![Page 1: [IEEE 2011 International Conference on Quality, Reliability, Risk, Maintenance, and Safety Engineering (ICQR2MSE) - Xi'an, China (2011.06.17-2011.06.19)] 2011 International Conference](https://reader035.fdocuments.net/reader035/viewer/2022080505/5750aba41a28abcf0ce101bc/html5/thumbnails/1.jpg)
Study on Integrated Plan Model of Equipment Quality Management
Chong Meng, Huawen Song Department of Equipment Command
Institute of Equipment Command & Technology Beijing, China
Abstract—Equipment quality management planning, controlling and improving are the main contents of equipment quality management job. In order to enhance equipment quality management efficiency, a sort of equipment quality management integrated plan model is presented in this paper. Firstly, the contents of equipment quality management integrated plan are analyzed, concerning of total process integration, total hierarchy integration, and total member integration. Secondly, according as equipment quality management integrated plan principle, equipment quality management integrated plan conceptual model is designed. Lastly, Implement measures of equipment quality management integrated plan are brought forward. The implement flow is as follows, analyzing equipment quality management integrated plan environment on the stratagem and battle level, constructing equipment quality management integrated plan goal system based on QFD (quality function deployment) on the tactics level, and designing equipment quality management integrated plan scheme based on Knowledge-Petri net. This novel equipment quality management plan mode is a new seeking of solving equipment quality management problems effectively.
Keywords-equipment quality management; integrated plan; QFD; goal program; knowledge-petri net
I. INTRODUCTION Equipment quality management plan is a systemic arrange
of taking scientific, logistic, effective and operable action for realizing equipment quality management goals, in order to instruct and control the rational exertion of equipment quality management resources, which is a guidance document of equipment quality management system running. At present, academia and war industry corporation at home and overseas have develop a lot of researches on equipment quality management theory and practice. Firstly, many advanced management ideas are forming step by step. For example, total quality management [1-3], process management [4-5], lean management [6], and so on. Secondly, several kinds of technologies and methods are exerted to solving the organization structure problem, running mode problem, and law rule problem about equipment quality management. For example, QFD [7], 6б [8], TRA (Technology Readiness Assessment) [9], and so on. Thirdly, the authentication and evaluation institution of equipment quality management system are carried out. But we find that, study on equipment quality management planning is singularly. If we enlarge the range of literature search, study on quality planning is still
singularly. Literature [10] studied systemically the theory and method of quality planning, and established the process model of quality planning, which offer use for reference for our paper. But aiming at equipment quality management planning, the following three points is very important. Firstly, actuality of equipment quality management system must be fully considered at present. Secondly, differences and relations between quality planning and quality management planning must be recognized. Thirdly, solving equipment quality management problems must be regarded as the study goal. Hence, this paper establishes equipment quality management integrated plan model based on the total system and life-cycle equipment quality management idea, and presents the new mode of equipment quality management planning.
II. EQUIPMENT QUALITY MANAGEMENT INTEGRATED PLAN CONTENT
Equipment quality management integrated plan is a planning management job of systemic, synthetical, compositive and comprehensive characteristic. It deals with equipment quality management total process integration (demonstrate phase, manufacture and production phase, trial and appraisal phase, use and support phase, retire and scrap phase), total hierarchy integration (stratagem level, battle level and tactics level), total member integration (military unit, supplier and consultation institution).
A. Total Process Integrated Plan Equipment quality management total process integrated
plan contents contain as follow. Firstly, phase current plan contents (taking demonstrate phase as an example). (1) Quality management range list. For example, current and appropriative quality characteristic design request. (2) Quality management goal list. For example, demonstrate personnel specialization, demonstrate measure scientific, and demonstrate judge standardization. (3) Time and logic arrange. (4) Power arrange. (5) Implement scheme. Secondly, interface management contents between phases on the course of total process integrated plan. Thirdly, inner joints identify method in phases on total life cycle.
B. Total Hierarchy Integrated Plan Equipment quality management total hierarchy integrated
plan contents contain as follow. Firstly, equipment quality management plan contents on stratagem (battle and tactics)
978-1-4577-1232-6/11/$26.00 ©2011 IEEE
![Page 2: [IEEE 2011 International Conference on Quality, Reliability, Risk, Maintenance, and Safety Engineering (ICQR2MSE) - Xi'an, China (2011.06.17-2011.06.19)] 2011 International Conference](https://reader035.fdocuments.net/reader035/viewer/2022080505/5750aba41a28abcf0ce101bc/html5/thumbnails/2.jpg)
level. (1) Analyze the inner and external (inner and unit inner) environment of equipment quality management system. (2) Establish equipment quality management stratagem (battle and tactics) goal system. (3) Constitute equipment quality management stratagem (battle and tactics) programming. Secondly, communicate effectively between each management levels. (1) Communication plan. (2) Information spread. (3) Execute report. (4) Feedback summarization.
C. Total Member Integrated Plan Equipment quality management total member integrated
plan means that, equipment quality management participants develop integrated plan job aim at their respective request and expectation, according as benefit maximum principle of equipment quality management. The contents contain that, (1) Total member participation. (2) Collaboration and restriction between members.
III. EQUIPMENT QUALITY MANAGEMENT INTEGRATED PLAN MODEL
Process dimension, hierarchy dimension and personnel dimension compose three-dimensional structure of equipment quality management integrated plan system. How to make these plan elements integrated organically, this paper establishes equipment quality management integrated plan model.
A. Equipment Quality Management Integrated Plan Principle
1) Flexibility principle Plan arranges should conform to flexibility principle. On
the one hand, plan contents should be adjustable at the key
node, and multifold plan adjustable schemes should be provided. On the other hand, it is very important for plan to rolling put in practice. Plan contents need to be detailed and operable in the initial several nodes of certain phase of equipment quality management, and it is sketchy and foreseeable in the last several nodes, so as to emend equipment quality management plan according to environmental change.
2) Core member oriented integrated plan principle Equipment quality management integrated plan design
equipment quality management resources and factors from systemic visual angle. But that don’t mean to change drastically the traditional plan mode. Integrated plan mode should regard certain core phase or core participant of certain phase as center to integrate plan network. For example, manufacture and production phase is the core phase of equipment quality management, which is the tache of plan integration.
3) Military member oriented principle Equipment quality construction problem relates to nation
safety and army battle effectiveness, which is different essentially with general commodity quality problem. The core competitor may be not dominant. In other words, implement of equipment quality management integrated plan must show military member oriented effect.
B. Equipment Quality Management Integrated Plan Conceptual Model On the basic of analyzing synthetically equipment quality
management integrated plan contents, according to equipment quality management integrated plan principle, this paper designs equipment quality management integrated plan conceptual model, which is shown in Fig.1.
AB
CD
E
Whole environment
analysis
Confirm overall goal
and phase goal
Design scheme
A
A-B interface
B
Phase Benvironment
analysis
Confirm phase B goal and adjust
overall goal
Design phase B scheme
B-C interface
……
D-E interface
Phase Eenvironment
analysis
E
Confirm phase E goal
Design phase E scheme
Process Dimension
Personnel Dimension
Hiberarchy Dimension
demonstrate phase
manufacture and production phase
trial and appraisal phase
use and support phasemilitary unit
supplier
consultation institution
stratagem level
battle level
tactics level hierarchical plan
Hierarchical Plan
Retire and scrap phase
Figure 1. Equipment quality management integrated plan conceptual model
In Fig. 1, A denotes the starting point of making equipment quality management integrated plan and demonstrate phase equipment quality management integrated plan. At this point, equipment quality management integrated plan is constituted roughly from stratagem visual angle, and demonstrate phase equipment quality management integrated plan need to be constituted in detail. B denotes the starting point of making
manufacture and production phase equipment quality management integrated plan. At this point, equipment quality management integrated plan is emended, and manufacture and production phase equipment quality management integrated plan need to be constituted in detail. C denotes the starting point of making trial and appraisal phase equipment quality management integrated plan. D denotes the starting point of
![Page 3: [IEEE 2011 International Conference on Quality, Reliability, Risk, Maintenance, and Safety Engineering (ICQR2MSE) - Xi'an, China (2011.06.17-2011.06.19)] 2011 International Conference](https://reader035.fdocuments.net/reader035/viewer/2022080505/5750aba41a28abcf0ce101bc/html5/thumbnails/3.jpg)
making use and support phase equipment quality management integrated plan. E denotes the starting point of making retire and scrap phase equipment quality management integrated plan. The function of point C, D, E is similar with that of point B.
C. Equipment Quality Management Integrated Plan Implement Measure Fig. 1 shows equipment quality management integrated
plan conceptual model, and then, how to constitute equipment quality management integrated plan, this paper presents detailed implement measures.
1) Equipment quality management integrated plan environment analysis
Environment analysis is the important foundation of equipment quality management integrated plan. At point A, we mainly analyze stratagem environment of equipment quality management. At point B, C, D and E, we mainly analyze battle environment of equipment quality management, and adjust stratagem plan direction timely. Detailed analysis contents are shown in Table I.
TABLE I. EQUIPMENT QUALITY MANAGEMENT INTEGRATED PLAN ENVIRONMENT ANALYSIS
Node Environment Analysis Element Environment
Analysis Measure Environment Analysis
Characteristic Level 1 Index Level 2 Index
A
Stratagem environment
Organization structure
Mainly by qualitative
analysis
Decision-making level overall
long-term authoritative
steady synthetical
Running mechanism
Guideline policy
Manpower resource
Technology resource
Information system
Battle environment
Demonstrate quality management system
Qualitative analysis combined with quantitative
analysis
Executive level partial
medium/short-term instructional
flexible operable
Demonstrate quality guideline, goal and procedure Demonstrate personnel Demonstrate measure
Demonstrate mean
B
Manufacture and production total request Manufacture and production criterion
Military delegate quality management system Supplier quality management system
Consultation institution participate in manufacture and production instance
C
Trial and appraisal plan Trial and appraisal quality request
Trial and appraisal quality management system Consultation institution participate in Trial
and appraisal instance
D
Use and support plan Use and support quality management system
Supplier and consultation institution participate in maintain and support instance
E Retire and scrap plan Retire and scrap assess institution
2) Equipment quality management goal analysis based on QFD
Equipment quality management planning is virtually such a course as designing equipment quality management schemes and measures in order to carry out equipment quality management goal. Hence, equipment quality management goal is the vital content of equipment quality management planning. This paper analyzes equipment quality management goal based on QFD.
QFD is one of these techniques that make the function and operation of forming quality deployed by a set of purposes and means step by step [11], its core part is house of quality (HoQ).
By establishing HoQ, designer can availably connect requirement of customer with technology characteristic, and design purposefully technology characteristic of product to meet requirement of customer.
Equipment quality management goal analysis principium based on QFD is that, quality requirements of army are translated into equipment quality management goals on different phase of life cycle by HoQ. Namely, equipment using requirements are mapped as demonstrate requests, design requests, develop requests and trial requests gradually, by conversion matrix, equipment quality management goal chain is established [12], shown as Fig.2.
![Page 4: [IEEE 2011 International Conference on Quality, Reliability, Risk, Maintenance, and Safety Engineering (ICQR2MSE) - Xi'an, China (2011.06.17-2011.06.19)] 2011 International Conference](https://reader035.fdocuments.net/reader035/viewer/2022080505/5750aba41a28abcf0ce101bc/html5/thumbnails/4.jpg)
conflict analysis
D1
conversion matrix
S1
R1
conflict analysis
D2
conversion matrix
S2
R2
conflict analysis
D3
conversion matrix
S3
R3
conflict analysis
D4
conversion matrix
S4
R4
conflict analysis
D5
conversion matrix
S5
R5
conversion matrix
G4 G3 G2 G1G5
R1: equipment using quality requirements
R2: equipment demonstrate quality requirements
R3: equipment design quality requirements
R4: equipment accessory characteristic quality requirements
R5: equipment develop quality requirements
D1: equipment demonstrate quality demands
D2: equipment design quality demands
D3: equipment accessory characteristic quality demands
D4: equipment develop quality demands
D5: equipment trial and appraisal quality demands
G1: equipment using quality management goal
G2: equipment demonstrate quality management goal
G3: equipment design quality management goal
G4: equipment develop quality management goal
G5: equipment trial and appraisal quality management goal
S1: equipment demonstrate resource restrict
S2: equipment design resource restrict
S3: equipment technics resource restrict
S4: equipment develop resource restrict
S5: equipment trial and appraisal resource restrict
Figure 2. Equipment quality management goal chain
Taking demonstrate phase as a example, we introduce that how to confirm equipment quality management goal on this phase.
Step1. List equipment using quality requirements index set {r1,r2,…,rm}. List demonstrate quality demands index set of affecting equipment using requirements {l1, l2,…,ln}. List resource restrictions of affecting demonstrate quality demands (S), such as economy feasibility (E), technology feasibility (T), and so on.
Step2. Suppose these indexes are independent in the same index set, calculate weight of index by AHP, timely, {w1, w2,…,wm}(using quality requirements indexes), {w’1, w’2,…,w’n}(demonstrate quality demands indexes) and {wA,wC,wT}(weight relation between equipment demonstrate quality goals and its resource restrictions).
Step3. Establish and solve the goal programming model in order to seek to minimum of restriction conditions windage d [13].
Min {wA(d1+/-)+ wC(d2
+/-)+wT(d3+/-)}
S(x1,x2,…,xn,d1,d2,d3)=0 Step4. Because these relations between equipment
demonstrate quality requirements and equipment demonstrate quality management goals are direct. Therefore, we don’t consider resource restriction problems, and confirm directly equipment demonstrate quality management goals based on QFD.
According to all above, equipment demonstrate quality management goals are confirmed, and the relative importance degree between goals can be easily distinguished, which offer foundations for designing equipment quality management integrated plan scheme.
3) Equipment quality management integrated plan scheme design based on Knowledge-Petri net
A Petri net is an important analytical and modeling tool, can denote the static structure and dynamic characteristic by place, transition, arcs and token, and has the capacity for modeling and planning an equipment quality management system. This paper describes equipment quality management integrated plan scheme based on Knowledge-Petri net, which can integrate equipment quality management resources and elements, and show scientifically equipment quality management plan functions and demands.
Knowledge-Petri net is a modeling method of integrating knowledge expert system to the Petri net. On the one hand, it can enhance the formalization expressive force of Petri net, simplify description process of Petri net; On the other hand, it can adjust dynamic quality management plan contents and time. Knowledge expert system stores large number of static data and dynamic data about equipment quality management by the incident chain-list. Static data contain Clock Set, Person Set (member type, management member base, and expert base), Goal Set, Index Set, and Content Set; dynamic data contain Fire Condition Set, Storage Set and Scheme Adjustable Set. The incident chain-list is shown in Fig.3 [14].
Incident chain-list can reflect the instances of place and transition at the real time, and store correlative information. Therefore, place nodes and transition nodes of Petri net model in Fig. 4 integrated with above incident chain-list, which is Knowledge-Petri net model of equipment quality management integrated plan. This model reflects fully plans and arranges of equipment quality management participants in total life cycle. Meanings of every node variable of equipment quality management integrated plan are shown in Table2.
![Page 5: [IEEE 2011 International Conference on Quality, Reliability, Risk, Maintenance, and Safety Engineering (ICQR2MSE) - Xi'an, China (2011.06.17-2011.06.19)] 2011 International Conference](https://reader035.fdocuments.net/reader035/viewer/2022080505/5750aba41a28abcf0ce101bc/html5/thumbnails/5.jpg)
Incident Node Number
Clock Set
Person Set
Goal Set
Index Set
Content Set
Transition Node Number
Fire Condition Set
Stroge Set
Scheme Adjustable Set
Figure 3. Incident chain-list
IV. CONCLUSION Equipment quality management integrated plan is a useful
theory seeks of innovating equipment quality management mode. This paper establishes equipment quality management integrated plan conceptual model, and represents detailed implement measures, which offer novel thought for improving equipment quality management plan method. But lots of detail problems about equipment quality management can’t be still solved in this paper. For example, the dynamic characteristic problem of equipment quality management integrated plan Knowledge-Petri net model, plan management interface problem between phases. Those will be our research direction in the future.
TABLE II. PETRI NET MODEL NODE VARIABLE MEANINGS EXPLANATION
Place element Meanings Transition
element Meanings
P0 Equipment demonstrate preparation T0 Constitute demonstrate group P1 Requirement analysis T1 Requirement analysis quality assess P2 Feasibility demonstrate T2 Feasibility demonstrate quality assess
P3 Pertinence Requirement analysis T3 Pertinence Requirement analysis quality assess
P4 Develop total request demonstrate T4 Demonstrate quality synthetically assess P5 Primary products develop T5 Primary products trial and appraisal assess P6 Sample develop T6 Sample trial and appraisal assess P7 Small batch production T7 Military delegate quality supervision P8 Large batch production requirement T8 Requirement return receipt P9 Large batch production T9 Military delegate quality supervision P10 Equipment deployment T10 Equipment deployment quality supervision P11 Equipment using T11 Equipment using quality supervision P12 Equipment maintain T12 Equipment maintain quality supervision P13 Equipment deposit T13 Equipment deposit quality supervision P14 Equipment retire and scrap
Figure 4. Equipment quality management integrated plan Petri net model
REFERENCES [1] H. G. Wang, G. Y. Xu, and Y. M. Zhang, “Equipment total quality
management,” Beijing: National Defense Industry Publishing Company, 2003.
[2] J. F. Sun, J. Y. Huang, and X. M. Du, “Application of TQM in military equipment quality management,” O.I. Automation, vol. 27, pp.47-49, 2008.
[3] L. Hong, and F. G. Zhang, “Military soft total quality management,” Si Chuan Armament Journal, vol. 30, pp.147-148, 2009.
![Page 6: [IEEE 2011 International Conference on Quality, Reliability, Risk, Maintenance, and Safety Engineering (ICQR2MSE) - Xi'an, China (2011.06.17-2011.06.19)] 2011 International Conference](https://reader035.fdocuments.net/reader035/viewer/2022080505/5750aba41a28abcf0ce101bc/html5/thumbnails/6.jpg)
[4] H. C. Dai, “Research on equipment quality surveillance management based on process approach,” Ph.D. Dissertation, Shi Jiazhuang Ordnance Engineering College, 2007.
[5] Y. Q. Bian, J. X. Huang and L. Zhang, “Study on military production quality control and manage based on process,” Equipment Quality, pp. 8-15, 2009.
[6] Y. H. Li and X. M. Cheng, “United State Army carry out lean six sigma management to enhance quality management,” Equipment Quality, pp. 1-6, 2006.
[7] X. G. Han, G. T. Feng, and W. Y. Liu, “Branch design of maintenance quality management based on QFD,” Journal of Ordnance Engineering College, vol.18, pp. 37-40, 2006.
[8] Y. Liu, “Application of 6 sigma management during military production quality controlling,” Navy Equipment, pp.28-29, 2009.
[9] Y. H. Ma, Y. S. Li, and Y. Hu, “Application of technology readiness assessment in the astronautics engineering,” Equipment Quality, pp. 1-8, 2011.
[10] J. Chen, “Study on quality planning theory and measure and development practice,” University of Aeronautics and Astronautics, pp. 7-14, 1999.
[11] S. Mizuno and Y. Akao, “QFD: the customer-driven approach to quality planning and development,” Asian Productivity Organization, 1994.
[12] Y. Y. Xiao and W. B. Chang, “Research on supply chain quality fluctuation model based on QFD,” Equipment Quality, pp. 34-39, 2009.
[13] Y. Z. Lian and S. C. Kwai, “QFD based optimal process quality planning,” Int J Adv Manu Technol, vol. 26, pp. 831-841, 2005.
[14] X. F. Zha, S. Y. E. Lim, and S. C. Fok, “Integrated knowledge-based petri net intelligent flexible assembly planning,” Journal of Intelligent Manufacturing, vol. 9, pp. 235-250, 1998.