V V V
Haloragis exalata Square Raspwort
V V
Leptorhynchos waitzia Button Immortelle
E
Phyllanthus maderaspatensis
E
Solanum karsense Menindee Nightshade
V V
Swainsona adenophylla Violet Swainson-pea
E
3.1.2 Fauna
Riparian and wetland vegetation and habitats associated with the inundated areas of the Menindee Lakes
system provide important habitat for a broad range of terrestrial and aquatic fauna species, including
macroinvertebrates, amphibians, aquatic reptiles, aquatic mammal species, fish and waterbirds. Diverse
vegetation and habitat types are important for the various fauna groups, which may use different vegetation and
habitat types for different purposes and at different times.
A desktop review (GHD, 2015) of all available relevant previous studies, literature and a number of databases
indicate that a total of 348 native and 17 exotic vertebrate fauna species have been documented to occur
within the study area, and an additional four native species have been predicted to occur within the study area.
These include 11 native frog species, 249 native and six exotic species of bird, 27 native and eight exotic mammal
species and 54 native reptile species.
A total of 14 native and two introduced species of fish have been recorded or are predicted to occur in the
Menindee Lakes (URS 2005). This includes threatened species such as silver perch (Bidyanus bidyanus) and
Murray Cod (Maculochella peelii). The Lakes, however, are dominated by four native and two introduced species
(SKM 2002):
Australian Smelt (Retropinna semoni)
Bony Bream (Nematalosa erebi)
Western Carp Gudgeon (Hypseleotris klunzingeri)
Golden Perch (Macquaria ambigua)
3 (URS 2005) Listing Codes: E = endangered, V= vulnerable.
MeMneinndienedLeaekeLsaNkeotsificWataiotenr- SAattavcinhmgsenPt rAoject
COMMERICAL IN CONFIDENCE PAGE 30
Common Carp (Cyprinus carpio)
Eastern Gambusia (Gambusia holbrooki)
The site is especially important for waterbirds, with over 70 species recorded in the Lakes. There are 37 waterbirds
listed under the EPBC Act, which includes birds listed under international migratory bird agreements. Of these,
however, only nine species could be considered international migrants. Six species, the Brolga (Grus rubicunda),
the Freckled Duck (Stictonetta naevosa); Blue-Billed Duck (Oxyura australis); Double Banded Plover (Charadrius
bicinctus); Lesser Sand Plover (Charadrius mongolus) and the Australian Painted Snipe (Rostratula benghalensis) are
also listed under the NSW Threatened Species Conservation (TSC) Act (1995).
Large numbers of waterbirds are known to congregate on the Lakes with maximum counts exceeding 200,000.
The Lakes have been known to support more than one per cent of the world populations of the Freckled Duck
(Stictonetta naevosa), Grey Teal (Anas gracilis), Pink-eared Duck (Malacorhynchus membranaceus), Red-necked
Avocet (Recurvirostra novaehollandiae), Sharp- tailed Sandpiper (Calidris acuminata) and Red-capped Plover
(Charadrius ruficapillus) (Lau 2014). The site also supports waterbird breeding, particularly of colonial nesting
species (URS 2005).
3. 2 L o w er D ar l in g a nd G rea t Dar l i ng A n ab ranch
The Lower Darling River and Great Darling Anabranch (an ancestral channel of the Darling River) support
significant ecological values. The Anabranch has a complex geomorphology characterised by extensive
meanders, deep riverine pools, riverine benches, adjoining saline Lakes, lignum swamps, channel complexes,
backwaters, and billabongs. These wetlands are listed as a nationally important wetland complex in the Directory
of Important Wetlands in Australia.
The Lower Darling River supports extensive areas of riparian vegetation dominated by river red gum woodland on
the channel banks and the immediate floodplain, and large areas of black box on the outer floodplain. Lignum
and nitre goosefoot are common understorey species on the floodplain.
The Lower Darling catchment provides terrestrial, floodplain and aquatic habitat for a range of significant
plant and animal species. There are 46 threatened animal species and 14 threatened plant species within the
region that are protected under the NSW Threatened Species Conservation Act 1995 (Green et al. 2012).
MeMneinndienedLeaekeLsaNkeotsificWataiotenr- SAattavcinhmgsenPt rAoject
COMMERICAL IN CONFIDENCE PAGE 31
4 MENINDEE LAKES OPERATIONAL ARRANGEMENTS
4.1 1 O p e r ati ng O bj ec tive s
General operations of the Lakes are currently divided into two sets of objectives that are related to consumptive
water use and environmental benefits. The priority for operations is to maximise the potential supply of the
water resources for all users, ensure that the operations provide long term ecological sustainability, and to
maximise water quality within the Lakes and the Lower Darling River. To achieve these objectives, the Lakes have
generally been operated to:
a. minimise evaporation;
b. maximise storage volumes where they are most useful;
c. maximise water quality (in terms of salinity);
d. maximise ability to supply users; and
e. mitigate floods where possible.
Since the 1990s, the operating strategies have been modified to address a range of new objectives including:
a. providing ecological benefits, including fish and wildlife habitat;
b. improving water quality (in terms of mitigating blue-green algal bloom risks);
c. managing flood mitigation for the lower Darling River to provide environmental benefits;
d. controlling foreshore erosion; and
e. minimising erosion of cultural heritage sites.
4.2 2 C ur re nt O pe ra ti ng S tr a teg y
The general operating strategy in each season, where Menindee Lakes are holding water in excess of agreed
control thresholds, is for the Lakes to preferentially supply demands for water in the Murray River. This draws down
water levels in Menindee Lakes ahead of other key storages in the Murray system, in order to reduce annual
operating losses. The shared management mode of operation is managed by the MDBA on behalf of NSW and
other jurisdictions, under the MDB Agreement.
Under current operating and water supply arrangements, to ensure ongoing supply of water to Broken Hill and
surrounds and the Lower Darling River, supply of water to meet Murray demands is reduced to minimal levels when
the total storage at Menindee Lakes reduces 480 GL. Additionally, to ensure critical water supply needs are able
to be met during periods of low inflows, the current operating strategy also preferences water storage in Lakes
Wetherell and Pamamaroo over Lakes Menindee and Cawndilla. This also minimises evaporation loss.
The Lakes filling strategy is therefore as follows:
a. Fill Lake Wetherell to 59.8 m AHD (top of the old river channel)
b. Fill Lake Pamamaroo to full supply level (60.45 m AHD) (filling Lakes Pamamaroo and Wetherell
simultaneously above 59.8 m AHD
c. Fill Lake Menindee/Cawndilla to full supply level (59.94 m AHD)
d. Fill Lake Wetherell to full supply level (61.67 m AHD) and
e. If required fill Lake Pamamaroo (61.5 m AHD) and Lake Wetherell (62.3 m AHD) to full operating
level and then Lakes Menindee and Cawndilla (60.45 m AHD)
MeMneinndienedLeaekeLsaNkeotsificWataiotenr- SAattavcinhmgsenPt rAoject
COMMERICAL IN CONFIDENCE PAGE 32
In most instances, the procedures for releasing water from the Lakes are generally the reverse of this, with all
immediate consumptive demands being firstly met from Lake Menindee then Lake Cawndilla and Lake Wetherell
above 59.8 m AHD.
4.3 3 Dr ou gh t O perati o n s
In a continuing drought where the availability of water for licensed consumptive use on the Lower Darling River
is reduced, and where restrictions may become necessary, water is supplied according to the following order of
priority:
a. Town and village water supply and riparian entitlement for domestic supply;
b. Riparian and licensed entitlement for stock supply, some of which provides water a
considerable distance from the Lower Darling River;
c. Irrigation supply;
i. High security for permanent plantings (horticulture and vines); and
ii. General security for non-permanent plantings (pasture and cereal crops)
As water storage reduces due to evaporation, water salinity increases and in an extended drought it may be
unsuitable for some irrigation, and town water supply irrespective of availability of supply. During times of drought
the water remaining in the Lakes becomes an important refuge habitat that is necessary to sustain fish populations
and other aquatic and terrestrial fauna until the arrival of the next significant inflow.
4.4 4 F l o od O peratio n s
The severity of floods in the Menindee Lakes and the Lower Darling River is dependent on:
a. The volumes, peak and duration of floods upstream;
b. The prior storage volume in the Lakes;
c. The level of surcharge adopted during a flood event; and
d. The rate and duration of release from storage.
The primary objectives of flood operations is to ensure that the integrity of the structures is maintained; to maintain
security of future supply of entitlements by limiting pre-releases to levels below expected inflows, and where
possible to minimise damage to downstream property. Management of inflows requires consideration of various
factors including water quality and levee bank stability. While the scheme was not constructed to provide flood
mitigation, some flood mitigation capacity may be achieved by pre-releasing before the peak inflow reaches the
Lakes. Airspace in the Lakes up to the selected surcharge volume may then be used to store inflows and mitigate
the peak flow.
Pre-releasing is considered when projected release requirements would otherwise cause the storage to exceed
the capacity of the Lakes when filled to their maximum surcharge levels. Pre-releasing has the potential to reduce
downstream flood peaks, but may cause increased flood duration downstream. Flood releases are currently
managed where possible to mimic a more natural flow pattern.
MeMneinndienedLeaekeLsaNkeotsificWataiotenr- SAattavcinhmgsenPt rAoject
COMMERICAL IN CONFIDENCE PAGE 33
4.5 “ Harm on y O pe ra tion” w i th La k e V ic tor ia
Under the process of 'Harmony Operation' water can be transferred from Menindee Lakes to Lake Victoria
(located in the Lower Murray), if flows in the River Murray are insufficient to satisfy consumptive and
environmental demands for water. This process requires shared management of Menindee Lakes, coordinated
by the MDBA, to balance the advantages of operational flexibility and reduced evaporation against the increased
risk of loss of water as a result of spill from Lake Victoria, should conditions turn wet. These transfers are typically
made in late Spring or Summer.
Additional Dilution Flow (ADF) requirements also influence the operation of Menindee Lakes. The ADF procedure
aims to reduce river salinities further downstream, without impacting on water availability, and occurs when
the storage in Menindee Lakes exceeds agreed target storage volumes (generally between 1,300 to 1,650GL
depending on the month) and the combined storage in Hume and Dartmouth Reservoirs exceeds 2,000GL.
MeMneinndienedLeaekeLsaNkeotsificWataiotenr- SAattavcinhmgsenPt rAoject
COMMERICAL IN CONFIDENCE PAGE 34
5 OVERVIEW OF PROPOSED WORKS AND MEASURES
The initial modelling undertaken by the MDBA in 2013, based on works and measures proposed by NSW at that
time, indicated water savings of only 72GL for the Menindee project. The collective view of the jurisdictions at that
time was that more needed to be done to capture a greater share of the well documented system losses at
Menindee. In response, the NSW Government developed a proposal, which was submitted in August 2016,
this was further revised and expanded into a package of integrated works and measures. NSW submitted
this as an Interim Business Case and modelling advice in April 2017.
The package includes five categories of works and measures: -
1. Infrastructureworks
2. Structural Adjustment measures
3. Proposed Institutional Arrangements / Operating Rules
4. Concurrent Measures
5. Other Measures
Whilst individual elements each bring their own specific benefits and costs to the project, there are critical
dependencies between the elements of the package, which may in some cases render the project unviable
if one or more elements are not pursued as part of the package.
For example, the proposed structural adjustment package represents a potentially large cost to the project;
however, its inclusion is critical to decommissioning Lake Cawndilla and avoids much greater costs in providing
alternate supply infrastructure to service Webster Ltd (Tandou) operations.
Likewise, the removal of Lower Darling high security entitlement avoids the need to continue providing a
large operational reserve, enabling the reserve reduction from 275GL to around 80GL. Similarly, the Broken Hill
pipeline project, separately funded by NSW and currently in procurement phase, is critical to the Menindee
Project in that it removes high security demands on the Lakes, enabling them to be evacuated more rapidly
and in turn reducing evaporative losses.
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
FIGURE 5: PROPOSED LOCATION OF INFRASTRUCTURE WORKS IN SCOPE
COMMERICAL IN CONFIDENCE PAGE 35
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
COMMERICAL IN CONFIDENCE PAGE 36
6 PROPOSED INFRASTRUCTURE MEASURES
This section provides details of individual construction projects contemplated within the overall package of
works and measures, consistent with Table 1 and summarised again below: -
Proposed Infrastructure Works
Measure 1 Enlarged Menindee Regulator
Measure 2 Lake Menindee Channel
Measure 3 Morton-Boolka Regulator
Measure 4 Old Menindee Town Weir removal
Measure 5 Emu Lake Offtake regulator
Measure 6 Yartla Lake Offtake Regulator
Measure 7 Cawndilla Regulator
Measure 8 Anabranch Offtake Regulator
Measure 9 Anabranch E-flow Regulator & Road Bridge
Measure 10 Main weir fishway
Measure 11 183 Dam regulator, road bridge & fishway
Measure 12 Menindee Flood Protection
Measure 13 Lower Darling Constraints Mitigation works
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
COMMERICAL IN CONFIDENCE PAGE 37
6.1 Measure 1 – En larg e d Menin dee Re gu l a tor Outle t
6.1.1 Objectives
The purpose of the new Menindee Outlet Regulator, inlet and outlet channels is to increase outlet capacity to
enable faster drawdown of the level of Lake Menindee. This will: -
improve the efficiency of sequential storage drawdowns
enable operators to minimise residual surface area quickly
address existing issues with piping failures and downstream channel erosion, and
address a major operational constraint in relation to lower Murray Basin Plan flow targets.
6.1.2 Description
The proposal is to replace the existing limited capacity pipe outlet of approximately 4,000ML/day maximum
flow with a more substantial gated structure capable of passing flows of up to 14,000ML/day under low driving
head conditions. Scope includes a new 14,000ML/day structure (incl. outlet channel sections and downstream
creek widening) with 5 dual-leaf gates, 3m wide x 8.15m high. The new regulator will target the following outlet
objectives:
a. 14,000ML/day flow at upstream lake level of 57.5 m AHD
b. 2,000ML/day flow at upstream lake level of 56.0 m AHD.
To achieve this, it is proposed that the outlet regulator will have a sill level of RL 52.85 m AHD, to match the
crest of Weir 32 crest. The sill level would be able to be raised or lowered depending on the targeted functionality
and relationship with the Lake Menindee residual pool drainage channel. The structure will accommodate a
maximum surcharge level (MSL) in the lake of 60.45m AHD. Gate operation will be undertaken locally through a
portable actuator and power supply.
Overshot gates that can be lifted clear of the water will provide for downstream fish passage. Provision
has been made for installation of fish passage infrastructure in the costings, however due to the height of the
upstream storage level range (around 7.65m) the final design has not yet been determined.
The location has been selected to minimise impact to cultural heritage and dewatering requirements, as well as
minimising the footprint of the structure. The existing regulator will be required for continued operation
throughout construction, and will be retained to augment the new regulator capacity.
The Menindee Creek downstream of the proposed new regulator will be widened to convey the design flow.
Widening works will be constrained to the right (western bank) to minimise disturbance of the more sensitive left
bank areas. Rock erosion protection works in combination with limiting maximum channel velocities is required
to control channel scour.
Connecting channels upstream and downstream of the new regulator will be constructed and optimized to limit
scouring impacts, particularly in Menindee Creek. In addition, de-silting of the existing inlet channel may be
necessary to improve flow capacity.
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
FIGURE 6: MEASURE 1 - ENLARGED MENINDEE REGULATOR
COMMERICAL IN CONFIDENCE PAGE 38
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
6. 2 M ea sur e 2 – La k e M enind e e D rai na g e C h an nel
6.2.1 Objectives
The inclusion of these works improves the upstream head conditions for the Lake Menindee Outlet It will address
the issue of stored water pulling away from the outlet wall relatively early in the drawdown sequence which
currently reduces outlet capacity. It is expected that maximum flows can be extended by at least two weeks as
a result of these works, helping to capture the full benefits of related increases in outlet capacity.
These works will also enable operators to access the residual pool of water otherwise considered to be “dead
storage” in Lake Menindee – the Menindee outlet is on the high side of the bed of Lake Menindee with a
substantial residual pool of approximately 60GL.
6.2.2 Description
The proposed scope involves construction of a channel bed of varying width approximately 9km long and up to 9m
in depth.
Currently at lower lake levels, flow control recedes upstream away from the existing Menindee Outlet Regulator
and therefore the residual pool becomes isolated from the Regulator. A new internal lake drainage channel will
provide access to the full depth of the residual pool and at higher flow rates.
The new channel will make use of a portion of the existing creek system, however, avoids the most downstream
reach of the original creek length, within the lake, due to a high concentration of cultural heritage items.
The channel is also expected to potentially reduce fish mortality by allowing fish to move downstream to the Darling
River and escape the residual pool. To maximise residual pool drainage rates, the regulator gates would be
raised clear of the flow. The avoidance of high energy undershot gate flows is a key component for safe
downstream fish passage.
The location of the channel has aimed to minimise channel length, with satisfactory hydraulic performance,
as well as minimising the risk of scouring.
The aim of the project is to undertake the works to the drainage channel in the ‘dry’ due to the high additional
cost of constructing in the ‘wet’ (not currently included in base costs) and to address potential environmental
and heritage concerns.
COMMERICAL IN CONFIDENCE PAGE 39
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
FIGURE 8: MEASURE 2 - LAKE MENINDEE DRAINAGE CHANNEL (CONCEPT PLAN)
COMMERICAL IN CONFIDENCE PAGE 40
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
6. 3 M ea sur e 3 – M or ton- B o ol ka Re gul a tor
6.3.1 Objectives
Construction of a new regulator at Morton-Boolka allows Lake Menindee to be operated independently of
Lake Cawndilla and for the lake levels to be equalised as Darling River floods approach, so that floodwaters
can be captured within either or both Lakes.
The volume of water released into Cawndilla will be the amount required to periodically maintain environmental
values. These works are central to achieving the water savings for the Menindee Project and therefore
critical to project success.
6.3.2 Description
A new regulator capable passing flows of at least half the peak inflows from Copi Hollow is proposed –
notionally 14,000ML/day. The concept design includes adjacent abutment banks and 8 dual-leaf gates,
3m wide by 4.95m high.
Historical records of lake operations in conjunction with hydraulic modelling will be utilised to assess past
demands placed on Cawndilla Creek during transfer flows for the purpose of determining initial
limiting creek velocity values. Subsequent later geomorphology considerations would add further guidance
for the establishment of acceptable operating rules.
Rock protection of large sections of the creek is not considered practical, cost effective or permissible
given the location within Kinchega National Park and construction access requirements and the number
of identified cultural heritage sites.
The structure has a sill level closely matching the existing natural commence-to-flow level at the Morton-
Boolka site to maintain the natural channel control conditions and ability for lake equalisation.
Provision for fish passage in both directions is almost certain to be a requirement of the approvals
process and has been provided for in the cost estimates. From Menindee to Cawndilla downstream
passage is anticipated via overshot gates that can also be lifted clear of the water. During reverse f low
conditions from Cawndilla to Menindee downstream fish passage will be able to be achieved through an
open structure with gates fully raised.
COMMERICAL IN CONFIDENCE PAGE 41
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
FIGURE 9: MEASURE 3 - MORTON BOOLKA REGULATOR (SHOWN SOUTH TO TOP OF PLAN)
COMMERICAL IN CONFIDENCE PAGE 42
6. 4 M ea sure 4 – O l d M eni nde e To wn We i r re m o va l
6.4.1 Objectives
COMMERICAL IN CONFIDENCE PAGE 43
The objective of this measure is to remove the existing weir and allow operators to extend the duration of peak flows
emanating from Lake Menindee outlet by up to 1 week.
An additional benefit of removing the weir will be an improvement in fish passage in the Darling River.
6.4.2 Description
Menindee town weir on the Darling River serves no operational purpose. Town water supplies are being drawn
from Weir 32 and from a dedicated groundwater bore, following recent works by Water NSW. The existence of
this redundant fixed crest weir does however lift the height of the pool downstream of the Menindee Lake
outlet during low-mid Darling River flows, thereby reducing head differential and limiting flows through the Lake
Menindee outlet.
Menindee town weir is assumed to comprise a 2.44m high U/S steel sheet pile, D/S timber crib structure with
rockfill infill.
COMMERICAL IN CONFIDENCE PAGE 44
6. 5 Mea sure 5 &6 – Low er D ar l ing C ha nn el Ca p ac i ty ( Yar tl a & Em u L a k es )
6.5.1 Objectives
These works will allow increased flows of up to 14,000ML/day in the Darling River channel downstream of Menindee
by controlling water at key points of escape from the main channel, vis a vis Yartla Lake and Emu Lake offtakes.
The works will also enable public access to be maintained during managed high flow events.
Increased flows in the Lower Darling, coupled with reduced losses, will assist with Murray River environmental
watering requirements; maximise SDL offsets from this project, and help restore some seasonality to the flows in
the Lower Darling.
6.5.2 Description
Before regulation, the Lower Darling was subject to highly variable flow conditions (Green et al. 2012). Since the
completion of the Menindee Lakes storage scheme in the 1960s, flow in the Lower Darling has been highly
regulated and the majority of flows are captured in the 1,700GL storage. The seasonality of flows has also
changed, with the largest volumes of water now flowing throughout summer, rather than autumn or spring.
Winter flows are also less variable and bank full flows occur less frequently (Gippel & Blackham 2002).
MDBA modelling undertaken for the Basin Plan shows that, without development of storages and weirs, flows
in the Lower Darling would have played a key role in contributing to large overbank events in the lower River Murray.
Currently, higher flows down the Lower Darling primarily exceed the low commence-to-flow threshold for a few creeks
and anabranches, including the Great Darling Anabranch, Yartla Lake and Emu Lake.
Inundation modelling using CSIRO’s RiMFIM software has been used below Weir 32 to assess likely areas of
inundation, and indicates approximately 7,500 ha of additional inundation as flows increase from 9,000 to
14,000ML/day. The majority of the additional inundation occurs at two small Lakes – Yartla Lake and Emu Lake,
with some creeks inundated near the Talyawalka area.
The Constraints Management Strategy includes the Lower Darling River as one of seven priority areas of physical
flow constraints to be addressed to improve environmental outcomes under the Basin Plan. The principal
constraint to release of higher flows is the physical and operational issues at Menindee Lakes, which have
been addressed in this draft Business Case – Options Report for the purpose of achieving water savings.
Addressing constraints will increase the potential for the Lower Darling to contribute to higher flows in the lower River
Murray, delivering benefits to key environmental assets. The increased operating releases to the Darling River
below Menindee potentially allow for the Darling Anabranch to be provided with flows as well as increased
flows to be available to downstream environments.
There is not expected to be any significant impact on public infrastructure in addition to the levees near Menindee
town described in Measure 12.
COMMERICAL IN CONFIDENCE PAGE 45
The scope of works includes:
a regulator with 3 vertical lift gates, 3.5m wide x 1.5m high; and
a regulator with 1 vertical lift gate, 2.1m wide x 1.0m high; and
a road bridge over Charlie Stone Creek in the Talyawalka floodplain.
COMMERICAL IN CONFIDENCE PAGE 46
6. 6 M ea sur e 7 – C aw ndil l a Cr ee k Re gu l a tor
6.6.1 Objectives
Cawndilla Creek links Lake Menindee and Lake Cawndilla, and the area between the two lakes supports
important ecological and cultural heritage values. The proposed new operating regime for the Lakes will
substantially decrease inundation of areas downstream of the Morton-Boolka regulator, including Cawndilla Creek,
Lake Eurobilli and Lake Cawndilla.
Construction of a new regulator at the offtake to Cawndilla Creek will enable operators to isolate these areas when
Menindee is draining. Additionally, if necessary it will facilitate environmental flows to the higher value asse ts, using
held entitlement in between events which would otherwise fill the Menindee system (typically flow events greater
than 600GL/mth at Bourke).
6.6.2 Description
The need to consider the “wetted” ecology of Cawndilla and Menindee Lakes was identified by NSW National Parks
and Wildlife Service (NPWS) and within the report for Stages A1 and A2 on Environmental Water Needs and
Water Management Arrangements (GHD, Mar. 2015). The works are likely to provide offset and mitigation to
potential changes to the wetting and drying of Lake Cawndilla..
Scope of works includes a regulator (incl. adjacent levee/abutment, 6 dual-leaf gates) 3m wide by 4.61m high
near the entrance to Lake Cawndilla to allow upstream inundation of Morton-Boolka, Lake Eurobilli and Cawndilla
Creek for the benefit of vegetation communities in the area between Lake Menindee and Lake Cawndilla.
The site selection for this regulator is aimed at mitigating the impacts of lower Lake Cawndilla storage levels on River
Red Gum and Black Box communities along the fringes of Lake Cawndilla, Morton- Boolka, Lake Eurobilli and
Cawndilla Creek Figure 7 shows inundation mapping of Cawndilla Creek.
The structure is to be located on Cawndilla Creek and incorporate provisions to allow flow in either direction.
Reverse flow from Lake Cawndilla to Lake Menindee is needed to ensure that the residual storage level of Lake
Cawndilla is not raised when Lake Menindee is being drawn down. Fish passage will be facilitated through the gated
section of the regulator structure up to a maximum flow of 6,000ML/day.
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
FIGURE 7: MEASURE 7 - CAWNDILLA CREEK INUNDATION MAPPING
COMMERICAL IN CONFIDENCE PAGE 47
COMMERICAL IN CONFIDENCE PAGE 48
6. 7 M ea sur e 8, 9 & 11 – A n a br anch O ffta k e R egu lat ors, Da m 18 3 reg ula to r
6.7.1 Objectives
Existing Menindee releases to the Lower Darling are limited to 9,000ML/day to prevent excessive losses into
the Great Darling Anabranch and to other areas along the Lower Darling River. These works will enable
operators to exclude higher flows from entering the Anabranch system to take advantage of increased
Menindee discharge capacity. Natural high flows will not be excluded, and the regulator will also be opened for
environmental water and potentially transmission delivery to the Anabranch which can be piggybacked onto Murray
releases.
These works provide water savings, address the Constraints Management Strategy and facilitate more
efficient delivery of environmental account water to the Darling Anabranch and the nature reserve at Nearie
Lake.
6.7.2 Description
The Anabranch works are made up of three components:
Works at the existing Anabranch regulated offtake
o a regulator with 7 dual-leaf gates, 3.65m wide by 2.4m high.
Works at the Anabranch environmental offtake. (Offtake regulator to replace current Darling Anabranch
offtake)
o a regulator with 3 dual leaf gates, 2.05m wide by 3.5m high;
o a channel bed of width 6.5m and length approximately 800m; and
o a road bridge of 4m width, dual carriage approach and giveway bay.
Works at Dam 183
o a regulator with 4 dual leaf gates, 2.1m wide by 2.5m vertical height;
o a road bridge of 4m width single span; and
o a vertical slot fishway of height 2.24m
The proposed Darling Anabranch twin regulators will enable either the complete exclusion of higher Darling River
flows, or the diversion of a proportion of flows to the Anabranch during higher managed releases from Menindee
Lakes.
The upstream regulator design will allow for the exclusion of a higher Darling River is a gated sheet pile
construction with a height in the order of 1.5m tying into the top of bank levels. The structure will provide a nominal
waterway area equivalent to 100% of the natural channel waterway. The downstream regulator and associated
cutting will allow diversions into the Anabranch, when required for environmental needs, during high flows in the
Darling River. This will provide a replacement for the current diversion point into the Anabranch via Lake Cawndilla.
The twin regulator proposal has been supported to minimise engineering complexity, as the natural offtake sill
(the site of the upstream regulator), initially leads to a broad area of inundation that would significantly add to the
volume of water required to provide an environmental flow along the Anabranch.
COMMERICAL IN CONFIDENCE PAGE 49
The upstream structure is proposed to operate for the most part in the “fully open” default position, unless
environmental flows are released down the Darling River, in which case the structure can be “fully closed” to
contain flows within the Darling River.
The downstream Anabranch environmental regulator will be designed to minimise the disturbance foot print
during operation. The regulator would only need to be opened at those times when an environmental flow
would need to be delivered to the Anabranch, at all other times the regulator would remain closed.
Fish passage structures are not considered necessary since the structures would be normally fully open with
a waterway area, matching 100 per cent of the natural cross-section of the stream. The structure is to be
located on the choke point in the Anabranch offtake approximately 100 metres downstream of the existing
road bridge.
COMMERICAL IN CONFIDENCE PAGE 50
FIGURE 8: MEASURE 8 – APPROXIMATE LOCALITY OF ANABRANCH REGULATOR
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
FIGURE 9: MEASURE 8 – PROPOSED ANABRANCH OFFTAKE REGULATOR
COMMERICAL IN CONFIDENCE PAGE 51
6. 8 Mea su re 1 0 – Meni n de e Mai n We i r Fi sh Passa ge
6.8.1 Objectives
COMMERICAL IN CONFIDENCE PAGE 52
The objective of these works is to improve fish passage in the Darling River in anticipation of likely regulatory
approvals requirements.
6.8.2 Description
Section 218 of the NSW Fisheries Management Act requires fish passage to be provided in the construction
and/or augmentation of dams and weirs.
Specifically, the Minister may, by order in writing, require a person (other than a public authority) who constructs,
alters or modifies a dam, weir or reservoir on a waterway to carry out works “to enable fish to pass through or over
the dam, weir or reservoir”. The Minister may also, by order in writing, require a person responsible for the
management or control of a dam, weir or reservoir to carry out repairs to a fishway or fish by-pass.
In addition, a public authority that “proposes to construct, alter or modify a dam, weir or reservoir on a waterway”
must “notify the Minister of the proposal, and must, if the Minister so requests, include as part of the works for the
dam, weir or reservoir, or for its alteration or modification, a suitable fishway or fish by-pass”.
Whilst works on Menindee Main Weir are not proposed, almost certainly the requirement for fish passage at
this weir will be assessed as part of the Environmental approvals under the State Significant Projects process.
COMMERICAL IN CONFIDENCE PAGE 53
6. 9 Mea sure 1 2 – Fl ood P rotecti o n - Meni n de e residents
6.9.1 Objectives
The intention to pass regulated high flows past Menindee to achieve Lower-Darling flows of up to 14,000ML/day
will likely result in some localised flooding of Menindee residential properties. The objective with this component
of the package is to construct a levee of sufficient height and length to protect riparian residential properties from
these managed events.
6.9.2 Description
Flood protection for at least ten properties and access roads is proposed. The scope of works includes levees and
access road raisings for a design flood level at a flow of 25,900ML/day (moderate flood level). Figure 10 provides
an aerial view of the estimated inundation at 25,000ML/day.
A number of property boundary levees and raised access roads will be required to protect residents from
inundation impacts (below floor levels) due to potentially more frequent flooding under modified lake operation and
release conditions.
The level of flood protection is to be increased from the current minor flood level at about 17,000ML/day up to a
moderate flood level of at least 25,900ML/day. This will provide residents with at least the same or better flood
protection as existing compared to the level of protection proposed under modified lake operating conditions.
The proposed works are within the vicinity of the Menindee township, adjacent either side of the river.
COMMERICAL IN CONFIDENCE PAGE 54
FIGURE 10: MENINDEE TOWNSHIP INUNDATION MAP AT 25,000ML/DAY
Page 55
6. 10 M ea sure 1 3 – L o w er D ar l ing C onstra i nts M i ti ga ti on Wor k s
6.10.1 Objectives
Increased flows in the Lower Darling as a result of the enlarged Menindee regulator and flows up to 14,000ML/day
will have an impact on private diversion points for stock and domestic supplies along the river. The objective of this
component of the package is to undertake works which allow continued stock and domestic access and irrigation
access for impacted landholders under the proposes changed river operations.
During periods of low flow, it is anticipated the water will be pulsed down the river to minimise losses. This pulsing
may necessitate the provision of on-farm storage or access to ground water alternatives to maintain supply for
stock and domestic purposes.
6.10.2 Description
As a result of the changed operations a number of licence holder pumps and installations will be impacted
and need to be modified, replaced or relocated. The impact will be limited primarily to stock and domestic and some
irrigation pumps given the intended buyback of high security licences and structural adjustments.
TABLE 9: LICENCE NUMBERS BY CATEGORY IN LOWER DARLING
Standard^
Licences
Stock & Domestic 114
Regulated River (General Security) 84
Regulated River (High Security) 59
Local Water Utility 2
Supplementary Water 1
Total 260
Source: http://www.water.nsw.gov.au/water-licensing/registers ^Excludes zero allocation licences
It has been assumed that all stock and domestic installations will require further review and potential modification
along with all irrigation equipment related to remaining irrigation licences. In excess of 200 licences may be
impacted to some extent. It is expected that each licence may have more than one piece of infrastructure related
to a licence requiring attention.
As part of the Phase 4 design process, a full audit and survey of the infrastructure at each licence holder
location would be undertaken.
The scope of the work required at each location is yet to be determined but may include:
Pump relocation;
Fitment of floating pickups;
On-site storage or groundwater options; and
Pump replacement due to changed head conditions.
Page 56
Before works were commenced, an agreement would be required with each of the licence holders to confirm the
scope to modify the equipment and to ensure that no ongoing obligations are incurred to maintain any of the
equipment.
Page 57
7 PROPOSED STRUCTURAL ADJUSTMENT MEASURES
7.1 1 M ea sure 1 4 – Ac qui si tion of L o w er Dar li ng & We bster L td. (Ta nd ou) en ti tl e m en t s
7.1.1 Objectives
There are a number of entitlement holders of various categories in the Lower Darling Water Source who will
need to be considered in the changes to the management of the Lakes with the primary objective being to
remove High Security irrigation demand from the Darling downstream of Menindee.
This in turn will reduce NSW commitment to holding upstream water reserves in the system and therefore
maximise potential water savings from the project.
Reduced use of Lake Cawndilla impacts on the gravity supply frequency to Lake Tandou. The infrastructure
cost of providing alternate pumping and channel infrastructure to supply 80 GL annually to Lake Tandou is significant.
It is better value to facilitate a cessation of irrigation on the property.
Additionally, Lower Darling irrigation creates system commitments which when removed will enable quicker and
more extensive evacuation of the Lakes.
7.1.2 Description
The Lower Darling is the section of the Darling River between Menindee Lakes and the confluence of the Darling
with the River Murray at Wentworth in south-western New South Wales. The townships of Menindee, Broken Hill and
Pooncarie are all supplied with water from the Lower Darling system. There are also a number of private irrigators
located near Menindee town, and south of Menindee Lakes who extract water directly from the river.
The Lower Darling Water users; particularly the high security entitlement holders, have long expressed concerns
that releasing additional, larger flows from the Menindee Lakes storage system, and having shared control
(administered by the MDBA) extend to a lower storage volume, will negatively affect the reliability of their water
entitlement supplies.
It is proposed to assist water users’ transition from permanent plantings to annual cropping, and to provide
increased resilience to sustained periods of no or low flows in the Lower Darling river. A group of vineyard and
orchardists below Pooncarie, representing the majority of permanent plantings in the Lower Darling, have brought
forward a proposal to the NSW and Commonwealth Governments, which is currently under consideration.
Prior submissions assumed a reduction (but continuance) of demand consistent with Basin Plan recovery
targets.
The enhanced Menindee Project is predicated on reducing or removing high security licence obligations and
some targeted general security entitlements in the Lower Darling. This component of the package is therefore
fundamental to the success of the overall package.
Page 58
7.1.3 Current Licence Entitlements
According to the Lower Darling Water Sharing plan there are a total of 282 open licences covering 347GL of
entitlement in the Lower Darling, including 250GL of supplementary water and with a total of 86GL allocated against
high and general security licences.
Of the 7.7GL of high security entitlements, the State and Federal Governments currently hold 1.2GL. The further
high security entitlements of 6.5GL are covered by 59 high security licences but dominated by Websters Limited
(Tandou) at 2.5GL.
TABLE 10: LICENCES
Standard
Licences
Zero Value
Licences
Total
Licences Shares
Stock & Domestic 114 0 114 1.4 GL
Local Water Utility 2 0 2 10.1 GL
Regulated River (General Security) 84 10 94 78.3 GL
Regulated River (High Security) 59 10 69 7.7 GL
Supplementary Water 1 2 3 250.0 GL
Total 260 22 282 347.4 GL
TABLE 11: LICENCE ENTITLEMENTS (VOLUMES)
Websters
Limited
(Tandou)
Other Lower
Darling Water
Licences
WAMC /
Commonwealth
Total
Entitlement – High Security 2.5 GL 4.0 GL 1.2 GL 7.7 GL
Entitlement – General Security 19.4 GL 10.1 GL 48.8 GL 78.3 GL
Entitlement – Total 21.9 GL 14.1 GL 50.0 GL 86.0 GL
7.1.3.1 Small Licence Holders
Beyond Webster Ltd. (Tandou) and some larger
scale irrigators, there are a high proportion of
small licence entitlements held in the Lower
Darling (as identified in Figure 11). A number of
these have been inactive in regard to physical
use, but have been regularly traded.
Any change to the nature of entitlements in
this region will generate significant
interest from the licence holders.
3,000
2,500
2,000
1,500
1,000
500
0
1 4 7 10 131619222528 3134 3740 4346495255
FIGURE 11: LICENCE ENTITLEMENTS – HIGH SECURITY
LIC
ENC
E EN
TITL
EME
NT
(ML)
Page 59
8 PROPOSED INSTITUTIONAL ARRANGEMENTS / OPERATING RULES
8.1 1 Measure 1 5 - Men in de e Syste m Co ntro l Transfer & Stora g e D rawd own
8.1.1 Objectives
The removal of thresholds which determine “decision control” for Menindee releases provides MDBA with increased
flexibility, helping to increase drawdown rates, reduce evaporation, increase the overall regulated supply to the
Murray and harmonise operations with Lake Victoria. These measures enable the value of proposed infrastructure
works and therefore potential SDL offsets to be maximised.
8.1.2 Description
Current operating rules assume control triggers at 480GL (below which NSW resumes management of the Lakes)
and 640GL (above which MDBA assumes management of the Lakes). The intent of the thresholds has been to
ensure NSW retains control of the storage volumes to meet residual demands of high security water users’
dependent on the Lakes as the Lakes dry out.
Previous modelling of Menindee options assumed a continuance of (reduced) Broken Hill, Tandou and Lower
Darling demand, thereby constraining operating flexibility and NSW ability to handover control. Partial relaxation
of the thresholds was possible, to 275GL and 615GL. It was assumed the residual 275GL in dry years would be
held in Pamamaroo and Wetherell.
The current proposal effectively removes the thresholds altogether. To enable this, it is essential to remove all
TWS and high security irrigation demands from the Menindee system via the provision of an alternate Broken Hill
supply from the Murray and the Lower Darling/Tandou structural adjustment package.
However, in order to protect basic landholder rights in the Lower Darling, it is proposed that operators retain
approximately 80GL of water for riparian demands until the end of the year following evacuation of the other Lakes,
with this volume able to be held in the Lake Wetherell old channel. Sufficient water will be retained to supply any
remaining account volumes through ongoing resource assessment processes.
Earlier modelling of the impact of system control and drawdown changes, for model run 35, indicated nil to slightly
positive impact on the supply to Murray River entitlement holders (Turner, 2016). However, the latest changes
to the proposal have not yet been tested and there have also been concurrent changes to the model in so
far as the operating loss regression function, both of which will potentially alter the outcome. Whilst not expected
to have a material adverse consequence, this will need to be confirmed prior to the submission of a Phase 3
Business Case.
Page 60
8. 2 Mea sure 1 6 - B r ok en H il l E nti tl e m e n t
8.2.1 Objectives
With interrelated works underway to construct a pipeline supply from the Murray River for Broken Hill, agreement will
also be required in respect of shifting Broken Hill TWS entitlements. This component of the package will establish
and model the likely operating conditions attached to the new licence.
8.2.2 Description
Previous options and modelling assumed that Broken Hill TWS continued from the Darling via Menindee
with access to groundwater during times of surface water restriction / shortage. The current proposal assumes the
entire demand is shifted to the Murray River.
The model needs to remove Broken Hill demand from the Darling and create a new demand node connected
to the Murray near Sunraysia. The pipeline design capacity will be up to 37ML/day.
Page 61
8. 3 Mea sure 1 7 - Cawndil l a A dditi onal E -f lo w s
8.3.1 Objectives
Lake Cawndilla incorporates parts of Kinchega National Park and notwithstanding the impact of historical
works and operations, the lake is a culturally and environmentally significant area.
This project proposes the decommissioning of Cawndilla for the purposes of regulated water supplies, with future
filling only occurring during natural events that would otherwise fill the Lakes. This component of the package provides
the capacity to manage and protect Cawndilla’s cultural and environmental values by developing a regime of
managed, periodic inundation of the Lake using held entitlement.
8.3.2 Description of works
The proposal to reduce use of Lake Cawndilla as a water conservation storage may have impacts on the
environmental values that have developed around Lake Cawndilla during regulation. As described in Section 3,
fringing vegetation is now higher up the banks of the Lake, and is dependent on the Lake filling with more frequently
(and at higher levels) than under natural conditions.
The SDLAM environmental equivalence scoring framework does not directly recognise environmental values at
Menindee Lakes, and a separate assessment of the local environmental needs has been commenced to
support this business case. Further work will be necessary as part of the formal EIS process.
To support the existing environmental values of Lake Cawndilla, the proposed operational regime has been
adjusted to include periodic filling during natural high flow events for a short period of time. However, increasing
the provision of water to Lake Cawndilla reduces evaporative water savings, and there is a trade-off between local
environmental values and the benefits of evaporative savings for the environment more generally.
There is also the potential for changed operation at Lake Cawndilla to adversely impact on nationally and NSW
State listed threatened flora species including the Menindee Nightshade which is endemic to the Lakes.
Taking into account the water needs of the existing environmental values around Lake Cawndilla, a practical set
of triggers has been proposed for the periodic environmental filling and subsequent release from the Lake. This
trigger for a filling event at Lake Cawndilla is that it has been more than 36 months since the last successful filling
event, and more than 600GL has passed Wilcannia. Whilst these criteria have been designed to minimise failed
filling events given the highly variable nature of flows in the Darling, modelling indicates that the period between
events to fill Lake Cawndilla may be up to 10 years in some cases. This longest period between events also occurs
in the modelled without development scenario.
Reducing the dry period trigger from 36 months would increase the frequency of watering events and reduce the
likelihood of adverse impacts on the current ecological values, in particular the River Red- Gum and Black Box
woodlands that fringe the Lake. This would also enable more frequent releases
Page 62
from Lake Cawndilla to the Great Darling Anabranch. However, this operation would substantially reduce the
evaporation savings.
The request for modelling assumes the above arrangements for filling of Cawndilla when Darling River flows at Bourke
exceed 600GL per month and it has been three years since the previous fill event. The change with this current
proposal is to provide for watering between events using held environmental entitlement.
Page 63
8. 4 M ea sure 1 8 - R i ver M urr a y I mpr o ve d O p erati ons
8.4.1 Objectives
Although not a direct component of this Menindee package, changes to the MDBA Monthly Simulation
Model (MSM) to reflect contemporary operations and water sharing arrangements are essential in order to
capture the full extent of SDL supply benefits from the Menindee project.
8.4.2 Description
Model Run 35 included estimates of River Murray operating losses (OPLOSS) based on a regression equation
assuming practices and seasonal conditions pre-2000. Extrapolating forward to post- drought/post-Plan
conditions, it appears that the model is overestimating OPLOSS, which manifests as higher averaging storage
levels in Lake Victoria despite actual river operations data to the contrary. The capacity to re-regulate additional
water emanating from this Menindee project is intrinsically linked to the ability of operators to re-regulate flows in
Lake Victoria.
NSW DPI proposes that the OPLOSS regression equation be recalibrated in order to more accurately capture the
new operating paradigm and the full extent of benefits from SDL projects such as Menindee.
8. 5 M ea sure 1 9 - La k e W e ther ell (f l oo dpl ai n) d r ying cyc l e
8.5.1 Objectives
The objective of this change in operations of Lake Wetherell is to improve local environmental outcomes by
restoring some of the region’s natural hydrologic profile. The Wetherell floodplain environment has deteriorated
as a result of conditions being too wet over extended periods and the situation will further decline as a result of
this project unless measures are taken. This initiative will reinstate some drying cycles more typical of natural
ephemeral conditions.
8.5.2 Description
Previous modelling made no provision for Wetherell drying cycles, however it is an existing practice in operating
protocols to allow drawdown of water on the Wetherell floodplain back to the confines of the Old Channel. In light of
the issues raised during stakeholder engagement to date, the project team is anticipating that consent conditions
may require formalisation of the wetting and drying cycles for Lake Wetherell.
Page 64
9 CONCURRENT MEASURES
9.1 1 Mea sure 2 0 - B r ok en H il l T W S Alter na te S uppl y
9.1.1 Objectives
The objective of this concurrent (but separate) project is to eliminate the need to hold a substantial volume of
water (200-250GL) in the Menindee Lakes System in order to ensure a minimum of 18 months security of supply
for Broken Hill TWS.
9.1.2 Description
Critical to the management of Menindee Lakes in drought periods is the security of water supply for Broken Hill.
Development of an alternate supply to Broken Hill is a core component of the overall scheme, as an enabling
measure to allow changes to shared management arrangements.
The Darling River off-take at the Menindee Lakes Scheme is the main source of water for Essential Water’s
supply of Broken Hill. Essential Water uses an intake structure in the river at Menindee and a pump station to
pump water to Broken Hill. The licensed entitlement is 9.975GL per year. The water for Broken Hill has to be
pumped a height of 287 metres over a distance of 116 kilometres from its source at the Darling River to the
Stephens Creek reservoir. Essential Energy also has a licence for 25ML per year for raw water for Menindee.
The current decision to pump from Menindee is based on a broad range of factors, including, but not limitedto:
Water demand in Broken Hill;
The time of year (summer versus winter);
Efficiency gains and reduction of costs of pumping in off-peak times;
Overall efficient balance of supply between Broken Hill and Stephens Creek;
Maintenance of pumping stations and the pipeline;
Responding to supply outages and the need to catch-up supply in local storages;
Refreshing the pipeline to maintain water quality in the pipeline; and
Maintaining supply to pipeline customers, including those at Sunset Strip.
This matrix of issues impacts on the quantity of water required from Menindee and the rate at which the supply is
moved between Menindee and Stephens Creek and then on to Broken Hill. Eight in every ten years water
supply to Broken Hill is reliant on pumping from the Darling River. Essential Water’s service area is the most arid
in the state and experiences extreme conditions including low rainfall, long distances to transport water, ageing
infrastructure and high evaporation. The unique operational circumstances combined with dry conditions
cause salinity and other water quality problems in the raw water.
Page 65
The Scheme requires a substantial volume of water (200-250 GL) to be stored in the Menindee Lakes System, in
order to ensure a minimum of 18 months security of supply for Broken Hill. Recent drought periods have resulted
in extended low/no flow periods that have required the implementation of various contingency measures to
ensure ongoing supply for Broken Hill. Essential Water operates to minimise evaporation within their Water Supply
Scheme and therefore minimise pipeline transfers.
FIGURE 12: BROKEN HILL WATER SUPPLY - SCHEMATIC
Due to recent prolonged periods of drought, the Menindee Lakes System did not provide an adequate security of
supply for Broken Hill. In 2015, the volume of inflows to the Menindee Lakes system fell to new historic lows, and
emergency measures were required; including block banks and pumping to concentrate the remaining volume
of water in the most efficient parts of the Lakes system, the commissioning of the desalination plant at Broken
Hill, which is now in operation, and the investigation and drilling of two bore fields at Lake Menindee and Talyawalka.
In 2016 the NSW Government approved for the construction of a pipeline from the Murray River at Wentworth to
Broken Hill. WaterNSW is currently out to market for a Design, Build, Operate and Maintain project. The project
is set for completion in late 2018.
Page 66
10 OTHER MEASURES
10.1 1 M ea sure 2 1 - N orthern Ba si n Infl o w s
10.1.1 Objectives
The primary objective is to provide formal recognition of additional Menindee inflows related to Basin Plan
environmental recovery in the Northern portion of the Basin. Formally recognised additional inflow would be
made callable for environmental purposes in the Lower Murray and Lower Darling systems.
10.1.2 Description
Additional inflows may be the result of upstream environmental water recovery actions upstream, or deliberate
transfers from Northern systems to the Murray and Lower Darling and are at the discretion of future environmental
water managers.
It is expected that formally recognising the additional inflow and making it callable will improve environmental
outcomes by giving Murray environmental managers control over timing of delivery for the additional water.
10.2 2 M ea sure 2 2 - Lo w er D ar l ing Tem p orar y Trad e
10.2.1 Objectives
Allowing temporary trade of water allocation into the Lower Darling system when there are sufficient reserves to
supply water orders is consistent with the Basin Plan dealing rules and broader National Water Initiative
agreements relating to water trading.
Whilst water will only be suitable to support opportunistic cropping, these dealing rules will enable limited
economic returns to landholders who remain in the Lower Darling without undermining the structural adjustment
activities.
10.2.2 Description
Lower Darling water entitlement holders will be allowed to trade allocation down to the Murray at any time. This
enhances the value to holders by increasing the size of the market for their account water, and will also provide
increased management options for the holders of the TLM environmental entitlement.
Allowing upstream allocation trade is required by Basin Plan dealing rules and can only be restricted for physical
limitations. In this case, the relevant physical limit is the volume remaining in the Lakes available to meet the new
delivery during the current water year.
Page 67
11 KEY STAKEHOLDERS AND THE BROADER COMMUNITY
Community consultation surrounding Menindee over the last decade has experienced difficulties because of
the complexity of issues involved, including extreme and prolonged periods of drought, flooding, water sharing
conflicts, environmental and heritage issues and Broken Hill water security issues.
Extensive consultation took place during the development of the options analysis by the NSW Government
between 2006 and 2012. During this process, and in the early stages of business case investigations, key
stakeholders indicated concerns regarding:
a. entitlement holders are concerned about security of supply being impacted by the proposal,
particularly during dry periods;
b. Lower Darling irrigators:
i. suggest that flows of 14,000–17,000ML/day are “probably manageable”, but were
concerned that releasing such additional, larger flows from the Menindee Lakes storage
system will negatively affect the reliability of their water entitlement supplies, and
ii. are also concerned that higher flows may adversely affect the ecology of the Lower
Darling, and feel that additional work should be done to understand and protect this unique
environment;
iii. are concerned that rates of rise and fall do not consider the wetting and drying needs of
the banks of the river - causing increased tree fall.
c. landholders on the Great Darling Anabranch are concerned that installation of a Regulator on the
Anabranch offtake could lead to poorer ecological outcomes in the Anabranch, and fear that
rules could change after a regulator is installed, and it will be used to stop flows to the Anabranch
more frequently,
d. concern that the environment of the Lower Darling, the Lakes and the Darling Anabranch will be less
valued than downstream environments;
e. there is general concern about the environmental values that have developed around current
Lakes operations, and whether they will be protected;
f. there is a perception that evaporation occurring elsewhere in the basin is not being addressed,
and that Menindee Lakes is being unfairly targeted;
g. local Indigenous people and Traditional Owners are highly concerned that the environment
upon which their culture is based will be changed for the worse.
h. local Indigenous people are also concerned that irrevocable damage will occur to special areas and
their cultural heritage;
i. Menindee Town and the economy of the area will be permanently depressed; and
j. communities in Broken Hill and Menindee rely on the Lakes for amenity, and a number of
community groups have strongly objected to any diminution of water levels in the Lakes, which
are a key asset for the regional community.
Page 68
The reinvigoration of this project provides an opportunity to reengage with the key stakeholders to ensure issues
are brought to the table and appropriately addressed.
At the time of preparation of this draft Business Case, stakeholder and community consultation is currently
focused on commercial negotiations with directly affected parties, as a precursor to the development of a
structural adjustment package.
Appendix 1 and 2 detail the proposed Terms of Reference for the NSW Inter-Agency Working Group and Inter-
Jurisdictional Working Group (MDB). Consultation has already commenced informally and will be formally
commenced from July 2017. Broader community consultation is expected to commence in the last quarter of
2017 when commercial discussions are more advanced.
A communication strategy is required to engage and provide information to all key stakeholders and the local
community on:
1. Each major component of the proposed Menindee Lakes Water Savings Project;
2. The current water management policy at Menindee Lakes, and the relationship to wider Murray-
Darling Basin management; and
3. The structural and water management options being considered how the operation of the
Menindee Lakes would change if these were implemented.
Following advice and feedback local Aboriginal Elders at a pre-engagement meeting held in Menindee on 5 March
2014, it has been agreed that there need not be any specialised tools or methods of engagement be used
for Aboriginal people. The Elders advised that they would like a single point of contact for information coming from
DPI Water, that is the Menindee Local Aboriginal Land Council, and that they would provide advice directly to DPI
Water, or via the Regional Advisory Group.
TABLE 12: STAKEHOLDER MATRIX
Stakeholder Communication Objective Principal Communication / Engagement Strategy
Group 1: Stakeholders directly involved in commercial negotiations over buyback / structural adjustment.
Webster Ltd
(Tandou)
Commercial negotiations Direct communications
Lower Darling
Horticultural Group
Commercial negotiations and
consultation in relation to
ongoing service
Direct communications
Lower Darling
Landholders
Consultation in relation to
ongoing service
Direct communications
Group 2: Stakeholders directly involved in decision making processes during the project.
Commonwealth,
NSW & other
Jurisdictional
Governments
Seek key approvals
throughout project via
BOC/MinCo
Governance - representation on IJWG
Formal Presentations & reports – key project milestones
to IJWG.
Media Releases
Modelling liaison and review
Page 69
Stakeholder Communication Objective Principal Communication / Engagement Strategy
MDBA Technical liaisons in relation
to key agreements and
operating rules. Iterative
modelling changes.
Direct communications
NSW DPI Water Inform, provide direction and
approval
Governance meetings including facilitation of Project
Governance through IAWG.
Review key documents
NSW Premiers &
Cabinet
Inform and seek support IAWG
Formal Presentations, reports.
NSW Planning Direct approval IAWG – Meetings, presentations, reports
Planning Focus meeting
Environmental Assessment, AHIP.
NSW Office of
Environment &
Heritage, EPA
Inform and seek approvals IAWG - Governance meetings, presentations, modelling
progress and review
Formal consultation v/v SSP approvals
DPI Fisheries Inform and seek requirements
as part of approvals
IAWG - Governance meetings, presentations, modelling
progress and review
Formal consultation v/v SSP approvals
WaterNSW Modified Operational Plans,
licence changes, potential
project delivery
IAWG - General project communications, Iinstitutional
arrangements
Future O&M - working group / task force leading to
modified ops plan / strategy to achieve savings and
appropriate water management.
Potential project delivery – CEO to CEO
Group 3: Stakeholders who are important to the Project, will be engaged and will provide input which may influence
the project outcomes, but who may not necessarily influence the decision-making processes.
Aboriginal
Community,
Traditional Owners,
Elders Groups
Inform and engage
community, particularly during
cultural heritage assessment
in planning phase & cultural
heritage monitoring during
construction
Briefing to community groups
Representative(s) on Regional Consultative Committee.
Engagement during cultural heritage assessment &
monitoring.
Likely that an Aboriginal Heritage Impact Permit (AHIP) is
required. An AHIP has statutory engagement strategies.
Menindee Township Inform and engage the
community, particularly
regarding Menindee Flood
ProtectionWorks
Media Releases
Council newsletters
Regional Consultative Committee representation.
Broken Hill, Sunset
Strip & Silverton
Communities
Inform and engage
communities
Media Releases
Council newsletters
Representation via a regional consultative committee.
Local Tourist Industry
& Mining Industry
Inform and engage tourist
and mining industry
Representation via a regional consultative committee.
Broken Hill City
Council
An informed community Representation via a regional consultative committee.
Media Releases
Council briefings.
Water Users Inform and engage
communities
Representation via a regional consultative committee.
Media Releases
Page 70
Stakeholder Communication Objective Principal Communication / Engagement Strategy
NSW Irrigators Council
Group 4: Stakeholders who need to be kept informed of the Project.
Media An informed community Manage external media opportunities to promote
milestones
Manage external media enquiries regarding the project
Page 71
12 ENVIRONMENT AND HERITAGE
12.1 1 E n vi r o n m en t al Im p ac t s
12.1.1 Current State of Activities and Investigations
There have been several large-scale investigations into the Menindee Lakes system, including assessments
of potential impacts of proposed water savings measures. This includes:
The Ecologically Sustainable Development Project, 2000
An Environmental Impact Statement, 2005
The Menindee Water Savings Project, Ecological Status and Scoping, 2014
These investigations summarised existing information and augmented this with on ground field assessments
of water quality, fluvial geomorphology, vegetation, fish, waterbirds, amphibians and terrestrial fauna. They
assessed the likely impacts of the former works and measures proposed for the Menindee Lakes system
including effects to the Lower Darling River and Great Darling Anabranch.
There have been several environmental watering and water resource plans developed for the Lower Darling and
Great Darling Anabranch. The Water Sharing Plan for the New South Wales Murray and Lower Darling Regulated
Rivers Water Sources commenced on 1 July 2004 and applied until 30 June 2014. It was suspended during the
drought and a new Water Resource Plan is being developed by DPI Water for the NSW Murray and Lower
Darling, consistent with the Basin Plan and SDLs. This plan will include mechanisms to manage environmental
risks.
Darling Anabranch Adaptive Management and Monitoring Plan (MDFRC 2013) is a program to monitor the
ecological effects of changed hydrology in the Darling Anabranch. The program commenced in 2010 and is
expected to continue until 2020. It provides additional information on the ecology of the study area, particularly in
the Great Darling Anabranch.
Page 72
12.1.2 Activities to be completed
There has been considerable work completed in various iterations of the Menindee Lakes Water Savings
Project over the past two decades. The works and measures, and consequent operating regime, however,
have changed since previous investigations were completed. In order to ensure that any impact assessment builds
on previous work, rather than duplicating studies and investigations, a two-stage process is proposed:
1. A Scoping Study - which collates all existing information, confirms the proposed operating regime of
the new scheme configuration and completes a preliminary qualitative assessment of benefits and
impacts; and
2. An Environmental Impact Statement (EIS) - guided by the scoping study and the Director General’s
(Planning) requirements, which fulfils statutory obligations for environmental and heritage impact
assessment under NSW legislation.
The Menindee project falls under the State Significant Infrastructure category of development, which requires
approval from the Department of Planning and Infrastructure. The formal Environmental Impact Assessment
for the project will likely follow the process prescribed by NSW policy and legislation.
TABLE 13: LIKELY APPROVALS PROCESS FOR THE MENINDEE LAKES PROJECT
Activity Outcome Likely timing
DPI Water submits and
application to the
Director-General of
Planning and
Infrastructure
Director-General prepares site-specific environmental
assessment requirements (DGRs) which DPI Water must
address in an environmental impact statement (EIS)
28 days
DPI water prepares EIS EIS which contains:
a summary of the environmental impact statement,
a statement of the objectives of the development,
an analysis of any feasible alternatives to the
carrying out of the development in relation to its
objectives, and the consequences of not carrying it
out,
an analysis of the development, including:
o a full description of the development,
o a general description of the environment
likely to be affected by the development,
o a detailed description of those aspects of the
environment that are likely to be significantly
affected,
o the likely impact of the development on the
environment,
o a full description of mitigation measures
proposed,
o a list of any approvals that may be obtained
under any other Act – such as a licence to
6 - 12 months
Page 73
Activity Outcome Likely timing
pollute (environment protection licence)
from the Office of Environment and Heritage,
and
Reasons justifying the carrying out of the
development in the manner proposed.
Director General accepts
EIS
Public consultation period 30 days
Director General
produces a report
detailing issues that must
be addressed
DPI Water responds to the issues outlining any proposed
changes to the project 10 weeks
provided as
estimate in plan
Director General prepares
an environmental
assessment report for the
Minister
Report must be considered by the Minister in the decision-
making process.
6 months
provided as
estimate in plan Planning Minister makes
a decision
Approval, approval with modifications, not approval.
12.1.3 EIS Scoping Study – Statement of Requirements (Draft)
Appendix 4 provides a draft “statement of requirements” for the request for tender (RFT) for Stage 1 the EIS
process. It is intended that these will be finalised by DPI Water once the finer details of the project are decided.
It should be noted that the Director-General of the Department of Planning and Environment establishes the
requirements for the EIS and that these RFT will need to reflect those requirements.
12.2 2 C ultur al H er ita g e
12.2.1 Current State of Activities and I nvestigations
The Menindee area continues to be a focal point for Barkandji people because of the close proximity of the
important riverine landforms belonging to the Darling River, Menindee Lakes and the Talyawalka-Anabranch
system (Martin, 2001). Aboriginal people have occupied the Menindee region for at least 47,000 years (Balme
and Hope, 1990) consequently the lake system and surrounding floodplains contain many sites of significance
to Aboriginal Cultural Heritage.
The Lakes are an element of the Aboriginal cultural landscape and the proposed Menindee Lakes Water
Savings Project would impact on this landscape and potentially the associated Aboriginal cultural heritage
values.
A list of Aboriginal sites recorded on the Aboriginal Heritage Information Management System (AHIMS) that
are located within the four areas of interest as follows:
1. Lake Cawndilla - Lake Cawndilla, Cawndilla Creek, Morton-Boolka and Lake Eurobilli.
Page 74
2. Lake Menindee - Lake Menindee and Speculation Lake.
3. Lake Wetherell - The section between the Darling River and Lake Pamamaroo, including Tandure
Lake, Bijije Lake and Balaka Lake.
4. Darling Anabranch - The section between the southern edge of Lake Cawndilla and Lake Tandou.
Table 14 summarises the Registered Aboriginal Sites within the Study Area received from the NSW Office of
Environment and Heritage (OEH) on the 22nd September 2014. The sites represent point data (Aboriginal sites)
and do not represent site extents.
TABLE 14: REGISTERED ABORIGINAL SITES WITHIN THE STUDY AREA
Study Area Registered Aboriginal Sites
Lake Cawndilla 220
Lake Menindee 155
Lake Wetherell 10
Darling Anabranch 57
Total 442
A total of 442 registered Aboriginal sites were located within the four areas of interest comprising the study area.
Many of these Aboriginal sites may be impacted by the proposed Menindee Lakes Water Savings Project.
Registered Aboriginal sites within the study area include artefact scatters, burials, hearths, scarred trees, shell
middens, non-human bone and organic materials, potential archaeological deposits and combinations of up to
four individual features in one registered site. Aboriginal Ceremony and Dreaming sites are also located within
the study area. Each Aboriginal site is protected under Section 90 of the National Parks and Wildlife Act 1974.
Lake Cawndilla is the study area most affected by the proposed structural changes and encompasses the largest
number of registered Aboriginal sites. Preliminary investigations indicate that the majority of recorded sites are
likely to be located above the full supply level. This is based on the point data from the AHIMS which does not
represent the full extent of each site.
Potential impacts include:
A decrease in water levels may lead to further unearthing and destruction of archaeological material
through wind erosion.
Lower water levels may be beneficial to scarred trees.
A more rapid fill rate may lead to an increase in wave erosion, further damaging and
repositioning archaeological deposits located along the lake margin, lunettes and banks.
A marked decrease in total inundation may have a beneficial effect of Aboriginal cultural heritage
located within the shoreline by reducing shoreline erosion.
Page 75
A reoccurring increase in artificially raised water levels may create inundation and further impact
archaeological deposits through shoreline erosion from inundation.
Wave erosion, created by increasing and decreasing water levels will further damage
archaeological deposits around the lunettes, lake margins and banks.
The high density of burials and artefact scatters surrounding the lake would be particularly impacted
by an increase in water levels
TABLE 15: ISSUES SUMMARY
Issue Impact Potential Mitigation
Construction
activities will be in
the vicinity of
traditional sites
Future water
management will
increase the
frequency that the
Lakes are dry
The benefits arising
from estimated
water savings have
not been clearly
articulated
Unless construction is carefully
planned, items would be damaged
leading to a reduction in cultural
heritage
Increased frequency of drying
could lead to increased erosion
risks potentially exposing and
damaging cultural heritage items.
General skepticism of the benefits
of the project will reduce support
from the local community or lead
to active disapproval.
- Ensure that thorough site assessments are completed in
collaboration with the community to identify sites/items at
risk.
- If at-risk Aboriginal items are identified at proposed
construction sites, determine jointly with the community
how these items can be protected, including potential
removal and reinstatement.
Studies of potential increases in erosion to be completed and, if increases are identified, develop plans to protect heritage items.
- Clearly articulate the benefits to all stakeholders,
including the benefits to the local community. If it is found
that there are negative impacts, consider what form of
compensation is required.
- Implement a well-planned, culturally sensitive and
comprehensive communications strategy with the local
Aboriginal community to ensure there is a better
description of the project and develop a deeper
understanding of the activities and benefits.
- Implement a well-planned socio-economic analysis
(leading to mitigation strategies) giving due regard to the
potential effects to the local Aboriginal community.
Delay in receiving
information on
project activities
Inability to provide well informed
feedback to guide construction
activities while at the same time
protecting cultural heritage sites
and artefacts.
NSW DPI Water to include a representative of the local
Aboriginal community within a formal project consultation
committee that meets as required to ensure full disclosure
of plans, with access to independent dispute resolution, if
this is required.
Page 76
13 RISKSAND ISSUES
A risk assessment was carried out to identify the likelihood and severity of major risks present in the project. The
primary focus was largely on the risks associated with the development stages of the project and less on
specific construction risks.
As the project progresses it is expected that the risk register would be updated and evolve to identify any
significant risks associated with construction and the chosen construction processes to be employed.
13.1 1 Assess me n t Pr ocess
To meet the requirements of ISO 31000:2009 a 5 by 5 risk matrix and supporting consequence matrix were adapted
for use in the assessment of risk for the Menindee Water Savings project.
The preliminary analysis shows that there are no intolerable residual risks remaining after the application
of controls. This of course has the potential to change as the project unfolds and for this reason the Risk Matrix
and Heat Maps should remain live documents for continuous monitoring by the project working groups and project
steering committee.
13.1.1 Risk Register
Risks were identified and recorded in the risk register attached in Appendix 3. In total 60 risks were identified as
impacting on the project based on currently available information. It is expected that the risk register will be updated
and maintained throughout the life of the project.
Due to the early phase of the project, detailed construction risks were not included in the current register.
13.1.2 Risk Matrix
Once risks were identified, each risk was assessed for likelihood and consequence. The definitions used to
assess consequence follow in Table 17.
This combination of likelihood and consequence then provides the basis for risks to be classified as either
extreme, high, medium or low.
TABLE 16: RISK MATRIX
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
13.1.3 Consequence Matrix
Table 17 provides the consequence matrix adapted for use to clearly assess the consequence of currently identified risks.
TABLE 17: CONSEQUENCE MATRIX
Consequence Category
Negligible Minor Moderate Major Severe
Facto
r o
f C
on
sequ
en
ce
Stakeholders
No impact. Confident that all stakeholders and their
needs/views have been identified and issue under
active management. All groups that may influence the
project have also been identified and management
strategies have been developed.
Localised issues only, very small number of
stakeholders involved, negligible risk of contagion,
under active management, unlikely to be risks to client
or contractor reputation.
Localised issues with potential risk of contagion,
moderate and growing number of stakeholders
involved, under active management but some risks to
client or contractor reputation if not resolved.
Broader and growing distribution of concerns with high
risk of major breakout if not addressed, large number
of vocal and/or influential stakeholders involved,
management interventions not containing issue, large
risks to client or contractor reputation if not resolved.
Adverse short and long-term i mpact on contractor or
client reputation or i mage. Signi ficant government
intervention/involvement, protracted legal dispute,
Major loss of shareholder or community support.
Scope
Isolated issue, neglible impact on time, cost, quality.
Client’s requirements are generally understood. Client
communicates requirements clearly. The indicative
program is realistic.
More than an isolated issue with some minor impacts
on time, cost & quality. Client's requirements not well
communicated or understood. Some components of
program require clarification. In the context of a minor
number of RFI's submitted.
More frequent issue and moderate impact on time, cost
and quality. Client has not communicated requirements
clearly or contractors understanding is limited. The
indicative program may not be realistic. In the context of
moderate number of RFI's but able to be resolved.
Common issue and/or major impact on time, cost and
quality. Client has not communicated requirements
clearly or contractors understanding is poor. The
indicative program is not be realistic. Unable to be
resolved and requires escalation to Snr Leadership
Client’s requirements and/or contractor claims are
disputed. Agreement canot be reached on delivery of
the program . Objectives of the project at significant
risk. Significant number of outstanding RFI's with high
likelihood of contractual dispute.
Cost
Less than $50K $50K-$250K $250K-$1M $1M-$5M >$5M
Time
No impact. Delays less than 5% Delays of 5% to 10% Delays of 10% to 20% Delays >20%
Environment
- Ecosystems
Alteration or disturbance to ecosystem within natural
variability. Ecosystem interactions may have changed
but it is unlikely that there would be any detectable
change outside natural variation / occurrence.
Localised measurable changes to the ecosystem
components without a major change in function (no loss
of components or introduction of new species that
affects ecosystem function). Recovery (if relevant) in
less than 1 year.
Widespread measurable changes to the ecosystem
components without a major change in function (no loss
of components or introduction of new species that
affects ecosystem function). Recovery (if relevant) in 1
to 2 years.
Widespread measureable changes to the ecosystem
components with a major change in function. Recovery
(i.e. within historic natural variability) in 3 to 10 years.
Long term and possibly irreversible damage to one or
more ecosystem function. Recovery, if at all, greater
than 10 years.
- Habitat
Alteration or disturbance to habitat within natural
variability. Less than 1% of the area of habitat affected
or removed.
1 to 5% of the area of habitat affected in a major way or
removed.
5 to 30% of the area of habitat affected in a major way
or removed.
30 to 90% of the area of habitat affected in a major way
or removed.
Greater than 90% of the area of habitat affected in a
major way or removed.
- Species
Population size or behaviour may have changed but it
is unlikely that there would be any detectable change
outside natural variation / occurrence.
Detectable change to population size and / or
behaviour, with no detectable impact on population
viability (recruitment, breeding, recovery) or dynamics.
Detectable change to population size and / or
behaviour, with no impact on population viability
(recruitment, breeding, recovery) or dynamics.
Detectable change to population size and / or
behaviour, with an impact on population viability and or
dynamics.
Local extinctions are imminent / immediate or
population no longer viable.
Project Communications
Isolated issue. Otherwise good communication.
Information generally available and shared and if not
being resolved at operative level.
One of small number of communication issues between
client/contractor. Requiring escalation to steeri ng
committee level. No delays to project.
Consistent with a moderate number of communication
issues between client/contractor, escalation to steering
committee for resolution . Causing delays to project.
Client / contractor communications have broken done
at a steering committee level requiring escalation to
Snr leadership group to resolve, potentially requiring a
change in client and/or contractor personnel.
Major dispute in progress. Threatened and /or actual
litigation, arbitration and/or mediation in train. Change
in client and/or contractor personnel required if project
proceeds.
Quality
Isolated and minor non-conformance with quality
requirements otherwise clearly defined and being
delivered.
Some quality requirements are requiring further
clarification with some minor corrective actions
required.
Related to moderate number of quality issues, not
clearly defined by Client and/or a number of corrective
actions required.
Quality requirements not clearly defined by Client
and/or significant number of corrective actions and/or
works suspended.
Contract suspension actual or highly likely, major
dispute over quality standard being requested versus
delivered, threatened or actual litigation, arbitration,
mediation
Safety
• OHS: Incident - no lost time.
• Security: No notifiable or reportable incident.
• OHS: Injury - no lost time. First aid may be required.
• Security: Localised incident. No effect on operations.
• OHS: Injury - lost time.
Compensable injury.
• Security: Significant effect on operations.
• OHS: Serious injury resulting in hospitalisation / long
term illness or serious injury.
• Security: Signi ficant incident affecti ng multiple
locations.
• OHS: Fatality / permanent disability or ill health.
• Security: Extreme incident affecting organisation's
survival.
Hazard
Isolated and negligible WHS or public safety
consequence. Confident that all hazards have been
identified and a management strategy (SWMS) has
been established for each identified hazard. A Risk
Register has been established for the project, and all
Minor public or WHS safety consequence. All hazards
have been identified and a management strategy
(SWMS) has been established for key hazards. A Risk
Register has been established for the project, and all
risks are managed throughout the project.
Moderate WHs or public safety consequence. Some
hazards have been identified and a management
strategy (SWMS) has been established for some
hazards. A Risk Register has been established for the
project.
Major WHS or public safety consequence. All key
hazards have not been identified and a management
strategy (SWMS) has not been established for key
hazards. A Risk Register has been established for the
project, but is not re-visited throughout the project.
Severe safety consequence. Hazards have not been
identified. A Risk Register has not been established
for the project.
Sub-Contractors
Negligible issue and able to be dealt with in the normal
course of business. No time,cost or quality impacts, no
risk of SOPA claim,
Minor issue(s) requiring more effort but with little impact
on time, cost, quality. Little risk of SOPA claim.
Moderate issue(s) requiring considerable effort and
impacting on time, cost, quality. Reasonable risk of
SOPA claim. Some concerns over competency or
viability.
Major issue(s) with significant impact on resourcing,
time, cost, quality. Parts of proejct threatened. Major
risk of SOPA claim. Real competency or viability
issues.
Severe issue(s), whole project delivery threatened,
SOPA clai m and / or litigation, arbitration, mediation in
motion. Real competency or viability issues.
Page 77
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
13.1.4 Risk Analysis – Heat Maps
The two Heat Maps in Table 18 and 19 provide a before and after visual of the currently identified project risks.
It is to be expected that the inherent risks in Map 1 are predominantly Red, Amber and Yellow, there being little
benefit in mapping risks with minimal likelihood and consequence.
What is more important to the success of the project is that all residual risks are reduced to be no greater
than amber and that stakeholders have confidence in the proposed control measures to achieve these
revised ratings.
Page 78
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 79
13.2 R i sk a nd I ssue s – I nher e nt H ea t M a p ( b e f or e m i ti g a ti o n )
TABLE 18: INHERENT RISK HEAT MAP
BUDGET (10) COMMUNICATION (4) DEPENDENCY (4) ENVIRONMENT (16) GOVERNANCE, LEGAL &
REGULATORY (6) HERITAGE(4) OPERATIONS (2) POLITICAL (7) PROJECT MANAGEMENT (4) STAKEHOLDER (3)
Scope changes increase cost of
project significantly beyond the
contingecy allowance.
Perception of waste, due to
duplication of previous work already
carried out and representations
made.
EIS consent conditions recommend
works and/or operating rules that
reduce the overall water saving
benefits.
Reductions in bankful and overbank
flows decrease stream metabolism
and affect primary productivity in
the Lower Darling River and Great
Darling Anabranch
3rd parties raise injuction against
any or all of the project procesing.
Project is unable to meet all of the
aspirations of Native Title Owners /
local / wider aboriginal interests.
Potential for interested stakeholder
groups to require excessive works
and operations that impose costs on
the project.
The assumed impacts of the changes
to licence entitlements is broader
than expected and the planned
structural adjustment package is
insufficient to address all impacts.
Increased noise & traffic during
construction phases.
Menindee Township & Sunset Strip
concerned about future water
quality and supply.
Potential to undersize or oversize
design elements.
Key stakeholders are not clearly
identified and re-engaged at an early
enough stage in the process and
actively campaign against the
project.
Third party approval process have
significant potential to delay project
program.
Impacts to threatened species during
construction activities
Landowners are reluctant / unwilling
to permit easements on title for
levee construction.
Heritage concerns and located
artifacts providing potential to delay
or require major scope changes to
the project or program.
Modelled outcomes from the
inclusions of SDL package are
insufficient to justify the
expenditure.
Removal of Old Menindee Town
Weir is resisted by commu nity.
Risk of flooding or inundation during
construction.
Total compensation paid for
structural adjustments distorts
Water Licence markets and sets
unwanted precedents.
Potential to exceed construction
budget, if construction constraints
are not managed.
Project currently assumes sequential
program to reduce regret cost.
Pressure to bring program forward
will increase the likelihood of regret
costs and need to re-do some
activity if scope changes.
Perceptions that evaporation
occurring elsewhere in the basin is
not being addressed, and that
Menindee Lakes is being unfairly
targeted.
The benefits arising from estimated
SDL offsets, environmental benefits
and basin plan objectives have not
been clearly articulated to all
stakeholders.
Clash between stucture of State
Significant Project framework and
timelines vs stakeholder processes
Without parallel scheduling,
program has no capacity to slip due
to extreme weather conditions and
still meet 2024 deadline.
Operation changes create negative
impacts on Kinchega National Park
Operation changes impacts on
Wetting & Dying cycles of the
Menindee Lakes
Change of o wnership of properties in
Lower Darling occurs and new
owners do not h onour option for
licence buy-back & impairment of
works approvals.
Intra state institutional
arrangements pose constraints on
the project that threaten the
projects viability
Concerns that the Morton Boolka
regulator would attract vistors who
would collect artefacts in the area.
Increased frequency of drying could
lead to increased erosion risks
potentially exposing and damaging
cultural heritage items.
Property values in Menindee and
other related townships decrease
due loss of amenity and/or economic
activity from buy-back of Lower
Darling licences and changes to
operations.
Community feels previously raised
concerns/issues have been ignored.
Significant weather event delays
planning activities in project (geo,
survey)
Project works are completed during
dry spell in lakes and works can't be
adequately tested and
commissioned.
Landholders on the Anabranch are
concerned that installation of
regulators could lead to poorer
ecological & socio-economic
outcomes in the Anabranch, & fear
that the Anabranch regulators will
be used to stop flows to the
Anabranch more frequently,
Budget has been constructed in real
dollars. Final nominal project costing
will be significantly higher and is
largely subject to agreement on
timeline & inclusions.
Fish management act will trigger
requirement for fish passage
structures at each of the new works
and potentially the existing main
weir.
Interstate institutional arrangements
pose constraints on the project that
threaten the projects viability
Upstream communities try to link
otherwise unrelated issues to the
project and threaten its viability.
A significant body of work has
already been undertaken
(particularly environment). Budget
assumes that some benefit will be
derived in time/cost from use.
Budget will be negatively impacted if
prior body of work is not used or no
longer relevant.
Risks associated with wet
construction costs will be high.
Contractual risk sharing will need to
be considered carefully to avoid
having the full cost embedded in the
base price
Death of trees due to lack of
flooding.
Risk to Black Box-Coolabah as listed
Endangered Ecological Community.
Concerns that inter-jurisdictional
stakeholders aren't adequately
consulted and engaged during the
project leading to delays during final
approval processes.
Potential action by residents of
Sunset Strip & Copi Hollow based on
the perceived reduction in
availability of water for water sports
and other recreational activity.
Interest groups use project to
increase pressure to have Lake
system listed with Ramsar and
potentially delays project.
Websters Limited (Tandou) currently
have a zero value supplementary
licence available. Government have
previou sly purchased a
supplementary licence from Tandou.
Rapid rises during filling events may
drown emergent species & rapid rate
of draining may expose aquatic
species.
A12 :
RSK
020
R20 :
RS
K009
A12
: R
SK007
R20 :
RS
K006
A12 : R
SK
005
Y9 : R
SK004
Y9 :
RSK
003
A
12 : R
SK
002
A12 : R
SK
013
R15 :
RS
K012
R20 : R
SK
011
A12 : R
SK
010
R15 :
RS
K019
A12 : R
SK
018
R20
: R
SK
017
R25 : R
SK
015
A12 :
RSK
027
A12 :
RSK
025
R1
5 :
RS
K02
4
R15 :
RS
K023
R20 :
RS
K022
Y9 : R
SK021
Y9 :
RSK
016
A
12 : R
SK
014
A12 :
RSK
068
R16 :
RS
K050
R16 :
RS
K047
A12 : R
SK
046
Y9 :
RSK
045
R
15 : R
SK
008
Y9 : R
SK042
Y9 : R
SK041
A12 : R
SK
040
R16 : R
SK
039
R15 : R
SK
051
Y9 :
RSK
048
A12 :
RSK
061
R20
: R
SK
059
A
12 :
RSK
058
A12 : R
SK
057
R15 :
RS
K053
Y9 :
RSK
052
R
15 : R
SK
001
Y9 : R
SK065
Y9 : R
SK064
A12 : R
SK
063
Y9 :
RSK
062
R16 :
RS
K067
R16 : R
SK
066
A12 : R
SK
049
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 80
Risk and Issues – Inherent Heat Map (before mitigation) cont….
BUDGET (10) COMMUNICATION (4) DEPENDENCY (4) ENVIRONMENT (16)
GOVERNANCE, LEGAL &
REGULATORY (6) HERITAGE(4) OPERATIONS (2) POLITICAL (7) PROJECT MANAGEMENT (4) STAKEHOLDER (3)
Buy back is rejected by Licence
Holders and Government required to
use alternate measures for removing
high security entitlements from
Lower Darling.
Impacts to threatened species due to
altered hydrology.
No certainty for funding for ongoing
O&M costs.
Impact on recruitment success from
waterbird breeding and frog
breeding.
Changes to water levels impact
feeding and roosting of waterbirds
(including international migatory
species)
Elevated water levels in Menindee
Lake adjacent to the empty Lake
Cawndilla leading to salinization
nearby (including within Lake
Cawndilla),
Potential for sediment to be
generated in channels
Impact of clearing operations on
threatened ecological species or
endangered ecological communities
Concern that the environment of the
Lower Darling, the Lakes and the
Anabranch will be less valued than
downstream environments;
EIS identifies endangered fauna/flora
and require acquisition of significant
off-sets. Location and agreement of
offsets have the potential to delay
project and increase costs.
A1
2 : R
SK
069
R15 : R
SK
055
R16 :
RSK
037
Y9 :
RSK
036
A12 :
RS
K035
Y9
: R
SK0
34
Y9 :
RSK
033
R16 : R
SK
030
A12
: R
SK
029
A12 : R
SK
028
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 81
RS
13.3 R i sk a nd I ssue s – R e si du a l H e a t M a p ( a f te r m i ti g a ti o n )
TABLE 19: RESIDUAL RISK HEATMAP
BUDGET (10) COMMUNICATION (4) DEPENDENCY (4) ENVIRONMENT (16) GOVERNANCE, LEGAL &
REGULATORY (6)
HERITAGE (4) OPERATIONS (2) POLITICAL (7) PROJECT MANAGEMENT (4) STAKEHOLDER (3)
Scope changes increase cost of
project significantly beyond the
contingecy allowance.
Perception of waste, due to
duplication of previous work already
carried out and representations
made.
EIS consent conditions recommend
works and/or operating rules that
reduce the overall water saving
benefits.
Reductions in bankful and overbank
flows decrease stream metabolism
and affect primary productivity in
the Lower Darling River and Great
Darling Anabranch
3rd parties raise injuction against
any or all of the project procesing.
Project is unable to meet all of the
aspirations of Native Title Owners /
local / wider aboriginal interests.
Potential for interested stakeholder
groups to require excessive works
and operations that impose costs on
the project.
The assumed impacts of the changes
to licence entitlements is broader
than expected and the planned
structural adjustment package is
insufficient to address all impacts.
Increased noise & traffic during
constru ction phases.
Menindee Township & Sunset Strip
concerned about future water
quality and supply.
Potential to undersize or oversize
design elements.
Key stakeholders are not clearly
identified and re-engaged at an early
enough stage in the process and
actively campaign against the
project.
Third party approval process have
significant potential to delay project
program.
Impacts to threatened species during
construction activities
Landowners are reluctant / unwilling
to permit easements on title for
levee construction.
Heritage concerns and located
artifacts providing potential to delay
or require major scope changes to
the project or program.
Modelled outcomes from the
inclusions of SDL package are
insufficient to justify the
expenditure.
Removal of Old Menindee Town
Weir is resisted by community.
Risk of flooding or inundation during
constru ction.
Total compensation paid for
structural adjustments distorts
Water Licence markets and sets
unwanted precedents.
Potential to exceed construction
budget, if construction constraints
are not managed.
Project currently assumes sequential
program to reduce regret cost.
Pressure to bring program forward
will increase the likelihood of regret
costs and need to re-do some
activity if scope changes.
Perceptions that evaporation
occurring elsewhere in the basin is
not being addressed, and that
Menindee Lakes is being unfairly
targeted.
The benefits arising from estimated
SDL offsets, environmental benefits
and basin plan objectives have not
been clearly articulated to all
stakeholders.
Clash between stucture of State
Significant Project framework and
timelines vs stakeholder processes
Without parallel scheduling,
program has no capacity to slip due
to extreme weather conditions and
still meet 2024 deadline.
Operation changes create negative
impacts on Kinchega National Park
Operation changes impacts on
Wetting & Dying cycles of the
Menindee Lakes
Change of ownership of properties in
Lower Darling occurs and new
owners do not honour option for
licence buy-back & impairment of
works approvals.
Intra state institutional
arrangements pose constraints on
the project that threaten the
projects viability
Concerns that the Morton Boolka
regulator would attract vistors who
would collect artefacts in the area.
Increased frequency of drying could
lead to increased erosion risks
potentially exposing and damaging
cultural heritage items.
Property values in Menindee and
other related townships decrease due
loss of amenity and/or economic
activity from buy-back of Lower
Darling licences and changes to
operations.
Community feels previously raised
concerns/issues have been ignored.
Significant weather event delays
planning activities in project (geo,
survey)
Project works are completed during
dry spell in lakes and works can't be
adequately tested and
commissioned.
Landholders on the Anabranch are
concerned that installation of
regulators could lead to poorer
ecological & socio-economic
outcomes in the Anabranch, & fear
that the Anabranch regulators will
be used to stop flows to the
Anabranch more frequently,
Budget has been constructed in real
dollars. Final nominal project costing
will be significantly higher and is
largely subject to agreement on
timeline & inclusions.
Fish management act will trigger
requirement for fish passage
structures at each of the new works
and potentially the existing main
weir.
Interstate institutional arrangements
pose constraints on the project that
threaten the projects viability
Upstream communities try to link
otherwise unrelated issues to the
project and threaten its viability.
A significant body of work has
already been undertaken
(particularly environment). Budget
assumes that some benefit will be
derived in time/cost from u se.
Budget will be negatively impacted if
prior body of work is not used or no
longer relevant.
Risks associated with wet
construction costs will be high.
Contractual risk sharing will need to
be considered carefully to avoid
having the full cost embedded in the
base price
Death of trees due to lack of
flooding.
Risk to Black Box-Coolabah as listed
Endangered Ecological Community.
Concerns that inter-jurisdictional
stakeholders aren't adequately
consulted and engaged during the
project leading to delays during final
approval processes.
Potential action by residents of
Sunset Strip & Copi Hollow based on
the perceived reduction in
availability of water for water sports
and other recreational activity.
Interest groups use project to
increase pressure to have Lake
system listed with Ramsar and
potentially delays project.
Websters Limited (Tandou) currently
have a zero value supplementary
licence available. Government have
previously purchased a
supplementary licence from Tandou.
Y9
: R
SK009
Y6 :
RSK
007
G4 : R
SK
006
A12 :
RS
K005
Y9 :
RSK
004
Y9 :
RSK
003
Y6 :
RSK
002
Y9 :
RSK
013
A12
: R
SK
012
Y9 :
RSK
011
Y9 :
RSK
010
A12 :
RS
K019
G4 :
RS
K018
Y9
: R
SK0
17
A12 : R
SK
015
Y6 :
RSK
027
Y6 :
RSK
025
Y6 :
RSK
024
G4 : R
SK
023
A
12 :
RS
K022
G6 :
RS
K021
G2 :
RS
K016
Y9 :
RSK
014
Y9 :
RSK
068
Y9 :
RSK
050
A12 :
RS
K047
G4 :
RS
K046
G4 :
RS
K045
Y6 :
RSK
008
Y9 :
RSK
042
Y6 :
RSK
041
Y9
: R
SK0
40
Y9 :
RSK
039
A12 :
RS
K051
Y6 :
RSK
048
Y9 :
RSK
061
Y9 :
RSK
059
G6 : R
SK
058
Y9 :
RSK
057
A12
: R
SK
053
Y9
: R
SK0
52
Y9 :
RSK
001
Y9 :
RSK
065
Y9 :
RSK
064
Y9
: R
SK0
63
Y9 :
RSK
062
Y9A
:1R2
SK: 0R
S6K7
066
Y9 :
RSK
049
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
R s.
a
p
i
d
r
i
s
e
s
d
u
r
i
n
g
f
i
l
l
i
n
g
e
v
e
n
t
s
m
a
y
d
r
o
w
n
e
m
e
r
g
e
n
t
s
p
e
c
i
e
s
&
r
a
p
i
d
r
a
t
e
o
f
d
r
a
i
n
i
n
g
m
a
y
e
x
p
o
s
e
a
q
u
a
t
i
c
s
p
e
c i
e Page 82
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Risk and Issues – Residual Heat Map (after mitigation) cont….
BUDGET (10) COMMUNICATION (4) DEPENDENCY (4) ENVIRONMENT (16) GOVERNANCE, LEGAL &
REGULATORY (6) HERITAGE(4) OPERATIONS (2) POLITICAL (7) PROJECT MANAGEMENT (4) STAKEHOLDER (3)
Buy back is rejected by Licence
Holders and Government required to
use alternate measures for removing
high security entitlements from
Lower Darling.
Impacts to threatened species due to
altered hydrology.
No certainty for funding for ongoing
O&M costs.
Impact on recruitment success from
waterbird breeding and frog
breeding.
Changes to water levels impact
feeding and roosting of waterbirds
(including international migatory
species)
Elevated water levels in Menindee
Lake adjacent to the empty Lake
Cawndilla leading to salinization
nearby (including within Lake
Cawndilla),
Potential for sediment to be
generated in channels
Impact of clearing operations on
threatened ecological species or
endangered ecological communities
Concern that the environment of the
Lower Darling, the Lakes and the
Anabranch will be less valued than
downstream environments;
EIS identifies endangered fauna/flora
and require acquisition of significant
off-sets. Location and agreement of
offsets have the potential to delay
project and increase costs.
Page 83
G4
: RS
K06
9
A12 : R
SK
055
Y9 :
RSK
037
Y9 :
RSK
036
Y9 :
RSK
035
Y9 :
RSK
034
Y9 :
RSK
033
Y9 :
RSK
030
Y6 :
RSK
029
Y6 :
RSK
028
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 83
14 PROJECT COSTS
The overall Menindee Water Savings Project is effectively a construct of multiple measures as sub- projects.
Given the nature of the sub-projects and the interdependencies between each, the cost of the projects must be
considered as a single project and have been costed on that basis. Removal or alterations to some of the
measures within the project will require subsequent changes to other elements of the project and may result
in a material changes to the overall project cost estimate.
In total, the cost of the project (excluding structural adjustments) is currently estimated to be $151.8m and it is
constructed with the main components being direct infrastructure costs, non-construction project costs &
contingencies.
FIGURE 13: PROJECT COST BREAKDOWN
14.1 1 I nf ra structure Costs
A significant amount of work has been carried out by NSW Public Works to provide concept designs for the
structures proposed and associated non-construction costs.
The detailed costings for the Total Prime Costs (PC) of each of the measures is included in Appendix
1. The estimates have been broken down into the following main components for each measure:
Prime Cost Items – Estimated quantities, construction rates or construction item costs that would be
submitted by a contractor to construct the works now, including the contractor’s direct (labour,
equipment, materials, etc.) and indirect (overheads, insurance, profit margin, etc.) costs.
Preliminaries, Diversion and Water Management - includes establishment, disestablishment, the
contractor’s management plans and the contractor’s costs in diversion/coffer dam systems and
dewatering systems, landscaping and site rehabilitation,
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 84
haul road rehabilitation, contractor’s traffic and safety management, plus O & M Manuals and
Commissioning.
Total Prime Cost – PC - This is the total estimated construction cost by the contractor for the works
as developed at this stage and includes Prime Cost Items and Preliminaries, Diversion and Water
Management.
Table 20 summarises the expected Total Prime Cost for each of the measures included in the
Menindee Water Savings project:
TABLE 20: INFRASTRUCTURE COSTS (TOTAL PRIME COSTS)
Overall the estimates are considered to be at a reasonable feasibility level, however current constraints include
a lack of geotechnical investigation, associated final engineering design assessments and changes required
due to EIS approval constraints.
14.2 2 N on-C o nstructio n Pr oject C ost s
In addition to the direct infrastructure costs there are a number of non-construction intangibles that cut across
the project. The inclusions provided in each category are as follows:
Non-Construction Intangibles – NCI - These are the estimated cost required outside of the contractor’s
construction costs and include Geotechnical Investigations, Site Surveys, Concept and Detailed
Design, Environmental Studies, Social and Community Studies, Contract Administration, Project
Management and Client Internal Costs.
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 85
The following table provides a summary of the allowances made in each of the categories within non- construction
project costs.
TABLE 21: NON-CONSTRUCTION PROJECT COSTS
14.2.1 Surveys / Easements
Allowance provided
Survey
Extensive surveys are required for the measures proposed.
The surveys are scheduled to be undertaken early in the project and are proposed to occur in parallel with the
EIS assessment. This has been recommended to shorten the overall length of the project delivery time frame.
A risk with this approach is the potential to have to redo some survey work due to changes required by the final
findings of the EIS approvals and thereby incur regret costs from the accelerated plan.
The alternate approach is to delay most survey and geo-technical works until after the final EIS approvals
are granted. This would add between 6 -12 months to the overall length of the project.
In addition to land surveys, a bathymetric survey has been recommended to confirm the lake bed profiles and
lake volumes and to provide accurate data to model the water savings benefits on.
Easements
To facilitate some of the works and in particular the Menindee flood protection works, it is anticipated that a
number of easements will be required to be negotiated with landholders and registered on title.
Allowances have been provided for the cost of negotiating, acquiring and registering of these
easements.
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 86
14.2.2 Geo-tech
Allowance provided
As per surveys, it is anticipated that geo-technical assessments will take place early in the project and are also
proposed to occur in parallel with the EIS assessment. Consistent with the approach to survey work, this has been
recommended to shorten the overall length of the project delivery time frame.
The risk with this approach as per the survey work is the potential to have to redo some geo-tech work due
to changes required by the final findings of the EIS approvals and incur some regret costs.
14.2.3 EIS (EIS/ AHIP)
Allowance provided
The project plan provides for a 2 stage EIS process. This process has been recommended to reduce the overall
cost for EIS activity and potentially provide additional time savings over a greenfield approach to developing
the EIS.
14.2.3.1 Stage 1 – EIS Scoping Study
The first stage is proposed to provide a scoping study.
The intent of this stage is to review the large body of work that has already been undertaken for environmental
and heritage purposes in the Menindee region and to instruct the stage 2 consultant to use this body of work.
The expectation is this will reduce the likelihood of reproducing studies already in existence thereby reducing both
the time and cost to deliver the overall EIS/AHIP process.
14.2.3.2 Stage 2 – Formal EIS Process
Stage 2 will be the formal EIS/AHIP processes. It has been assumed that the process will be abridged as a result
of the Stage 1 scoping study and the reduction in the workload due to the earlier identification and
utilisation of existing information and studies.
14.2.4 Design & Documentation
Allowance provided
The allowance for design and documentation provides for 4 phases of work:
Completion of basis of design;
Cost estimation for the designs proposed;
Detailed engineering design;
Final documentation of structures as built.
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 87
14.2.5 Probity / Legal / Professional Fees
Allowance provided
Probity / Legal / Professional Fees covers a range of activities including but not limited to:
Professional advice and drafting associated with changes required to legislation, works
approvals, water licences, MDBA agreements etc.;
Development of construction contracts;
Development of significant consultancy agreements (ie EIS);
Agreements associated with land-holder works for mitigation measure;
Agreements for easements associated with flood protection levies;
Probity processes including probity officer.
14.2.6 Project Management
Allowance provide
Client oversight of the project and the provision of project assurance services includes the following
components:
'Owners Engineer' to provide quality assurance services during Planning & Approvals and
Executions phases of the project.
Client project team(s) to manage stakeholder involvement, environmental, technical and
operational oversight, commercial mgt.
An estimate of project resourcing (full time equivalent) over the life of the project is outlined in Section 15.2.1
14.2.7 Client Costs & Business Case Development
Allowance provided
An allowance has been provided to fund necessary external professional services to assist in developing the
final business case as well as a contribution towards funding necessary additional resources within the
department
Given the length of the project at over 7 years and removing business case development costs, it is estimated
that the allowance amounts to approx. 1 to 1.5 FTE’s for the life of the project.
14.3 3 Co ntin gencies
Allowance provided .
Contingencies are reflective of the considered robustness of the engineering and other assessments at the
current phase of the project intended to cover all unknown risks that may occur to successfully complete the works.
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 88
An overall 30% contingency factor of Prime Costs has been used in this phase of the business case, which
compares to overall 25% and 15% contingency margins usually applied by NSW Public Works for the full concept
and detailed design phase cost estimates respectively.
A key recommendation is to conduct a contingency assessment as the project develops in detailed design to
provide cost estimate figures and corresponding likely probabilities/confidence levels of not being exceeded (Monte
Carlo type analysis).
Currently all construction estimates have been made based on good weather conditions with no significant
delays and no other latent site defects. It would be expected that adverse weather conditions would be
expected to be funded from the contingency provision.
What is not expected to be covered by the contingency allowance is construction to be undertaken in “Wet”
conditions.
In addition to wet weather, it is possible that construction may be required to be carried out in the “wet”.
Currently all project costs have been assumed to have been based on construction taking place in the “dry”.
Construction in the “wet” includes a number of additional activities such as, the construction of coffer dams and
significant dewatering of the sites. The time taken to deliver projects will also be significantly higher. The additional
costs of developing the structures in the “wet” is significant and would add between 30% and 300% to the
construction costs of the various elements of the proposal and have a material impact on the total cost / benefit
results for the project.
To mitigate the cost impact of the potential “wet” construction costs the recommended approach will be to adjust
the project plan according to the prevailing site conditions nearer to construction and delay construction if
possible until “dry” conditions return. This will have the effect of delaying a proportion of the water savings until
construction can be carried out but will result in significantly lower overall costs of the project.
Alternately the construction can be undertaken in the “wet” if the benefits are considered significant enough to
justify the amended cost/benefit.
14.4 4 S tructural Adj ustme n t Cost s
Additional costs for structural adjustment package for the Lower Darling will largely be determined by the
Commonwealth after discussions with the relevant licence holders in the Lower Darling and have not been
assessed at this time.
TABLE 22: STRUCTURAL ADJUSTMENT PROVISIONS
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 89
14.5 Fu nding Re qu ire ments - Timi ngs
Due to construction not taking place until the back half of the project, it is expected that the major expenditure
will not be required until 2021/22, with $20.8m (real terms) required prior to that date.
$120
$100
$80
$60
$40
$20
$0
2016/17 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 2024/25
FIGURE 14: PROJECTED PROJECT EXPENDITURE BY YEAR
14.6 P ri c e Escala tio n
All project costs have been provided in “real” 2017 value and exclude GST.
Given the long lead time of this project, it is expected that construction and other costs will increase in nominal
terms. Based on current projected cashflow and an annual 2.5% escalation, it could be expected that final
project cost to increase a further $17.6m.
14.7 O p e ratin g an d Main tena nc e Costs
Estimated operation and maintenance (O & M) costs4 have been assessed for the various structures proposed
in this study. These operating costs need to be peered reviewed before the final phase 3 submission and post
any final design changes.
4 Provided by DPI Water and NSW Public Works
Mill
ions
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 90
Costs have been assessed in 3 categories, operating costs, routine maintenance and periodic maintenance. The
annualised expenditure is currently estimated to be or approximately of the total estimated capital
value of the structures as proposed.
The most significant expense is the estimated required every 2nd year to dredge or remove silt from the
proposed Menindee drainage channel. Without regular maintenance, it is expected that silt will reduce the
capacity of the channel and impact the overall water savings achieved as a result of slower drawdown rates and
the ability to access the entire pool.
Annual Operating Costs
Operating costs allowances have been made for the operational management of the structures. The cost relates
largely to provision of manpower to manage and operate the new structures and associated mainly with the
opening, closing and manipulation of the gates on all of the gated control structures. Operating costs have been
based on a 10 year operating cycle. All gated control structures are proposed to be operated by a portable actuator
and power supply.
Operating costs include personnel resource costs for remote operation and monitoring, scheduled and
unscheduled visits by operating personnel to the pump station and operating personnel involvement in regular
clearing of the trash screens.
Maintenance – Routine
Routine maintenance allowance is for the provision of materials or 3rd party services related to regularly
maintaining the structures and repair of vandalised plant and equipment covering the civil, mechanical and
electrical works as appropriate.
Maintenance – Periodic
Periodic maintenance costs cover the same item costs as routine maintenance and would typically be larger
maintenance items carried out at regular intervals including 2-yearly, 5-yearly, 10-yearly, 15-yearly and 30-yearly.
The estimate has been based on maintenance being required every 2nd year after construction to maintain
the structures in good working order for the first 10 years. Beyond this time the allowance would need to increase
to allow for major refurbishment works such as replacement regulator gates, control systems as required and
repair of erosion downstream of dissipaters.
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 91
The estimated O & M costs for individual structures are summarised in the table below.
TABLE 23: OPERATING AND MAINTENANCE COSTS
5 Indicative only. Capitalisation rate will require professional advice at the time of capitalising assets.
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 92
15 PROJECT DELIVERY
15.1 1 P r oj e ct M a na g e me nt P l a n
The delivery Proponent will be expected to arrange for the construction, operation and maintenance of the
required infrastructure and overall Menindee Lakes scheme. The delivery of works is to be undertaken based
on a traditional project model split into two key phases being;
a) Planning and Approvals
b) Execution
15.1.1 Phase 4a – Planning and Approvals
The objectives of this phase are to:
Minimise and project delivery/construction risks by undertaking necessary onsite technical
studies/activities (such as geotechnical, survey and environmental) and optimization of risk
allocation and mitigation
Minimize cost to the Proponent through scope design requirement optimization
Gain relevant planning approvals (IES, land access etc) that facilitate an uninterrupted construction
program
Facilitate the consultation and community communication of the proposed works and seek feedback
on specific infrastructure and operational measures to be implemented
Development of a robust tender document and competitive procurement process for the detailed
design and construction activities.
15.1.2 Phase 4b – Execution
The objectives of this phase are to:
Undertake detailed design and construction activities to agreed timeframes, cost and quality
requirements across the key elements of: -
o Infrastructure works;
o Structural Adjustment measures; and
o Facilitate the changes to institutional arrangements and operating rules.
Figure 15 provides the key milestones for the Menindee Water Savings across the phases of the project
plan. The detailed project plan is attached in Appendix 8.
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 93
FIGURE 15: KEY MILESTONES FOR PROJECT
15.2 2 Pr o ject Sc hedu le
The implementation timeframe is heavily influenced by two key activities being:
Environmental planning and approvals (including stakeholder engagement)
Conditions for construction (dry or inundated)
The Environmental Planning and Approval process is a gateway activity that requires finalisation prior to awarding a
contract for construction. This activity impacts the schedule in terms of time to complete the EIS and time to
implement resultant management actions prior to construction activities commencing. A scoping study will
establish the extent of general and specialist studies required and refine the estimated time to complete. The
resultant management measures may require further invasive testing and test pitting prior to construction to
assess the likelihood and significance of aboriginal heritage within the area. These two items are critical path
activities and are yet to have a full investigation undertaken. A conservative approach has been adopted for
estimation of timeframes which is consistent with industry best practice at this stage of project development.
Construction conditions, in particular the scenario of either dry or inundated conditions, is a ‘extreme’ risk to the
schedule and budget. The schedule incorporates a ‘dry’ construction program with risk to time and cost included
in the detailed risk register. Whilst construction activities can be undertaken in inundated conditions, there is a
cost premium for alternative construction methods (coffer dams/dredging etc) and a time for alternative site set-
ups.
Table 24 below lists the milestones for the project, along with their estimated completion timeframe.
TABLE 24: ESTIMATED PROJECT MILESTONES
Milestones Estimated
Completion Timeframe
Phase 4a: Planning & Approvals
Detailed project Plan February 2018
Basis of Design March 2021
Planning Approvals November 2020
EOI August 2020
ECI & Finalise Tender Documentation July 2021
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 94
Milestones Estimated
Completion Timeframe
RFT/Award Contract December 2021
Phase 4b: Detailed Design & Construction
Detailed Design May 2022
Construction and testing July 2023
Commissioning and Handover September 2023
15.2.1 Project Resourcing – Phase 4a & 4b
Client side resourcing requirements for Phase 4 have been assessed for each component of the Project;
this includes project management and administration, procurement, contract management, legal,
intergovernmental and stakeholder engagement. The resourcing requirements are reflected in the Project budget
and early guidance of requirements in Figure 16.
FIGURE 16: EARLY ESTIMATES OF FTE REQUIREMENTS
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 95
15.3 3 Pr ocur e men t S trategy
Phase 4a will deliver a concept design, technical specification, environmental approval (EIS) and land access
approvals that will facilitate the development of a Design and Construction tender(s).
Infrastructure works will be developed in packages of works and tendered either as a whole or in
components, if required.
Structural Adjustment works will be procured independently from Infrastructure works due to the early
commencement on these activities and relative unique work required to be implemented.
The Planning and Procurement Strategy has four key objectives:
Minimise the risk cost to Government from potential costly reworks during the detailed design
& construction phase
Remove and/or minimise construction risk that would otherwise translated to increased cost with a price
premium by tenderers
Ensure value for money for the Government
Maximise allowable construction time (to ensure works are completed late 2024) by running an EOI and
ECI process in parallel to the concept design and Environmental Assessment activities.
The details of the procurement strategy are provided in Appendix 9.
15.4 4 Q u a li t y A ssur an c e
Quality assurance processes will largely be dependent on the proposed Proponents corporate policies and
processes. The project will, as a minimum, need to implement a range of quality assurance processes and
procedures practices including:
Adoption of relevant Australian Standards and performance requirements for design, product
and construction works
Review and improvement processes (peer review of standards and performance criteria)
Development of specific project management procedures and practices
Adoption of sound record keeping process
Change control process
Procurement processes
Records management
Defects and non-conformance process
Quality Management systems processes for Work Health Safety and Environmental
Management.
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 96
16 PROJECT GOVERNANCE
16.1 1 G o ve r na nc e O ve r vi ew
NSW DPI Water has commenced the initial stages of providing information and briefings for the relevant
jurisdictions in relation to the Menindee Project; however, consultation to date has been minimal due to the
commercial-in-confidence aspects of the proposal and conceptual nature of the proposal to date. NSW DPI
Water notes the need for cooperative develop of a conceptual proposal inclusive of relevant operational rules,
modelling outputs and pathways to amend the relevant legal instruments, that will require a significant increase
in consultation with partner jurisdictions, under the MDB Agreement.
NSW DPI Water is proposing a more comprehensive engagement with interjurisdictional partners in the
development of the Menindee Lakes Water Savings Project and SDL Adjustment Package Business Case,
under Phase 3, as part of the SDL Adjustment Mechanism process. This will ensure that all matters that relate
to the MDB Agreement and other jurisdictions, particularly in regard to reliability and ongoing water supply,
have the ability to be fully discussed and integrated as part of the development of a Phase 3 business case.
This Business Case represents the best estimates of the Menindee Lakes Water Savings Project proposal
at this point in time. As the development of the proposal progresses and further information is gained from
Environmental Impact Statements and other planning activities, NSW will continue to work with the relevant
jurisdictions to update and progress the proposal.
In regards to establishing an appropriate Governance arrangement, NSW proposes the following objectives
to guide engagement:
All parties commit to working collaboratively, transparently and respectfully with each other, including
acknowledging and respecting each other’s roles, responsibilities and legislative frameworks;
It is recognised that NSW, as the proponent state, has lead responsibility for progressing the Menindee
project;
A working group will operate consistent with the intent of, and provisions in, the MDB Intergovernmental
Agreement;
Consistent with this, the Menindee project will be implemented in a way that delivers a triple bottom line
outcome for regional MDB communities and the environment;
The project will also be developed within an adaptive management and outcomes based approach,
which will likely necessitate ongoing adjustments to the project to incorporate expert advice and the best
available information;
A specific working group will be required to be established for the purposes of discussing and providing
advice to NSW DPI Water on issues that relating to the Menindee project that will have a potential impact
on Victoria, South Australia and the Commonwealth;
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 97
NSW will work with jurisdictions to develop final terms of reference for the group by early July 2017, based
on the draft provided in Appendix 1 to guide the activities and focus of the working group;
The Inter-Jurisdictional Working Group forum will facilitate timely and open provision of information to the
relevant jurisdictions to ensure informed discussions and due consideration of issues;
Membership of the Working Group will include representatives from NSW, Victoria, South Australia and
Commonwealth Governments. Membership will also include the MDBA in an advisory capacity;
The Working Group will operate in the first instance for to the duration of the development of the details
of the Menindee project proposal to a level consistent with the SDLAM Phase 3 business case
requirements, this also includes the period for amending or revising the Intergovernmental Agreement
regarding Basin Plan Implementation, from 1 June to 30 November 2017;
At this point the ongoing requirement of the working group to be reviewed by NSW DPI Water, with input
from the group to determine the framework for continuance of the Working Group in relation to ongoing
discussions required to identify and assess the rules or operating changes that are required to give effect
to the Menindee Lakes project proposal. This will be in a manner that gives effect to the intent of the MDB
Agreement water sharing arrangements; and
NSW will manage community and stakeholder consultations on the project, but will work closely with
Victoria, South Australia and the Commonwealth on relevant communications regarding implications of
the project for each jurisdiction.
Responsibility for the business case development and implementation, should it proceed, lies with NSW
DPI Water. Delivery of the Menindee Water Savings Project will also engage key agencies including:
MDBA as coordinator of Murray–Darling Basin water resources;
DPI Water, as the project proponent and NSW’s water manager;
DAWR (Cth), DEWLP (Vic) and DEWNR (SA);
Water NSW, as the manager and operator of river assets;
NSW OEH: as the environmental authority; and
Other NSW agencies as appropriate, including NSW Fisheries, NSW National Parks and Wildlife
Service.
Governance arrangements led by the DPI Water will be continued with these parties during project
implementation.
Within NSW, NSW DPI will manage agency consultation through the IAWG (Inter-Agency Working Group
for which the terms of reference are included in Appendix 2.
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 98
17 LEGISLATIVE AND REGULATORY FRAMEWORKFOR MENINDEE LAKES
17.1.1 Overview
The ownership, operations and maintenance of the Menindee Lakes sits within a complex suite of independent
but interrelated legislative, regulatory and commercial instruments and agreements. The changes contemplated
in this Business Case will necessitate changes to these guiding documents. Whilst a detailed legal review is
yet to be undertaken, provision has been made in both time and cost to undertake such a review as part of the
Phase 3 final submission.
The following represents a preliminary scan of the key instruments and an indication of areas that may require
further consideration by the jurisdictions. It is not intended to be a definitive term sheet at this stage, the relevant
clauses that will require review.
17.1.2 Murray Darling Basin Agreement
The operation of the Lakes are subject to the MDB Agreement. Murray Darling Basin Authority controls the
allocation of the waters stored by Menindee assets and the MDB Agreement links the control of the assets to
the control of the water. However, the Menindee Lakes are not (and never were) listed as “Works” in Schedule
A of the MDB Agreement and unlike other MDB joint venture assets, there is no responsible State nominated in
the case of Menindee.
This is a legacy of history, dating back to an agreement in 1962 between then Premier of NSW and the Prime
Minister, later ratified in a 1963 Agreement between the Victoria, South Australia, NSW and the Commonwealth and
codified in the Menindee Lakes Storage Agreement Act 1964 (1964 Act). The 1964 Act established cost sharing
arrangements, requiring the MDB Commission (MDBC) to make annual payments to NSW to operate and
maintain the works. Effectively the 1964 Act linked Menindee assets and operations to the MDB Agreement,
but they otherwise stood to the side of the detailed machinery of the Agreement (pers com. Nosworthy).
Relevant provisions within the MDB Agreement include: -
Part XII Clause 94(c) sets out the entitlements of NSW and Victoria to Menindee Resources
Part XII Clause 95 provides further detail on the NSW entitlement to water in Menindee including
the effect of control triggers on operations.
Part XII Clause 98 provides that the MDBA may give directions for the release of water and that water
must be released in accordance with that Direction.
Part XII Clause 99 details the current 480GL/640GL control thresholds.
Part XII Clause 107 deals with the Allocation of water in Menindee between NSW and Victoria in respect
of Darling River inflows.
Part XII Clause 120 defines and details accounting for Menindee releases.
Part XII Clause 121 deals with reallocation of water between NSW and Victoria.
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 99
Part XII Clause 136 requires NSW to maintain the Menindee Lakes Storage and associated works in
good order and condition necessary to meet full supply levels and storage capacity.
Part XII Clause 137 specifies Full Supply Levels for each of the Lakes.
Part XII Clause 138 details the annual payments to NSW in return for operating and
maintaining the assets.
Schedule G Part 4 Clause 23 details provisions for accounting deferred water stored in
Menindee including the interplay with Additional Dilution Flow for South Australia.
The MDB Objectives and Outcomes for River Operations 2016 (O & O) provides more prescriptive guidance on
the MDB system operations and has provisions relevant to Menindee and this proposal. Relevant provisions under
Appendix A Specific Objectives and Outcomes include:
Clauses 10.1 through to 10.4, dealing with
o maximum downstream releases;
o rates of rise and fall;
o planned seasonal release rates, and
o planned distribution of water between the Lakes to increase efficiency.
Clause 12.2 details the harmonisation practices between Menindee and Lake Victoria.
Clause 12.3 provides guidance on, and amendment to, the delivery of Additional Dilution Flows to
South Australia.
17.1.3 NSW Water Sharing Plan
The Water Sharing Plan for the New South Wales Murray and Lower Darling Regulated Rivers Water Sources
(2016) applies to water sources that include the Menindee Lakes. As such as number of provisionswithinthe
Planwillrequirereviewand potentialamendmenttoaccommodatetheproposed changes, including: -
Clause 31 – deals with environmental water rules in the Lower Darling including the interaction between
storage levels and environmental account management.
Clause 34 deals with flood operation rules and the requirement for consistency with the MDB
Agreement.
Clause 35 deals with the need to provide airspace in accordance with the MDB Agreement.
Clause 52(7)(b) deals with water allocation accounts and evaporative losses.
Clauses 54 (6) and (7) deals with access to supplementary water and the requirement not to impact
on obligations to South Australia.
Appendix 3 deals with triggers around Additional Dilution Flows and minimum flows into the Lower
Darling.
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 100
17.1.4 NSW Works Approval
Also at the NSW level, Menindee infrastructure and operations are recognized in the 2012 NSW Murray Lower
Darling Work Approval issued to WaterNSW. The infrastructure listing is high level, referring only to “Menindee
Lakes and Associated Structures” and “Weir 32 and Fishway”. In respect of operation, relevant provisions include:
-
Clauses 8 and 9 deals with the Lower Darling Environmental Contingency Allowance (ECA) and the
requirement for an account to be kept for credits and debits to the ECA.
Clauses 10 and 11 deals with the Murray Additional Environmental Allowance, requiring the Approval
holder to keep and account of credits and debits and for releases of water in accordance with
Ministerial Directions.
Clause 12(f) deals with water delivery and channel capacity constraints in the Lower Darling, requiring
regulated flows no greater than 20,000ML/day at Pooncarie; and
Clause 13 compels the Approval Holder to “advise the Minister of any new information that becomes
available that is relevant to the maximum channel capacities and maximum regulated rates required
by condition twelve (12)”, including:
o inundation of private land or interference with access;
o the transmission losses expected to occur; and
o capacities of water management structures.
Clauses 15-17 deal with Menindee flood operations and specifically the requirement
o to meet Dam Safety obligations and Directions
o to mimic natural hydrographs during flood operations releases
o not to exceed daily threshold flow reduction changes in the flood recession phase of
operations.
Clause 18 compels the Approval Holder to achieve minimum flow targets at Weir 32.
Clause 20 specifies weir pool draw down and fill rates that cannot be exceeded in anything other than
“natural” events.
17.1.5 Additional Dilution Flow
Alternative operating procedures were examined for Menindee Lakes and Lake Victoria as part of studies into
options for mitigating salinity in the River Murray system. As a result of these studies a package of measures
were adopted by the Murray Darling Basin Commission in June 1987. This package included rules in relation
to the distribution of water between the Lakes in at Menindee; the harmonisation of operations between Menindee
and Lake Victoria; flushing rules at Lake Victoria and the provision of Additional Dilution Flow(ADF) to South Australia.
ADF requirements are allowed for but not specified in the MDB Agreement however they are specified in the MDBA
Specific Objectives and Outcomes. ADF is 3,000ML/day and is only provided when the
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 101
storage in Menindee Lakes and the combined storage in Hume and Dartmouth exceeds agreed triggers
described in the O&O document.
ADF therefore influences the operations at Menindee and as such changes proposed in this project will need to
be assessed in terms of ADF objectives.
Preliminary advice (Turner, 2016) suggests that the Menindee Savings will provide outcomes consistent with the
original intent of the ADF rules, although ADF itself will effectively become obsolete.
17.1.6 Accounting for Additional Inflows
Clause 107 of the MDB Agreement specifies that the water entering Menindee Lakes is shared between
Victoria and NSW in equal shares. This project effectively increases the inflows at Menindee (by reducing
evaporative losses) as do the concurrent Northern Basin measures.
It is proposed as part of the Menindee Project, that the MDB Agreement quarantine the additional flows into
environmental accounts. The revised modelling currently underway will provide details on options to pursue this
change with consideration provided for third party issues or impacts as a result of this change.
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 102
REFERENCES
Balme, J. and Hope, J., (1990). Radiocarbon dates from midden sites in the lower Darling River area of
western New South Wales. Archaeology in Oceania 25, 85-101.
Bogenhuber D. Wood D. Pay T. and Healy S., (2014). The Darling Anabranch Adaptive Management Monitoring
Program Final Report 2014. Prepared in conjunction with NSW Office of Environment and Heritage by the
Murray-Darling Freshwater Research Centre.
NSW Public Works (2015), Menindee Water Saving Optimisation Study & Concept Design, report No. DC15012
July 2015
GHD, (2015). Menindee Water Savings Project Stages A1 and A2 - Environmental Water Needs and Water
Management Arrangements. GHD.
Gippel C. J. and Blackham D., (2002). Review of environmental impacts of flow regulation and other water resource
developments in the River Murray and Lower Darling River system. Final Report. Fluvial Systems Pty Ltd, Stockton,
to Murray-Darling Basin Commission, Canberra, ACT.
Green D., Ali A., Petrovic J., Burrell M., Moss P. (2012). Water resources and management overview: Lower
Darling River Catchment, NSW Department of Primary Industries, Sydney.
Green D. L. Shaikh M. Maini N. Cross H. and Slaven J., (1998). Assessment of environmental flow needs for the
Lower Darling River. A report to the Murray–Darling Basin Commission. NSW Land and Water Commission,
Sydney.
Martin S. Witter D. and Webb C., (1994). The archaeology of Lakes Menindee and Cawndilla and the impact of
artificial water storage : a report to the NSW NPWS and the NSW Department of Water Resources. NSW
NPWS and the NSW Department of Water Resources.
Maunsell Australia Pty Ltd, (2007). Darling River Water Savings Project – Part A Report. Maunsell Australia Pty Ltd.
MDBA Licenced under a Creative Commons Attribution 3.0 Australia Licence, (2012) Assessment of environmental
water requirements for the proposed Basin Plan: Lower Darling River System. (MDBA).
SKM (2002) Menindee Lakes Aquatic Fauna, Integration Report for Menindee Lakes ESD Project, DLWC, Sydney.
SKM, (2010). Darling River Water Savings Project – Part B Final Report. SKM.
Taylor-Wood, E. McCormick S. Mueck S. Richardson M. and Jukic M., (2001). Vegetation/Habitat Mapping of
Inundated Areas of Menindee Lakes. Report for the Menindee Lakes Ecologically Sustainable Development
Project Steering Committee: Biosis.
Turner G, (2016). River Murray Operations Framework Changes to support SDL Adjustment : Menindee
Lakes – Issues Paper – Draft
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 103
APPENDIX 1 – MENINDEE LAKES INTER-JURISDICTIONAL WORKING GROUP
Establishment of the Working Group
The Menindee Lakes Water Savings Project Intergovernmental Working Group (the Working Group) is established
to identify inter-jurisdictional issues and jurisdictional issues associated with the project, and provide advice to NSW
on such issues in the further development of the Menindee Lakes Water Savings Project Business Case.
Role of the Working Group
The Working Group will provide advice to NSW as the lead jurisdiction in the development of the Menindee
Lakes Water Savings Project and has the following roles:
The Working Group will focus on specific details within this framework on implications of MDBA June 2017
modelling;
Reconciliation milestones;
Reviewing changes to the River Murray Framework;
Processes for recognising the additional inflows to Menindee from the Northern Basin; and
Discussion of framework changes will build on the work commissioned by the MDBA.
NSW will continue to hold primary responsibility for Commonwealth and NSW regulatory approvals for the design
and construction of the proposed infrastructure changes. This will include community engagement and cultural
heritage requirements. It is likely that the project, if approved to proceed will be NSW State Significant
Infrastructure. The Working Group will need to operate within the constraints of this structure as provided by
the NSW Government.
The Commonwealth will lead negotiation of the structural adjustment and strategic water entitlement purchase
activities for the Lower Darling.
Both these elements of the project development will be outside the scope of the Working Group but will need to
report to the Working Group on progress and if issues arise that will affect the broad cost benefit of the project.
Membership
Membership of the Working Group will include up to two representatives each from NSW, Victoria, South Australia
and the Commonwealth.
NSW will Chair the Working Group as the lead jurisdiction for the Menindee Lakes Water Savings Project.
Recognising its role in water management, the MDBA is requested to nominate two representatives to attend
meetings as observers and in the provision of advice to the Working Group in relation to river operations,
Menindee Lakes and SDL Adjustment Mechanism modelling, and MDB Agreement matters.
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 104
Other representation may occur at the discretion of NSW as the lead jurisdiction.
Members and alternates should be appropriately authorised to provide advice and make decisions on behalf of
their jurisdiction and/or agency.
Relevant technical staff may attend meetings and provide advice as appropriate.
Chair and Committee Support
Department of Primary Industries, Water will Chair the Committee and provide secretariat services.
Procedural Directions
Best endeavours will be made to reach in principle agreement on the required changes post June 2017, with
discussions extended beyond the November 2017 timeframe for agreement to the revised or new
Intergovernmental Agreement for Basin Implementation if required.
An indication of the timing for the Menindee proposal development against the 2017 Ministerial Council
endorsed Finalisation Plan is set out in Table 2 as a basis for the Working Groups activities, as part of the
finalisation of the development of the amended notification advice and Phase 2 Business Case.
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 105
APPENDIX 2 – MENINDEE LAKES INTER-AGENCY WORKING GROUP
Establishment of the Working Group
The Menindee Lakes Water Savings Project NSW Interagency Working Group (the IAWG) is established
to provide whole-of-government input into the Final (Phase 3) Menindee Project Business Case, to be submitted for
approval of the MDB Ministerial Council.
Role of the Working Group
The Working Group will provide advice to DPI as the Project Proponent in the development of the Menindee
Lakes Water Savings Project and has the following roles:
Provide advice in relation to the development of the EIS Scoping Study, including
o Identification of likely Environment and Heritage risks and issues
o Development of the Director-General’s requirements
o Provision of subject matter expertise where required
o Review the EIS Request for Tender (RFT) documentation prior to public consultation
Review and contribute to the MDBA modelling;
Provide advice and support in relation to statutory / regulatory approvals processes
Consider progress against the project plan and key milestones
Assist with key stakeholder liaison and communications including respective Ministerial offices.
DPI Water will lead the NSW Government in Inter-government liaison and negotiations.
Membership
Membership of the Working Group will include a maximum of two representatives each from each of the following
entities: -
Department of Primary Industries Water
Department of Premier and Cabinet
NSW Treasury
Office of Environment and Heritage
NSW Fisheries
NSW Department of Planning
WaterNSW
Members and alternates should be appointed and authorised to speak on behalf of the respective agency /
corporation.
Relevant technical staff may attend meetings and provide advice as appropriate.
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 106
Chair and Committee Support
Department of Primary Industries, Water will Chair the Committee and provide secretariat services.
Decision Making Authority
The IAWG is an advisory group only. Notwithstanding this advice, decisions in relation to the Phase 3 Business
Case will reside with DPI Water, however opportunities to represent formal agency positions in relation to the
proposal will be available through the normal regulatory approvals process for State Significant Projects in NSW.
Tenure
The initial tenure of the IAWG will be from June 2017 until the Basin Officials Committee approves the Phase 3
Business Case for the Menindee Project – expected to be November 2017.
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 107
APPENDIX 3 – RISKS AND ISSUES – RISK REGISTER
IDENTIFICATION INHERENT RISK ANALYSIS TREATMENT AND RESIDUAL RISK EVALUATION
Risk ID Risk Title Risk Description Risk Category Inherent Risk
Likelihood
Inherent Risk
Consequence
Inherent Risk
Rating
Risk Treatment / Actions to Mitigate Residual Likelihood Residual
Consequence
Residual Risk
Rating
RSK002 Program Scope changes increase cost of project Budget
significantly beyond the contingecy allowance.
Possible Major A12 Early en gagement of PW and other advisors used to Unlikely refine scope for necessary measures and design
concepts. Outcome of EIS findings for enviro an d
heritage impacts will impact final req'ts.
Moderate Y6
RSK003 Third Party Impacts Potential to undersize or oversize design Budget
elements.
Possible Moderate Y9 Multi stage process used to refin e the necessary Possible measures and design concepts.
Moderate Y9
RSK004 Costs Potential to exceed construction budget, if Budget
construction constraints are not managed.
Possible Moderate Y9 Commercial terms to be developed during pre- Possible
tender phase to ensure appropriate risk sharing
is included in final contractual documentation.
Moderate Y9
RSK005 Program Project currently assumes sequential program Budget
to reduce regret cost. Pressure to bring program
forward will increase the likelihood of regret
costs and need to re-do some activity if scope
changes.
Possible Major A12 Continue to monitor deadline requirements. Possible
Ensure that bulk of activity is targetted for
completion under dry conditions prior to EOY
2024.
Major A12
RSK006 Stakeholders Budget has been constructed in real dollars. Budget
Final nominal project costing will be significantly
higher and is largely subject to agreement on
timeline & inclusions.
Almost Certain Major R20 Ensure that all funding parties are made aware Unlikely
of the 'real' pricing used in project. Where
possible, lock contracts in place with fixed
pricing with limited escalation clauses.
Minor G4
RSK007 Program A significant body of work has already been Budget
undertaken (particularly environment). Budget
assumes that some benefit will be derived in
time/cost from use. Budget will be negatively
impacted if prior body of work is not used or no longer relevant.
Likely Moderate A12 Two phase EIS process to be used to narrow Unlikely
down scope of additional work required. EIS
scoping phase to provide listing of known
previous bodies of work in relation to Menindee
works.
Moderate Y6
RSK009 Costs Risks associated with wet construction costs will Budget
be high. Contractual risk sharing will need to be
considered carefully to avoid having the full cost
embedded in the base price
Almost Certain Major R20 Early Contractor Involvement (ECI) to be used Possible
prior to the formal tender process to identify
significant contractor risks and appropriate cost
sharing mechanisms.
Moderate Y9
RSK020 Water Licences Websters Limited (Tandou) currently have a Budget
zero value supplementary licence available.
Government have previously purchased a
supplementary licence from Tandou.
Possible Major A12 Treatment of zero share licence and Unlikely
relationship with prior purchase (if any) to be
resolved.
Negligible G2
Page 108
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Risk Register Cont…
IDENTIFICATION INHERENT RISK ANALYSIS TREATMENT AND RESIDUAL RISK EVALUATION
Risk ID Risk Title Risk Description Risk Category Inherent Risk
Likelihood
Inherent Risk
Consequence
Inherent Risk
Rating
Risk Treatment / Actions to Mitigate Residual Likelihood Residual
Consequence
Residual Risk
Rating
RSK055 Water Licences Buy back is rejected by Licence Holders and Budget
Government required to use alternate
measures for removing high security
entitlements from Lower Darling.
Possible Severe R15 Develop stuctural adjustment strategy and Likely
engage the Licence Holders as early as possible.
Fall-back position will be to have licence holders
accept alternate measure to convert licences
from high security entitlement.
Moderate A12
RSK069 Budget No certainty for funding for ongoing O&M costs. Budget Likely Moderate A12 O&M provisions to be identified early. Unlikely
Confirmation required on where assets will be vested
and whether funding will be by way of
return on RAB or externally provided.
Minor G4
RSK010 Community Concerns Perception of waste, due to duplication of Communication
previous work already carried out and
representations made.
Likely Moderate A12 Engage sufficient resources to manage comms Possible
plan and stakeholder engagement process.
Moderate Y9
RSK011 Stakeholders Key stakeholders are not clearly identified and Communication re-
engaged at an early enough stage in the
process and actively campaign against the
project.
Likely Severe R20 Engage sufficient resources to manage comms Possible
plan and stakeholder engagement process.
Broader stakeholders to be provided with
regular communications.
Moderate Y9
RSK012 Community Concerns Perceptions that evaporation occurring Communication
elsewhere in the basin is not being addressed,
and that Menindee Lakes is being unfairly
targeted.
Almost Certain Moderate R15 Refer broader basin plan issues back to Likely
appropriate authority to provide response.
Moderate A12
RSK013 Stakeholders The benefits arising from estimated SDL offsets, Communication
environmental benefits and basin plan
objectives have not been clearly articulated to
all stakeholders.
Likely Moderate A12 Engage sufficient resources to manage comms Possible
plan and stakeholder engagement process.
Moderate Y9
RSK015 Operating Rules EIS consent conditions recommend works Dependency
and/or operating rules that reduce the overall
water saving benefits.
Almost Certain Severe R25 Project to only proceed based on acceptable Possible
level of cost/benefits.
Major A12
RSK017 Third Party Impacts Third party approval process have significant Dependency
potential to delay project program.
Likely Severe R20 Sufficient time has been allowed for in the Possible
project plan for necessary responses from
authorities, public and other significant
stakeholders.
Moderate Y9
Page 109
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Risk Register Cont…
IDENTIFICATION INHERENT RISK ANALYSIS TREATMENT AND RESIDUAL RISK EVALUATION
Risk ID Risk Title Risk Description Risk Category Inherent Risk
Likelihood
Inherent Risk
Consequence
Inherent Risk
Rating
Risk Treatment / Actions to Mitigate Residual Likelihood Residual
Consequence
Residual Risk
Rating
RSK018 Governance Clash between stucture of State Significant Dependency
Project framework and timelines vs stakeholder
processes
Possible Major A12 Project plan has provided sufficient time to Unlikely
meet State Significant project processes to be
met.
Minor G4
RSK019 Program Without parallel scheduling, program has no Dependency
capacity to slip due to extreme weather
conditions and still meet 2024 deadline.
Possible Severe R15 Utilise parallel scheduling where possible for Possible
geo, survey and some preliminary design works
where possible to provide a 6 month buffer for
wet weather delay.
Major A12
RSK014 Ecological – Operations Reductions in bankful and overbank flows Environment
decrease stream metabolism and affect primary
productivity in the Lower Darling River and
Great Darling Anabranch
Possible Major A12 Adverse impacts to be assessed and mitigated Possible
through extensive EIS and EMP.
Moderate Y9
RSK016 Environmental Impacts – Construction Impacts to threatened species during Environment
construction activities
Possible Moderate Y9 Adverse impacts to be assessed and mitigated Unlikely
through extensive EIS and EMP. Requirement
for Construction Contractors to develop suitable
management plan to remove impact on
threatened species during construction.
Negligible G2
RSK021 Community Concerns Operation changes create negative impacts on Environment
Kinchega National Park
Possible Moderate Y9 Adverse impacts to be assessed and mitigated Possible
through extensive EIS and EMP.
Minor G6
RSK022 Community Concerns Operation changes impacts on Wetting & Dying Environment
cycles of the Menindee Lakes
Almost Certain Major R20 Adverse impacts to be assessed and mitigated Likely
through extensive EIS and EMP. Some long term
changes to flora/fauna inevitable due to
changes in cycles.
Moderate A12
RSK023 Ecological – Operations Fish management act will trigger requirement Environment
for fish passage structures at each of the new
works and potentially the existing main weir.
Almost Certain Moderate R15 Include cost of fish passage in concept designs. Unlikely Minor G4
RSK024 Ecological – Operations Death of trees due to lack of flooding. Environment Almost Certain Moderate R15 Adverse impacts to be assessed and mitigated Unlikely
through extensive EIS and EMP
Moderate Y6
Page 110
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Risk Register Cont…
IDENTIFICATION INHERENT RISK ANALYSIS TREATMENT AND RESIDUAL RISK EVALUATION
Risk ID Risk Title Risk Description Risk Category Inherent Risk
Likelihood
Inherent Risk
Consequence
Inherent Risk
Rating
Risk Treatment / Actions to Mitigate Residual Likelihood Residual
Consequence
Residual Risk
Rating
RSK025 Ecological – Operations Risk to Black Box-Coolabah as listed Endangered Environment
Ecological Community.
Possible Major A12 Adverse impacts to be assessed and mitigated Unlikely
through extensive EIS and EMP
Moderate Y6
RSK027 Ecological – Operations Rapid rises during filling events may drown Environment
emergent species & rapid rate of draining may
expose aquatic species.
Likely Moderate A12 Adverse impacts to be assessed and mitigated Unlikely
through extensive EIS and EMP
Moderate Y6
RSK028 Ecological – Operations Impacts to threatened species due to altered Environment
hydrology.
Possible Major A12 Adverse impacts to be assessed and mitigated Unlikely
through extensive EIS and EMP
Moderate Y6
RSK029 Ecological – Operations Impact on recruitment success from waterbird Environment
breeding and frog breeding.
Possible Major A12 Adverse impacts to be assessed and mitigated Unlikely
through extensive EIS and EMP
Moderate Y6
RSK030 Ecological – Operations Changes to water levels impact feeding and Environment
roosting of waterbirds (including international
migatory species)
Likely Major R16 Adverse impacts to be assessed and mitigated Possible
through extensive EIS and EMP
Moderate Y9
RSK033 Ecological – Operations Elevated water levels in Menindee Lake Environment
adjacent to the empty Lake Cawndilla leading to
salinization nearby (including within Lake
Cawndilla),
Possible Moderate Y9 Adverse impacts to be assessed and mitigated Possible
through extensive EIS and EMP
Moderate Y9
RSK034 Ecological – Operations Potential for sediment to be generated in Environment
channels
Possible Moderate Y9 Adverse impacts to be assessed and mitigated Possible
through extensive EIS and EMP. Operational
plan to be developed to manage sediment build-
up in channels.
Moderate Y9
RSK035 Environmental Impacts – Construction Impact of clearing operations on threatened Environment
ecological species or endangered ecological
communities
Possible Major A12 Adverse impacts to be assessed and mitigated Possible
through extensive EIS and EMP
Moderate Y9
Page 111
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Risk Register Cont…
IDENTIFICATION INHERENT RISK ANALYSIS TREATMENT AND RESIDUAL RISK EVALUATION
Risk ID Risk Title Risk Description Risk Category Inherent Risk
Likelihood
Inherent Risk
Consequence
Inherent Risk
Rating
Risk Treatment / Actions to Mitigate Residual Likelihood Residual
Consequence
Residual Risk
Rating
RSK036 Community Concerns Concern that the environment of the Lower Environment Possible
Darling, the Lakes and the Anabranch will be
less valued than downstream environments;
Moderate Y9 Adverse impacts to be assessed and mitigated Possible
through extensive EIS and EMP
Moderate Y9
RSK037 Community Concerns EIS identifies endangered fauna/flora and Environment Likely
require acquisition of significant off-sets.
Location and agreement of offsets have the
potential to delay project and increase costs.
Major R16 Adverse impacts to be assessed and mitigated Possible
through extensive EIS and EMP
Moderate Y9
RSK008 Stakeholders 3rd parties raise injuction against any or all of Governance, Legal & Possible
the project procesing. Regulatory
Severe R15 Early & active engagement of community Unlikely Moderate Y6
RSK045 Legal Landowners are reluctant / unwilling to permit Governance, Legal & Possible
easements on title for levee construction. Regulatory
Moderate Y9 Negotiations to take place early during project. Unlikely Agreement to create easement sought by way of
option or other instrument. In ducement paid as
part of early option. Fallback to use compulsory
acquistion powers.
Minor G4
RSK046 Legal Change of ownership of properties in Lower Governance, Legal & Possible
Darling occurs and new owners do not honour Regulatory
option for licence buy-back & impairment of
works approvals.
Major A12 Caveat to be placed on title at time of Unlikely
negotiating option to buy-back. Caveat to be
removed if project does not proceed.
Minor G4
RSK047 Legal Intra state institutional arrangements pose Governance, Legal & Likely
constraints on the project that threaten the Regulatory
projects viability
Major R16 Identification of approvals needed and Possible
associated drafting to be undertaken as early as
possible.
Major A12
RSK050 Consent Authorities Interstate institutional arrangements pose Governance, Legal & Likely
constraints on the project that threaten the Regulatory
projects viability
Major R16 Identification of approvals needed and Possible
associated drafting to be undertaken as early as
possible.
Moderate Y9
RSK068 Stakeholders Concerns that inter-jurisdictional stakeholders Governance, Legal & Possible
aren't adequately consulted and engaged Regulatory during
the project leading to delays during final
approval processes.
Major A12 Engage all inter-jurisdictional stakeholders early Possible
include requirements in communications plan.
Moderate Y9
Page 112
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Risk Register Cont…
IDENTIFICATION INHERENT RISK ANALYSIS TREATMENT AND RESIDUAL RISK EVALUATION
Risk ID Risk Title Risk Description Risk Category Inherent Risk
Likelihood
Inherent Risk
Consequence
Inherent Risk
Rating
Risk Treatment / Actions to Mitigate Residual Likelihood Residual
Consequence
Residual Risk
Rating
RSK039 Community Concerns Project is unable to meet all of the aspirations Heritage
of Native Title Owners / local / wider aboriginal
interests.
Likely Major R16 Engage with aboriginal interest groups early and Possible
seek input into possible heritage concerns.
Moderate Y9
RSK040 Heritage Heritage concerns and located artifacts Heritage
providing potential to delay or require major
scope changes to the project or program.
Likely Moderate A12 Engagement of Project Archaeologist throughout Possible planning and construction phases. Undertake early
extensive cultural heritage investigation in
partnership with the local Aboriginal communities.
Moderate Y9
RSK041 Heritage Concerns that the Morton Boolka regulator Heritage
would attract vistors who would collect
artefacts in the area.
Possible Moderate Y9 Engagement of Project Archaeologist to identify Unlikely likely heritage artefacts. Develop plan in
consultation with indigenious stakeh olders to
protect heritage items.
Moderate Y6
RSK042 Operational changes Increased frequency of drying could lead to Heritage
increased erosion risks potentially exposing and
damaging cultural heritage items.
Possible Moderate Y9 Engagement of Project Archaeologist to identify Possible likely heritage artefacts. Develop plan in
consultation with indigenious stakeh olders to
protect / relocate h eritage items where possible.
Moderate Y9
RSK048 Operations Potential for interested stakeholder groups to Operations
require excessive works and operations that
impose costs on the project.
Possible Moderate Y9 Develop robust stakeholder engagement Unlikely
processes that clearly specify roles and
responsibilities.
Moderate Y6
RSK051 Modelling Modelled outcomes from the inclusions of SDL Operations
package are insufficient to justify the
expenditure.
Possible Severe R15 Project is unlikely to proceed until sufficient SDL Possible
benefit is available vs the expenditure.
Major A12
RSK052 Community Concerns Removal of Old Menindee Town Weir is resisted Political
by community.
Possible Moderate Y9 Early community consultation on need to Possible
remove weir to gain most long term benefit.
Moderate Y9
RSK053 Community Concerns Property values in Menindee and other related Political
townships decrease due loss of amenity and/or
economic activity from buy-back of Lower
Darling licences and changes to operations.
Almost Certain Moderate R15 Review options to provide structural adjustment Likely
package to Menindee township.
Moderate A12
Page 113
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Risk Register Cont…
IDENTIFICATION INHERENT RISK ANALYSIS TREATMENT AND RESIDUAL RISK EVALUATION
Risk ID Risk Title Risk Description Risk Category Inherent Risk
Likelihood
Inherent Risk
Consequence
Inherent Risk
Rating
Risk Treatment / Actions to Mitigate Residual Likelihood Residual
Consequence
Residual Risk
Rating
RSK001 Water Licences The assumed impacts of the changes to licence Political Possible
entitlements is broader than expected and the
planned structural adjustment package is
insufficient to address all impacts.
Severe R15 Modelling is required to confirm reliability Possible
changes for all water entitlement holders that
remain and quantify any impacts.
Moderate Y9
RSK057 Community Concerns Community feels previously raised Political
Likely concerns/issues have
been ignored.
Moderate A12 Specialist to be engaged for the development of Possible
comprehensive comms and community
engagement plan.
Plan to clearly address why (if any) community
issues not addressed.
Moderate Y9
RSK058 Stakeholders Upstream communities try to link otherwise Political Possible
unrelated issues to the project and threaten its
viability.
Major A12 Communication plan to clearly outline the Possible
savings relate to agreements under the basin
plan.
Minor G6
RSK059 Community Concerns Potential action by residents of Sunset Strip & Political Almost Certain
Copi Hollow based on the perceived reduction
in availability of water for water sports and
other recreational activity.
Major R20 Engage with local residents/users to fully Possible
understand their needs and the capacity of the
project to accommodate their.
Moderate Y9
RSK061 Community Concerns Interest groups use project to increase pressure Political Possible
to have Lake system listed with Ramsar and
potentially delays project.
Major A12 Manage stakeholder expectations through intra Possible
and inter government processes.
Moderate Y9
RSK062 Environmental Impacts – Construction Increased noise & traffic during construction Project Management Possible
phases.
Moderate Y9 Development of a memorandum of understanding Possible for monitoring of construction activities.
Moderate Y9
RSK063 Environmental Impacts – Construction Risk of flooding or inundation during Project Management Possible
construction.
Major A12 Development of a memorandum of understanding Possible for monitoring of construction activities.
Moderate Y9
RSK064 Program Significant weather event delays planning Project Management Possible
activities in project (geo, survey)
Moderate Y9 Planning activities including Geo & Survey to be Possible
undertaken as early as possible after agreement
has been reached on potential regret cost
budgets.
Moderate Y9
Page 114
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Risk Register Cont…
IDENTIFICATION INHERENT RISK ANALYSIS TREATMENT AND RESIDUAL RISK EVALUATION
Risk ID Risk Title Risk Description Risk Category Inherent Risk
Likelihood
Inherent Risk
Consequence
Inherent Risk
Rating
Risk Treatment / Actions to Mitigate Residual Likelihood Residual
Consequence
Residual Risk
Rating
RSK065 Program Project works are completed during dry spell in Project Management Possible
lakes and works can't be adequately tested and
commissioned.
Moderate Y9 Construction contracts to make provision for Possible
extended testing / commission period if lakes
are subject to an extreme weather event.
Moderate Y9
RSK049 Community Concerns Menindee Township & Sunset Strip concerned Stakeholder Likely
about future water quality and supply.
Moderate A12 This issue is being addressed as part of Broken Possible
Hill pipline project.
Moderate Y9
RSK066 Water Licences Total compensation paid for structural Stakeholder Likely
adjustments distorts Water Licence markets and
sets unwanted precedents.
Major R16 Recommend to Commonwealth that market Possible
price is paid for high security water licence
purchases. Any additional payments required
should reflect compensation for other impacts.
Major A12
RSK067 Community Concerns Landholders on the Anabranch are concerned Stakeholder Likely
that installation of regulators could lead to
poorer ecological & socio-economic outcomes
in the Anabranch, & fear that the Anabranch
regulators will be used to stop flows to the
Anabranch more frequently,
Major R16 Adverse impacts to be assessed and mitigated Possible
through extensive EIS and EMP
Moderate Y9
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
APPENDIX 4 – EIS REQUEST FOR TENDER – (DRAFT REQUIREMENTS)
Background
The Menindee Lakes are located in South-West New South Wales on the floodplain of the Darling River. The
system consists of seven major Lakes; Menindee, Cawndilla, Pamamaroo, Tandure, Bijijie, Balaka and Malta and
a number of smaller wetlands (Spectacle, Speculation and Eurobilli). The impounding of the Darling River has
led to the creation of an additional waterbody, Lake Wetherell.
Although naturally intermittent, the Lakes have been used for water storage since the 1960s, increasing their
permanence. They are listed on the Directory of Important Wetlands of Australia, primarily for their role in
supporting waterfowl. They periodically support large numbers of ducks and cormorants acting as a feeding and
breeding ground and an important drought refuge. The site also has significant cultural and social values.
The large shallow nature of the Menindee Lakes results in large amounts of water loss through evaporation,
prompting calls for infrastructure and operating improvements. In September 1998, the Premier of NSW Bob Carr
announced that the NSW Government would undertake investigations into the feasibility of structural and
operational changes to the Menindee Lakes system for improved management.
Since that time there have been several iterations of proposed structural works and assessments of their
effectiveness and impacts. In 2013, the Commonwealth and NSW governments agreed to further investigate a
scope of infrastructure works and potential changes to the Murray-Darling Basin Agreement. The MDBA
completed preliminary modelling of Menindee in 2013 for the proposed suite of works and measures at that time.
This modelling indicated water savings of 72GL for the Menindee project.
A revised suite of works and measures designed to reduce evaporation, reduce water security demands,
maximise water savings and improve water quality was developed and approved as an Interim Business Case
in June 2017. The proposal builds on previous plans, to improve water savings and is considered sufficiently
different from former works and measures to require a new assessment of potential benefits and impacts.
Current proposed works
The current proposed works and measures are illustrated in Figure 17 and tabulated in Table 26.
Page 115
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 116
FIGURE 17: OVERVIEW OF PROPOSED WORKS
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 117
TABLE 25: COMPARISON OF THE CURRENT PROSED MENINDEE PROJECT WITH THE 2013 PROPOSAL.
residents
Feature Details Basin Plan
Outcomes
Infr
ast
ruct
ure
Measure 1 Menindee outlet regulator capacity increased from 5,000ML/day.
Works to increase up to 14,000ML/day SDL supply measure, and Constraints Management
Measure 2 Lake Menindee drainage channel to feed outlet and improve discharge
Drainage channel up to 14,000ML/day SDLsupply measure
Measure 3
Morton-Boolka transfer regulator to control
releases to and from Menindee and
Up to 14,000ML/day regulator SDLsupply measure
Measure 4
Cawndilla
Old Menindee Town Weir removal
Removal of redundant Menindee town weir to improve
Menindee outlet regulator flows by reducing downstream
Constraints Management
Measure 5, 6 &
Increased Lower Darling channel capacity to
head
Two regulators to prevent escape flows into Yartla Lake
SDL supply measure, and
11 take higher Menindee discharge – offtake and Emu Lake + bridge at Charlie Stone Crossing Constraints Management
Measure 7
Measure 8 & 9
regulators at Emu Lake and Yarta Lake
Cawndilla Creek Regulator
Anabranch offtake regulators constructed
Up to 14,000ML/day regulator
New Anabranch diversion regulator #1 to control up to
14,000ML/day
Environmental mitigation
SDL supply measure, and
Constraints Management
New Anabranch environmental Regulator #2 to control up
to 1,000ML/day, and Dam183 road bridge, regulator, and
Environmental mitigation
Lake Nearie Nature Reserve
Measure 10
Works to facilitate fish passage at Menindee
Main Weir
fishway
No change to hydrology but fishway on Main Weir included
in costings
Measure 12
Flood protection measures for Menindee
Construction of Menindee town high flow levee bank
Constraints Management
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 118
Measure 13 Lower Darling constraints mitigation -
landholders stock and domestic & some
irrigation pump infrastructure.
Assumption holds. Works now protect and maintain
capacity of pumps during high flow events (ie : floating
suctions, on farm storage and / or groundwater options)
Constraints Management
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 119
Feature Details Basin Plan
Outcomes St
ruct
ura
l
Ad
just
ment
Measu
res
Measure 14
Acquisition of Lower Darling and Tandou
water entitlements
Purchase all Tandou entitlements and purchase or convert
Lower Darling HS entitlement.
Structural adjustment
mechanism
Chan
ges to
Opera
tin
g R
ule
s an
d A
gre
em
ents
Measure 15
Menindee System control transfer rule
(between NSW and the MDBA) and storage
drawdown sequencing
No control transfer in place – MDBA to assume full control
of Menindee on understanding 80GL Wetherell reserve is
retained for riparian demands to end of following year.
SDL supply measure
Measure 16
Broken Hill Entitlement
10,000M TWS entitlement shifted to Murray upstream
SDL supply measure
Wentworth.
Measure 17 Capacity for additional E-flows into Lake
Cawndilla
Potential use of Environmental account water to inundate
key assets in addition to natural events. Environmental mitigation
Measure 18
Improved operations of the River Murray
connected system
Proposed recalibration of the SDL Projects Pack OPLOSS
regression equation to better reflect current operating
environment
SDL supply measure
Measure 19
Lake Wetherell drying cycle
Hardwired drying cycle for Wetherell floodplain
Environmental mitigation
Measure 20 Broken Hill TWS system – alternate supply Pipeline from Murray River @ Wentworth SDL supply measure
Page 120
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Feature Details Basin Plan
Outcomes
O
ther
Measu
res Measure 21 Recognition of additional Northern basin
inflows to Menindee Lakes from Basin Plan
environmental recovery
Formally recognise the additional inflow and make callable
from a separate account
Supply measure
Measure 22 Limited temporary general security trade to
the Lower Darling subject to resource
assessment
Will be reflected in water planning rules
Basin Plan dealing rules
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 120
Scope
This RFT is to undertake a series of scoping investigations to assess the qualitative benefits and impacts of
the proposed Menindee Project. On the assumption that the outcomes of this scoping study demonstrate project
feasibility, a formal Environmental Impact Assessment (EIA) will be required. In order to ensure that this scoping
study is an independent assessment of the benefits and impacts of the proposed works, the successful
organisation for this scoping study will not be eligible to undertake the EIA.
Specifically, this scoping study comprises:
A collation and synthesis of existing information on the hydrology, ecology cultural significance
and socio-economic features of the system.
A preliminary, qualitative assessment of the potential benefits and impacts from the proposed
works to the Menindee Lakes, lower Darling River and Great Darling Anabranch.
Identification of any intolerable risks from the proposed projects and measures to mitigate
those risks.
Documentation of priority knowledge gaps to be filled in the EIS process.
Facilitation of agreement between government agencies on the future water savings and
feasibility of the proposed Menindee Project.
Draft RFT documentation for the full EIS.
Tenderers require specialist knowledge and experience in the fields of hydrology (including hydrologically
modelling), geomorphology, ecology, Aboriginal cultural heritage and economics. It would be advantageous if the
members of the tenderers team were familiar with the Menindee Lakes and the lower Darling River.
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 121
It should be noted that there will be no new field assessments or studies completed as part of this scoping
study. Where significant knowledge gaps are identified, these will be documented and prioritised for
consideration in the EIS process.
The successful tenderer will work closely with the Department of Primary Industries (DPI) and the NSW Office
of Environment and Heritage (OEH) to reach agreement on the final operating regime and associated water
savings.
Exclusions
Impacts associated with the construction of the Murray pipeline from the Murray River at Wentworth to Broken Hill
are not part of this scoping study.
Project requirements
The current proposal for Menindee Lakes will alter the hydrology of Lake Cawndilla, reinstating a drying cycle.
It will also result in changes to the hydrology of Lakes Wetherell, Menindee and Pamamaroo, with potential
effects to the other Lakes in the system and the Darling River downstream.
There have been several large scale investigations into the Menindee Lakes system, including assessments
of potential impacts of proposed water savings measures. This includes:
The Ecologically Sustainable Development Project, 2000
An Environmental Impact Statement, 2005
The Menindee Water Savings Project, Ecological Status and Scoping, 2014
It is not the intention of this consultancy to duplicate any previous work, but rather to consolidate the findings of
these various studies and update with more recent information. In addition, there is new hydrological modelling
being developed by the MDBA to assess the effects of the current proposed works and measures, which needs
to be considered when assessing potential benefits and impacts.
Task 1: Current values and condition of the Menindee Lakes system
Conduct a desktop review of existing information to describe the ecological, cultural and socio- economic
values of the Menindee Lakes system and their current condition. The following components, processes and
ecosystem services will need to be considered:
Current wetland hydrology, considering important parameters for the ecology of the system
(duration and frequency of wet and dry periods, rate of rise and fall, water depths).
Water quality, primary productivity, phytoplankton, including variability over time.
The most recent extent and condition of vegetation communities in and around the Lakes,
including identification of important or threatened species.
Aquatic fauna communities (invertebrates, fish, frogs), including important or
threatened species.
Wetland dependent mammals.
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 122
Waterbird abundance, diversity and breeding, including species that are listed under
migratory agreements and threatened species legislation.
Bushbirds that are dependent on the Lakes or the vegetation communities around the Lakes.
The importance of the Menindee Lakes to downstream aquatic ecosystems of the Lower
Darling River and Great Darling Anabranch.
Cultural heritage of the site and the broader study area (including a prediction of potential
cultural heritage implications of infrastructure works).
Socio- economic values dependent on the Menindee Lakes, Lower Darling River and Great
Darling Anabranch.
The above will be documented in a short, plain English report, which clearly identifies information sources and
critical knowledge gaps.
Task 2: Hydrological regimes under the Menindee Project
The consultant team will need to work with the MDBA to determine the likely future water regime in the Menindee
Lakes system under the proposed works and measures. This will at a minimum cover the affected Lakes
(Menindee, Pamamaroo, Cawndilla and Wetherell) and the Lower Darling River and Great Darling Anabranch.
This needs to be characterised in terms of the aspects of hydrology most important for maintaining the values
of the system:
Frequency and duration of wetting
Frequency and duration of drying
Rate of rise and fall
Magnitude of flow regimes
Connectivity between Lakes and river systems.
The hydrological outputs need to consider likely future climate with respect to rainfall, run-off and evaporation.
Task 3: Benefits and impacts of the Menindee Project
Using the outputs of Task 1 and 2, complete a qualitative assessment of the benefits and impacts of the proposed
Menindee Lakes Project. At a minimum this will need to consider:
Hydrology
Geomorphology
Water quality and primary productivity
Ecology
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 123
Cultural heritage
Socio-economic effects
Contributions to the objectives of the Basin Plan.
Where there is insufficient information to determine potential benefits and impacts, priority knowledge gaps should
be documented. Those knowledge gaps deemed critical to the successful assessment of benefits and impacts
will be described, together with a rationale for their inclusion in the EIS process. A brief description of the
methods recommended to fill each priority knowledge gaps is required.
Task 4: Risk assessment
Conduct a preliminary risk assessment to identify any “intolerable” risks, consistent with ISO 31000:2009,
Risk management – Principles and guidelines and the Standards Australia Handbook: Environmental risk
management - principles and process (HB 203-2000; Standards Australia and Standards New Zealand 2006).
Intolerable risks in this context are those where environmental and / or heritage impacts from the current
scope of works and measures are likely to threaten regulatory approval. These will be will be defined in conjunction
with DPI Water. For each intolerable risk, a description of the proposed mitigation measures and residual
risk will be provided. The effects of these mitigation measures on project costs and water savings needs to be
considered.
Task 5: Reporting
Produce a report that includes:
The requirements under State and Federal government legislation relating to environmental
and heritage approvals for each of the sites in the Menindee Lakes system likely to be
affected by the project.
The environmental, cultural and economic benefits and impacts of the proposed
Menindee Lakes Project.
Identification of intolerable risks and mitigation required to address those risks.
The impacts of recommended mitigation options on the water savings and project costs.
Identification of critical knowledge gaps and recommendations to fill those gaps to the level of
detail required for the EIS process.
Draft RFT specifications to form the basis of EIS procurement stage 2.
Task 6: Facilitation of agreement on the Menindee Lakes Project
The consultant team will need to work with several agencies at the local, State and Federal level to reach
agreement on the feasibility of the Menindee Lakes Project. Activities will include:
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 124
Working with the MDBA to produce the hydrological model outputs required to assess benefits
and impacts of the project, including:
o Modelling to inform the expected water savings to be gained from the project; and
o Modelling of likely operating regime and effects on the hydrology of the Lakes, Lower
Darling River and Great Darling Anabranch.
Facilitation of a cross agency technical advisory group/steering committee to oversee the
technical quality of the study and to:
o Reach agreement on the definition of intolerable risks
o Identify realistic mitigation options
o Determine the effects of mitigation options on the project costs and water savings.
o Reach agreement on the feasibility of the project to progress to the next stage.
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 125
EIS milestones
To be confirmed during further Phase 3 refinements.
Selection criteria
This tender will be judged on (in ascending order of importance):
Standard NSW Government contractual requirements and formats apply inclusive of public and
professional liability insurances.
Ability to work closely, continually and collaboratively with DPI Water staff, under direction and
by negotiation without variations to cost
Knowledge and understanding of ecological surveys, environmental management, floodplain
ecology, functions and processes, knowledge of arid zone river, wetland and terrestrial
ecosystems, familiarity with the Menindee Lakes System, its history, ecology and socio-economic
features.
Innovation or value adding components, including creative solutions to optimising
environmental benefit while minimising any harm to cultural heritage and cultural or ecological
systems.
Price and value for money
Experience - demonstrated experience, reliability, and successful performance by the
Respondent in undertaking similar projects.
Ability to meet timelines.
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 126
Relevant documents
Balme, J. and Hope, J., (1990). Radiocarbon dates from midden sites in the lower Darling River area of western
New South Wales. Archaeology in Oceania 25, 85-101.
Bogenhuber D. Wood D. Pay T. and Healy S., (2014). The Darling Anabranch Adaptive Management Monitoring
Program Final Report 2014. Prepared in conjunction with NSW Office of Environment and Heritage by the Murray-
Darling Freshwater Research Centre.
Brown, G.W., Cherry, K.A., Dickins, M.J., Grgat, L.M., Nelson, J.L., and B.D. Van Praagh, (2001) The terrestrial flora
and fauna of the Menindee Lakes System, New South Wales – Interpretation and Assessment, Arthur Rylah
Institute for Environmental Research, Department of Natural Resources and Environment, Heidelberg, Victoria,
Australia.
Brown, G.W., Cherry, Grgat, L.M., Nelson, and Tumino, M., (2001) The terrestrial flora and fauna of the Menindee
Lakes System, New South Wales – Literature Review, Arthur Rylah Institute for Environmental Research,
Department of Natural Resources and Environment, Heidelberg, Victoria, Australia
GHD, (2015). Menindee Water Savings Project Stages A1 and A2 - Environmental Water Needs and Water
Management Arrangements. GHD.
Gippel C. J. and Blackham D., (2002). Review of environmental impacts of flow regulation and other water resource
developments in the River Murray and Lower Darling River system. Final Report. Fluvial Systems Pty Ltd,
Stockton, to Murray-Darling Basin Commission, Canberra, ACT.
Green D. L. Shaikh M. Maini N. Cross H. and Slaven J., (1998). Assessment of environmental flow needs for the
Lower Darling River. A report to the Murray–Darling Basin Commission. NSW Land and Water Commission, Sydney.
Martin S. Witter D. and Webb C., (1994). The archaeology of Lakes Menindee and Cawndilla and the impact of
artificial water storage : a report to the NSW NPWS and the NSW Department of Water Resources. NSW
NPWS and the NSW Department of Water Resources.
Maunsell Australia Pty Ltd, (2007). Darling River Water Savings Project – Part A Report. Maunsell Australia Pty
Ltd.
MDBA Licenced under a Creative Commons Attribution 3.0 Australia Licence, (2012) Assessment of environmental
water requirements for the proposed Basin Plan: Lower Darling River System. (MDBA).
Nicol, J.M., (2004). Vegetation dynamics of the Menindee Lakes with reference to the seed bank Thesis (Ph.D.)--
School of Earth and Environmental Studies, University of Adelaide.
NSW Public Works (2015), Menindee Water Saving Optimisation Study & Concept Design, report No. DC15012 July
2015
SKM, (2010). Darling River Water Savings Project – Part B Final Report. SKM.
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 127
Taylor-Wood, E. McCormick S. Mueck S. Richardson M. and Jukic M., (2001). Vegetation/Habitat Mapping of
Inundated Areas of Menindee Lakes. Report for the Menindee Lakes Ecologically Sustainable Development
Project Steering Committee: Biosis.
URS (2005). Menindee Lakes Structural Works Project – Environmental Impact Statement, URS Australia,
Sydney, NSW.
Witter, D., (2009), Lake Bed Archaeological Survey for Menindee, Cawndilla and Pamamaroo Lakes, including
appendices, Witter Archaeology, New Zealand
Assistance provided by DPI Water
Provision of time series model outputs for ‘without development’, ‘benchmark’ and ‘draft
proposal’
Hydrological data related to flow scenarios that is held or readily accessible by DPI Water
Any reports that the Agency may have
Access and introduction to local Office of Water operational staff and provide a contact for local
knowledge regarding operations.
Description of the watering regime in the draft proposal and previously proposed watering
regimes
Australian GeoScience LIDAR mapping analysis of Lower Darling floodplain
Access to technical personnel – timeframes need to be negotiated well in advance.
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 128
APPENDIX 5 – MENINDEE PROJECT COSTINGS
TABLE 26: MEASURE 1 – ENLARGED MENINDEE REGULATOR (PRIME COSTS)
Source: NSW Public Works
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 129
TABLE 27: MEASURE 2 – MENINDEE DRAINAGE CHANNEL (PRIME COSTS)
Source: NSW Public Works
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 130
TABLE 28: MEASURE 3 – MORTON-BOOLKA REGULATOR (PRIME COSTS)
Source: NSW Public Works
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 131
TABLE 29: MEASURE 4 – OLD MENINDEE TOWN WEIR REMOVAL (PRIME COSTS)
Source: NSW Public Works
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 132
TABLE 30: MEASURE 5 – EMU LAKE OFFTAKE REGULATOR (PRIME COSTS)
Source: NSW Public Works
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 133
TABLE 31: MEASURE 6 – YARTLA LAKE OFFTAKE REGULATOR
Source: NSW Public Works
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 134
TABLE 32: MEASURE 7 – CAWNDILLA CREEK REGULATOR (PRIME COSTS)
Source: NSW Public Works
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 135
TABLE 33: MEASURE 8 – DARLING ANABRANCH OFFTAKE REGULATOR (PRIME COSTS)
Source: NSW Public Works
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 136
TABLE 34: MEASURE 9 – DARLING ANABRANCH E-FLOW REGULATOR (PRIME COSTS)
Source: NSW Public Works
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 137
TABLE 35: MEASURE 10 – MAIN WEIR FISHWAY (PRIME COSTS)
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 138
TABLE 36: MEASURE 11 – 183 DAM REGULATOR, ROAD BRIDGE & FISHWAY (PRIME COSTS)
Source: NSW Public Works
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 139
TABLE 37: MEASURE 12 – MENINDEE TOWN FLOOD PROTECTION WORKS (PRIME COSTS)
Source: NSW Public Works
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 140
TABLE 38: MEASURE 13 – LOWER DARLING CONSTRAINTS MITIGATION WORKS (PRIME COSTS)
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 141
APPENDIX 6 – ENGINEERING CONCEPT DESIGN DRAWINGS AND SPECIFICATIONS
FIGURE 18: MEASURE 1 – MENINDEE REGULATOR – AERIAL VIEW
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 142
FIGURE 19: MEASURE 1 – MENINDEE REGULATOR – SIDE VIEW
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 143
FIGURE 20: MEASURE 2 – MENINDEE CHANNEL – CROSS SECTIONS 1
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 144
FIGURE 21: MEASURE 2 – MENINDEE CHANNEL – CROSS SECTIONS 2
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 145
FIGURE 22: MEASURE 3 – MORTON-BOOLKA REGULATOR
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 146
FIGURE 23: MEASURE 8 – DARLING ANABRANCH OFFTAKE REGULATOR
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 147
APPENDIX 7 – ENVIRONMENTAL WATER NEEDS AND WATER MGMT ARRANGEMENTS
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 148
APPENDIX 8 – DETAILED PROJECT SCHEDULE
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 149
APPENDIX 9 – PROCUREMENT PLAN
EOI & ECI Process
An Expression of Interest and shortlisting process will be run in parallel to the concept design and planning
approval works. The benefit of running the EOI / ECI processes are:
Open invitation and shortlisting of capable Engineering, Procurement and Construction (EPC) companies
to proceed to the ECI and Tender phases.
Commitment of shortlisted companies to the ECI process (3 short listed companies)
Incorporation of construction industry knowledge into design requirements and tender
documents
Agreement to the project objectives, specification, operational and functional requirements
Agreement on commercial terms and conditions - limitation of qualification and exclusion and contractual
negotiations to expedite the delivery contract award process
Consolidated ‘Request for Tender’ package developed prior to RFT stage.
Tender Process and Evaluation criteria
A General Conditions of tendering and Tender Evaluation Criteria will be established prior to the
commencement of the formal Request for Tender process. These documents will guide the tender process to
ensure a fair and equitable outcome is achieved that provides the project team with a value for money solution.
The tender process (including the EOI/ECI) is be overseen by an independent Probity officer to ensure adherence
to process and procedures.
INSW Gateway 3 Process – Pre-Tender Review
A Gateway 3 process will be undertaken prior to issuing the final tender document to contractor companies
for pricing. This review confirms that a suitable Procurement Strategy is selected to meet the project objectives
within the budget and time constraints and that the project is ready to proceed to the tender stage. It is undertaken
after a discrete project has been defined and approved, but before any commitment to a procurement methodology
contracting system, or market approach.
The key checklist items for the project team to address as part of the gateway process are:
Is the specification of requirements clear and unambiguous?
Are we being realistic about our ability to achieve a successful outcome?
Can we confirm that the Business Case still meets the business need and is complete?
Have we explored all the procurement options?
Have we devised trade off criteria, contingency fund management?
Is the procurement strategy legal, robust, appropriate and understood by suppliers?
Is there a realistic project plan through to completion, with the right people allocated?
Do we have adequate financial controls, funding and resourcing? Can we confirm
funding availability for the whole project?
Are we taking the right approach to development and delivery – broken down into small
enough components?
Do we have enough commercial expertise to understand the current supplier market
capability and track record?
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 150
Are the issues relating to business change understood?
Can we confirm that funding is secured for the procurement?
Request for Tender
At the completion of the INSW Gateway Review, tender documents will issued to the selected participants
as a Request for Tender. It is anticipated the tender process will take approximately 8 - 10 weeks to complete
including the evaluation of tenders and recommendation of preferred tenderer. The recommendation report and
award of Contract will signal the completion of the Planning Phase and commencement of the Execution project
phase
Menindee Lakes Notification - Attachment A
Menindee Lakes Water Savings Project
Page 151
APPENDIX 10 – INTERIM PROJECT PROPOSAL – APRIL 2017
Menindee Lakes Notification - Attachment B
Menindee Lakes
Interim Project Proposal
Menindee Lakes Notification - Attachment B
Blackwatch Consulting Pty Ltd
37 Avenue Rd Mosman NSW 2088
0409164566
This document is and shall remain the property of Blackwatch Consulting. The document may only be used for the purpose for which it was
commissioned and in accordance with the Terms of Engagement for the commission. Unauthorised use of this document in any form
whatsoever is prohibited.
Document Status
Status Version Date Author Reviewed Date Approval
Table of contents 1 12th April 2017 BT DPI 12th April 2017
Preliminary Draft 1 18th April 2017 BT DPI - DJ 19th April 2017
Draft 2 22nd April 2017 BT BH 23rd April 2017
Draft 2.1 23rd April 2017 BT DPI 23rd April 2017
Draft 2.3 25th April 2017 BT DPI 26th April 2017
Final 2.4 26th April 2017 BH DPI 26th April 2017
Final (Amended) 2.41 1st May 2017 BH DPI - GH 1st May 2017
© Blackwatch Consulting Pty Ltd
Interim project proposal - modelling submission V2.41_FINALclean
Menindee Lakes Notification - Attachment B
1. Table of Contents
1. Table of Contents .......................................................................................................................................................... 3
2. Executive Summary ....................................................................................................................................................... 4
3. Background .................................................................................................................................................................... 6
4. Summary of Scope Changes ....................................................................................................................................... 9
5. Details of Revised Scope to inform revised modelling ........................................................................................ 13
A. Morton-Boolka Regulator ..................................................................................................................................... 13
B. Lake Menindee Drainage channel to outlet regulator ........................................................................................... 14
C. Cawndilla Creek Regulator ................................................................................................................................... 15
D. Menindee outlet regulator ..................................................................................................................................... 16
E. Lower Darling Channel capacity ........................................................................................................................... 17
F. Anabranch offtake regulator ................................................................................................................................. 17
G. Broken Hill TWS ................................................................................................................................................... 19
H. Removal of Menindee Town Weir......................................................................................................................... 20
I. Lower Darling stock and domestic supplies .......................................................................................................... 20
J. Flood protection works for Menindee town residents ............................................................................................ 21
K. Menindee Main Weir Fish Passage ...................................................................................................................... 22
L. Menindee control transfer triggers and sequencing .............................................................................................. 22
M. Broken Hill entitlement ......................................................................................................................................... 23
N. Capacity for additional Eflows into Lake Cawndilla ............................................................................................... 24
O. River Murray Improved Operations ...................................................................................................................... 25
P. Lake Wetherell (floodplain) drying cycle ............................................................................................................... 26
Q. Acquisition of Lower Darling / Tandou Entitlements .............................................................................................. 26
R. Temporary trade rules .......................................................................................................................................... 29
6. Proposed interjurisdictional governance and engagement ................................................................................ 30
7. Conclusions and next steps ....................................................................................................................................... 31
Appendix A ................................................................................................................................................................. 33
Draft Terms of Reference Menindee Lakes Water Savings Project Working Group ................................... 33
A. Establishment of the Working Group .................................................................................................................... 33
B. Role of the Working Group ................................................................................................................................... 33
C. Membership 34
D. Chair and Committee Support .............................................................................................................................. 34
E. Procedural Directions ........................................................................................................................................... 34
Menindee Lakes Notification - Attachment B
Interim project proposal - modelling submission V2.41_FINALclean
2. Executive Summary
Previous studies over a long period have focused on the need to save water at Menindee by reducing the evaporative surface area
of Menindee Lakes. Prior studies have mostly focused on increased release rates, new outlet paths and tightening up sequential
releases from the four lakes. However, the various proposals to date have failed to overcome the many constraints which limit our
capacity to capture water savings.
The current package of works proposed for Menindee builds on previous submissions and model runs but introduces some new
works and measures which address the key limitations. The package represents a more balanced approach, incorporating a wider
range of infrastructure, operations, regulatory and adjustment options which in combination will deliver greater water savings and
value for money.
In broad terms, the package now includes :-
Works to improve discharge from the Menindee Lakes system
Works to facilitate management of Lake Cawndilla, independent of Menindee Lake
Works to control losses and facilitate higher flows in the Darling below Menindee
Operating changes that complement the above works
Rule changes and structural adjustment measures which lift constraints and maximise the potential for the suite of works
to deliver larger environmental benefits
Confirmation that Broken Hill’s Town Water Supply will be secured from Murray River resources via a
direct pipeline from Wentworth
Interrelated works and measures to mitigate local environmental impacts as a result the proposed core works and
measures
Structural adjustment and strategic purchase for water users on the Lower Darling
Maximum offsets and savings are only achieved through the integrated package. Withdrawal of individual elements has implications
for other aspects of the proposal, and in some cases renders the project unviable. For example, the benefits from constructing the
enlarged Menindee outlet regulator cannot be fully realised without related works upstream (Menindee lake drainage channel) and
downstream (Menindee Town weir removal). Similarly, the institutional changes allowing removal of transfer triggers and changes
to Lake management arrangements, are only possible when high security demand on the Lakes from Broken Hill TWS, Tandou and Lower
Darling irrigators have been resolved – thus making the structural adjustment package and the Broken Hill pipeline essential for success.
The purpose of this report is to provide details of the proposed new package; a comparison of how this package relates to
previously notified Menindee proposal, recommendations in relation to the modelling approach required to capture the changes
and a governance framework for ongoing intergovernmental discussions of project refinement, focussing on those elements of
the proposal that relate to the MDB Agreement and other jurisdictions, particularly in regard to reliability and ongoing water supply
requirements. A brief analysis of key risks and issues is also provided for each element of the package.
This document outlines the key parameters of the amended Menindee supply and constraint measure. Following submission of
this interim Menindee proposal, the MDBA will be required to confirm that sufficient
Menindee Lakes Notification - Attachment B
Interim project proposal - modelling submission V2.41_FINALclean
modelling direction is provided to ensure inclusion of this proposal in the MDBA June 2017 interim advice. Following this, an
amended notification document will be developed taking into account the advice from the MDBA for BOC consideration by mid-June
2017 for the purposes of notification by 30 June 2017.
Additionally, Business Case document which addresses Phase 2 guideline requirements will also be provided at this time, which will
reflect initial input from the proposed Menindee Project SDL inter-governmental working group. Business case issue resolution and
confirmation of the proposal is anticipated to occur in mid- September 2017, to be informed by the MDBA modelling of the full
package, the Menindee Lakes Water Savings Project Intergovernmental Working Group advice and discussions of River Murray
Framework changes.
Menindee Lakes Notification - Attachment B
Interim project proposal - modelling submission V2.41_FINALclean
3. Background
The Menindee Lakes are a significant natural, cultural and economic resource for Australia. The Lakes are an integral asset in the
Murray-Darling system, encompassing areas of significant environmental and heritage importance; supplying towns and irrigation
along the Murray and Lower Darling rivers; and providing recreational amenity and tourism opportunities for the region.
The Lakes were significantly modified in the 1950’s and 1960’s to improve water availability and security for Broken Hill, irrigated
agriculture in SW NSW and for managing South Australian entitlement flows. The regulated storage system now consists of
four main interconnected lakes – three of these being modified natural depressions and one artificial lake along the main river
channel.
The Menindee operating environment is dominated by high evaporative losses, long periods of zero inflows, and significant base
salinity inputs from the Barwon-Darling system. With average evaporative losses in the order of 425 gigalitres (GL) per annum, there
have long been calls for infrastructure and operating improvements to reduce water losses.
In 2013, the Commonwealth and NSW governments agreed to further investigate a scope of infrastructure works and potential
changes to the Murray-Darling Basin Agreement, the elements of which were captured in Model Run 35 and formed the basis for the
Menindee supply and constraints proposal included in the package of measures notified in May 2016 (DPI Water, 12 May 2016)
The current proposal builds on previous investigations and proposals, now incorporating changes and additions based on issues
identified during the millennium drought and through broader stakeholder engagement. The proposal provides for an integrated
suite of infrastructure works, rules changes, operating changes, structural adjustment measures and environmental offsets which in
combination seek to maximise water savings available for Basin Plan outcomes, whilst ensuring local environmental values are not
unduly compromised. An amended notification, reflecting the new scope of this proposal, will be provided for BOC consideration by
mid-June 2017, with further amendments to be made post-notification if required. It is proposed that these changes would be
made in mid-September 2017.
Menindee Lakes Notification - Attachment B
Figure 1 – Location overview of Menindee Lakes system
Menindee Lakes Notification - Attachment B
Figure 2 – Overview of proposed works
Figure 3 – Satellite Imagery of Menindee Lakes System
Menindee Lakes Notification - Attachment B
4. Summary of Scope Changes
Proposals for the augmentation of Menindee Lakes have been around for decades but have gathered momentum in recent years
as a result of the Murray-Darling Basin Plan and the associated MOU between the Commonwealth and NSW Governments, signed in
2013.
The initial SDL modelling undertaken by the MDBA in 2013, based on works and measures proposed by NSW at that time, indicated
water savings of only 72GL for the Menindee project. The collective view of the jurisdictions was that more needed to be done to
capture a greater percentage of the well documented system losses at Menindee.
Table 1 in this Section 4 provides a reconciliation of the project elements that have been added, deleted or modified since Model
Run 35 was tabled and the supply measure notified. Section 5 of this report then provides more detail on each element of the
proposed new package.
Menindee Lakes Notification - Attachment B
Interim project proposal - modelling submission V2.41_FINALclean
Table 1 – Reconciliation of changes to the Menindee Lakes package of works and measures
Category Feature Run35 Current Proposal Basin Plan Outcomes
Infrastructure A. Morton-Boolka transfer regulator Up to 14,000 ML/d regulator No Change SDL supply measure
to control releases to and from Menindee and Cawndilla
B. Lake Menindee drainage channel to feed outlet and improve discharge
Some assumed improvement in drainage captured in outlet rating curve
Drainage channel up to 14,000 ML/d SDL supply measure
C. Cawndilla Creek Regulator
Not included
Up to 14,000 ML/d regulator
Environmental mitigation
D. Menindee outlet regulator Works to increase up to 14,000 ML/d No Change SDL supply
capacity increased from measure, and 5,000ML/d Constraints
Management
E. Increased Lower Darling channel capacity to take higher Menindee
No works included in prior submissions but assumptions made in modelling that
Two regulators to prevent escape flows into Yartla Lake and Emu Lake + bridge at
SDL supply measure, and
discharge – offtake regulators at Emu Lake and Yarta Lake
F. Anabranch offtake regulator constructed
constraints would be lifted
Works (regulator) to exclude up to 14,000 ML/d
Charlie Stone Crossing
New Anabranch diversion regulator #1 to control up to 14,000 ML/d
New Anabranch environmental Regulator #2 to control up to 1,000 ML/d, and Dam183 roadbridge, regulator, and fishway
Constraints Management SDL supply measure, and Constraints Management
Environmental mitigation Environmental mitigation Lake Nearie Nature
Reserve
Menindee Lakes Notification - Attachment B
Interim project proposal - modelling submission V2.41_FINALclean
G. Broken Hill TWS system – alternate supply
Assumed groundwater / desal supply required when HS fully restricted
Pipeline from Murray River @ Wentworth SDL supply measure
H. Old Menindee Town Weir removal to improve Menindee outlet regulator flows by reducing downstream head
No included Removal of redundant Menindee town weir
Constraints Management
I. Lower Darling landholders stock and domestic pump supplies
No inclusion of costs but assumption in modelling would be fixed
Assumption holds. Works now protect and maintain capacity of pumps during high flow events (ie : floating suctions)
Constraints Management
J. Flood protection measures for Menindee residents
K. Works to facilitate fish passage at Menindee Main Weir
Not included Construction of Menindee town high flow levee bank
Not included as no impact on modelling No change to hydrology but fishway on Main Weir included in costings
Constraints Management
L. Menindee System control transfer rule (between NSW and the MDBA) and storage drawdown sequencing
615GL/275GL triggers. Residual 275GL stored in Wetherell and Pamamaroo - No MDBA orders supplied when 275GL or less.
No control transfer in place – MDBA to assume full control of Menindee on understanding 80GL Wetherell reserve is retained for riparian demands to end of following year.
SDL supply measure
M. Broken Hill Entitlement Entitlement retained from Darling via Menindee + supplementation from groundwater
10,000 ML TWS entitlement shifted to Murray upstream Wentworth.
SDL supply measure
N. Capacity for additional Eflows into Lake Cawndilla
O. Improved operations of the River
Murray connected system
Commence Cawndilla filling only when Bourke exceeds 600GL/Mth and >3yrs return interval.
Benchmark OPLOSS regression model calibrated with data pre-2000, not recognising changes since millennium drought and underestimating Lake Vic
airspace Potential use of Env account water to inundate key assets in addition to natural events.
Proposed recalibration of the SDL Projects Pack
Menindee Lakes Notification - Attachment B
Interim project proposal - modelling submission V2.41_FINALclean
OPLOSS regression equation to better reflect current operating environment
Environmental mitigation
SDL supply measure
P. Lake Wetherell drying cycle Informal annual drying cycle to protect trees
Hardwired drying cycle for Wetherell floodplain
Environmental mitigation
Menindee Lakes Notification - Attachment B
Interim project proposal - modelling submission V2.41_FINALclean
Category Feature Run35 Current Proposal Basin Plan Outcomes
Structural adjustment
Q. Acquisition of Lower Darling and Tandou water entitlements
Pro-rata water recovery of entitlement based on Basin Plan age recovery = 9GL reduction IVT
Purchase all LD HS and Tandou entitlement and no IVT.
Structural adjustment mechanism
Additional northern basin inflow
R. Recognition of additional northern basin inflows to Menindee Lakes from Basin Plan environmental recovery
Additional water modelled as increased default shares to NSW and Victoria
Formally recognise the additional inflow and make callable from a separate account
Supply measure
Trade S. Limited temporary general security trade to the Lower Darling subject to
Not included Will be reflected in water planning rules Basin Plan dealing rules
Works measures
and
resource assessment
T. Lake Pamamaroo Drainage channel to
capture dead storage
Drainage channel in scope N/A – works removed from scope N/A
U. Penellco Channel increased capacity to service Tandou
Increased capacity to 2,000 ML/d channel and pumps
N/A - Works removed from scope N/A
Menindee Lakes Notification - Attachment B
Interim project proposal - modelling submission V2.41_FINALclean
5. Details of Revised Scope to inform revised modelling
The following chapter expands on the summary contained in Chapter 4, in order to inform the revised modelling effort. Only
those works and measured proposed to be carried forward in the revised Menindee package are included.
A. Morton-Boolka Regulator
i. Objectives
Construction of a new regulator at Morton-Boolka allows Lake Menindee to be operated independently of Lake
Cawndilla and for the lake levels to be equalised as Darling River floods approach, so that floodwaters can be captured
within either or both lakes. In effect this will reduce the average volume of water released into Cawndilla to only that
required to periodically maintain environmental values (see section N). These works are central to achieving the water
savings for the Menindee Project and therefore critical to project success.
ii. Brief Description of works (if any)
Scope includes a new regulator capable passing flows of at least half the peak inflows from Copi Hollow. Structure to
include adjacent levee banks 8 dual-leaf gates, 3m wide x 4.95m high
iii. Change from prior submissions
No change is proposed from previous modelling undertaken for Runs 35. The structure will be designed to pass flows
of up to 14,000 ML/d.
iv. Model Parameters
No additional model changes required.
v. Key assumptions, risks and issues
Key risks for this component of the package relate to environmental and heritage management and approvals.
Firstly, the preferred location of the regulator presents a significant risk of uncovering heritage artefacts and this will
make approvals more difficult and (potentially) project costs higher than normal. There is some risk the location may be
deemed unacceptable, however the draft designs and configuration have attempted to minimise disturbance where possible
to reduce this risk.
Secondly, Lake Cawndilla incorporates parts of Kinchega National Park. The upper bound of savings possible from
decommissioning Cawndilla as a regulated storage may be attenuated by a requirement
Menindee Lakes Notification - Attachment B
Interim project proposal - modelling submission V2.41_FINALclean
to periodically inundate the Lake, unless separate environmental entitlement is secured to achieve same.
Finally, as with all Menindee works, there are construction risks resulting from the potential inundation of the site, although
construction methods can overcome this risk to a large extent.
B. Lake Menindee Drainage channel to outlet regulator
i. Objectives
The inclusion of these works improves the upstream head conditions for the Lake Menindee Outlet – it will address the
issue of stored water pulling away from the outlet wall relatively early in the drawdown sequence which currently
reduces outlet capacity. It is expected that maximum flows can be extended by at least two weeks as a result of these works,
helping to capture the full benefits of related increases in outlet capacity.
These works will also enable operators to access the residual pool of water otherwise considered to be “dead storage” in
Lake Menindee – the Menindee outlet is on the high side of the bed of Lake Menindee with a substantial residual pool of
approximately 60GL.
ii. Brief Description of works (if any)
Scope involves construction of a channel bed of varying width approximately 8,991m long and up to 9m in depth.
iii. Change from prior submissions
Model Run 35 incorporated some changes to outlet rating curves however some additional work may be necessary to capture
higher flow rates at bottom end of discharges.
iv. Model Parameters
Menindee outlet discharge curves to be reviewed in light of new Public Works Hydraulic model, based on 14,000 ML/d channel
and outlet works.
v. Key assumptions, risks and issues
Key risks will include approvals and construction risk.
In the project planning stage the significant risk of uncovering heritage artefacts will prolong the approvals process
and potentially add consent conditions that increase the cost of works above comparable works in non-sensitive areas.
Construction risk results from working in the lake bed. Preliminary concept designs show substantial cost differentials
between wet and dry construction and the risk of complete demobilisation due to
Menindee Lakes Notification - Attachment B
Interim project proposal - modelling submission V2.41_FINALclean
flooding will be ever present. Furthermore, geotechnical investigations have not yet been undertaken so the risk of unsuitable
ground conditions remains until proven otherwise.
Operationally, a key risk will be maintenance of channel capacity due to likely siltation. Periodic maintenance will be
required to ensure capacity is not constrained.
In terms of key assumptions, the capacity of this channel is clearly linked to decisions in relation to the Lake Menindee outlet
capacity and subsequent downstream structures.
C. Cawndilla Creek Regulator
i. Objectives
Cawndilla Creek links Lake Menindee and Lake Cawndilla, and the area between the two lakes supports important
ecological and cultural heritage values.
The proposed new operating regime for the Lakes will substantially decrease inundation of areas downstream of the
Morton Boolka regulator, including Cawndilla Creek, Lake Eurobilli and Lake Cawndilla.
Construction of a new regulator at the offtake to Cawndilla Creek will enable operators to isolate these areas when Menindee
is draining. Additionally, if necessary it will facilitate environmental flows to the higher value assets, using held entitlement in
between events which would otherwise fill the Menindee system (typically flow events greater than 600GL/mth at Bourke).
ii. Brief Description of works (if any)
The need to consider the “wetted” ecology of Cawndilla and Menindee Lakes was identified by NSW National Parks and
Wildlife Service (NPWS) and within the report for Stages A1 and A2 on Environmental Water Needs and Water Management
Arrangements (GHD, Mar. 2015). The works are likely to form part of the consent conditions. Scope includes a regulator (incl.
adjacent levee banks 6 dual-leaf gates) 3m wide x 4.61m high.
iii. Change from prior submissions
Model Run 35 made no provision for these works. Proposed change is to construct a regulator with a capacity of up to 14,000
ML/d.
iv. Model Parameters
No additional model changes required. Held environmental entitlements/account water to be used.
Menindee Lakes Notification - Attachment B
Interim project proposal - modelling submission V2.41_FINALclean
v. Key assumptions, risks and issues
In light of issues raised during stakeholder engagement to date, the project team is anticipating that the construction of this
regulator will form part of the consent conditions for the Menindee project.
Key risks are comparable with that of the Morton-Boolka regulator, being the issues arising during the process of environment
and heritage approvals and to a lesser extent construction risks.
D. Menindee outlet regulator
i. Objectives
The objective of these works is to :-
improve the efficiency of sequential storage drawdowns
enable operators to minimise residual surface area quickly
address existing issues with piping failures and downstream channel erosion, and
remove a major operational constraint for achieving lower Murray Basin Plan flow targets.
ii. Brief Description of works (if any)
The proposal is to replace the existing limited capacity pipe outlet of approximately 5,000 ML/d maximum flow with a
more substantial gated structure capable of passing flows of up to 14,000 ML/d under low driving head conditions.
Scope includes a 14,000 ML/d structure (incl. outlet channel sections and downstream creek widening) with 5 dual-leaf gates,
3m wide x 8.15m high
iii. Change from prior submissions
Model Run 35 incorporated some changes to outlet rating curves however some additional work may be necessary to capture
the latest data from Public Works concept designs to 14,000 ML/d.
iv. Model Parameters
Menindee outlet discharge curves to be reviewed in light of new Public Works Hydraulic model, based on 14,000 ML/d channel
and outlet works.
v. Key assumptions, risks and issues
The risk profile surrounding environmental and heritage approvals compared with Morton-Boolka and Cawndilla Creek is
similar even with the level of pre-existing disturbance at the location of the works. Additionally the enlarged / realigned
channel to the Darling River traverses known sites of cultural
Menindee Lakes Notification - Attachment B
Interim project proposal - modelling submission V2.41_FINALclean
heritage significance. Construction risks remain comparable, given the new outlet regulator is being constructed in the close
vicinity (but not the exact location) of the existing structure.
E. Lower Darling Channel capacity
i. Objectives
These works will allow flows in the Darling River channel downstream of Menindee of up to 14,000 ML/d by preventing
water from escaping at key locations; Yartla Lake and Emu Lake offtakes. These works will reduce losses under managed,
high flow conditions, helping to maximise SDL offsets by allowing operators to discharge higher volumes from Menindee to
achieve environmental flow targets in the Lower Murray. The works at Charlie Stone Creek Crossing on the Talyawalka
flood plain are necessary to allow for road access during high flow events.
ii. Brief Description of works (if any)
Scope includes :
a regulator with 3 vertical lift gates, 3.5m wide x 1.5m high; and
a regulator with 1 vertical lift gate, 2.1m wide x 1.0m high; and
a road bridge over Charlie Stone Creek in the Talyawalka floodplain.
iii. Change from prior submissions
Previous submissions did not include these works although assumptions were made in Model Run 35 that channel capacity
constraints would be overcome.
iv. Model Parameters
MDBA to confirm if the loss function has already been altered to account for the impact of these works
v. Key assumptions, risks and issues
Relaxing the constraints in the Lower Darling river from 9,000 ML/d to 14,000 ML/d involves mitigating the effects of the
relaxation on landholder practices and land.
No other special risks identified other than ones already described in other works and measures.
F. Anabranch offtake regulator
i. Objectives
Existing Menindee releases to the Lower Darling are limited to 9,000 ML/d to prevent excessive losses into the Great Darling
Anabranch and to other areas along the Lower Darling River. These works will
Menindee Lakes Notification - Attachment B
Interim project proposal - modelling submission V2.41_FINALclean
enable operators to exclude higher flows from entering the Anabranch system to take advantage of increased Menindee
discharge capacity. Natural high flows will not be excluded, and the regulator will also be opened for environmental delivery
to the Anabranch which can be piggybacked onto Murray releases.
These works provide water savings, address the Constraints Management Strategy and facilitate more efficient delivery of
environmental account water to the Darling Anabranch and the nature reserve at Nearie Lake.
ii. Brief Description of works (if any)
The Anabranch works are made up of three components :
Works at the existing Anabranch regulated offtake
o a regulator with 7 dual-leaf gates, 3.65m wide x 2.4m high and
Works at the Anabranch environmental offtake. (Offtake regulator to replace current Darling Anabranch offtake)
o a regulator with 3 dual leaf gates, 2.05m wide x 3.5m high; and
o a channel bed of width 6.5m and length approx. 800m; and
o a road bridge of 4m width, dual carriage approach and giveway bay; and
Works at Dam 183 o a regulator with 4 dual leaf gates, 2.1m wide x 2.5m vertical height; and
o a roadbridge of 4m width single span; and
o a vertical slot fishway of height 2.24m
iii. Change from prior submissions
Model Run 35 assumed a single regulator upgrade to enable flows of up to 14,000 ML/d to be kept out of the current
Anabranch offtake. The default model configuration is “gates fully open” but with no flows through offtake until flows exceed
14,000 ML/d.
This current proposal includes the original proposed works and in addition a second regulator of 1,000 ML/d at the Anabranch
environmental offtake.
The two regulator configuration is required to provide efficient delivery of held environmental account water and potentially
transmission flows to the Darling Anabranch over a range of flows in the Lower Darling River.
iv. Model Parameters
Some minor refinement of the model configuration may be required to accommodate new works.
Menindee Lakes Notification - Attachment B
Interim project proposal - modelling submission V2.41_FINALclean
v. Key assumptions, risks and issues
No special risks identified other than ones already described in other works and measures.
G. Broken Hill TWS
i. Objectives
Critical to the management of Menindee Lakes in drought periods is the security of water supply for Broken Hill.
Development of an alternate supply to Broken Hill is a core component of the overall scheme as an enabling measure to
allow changes to shared management arrangements.
NSW has adopted a Murray pipeline as the alternate supply for Broken Hill. The pipeline is currently in procurement phase
with WaterNSW, with completion set for late 2018.
ii. Brief Description of works (if any)
Not applicable
iii. Change from prior submissions
Prior submissions assumed the TWS for Broken Hill would continue to be sourced via the Menindee pipeline, utilising surface
water from Weir 32 and Lake Menindee with groundwater supplementation towards the end of extreme drought sequences.
The new pipeline, with a point of offtake from the Murrray River at Wentworth, completely removes the Broken Hill high
security surface water demand from the Lakes system.
iv. Model Parameters
To model this work the Broken Hill demand should be connected to the Murray near Sunraysia and an equal sized TWS licence.
The Lower Darling licence should be deleted. This can be approximated by adding the TWS licence to NSW Sunraysia, and
scaling up the demand to have the same long term average increase as the former Broken Hill demand.
v. Key assumptions, risks and issues
Design, approvals and procurement are now well advanced with WaterNSW following early concept development by NSW
Public Works on behalf of DPI. Construction risk is not expected to be significant in light of the proposed..
Menindee Lakes Notification - Attachment B
Interim project proposal - modelling submission V2.41_FINALclean
H. Removal of Menindee Town Weir
i. Objectives
Menindee town weir on the Darling River serves no operational purpose. Town water supplies are being drawn from Weir
32 and from a dedicated groundwater bore, following recent works by WNSW. The existence of this redundant fixed crest weir
does however lift the height of the pool downstream of the Menindee Lake outlet, thereby reducing head differential and
limiting flows through the outlet. The objective of this proposal is to remove the weir and allow operators to extend the
duration of peak flows emanating from Lake Menindee outlet by up to 1 week. An additional benefit will be an improvement
in fish passage in the Darling River.
ii. Brief Description of works (if any)
Removal of original Menindee town weir assumed to comprise a 2.44m high U/S steel sheet pile, D/S timber crib structure
with rockfill infill.
iii. Change from prior submissions
This measure was not included in Run35. Its inclusion will enable the modellers to factor in an extended discharge
curve for releases from Lake Menindee.
iv. Model Parameters
Menindee outlet discharge curves to be reviewed in light of new Public Works Hydraulic model, based on 14,000 ML/d channel
and outlet works together with improved downstream head conditions.
v. Key assumptions, risks and issues
Notwithstanding the environmental benefits of weir removal, this proposal may encounter significant opposition from
Menindee residents who may place social amenity and historical value on retention of the weir. This would need to be
carefully considered in the EIS and approvals process.
I. Lower Darling stock and domestic supplies
i. Objectives
Increased flows in the Lower Darling as a result of this Menindee project will have an impact on private diversion points for
stock and domestic supplies along the river. The objective of this component of the package is to undertake works which
allow continued stock and domestic access for these landholders.
Menindee Lakes Notification - Attachment B
Interim project proposal - modelling submission V2.41_FINALclean
ii. Brief Description of works (if any)
Not applicable
iii. Change from prior submissions
Previous submissions assumed that this constraint would be resolved but no costings were provided to undertake pump
relocation works.
iv. Model Parameters
No additional change proposed to the modelling.
v. Key assumptions, risks and issues
The key concern of landholders on the Lower Darling will be riparian water security, related to the adequacy of the
proposed reserves held in Lake Wetherell. The approvals process will justifiably necessitate consultation with Lower
Darling landholders and it can be expected the issue of pump relocation will be raised in the course of these discussions
with landholders.
J. Flood protection works for Menindee town residents
i. Objectives
The intention to pass regulated high flows past Menindee to achieve lower Darling flows of up to 14,000 ML/d will
likely result in some localised flooding of Menindee residential properties. The objective with this component of the
package is to construct a levee of sufficient height and length to protect residential properties from these managed events.
ii. Brief Description of works (if any)
Flood protection for at least ten properties and access roads. Scope includes levees and access road raisings for a design
flood level at a flow of 25,900 ML/d (moderate flood level)
iii. Change from prior submissions
The prior submissions assumed higher Darling River flows but no allowance was made for works to manage the impacts of
these flows.
iv. Model Parameters
No additional change proposed to the modelling.
Menindee Lakes Notification - Attachment B
Interim project proposal - modelling submission V2.41_FINALclean
v. Key assumptions, risks and issues
There may be some slight lowering of inundation levels with the removal of the Menindee Town Weir. Further detailed survey
and analysis is required.
No further special risks identified other than those already described in other works and measures. Management of
stakeholder expectations and concerns will be critical.
K. Menindee Main Weir Fish Passage
i. Objectives
The objective of these works is to improve fish passage in the Darling River
ii. Change from Prior Submissions
Model Run 35 made no provision for these works. The proposed change is to construct a fishway at Menindee Main weir.
iii. Model Parameters
No additional change proposed to the modelling.
iv. Key assumptions, risks and issues
In light of the issues raised during stakeholder engagement to date, the project team is anticipating that the provision of
fish passage through the lakes will form part of the consent conditions for the Menindee project. The NSW Fisheries
Management Act provisions will be triggered by the works associated with this project, which will necessitate consideration
of fish passage.
L. Menindee control transfer triggers and sequencing
i. Objectives
The removal of thresholds provides MDBA with increased control of the Menindee system, helping to increase drawdown
rates, reduce evaporation, increase the overall regulated supply to the Murray and harmonise operations with Lake
Victoria. These measures enable the value of proposed infrastructure works and therefore potential SDL offsets to be
maximised.
ii. Brief Description of works (if any)
Not applicable
Menindee Lakes Notification - Attachment B
Interim project proposal - modelling submission V2.41_FINALclean
iii. Change from prior submissions
Current operating rules assume control triggers at 480GL (below which NSW resumes management of the lakes) and 640GL
(above which MDBA assumes management of the lakes ). Run35 modelling assumed a continuance of (reduced) Broken
Hill, Tandou and Lower Darling demand, thereby limiting the relaxation of these thresholds to 275GL and 615GL. It was
assumed the residual 275GL in dry years would be held in Pamamaroo and Wetherell.
The current proposal effectively removes the thresholds altogether. To enable this, it is essential to remove all TWS and
irrigation demands from the Menindee system via the provision of an alternate Broken Hill supply from the Murray and the
Lower Darling/Tandou structural adjustment package.
However, in order to protect basic landholder rights in the Lower Darling, it is further proposed that operators retain
approximately 80GL of water for riparian demands until the end of the year following evacuation of the other Lakes, with this
volume able to be held in the Lake Wetherell old channel.
iv. Model Parameters
The Model needs to be set to assume an ability to continue ordering water for the Murray until 80GL remains in Wetherell
Old Channel, after which orders will cease.
v. Key assumptions, risks and issues
Menindee and Lower Darling stakeholders have put forward the view that an 80GL reserve in Wetherell is insufficient
security for their needs. Formal consultation is yet to take place however the project can expect some local community anxiety
over operating changes which would result in more rapid and complete evacuation of the Lakes.
M.Broken Hill entitlement
i. Objectives
With interrelated works underway to construct a pipeline supply from the Murray River for Broken Hill, agreement will also
be required on the shift of water entitlements. The component of the package will establish and model the likely operating
conditions attached to the new licence.
ii. Brief Description of works (if any)
Not applicable
Menindee Lakes Notification - Attachment B
Interim project proposal - modelling submission V2.41_FINALclean
iii. Change from prior submissions
Model Run 35 assumed that Broken Hill TWS continued from the Darling via Menindee with access to groundwater during
times of surface water restriction / shortage. The current proposal assumes the entire demand is shifted to the Murray above
Wentworth confluence.
iv. Model Parameters
The model needs to remove Broken Hill demand from the Darling and create a new demand node connected to the
Murray near Sunraysia. The design pipeline capacity will be up to 37ML/d.
v. Key assumptions, risks and issues
Key risks for this component of the package will be reaching agreement on water yield and security equivalence by shifting
entitlement to the Murray.
N. Capacity for additional Eflows into Lake Cawndilla
i. Objectives
Lake Cawndilla incorporates parts of Kinchega National Park and notwithstanding the impact of historical works and
operations, the lake is a culturally and environmentally significant area. This project proposes the decommissioning of
Cawndilla for the purposes of regulated water supplies, with future filling only occurring during natural events that would
otherwise fill the Lakes. This component of the package provides the capacity to manage and protect Cawndilla cultural
and environmental values by developing a regime of managed, periodic inundation of the Lake using held entitlement.
ii. Brief Description of works (if any)
Not applicable
iii. Change from prior submissions
Modelling will assume filling of Cawndilla when Darling River flows at Bourke exceed 600GL per month and it has been three
years since the previous fill event. The change with this current proposal is to provide for watering between events using
held environmental entitlement.
iv. Model Parameters
No additional changes to the model are proposed as it is assumed that water used for these events would be sourced from
held entitlement.
Menindee Lakes Notification - Attachment B
Interim project proposal - modelling submission V2.41_FINALclean
v. Key assumptions, risks and issues
In light of the issues raised during stakeholder engagement to date, the project team is anticipating that consent conditions
will require provision of environmental flows for Lake Cawndilla or a variation of this.
O. River Murray Improved Operations
i. Objectives
Although not a direct component of this Menindee package, changes to the MDBA Monthly Simulation Model (MSM) to reflect
contemporary operations and water sharing arrangements are essential in order to capture the full extent of SDL supply
benefits from the Menindee project.
ii. Brief Description of works (if any)
Not applicable
iii. Change from prior submissions
Model Run 35 included estimates of River Murray operating losses (OPLOSS) based on a regression equation assuming
practices and seasonal conditions pre-2000. Extrapolating forward to post- drought/post-Plan conditions, it appears that
the model is overestimating OPLOSS, which manifests as higher averaging storage levels in Lake Victoria despite actual river
operations data to the contrary. The capacity to reregulate additional water emanating from this Menindee project is
intrinsically linked to the ability of operators to reregulate flows in Lake Victoria.
NSW DPI proposes that the OPLOSS regression equation be recalibrated in order to more accurately capture the new
operating paradigm and the full extent of benefits from SDL projects such as Menindee.
iv. Model Parameters
DPI understands that the MDBA is currently working on a potential recalibration of the MSM.
v. Key assumptions, risks and issues
The key risk with this issue is a failure of the modelling framework to capture the full extent of benefits arising out of key
projects such as Menindee, with associated detrimental impacts on benefit/cost ratios.
Menindee Lakes Notification - Attachment B
Interim project proposal - modelling submission V2.41_FINALclean
P. Lake Wetherell (floodplain) drying cycle
i. Objectives
The objective of this change in operations of Lake Wetherell is to improve local environmental outcomes by restoring
some of the region’s natural hydrologic profile. The Wetherell floodplain environment has deteriorated as a result of
conditions being too wet over extended periods and the situation will further decline as a result of this project unless
measures are taken. This initiative will reinstate some drying cycles more typical of natural ephemeral conditions.
ii. Brief Description of works (if any)
Not applicable
iii. Change from prior submissions
No provision was made for Wetherell drying cycles in prior submissions however this change can easily be accommodated in
operating protocols by allowing drawdown of water on the Wetherell floodplain back to the confines of the Old Channel.
iv. Model Parameters
No additional change proposed to the modelling.
v. Key assumptions, risks and issues
In light of the issues raised during stakeholder engagement to date, the project team is anticipating that consent conditions
will require provision of wetting and drying cycles for Lake Wetherell.
Q. Acquisition of Lower Darling / Tandou Entitlements
i. Objectives
There are a number of entitlement holders of various categories in the Lower Darling Water Source who will need to be
considered in the changes to the management of the lakes with the primary objective is to remove irrigation demand
from the Darling downstream of Menindee.
This in turn will reduce NSW commitment to holding upstream water reserves in the system and therefore maximise
potential water savings from the project.
Reduced use of Lake Cawndilla impacts on the gravity supply frequency to Lake Tandou. The infrastructure cost of providing
alternate pumping and channel infrastructure to supply 80 GL annually to Lake Tandou are significant. It is better value to
facilitate a cessation of irrigation on the property.
Menindee Lakes Notification - Attachment B
Interim project proposal - modelling submission V2.41_FINALclean
Additionally, Lower Darling irrigation creates system commitments which when removed will enable quicker and more
extensive evacuation of the Lakes.
ii. Brief Description of works (if any)
Not applicable
iii. Change from prior submissions
Prior submissions assumed a reduction (but continuance) of demand consistent with Basin Plan recovery targets.
The current proposal is predicated on drastically reducing licenced obligations other than basic landholder rights.
This component of the package is therefore fundamental to the success of the package.
iv. Model Parameters
This initiative should be modelled by switching off the Lake Tandou and the Lower Darling horticulture irrigation demand..
v. Key assumptions, risks and issues
Structural adjustment will require extensive negotiations with entitlement holders involved. These negotiations will take
time and potentially may trigger Just Terms Acquisition if agreements cannot be reached. Expectations management will be a
key risk in this process.
This modelling may demonstrate a small reduction in allocation liability to the remainng licence holders (anticipated
to be less than 1GL). NSW will negotiate mitigation options with affected licence holders to increase supply in non-critical
years which do not increase overall take and are consistent with the broader Menindee project outcomes.
The project can also expect community concern about the withdrawal of irrigation, particularly from Lake Tandou. Menindee
township is heavily reliant on Tandou for employment and other economic activity so the residents may be understandably
anxious about this issue.
R. Additional Northern Basin Inflows
i. Objectives
The primary objective is to provide formal recognition of additional Menindee inflows related to Basin Plan environmental
recovery in the portion of the basin.
Formally recognised additional inflow would be made callable for environmental purposes in the Lower Murray and
Darling systems.
Menindee Lakes Notification - Attachment B
Interim project proposal - modelling submission V2.41_FINALclean
Additional inflows may be the result of return flows from environmental watering actions upstream, or deliberate transfers
from northern systems to the Murray and Lower Darling and are at the discretion of future environmental water
managers.
It is expected that formally recognising the additional inflow and making it callable will improve environmental
outcomes by giving Murray environmental managers control over timing of delivery for the additional water.
ii. Brief Description of works (if any)
Not applicable
iii. Change from prior submissions
Prior submissions assumed that additional inflows were assigned equally to NSW and VIC shares consistent with the
default set by the Murray Agreement, and the additional water contributes to increased allocations across the system.
Since irrigation cannot increase, the environmental benefit will be expressed as an increase in spill volumes.
The current proposal assumes that States will make changes to the Agreement that result in the additional inflows
becoming callable in the Murray system after being recognised through a process determined by the development of
arrangements for protecting environmental flows in the Barwon- Darling.
iv. Model Parameters
This initiative should be modelled by creating equal LTCE value entitlements for NSW Murray General Security and VIC Murray
Low Reliability.
v. Key assumptions, risks and issues
Changes to the Agreement require consent by all States and it is difficult to know in advance what form of water holding
and inflow recognition will be acceptable to everyone involved. A bilateral agreement between NSW and VIC may be
required in the absence of a broader arrangement.
Further development of arrangements for protecting environmental flows in the Barwon-Darling (Phase 2 Shepherding
project)is intended to address the question of downstream recognition and delivery arrangements, but has not commenced
and is subject to Commonwealth funding.
Menindee Lakes Notification - Attachment B
Interim project proposal - modelling submission V2.41_FINALclean
S. Temporary trade rules
i. Objectives
Allowing temporary trade of water allocation into the Lower Darling system when there are sufficient reserves to supply water
orders is consistent with the Basin plan dealing rules and broader National Water Initiative agreements relating to water
trading. Whilst water will only be suitable to support opportunistic cropping, these dealing rules will enable limited
economic returns to landholders who remain in the Lower Darling without undermining the structural adjustment activities
outlined in Q below
ii. Brief Description of works (if any)
No works are required
iii. Change from prior submissions
Not explicitly included in prior submissions.
iv. Model Parameters
No additional modelling is required
v. Key assumptions, risks and issues
The key risk with allowing trade into the Lower Darling is that new water allocations could be used for permanent plantings
which cannot be sustained with periodic access to water under the proposal. These issues are likely to raise some concerns
in the process of stakeholder engagement.
Menindee Lakes Notification - Attachment B
Interim project proposal - modelling submission V2.41_FINALclean
6. Proposed interjurisdictional governance and engagement
NSW DPI Water has commenced the initial stages of providing information and briefings for the relevant jurisdictions
in relation to the Menindee Lakes project. However, consultation to date has been minimal, which reflects the need to
cooperatively develop of a conceptual proposal inclusive of relevant operational rules, modelling outputs and pathways to
amend the relevant legal instruments
NSW DPI Water is proposing a more comprehensive engagement with interjurisdictional partners in the development of the
Menindee Lakes Water Savings Project Menindee Lakes Water Savings Project and SDL Adjustment Package Business Case, as
part of the SDL Adjustment Mechanism process. This will ensure that all matters that relate to the MDB Agreement and
other jurisdictions, particularly in regard to reliability and ongoing water supply, have the ability to be fully discussed and
integrated as part of the development of a business case for submission by 30 June 2017.
However, it should be noted that the Phase 2 Business Case that will submitted as part of the 2017 notification will
represent best estimations of the Menindee Lakes Water Savings Proposal at this point in time. As the development of
the proposal progresses and further information is gained from Environmental Impact Statements and other planning
activities, NSW will continue to work with the relevant jurisdictions to update and progress the proposal.
In regards to establishing an appropriate Governance arrangement, NSW proposes the following principles to guide
engagement:
All parties commit to working collaboratively, transparently and respectfully with each other, including
acknowledging and respecting each other’s roles, responsibilities and legislative frameworks;
It is recognised that NSW, as the proponent state, has lead responsibility for progressing the Menindee project;
A working group will operate consistent with the intent of, and provisions in, the MDB Intergovernmental
Agreement;
Consistent with this, the Menindee project will be implemented in a way that delivers a triple bottom line outcome
for regional communities and the environment;
The project will also be developed within an adaptive management and outcomes based approach, which
will likely necessitate ongoing adjustments to the project to incorporate expert advice and the best available
information;
It is recognised that, a specific working group will be required to be established for the purposes of discussing
and providing advice to NSW DPI Water on issues that relating to the Menindee project that will have a
downstream impact on Victoria, South Australia and the Commonwealth;
Menindee Lakes Notification - Attachment B
Interim project proposal - modelling submission V2.41_FINALclean
NSW will work with jurisdictions to develop final terms of reference for the group by early May 2017, based on
the draft provided in Appendix A, to guide the activities and focus of the working group;
The Working Group forum will facilitate timely and open provision of information to the
relevant jurisdictions to ensure informed discussions and due consideration of issues;
Membership of the Working Group will include representatives from NSW, Victoria, South Australia and
Commonwealth Governments, and the MDBA;
The Working Group will operate in the first instance for as long as it takes to develop the details of the
Menindee project proposal to a level consistent with the other SDL projects’ final business cases, and then in a
future capacity to identify the rules or operating changes that are required to give effect to the Menindee Lakes
project proposal. This will be in a manner that gives effect to the intent of the MDB Agreement water sharing
arrangements;
This group will operate within a limited time span commencing 1 May 2017 to 30 November 2017, in line with the
proposed timeframe for the revised or new Intergovernmental Agreement regarding Basin Plan Implementation.
At this point the ongoing requirement of the working group to be reviewed by NSW DPI Water, with input from the
group to determine the need for continuance; and
NSW will manage community and stakeholder consultations on the project, but will work closely with Victoria,
South Australia and the Commonwealth on relevant communications regarding implications of the project for
each jurisdiction.
7. Conclusions and next steps
This document outlines the key parameters of the amended Menindee supply and constraints measure. NSW has worked
closely with the MDBA to provide clarity on the modelling assumptions which are required to incorporate this reshaped
proposal into the MDBA assessment framework.
Following submission of this interim Menindee proposal, the MDBA will need to confirm that sufficient modelling direction and
resources are provided to ensure inclusion of this proposal in the MDBA June 2017 interim modelling advice. An amended
notification will be developed in light of this advice for the Basin Officials’ Committee (BOC) consideration by mid-June 2017.
Preparation of a more detailed Business Case document based on the parameters outlined in this document, which
meets Phase 2 Business Case guidelines, has commenced. This document will be provided for inter-jurisdictional
consideration in mid-June 2017, ahead of the 30 June 2017 notification date. Recognising that key requirements (eg.
risk identification and mitigation, responsibility for operations and management, etc.) will not be fully understood at this
stage, it is proposed that some Phase 2 Guideline requirements will be described using the best available information,
with a process and timeline outlined for further refinement of the proposal post-30 June 2017.
The proposed Menindee Lakes Water Savings Sustainable Diversion Limit Adjustment Mechanism Project
Intergovernmental Working Group, as outlined in Appendix A will provide the necessary
Menindee Lakes Notification - Attachment B
Interim project proposal - modelling submission V2.41_FINALclean
governance framework for the agreement on those elements of the proposal which have the potential to affect the Murray
Darling Basin Agreement and other jurisdictions.
Menindee Lakes Notification - Attachment B
Interim project proposal - modelling submission V2.41_FINALclean
Appendix A
Draft Terms of Reference Menindee Lakes Water Savings Project Working Group
A. Establishment of the Working Group
The Menindee Lakes Water Savings Project Intergovernmental Working Group (the Working Group) is established to identify
inter-jurisdictional issues and jurisdictional issues associated with the project, and provide advice to NSW on such issues in
the further development of the Menindee Lakes Water Savings Project Business Case.
B. Role of the Working Group
The Working Group will provide advice to NSW as the lead jurisdiction in the development of the Menindee Lakes Water
Savings Project and has the following roles:
The Menindee IG working group will focus on specific details within this framework on implications of
MDBA June 2017 modelling;
Reconciliation milestones;
Reviewing changes to the River Murray Framework;
Processes for recognising the additional inflows to Menindee from the Northern Basin; and
Discussion of framework changes will build on the work commissioned by the MDBA.
NSW will continue to hold primary responsibility for Commonwealth and NSW regulatory approvals for the design and
construction of the proposed infrastructure changes. This will include community engagement and cultural heritage
requirements. It is likely that the project, if approved to proceed will be NSW State Significant Infrastructure. The Working
Group will need to operate within the constraints of this structure as provided by the NSW Government.
The Commonwealth will lead negotiation of the structural adjustment and strategic water entitlement purchase activities for
the Lower Darling.
Both these elements of the project development will be outside the scope of the Working Group but will need to report to
the Working Group on progress and if issues arise that will affect the broad cost benefit of the project.
.
Menindee Lakes Notification - Attachment B
Interim project proposal - modelling submission V2.41_FINALclean
C. Membership
Membership of the Working Group will include a maximum of two representatives each from NSW, Victoria and South
Australia.
NSW will Chair the Working Group as the lead jurisdiction for the Menindee Lakes Water Savings Project.
Recognising its funding role the Commonwealth Department of Agriculture and Water Resources will nominate one member.
Recognising its role in water management, the MDBA is requested to nominate two representatives to attend meetings as
observers and in the provision of advice to the working group in relation to river operations, Menindee Lakes and SDL
Adjustment Mechanism modelling, and MDB Agreement matters.
Other representation may occur at the discretion of NSW as the lead jurisdiction.
Members and alternates should be appropriately authorised to provide advice and make decisions on behalf of their
jurisdiction and/or agency.
Relevant technical staff may attend meetings and provide advice as appropriate.
D. Chair and Committee Support
TBC
E. Procedural Directions
Best endeavours will be made to reach in principle agreement on the required changes post June 2017, with discussions
extended beyond the November 2017 timeframe for agreement to the revised or new Intergovernmental Agreement for Basin
Implementation if required.
An indication of the timing for the Menindee proposal development against the 2017 Ministerial Council endorsed
Finalisation Plan is set out in Table 2 as a basis for the Working Groups activities, as part of the finalisation of the development
of the amended notification advice and Phase 2 Business Case.
Menindee Lakes Notification - Attachment B
Interim project proposal - modelling submission V2.41_FINALclean
Table 2
9 June 2017
Stage in Process Menindee Project Timeframes (proposed)
Interim Menindee proposal (Modelling) Amended Menindee Phase 2 Business Case proposal
27 April 2017
Phase 2 assessment & issue resolution, including: Mid-June 2017
Initial reconciliation milestones
Amended notification Menindee proposal
In principle agreement to scope of changes to River Murray Framework
Mid-June 2017
Agreement on IGA provisions, if required, covering
Menindee IG WG
September 2017 (BOC)
Further development of River Murray Framework
changes
Reconciliation milestones
Confirmation and further notification amendment if
required
November 2017 (MinCo)
Mid-September 2017
Final package (removal of projects) Detailed design (as part of an EIS process, including:
Consultation, cultural heritage
-
March 2020
Structural adjustment September 2020
Procurement September 2020
Construction (wet conditions) December 2022
NSW licensing and water sharing plan changes By June 2024
Agreement and implementation of processes for By 30 June 2024 recognising Northern Basin environmental water
River Murray Framework changes By June 2024
Amendment 1 to Menindee Lakes Water Saving Project Notification
Attachment C: Amendment 1 to Structural and operational changes at Menindee Lakes (NSW)
Appendix A: Evaporation loss calculation
A standard loss rate for net evaporation is applied based on monthly data from climate station at Menindee Lake for pan evaporation with a pan
factor of 0.7 and at Wentworth for monthly rainfall.
Appendix B: Summary of the modelling parameters changed to represent proposed structural and rule
changes
Overview
Proposals to improve operations at Menindee Lakes with combinations of rule changes and structural works targeted at reducing evaporation
losses from storage have been under investigation for a many years. After a number of broad ranging studies, NSW and the Commonwealth
agreed to focus the ongoing effort on the package of measures described in the MSM/Bigmod modelling scenario known as Run 35. This
project has been built on Run 35 with some additional changes to reflect the Menindee Lakes Interim Project Proposal (DPI Water, May 2017).
In this attachment, the model changes required from the SDL benchmark are documented in detail.
Morton-Boolka Regulator
This regulator allows Lake Menindee to be operated independently of Lake Cawndilla. Changes to relevant model parameters are
presented at Table 1.
Table 1: Changes to MSM parameters for representing Morton-Boolka regulator
Variable Card Benchmark Proposal Purpose
RCMMEN Card 33, Column
21-26
0.0 60.5 To represent the water level for the
crest of the regulator (mAHD)
RCMCAW Card 33, Column 27-32
0.0 60.0 To represent the trigger level
(mAHD) for Cawndilla operation rule
ICMRULE
ICMRULE Card 33, Column
33-38
0 5 To represent the hard wired
Cawndilla operational rule which
codification is available from MSM
Rev No. 929. This rule is used in
conjunction with environmental targets specified on Card 79-2
Lake Menindee enlarged release capacity and drainage channel to outlet regulator
These works will allow flows in the Darling River channel downstream of Menindee of up to 14,000 ML/d with the inclusion of works improving
the upstream head conditions for the Lake Menindee Outlet and also enabling operators to access the residual pool of water otherwise
considered to be “dead storage” in Lake Menindee. Specific model changes are implemented by revising Lake Menindee discharge rate
with/without backwater effects. The changes are made to model variable BWOutCap at MSMConstant file (MSM Rev No. 929). Figure 1 shows
an example of outlet discharge capacity when backwater is not a constraint factor.
Amendment 1 to Menindee Lakes Water Saving Project Notification
HighFlow
Figure 1: Lake Menindee outlet discharge without backwater effect
Lower Darling channel capacity and anabranch offtake regulator
These works will allow flows in the Darling River channel downstream of Menindee of up to 14,000 ML/d by preventing excessive losses into
the Great Darling Anabranch. The model has been changed to reflect less overbank flow losses due to the Anabranch offtake regulator. The
hard-wired high flow loss for the lower daring reach in MSM has been changed to reflect regulator controls as below.
𝐿 =max(0, 0.0464×(Q-DarlHighLossThres))+ 0.210×max(0, Q-max(550,DarlHighLossThres))+ 0.214×max(0, Q- 1000) − 0.445×max(0, Q-2450) − 0.150×max(0, Q-3180),
where:
𝐿HighFlow is the high flow loss,
Q is flow at Weir 32 in GL/month,
DarlHighlossthres is set to be min(darlch, AnaoffRegThres),
darlch is the channel capacity without the regulator (279 GL/m = 9,300 ML/d) and AnaoffRegThres is the
capacity with the regulator fully closed (426 GL/m = 14,000 ML/d).
In Bigmod, impacts of the regulator are modelled as flow control from Lower Darling to Anabranch depending on
opening of the regulator as per Table 2.
Table 2: Flows from Lower Darling to Anabranch
Flow at Lower Darling
(ML/d)
Anabranch flow
(ML/d)
fully
closed
fully
open
Menindee Lake discharge without backwater effects
25000
20000
15000
10000 Existing
Proposed
5000
0
49.5 51.5 53.5 55.5 57.5 59.5 61.5 63.5
Reduced Level (m) of Menindee Lake
Ou
tlet
Cap
city
of
Men
ind
ee L
ake
(ML/
d)
Amendment 1 to Menindee Lakes Water Saving Project Notification
0 0 0
9000 0 0
14000 0 1250
15000 340 1500
18000 2007 3167
19500 2840 4000
20000 3231 4391
21340 4280 5440
25080 6020 7180
29000 8840 10000
78000 51840 53000
120000 68840 70000
190000 85840 87000
Alternative supply for Broken Hill TWS
Critical to the management of Menindee Lakes in drought periods is the security of water supply for Broken Hill and its population of
approximately 20,000 people. The existing share management arrangements (480/640GL storage thresholds for ceasing and resuming shared
management of the Lakes) is already resulting in the need for contingency works to provide adequate surety for Broken Hill’s ongoing supply of
water. Any reduction to existing thresholds would require an alternate source of water to augment supply for Broken Hill to ensure adequate
security of supply.
In the modelling, it is assumed that an alternative supply is available for Broken Hill through a pipe-line infrastructure directly from Murray. To
model the alternative supply, the Broken Hill TWS entitlement has been transferred to Murray. Other relevant changes to MSM parameters are
presented at Table 3.
Table 3: Changes to MSM parameters for representing the alternative water supply for Broken Hill TWS
Variable Card Benchmark Proposal Purpose
BROKHILLMurrayPump Card 8, Column
25-30
0 1 To divert water directly from Murray
US Lake Victoria
nummonthsproj Card 97, Column
1-2
18 -1 To indicate that the resource
assessment should cease to forecast
18 months into the future, and
instead project to the end of the
current water year to supply existing
allocation commitments
Changes to Shared Management Thresholds
The removal of the thresholds used for the Benchmark (480 GL/640 GL) provides MDBA with increased control of the Menindee system, helping
to increase drawdown rates, reduce evaporation, increase the overall regulated supply to the Murray and harmonise operations with Lake
Victoria.
Amendment 1 to Menindee Lakes Water Saving Project Notification
Relevant changes to MSM parameters are presented at Table 4.
Table 4: Changes to MSM parameters for representing shared management thresholds
Variable Card Benchmark Proposal Purpose
RMLDDD Card 42, Column
1-6
480 80 To represent the NSW reserve in the
lakes when the system is draining
WETPAMMDBA Card 42, Column 13-18
0 80 To represent the volume in
Wetherell & Pamamaroo that is not
available for MDBA supply
RMLDFIL Card 43, Column
1-6
640 80 To represent the NSW reserve in the
lakes when the system is filling
Lake Cawndilla Environmental Operation
At present, Lake Cawndilla is operated to meet water conservation objectives, which means that the lake will typically fill to a high level during
wet periods, and then be held for a period of time until system demands gradually empty the lake over a few years.
This has heavily modified the natural state of the lake, creating an artificial vegetation ring around the top of the lake, at a higher level
than under natural conditions.
Following consideration of a number of options, the modelled NSW proposal is to fill Lake Cawndilla to maximum surcharge level, when there is
a major high flow event (i.e. when Burke flow > 600 GL/m) in the Barwon-Darling and more than 3yrs since the last surcharge event, hold the
water briefly, and then release water from the storage over a short period of time. This is expected to maintain existing vegetation higher in the
lake profile and allow a transition through to ephemeral colonising species in the lower parts of the lake.
Relevant changes to MSM parameters are summarised below.
Table 5: Changes to MSM parameters for representing Lake Cawndilla environmental operation
Variable Card Benchmark Proposal Purpose
LevlkCawnEnvThreshStart(4) Card 79-2, 0.0 60.43 Level in Lake Cawndilla that
Column 85-90 indicates an environmental filling target
lkMeniEnvTarg(4) Card 79-2, 0 36 A number of months to wait before Column 91-96 attempting a new environmental
filling event
MeniEnvDump Card 79-2, 0 2 To release water after Column 100-102 environmental filling event has
occurred via Darling Anabranch
CawndillaShare Card 79-2, 0 1 To represent that the dumped water Column 103-105 is owned equally by NSW and
Victoria
BourkTrig Card 79-2a, 0 600 To represent the monthly flow Column 1-6 (GL/m) at Bourke that must be
exceeded before an environmental fill of Lake Cawndilla is attempted
Amendment 1 to Menindee Lakes Water Saving Project Notification
Structural adjustment
There are a number of entitlement holders of various categories in the Lower Darling Water Source who will need to be considered in the
changes to the management of the lakes with the primary objective is to remove irrigation demand from the Darling downstream of
Menindee.
This in turn will reduce NSW commitment to holding upstream water reserves in the system and therefore maximise potential water savings
from the project.
Reduced use of Lake Cawndilla impacts on the gravity supply frequency to Lake Tandou. The infrastructure cost of providing alternate
pumping and channel infrastructure to supply 80 GL annually to Lake Tandou are significant. It is better value to facilitate a cessation of
irrigation on the property.
Additionally, Lower Darling irrigation creates system commitments which when removed will enable quicker and more extensive
evacuation of the Lakes.
The enhanced Menindee project is predicated on reducing or removing high security licence obligations and some targeted general security
entitlements in the Lower Darling. To reflect this in the model, all irrigation entitlements for the Lake Tandou and the Lower Darling
horticulture irrigation are switched off.
Modelling approach to assess SDL adjustment
A two staged approach is used as below to assess SDL adjustment potential from this project.
1. Structural and rule changes
a. Without additional flows from North, determine the size of entitlements in Murray that can be created without
affecting third party users when the project is fully implemented.
b. The third party impacts are assessed against the Benchmark conditions.
c. The entitlements to be created are NSW Murray general security and Vic Low Reliability Water Share. The size of
entitlements will be determined so that long term yields are shared equally.
2. Northern system inflows
a. When the final package is formed, the additional flows from the Northern basin are included.
b. Additional benefits due to the increased inflows are modelled as a part of the final package assessment through
the default method as per schedule 6 of the Basin Plan.
Attachment D - Menindee Lakes Water Saving Project (NSW)
Accounting for evaporative savings For the purpose of modelling the Menindee Lakes proposal in the SDL adjustment framework in 2017, the MDBA’s approach to determining the water savings amount using the benchmark model is outlined below:
1) Extract an amount downstream of Hume Dam based on the typical pattern of irrigation demands
2) For simplicity, the extracted volume use in NSW and Victoria is based on allocation levels for NSW Murray general security entitlements
3) Total extraction in a month is attributed equally between NSW and Victoria
4) Adjust the volume of extraction until allocation and use are equivalent to a base case scenario, in which:
a) the benchmark is used, with baseline inflows to the Menindee system
b) the use of the Tandou inter-valley transfer is assigned to NSW Murray users
c) Broken Hill township water needs are supplied from Murray, through a new NSW Murray diversion with the modelled diversion from the River Murray at Wentworth.
Using this methodology, MDBA modelling shows that the project can allow a long term average of 106 GL/y to be extracted downstream of Hume Dam without adversely affecting existing water users. Representation of the project in the total SDL adjustment project package assessment used assumptions adopted for the SDL benchmark. For modelling purposes, the savings have been distributed equally between NSW and Victoria for the environment as follows:
NSW Murray (10:90 high security: general security)
Vic Murray (82:18 high reliability water share: low reliability water share).
Note:
This modelling does not bind the NSW or Victorian governments and does not represent agreement by the NSW or Victorian governments to create the entitlements as modelled, noting that changes to modelling parameters may change the determination outcome.
The enduring environmental outcomes attainable under the Menindee project (modelled by the MBDA as 106 GL LTAAY) will be provided by means agreed by all jurisdictions and the MDBA. If entitlement is created it must be based on realistic information, have no impact on reliability of existing water users and comply with all NSW and Victorian statutory requirements for the creation of new entitlement. If entitlements are created the quantum, type and location of entitlement must be reflective of the water saved. Changes to the project may require further notification amendments which would be considered by all jurisdictions via the SDL Implementation Committee and BOC. The final mechanism used to provide enduring protection of the evaporative and system loss savings from the project will be subject to further detailed investigation including modelling by MDBA plus ongoing discussion and agreement between Basin governments.
Accounting for additional northern Basin environmental inflows
For the purpose of modelling for the determination the increased northern Basin environmental flows were subject to water sharing arrangements in the Murray-Darling Basin Agreement. That is, the 50/50 sharing arrangement between NSW and Victoria that applies to all Menindee inflows.
Note:
The final mechanism used to provide enduring protection of the additional inflows for environmental benefit will be subject to ongoing discussion and agreement between Basin governments.