Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment...

45
Market design and support policies for a low carbon electricity future David Newbery Global CO 2 economics Sønderborg, Denmark 18-19 August 2009 http://www.electricitypolicy.org.uk

Transcript of Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment...

Page 1: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

Market design and support policies for

a low carbon electricity future

David Newbery

Global CO2 economics

Sønderborg, Denmark 18-19 August 2009http://www.electricitypolicy.org.uk

Page 2: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 2

Outline

• How much & what low-C electricity for 2050?

• Investment risks and Renewables Directive

• Consequences of large wind share

• Suitable market design

– Congestion management, plant operation

– Location/type of generation and nodal pricing

– Treatment of existing assets

• Support policies for RD&D

Page 3: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 3

Why low-C electricity?

• 80% GHG reduction by 2050:

– Easier to decarbonise electricity than fuel

– switch much heating, transport to electricity

• Wide range of low-C electricity

– constrained by resource base

– and cost => need for RD&D to lower cost

But government energy policies are target

driven, lack economic rationality

Page 4: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 4

Start of ETS

2020 UK’s carbon targets are challenging

183 Mt

100 Mt = 55% 2006

Almost decarbonised

what balances the system?

Page 5: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 5

How to de-

carbonise UK

MacKay’s

estimates

indicate the large

role of low-C

electricity in any

future low-C

UK-sized

economy

http://www.withouthotair.com/

Delivered “free” from the

heat pumps incl in blue part

Page 6: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 6

Delivering low-C electricity

• Hydro: limited EU resources (but pump storage)

• Nuclear: e.g. France post oil shock

• Wind: costs falling, but other challenges

• Wave/tidal: costly

• Biomass: more efficient for heat raising?

• CCS: moderately mature but expensive

• Solar PV: too expensive? Could become cheaper?

• Solar Concentrated Power in N Africa?

Page 7: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 7

Solar Concentrated Power

One Wales

(red square)

is enough to

supply all

British power

consumption

125 kWh/d/p;

yellow square

(one Germany)

could supply

all Europe’s

power

http://www.withouthotair.com/

Page 8: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 8

5 plans “that add up” for 50kWh/d/p electricitydiversity Nimby LibDem Green Economic?

http://www.withouthotair.com/

Page 9: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 9

“A plan that adds up”

Composite of

5 plans

with 35 GW

onshore and

29 GW off

shore wind

48 GW PV

50 GW CSP

45 GW nuclear

Cap cost €1,020 bn

= €17,000/hd

http://www.withouthotair.com/

Page 10: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 10

Investment in liberalised markets

• CEC presses for single electricity market

– based on market principles

– with substantially more interconnection

• Capacity margins projected to fall 2016

with LCPD => investment needed

• Transmission investment needed

– for wind, interconnection

What are the risks facing investors?

Page 11: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 11

Start of ETS

Development of existing GB gen cap

SKM’s

mid-scenario

projection

20200

10,000

20,000

30,000

40,000

50,000

60,000

70,000

80,000

90,000

100,000

110,000

2020 middle

interconnect

or

other RES

other

biomass

offshore

wind

onshore

wind

gas

nuclear

new coal

old coal

Page 12: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 12

Electricity market risks• Huge oil price volatility: $145-40/bbl

– contract price of gas linked to and lags oil

– UK gas prices 20p/th-110, now 50p/th

– coal prices $50-200/t; now $100/t

– 2nd period EUA prices € 12-30/t, now € 14/t

• Forward clean spark spread £6-9/MWh

• Forward dark green spread $15-25/MWh

Electricity prices mirror gas prices

coal and gas costs move together

Page 13: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 13

UK price movements: 2007 to 2009 in €

0

20

40

60

80

100

120

1-Jan-0

7

1-Apr-0

7

1-Jul-0

7

1-Oct

-07

1-Jan-0

8

1-Apr-0

8

1-Jul-0

8

1-Oct

-08

1-Jan-0

9

€/M

Wh

e

Electricity forward 2010 (€/MWh)

Gas cost forward (2010) + EUA

Coal cost forward (2010) + EUA

EUA price in €/tCO2

Correlation of coal+EUA on gas+EUA high at 96%

Page 14: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 14

EUA price 25 October 2004-7 August 2009

0

5

10

15

20

25

30

35

Oct-

04

Dec-

04

Apr-

05

Jul-

05

Sep-

05

Dec-

05

Mar-

06

Jun-

06

Sep-

06

Dec-

06

Mar-

07

Jun-

07

Sep-

07

Dec-

07

Mar-

08

Jun-

08

Sep-

08

Dec-

08

Mar-

09

Jun-

09

Sep-

09

Eu

ro

/t C

O2

Futures Dec 2007

OTC IndexSecond period Dec 2008

Second period Dec 2009

CER 09

start of ETS

Second period

Page 15: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 15

Source: SKM

BERR URN 08/1021

Page 16: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 16

CO2 emissions per kWh 1971-2000

0

100

200

300

400

500

600

700

800

900

1000

1970 1975 1980 1985 1990 1995 2000

gm

/kW

h

USA

Italy

UK

Europe

France

Page 17: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 17

Average annual increment to nuclear capacity

-1,000

0

1,000

2,000

3,000

4,000

5,000

1975-80 1980-85 1985-90 1990-95 1995-2000 2000-05

MW

US France Germany Sweden UK Japan

UK always modest

France delivers 50 GW nuclear 1975-90

Page 18: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 18

Equivalent increment in effective wind capacity previous

five years

0

100

200

300

400

500

600

1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005

MW

eq

uiv

ale

nt

(70

00

hrs

/yr)

Denmark Germany Spain UK

French nuclear investment

9 times high as as German

wind for 15 years

Page 19: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 19

Effective total wind capacity

0

1,000

2,000

3,000

4,000

5,000

6,000

1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008

MW

eq

uiv

ale

nt

(70

00

hrs

/yr)

Denmark Germany Spain UK

Page 20: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 20

Criteria for market design

• Foster competition and entry => efficiency

• Incentives for timely, efficient (location and

type) and adequate investment in G and T

– reflecting comparative advantage

• Reflect social cost of carbon

• allow RD&D support without distortion

• deliver efficient dispatch

• at acceptable cost to final consumers

Page 21: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 21

Implications for Europe

• European market operates as integrated whole

– efficient Europe-wide dispatch

– efficient SO/balancing across borders

• Renewables built where cheapest

– but costs share equitably

• Cost-effective interconnection as needed

– to reduce cost of intermittency

None of these currently guaranteed

Page 22: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 22

UK’s 2020 renewables target= 40% renewable ELECTRICITY (SKM mid scenario)

= 150 TWh; wind = 38GW; total 110 GW

– 56 GW conventional @ 31% fossil fuel load factor

– investment cost of renewables = €70 bn + €15 bn grid

– of non-renewables = £12 b, (£coal=3.9b; nuclear = £3.9b)

= €95/t CO2 c.f. €14/t current EUA

• 38 GW> demand for many hours

=> volatile supplies, prices, congestion, ….

• Offshore wind dependent on electricity price

– now looks unfavourable even with banded ROCs

– FIT cheaper than HMG’s banded ROCs (Redpoint)

Page 23: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 23

SKM’s projected capacity mix

Page 24: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 24

SKM’s projected output mix

Page 25: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 25

Implications of substantial wind

• Much greater price volatility

– mitigated by nodal pricing in import zones

– requires CfDs and nodal reference spot price

• Reserves (much larger) require

remuneration

– VOLL*LOLP capacity payment?

– or contracted ahead by SO?

– Or will spot price volatility induce contracts

that cover availability costs?

Page 26: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 26

Simulation – more volatility, harms baseload (nuclear)

0

10

20

30

40

50

60

70

80

90

100

Euro/MWh

2005

2010

2015 2020

0 8760 hours

Illustrative

Price duration schedule

Page 27: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 27

Is nuclear viable in liberalised markets?

• Credit supply drying up

– low risk free rate (indexed bonds)

– but high cost of capital to most companies

• Low debt-equity needed for construction

• electricity price-cost margin very volatile

– issue electricity indexed bonds?

– or require long-term carbon price guarantee?

Is any electricity investment viable without

an off-take contract?

Page 28: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 28

Towards a Single Buyer?

• The cost of off-shore is huge

– unsustainable in current conditions?

– Precipitate move to long-term contracting?

– Spot market too risky to support investment?

– Balancing market works overtime with wind

• Any investment without a long-term contract?

– But then need a Single Buyer?

– With short-fall in spot market revenue via capacity

payment charged through grid?

How long before a viable market design?

Page 29: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 29

Current GB transmission access

• Connect for firm access

– delay until reinforcements in place

=> excessive T capacity for wind

– excessive delays in connecting wind

• TSO uses contracts and Balancing

Mechanism to manage congestion

– weak incentives on G to manage output

– costly to deal with Scottish congestion

Page 30: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 30

Balancing - problems and requirements

• efficient dispatch: schedule ahead of time

– to allow for warm-up, ramping, etc

• wind forecasts increasingly accurate at -4hrs

• day-ahead market bad for wind contracting

• managing cross-border balancing requires

more co-operation (and area-wide dispatch?)

Page 31: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 31

The argument for change

• A flawed system can be improved

=> potentially everyone can be made better off

• The challenge:

– identify the efficient long-run solution

– that can co-exist with an evolving regime for

incumbents

– apply new regime to all new generation

– which compensates incumbents for any change

– while encouraging them to migrate

Page 32: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 32

Efficient congestion management

• Nodal pricing or LMP for optimal spatial dispatch

• All energy bids go to central operator

• Determines nodal clearing prices – reflect marginal losses with no transmission constraints

– Otherwise nodal price = MC export (or MB of import)

• Bilateral energy contracts – Can submit firm bids => pay congestion rents

– Can submit price responsive bids => more profit

• Financial transmission contracts hedge T price risk

Page 33: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 33

Spatial and temporal optimisation

=> nodal pricing + central dispatch

• Nodal price reflects congestion & marginal losses

– lower prices in export-constrained region

– efficient investment location, guides grid expansion

• Central dispatch for efficient scheduling, balancing

• Market power monitoring – benchmark possible

• PJM demonstrates that it can work

– Repeated in NY, New England, California (planned)

Page 34: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 34

GB objections to nodal pricing

• Disadvantages Scottish generators

– but would benefit voting Scots consumers!

=> Large revenue shifts for small gains

• All earlier attempts thwarted by courts

=> need to compensate losers

Need to make change before large

investments made (wind + transmission)

Page 35: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 35

Transition for existing plant

• Existing G receives long-term transmission

contracts but pays grid TEC charges

• for output above TEC, sell at LMP

G significantly better off than at present

No T rights left for intermittent generation

Challenge: devise contracts without excess

rents and facilitate wind entry

Page 36: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 36

Politics and constraints

• Aim: Security, Sustainability, Affordability

• choose any two of three?

– Or minimise cost of achieving efficient level of

security while meeting CO2 and renewables

objectives

• Currently costs all levied on consumers

– and excessive because of ROCs etc

Creates additional policy uncertainty

Page 37: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 37

Costs of renewables (Ofgem)

• 150 TWh renewables by 2020?

• 2006/7 14.6 TWh = £10/year/HH

(household) HH 29% total =£250 m; total

£870m

• BERR predicts £32-53/HH/yr

– HH = £0.8-1.32 b/yr; total = £2.8-4.6b/yr

• SKM’s estimate = £60-90/HH =>£5.2-

7.8b/yr

Even the low estimate is a 6-fold increase

Page 38: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 38

Annual average domestic standard electricity bill

0

50

100

150

200

250

300

350

400

1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007p

£ p

er

year

0

1

2

3

4

5

6

7

Nu

mb

er

of

ho

useh

old

s f

uel

po

or

mil

lio

ns

pre-paymentstandard creditfuel poor Englandfuel poor UK

4 million taken

out of fuel poverty

by £100 fall

500,000 more

for a £20 rise

British fuel poverty

Page 39: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 39

Support for RD&D

• Renewables subsidy above C price justified

by learning benefits => commercialise to

save the planet

• Why charge electricity consumers for that?

– VAT on energy better but still inefficient

– except to correct energy subsidies

Solution - fund from general taxation or

EUA auction revenues (as with CCS)

Page 40: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 40

Conclusions-1

• Low-C electricity requires proper C price

• Renewables target justified by learning benefits

– requires and currently lacks

• efficient transmission access regime

• efficient market design for dispatch and balancing

• Efficient decisions require either Single Buyer

or nodal pricing + pool/SO control

• both require transition arrangements/contracts

– for new/old Generation

Page 41: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 41

Conclusions-2• Renewables and other targets undermine

liberalised market

=> threatens all generation investment

• Current UK support for RES risky and costly

=> required shift to long-term contracting marks

end of liberalised market?

Nuclear power needs an attractive offering to

compete politically with renewables:

attractive real return with sensible C price

Page 42: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 42

Conclusions - 3

• Carbon pricing: ETS needs CfDs

– or a central carbon bank to stabilise EUA price

• RD&D support needed to lower costs

– to commercialise in BRICs etc

• needs design driven by learning objective

– burden sharing via country targets helps

– but emphases least cost not most learning

– support should be from public expenditure

Page 43: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

Market design and support policies for

a low carbon electricity future

David Newbery

Global CO2 economics

Sønderborg, Denmark 18-19 August 2009http://www.electricitypolicy.org.uk

Page 44: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 44

Acronyms

CCS: carbon capture and sequestration

CEC: European Commission

CfD: contract for difference

EUA: European emission allowance (for 1 tonne CO2)

FIT: feed-in tariff

GHG: greenhouse gas

G: generation

LCPD: large combustion plant directive

LMP: locational marginal pricing

MC, MB: marginal cost, marginal benefit

PV: photo-voltaic

Page 45: Market design and support policies for a low carbon electricity … · 2017-12-08 · –investment cost of renewables = €70 bn + €15 bn grid –of non-renewables = £12 b, (£coal=3.9b;

D Newbery Denmark Aug 09 45

Acronyms

RES: renewable electricity supply

ROC: renewable obligation certificate

SO: System operator

T: transmission

TEC: transmission entry capacity (to access grid)

TSO: transmission system operator