LINAC 4 Emittance Meter

45
LINAC 4 Emittance Meter

description

LINAC 4 Emittance Meter. Linac 4 Emittance Meter. 1er design for commissioning of the source Slit Sem -grid Measurement plate (F.C.) Emittance meter Upgrade of the slit for 3Mev New slit. SLIT. SLIT 0.1 mm Stainless steel plate: thickness 1 mm with 0.2 mm at the slit position. - PowerPoint PPT Presentation

Transcript of LINAC 4 Emittance Meter

Page 1: LINAC 4 Emittance  Meter

LINAC 4Emittance Meter

Page 2: LINAC 4 Emittance  Meter

2

Linac 4 Emittance Meter

• 1er design for commissioning of the sourceSlitSem-gridMeasurement plate (F.C.)Emittance meter• Upgrade of the slit for 3MevNew slit

LINAC 4 Beam Instrumentation Review - 18-19 October 2011 D. GERARD BE/BI/ML

Page 3: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

3

SLIT

D. GERARD BE/BI/ML

SLIT 0.1 mmStainless steel plate: thickness 1 mm with 0.2 mm at the slit position

Page 4: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

4D. GERARD BE/BI/ML

SEM-GRID

48 wires 40 µm Tungsten space 0.75 mm

Page 5: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

5D. GERARD BE/BI/ML

SEM-GRID

Page 6: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

6D. GERARD BE/BI/ML

SEM-GRID

Page 7: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

7D. GERARD BE/BI/ML

SEM-GRID

Polarized plate

Page 8: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

8D. GERARD BE/BI/ML

SEM-GRIDAngle setting

Page 9: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

9D. GERARD BE/BI/ML

Measurement plate (F.C.)

Page 10: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

10D. GERARD BE/BI/ML

Measurement plate (F.C.)

Page 11: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

11D. GERARD BE/BI/ML

Measurement plate (F.C.)

Page 12: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

12

Emittance Meter

D. GERARD BE/BI/ML

Page 13: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

13

Emittance Meter

D. GERARD BE/BI/ML

Page 14: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

14

Emittance Meter

D. GERARD BE/BI/ML

Page 15: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

15

Emittance Meter

D. GERARD BE/BI/ML

Page 16: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

16

Emittance Meter

D. GERARD BE/BI/ML

Page 17: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

17

New Slit Design• Slit used at source front-end would reach too high temperatures at 3 MeV and

would not be thick enough at 12 MeV• New slit design based on

– Energy deposition: dilute energy deposition density by putting the blade with an angle w.r.t. beam axis

– Minimize scattering along slit gap: minimize slit thickness• New design based on graphite plates with an angle of 15 degrees w.r.t. beam

trajectory

D. GERARD BE/BI/ML

Page 18: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

18

New Slit -Thermo-Mechanical Calculations (EN-MME)

D. GERARD BE/BI/ML

ANSYS Model Temperature Evolution during multi-shots

Without Cooling

With Cooling

Design Completed Fabrication Launched

Page 19: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

19

Specification3 MeV 12 Mev

H- range in Carbon [mm] 0.1 1

Min/Max Slit thickness [mm] 2/5

Min single blade width [mm] 67

Min single blade height [mm] 67

Min slit fullstroke [mm] 134

Blade distance (slit gap) all along the slit thickness

[µm] 100, adjustable to 200

D. GERARD BE/BI/ML

Page 20: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

20

NEW SLIT

D. GERARD BE/BI/ML

Page 21: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

21

Graphite plateBEAMdirection15°

D. GERARD BE/BI/ML

NEW SLIT

Slit: 0.1 mm or 0.2 mm

Page 22: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

22

wedge to adjust by machining after metrology measurement

D. GERARD BE/BI/ML

NEW SLIT

Page 23: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

23

Additional graphite plates needed to cover the whole beam during the measurement

Five set of plates are ordered (3 spares)

D. GERARD BE/BI/ML

NEW SLIT

Page 24: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

24

The back copper support of the graphite plate integrate the cooling circuit hole

D. GERARD BE/BI/ML

NEW SLIT

Page 25: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

25

Two side plate close the cooling circuit. In the assembly, it is the only position where a brazing separate vacuum from the water of the cooling circuit

D. GERARD BE/BI/ML

NEW SLIT

Page 26: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

26

Fixation of the graphite plate on the support

D. GERARD BE/BI/ML

NEW SLIT

Thickness at the slit position : 1 mm

Page 27: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

27D. GERARD BE/BI/ML

NEW SLIT

Page 28: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

28

NEW SLIT

Horizontal et vertical slit

D. GERARD BE/BI/ML

Page 29: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

29

NEW SLITHorizontal et vertical slit movement with potentiometer

Window for laser profile measurement

Sliding support

D. GERARD BE/BI/ML

Stepping motor: 200 step / turn

Manipulator1.27 mm/turn => resolution 6.35 µm / motor step

Page 30: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

30

NEW SLITSlope setting with the back micrometric screw

Tilt setting with the 2 front screw

D. GERARD BE/BI/ML

0.25 mm/ turn

BEAMPotentiometer will be added to the micrometric screw to be able to keep the position of the alignment setting

Page 31: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

31

TILT setting

D. GERARD BE/BI/ML

Is done with a optical benchThe slit assembly is installed in the tank The tank is aligned to a optical bench (the survey target and the tilt reference plate are set).The assembly will be under vacuum.By acting on the 2 front micrometric screw the slit will be aligned

For the slope setting the assembly will stay on the same bench and under vacuum but a laser will replace the optical system.

Horizontal ref of the optical system

Several iteration by acting on the 2 micrometric srewuntil getting the slit horizontal

Page 32: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

32

Slope setting

D. GERARD BE/BI/ML

LASER BEAM

Laser beam sensor

Vertical movement of the laser

Mechanism under vacuum

Several iteration until getting the maximum value at the laser beam sensor

Setting the position of the slit by action on the back screw

Page 33: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

33

NEW SLIT

D. GERARD BE/BI/ML

Page 34: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

34

NEW SLIT

D. GERARD BE/BI/ML

Page 35: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

35

Budget new slit

• Design: 93 kCHF• Manufacturing: 150 kCHF (88 kCHF + 60

KCHF)Total: ~250 kCHF

D. GERARD BE/BI/ML

Page 36: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

36D. GERARD BE/BI/ML

Some pictures

Page 37: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

37D. GERARD BE/BI/ML

GEFRAN PKM175 Répétitivité : 0.01 mm

Page 38: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

38D. GERARD BE/BI/ML

Page 39: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

39D. GERARD BE/BI/ML

Page 40: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

40

Planning

• AP : delivery of the mechanical part earliest end of November.

• The supply parts are already at CERN except water flow, screw...

• Planning (working days):see next slide

D. GERARD BE/BI/ML

Page 41: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

41

Planning 1. Assembly of the graphite plate, metrology lab, machining of the wedge, cleaning, reassembly and remetrology

lab:7 days 2. Assembly of the 2 slit out of the tank:10 working days 3. Assembly of the tank with the setting support on the optical alignement bench and alignment:3 working days 4. Assembly of the 2 slits inside the tank:2 working days 5. Tilt alignment of the 2 slits:2 working days Slope alignment of the 2 slits (not usual, probably with laser and captor):3 working days Check of the alignment and survey alignment2 working days

Mechanical assembly finish: 29 working days

But the position setting and check of the movement for the soft and hardware electronic needed to be done with the slit assembly on the optical alignment bench and with the support of the ML section

D. GERARD BE/BI/ML

Page 42: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

42D. GERARD BE/BI/ML

Planning

If the delivery from the AP (Main Workshop) is end-of November Þ25/01/2012 the new slit will be ready (mechanical) BUT in parallel the Winter Shut Down !!!

Page 43: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

43

• Thanks to:F. Roncarolo, B. CheymolB. Riffaud, E. Berthome, D. Steyaert, A.

DallochioG. Favre, S. Mathot M. Duraffourg, G. J. Focker....and all other people involved in this project

D. GERARD BE/BI/ML

Page 44: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

44

Question?

• Thank for your attention• Question?

D. GERARD BE/BI/ML

Page 45: LINAC 4 Emittance  Meter

LINAC 4 Beam Instrumentation Review - 18-19 October 2011

45

Cut view

D. GERARD BE/BI/ML