L15 Temporary Earth Retaining Structures
description
Transcript of L15 Temporary Earth Retaining Structures
-
Lecture 31, 32, 33Temporary Earth Retaining StructuresJuly 29, 2009Meeting 11
-
CofferdamsTemporary Structures to keep out water and soil to permit construction in the dryTypesSheet Pile Wall with bracing (used for compact structures)Cellular cofferdams (used for large construction areas)
-
Typical Z Section Piling
-
Cofferdam Construction StepsPre-dredge to remove soft material and level area
-
Install temporary support pilesSet bracing frame and hang from temp piles
-
Drive Sheet Pile Wall using frame a guideExcavate bottom of cofferdamPlace concrete sealDewater and commence construction
-
Tremie PipeConcrete Seal
-
Compact CofferdamSteel Sheet PilesBracingConcrete Seal
-
Cellular CofferdamsMainCellConnecting Arc
-
Cellular CofferdamsUsed to dike off a large construction areasPractical to depths of 75 ft.Cells are filled with granular material
-
Cellular Cofferdam ConstructionFalsework ring templates must be usedGuide rings are temporarily supported by temporary pilesSheeting installation starts with the Y section.Pile layouts should be marked on the guide ringAfter Sheet piling is complete Cells are filled
-
Typical Flat Sheet Pile SectionsFabricated Y
-
Cofferdam Example
-
Cofferdam Detail
-
Other Earth Retaining Structures
-
Trench Boxes Prefabricated structure that is moved as the work progresses
-
Trench Box
-
Vertical Wood SheatingVertical woodsheatingTimber waleTimber cross bracing
-
Steel Soldier Piles and Horizontal SheatingHorizontal sheating set behind the flangeDriven sheet H piles
-
Braceless Systems Using Tie BacksTendonStressing UnitGrout
-
Tie back Example
-
Installing Tie backs
*