MCset 17.5 kV - Schneider...

71
Medium Voltage Distribution Installation instruction April 2012 Air insulated switchboard Withdrawable switchgear SF6 or vaccum technology MCset 17.5 kV

Transcript of MCset 17.5 kV - Schneider...

Medium Voltage Distribution

Installation instructionApril 2012

Air insulated switchboard Withdrawable switchgear SF6 or vaccum technology

MCset 17.5 kV

version 0707897301EN.indd 1

Contents

General 2Glossary 2Earthing switch control symbols 2Moving part control symbols 3Recommendations 3Standard tightening torques 4List of bags and accessories 4Packaging 5

Dimensionsandweights 6AD, CL-GL, VT cubicles 6Cubicle fitted with IPX1/IPX2 roofs 9DI2 cubicle 9RHB, RHC cubicles 10Transition enclosure MTP 11

Handlinginstructions 12Land packaging 12Ocean shipment packaging 12Handling using a sling 12Handling by rolling 13Storage 13

Installationandoperationrecommendation 14

Floorfinishingandcubiclefastening 15Surface condition 15Floor quality 15Description of irons and accessories 15Placing and adjusting on non earthquake resistant civil engineering works 15Placing and adjusting on earthquake resistant civil engineering works 17

Installationinstructions 19Unpacking cubicles 19Placing cubicles in a switchboard 19Coupling of cubicles 22Rack-in check 24Removing the mobile part transport fixations 24Installing the main earth connection 25Installing the electric connections of the busbars and MV cables 27Installing busbars 29Installing busbars between MTP and the MOTORPACT cubicle 33Placing MV cables on AD cubicle 36Placing MV cables on RHC cubicle 42MV cable screen earthing 46LV cable routing and connection 47Installing the tunnel 49Installing the IPX1/IPX2 roofs or anti arc IPx1/IPx2 tunnels 52Installing the tunnel end sheets 58Installing the end sheets 60Installing fans on versions 3600 A / 4000 A 63

InstallationofaFUequippedwithelectromagneticlockingoptions 64Earthing switch with electromagnetic locking 64Rack-in prevention with electromagnetic locking 65Prior to installing the front panels 65

Stepstobetakenfortestsandinspection 66Power frequency dielectric test 66

Testsonsite 67Checking and setting up the internal arcing detector 67

Index 68

2 07897301EN.inddversion 07

Open earthing switch mechanical indicator.

Operation position.

Rack-in or racked-out position.

Rack-in prevention position. Locking possible.

General

Earthingswitchcontrolsymbols

Nota:this document is available for all the units ordered from April 2012.

Glossary UF Functionnal Unit (cubicle + mobile part + Sepam)

AD Incoming / feeder cubicle

CL-GL Withdrawable line coupling cubicle

TT Measurement and busbar earthing cubicle

RHB Connection from the top by bar

RHC Connection from the top by cable

MTP Connection enclosure between an MCset cubicle and a MOTORPACT cubicle

DI Fuse switch feeder cubicle

TT Voltage transformer

TC Current transformer or current sensor

VPIS Voltage Presence Indicator System

LV Low voltage

MV Voltage class, including levels 7.2 - 12 and 17.5 kV

SMALT Earthing switch

Mobilepart

LF SF6 withdrawable circuit breaker which is used in AD and CL cubicles

Rollarc400 SF6 breaking withdrawable contactor used in AD1 cubicle

EVOLIS Vacuum circuit breaker which is used in AD and CL cubicles

CTV1 Vacuum breaking withdrawable contactor used in AD1 cubicle

OED Tool to remove/insert the mobile part from the switchgear. The tool allows to place the mobile part on the floor.

Extractiontable Tool to remove/insert the mobile part from the switchgear. The tool DOES NOT allow to place the mobile part on the floor.

version 0707897301EN.indd 3

Marking

All type of equipment installation such as lamp or light are forbidden.Installationabovetheswitchboard

Recommendations

Insertion / extraction position.

“Racked-out” position.

“Racked-in” position.

Operation position.

Position can be locked using pad lock.

Closed earthing switch mechanical indicator.

General

It is compulsory forbidden to walk on the parts with this label.

It is compulsory forbidden to remove the parts with this label when the equipment is energised.

Movingpartcontrolsymbols

4 07897301EN.inddversion 07

Switchboardpackaging

Listofbagsandaccessories

General

Applicationmethods:

The elastic washers placed on the external sides of the connections and busbars ensure better distribution of stress induced by the screw torque.

Screw TorqueinNmØ 6 13

Ø 8 28

Ø 10 50

Ø 12 75

Ø 14 120

(Nongreasedscrewsandbolts)

Standardtighteningtorques

Package(Optional) ContentTestsandinspection - Manual earthing kit

Spareparts - Fuses

Optionalaccessories - 1 busbar earthing truck- 1 phase balance testing device- 1 I and U test lead- 1 tunnel closure kit- 1 mobile part extraction tool (ERT or extraction table)

Package ContenuSwitchboardendandfixing - Switchboard end sheets

- Fixation beams- Bag of screws and bolts - Top wireway and cover

Switchboard - 2 cubicle operation cranks- 10 mm2 wire- 1 earth fishplate and seal- Civil engineering guide- Installation manual- Operating manual

Civilengineering - Cubicle fastening rails- Expansion screws- Bag of screws and bolts

version 0707897301EN.indd 5

Packaging

General

Content Cubiclepackaging

Separatepackaging

Screwsandboltsfor:- Busbar fastening (1) 2

- Busbar shims (1) 2

- Lock associated with the cubicle 1 2

- Lock unit 1 2

- Cubicle fastening on civil engineer. works 1

- Intercubicle fastening 2 1

- Coupling gaskets 2 1

Cablefastening(ADcubicle):- Flange supports 1

- Flanges 1

Cablefloor:- Bottom plates 1

- Cable support sleeves 1

- Bag of screws and bolts 1 2

- Busbar 1250 A 1 2

- Cable connection brackets 1

- Busbar covers 1 2

- Zero frequence toroids 2 1

- Busbars 2500 A, 3150 A and more 2 1

- Cable compartment 1

- Fan compartment (FU 3600 A/ 4000 A) 1

(1) in general.(2) these parts can sometimes be dispatched in a separate package.

Thecableboxesinstallationdrawingscanbeprovideduponrequest:

AD1 : AAV8094101AD2 : AAV8900201AD3 : BBV1456801.

6 07897301EN.inddversion 07

Dimensionsandweights

Dimensions AD1 AD2 AD3 CL1 CL2 CL3 TT1 TT2(2500A) (3150A)

(3600A)(4000A)

(2500A) (3150A)(3600A)(4000A)

Width(mm)L 570 700 900 900 900 570 x 2 700 x 2 900 x 2 900 x 2 900 x 2 570 700

Height**(mm)H 2300 2300 2300 2300 2445 2300 2300 2300 2300 2445 2300 2300

Depth(mm)P 1550 1550 1550 1700 1700 1550 1550 1550 1700 1700 1550 1550

Weight*(kg) 850 1000 1300 1700 1760 650 x 2 750 x 2 850 x 2 1250 x 2 1310 x 2 500 550

Weight(kg)ofVTcompartment 120 130 130 130 130 120 130 130 130 130 120 130

* Maximum fully fitted weight.** This dimension excludes cable flanges as well as any compartments placed under the cubicle.

AD,CL-GL,VTcubicles

Cubicleswith1CTperphase,internalarcingwithstandandGasExhaustversion(wall-mounted)ornointernalarcing

Boxes for 3600A / 4000A

version 0707897301EN.indd 7

Dimensionsandweights

Boxes for 3600A / 4000A

Dimensions AD1 AD2 AD3 CL1 CL2 CL3 TT1 TT2(2500A) (3150A)

(3600A)(4000A)

(2500A) (3150A)(3600A)(4000A)

Width(mm)L 570 700 900 900 900 570 x 2 700 x 2 900 x 2 900 x 2 900 x 2 570 700

Height**(mm)H 2300 2300 2300 2300 2445 2300 2300 2300 2300 2445 2300 2300

Depth(mm)P 1725 1725 1725 1725 1725 1725 1725 1725 1725 1725 1725 1725

Weight*(kg) 850 1000 1300 1700 1760 650 x 2 750 x 2 850 x 2 1250 x 2 1310 x 2 500 550

Weight(kg)ofVTcompartment 120 130 130 130 130 120 130 130 130 130 120 130

* Maximum fully fitted weight.** This dimension excludes cable flanges as well as any compartments placed under the cubicle.

AD,CL-GL,VTcubicles

Cubicleswith1CTperphase,internalarcingwithstandon4sides

8 07897301EN.inddversion 07

Dimensionsandweights

Boxes for 3600A / 4000A

Dimensions AD1 AD2 AD3(2500A) (3150A) (3600A/4000A)

Width(mm)L 570 700 900 900 900

Height**(mm)H 2300 2300 2300 2300 2445

Depth(mm)P 1725 1725 1725 1725 1725

Weight*(kg) 950 1110 1400 1800 1800

Weight(kg)ofVTcompartment 120 130 130 130 130

* Maximum fully fitted weight.** This dimension excludes cable flanges as well as any compartments placed under the cubicle.

Boxes for 3600A / 4000A

Cubicleswith2CTsperphase,internalarcingwithstandon4sides(installedinthemiddleoftheroom,nowall-mounting)

Dimensions AD1 AD2 AD3(2500A) (3150A) (3600A/4000A)

Width(mm)L 570 700 900 900 900

Height**(mm)H 2300 2300 2300 2300 2445

Depth(mm)P 1700 1700 1700 1700 1700

Weight*(kg) 900 1050 1350 1750 1810

Weight(kg)ofVTcompartment 120 130 130 130 130

* Maximum fully fitted weight.** This dimension excludes cable flanges as well as any compartments placed under the cubicle.

Cubicleswith2CTsperphase,internalarcingwithstandandGasExhaustversion(wall-mounted)ornointernalarcing

version 0707897301EN.indd 9

Dimensionsandweights

(e.g.:AD1withinternalarcingwithstandon4sides)

Rearanti-arcingcubicle,internalarcingwithstandon3or4sides

DI2cubicle

(3sides) (4sides)

Cubicle fitted with IPX1/IPX2 roofs

Dimensions DI2Internal arcing withstand on 3 sidesand no internal arcing Internal arcing withstand on 4 sides

Width(mm)L 700 700

Height(mm)H 2300 2300

Depth(mm)P 1550 1725

Weight(kg) 750 800

Dimensions AD1 IPX1 AD1 IPX2

Width(mm)L 570 570

Height(mm)H 2732 2732

Depth(mm)Ptunnel 1815 2485

10 07897301EN.inddversion 07

Dimensionsandweights

RHB,RHCcubicles Boxes for 3600A / 4000A

Cubicleswith2CTsperphase,internalarcingwithstandon4sides(installationinthemiddleoftheroom,nowall-mounting)

Boxes for 3600A / 4000A

Cubicleswith1CTperphase,internalarcingwithstandon4sides(installationinthemiddleoftheroom,nowall-mounting)

Dimensions RHB1 RHB2 RHB3(2500A) RHB3(3150A) RHB3RHC1 RHC1 RHC2 RHC2 RHC3(2500A) RHC3 RHC3(3150A)2 cables max.per phase

3 to 4 cablesper phase

2 cables max.per phase

3 to 4 cablesper phase

2 cables max.per phase

3 to 4 cablesper phase

2 cables max.per phase

(3600A)(4000A)

Width(mm)L 570 570 700 700 900 900 900 900

Height(mm)H 2300 2300 2300 2300 2300 2300 2300 2750

Depth(mm)P 2000 2275 2000 2275 2000 2275 2000 (RHB3)2275 (RHC3)

2000

Weight*(kg) 1000 1000 1150 1150 1450 1450 1850 1820

Weight(kg)ofVTcompartment 120 120 130 130 130 130 130 130

* Maximum fully fitted weight.

Dimensions RHB1 RHB2 RHB3(2500A) RHB3(3150A) RHB3RHC1 RHC1 RHC2 RHC2 RHC3(2500A) RHC3 RHC3(3150A)2 cables max.per phase

3 to 4 cablesper phase

2 cables max.per phase

3 to 4 cablesper phase

2 cables max.per phase

3 to 4 cablesper phase

2 cables max.per phase

(3600A)(4000A)

Width(mm)L 570 570 700 700 900 900 900 900

Height(mm)H 2300 2300 2300 2300 2300 2300 2300 2750

Depth(mm)P 2000 2275 2000 2275 2000 2275 2000 (RHB3)2275 (RHC3)

2000

Weight*(kg) 950 950 1100 1100 1400 1400 1800 1820

Weight(kg)ofVTcompartment 120 120 130 130 130 130 130 130

* Maximum fully fitted weight.

version 0707897301EN.indd 11

Dimensionsandweights

Thisenclosureisfactory-mountedtotherightorleftofanMCset(dependsonswitchboardconfiguration).

Dimensions MTP1250 A 2500 A 3150 A

Width(mm)L 375 375 375

Height(mm)H 2300 2300 2300

Depth(mm)P 1550 1550 1550

Weight(kg) 240 275 310

For more details see the “MOTORPACT civil engineering guide: 46032-700-07A”.

TransitionenclosureMTP(Motorpacttransitionenclosure)

12 07897301EN.inddversion 07

Landpackaging

FunctionalUnit

Oceanshipmentpackaging

Functionalunit

Handlinginstructions

Cubiclespackedbythrees

Handlingusingasling

FUwithcircuit-breaker

version 0707897301EN.indd 13

Storage

Longstorage

Storethedevicesintheiroriginalpackaging,placedondrygroundoronamaterialinsulatingitfromhumidity.

Handlingbyrolling

After long storage, clean insulating parts before operation.

Handlinginstructions

14 07897301EN.inddversion 07

Installationandoperationrecommendation

Itisstronglyadvisedtoperiodicallycarryout, (minimun every 2 years approximately),afewoperationcyclesonoperatingdevices.

Outsidenormalconditionsofuse,(between-5°Cand40°C,absenceofdust,corrosivegas,etc.),itisrecommendedtoexamine,withourSchneiderElectricservicescenter,thestepstobetaken,inordertoensurecorrectoperationoftheinstallation.

After 6 to 12 month operations, we recommend you to check the busbars and MV cable connection torque.It should be done with a calibrated torque wrench, adjust to lower torque compare to values indicated in page 4.If no issues are detected and if the busbars and cable connections haven’t been modified, it will not be necessary to do again this check.

Operationandmaintenance

1/ The necessity of correct implementationofconnections:New cold retractable or slip-on technology offers ease of installation that favours resistance over time.Their design allows them to used in polluted environments with harsh climatic conditions.

2/ Impact of the relative humidity factor:Installing a heating device is essential in climates with high relative humidity levels and major temperature differences.Ensure that draughts and / or thermal shocks are avoided in all cubicle compartments in order to avoid the creation of dew points (sources of partial discharges).

Theswitchgear’sresistancetoageinginanMVsubstationdependson3mainfactors:

The equipment must be installed in conformity with the relevant IEC standard. Outside of these normal usage conditions, we recommend contacting Schneider Electric to determine the operations to be carried out as well as their frequency according to the actual service conditions.

3/ Electrical room ventilation control:Grid size must be suited to the power dissipated in the substation. These grids must be placed exclusively in the vicinity of the transformer, in order to avoid air circulation on the LV switchboard.

In case of disassembly, the elastic contact washers must be changed and replaced by new ones supplied by Schneider Electric.

Ourservicecentreisatyourdisposalatanytime:bto diagnose the installation,bto offer, suitable maintenance operations,bto offer maintenance contracts,bto offer adaptations.

An MCset 17.5 kV Maintenance and Services guide is available. It gives practical information on:b maintaining the equipment in good operation,b ensuring that the equipment is safe during all installation, repair and service operations.DEAI03EN/ART833121DEAI03FR/ART833120

b Version 3600 A / 4000 A: We strongly recommend that you clean the ventilation grids Aand B regularly (every 2 years): A: standard grids B: grids only on RHB version.

b Afanmonitoringsystemmustbe installedwiththecubiclecontrol andmonitoringdevices. Permanentoperationofthe followingmustbeguaranteed:

Cubicles typesFans quantity

3600 A 4000 AAD3, CL3 1 2

RHB3 2 4

version 0707897301EN.indd 15

Descriptionofironsandaccessories

The floor must have a compression withstand u 33 MPa to roll the extraction tool on it without any damage.

Floorquality

Floor flatness is such that a 2 meter rule moved over all surfaces and in all directions, does not display a difference of more than 5 mm.

Surfacecondition

Placingandadjustingonnonearthquakeresistantcivilengineeringworks

Earthquakeresistantcivilengineering:- 2 iron sectionsA (length 2m) - 8 expansion pins B - 4 fastening shims C.

Standardcivilengineering:- 1 iron section A (length 2m)- 4 expansion pins B - 2 fastening shims C.

Cubiclefastening

Preparation

Drill a hole in the floor and irons.

Floor finishing andcubiclefastening

Place and fix the irons to the floor using the supplied expansion pins, screws and washers.

Cut the last iron to the required length.

Placingtheirons

Takethisequipmentfromthecivilengineeringpackageoftheswitchboardpackaging.

16 07897301EN.inddversion 07

Floor finishing andcubiclefastening

Transversaladjustment: using a the spirit level and using shims before tightening the screws.

Longitudinaladjustment: using a the water level and using shims before tightening the screws.

Tighteningirons

Donotbendtheirononinstallation.

Forthecorrectinstallationofcubicles,itisadvisedtocomplywitha tolerance of ± 0.2 cm/m and a max. gap of ± 10 mm/10m on the length of theswitchboard.

version 0707897301EN.indd 17

Floor finishing andcubiclefastening

Place and fix the irons to the floor using the supplied expansion, screws and washers.

Cut the last iron to the required length.

Placingtheirons

Preparation

Drill a hole in the floor and irons.

Placingandadjustingonearthquakeresistantcivilengineeringworks

Thispreparationremainsanexampleofanchoring.Forseismicapplications,theanchoragemustbedesignedandsizedforthegiveninstallationtakingintoaccountthesiteloads,thefloormaterialanddimensionsandtheanchoragetype.Also,aslabspacereservedattheFUisbetterthanaslabspaceoverallcivilengineering.

18 07897301EN.inddversion 07

Transversaladjustment: using a the spirit level and using shims before tightening the screws.

Longitudinaladjustment: using a the water level and using shims before tightening the screws.

Tighteningirons

Floor finishing andcubiclefastening

Donotbendtheirononinstallation.

Forthecorrectinstallationofcubicles,itisadvisedtocomplywitha tolerance of ± 0.2 cm/m and a max. gap of ± 10 mm/10m on the length of theswitchboard.

Theironsmustbeleveledverywellbecausethereisnoleveladjustementatthebackinthiscase.

version 0707897301EN.indd 19

Installationinstructions

Assembling,adjustingandfastening

Placingcubiclesinaswitchboard

Thepreparationofcubiclesmustbecarriedoutonthepremiseswheretheywillbeinstalled.

Removethe4handlinglugs(1and2).

The circuit-breakers are delivered in cubicles in a racked-out position.

Unpack the functional unit by removing the wooden columns (8 screws), then the plastic cover.

Remove the cubicle packaging.

Unpackingcubicles

Note: place switchboard cubicles according to front panel drawings and the single-line diagram.

Start by placing the cubicle located in the middle of the switchboard (except in the case of an extension of the existing switchboard) then place the cubicles on either side of it, according to the Civil Engineering Guide indications.

1bagofnonearthquakeresistantcivilengineeringscrewsandboltsn°51236072F0:

Rear adjustment accessories:A: 4 x HM12 nuts B: 2 quick cage nuts C: 5 flat washers D: 4 x (HM12x70) screws E: 2 support irons.

Front fastening accessories:F: 2 hook head bolts G: 2 fastening shimsH: rubber anti-vibration plate.

1bagofearthquakeresistantcivilengineeringscrewsandboltsn°51236075F0:

Rear fastening accessories:H: 2 hook head bolts K: 2 fastening shims.

Front fastening accessories:H: 2 hook head bolts J: 2 fastening shims.

ToavoiddamagingtheFUfrontpanelcomponents,leavetheprotectionfoaminplaceuntiltheswitchboardisintheoperationphase.

Cubicle «X» must not impede cubicle «X+1» and vis versa with respect tooveralldimensions.

Dependingontheload,ifacubicleisfoundtoberaisedafterthenextoneisinstalled,thereisariskofvibrations.

Dependingonthetypeofcivilengineering,takethefollowingfromthehardwarebags.

20 07897301EN.inddversion 07

Lift the rear of the cubicle by screwing the 2 screws to level the cubicle.

Place the lock nut D on each screw E,place washer F, then screw the actuators in the quick cage nuts C.

Place the 2 quick cage nuts C at the rear of the cubicle, from underneath the cubicle.

Position the support steel shim A and the rubber anti-vibration shimBat the rear of the cubicle from the maintenance space.

Theoperationsdescribedhereafter,mustonlybecarriedoutoncethecubicleispositionedoncivilengineeringworks.

Adjustingcubiclesonstandardcivilengineeringworks

Placement of the cubicle by rolling.

Note: placing can be carried out by lifting or rolling.

Placingabovethemaintenancespace

Installationinstructions

Donotremoveanypartofthecubicle.

Cubicle «X» must not impede cubicle «X+1» and vis versa with respect tooveralldimensions.

Dependingontheload,ifacubicleisfoundtoberaisedafterthenextoneisinstalled,thereisariskofvibrations.

version 0707897301EN.indd 21

Installationinstructions

Place the screws at the front of the cubicle and tighten them.

Pick from the two hardware bags.

Place the screws at the rear of the cubicle and tighten them.

Pick from the two hardware bags.

Note: if the cubicle is provided with VT’s, they must be removed, refer to the operating manual (07897302), the chapter on “Instructionsforaccesstotheinteriorofacubicle”.

Fasteningtotheflooroneearthquakeresistantcivilengineeringworks

Place the screws at the front of the cubicle and tighten them.

Pick from the hardware bag.

Note: if the cubicle is provided with VT’s, they must be removed, refer to the operating manual (07897302), the chapter on “Instructionsforaccesstotheinteriorofacubicle”.

Fasteningtotheflooronstandardcivilengineeringworks

Cubicle «X» must not impede cubicle «X+1» and vis versa with respect tooveralldimensions.

Dependingontheload,ifacubicleisfoundtoberaisedafterthenextoneisinstalled,thereisariskofvibrations.

22 07897301EN.inddversion 07

Installationinstructions

Assemblingcubicles

Place the self-adhesive inter cubicle gasket along the full height of the right side of the cubicle, except on the top wireway of the cubicle.This operation is not necessary for the cubicle at the right extremity of the switchboard.

Install the second cubicle on the flloor as descrivbed before. Level the second cubicle if provided with leveling screws. Assemble the 2 cubicles together (11 fastening points).

Accesstothefasteningpoints:-Refer to chapter on ”Instructionsforaccesstotheinteriorofacubicle” in the operating manual (07897302).- See ”Removingthemobileparttransportationdevices”.

Note: for a first generation switchboard extension, consult the installation manual (07897302) “Firstgenerationswitchboardextension”.

Installingtheintercubiclegasket

Couplingofcubicles

C: assembly of HM6 x 16 screws + M6 washers and HM6 nut + M6 washers.

A: assembly of HM8 x 30 screws + M8 washers and HM8 nut.

B:assembly of HM8 x 16 screws + M8 washers and M8 cage nuts.

Theliftingringsanditsassociatedcagenutsmustberemoved.

AFLRInternalArcoption:

D: assembly of 6 screws H M8 + M8 washers + HM8 nuts + M8 washers.

version 0707897301EN.indd 23

Installationinstructions

Assembling a MOTORPACT cubicle / MTPtransitionenclosure

Left-handassembly

Right-handassembly

Implementation:

1: disassemble the transition enclosure E front and rear panel2: open the top and bottom front doors of the Motorpact3: remove the central front cover D of MOTORPACT by removing the 4 screws4: remove the rear panels of the MOTORPACT compartments: see manual (46032-700-08B), Installationguide5: install screws A, nuts B and washers E as shown.

24 07897301EN.inddversion 07

Installationinstructions

1: remove the 2 transport fixations(3 screws per fixation)

2: place the 4 screws and washers to fix the CB front cover. Tighteningtorque:8.5Nm.

3: remove the warning label:

To extract the mobile part and to open the door, refer to operating manual in the chapter on “Operatinginstructions”.The operations described here after, must only be carried out once the cubicle has been placed and secured on the floor.

Removingthemobileparttransport fixations

1: remove the 2 transport fixations(3 screws per fixation)

2: place the 4 screws and washers to fix the CB front cover. Tighteningtorque:8.5Nm.

3: remove the warning label:

1: remove the front panel screws2: extract the circuit breaker (out of the cubicle)3: remove the top fixation with access via the LV compartment4: remove the fixation circuit breaker.Tighteningtorque:8.5Nm.5: remove the warning label:

For the insertion and rack-in of the mobile part as well as to open the door, refer to the operating manual (07897302) in the chapter on“Operatinginstructions“.

Each time a cubicle is linked to another one, check that the mobile can beracked-in and locked in position properly.

Rack-incheck

Donotoperatethemobilepartsbeforeremovingthetransportfixations.

OnLFcircuitbreaker

On a ROLLARC/ CTV1 contactor

OnanEVOLIScircuit-breaker

version 0707897301EN.indd 25

Installingthemainearthconnection

Installationinstructions

1: remove the 3 transport fixations (3 screws for the lower fixation and 3 screws for the upper fixation)

2: place the 6 scrwes and washers to fix the CB front cover.Tighteningtorque:8.5Nm.

3: remove the warning label:

OnanEVOLISHPcircuitbreaker

Connect the earth bar to the building’s earth at the end of the switchboard, on the right and on the left, place the specific link with the oblong hole inside the cubicle. Tightenwithatorqueof28Nm.

Note: during the installation of the end sheets, punch the knock-outs from the sheets.

For a switchboard with a MOTORPACT cubicle at the end, refer to MOTORPACT installation manual ref. 46032-700-08.

Fromtheswitchboardtothebuilding’searth

26 07897301EN.inddversion 07

Installationinstructions

Place the bolt and tighten it. UseonlyscrewsHM8x30. 28Nmtighteningtorque.

Stick the gasket onto the cubicle sheet as shown in A.

Install the link by sliding it from cubicle 2 to cubicle 1.

Pick the self adhesive gasket from the hardware bag.

Place this gasket around the link.

The connection is located at the base of the cubicle

Note: this connection can be done during the installation of each cubicle or at the end of switchboard assembly.

Inter-cubiclesMCset-MCsetandMCset-TransitionEnclosureMTP

Inter-cubiclesTransitionenclosureMTP-Motorpact

The connection is located in the middle of the cubicle.

The transition enclosure earth link is installed at the factory. When connecting it to the Motorpact, simply screw the transition enclosure earth link onto the earth bar inside the Motorpact.

version 0707897301EN.indd 27

Installationinstructions

CubicleADandCLwithoutVT

Note: to carry out the following preliminary switchboard operations see chapter “Instructionsforaccesstotheinteriorofacubicle”.

Connectionmaintenance:

During downtime, check the connection torquewithatorquewrench.

In the case of disassembly, change the elastic washers.

Assemblies with bolts for MV and LV internal equipment.

Screwsandboltstobeused:

Class 8.8 according to standard NF E 27 005, i.e. an elastic limit, Re 630 MPa.

Generalinformation

InstallingtheelectricconnectionsofthebusbarsandMVcables

Preliminaryoperationstobecarriedout

Placingbusbars

PlacingMVcables

Extraction of the mobile part (Optional)

Close the earthing switch

Remove the front panel protective cover plates

Remove the separation plate from between the switchgear compartment (moving part) and the cable compartment.

(Optional)

Remove the busbar access sheet

Remove the manhole sheet

Preliminaryoperationstobecarriedout

Placingbusbars

PlacingMVcables

Extraction of the mobile part (Optional)

Close the earthing switch

Remove the front panel protective cover plates

Remove the fixed VTs

Remove the separation plate from between the switchgear compartment (moving part) and the cable compartment.

(Optional)

Remove the busbar access sheet

Remove the manhole sheet

CubicleADandCLwithfixedVT

28 07897301EN.inddversion 07

Installationinstructions

TTcubiclewithwithdrawableVT

TTcubiclewithfixedVTs

CubicleADandCLwithwithdrawableVT Preliminaryoperationstobecarriedout

Placingbusbars

PlacingMVcables

Extraction of the mobile par (Optional)

Withdraw the VT fuses

Close the earthing switch

Remove the front panel protective cover plates

Remove the withdrawable VTs

Remove the separation plate from between the switchgear compartment (moving part) and the cable compartment.

(Optional)

Remove the busbar access sheet

Remove the manhole sheet

Preliminaryoperationstobecarriedout

Placingbusbars

PlacingMVcables

Remove the front panel protective cover plates

Remove the fixed VTs

Remove the separation plate from between the switchgear compartment (moving part) and the cable compartment.

(Optional)

Remove the busbar access sheet

Remove the manhole sheet

Preliminaryoperationstobecarriedout

Placingbusbars

PlacingMVcables

Withdraw VT fuses

Close the earthing switch

Remove the front panel protective cover plates

Remove withdrawable VTs

Remove the separation plate from between the switchgear compartment (moving part) and the cable compartment.

(Optional)

Remove the busbar access sheet

Remove the manhole sheet

version 0707897301EN.indd 29

Installationinstructions

A: top view of busbarsB: 1 x (100 x 8) bar per phase C: nutD: conical contact washerE: flat washer F: M10 x 40 screws.

1250Abusbars

Bag of 1250 A busbars: 03407033F0.

Principleofassemblingbusbars

Place the busbar between the 2 previously assembled cubicles (refer to chapter on “Principleofassemblingbusbars”).

Tighten the fixation screws from the head side.50Nmtighteningtorque.

Repeattheseoperationseachtimeaswitchboardcubicleisplaced.

This connection is done during the installation of each cubicle.

Access the busbars through the cubicle side. If this is not possible, access through the interior of the cubicle (refer to chapter on “Instructionsforaccesstotheinteriorofacubicle”).

Retrieve; - The main busbar in the cubicle packaging- The busbar shims and hardware bag in the cubicle packaging.

Installingbusbars

30 07897301EN.inddversion 07

E: flat washerF: M10 x 55 screwsG: 3 holes shim H: 6 holes shim.

A:top view of busbarssB: 2 x (100 x 8) per phaseC: nut D: conical contact washer

2500Abusbars

Bag of 2500 A busbars: 03407034F0.

Installationinstructions

E: conical contact washerG: M10 x 85 screws.

A:top view of busbarssB: 4 riser busbarsC: 3 x (100 x 8) per phase D: nut

EvolisHP3150Abusbars Bag of 3150 A busbars: 51237530FA.

version 0707897301EN.indd 31

Installationinstructions

3150Abusbars

Bag of 3150 A busbars: 03407035F0.

E: flat washerF: M10 x 70 screwsG: 3 holes shim H: 6 holes shim.

A:top view of busbarssB: 3 x (100 x 8) per phaseC: nut D: conical contact washer

E: conical contact washerF: flat washerG: M10 x 85 screwsH: 3 holes shim.

A:top view of busbarssB: 4 riser busbarsC: 4 x (100 x 8) per phase D: nut

EvolisHP4000Abusbars Bag of 4000 A busbars: 51237530FA.

32 07897301EN.inddversion 07

A:top view of busbarsB: 4 x (100 x 8) per phaseC: nut D: conical contact washerE: flat washerF: M10 x 85 screws (special)G: 3 holes shim H: 6 holes shim.

4000Abusbars

Bag of 4000 A busbars: 51237530F0.

Installationinstructions

version 0707897301EN.indd 33

Installationinstructions

Retrieve: from the cubicle packaging, the covers.

Coverassemblyprinciple(dependingonneeds)

Close the covers on the bars.Place the half-covers on the main busbar connections.

Assemblythecoverswithclips

Note: for mounting the covers with wire ties, see page 35.

InstallingbusbarsbetweenMTPandtheMOTORPACTcubicle

1250Abusbars MOTORPACTtotheright

MOTORPACTtotheleft

A: nutB: contact washerC: flat washerD: M10 x 40 screwsE: 1 x (76 x 9,5) per phaseF: 2 holes shimG: M10 x 60 screwsH: 1 hole shim.

Note: for phase 3, the connection bar on the transition enclosure side is fastened to an insulator support.

34 07897301EN.inddversion 07

2500Abusbars

Installationinstructions

A: nutB: contact washerC: flat washerD: M10 x 55 screwsE: 2 x (76 x 9,5) per phaseF: 1 hole shimG: M10 x 70 screws.

Note: for phase 3, the connection bar on the transition enclosure side is fastened to an insulator support.

MOTORPACTtotheright

MOTORPACTtotheleft

3150Abusbars

A: nutB: contact washerC: flat washerD: M10 x 70 screwsE: 3 x (76 x 9,5) per phaseF: 1 hole shimG: M10 x 80 screws.

Note: for phase 3, the connection bar on the transition enclosure side is fastened to an insulator support.

MOTORPACTtotheright

MOTORPACTtotheleft

version 0707897301EN.indd 35

Installationinstructions

Optionalinsulatedbusbars

For cover assembly, refer to the chapter “Covermountingprinciple”.

MTP-Topviews

Assemblingthecovers:

A: install a wire tie around the busbar, inside the cover (used to block the cover in position)

B: close the cover with wire ties

C: close the cover with the clips

D: fit the entire cover assembly with clips.

Close the covers on the bars by tightening the wire ties through the notches.

Assemblyofthecoverswithwireties

Position the half-covers on the busbar connection.

36 07897301EN.inddversion 07

Successively assemble, after having installed a row of cables:

- Cable support

- Flanges

- Floor plates.

MVcablemaintenanceonADcubicle

To access the interior of a cubicle (refer to the operating manual chapter on “Instructionsforaccesstotheinteriorofacubicle ”)

A: 3 single-pole cablesB: 1 three-pole cable.

An explanation is given for all types of cables.

Retrieve: from the cubicle packaging, floor plates, cable support and hardware bag.

Generalinformation

PlacingMVcablesonADcubicle

Install them around the cables.

Refertomanufacturerinstructionsforcabletermination.

Cut cable glands according to the number and diameter of cables.

Installationinstructions

Fixtheflangesupportunderthefloor,afterplacingthecablesverticaltotheirattachmentbracket.

Reassemble bottom plates.

Fill in the openings that have not been used with uncut cable glands.

Position the cable and its grommet correctly between the sheets (A).

Fix and press the flange support against the cable under the cubicle floor.

Block the cables with half-flanges.

Makesurethatthecabledielectricinsulationdoesnotcontactanygroundedmetalpartsorotherphases.

Thegroundedmetallicsupportmustbeincontactwiththeexternalprotectivecablesheath.

Onlyqualifiedpersonnelaretoperformcableterminationsandcableinstallation.Workersmustbeawareandunderstandthehazardsinvolvedinworkingwithmediumvoltagecircuits.Neglectingfundamentalinstallationrequirementsmayleadtopersonalinjury,aswellasdamagetoelectricalequipmentorotherproperty.

version 0707897301EN.indd 37

Installationinstructions

TighteningtorqueB:50NmE:20Nm.

Removing

Surgearrester

Cableterminationheight

Installing

Carry out the operations in the reverse order of removal.

Typeofcubicle Configuration H(mm)

AD1-AD2 630 A LV toroids 621

1 set of 3 CTs 454

2 sets of 3 CTs 438

1250 A LV toroids 621

1 set of 3 CTs 454

2 sets of 3 CTs 438

AD3 1250 A 1 set of 3 CTs 477

2 sets of 3 CTs 459

2500 A 1 set of 3 CTs 428

2 sets of 3 CTs 428

3150 A 1 set of 3 CTs 404

3600 A/ 4000 A 1 set of 3 CTs 653

1: remove the surge arrester connection2: remove the insulator support.

InthecaseofanAD1orAD2cubiclefittedwithasurgearrester,accesstothecablecompartmentthroughthefrontrequiresremovalofthesurgearresterassembly.

38 07897301EN.inddversion 07

Installationinstructions

Drill a hole in the bars according to the cable heads to be connected.

Remove the bars.

AD3,1to4cablesperphase

B:50Nmtighteningtorque.

Note: assembly sequence of the bolts for the bracket: 1: M10 x 30 screws2: M10 washer 3: M10 nuts.

Drill a hole in bracket A according to the cable head to be connected.

Place and fix bracket A.

An explanation is given for one phase.

Do the same for the two other phases.

Retrieve: in the cubicle packaging, the bracket and the hardware.

Connect the cables.Applystandardtighteningtorquedependingonthediameterofthebolt.

The cable support is installed after the row of cable is installed (see chapter on “MVcablemaintenanceonADcubicle”).

Dielectrictestsmustbecarriedoutbeforeconnectingthesurgearresters.

For the connection of surge arresters, refer to chapter on “Surgearresters”.

Place and fix brackets A,CandD.

B:50Nmtighteningtorque.

Connect the cables.Applystandardtighteningtorquedependingonthediameterofthebolt.

The cable support is installed after the row of cable is installed (see chapter on “MVcablemaintenanceonADcubicle”).

Dielectrictestsmustbecarriedoutbeforeconnectingthesurgearresters.

For the connection of surge arresters, refer to chapter on “Surgearresters”.

AD1andAD2,1,2or3cablesperphase

Single-poleorthree-polecablewithouttoroidTC

version 0707897301EN.indd 39

Installationinstructions

Put back the bars with new washers. Installthecablelugsinsidethebarsandplacethescrewheadoutsidethebars.Applystandardtighteningtorquedependingonthediameterofthebolt.

A: screwB: washerC: nutD: lug.

Dielectrictestsmustbecarriedoutbeforeconnectingthesurgearresters.

For the connection of surge arresters, refer to chapter on “Surgearresters”.Tighteningtorque:B:50NmE:20Nm.

Put back the bars with new washers. Installthecablelugsinsidethebarsandplacethescrewheadoutsidethebars.Applystandardtighteningtorquedependingonthediameterofthebolt.

A: screwB: washerC: nutD: lug.

Dielectrictestsmustbecarriedoutbeforeconnectingthesurgearresters.

For the connection of surge arresters, refer to chapter on “Surgearresters”.

Tighteningtorque:B:50NmE:20Nm.

Drill a hole in the bars according to the cable heads to be connected.

Remove the bars.

AD3 3150 A/ 4000 A up to 8 cables perphase

40 07897301EN.inddversion 07

Installationinstructions

Connect the cables on the link.

Applystandardtighteningtorquedependingonthediameterofthebolt.

The cable support is installed after the row of cable is installed (see chapter on “MVcablemaintenanceonADcubicle”).

Note:assembly sequence of the bolts for the cable heads:

1: M10 x 30 screws2: M10 washers3: M10 nuts.

Place phase 2 cable in the toroid.

The explanation is given for one phase.

Do the same for the two other phases.

AD11cableperphase

Place and fix link A. 50Nmtighteningtorque.

Note: assembly sequence of the bolts for the link:1: M10 x 30 screws2: M10 washers3: M10 nuts.

Drill a hole in link A according to the cable head to be connected.

The explanation is given for one phase.

Do the same for the two other phases.

Retrieve: in package of the cubicle packaging,links A and hardware.

AD1andAD2,1or2cablesperphase

Single-polecablewithtoroidCToncubicleAD1andAD2

Place the cables through the toroids.AD21cableperphase

version 0707897301EN.indd 41

Note: assembly sequence of the bolts for the cable heads:1: M10 x 30 screws2: M10 washer3: M10 nuts.

Connect the cables.

Applystandardtighteningtorquedependingonthediameterofthebolt.

Dielectrictestsmustbecarriedoutbeforeconnectingthesurgearresters.

After having installed a row of cables, then assemble the support flange (see chapter on “MVcablemaintenanceonADcubicle”).

Installationinstructions

Place the cables through the toroids.AD22cablesperphaseAD32cablesperphase

Note: assembly sequence of the bolts for the cable heads:1: M10 x 30 screws2: M10 washer3: M10 nuts.

Connect the cables.

Applystandardtighteningtorquedependingonthediameterofthebolt.

Dielectrictestsmustbecarriedoutbeforeconnectingthesurgearresters.

After having installed a row of cables, then assemble the support flange (see chapter on “MVcablemaintenanceonADcubicle”).

42 07897301EN.inddversion 07

Installationinstructions

Successively assemble, after having installed a row of cables:

- Cable support

- Flanges

- Cables glands plates.

MVcablemaintenanceonRHCcubicle

To access the interior of a cubicle (refer to the operating manual chapter on “Instructionsforaccesstotheinteriorofacubicle ”)

A: 3 single-pole cablesB: 1 single-pole cable.

An explanation is given for all types of cables.

Retrieve: from the cubicle packaging, floor plates, cable support and hardware bag.

Generalinformation

PlacingMVcablesonRHCcubicle

Install them through the cables.

Refertomanufacturerinstructionsforcabletermination.

Cut cable glands according to the number and diameter of cables.

Fixthecablesupporttotheroofafterthecablesarewellplacedvertically.

See chapter on “MVcablemaintenanceonADcubicle”) for installation instructions.

version 0707897301EN.indd 43

Installationinstructions

Note: assembly sequence of the bolts for the bracket fixation: 1: M10 x 30 screws2: M10 washer 3: M10 nuts.

Drill a hole in bracket A according to the cable head to be connected.

Place and fix bracket A.An explanation is given for one phase.

Do the same for the two other phases.

Retrieve: in the cubicle packaging, the bracket and the hardware bag.

Place and fix brackets AandC.

B:50Nmtighteningtorque.

Connect the cables.Applystandardtighteningtorquedependingonthediameterofthebolt.

The cable support is installed after the row of cable is installed (see chapter on “MVcablemaintenanceonRHCcubicle”).

Dielectrictestsmustbecarriedoutbeforeconnectingthesurgearresters.

For the connection of surge arresters, refer to chapter on “Surgearresters”.

Single-poleorthree-polecablewithouttoroidTC

RHC31250A,RHC1andRHC21,2or3cablesperphase

An explanation is given for one phase.

Do the same for the two other phases.

Retrieve: in the cubicle packaging, the bracket and the hardware bag.

Place and fix brackets A.

B:50Nmtighteningtorque.

Connect the cables.Applystandardtighteningtorquedependingonthediameterofthebolt.

The cable support is installed after the row of cable is installed (see chapter on “MVcablemaintenanceonRHCcubicle”).

Dielectrictestsmustbecarriedoutbeforeconnectingthesurgearresters.

For the connection of surge arresters, refer to chapter on “Surgearresters”.

RHC31250AandRHC24cablesperphase

Note: assembly sequence of the bolts for the bracket fixation: 1: M10 x 30 screws2: M10 washer 3: M10 nuts.

Drill a hole in bracket A according to the cable head to be connected.

Place and fix bracket A.

44 07897301EN.inddversion 07

Installationinstructions

Put back the bars with new washers.

Installthecablelugsinsidethebarsandplacethescrewheadsoutsidethebars

Applystandardtighteningtorquedependingonthediameterofthebolt.

A: screwB: washerC: nutD: lug.

Drill a hole in the bars according to the cable heads to be connected.

Remove the bars.

RHC32500A4cablesperphase

RHC33150Aupto8cablesperphase

Put back the bars with new washers.

Installthecablelugsinsidethebarsandplacethescrewheadoutsidethebars.

Applystandardtighteningtorquedependingonthediameterofthebolt.

A: screwB: washerC: nutD: lug.

Drill a hole in the bars according to the cable heads to be connected.

Remove the bars.

version 0707897301EN.indd 45

Installationinstructions

Note: assembly sequence of the bolts for the bracket fixation: 1: M10 x 30 screws2: M10 washer 3: M10 nuts.

Drill a hole in bracket A according to the cable head to be connected.

Place and fix bracket A.An explanation is given for one phase.

Do the same for the two other phases.

Retrieve: in the cubicle packaging, the bracket and the screws and bolts.

Single-polecablewithtoroidTC

RHC11or2cablesperphase

Place and fix brackets A.

B:50Nmtighteningtorque.

Connect the cables.Installthecablelugsinsidethebarsandplacethescrewheadoutsidethebars.

The cable support is installed after the row of cable is installed.(see chapter on “MVcablemaintenanceonRHCcubicle”).

There are three ways of installing the toroids (according to the width of the cubicles):

1: 1 single-pole cable2: 1 single-pole cable3: 2 single-pole cables.

Dielectrictestsmustbecarriedoutbeforeconnectingthesurgearresters.

For the connection of surge arresters, refer to chapter on “Surgearresters”.

46 07897301EN.inddversion 07

The braid earth connection is done on the switchboard earth bars inside the maintenance space.Example: one cable per phase, 3 braids to be connected. Two cables per phase,6 braids to be connected.

In all cases, the MV cable screen braids must be insulated and go through the zero frequence toroid before connection to the switchboard’s earth.

Exampleofcableinstallation:A: 1 three-pole cable 1 cable per phase 3 earthing braids

B: 2 three-pole cables 2 cables per phase 6 earthing braids

C: 3 single-pole cables 1 cable per phase 3 earthing braids D: 6 single-pole cables 2 cables per phase 6 earthing braids.

Forzerofrequencetoroid

In all cases, the insulated MV cable screen braids must go through the toroids before connection to the switchboard main earth bar.

The braid connection is done inside the cubicle.

Forsingle-poleortwo-poletoroidCT

MVcablescreenearthing

Installationinstructions

version 0707897301EN.indd 47

Cut the cable sheet taccording to the cables size to go through it.

Install the cable glands on the sheet and the cables.

Remove the small cable sheet on the roof (4 screws) and the roof (6 screws).

Incomingcablesthroughthetop,eachcubicle

Connect the wiring to the terminal blocks.

Reassemble the roofing sheets (6 screws per sheet).

Place the power supply lead cable inside the trough. Connect the wiring from the power supply lead cable for each cubicle through the cable glands.Place back the trough.

Remove the cubicle cable troughs.Remove the roof on each cubicle (6 screws).

Incomingcablesattheendoftheswitchboard

LVcableroutingandconnection

Installationinstructions

48 07897301EN.inddversion 07

Installationinstructions

Pull the wiring and cable up to the cubicle top through the troughs.

Install the cable trough.

Connect the wires on the terminal blocks.

Reassemble the roof (6 and 4 screws per sheet).

Remove the roof and eventually the top cable sheet (6 and 4 screws).

(maximum 5 diameters 20 mm) at the base of the cable trough.

Remove the cable trough.Cut according to the number and the diameter of the cables.

Incomingcablesfromthefloor,eachcubicle

Install the cable sheet on the roof (4 screws). Connect the wires to the terminal blocks.Install the roof (6 screws).

version 0707897301EN.indd 49

Installationinstructions

Nonwallmountedantiarctunnel

Wall-mountedantiarctunnel

Installingthetunnel

A: front of the cubicleB: HM6 screwsC: HM6 screws + M6 washers and HM6 nuts.

1/ First fix the angle bracket (2) on the wall using two screws.

2/ Fix the sheet (1) onto the cubicle using four screws (B) for MCset 1 and 6 screws (B) for MCset 2 and MCset 3.

3/ Fix the roof (3) onto the sheet (1) using two screws (C) for MCset 1 and three screws (C) for MCset 2 and MCset 3.

4/ Fix the roof (3) on the angle bracket (2) using two screws (C).

5/ Fix the tunnels of each cubicle together.

A: front of the cubicleB: HM6 screwsC: HM6 screws + M6 washers and HM6 nuts.

1/ First fix the sheets (1) onto the cubicle using four screws (B) for MCset 1 and 6 screws (B) for MCset 2 and MCset 3.

2/ Fix the roof (2) onto the sheet (1) using two screws (C) for MCset 1 and three screws (C) for MCset 2 and MCset 3.

3/ Fix the tunnels of each cubicle together.

50 07897301EN.inddversion 07

Installationinstructions

Wall-mountedantiarctunnelforversions 3600 A / 4000 A

Nonwallmountedantiarctunnelfor versions 3600 A / 4000 A

Wall-mountedantiarctunnel

A: front of the cubicleB: HM6 screwsC: HM6 screws + M6 washers and HM6 nuts.

1/ First fix the angle bracket (2) on the wall using two screws.

2/ Fix the sheet (1) onto the ventilation box using four screws (B) for MCset 1 and 6 screws (B) for MCset 2 and MCset 3.

3/ Fix the roof (3) onto the sheet (1) using two screws (C) for MCset 1 and three screws (C) for MCset 2 and MCset 3.

4/ Fix the roof (3) on the angle bracket (2) using two screws (C).

5/ Fix the tunnels of each cubicle together.

A: front of the cubicleB: HM6 screwsC: HM6 screws + M6 washers and HM6 nuts.

1/ First fix the sheet (1) onto the ventilation box using four screws (B) for MCset 1 and 6 screws (B) for MCset 2 and MCset 3.

2/ Fix the roof (2) onto the sheet (1) using two screws (C) for MCset 1 and three screws (C) for MCset 2 and MCset 3.

3/ Fix the tunnels of each cubicle together.

version 0707897301EN.indd 51

Installationinstructions

InstallingatunnelonaMTPtransitionenclosure

The sheets are fixed by HM6 screws + M6 washersand HM6 nuts (A):

1/ Mount the support sheets (1) first.

2/ Mount the side panel (2).

3/ Fasten together the support sheets of each cubicle.

4/ Mount the roof (3).

5/ Mount the tunnel closing sheets in the front and rear (4).

6/ Fasten together the tunnel roofs of each cubicle.

52 07897301EN.inddversion 07

Installationinstructions

Installing the IPX1/IPX2 roofsor anti arc IPx1/IPx2 tunnels

Wall-mounted IPX1 roof

Non wall-mounted cubicle IPX1 roof

A: front of the cubicleB: HM6 screwsC: HM6 screws + M6 washers and HM6 nuts.D: HM6 screws + M6 sealing washers and HM6 nuts.

1/ First fix the angle bracket (2) on the wall using two screws.

2/ Fix the sheet (1) onto the cubicle using four screws (B) for MCset 1 and 6 screws (B) for MCset 2 and MCset 3.

3/ Fix the roof (3) onto the sheet (1) using two screws (C) for MCset 1 and three screws (C) for MCset 2 and MCset 3.

4/ Fix the roof (3) on the angle bracket (2) using two screws (C).

5/ Fix the tunnels of each cubicle together using 5 screws according to the vue (D).

A: front of the cubicleB: HM6 screwsC: HM6 screws + M6 washers and HM6 nuts.D: HM6 screws + M6 sealing washers and HM6 nuts.

1/ First fix the sheets (1) onto the cubicle using four screws (B) for MCset 1 and six screws (B) for MCset 2 and MCset 3 for each sheet.

2/ Fix the roof (2) onto the sheet (1) using two screws (C) for MCset 1 and three screws (C) for MCset 2 and MCset 3.

3/ Fix the tunnels of each cubicle together using 5 screws according to the vue (D).

version 0707897301EN.indd 53

Installationinstructions

Wall-mounted IPX1 roof for versions 3600 A / 4000 A

Non wall-mounted IPX1 roof for versions 3600 A / 4000 A

A: front of the cubicleB: HM6 screwsC: HM6 screws + M6 washers and HM6 nuts.D: HM6 screws + M6 sealing washers and HM6 nuts.

1/ First fix the angle bracket (2) on the wall using two screws.

2/ Fix the sheet (1) onto the ventilation box using four screws (B) for MCset 1 and 6 screws (B) for MCset 2 and MCset 3.

3/ Fix the roof (3) onto the sheet (1) using two screws (C) for MCset 1 and three screws (C) for MCset 2 and MCset 3.

4/ Fix the roof (3) on the angle bracket (2) using two screws (C).

5/ Fix the tunnel of each cubicle together using 5 screws according to the vue (D).

A: front of the cubicleB: HM6 screwsC: HM6 screws + M6 washers and HM6 nutsD: HM6 screws + M6 sealing washers and HM6 nuts.

1/ First fix the sheets (1) onto the ventilation box using four screws (B) for MCset 1 and six screws (B) for MCset 2 and MCset 3 for each sheet.

2/ Fix the roof (2) onto the sheet (1) using two screws (C) for MCset 1 and three screws (C) for MCset 2 and MCset 3.

3/ Fix the tunnel of each cubicle together using 5 screws according to the vue (D).

54 07897301EN.inddversion 07

Installationinstructions

IPX1 roof on a MTP transition enclosure

The sheets are fixed with HM6 screws + M6 sealing washers and HM6 nuts (A):

1/ Mount the support sheets (1) first.

2/ Mount the side panel (2).

3/ Fasten the support sheets of each cubicle together.

4/ Mount the roof (3).

5/ Mount the tunnel closing sheets to the front and rear (4).

6/ Fasten the tunnel roof of each cubicle together.

Wall-mounted IPX2 roof

A: front of the cubicleB: HM6 screwsC: HM6 screws + M6 washers and HM6 nutsD: HM6 screws + M6 sealing washers and HM6 nuts.

1/ First fix the angle bracket (2) on the wall using two screws.

2/ Fitxthe sheet (1) onto the cubicle using four screws (B) for MCset 1 and 6 screws (B) for MCset 2 and MCset 3.

3/ Fix the feet (4) onto the cubicle using two screws (B).

4/ Fix the roof (3) onto the sheet (1) using two screws (C) for MCset 1 and three screws (C) for MCset 2 and MCset 3.

5/ Fix the roof (3) on the feet (4) using two screws (C) and on the angle bracket (2) using two screws (C).

6/ Fix the tunnel of each cubicle together using 5 screws according to the vue (D).

version 0707897301EN.indd 55

Installationinstructions

Non wall-mounted IPX2 roof

A: front of the cubicleB: HM6 screwsC: HM6 screws + M6 washers and HM6 nuts.D: HM6 screws + M6 sealing washers and HM6 nuts.

1/ First fix the sheets (1) onto the cubicle using four screws (B) for MCset 1 and six screws (B) for MCset 2 and MCset 3 for each sheet.

2/ Fix the feet (4) onto the cubicle using two screws (B).

3/ Fix the roof (2) onto the sheet (1) using two screws (C) for MCset 1 and three screws (C) for MCset 2 and MCset 3.

4/ Fix the roof (2) on the feet (4) using two screws (C).

5/ Fix the tunnel of each cubicle together using 5 screws according to the vue (D).

Wall-mounted IPX2 roof for versions 3600 A / 4000 A

A: front of the cubicleB: HM6 screwsC: HM6 screws + M6 washers and HM6 nuts.D: HM6 screws + M6 sealing washers and HM6 nuts.

1/ First fix the angle bracket (2) on the wall using two screws.

2/ Fix the sheet (1) onto the ventilation box using four screws (B) for MCset 1 and 6 screws (B) for MCset 2 and MCset 3.

3/ Fix the feet (4) onto the cubicle using two screws (B).

4/ Fix the roof (3) onto the sheet (1) using two screws (C) for MCset 1 and three screws (C) for MCset 2 and MCset 3.

5/ Fix the roof (3) on the feet (4) using two screws (C) and on the angle bracket (2) using two screws (C).

6/ Fix the tunnel of each cubicle together using 5 screws according to the vue (D).

56 07897301EN.inddversion 07

Installationinstructions

IPX2 roof on a MTP transition enclosure

The sheets are fixed by HM6 screws + M6 sealing washers and HM6 nuts (A):

1/ Mount the support sheets (1) first and the feet (5).

2/ Mount the side panel (2).

3/ Fasten the support sheet of each cubicle together.

4/ Mount the roof (3).

5/ Mount the tunnel closing sheets at the front and rear (4).

6/ Fasten the tunnel roof of each cubicle together.

Non wall-mounted IPX2 roof for versions 3600 A / 4000 A

A: front of the cubicleB: HM6 screwsC: HM6 screws + M6 washers and HM6 nuts.D: HM6 screws + M6 sealing washers and HM6 nuts.

1/ First fix the sheets (1) onto the ventilation box using four screws (B) for MCset 1 and six screws (B) for MCset 2 and MCset 3 for each sheet.

2/ Fix the feet (3) onto the cubicle using two screws (B).

3/ Fix the roof (2) onto the sheet (1) using two screws (C) for MCset 1 and three screws (C) for MCset 2 and MCset 3.

4/ Fix the roof (2) on the feet (4) using two screws (C).

5/ Fix the tunnel of each cubicle together using 5 screws according to the vue (D).

version 0707897301EN.indd 57

Installationinstructions

Tunnel sheets or IPX1/IPX2 roofs forRHBcubicle

1/ Mount first the support sheets (1) at the rear first, then in the middle and the front feet (front feet are only used for IPx2 roofs) (3c).

2/ Mount the sheets (2) on the RHB duct part.

3/ Fasten the support sheet of each cubicle together.

4/ Mount the tunnel roof (3a) or the IPX1 roof (3b) or the IPX2 roof (3c).

5/ Fasten the tunnel roofs of each cubicle together.

* Ventilation boxes for version 3600 A / 4000 A.

Tunnel sheets or IPX1/IPX2 roofs forRHCcubicle

1/ Mount first the support sheets (1) at the rear first, then in the middle, and the front feet (front feet are only used for IPx2 roofs) (3c)

2/ Mount the access sheets (4).

3/ Fasten the support sheet of each cubilce together.

4/ Mount the tunnel roof (3a) or the IPX1 roof (3b) or the IPX2 roof (3c).

5/ Fasten the tunnel roofs of each cubicle together.

58 07897301EN.inddversion 07

Installationinstructions

Foranti-arctunnelsorIPx1roofs

Installingthetunnelendsheets

A: front of the cubicleB: HM6 screwsC: HM6 screws + M6 washers and HM6 nuts.

1/ First fix the sheet (1) onto the cubicle with the screws (C).

2/ Fix the sheet (1) onto the tunnel with the screws (C).

Forantiarctunnelforversion3600 A/ 4000 A

A: front of the cubicleB: HM6 screwsC: HM6 screws + M6 washers and HM6 nuts.

1/ First fixthe sheet (1) onto the cubicle with the screws (C)

2/ Fix the sheet (1) onto the tunnel with the screws (C).

version 0707897301EN.indd 59

Installationinstructions

ForIPx2roofs

A: front of the cubicleB: rear of the cubicle

The sheets are fixed with HM6 screws + M6 washersand HM6 nuts.

1/ Fix the sheet (1) onto the cubicle and onto the tunnel

2/ Fix the sheet (2) onto the tunnel feet at the front.

3/ Fix the sheet (3) onto the cubicle, the tunnel and the sheet (1).

4/ Fix the sheet (4) onto the sheet (1).

60 07897301EN.inddversion 07

Installationinstructions

Installingtheendsheets

Punch the knock-out at the panel bottom to let the earth bus to go through it (1 per panel).

Assemblingcoverpanelsofcubicleends

On the left and right end cubicles, place and screw (M8 screw) the 4 end sheet support beams.

On the left end cubicle, place the cage nuts on the sides.

For internal arc switchboards, stick the self adhesive gasket (A) along the front of the switchgear for both end sheets

Note: operations are identical for the right or left ends of the switchboard.

Makesurethatthebusbarendcoverisassembledbeforemounting

theswitchboard’sendcovers.

version 0707897301EN.indd 61

Installationinstructions

Assemble the end cover panels 1 and 2 (right and left end of the switchboard).

A: HM8 screws+ M8 washersB: HM6 screws+ M6 washers D: assembly of HM8 x 30 screws + M8 washers and HM8 nut + M8 washers.

Note: operations are identical for the right or left ends of the switchboard.

On the right end panel, place the cage nuts at the front line.

62 07897301EN.inddversion 07

Installationinstructions

D: assembly of HM8 x 30 screws + M8 washers and HM8 nut + M8 washers.

Place the top wireway closing sheet 4.Place the two screws to fix the top wireway closing sheet.

Wall-mountedswitchboard

D: assembly of HM8 x 30 screws + M8 washers + HM8 nut + M8 washers.

E: assembly of HM8 x 6 screws + M8 washers + HM8 nuts + M8 washers.

Internalarcswitchboard.

RHB

version 0707897301EN.indd 63

Installationinstructions

Installingfansonversions3600 A / 4000 A

Fasten the box using 10 screws A.

Connect the wiring in top wireway B of the cubicle.

Topview

Maintenance procedures for ventilations and insulating parts are covered in the MCset 17.5 kV Maintenance and Services Guide DEAI03F/ART833120.

Pop the 2 rivets to fix the operating handle support at the front of the end sheets.

Store the operating handle in the front end panel.

64 07897301EN.inddversion 07

FUdeliveredwiththeearthingswitchclosed

Earthingswitchwithelectromagneticlocking

Openingtheearthingswitchwithoutauxiliarysupply

InstallationofaFUequippedwithelectromagneticlockingoptions

To rack-in and rack-out the circuit breaker, the earthing switch must be operated.

At the installation of the FU, the electromagnetic locking is not yet enegised, it must be manually released in order to operate the earthing switch.

Initialstatus: - The earthing switch is closed,- Selector 4 is in the locked closed position.

Insert a screwdriver via the box hole.Disassemble the VPIS without disconnecting the wiring.

Open the earthing switch, inserting the crank in reference 5 until the mechanical indicator light changes status.

Push back and hold in place the electromagnet (A) using the screwdriver, then pull towards you and turn the selector to the right in the operation position.

Put back the VPIS.Position selector 4 in the locked open position.

version 0707897301EN.indd 65

Initialstatus:- The circuit-breaker is in the racked-out position.- The earthing switch is closed.- The front panel is disassembled to access cable connections.

The locking system is accessible as per the arrow in the drawing opposite.

Rack-inpreventionwithelectromagneticlocking

To access the cable connection compartment, circuit-breaker rack-in must be prevented.

At the installation of the FU, the electromagnetic lock is not energised, it must be manually released in order to place the front panel when the operations are complete.

Priortoinstallingthefrontpanels

If lever (A) is positioned as per figure1, locking is active and prevents installation of the front panel.

To desactivate the locking, insert a tool (screwdriver) into the hole placed under the box support and push the electromagnet rod (B).Push the lever (A) to position it as per figure2.The system is released and the front panel can be placed back.

Figure1

Figure2

InstallationofaFUequippedwithelectromagneticlockingoptions

66 07897301EN.inddversion 07

Stepstobetakenfortestsandinspection

Surgearresterconnection

Press the pushbutton ”I” to close the circuit-breaker

Rack-in the circuit breaker(refer to the operating manual).

Remove the shim.

Raise and block the door lock rod using a 55 mm U shim.

OnFUsnotconnectedtothegenerator

Place the circuit-breaker in the test position, with the door open.

DefeatingInterlocks

This procedure requires to defeat the interlocks.

It is essential to follow the sequences here after.

The insulation level of the switchgear can be tested on site. The test voltage shall be 80 % of the rated short-duration power-frequency withstand voltage of the switchgear as specified in clause 7.105 of IEC 62271-200.

This test can be carried out in one single operation.

All circuit-breakers must be racked-in, closed, with FU doors open.

All the VT’s and surge arresters must be disconnected during this test.

More over, one of the FU feeder must have its lower panel open to connect the test cable.

Powerfrequencydielectrictest

Thistestmustbeperformedbytrained&authorizedpeople.

Thisoperationmustonlybecarriedoutafterdielectrictests,andbeforetheconnectionofmediumvoltagecablestotheFU.

Placeandfixtheconnectionofeachsurgearrester.RefertothechapteronMVcableconnection.

version 0707897301EN.indd 67

Testsonsite

Checkingandsettinguptheinternalarcingdetector(1)

This operation has to be made during assembly of the tunnels (option) or during operation on the roof of the cubicle.

The internal arcing detector is located on the roof of the cubicle.To be operational, it must be in spring loaded position.

Setting up the internal arcing detector:

- Push the metal rod (1) toward the back of the cubicle,

- Hook the rod (1) on the support (2).

1: metal rod,2: support.

(1) The internal arcing detector is mounted according to the internal arcing withstand characteristics of the cubicle.

68 07897301EN.inddversion 07

Index

AAD, CL-GL, VT cubicles 6

CChecking and setting up the internal arcing detector 67Coupling of cubicles 22Cubicle fitted with IPX1/IPX2 roofs 9

DDescription of irons and accessories 15DI2 cubicle 9

EEarthing switch control symbols 2Earthing switch with electromagnetic locking 64

FFloor quality 15

GGlossary 2

HHandling by rolling 13Handling using a sling 12

IInstalling busbars 29Installing busbars between MTP and the MOTORPACT cubicle 33Installing fans on versions 3600 A / 4000 A 63Installing the end sheets 60Installing the electric connections of the busbars and MV cables 27Installing the IPX1/IPX2 roofs or anti arc IPx1/IPx2 tunnels 52Installing the main earth connection 25Installing the tunnel 49Installing the tunnel end sheets 58

LLand packaging 12List of bags and accessories 4LV cable routing and connection 47

MMoving part control symbols 3MV cable screen earthing 46

OOcean shipment packaging 12

PPackaging 5Placing and adjusting on non earthquake resistant civil engineering works 15Placing and adjusting on earthquake resistant civil engineering works 17Placing cubicles in a switchboard 19Placing MV cables on AD cubicle 36Placing MV cables on RHC cubicle 42Power frequency dielectric test 66Prior to installing the front panels 65

RRack-in check 24Rack-in prevention with electromagnetic locking 65Recommendations 3Removing the mobile part transport fixations 24RHB, RHC cubicles 10

SStandard tightening torques 4Storage 13Surface condition 15

TTransition enclosure MTP 11

UUnpacking cubicles 19

07897301EN - REV. 07

SchneiderElectricIndustriesS.A.S35 rue Joseph MonierCS 30323 92506 Rueil Malmaison Cedexwww.schneider-electric.com

954 503 439 RCS NanterreCapital social : 896 313 776 €

04/2012

0789

7301

EN

- R

EV.

07

a S

chne

ider

Ele

ctric

Indu

strie

s S

AS

– A

ll rig

hts

rese

rved

.

As standards, specifications and designs change from time to time, please ask for confirmation of the information given in this publication. Thisdocumenthasbeenprinted onecologicalpaper.

Publishing: Schneider Electric Industries SAS.Design: Profil.Printing:

SchneiderElectricgroupservicecentersaretheretoprovide:- engineering and technical assistance,- commissioning,- training,- preventive and corrective maintenance,- adaptation work,- spare parts.

CallyoursalesrepresentativewhowillputyouintouchwithyournearestSchneiderElectricgroupservicecenterordirectlycallthefollowingtelephonenumber: +33 (0)4 76 57 60 60 Grenoble France.