Transcript of LAPS Arg Sunset Review

  • 8/3/2019 LAPS Arg Sunset Review

    1/2

    Name of Project

    +/Delta Sunset Review

    Date

    ParticipantsIleana Bonanni Argentina Branch Bill Borst - WINS Ana Lasher LAZ ZoneAlejandra Paesani Argentina Branch Felicia Horton WINS

    Carlos Sivori Argentina Branch Marilyn Foushee WINSAxel Trautenmiller Argentina Branch Adrienne Taub Weber - WINS

    Design Estimation

    + (What went well) (Areas for improvement) Owner Next Steps (If no action, why?)Test case document prepared by Marilynwas thorough

    Good Teamwork in day to day activities

    The right people were on the daily calls

    Ileana learned a lot from working withAxel who was experienced in WINS

    Good response time when issues wereidentified.

    Agile methodology user testing eachpiece as it was built vs. building it all andthen testing it.

    Walkthroughs on analysis and code savedrework.

    Dedicated resources to the project

    Recap of the to dos from Felicia afterdaily meetings

    Ana being involved with the testing and inhelping the branch understand what

    1- Educate the new branch on the project andexpected changes WIP cedeback, otherchanges.

    2 - Train new resources (if necessary) in WINSoperations analysis

    3- Obtain a better understanding up front of thetype of business the branch writes so that WINS

    and WIP test cases are more specific to thebranch.

    4. Create a questionnaire that gives moreinformation on the type of policies that the branchsends. Clarify what is done online vs. through thecurrent bridge

    5. Allow more time for testing

    Ana / Bill

    Ana / Branch personnel

    3. Ana / Bill Borst

    4. Bill / Ana

    5. Adrienne

    6. Branch contact

    1 This should be addressed at thebeginning of a conversion project. Arequirements questionnaire will bedeveloped to identify practices,procedures and issues in order to

    develop a better project plan forthe next country. Ana and Bill willwork on developing thequestionnaire with an expecteddelivery date of 07/10/08.

    2 The LAPS project and WIPCedeback documentation will besent to each country when theyreceive the requirementsquestionnaire.

    3 Same as #1

    4. Same as #1

    5. Additional testing time will be

    Page 1

  • 8/3/2019 LAPS Arg Sunset Review

    2/2

    Name of Project

    +/Delta Sunset Review

    Date

    needed to change.

    Buy in and participation from Carlos (ITmanager) at the user testing stage wasessential.

    6. Obtain more test policies from the branchwhen doing the initial / piece-at-a-time testing

    7. Incorporate a bigger system test before theuser test

    8. Review the common rejections with the currentbridge to identify branch-needed changes earlier

    9. Get commitment from users for testing time

    10. Establish regular weekly meetings with theusers

    11. Need to set up JCL and files for new jobsfurher in advance

    12. Have Argentina share information with thenew branch on what to expect and how to

    prepare.

    7. Adrienne

    8. Branch personnel /Ana / Bill

    9. Ana/Marilyn, Bill

    10. Felicia

    11. Felicia

    12. Ana / Argentina

    addressed in the next project plan.

    6. WIP testing, specifically thedownloading of data fromproduction to the test regions, isstill a concern, but it cannot beaddressed in the scope for theLAPS conversion project. LAPS WIPtesting will be greatly improved bythe availability of the LAPS code.

    7. This will be included in the projectplan and coordinated with the teamsand with QA.

    8. Same as #1

    9. This will be addressed as in #1 andwith a review of the project plan

    10. WINS will hold weekly meeting withbranch contact & should include branchIT contact during milestone testing.

    11. WINS will perform system testingwith production ready JCL and includethis in the project plan.

    12. Argentina personnel willproduce documentation includinglearning points as a guide for thenext countries. This documentationwill be reviewed with Anaapproximately 07/10/08 - 07/11/08.

    Page 2