L15 Temporary Earth Retaining Structures

download L15 Temporary Earth Retaining Structures

of 24

description

Construccion

Transcript of L15 Temporary Earth Retaining Structures

  • Lecture 31, 32, 33Temporary Earth Retaining StructuresJuly 29, 2009Meeting 11

  • CofferdamsTemporary Structures to keep out water and soil to permit construction in the dryTypesSheet Pile Wall with bracing (used for compact structures)Cellular cofferdams (used for large construction areas)

  • Typical Z Section Piling

  • Cofferdam Construction StepsPre-dredge to remove soft material and level area

  • Install temporary support pilesSet bracing frame and hang from temp piles

  • Drive Sheet Pile Wall using frame a guideExcavate bottom of cofferdamPlace concrete sealDewater and commence construction

  • Tremie PipeConcrete Seal

  • Compact CofferdamSteel Sheet PilesBracingConcrete Seal

  • Cellular CofferdamsMainCellConnecting Arc

  • Cellular CofferdamsUsed to dike off a large construction areasPractical to depths of 75 ft.Cells are filled with granular material

  • Cellular Cofferdam ConstructionFalsework ring templates must be usedGuide rings are temporarily supported by temporary pilesSheeting installation starts with the Y section.Pile layouts should be marked on the guide ringAfter Sheet piling is complete Cells are filled

  • Typical Flat Sheet Pile SectionsFabricated Y

  • Cofferdam Example

  • Cofferdam Detail

  • Other Earth Retaining Structures

  • Trench Boxes Prefabricated structure that is moved as the work progresses

  • Trench Box

  • Vertical Wood SheatingVertical woodsheatingTimber waleTimber cross bracing

  • Steel Soldier Piles and Horizontal SheatingHorizontal sheating set behind the flangeDriven sheet H piles

  • Braceless Systems Using Tie BacksTendonStressing UnitGrout

  • Tie back Example

  • Installing Tie backs

    *