HOPSRIG WIND FARM SCOPING REPORT - buccleuch.com · Scoping Report Hopsrig Wind Farm...
Transcript of HOPSRIG WIND FARM SCOPING REPORT - buccleuch.com · Scoping Report Hopsrig Wind Farm...
On behalf of
Hopsrig Wind Farm Ltd
Date
April 2016
Project Number
UK12-22427
HOPSRIG WIND FARM SCOPING REPORT
HOPSRIG WIND FARM SCOPING REPORT
Ramboll Environ 5th Floor 7 Castle Street Edinburgh EH2 3AH United Kingdom T +44 131 297 2650 www.ramboll-environ.com
Project No. UK12-22427 Issue No. 3Date 01/04/2016 Made by Demos Demosthenous / Rachael Martin Checked by Peter Bruce Approved by Nathan Swankie
Made by: Rachael Martin
Checked/Approved by: Peter Bruce
This report has been prepared by Ramboll Environ with all reasonable skill, care and diligence, and taking account of the Services and the Terms agreed between Ramboll Environ and the Client. This report is confidential to the Client, and Ramboll Environ accepts no responsibility whatsoever to third parties to whom this report, or any part thereof, is made known, unless formally agreed by Ramboll Environ beforehand. Any such party relies upon the report at their own risk. Ramboll Environ disclaims any responsibility to the Client and others in respect of any matters outside the agreed scope of the Services.
Version Control Log
Revision Date Made by Checked by Approved by Description
3 01/04/2016 RM PB Final Issue for Scoping Opinion
Scoping Report
Hopsrig Wind Farm
RUK12-22427_3_Scoping Report
CONTENTS
1. INTRODUCTION 11.1 Consenting Regime 11.2 Purpose of this Report 11.3 Structure of this Report 22. DESCRIPTION OF THE PROPOSED DEVELOPMENT 32.1 Site Description and Context 32.2 Policy Considerations 32.3 The Proposed Hopsrig Wind Farm 42.4 Construction 42.5 Decommissioning 43. SCOPE OF THE EIA 53.1 Design and Alternatives 53.2 Impact Assessments 53.3 Landscape and Visual Amenity 63.4 Ecology 83.5 Ornithology 123.6 Historic Environment 163.7 Hydrology, Hydrogeology and Geology, 193.8 Traffic, Transport and Access 213.9 Noise 243.10 Forestry 264. ISSUES SCOPED OUT OF THE EIA 284.1 Aviation and Defence 284.2 Socioeconomics 284.3 Air Quality 284.4 Shadow Flicker 294.5 Ice Throw 295. NEXT STEPS 30
LIST OF FIGURES
Figure 1: Site Location Figure 2: Cumulative Context Figure 3: Landscape Character Types Figure 4: Landscape Designations and Classifications Figure 5: ZTV and Viewpoint Locations Figure 6: Ecological and Ornithological Designations Figure 7: Cultural Heritage Assets within the Site Figure 8: Cultural Heritage Assets within 5 km Study Area Figure 9: Hydrological Constraints Figure 10: Peat Probe Locations and Recorded Peat Depth Figure 11: Abnormal Load Route Options Figure 12: Site Layout with 15 km Eskdalemuir Seismic Monitoring Station Buffer
Scoping Report
Hopsrig Wind Farm
RUK12-22427_3_Scoping Report
APPENDICES
Appendix A Figures
Appendix B Consultee List
Appendix C LVIA Supporting Information
Appendix D Ecology Supporting Information
Appendix E Ornithology Supporting Information
Appendix F Cultural Heritage Supporting Information
Scoping Report
Hopsrig Wind Farm
RUK12-22427_3_Scoping Report
1
1. INTRODUCTION
Hopsrig Wind Farm Limited (‘the Applicant’) proposes to submit an application for planning permission to construct and operate a wind farm, to be referred to as Hopsrig Wind Farm (‘the proposed development’), on land located approximately 7.5 km north west of Langholm, Dumfries and Galloway. The site location and wider context is shown on Figure 1. The land and the developer are wholly owned by The Buccleuch Estates Limited.
A provisional turbine layout has been prepared for the purposes of scoping, and comprises 18 turbines with a maximum tip height of 135 m. Based on currently available turbines, the typical maximum rated output per turbine is likely to be up to 3.2 MW. The turbine layout design is at an early stage and will be developed to take account of environmental and technical constraints and stakeholder consultation feedback. The provisional turbine layout is shown also on Figure 1 (see Appendix A).
1.1 Consenting Regime
For the purposes of scoping we have assumed that the proposed development would have a maximum generation capacity of > 50 MW. On this basis, an application for consent would be made to the Scottish Ministers under section 36 of the Electricity Act 1989. A deemed planning permission would follow such consent, under section 57 of the Town and Country Planning (Scotland) Act 1997.
Should the maximum generating capacity reduce to less than 50 MW through the design evolution process, an application would be made to Dumfries and Galloway Council under the Town and Country Planning (Scotland) Act 1997, as amended. We would expect that the views of consultees expressed in the course of scoping under the Electricity Works (Environmental Impact Assessment) (Scotland) Regulations 2000 would remain relevant should such an application be made under the 1997 Act, and no formal re-scoping exercise would be undertaken should this change occur.
In the event that the capacity of the proposed development falls below 50 MW, but remains in excess of 20 MW, a Proposal of Application Notice will be submitted to Dumfries and Galloway Council.
1.2 Purpose of this Report
This scoping report has been prepared to support a request for a scoping opinion from the Scottish Ministers under regulation 7 of the Electricity Works (Environmental Impact Assessment) (Scotland) Regulations 2000. The specific objectives of this report are to:
seek agreement on the likely significant effects associated with the proposed development, and confirm that all likely significant effects have been correctly included in the proposed scope of the EIA (‘scoped in’);
seek agreement where non-significant effects have been excluded (‘scoped out’); and
invite comment on the proposed approach to baseline data collection, prediction of environmental effects and the assessment of significance.
Unless consultees specifically request otherwise, all responses will be summarised and presented as a Technical Appendix to the Environmental Statement (ES), as a record of the results of the scoping exercise.
1.2.1 Consultees
The scoping report will be provided to the consultees set out in Appendix B.
Scoping Report
Hopsrig Wind Farm
RUK12-22427_3_Scoping Report
2
1.3 Structure of this Report
The remainder of this report is structured as follows:
section 2 provides a brief description of the nature and purpose of the proposed development, typical construction activities and decommissioning proposals;
section 3 describes the baseline environment conditions, the likely significant environmental effects identified and proposed method for further data collection and evaluation of effects;
section 4 describes the effects that are considered not to be significant, and proposes that these be excluded from the EIA, providing a rationale in each case; and
section 5 provides information on the process for making representations on the scoping report.
Scoping Report
Hopsrig Wind Farm
RUK12-22427_3_Scoping Report
3
2. DESCRIPTION OF THE PROPOSED DEVELOPMENT
2.1 Site Description and Context
The ‘site’, as defined by the red line boundary on Figure 1, is located west of the B709 road, approximately 7.5 km north west from the town of Langholm. The land is wholly owned by The Buccleuch Estates Limited.
Turbines are proposed for the western part of the site, on Calkin Rig (450 m), Ward Hill (387 m), Enzieholm Height (342 m), Threep Hill (336 m) and The Shin (359 m), around the headwaters of Boyken Burn. The Boyken Burn runs west to east through the centre of the site and joins the River Esk just outside of the site. The western section of the site is predominantly coniferous plantation woodland intersected with tributaries of the Boyken Burn and forest tracks. The eastern section of the site consists mainly of open moorland and semi-improved grassland used for grazing livestock. The site is also used for rearing pheasants and partridges, with high numbers observed on site during previous site visits.
The nearest village is Bentpath, located adjacent to the northern boundary of the site. The Old Hopsrig property is the only residential property located within the red line boundary, at 1.7 km south east of turbine 14.
As illustrated on Figure 1, the recently consented Ewe Hill wind farm is located immediately to the south with turbines very close to the boundary on the east flank of Ewe Hill and just off the summit of Ward Hill. The consented Ewe Hill wind farm comprises 22 turbines with 111.5 m tip height. In addition, the land to the south and east of the site is the subject of a planning application for Loganhead wind farm, comprising 13 turbines with a maximum tip height of 130 m. Land to the west is the subject of an application for Crossdykes wind farm, comprising 15 turbines with a maximum tip height of 130 m.
2.2 Policy Considerations
2.2.1 Project Need and National Planning Policy
A key Scottish Government target, as set out in The Routemap for Renewable Energy in Scotland, 2011 (as amended)1, is that the equivalent of 100% of gross electricity consumption should be generated from renewable sources by 2020. The Scottish Government expects that onshore wind generation would meet a significant component of the electricity generated to meet this target.
Scottish Planning Policy 2014 (SPP)2 introduces a presumption in favour of development that contributes to sustainable development (§§27-28, 32, 33 and 92 in particular).
The National Planning Framework 3 (NPF3)3 sets out the Scottish Government's commitment to establishing Scotland as a leading location for the development of renewable energy technology.
The proposed development is entirely consistent with the Scottish Government’s planning policy as set out in SPP and NPF3, and specifically the policy on the promotion of renewable energy and its target for the equivalent of 100% of Scotland’s electricity demand to be met from renewable sources by 2020.
1 The Scottish Government (2011) 2020 Routemap for Renewable Energy in Scotland, The Scottish Government, Edinburgh: URL: http://www.gov.scot/Publications/2011/08/04110353/ScreenPDF (accessed 11.12.15) 2 Scottish Planning Policy (2014): URL: http://www.gov.scot/Publications/2014/06/5823/0 (accessed 11.12.15) 3 National Planning Framework 3 (2014): URL: http://www.gov.scot/Publications/2014/06/3539/0 (accessed 11.12.15)
Scoping Report
Hopsrig Wind Farm
RUK12-22427_3_Scoping Report
4
2.2.2 Local Development Plan
The statutory development plan for the site comprises the Dumfries & Galloway Local Development Plan (the LDP) (adopted 29 September 2014)4 and associated formal statutory supplementary guidance (SG), including Wind Energy Development: Development Management Considerations (the Wind SG) (adopted 6 March 2015). A Planning Statement will be provided with the application to assess compliance with each relevant LDP policy.
At this stage, the key point of note is that the Wind SG (specifically the Wind Farm Landscape Capacity Study) identifies the landscape character type ‘Southern Uplands with Forest’ (19a), within which the site is located, as a preferred area of the development of large turbine typologies.
2.3 The Proposed Hopsrig Wind Farm
The main elements of the proposed development would be as follows:
up to 18 wind turbines, with a blade tip height of a maximum of 135 m;
associated external transformers and underground cabling;
new access tracks and hardstanding areas adjacent to each turbine;
borrow pit(s);
meteorological mast(s); and
an on-site electricity substation and control room.
It is expected that the wind turbines would have a generating capacity of up to 3.2 MW each, with a potential total generating capacity of 57.6 MW.
Access to the site would be taken from the B709 through the upgrade of an existing estate access track.
It is anticipated that the grid connection for the proposed development would be via an overhead line or underground cable, connecting to the Ewe Hill substation 4.4 km to the south. The grid connection would be subject to a separate consenting process led by the transmission license holder and is not included in the scope of the Hopsrig Wind Farm EIA.
2.4 Construction
Typical construction activities and work methods will be set out in the ES. Information will also be provided on proposals for forestry removal, an indicative construction programme, construction traffic generation and construction phasing. The ES will also contain details of appropriate environmental management measures, including pollution prevention measures (in line with Scottish Environment Protection Agency (SEPA)’s Pollution Prevention Guidelines (PPGs)), and waste minimisation and management measures.
2.5 Decommissioning
The proposed development would be operational for 25 years, following which, if there has been no approval to extend the life, the turbines would be dismantled and removed from the site. This operation would be similar to their erection and would be carried out according to relevant decommissioning guidelines prevailing at the time.
4 Dumfries and Galloway Local Development Plan (2014), URL: http://www.dumgal.gov.uk/index.aspx?articleid=11944
(accessed 11.12.15)
Scoping Report
Hopsrig Wind Farm
RUK12-22427_3_Scoping Report
5
3. SCOPE OF THE EIA
The content of ES will be prepared to meet the requirements of the EIA regulations and the Institute of Environmental Management and Assessment (IEMA) Quality Mark commitments. The EIA will cover all phases of the proposed development including construction, operation and decommissioning.
3.1 Design and Alternatives
Given the complexity of the cumulative context, and more particularly, the proximity of the Ewe Hill array, the proposed development design process will establish a layout and turbine typology which is sufficiently coherent with neighbouring developments, in accordance with SNH’s current design guidance on Siting and Designing Windfarms in the Landscape5.
Following completion of the main baseline landscape and visual assessment, design objectives will be developed and used to evaluate a series of layout options. These layouts will be examined from key design viewpoints to assess and optimise the number, size and layout of the proposed turbines in relation to the landform of the site and surrounds as well as adjacent wind farm developments. The design iteration process will take account of other environmental and technical factors to establish the final layout for the proposed development.
The design optimisation process will be reported and illustrated in the Environmental Statement and in an accompanying Design and Access Statement.
3.2 Impact Assessments
The ES will report on the likely significant direct effects, along with any indirect, cumulative, short, medium and long-term, permanent and temporary, beneficial and adverse effects.
Impact assessment chapters will be provided under the following topic categories:
landscape and visual amenity;
ecology;
ornithology;
historic environment;
traffic, transport and access; and
noise.
Cumulative effects will be addressed under each topic chapter. Cumulative effects are defined as the potential additional changes caused by a proposed development in conjunction with other similar developments or as the combined effect of a set of developments, taken together. Figure 2 shows the location and status of operational, consented and proposed wind farms (tip height >50 m) which are the subject of a valid application within 35 km from the proposed development. A final list of developments relevant to the assessment of cumulative effects would be agreed when the point of a finalised design is reached (approximately four months from submission).
In addition, factual reports will be prepared to provide sufficient environmental information on:
hydrology and hydrogeology; and
forestry.
5 Scottish Natural Heritage, 2009 version 2 Siting and Designing windfarms in the landscape. [pdf] Scottish Natural Heritage. Available
at: <http://www.snh.gov.uk/docs/A337202.pdf> [Accessed 2 February 2016].
Scoping Report
Hopsrig Wind Farm
RUK12-22427_3_Scoping Report
6
The following sub-sections provide a review of proposed technical issues to be considered as part of the ES.
3.3 Landscape and Visual Amenity
A Landscape and Visual Impact Assessment (LVIA) will be undertaken to establish potential significant effects of the proposed development on the landscape resource and visual amenity of an area equivalent to a 35 km radius from the outermost turbines of the development. The assessment will also address potential cumulative landscape and visual effects within this area. The assessment will be undertaken in line with European and national legislation, policy and guidance. The relevant legislation, policy and guidance documents are provided in Appendix C: LVIA Supporting Information.
3.3.1 Baseline
Key Landscape and Visual Issues
According to the Dumfries and Galloway Wind Farm Landscape Capacity Study (2011) the proposed development lies within the Southern Uplands with Forest Landscape Character Type which is identified as having low landscape sensitivity and low to medium visual sensitivity to large wind farm typologies, and that it has potential to accommodate ‘multiple large and medium typologies’ with some provisos relating to the avoidance of open topped hills and areas of more complex landform. Figure 3 illustrates the Landscape Character Types within a 35 km study area.
The Capacity Study also states that the “landscape is very sparsely populated and not readily visible from the wider landscape being sited away from settled areas and public roads. Visual sensitivity would be Medium in relation to the large typology and Medium-low in relation to the medium typology. The majority of this landscape is not covered by landscape designations and this, together with an absence of recreational use or other non-designated interests, would result in Low sensitivity in respect of landscape values.”
The key landscape and visual consideration for the proposed development will be its relationship with the established and emergent cumulative context (Figure 2), including Craig Wind Farm, Ewe Hill Wind Farm, Crossdykes Wind Farm, and Loganhead Wind Farm.
Other considerations relate to the predicted visibility and potential prominence of the Hopsrig turbines, particularly from the nearby high sensitivity valley of the River Esk (Narrow Wooded River Valley landscape at the eastern end of the site) (Figure 3) and from the open summits of the North Langholm Southern Uplands (within the Langholm Hills Regional Scenic Area (RSA)) to the north east and east of the site. Consideration will also be given to effects associated with the removal of forestry and a revised forest design plan given the anticipated felling at the site.
Landscape designations and classifications will also be considered as part of the LVIA. As shown on Figure 4, the eastern part of the site lies within the Langholm Hills Regional Scenic Area. However, none of the proposed turbine locations are within the Regional Scenic Area boundary.
Viewpoint Selection
A range of visual receptors within the study area will be identified, which are anticipated to include residents of settlements and scattered dwellings, recreational receptors including hill walkers and cyclists, and road users. Initial Zone of Theoretical Visibility (ZTV) analysis has been carried out based on the scoping layout for the proposed development to identify a list of candidate viewpoints representative of the main landscape and visual receptors in the study area, and at varying distances, directions and elevations from the proposed development. In addition, cognisance has
Scoping Report
Hopsrig Wind Farm
RUK12-22427_3_Scoping Report
7
been taken of the viewpoint selection in the LVIA of Loganhead and Crossdykes Wind Farms. The proposed viewpoints are listed in Table 1 in Appendix C and illustrated on the ZTV shown on Figure 5. The final selection of viewpoints for assessment will be agreed with Dumfries and Galloway Council and Scottish Natural Heritage (SNH) during the consultation process.
3.3.2 Potential Significant Effects
The Landscape and Visual Impact Assessment will consider effects on:
landscape fabric, caused by changes to the physical form of the landscape and its elements; landscape character, caused by changes in the key characteristics and qualities of the landscape as a result of the proposed development, including consideration of effects on designated areas; and visual amenity, caused by changes in the appearance of the landscape as a result of the proposed development, considering receptors in settlements and residential property, motorists and other road users, rail passengers, core paths and other recreational receptors.
The layout will be tested to ensure that it reflects current SNH guidance on Siting & Designing Wind Farms in the Landscape6.
3.3.3 Issues to be Scoped Out
Given the limited geographical extent of the proposed development viewshed (based on the ZTV analysis), the LVIA will not consider effects on the following receptors:
Talla-Hart Fell Wild Land (25 km to the north west of the site);
Torthorwald Ridge RSA (21.6 km to the south west);
Solway Coast RSA (25.3 km to the south);
Hadrian’s Wall Path (25.3 km to the south); and
the Southern Upland Way (appears 12 km to the north west at its closest point within the ZTV).
3.3.4 Effects Evaluation
The aim of the LVIA is to identify, predict and evaluate potential landscape and visual effects arising from the proposed development and associated ancillary elements. Wherever possible, effects will be quantified, but the nature of landscape and visual assessment requires interpretation by professional judgement. In order to provide a level of consistency to the assessment, landscape sensitivity to change, the prediction of magnitude of change/impact and assessment of significance of the residual effects has been based on pre-defined criteria which are based on guidance provided in the GLVIA 37, as refined for the purposes of wind farm assessment and taking account of SNH guidance.
6 Scottish Natural Heritage, 2014. Siting and Designing Wind Farms in the Landscape. Version 2. [pdf] Scottish Natural Heritage. Available at: <http://www.snh.org.uk/pdfs/strategy/renewables/Guidance_Siting_Designing_wind_farms.pdf> [Accessed 1 February 2016]. 7 Landscape Institute and Institute of Environmental Management & Assessment, 2013. Guidelines for Landscape and Visual Impact
Assessment, 3rd ed. Abingdon: Routledge.
Scoping Report
Hopsrig Wind Farm
RUK12-22427_3_Scoping Report
8
Study Area
The currently proposed extension turbines are 135 m to blade tip height. Consequently, in accordance with SNH’s Visual Representation of Windfarms Good Practice Guidance8, the study area will be 35 km radius from the outer edges of the proposed turbines.
LVIA Visualisations
Appendix C contains details of the supporting visual material for the LVIA ES chapter.
3.3.5 Cumulative effects
SNH Cumulative Guidance9 states that the focus should be on the key cumulative effects which are likely to influence decision making, rather than an assessment of every potential cumulative effect.
Based on the above and on the cumulative data collected to date (based on preliminary assessment of the locations of these developments and their potential interaction with the proposed development), the following cumulative assessment scope for the proposed development LVIA is suggested:
cumulative base plan within 35 km search area;
inclusion of all sites, which are operational, consented, at application stage and any at scoping within 10 km of the proposed development, to the cumulative assessment;
exclusion of <50 m turbines in the assessment;
exclusion of developments in scoping, beyond 10 km from the site;
exclusion of single turbines beyond 15 km from the site; and
due to the distance/location from the proposed development the following wind farms, Dalswinton, Great Orton, Langhope Rig, Birneyknowe, are not expected to interact with the proposed development and therefore would be excluded from the cumulative assessment.
A provisional list of cumulative schemes within 35 km of the proposed development are listed in Table 2 in Appendix C and shown in Figure 2.
3.4 Ecology
The ecology chapter will assess the potential significant effects on non-avian ecology during the construction, operational and decommissioning phases of the proposed development. The ornithology assessment will be presented in a separate chapter.
3.4.1 Baseline
Ecology surveys to date have been conducted between May and October 2015 at the site. Field surveys following current best practice guidance have been undertaken at the site, including:
National Vegetation Classification (NVC) Survey10;
great-crested newt (GCN) Habitat Suitability Index (HSI) Assessment11;
8 Horner + MacLennan and Envision, 2006. Visual Representation of Wind farms: Good Practice Guidance. [pdf] Scottish Natural
Heritage. Available at: <http://www.snh.gov.uk/docs/A305436.pdf> [Accessed 1 February 2016]. 9 Scottish Natural Heritage, 2012. Assessing the Cumulative Impact of Onshore Wind Energy Developments. [pdf] Scottish Natural Heritage. Available at: <http://www.snh.gov.uk/docs/A675503.pdf> [Accessed 1 February 2016]. 10 Rodwell, J.S. ed., 1991-2000. British Plant Communities. (Vols 1-5). Cambridge: Cambridge University Press 11 Oldham, R.S., Keeble, J., Swan. M.J.S. and Jeffcote, M., 2000. Evaluating the Suitability of Habitat for the Great Crested Newt
(Triturus cristatus). Herpetological Journal, 10, pp.143-155.
Scoping Report
Hopsrig Wind Farm
RUK12-22427_3_Scoping Report
9
otter survey12 13 14;
water vole survey15;
badger survey16 17;
pine marten survey18;
red squirrel survey19;
bat activity surveys (including at height surveys)20 21;
bat roost surveys22 23; and
reptile habitat suitability survey24.
In addition, the results of the NVC survey will be referenced against SEPA guidance (2014a25 and 2014b26) to aid identification of those habitats which may be classified, depending on the hydrological setting, as being potentially groundwater dependent (Groundwater Dependent Terrestrial Ecosystems (GWDTE)).
Badgers Meles meles and common lizard Zootoca vivipara are known to use the site. Evidence of squirrels Sciurus sp. were observed; however it is not possible to determine the species from the field evidence recorded. Surveys also found common amphibians present; however, GCN Trituruscristatus are unlikely to be present. A range of bat species were recorded on site predominantly using the forest edges on the higher elevations on the northern and southern boundaries for foraging and commuting. Common pipistrelle Pipistrellus pipistrellus, soprano pipistrelle Pipistrellus pygmaeus, Myotis species, Nyctalus species and brown long-eared bats Plecotus auritus have all been recorded during the surveys.
12 Bang, P. and Dahlstrøm, P., 2001. Animal Tracks and Signs. Oxford: Oxford University Press. 13 Chanin, P., 2003. Monitoring the Otter (Lutra lutra). Conserving Natura 2000 Rivers Monitoring Series No.10. Peterborough: English
Nature. 14 Sargent, G. and Morris, P., 2003. How to Find and Identify Mammals. London: The Mammal Society. 15 Strachan, R., Moorhouse, T. and Gelling, M., 2011. The Water Vole Conservation Handbook. 3rd ed. Oxford: Wildlife Conservation Research Unit, Department of Zoology, University of Oxford. 16 Neal, E. and Cheeseman, C.L., 1996. Badgers. London: Poyser Natural History. 17 Bang, P. and Dahlstrøm, P., 2001. Animal Tracks and Signs. Oxford: Oxford University Press. 18 O’Mahony D., O’Reilly, C. and Turner, P., 2006. National Pine Marten Survey of Ireland 2005. [pdf] Dublin: Corford. Available at: < http://www.coford.ie/media/coford/content/publications/projectreports/cofordconnects/PineMarten.pdf> [Accessed 7 March 2016]. 19 Gurnell, J., Lurz, P., McDonald, R. and Pepper, H., 2009. Practical Techniques for Surveying and Monitoring Squirrels: Forestry
Commission Practice Note October 2009. [pdf] Edinburgh: Forestry Commission. 20 Hundt, L., 2012. Bat Surveys: Good Practice Guidelines. 2nd ed. London: Bat Conservation Trust. 21 Natural England, 2014. Bats and onshore wind turbines: Interim guidance. 3rd ed. [pdf] Natural England. Available at: <
publications.naturalengland.org.uk/file/6122941666295808> [Accessed 7 March 2016]. 22 Hundt, L., 2012. Bat Surveys: Good Practice Guidelines. 2nd ed. London: Bat Conservation Trust. 23 Natural England, 2014. Bats and onshore wind turbines: Interim guidance. 3rd ed. [pdf] Natural England. Available at: <
publications.naturalengland.org.uk/file/6122941666295808> [Accessed 7 March 2016]. 24 Edgar, P., Foster, J. and Baker, J., 2010. Reptile Habitat Management Handbook. Bournemouth: Amphibian and Reptile
Conservation. 25 SEPA (2014a). Land Use Planning System Guidance Note 4: Planning guidance on on-shore windfarm developments, Version 7. [pdf] SEPA. Available at: < http://www.sepa.org.uk/media/136117/planning-guidance-on-on-shore-windfarms-developments.pdf> [Accessed 1 February 2016]. 26 SEPA (2014b). Land Use Planning System Guidance Note 31: Guidance on Assessing the Impacts of Windfarm Development Proposals
on Groundwater Abstractions and Groundwater Dependent Terrestrial Ecosystems, Version 2. [pdf] SEPA. Available at: < http://www.sepa.org.uk/media/144266/lups-gu31-guidance-on-assessing-the-impacts-of-development-proposals-on-groundwater-abstractions-and-groundwater-dependent-terrestrial-ecosystems.pdf> [Accessed 2 February 2016].
Scoping Report
Hopsrig Wind Farm
RUK12-22427_3_Scoping Report
10
3.4.2 Potential Significant Effects
Taking account of the findings of the work undertaken to date, whilst still adopting a precautionary approach at this preliminary stage, potential effects associated with the construction and operation of the proposed development include:
direct and indirect habitat loss;
disturbance to / loss of breeding sites, resting places, etc.;
direct / indirect loss of foraging resource;
displacement / disruption to movement of animals within / through the site;
direct effects upon protected fauna, i.e. road traffic accidents, etc.;
environmental effects, i.e. pollution of watercourses, etc.; and
changes to habitat composition through land-use change, increased human presence, etc.
In addition to the above, the habitats that fall under SEPA GWDTE categories will be assessed for their potential groundwater dependency based on the vegetation, topography and hydrological setting. If present, potential impacts to GWDTEs will be assessed and considered within the design, with mitigation measures proposed, where appropriate. A technical appendix to address the hydrogeology effects on GWDTE will be provided as an appendix to the Ecology chapter in line with SEPA LUPS Guidance Notes 4 and 31.
3.4.3 Issues to be Scoped Out
There are no international, national or local designated sites with non-avian ecological qualifying species within 5 km of the site. Effects on designated sites will therefore be scoped out of the assessment. Sites designated by Dumfries and Galloway Council, e.g. Sites of Importance to Nature Conservation (SINC) or similar, within 5 km of the site will be requested as part of the desk study, and assessed accordingly. Figure 6 shows the location of ecological and ornithological designated sites within 20 km of the site.
Sites designated for ornithological interests will be dealt with in the ornithology chapter.
Following the results of the GCN HSI assessment, the ponds on the site are not considered suitable to support GCN. The waterbodies on site are acidic, contain waterfowl and possibly fish; and they lack suitable submerged vegetation and surrounding terrestrial habitat. Full results of the survey will be detailed in the associated technical report; however GCN will be scoped out of the ecology chapter.
In addition, it is proposed that fish and fisheries are scoped out of the EIA. The Boyken Burn flows through the site and into the River Esk approximately 2 km downstream of the site. Although the banks are poached by livestock along some reaches, the majority of the habitat is considered to be suitable for a variety of salmonid and lamprey species. It is acknowledged that there is the potential for accidental events including the discharge of silt contaminated surface water or hydrocarbon/chemical spill from construction areas into the Boyken Burn and River Esk catchment. However the Construction Environmental Management Plan for the proposed Hopsrig wind farm would be designed to incorporate good practice measures to control surface water run-off rate and water quality, and to implement good practice pollution prevention measures. As a result of accepted and robust measures being put in place, there would be no likely significant direct or indirect effects on aquatic species during construction, operation and decommissioning.
Scoping Report
Hopsrig Wind Farm
RUK12-22427_3_Scoping Report
11
3.4.4 Additional Baseline Information Collection
The following organisations will be contacted for information and advice to inform the impact assessment: Dumfries and Galloway Council, SNH, Dumfries and Galloway Environmental Resource Centre, Scottish Badgers, Dumfries and Galloway Bat Group and the Dumfries and Galloway Amphibian and Reptile Group.
The desk study will gather ecological information (including relevant designated sites) from a variety of online sources and consultation with conservation organisations. In addition to those organisations listed above, the following will be consulted:
National Biodiversity Network NBN Gateway27 (http://data.nbn.org.uk/);
Scottish Natural Heritage, including Sitelink (http://gateway.snh.gov.uk/sitelink/index.jsp); and
Other available research into applicable habitats and species.
No further ecological surveys are proposed.
3.4.5 Effects Evaluation
The assessment will be undertaken in line with European and national legislation, policy and guidance. The relevant legislation policy and guidance documents are provided in Appendix D: Ecology Supporting Information.
The assessment process involves the following:
identification of the potential effects of the proposed development;
consideration of the likelihood of occurrence of potential effects where appropriate;
defining the Nature Conservation Value of the ecological receptors present;
establishing the receptor’s Conservation Status;
establishing the Magnitude of the likely effect (both spatial and temporal);
based on the above information, a professional judgement as to whether or not the identified effect is significant with respect to the EIA Regulations;
if a potential effect is determined to be significant, measures to mitigate or compensate for the effect will be presented;
opportunities for enhancement may be considered; and
residual effects after mitigation, compensation or enhancement are reported.
3.4.6 Cumulative effects
Cumulative effects require the assessment of additional effects when the proposed development is considered in combination with other developments. The context in which these effects are considered is heavily dependent on the ecology of the receptor assessed but in all cases will involve consideration of the cumulative effects upon the receptor extents/populations relevant to that receptor. For example, for water voles it may be appropriate to consider effects specific to individual catchments or metapopulations, should the distance between neighbouring catchments be sufficient to assume no movement of animals between them.
27 Please note that taxa/species shown on the NBN Gateway will not be listed due to NBN restrictions imposed relating to the use of
such data. (All material, data and/or information on the NBN website are protected by copyright, database rights and other intellectual property rights). The NBN information has been utilised solely to provide an assessment of the likely presence of such species/taxa on site based on the presence of recent (within 10 years) records within a 5km radius from the site central grid reference.
Scoping Report
Hopsrig Wind Farm
RUK12-22427_3_Scoping Report
12
3.5 Ornithology
The ornithology chapter will assess the potential significant effects on ornithology during the construction, operational and decommissioning phases of the proposed development.
3.5.1 Baseline
Ornithology surveys were initiated in May 2015, are ongoing through the 2015/2016 non-breeding season (i.e. September 2015 to mid-March 2016) and will continue through the 2016 breeding season. The survey results to date have revealed that the proposed development site appears to be of low importance for target bird species (target species are those considered to be at risk due to wind farm development).
Bird surveys following current best practice guidance have been undertaken at the site, these comprise:
flight activity (Vantage Point) surveys (from May 2015 and ongoing): One breeding season of survey data has been collected, and non-breeding season data collection is ongoing; within the site and surrounding area. Three vantage points provide coverage of the turbine area;
breeding bird surveys: 2015 breeding season within the site and 500 m buffer (where access permitted), with four survey visits following the Brown & Shepherd (199328) methodology and considering the recommendations set out in Calladine et al. (200929);
breeding raptor and owl surveys: 2015 breeding season within the site and 2 km buffer (where access permitted), following the methods described in Hardey et al. (201330);
black grouse Tetrao tetrix surveys: 2015 breeding season within the site and 1.5 km buffer (where access permitted), following guidance in Gilbert et al. (199831); and
winter walkovers: ongoing during the 2015/2016 non-breeding season within the site and 500 m buffer (where access permitted).
Very little breeding bird activity was recorded during the 2015 breeding season; this may be in part due to the adverse weather conditions during the early part of the breeding season, causing breeding failures. Snow falls and frost conditions occurred irregularly into late April and early May in 2015. Breeding waders were recorded in low numbers, with 1-2 territories each for curlew Numenius arquata, snipe Gallinago gallinago and oystercatcher Haematopus ostralegus. Overall there was a low level of site usage by foraging raptors, mainly by buzzard Buteo buteo and sparrowhawk Accipiter nisus. Buzzard bred close to the site, and sparrowhawk and kestrel Falcotinnunculus are likely to breed nearby. Roosting barn owl Tyto alba were also recorded within, and close to, the site, but there was no evidence of breeding.
Ongoing winter surveys also indicate the site to be of low importance to any migratory or over-wintering species, with only single flights recorded to date for golden plover Pluvialis apricaria and pink-footed geese Anser brachyrhynchus. The most frequently encountered species during the winter, and all year round, is buzzard.
28 Brown, A. F. and Shepherd, K. B. 1993. A method for censusing upland breeding waders. Bird Study, 40(3), pp.189-195. 29 Calladine, J., Garner, G., Wernham, C. and Thiel, A., 2009. The influence of survey frequency on population estimates of moorland
breeding birds. Bird Study, 56(3), pp.381-388. 30 Hardy, J., Crick, H., Wernham, C., Riley, H., Etheridge, B. and Thompson, D., 2013. Raptors: A field guide for surveys and monitoring. 2nd ed. Edinburgh: The Stationery Office. 31 Gilbert, G., Gibbons, D. W. and Evans, J., 1998. Bird Monitoring Methods: A manual of techniques for key UK species. Exeter: Pelagic
Publishing.
Scoping Report
Hopsrig Wind Farm
RUK12-22427_3_Scoping Report
13
The following designated sites are located within 20 km32 of the site and are designated for their ornithological interests (relevant features in brackets):
Langholm – Newcastleton Hills Special Protection Area (SPA): (designated for breeding hen harrier Circus cyaneus). Approximately 10 km east;
Langholm – Newcastleton Hills Site of Special Scientific Interest (SSSI): (designated for breeding hen harrier and breeding bird assemblage). Approximately 10 km east;
Castle Loch, Lochmaben (SPA & Ramsar): (designated for pink-footed goose, non-breeding). Approximately 20 km to the south-west; and
Castle Loch, Lochmaben (SSSI): (designated for pink-footed goose, greylag goose Anser anserand goosander Mergus merganser, all non-breeding). Approximately 20 km to the south-west.
3.5.2 Potential Significant Effects
Taking account of the findings of the work undertaken to date in the local area, whilst still adopting a precautionary approach at this preliminary stage, potential effects on birds associated with the construction and operation of the proposed development include:
a short-term reduction in breeding or wintering bird populations due to construction disturbance (affecting breeding or foraging behaviour and causing reductions in productivity or survival);
a long-term reduction in breeding or wintering bird populations due to the loss of habitat critical for nesting or foraging. This may arise as a consequence of direct loss of habitat under infrastructure or disturbance/displacement as a result of operational activities;
a long-term reduction in breeding or wintering bird populations due to collision mortality. If collision risk is identified as a concern, predicted collision rates will be calculated through theoretical collision risk modelling; and
cumulative effects with other projects or activities that are constructed during the same period, and / or with projects or activities which pose either a potential collision risk or loss of habitat by displacement.
Given the low levels of activity recorded to date, it is considered unlikely that significant effects will occur on ornithological receptors at the site, although this issue will be considered in detail as part of the EIA.
3.5.3 Issues to be Scoped Out
As bird surveys and data collection are ongoing, and despite the site appearing to be of low ornithological interest, it is not possible to scope out specific potential effects on any target species, or target species within the wider countryside, at this stage.
Effects on the Langholm – Newcastleton Hills SSSI and SPA, designated for breeding Hen Harrier, are scoped out. No hen harrier were recorded during any surveys during the breeding season, the habitats are unsuitable for nesting hen harrier, and as the majority of the site is mature commercial conifer plantation it is of limited foraging value. Furthermore, it is considered that there is unlikely to be any connectivity between the proposed development and the SSSI/SPA as these designated sites are approximately 10 km from the site. During the breeding season hen harriers have a core foraging range of 2 km (SNH, 201333). Breeding females hunt mostly within 1
32 Distances provided here are approximate until the final turbine layout is confirmed. 33 Scottish Natural Heritage, 2013. Assessing Connectivity with Special Protection Areas (SPAs). [pdf] Scottish Natural Heritage. Available at: <http://www.snh.gov.uk/docs/A994842.pdf> [Accessed 2 February 2016].
Scoping Report
Hopsrig Wind Farm
RUK12-22427_3_Scoping Report
14
km of the nest site with males foraging generally within 2 km, average home ranges during the breeding season are of the order of 8 km2 for males and 4.5 km2 for females, often with overlap in foraging areas of different pairs (Arroyo et al. 201434). Any assessment of potential effects on hen harrier will be considered in the context of the wider countryside population, unrelated to the SPA and SSSI.
All effects on the Castle Loch, Lochmaben SSSI, SPA and Ramsar are scoped out given their ornithological qualifying species as listed above (many of which have not been recorded during surveys, and with only a single flight of pink-footed geese to date), and the distance of these designated sites from the proposed development (approximately 20 km). The proposed development is also on the edge of, or outwith, the core foraging ranges for the species for which these sites have been designated (SNH, 201333). Further information provided in Mitchell (201235)indicates that Castle Loch, Lochmaben SPA no longer holds internationally important numbers of geese. Additionally, the sensitivity maps within Mitchell (201235) show that the distribution of geese at this SPA and their feeding locations are clustered immediately north of Castle Loch or to the south along the coast of the Solway Firth, no data indicates that any geese from Castle Loch move east towards the site area. Consequently it is considered that there is no connectivity between the site and Castle Loch, Lochmaben SSSI, SPA and Ramsar designations.
3.5.4 Additional Baseline Information Collection
The following organisations will be contacted for information and advice to inform the impact assessment: Dumfries and Galloway Council, Royal Society for the Protection of Birds (RSPB), SNH, Dumfries and Galloway Environmental Resource Centre, the Scottish Wildlife Trust and the Dumfries and Galloway Raptor Study Group. To gather further ornithological information, including designated sites, online sources will be consulted, including National Biodiversity Network NBN Gateway27 (http://data.nbn.org.uk/) and SNH, including Sitelink (http://gateway.snh.gov.uk/sitelink/index.jsp).
In addition, ornithological information available in the public domain relating to relevant applications of local wind farm projects in proximity of the site will be referred to (e.g. Loganhead Wind Farm, Crossdykes Wind Farm and Ewe Hill Wind Farm). This information includes scoping reports, environmental statements and consultation responses from relevant stakeholders.
Following completion of the 2015/2016 non-breeding season surveys, a further breeding season of surveys will be carried out over spring and summer 2016. These surveys will consist of the following:
flight activity (Vantage Point) surveys from three vantage points, 36 hours of data to be collected from each Vantage Point;
breeding bird surveys: within the site and 500 m buffer (where access permitted);
breeding raptor and owl surveys: within the site and 2 km buffer (where access permitted); and
black grouse surveys: within the site and 1.5 km buffer (where access permitted).
34 Arroyo, B.E., Leckie, F., Amar, A., McCluskie, A. and Redpath, S., 2014. Ranging behaviour of Hen Harriers breeding in SpecialProtection Areas in Scotland. Bird Study 1(8), pp.48-55. 35 Mitchell, C., 2012. Mapping the distribution of feeding Pink-footed and Iceland Greylag Geese in Scotland. [pdf] Slimbridge: Wildfowl
& Wetlands Trust / Scottish Natural Heritage. Available at: <http://monitoring.wwt.org.uk/wp-content/uploads/2013/07/FeedingDistribution_PGGJScot_2012.pdf> [Accessed 2 February 2016].
Scoping Report
Hopsrig Wind Farm
RUK12-22427_3_Scoping Report
15
It is considered that 18 months of survey effort (i.e. two breeding seasons and one non-breeding season) is sufficient to allow a robust characterisation of the baseline ornithological assemblage and usage of the proposed development site and surrounding area. Data collection for a second non-breeding season is not considered necessary given the low importance of the site for any migratory or over-wintering target species, the low levels of bird activity recorded, the low value habitats present for such species, and the absence of any connectivity with relevant designated sites (as detailed above). The data collected so far for the proposed development is also consistent with the findings presented as part of the Environmental Statements for the neighbouring Loganhead and Crossdykes Wind Farms (Muirhall Energy), which indicate low levels of bird activity for target species. The SNH response to the pre-scoping briefing note advises that the scope of surveys appears appropriate and the methods employed are consistent with SNH guidance.
3.5.5 Effects Evaluation
Effects on target species will be assessed in relation to the species’ reference population, range and distribution. The assessment of potential effects will follow guidelines published by the Institute of Ecology and Environmental Management (IEEM, 200636) and SNH (200637). The assessment will be undertaken in line with European and national legislation, policy and guidance. The relevant legislation policy and guidance documents are provided in Appendix E: Ornithology Supporting Information.
The evaluation for wider-countryside interests (interests unrelated to SPAs, but including SSSIs) involves the following process:
identification of the potential effects of the proposed development;
consideration of the likelihood of occurrence of potential effects where appropriate;
defining the Nature Conservation Value of the bird populations present;
establishing the population’s Conservation Status;
establishing the Magnitude of the Likely Effect (both spatial and temporal);
based on the above information, a judgement is made as to whether or not the identified effect is significant with respect to the EIA Regulations;
if a potential effect is determined to be significant, measures to mitigate or compensate the effect are suggested where required;
opportunities for enhancement are considered where appropriate; and
residual effects after mitigation, compensation or enhancement are reported.
Nature Conservation Value is defined on the basis of the geographic scale, and it is necessary to consider each receptor’s conservation status, its distribution and its population trend based on available historical records.
The significance of potential effects is determined by integrating the assessments of Nature Conservation Value and Magnitude in a reasoned way.
36 Institute of Ecology and Environmental Management, 2006. Guidelines for Ecological Impact Assessment in the United Kingdom. [pdf] Institute of Ecology and Environmental Management. Available at: <http://www.cieem.net/data/files/Resource_Library/Technical_Guidance_Series/EcIA_Guidelines/TGSEcIA-EcIA_Guidelines-Terestrial_Freshwater_Coastal.pdf> [Accessed 2 February 2016]. 37 Scottish Natural Heritage, 2006. Assessing significance of impacts from onshore windfarms on birds outwith designated areas. [pdf]
Scottish Natural Heritage. Available at: <http://www.snh.org.uk/pdfs/strategy/renewable/Significance%20of%20bird%20impacts%20July%2006.pdf> [Accessed 2 February 2016].
Scoping Report
Hopsrig Wind Farm
RUK12-22427_3_Scoping Report
16
A set of pre-defined significance criteria will be used in assessing the effects of the proposed development. It is necessary to establish whether there will be any effects which will be sufficient to adversely affect the receptor to the extent that its conservation status deteriorates above and beyond that which would be expected should baseline conditions remain (i.e. the ‘do nothing’ scenario). Furthermore, these predictions will be given with a level of confidence relative to the effect being assessed where required (in line with IEEM, 2006).
3.5.6 Cumulative effects
An assessment of cumulative effects will be undertaken following published guidance (SNH 201238). Cumulative effects on each receptor relevant to this proposed development will be assessed in relation to other projects and activities subject to the EIA process within a relevant search area, and their effects on a relevant reference population (for example at a Natural Heritage Zone level).
3.6 Historic Environment
3.6.1 Baseline
All heritage assets within a distance of up to 1 km from the site and all designated assets within 5 km of the site have been identified from available online records and historic Ordnance Survey mapping. All heritage assets noted within this report and shown on Figure 7 and Figure 8 are detailed in the Site Gazetteer39. There are 44 known heritage assets located within the site (Figure 7). The west, forested part, of the site has relatively few recorded heritage assets; a building associated with enclosures and lazy beds at Eild Beck (Site 2) and buildings at Boykenhopehead (Site 197). The remaining six assets within the west of the site are sheepfolds (Sites 3, 198, 203 and 210) and sheep shelters (Site 211 and 212) identified from historic mapping. In contrast, the east of the site is richer in archaeological and architectural remains and contains 36 heritage assets representative of Iron Age to post-medieval settlement. The identified assets include six Scheduled Ancient Monuments; Site 40, Boyken Burn, township 695 m W of Westerhall; Site 28, Old Hopsrigg, farmstead 700 m SW of; Site 34, Calkin, settlements and cultivation terraces 300 m N of; Site 37, Calkin, settlement 300 m E of; Site 24, Calkin, settlement, farmstead and linear earthworks 500 m SSE of, and Site 22, Calkin, farmstead 500 m WSW of). These monuments are part of the Boyken Burn Archaeologically Sensitive Area (ASA) (Figure 7) described as an exceptional cluster of multi-period remains and protected under Policy HE4: Archaeologically Sensitive Areas of the Dumfries and Galloway Local Development Plan4041.Additionally there are three Listed Buildings (Sites 55, 63 and 105) located on the eastern boundary of the site.
In addition to the Scheduled Monuments within the site there are 63 Scheduled Ancient Monuments located within the 5 km study area (Figure 8) and a further 49 Scheduled Monuments located between 5 km and 10 km of the site. The Conservation Area of Langholm, which contains 41 Listed Buildings is located 7.5 km southeast of the site, while an 89 additional Listed Buildings
38 Scottish Natural Heritage, 2012. Assessing the cumulative effects of onshore wind energy developments. [pdf] Scottish Natural
Heritage. Available at: <http://www.snh.gov.uk/docs/A675503.pdf> [Accessed 2 February 2016]. 39 Site Gazetteer will be sent to Historic Environment Scotland and Dumfries and Galloway Council. Available on request for otherconsultees. 40 Dumfries and Galloway Council, 2014a. Dumfries and Galloway Council Local Development Plan. [pdf] Dumfries and Galloway Council. Available at: <http://www.dumgal.gov.uk/CHttpHandler.ashx?id=11287> [Accessed 2 February 2016]. 41 Dumfries and Galloway Council, 2014b. Dumfries and Galloway Council Local Development Plan Technical Paper: Archaeologically
Sensitive Areas (ASAs). [pdf] Dumfries and Galloway Council. Available at: http://www.dumgal.gov.uk/CHttpHandler.ashx?id=11778&p=0 [Accessed 2 February 2016].
Scoping Report
Hopsrig Wind Farm
RUK12-22427_3_Scoping Report
17
(or elements of Listed Buildings) are located within 5 km. Of these, five are Category A Listed. There is a non-inventory locally designated designed landscape at Westerhall near Bentpath east of the site. The Tanlawhill ASA is located north-west of the site and within the 5 km study area. A further two ASA’s, Raeburnfoot and Dryfe Water, are located within 10 km of the site.
3.6.2 Potential Significant Effects
Construction of the proposed development has the potential to disturb, damage or destroy hitherto unknown features or buried remains of cultural heritage interest. Other construction activities, such as vehicle movements, soil and overburden storage and landscaping also have the potential to cause direct permanent and irreversible effects on cultural heritage assets. It is probable that modern forestry operations will have, to some degree, damaged archaeological remains within the west of the site. However, the east of the site has remained undisturbed in recent years and is rich in archaeological remains as recognised by its local designation as an ASA.
As Scheduled Monuments, Sites 22, 24, 28, 34, 37 and 40 as identified above are afforded statutory protection under the provisions of the Ancient Monuments and Archaeological Areas Act 197942 modified by the Historic Environment (Amendment) (Scotland) Act 201143. The boundary of each Scheduled Monument is shown on Figure 8. Any works within the boundary of these Scheduled Monuments would require Scheduled Monument Consent (SMC) from Historic Environment Scotland (HES). The works which require SMC are comprehensively defined in the 1979 Act and summarised as any works that result in demolition, destruction or damage, removal, repair, alteration or addition, flooding or tipping. It is assumed that proposed development works will avoid the Scheduled Monuments and as such impacts on the Scheduled Monuments will be limited to indirect effects on their settings.
Indirect effects include impacts upon the setting of designated assets such as Listed Buildings, Scheduled Monuments, Conservation Areas and Inventory Gardens and Designed Landscapes as well as non-designated assets identified as being of potentially nationally important in the Dumfries and Galloway Historic Environment Record (HER). Depending upon the final turbine layout and configuration there is the potential that a number of the assets in the vicinity of the site could be subject to impacts upon their settings. Such assets include the six aforementioned Scheduled Monuments within the site itself as well as those within the study area including the hill forts at Little Hill (Site 71) Camp Hill (Site 171) Newland Hill (Site 175) and Craighousesteads (Site 177) and the cluster of Monuments within the Tanlawhill ASA north of the site. The level and significance of settings effects will be determined following full analysis of the ZTV and site visits to identify the setting of each asset. Where appropriate, analysis of visualisations will also inform the assessment of indirect effects.
3.6.3 Issues to be Scoped Out
The proposed development will seek to avoid direct impacts upon any known heritage assets during construction though careful siting of infrastructure and, where appropriate, fencing off of known heritage assets. Direct effects on known heritage assets will therefore be scoped out of the assessment.
There are no World Heritage Sites, Inventory Gardens and Designed Landscapes or Inventory Battlefields located within the 10 km study area. Potential effects on designated assets within these categories will therefore be scoped out of the assessment. The Conservation Area of
42 The Ancient Monuments and Archaeological Areas Act 1979. (c.46). London: HMSO. 43 Historic Environment (Amendment) (Scotland) Act 2011. London: HMSO).
Scoping Report
Hopsrig Wind Farm
RUK12-22427_3_Scoping Report
18
Langholm and the 91 Listed Buildings (or elements thereof) contained within and immediately around the settlement are located outwith the provisional ZTV (see Figure 8). Settings effects on these 91 assets will therefore be scoped out of the assessment, provided they remain outwith the final ZTV. There are no other Conservation Areas within 10 km of the site.
3.6.4 Additional Baseline Information Collection
Further desk-based assessment will be undertaken to collate known archaeological information on the site and identify any previously unknown archaeological features through inspection of aerial photographic records and cartographic records. The results of the desk-based assessment, along with the walkover survey (see below) will be used to identify areas where the proposed development may impact on the assets identified or elements of the historic environment and will be used to inform the iterative design process and, if necessary, to facilitate consultation with HES and Dumfries and Galloway Archaeology Service.
Subject to the ZTV and consultation with Historic Environment Scotland and the Dumfries and Galloway Archaeology Service, assets located between 5 km and 10 km of the proposed development which have the potential to be significantly affected by the proposed development will be identified and assessed in full within the ES.
Sources to be consulted for the collation of data will include:
Dumfries and Galloway Historic Environment Record (HER);
The National Monuments Record of Scotland (HES);
Ordnance Survey maps (principally First and Second Edition), and other published historic maps held in the Map Library of the National Library of Scotland;
Unpublished historic maps and documents held by the National Archives of Scotland;
Vertical and oblique aerial photographs held by HES;
Published bibliographic sources, including historical descriptions of the area (Statistical Accounts, Parish Records);
The Scottish Palaeoecological Database; and
The Historic Land-use Assessment Data (HLAMap) for Scotland (HES).
The collation of baseline information will be conducted in accordance with the Chartered Institute for Archaeologists’ ‘Code of Conduct’44 and ‘Standard and Guidance for Historic Environment Based Desk-Based Assessment’45.
An archaeological walkover survey of the site will be undertaken with the aim of identifying any previously unknown remains. The site will be surveyed, where breaks in the forestry allow, along transects. All accessible known heritage assets will be assessed in the field to establish their survival, extent, significance and relationship to other assets. Weather and any other conditions affecting visibility during the survey will also be recorded. All heritage assets encountered will be recorded and photographed. Hand-held Global Positioning System (GPS) will be used to note and confirm the position of each asset. All assets will be marked on plans, at a relevant scale keyed by means of Grid References to the Ordnance Survey mapping.
44 Chartered Institute for Archaeologists, 2014b. Code of conduct. [pdf] Chartered Institute for Archaeologists. Available from: <http://www.archaeologists.net/sites/default/files/CodesofConduct.pdf> [Accessed 2 February 2016]. 45 Chartered Institute for Archaeologists, 2014a. Standards and Guidance for historic environment desk-based assessment. [pdf]
Chartered Institute for Archaeologists. Available from: <http://www.archaeologists.net/sites/default/files/CIfAS&GDBA_2.pdf>[Accessed 2 February 2016].
Scoping Report
Hopsrig Wind Farm
RUK12-22427_3_Scoping Report
19
3.6.5 Effects Evaluation
Having established the heritage baseline, an assessment of the potential direct and indirect effects of the proposed development on the historic environment will be undertaken.
The assessment will be undertaken in line with relevant policy and guidance. The relevant legislation, policy and guidance documents are provided in Appendix F: Cultural Heritage Supporting Information. The approach to the assessment will involve establishing the value and importance of the heritage receptor and then assessing the sensitivity of the asset to change. A judgement regarding the impact magnitude that may be experienced will be made. Further information on the detailed significance criteria proposed for use in the assessment are provided in Appendix F: Cultural Heritage Supporting Information.
The proposed development has the potential to affect the setting of cultural heritage assets within the study area. An asset’s sensitivity to impacts upon its setting refers to its capacity to retain its cultural value in the face of changes to that setting. Assets with high sensitivity will be vulnerable to changes which affect their settings and even slight changes may reduce their value or the ability of their settings to contribute to the understanding, appreciation and experience of that asset. Less sensitive assets will be able to accommodate greater changes to their settings without significant reduction in their cultural value and in spite of such changes the relationship between the asset and its setting will still be legible. Where there is the potential for the proposed development to impact upon the setting of an asset, the asset’s setting will be defined as will the sensitivity of that setting to changes. Assessment of individual assets will be informed by knowledge of the asset itself; of the asset type, if applicable, and by site visits to establish the current setting of the assets. This will allow for the use of professional judgement and each asset will be assessed on an individual basis. The criteria proposed for assessing the significance of setting effects is detailed in Appendix F: Cultural Heritage Supporting Information.
3.6.6 Cumulative effects
Cumulative effects on cultural heritage assets will be assessed, taking into consideration the additional effects of the proposed development on the settings of both designated and non-designated assets within 10 km of the site in combination with the likely effects of other operational, consented and proposed wind farm developments (at the application stage). Those heritage assets which have been included in the detailed setting assessment, under operational effects for the proposed development, will be considered when assessing the potential for cumulative effects. However, only those assets which were judged to have the potential to be subject to significant cumulative effects will be included in the detailed cumulative assessment.
The assessment will take into account the relative scales (i.e. size and number of turbines) of the other developments, their distances from the affected assets and the potential degree of visibility to the various developments. While all turbines >50 m to tip within 15 km will be considered, only those which contribute to, or have the possibility to contribute to, cumulative effects on specific heritage assets will be discussed in detail in the text.
3.7 Hydrology, Hydrogeology and Geology,
3.7.1 Baseline
Hydrology
As identified during the desk-based survey, and during the initial site visit, the site is drained by a number of small burns, including Trough Burn, Eild Beck, Clackanna Sike and Auchenbeg Sike;
Scoping Report
Hopsrig Wind Farm
RUK12-22427_3_Scoping Report
20
these mainly form tributaries to the Boyken Burn. The Boyken Burn flows into to the River Esk, located adjacent to the east of the site. A small reservoir is also located within the site adjacent to the existing track, which is supplied by Wet Sike and Yadlairs Sike. The existing track traverses across an earth dam structure. Hydrological constraints are mapped on Figure 9.
According to the SEPA’s River Basin management Plan (RBMO) Interactive Map46, the River Esk was classified as having Good overall status with High confidence in 2008 with overall ecological status of Good and overall chemical status of Pass.
A review of the SEPA Indicative River & Coastal Flood Map47 shows that areas at risk of flooding within the site and its vicinity are confined to the areas alongside the Boyken Burn.
There is one private water supply (PWS) located on the eastern site boundary, Carlesgill PWS, (NGR NY 32700 87600) which serves Burn Cottage (NGR NY 33263 87956). There are no PWS abstractions located within 2 km of the proposed turbines (the nearest turbine, turbine 14, is located 2.1 km from North Lodge PWS (NGR NY 31500 90600)).
Hydrogeology
The site is located over two major aquifers according to the 1:625,000 UK Digital Hydrogeological Data; Hawick group and Riccarton Group. Both of these are low productivity aquifers in which flow is virtually all through fractures and other discontinuities.
Geology
According to the Geology of Britain viewer (online)48 small areas of peat are located within, adjacent and in close proximity to the site, with larger areas of Diamicton (Langholm Till Formation) located within and near the site.
A peat probing survey comprising 351 peat probe locations was completed for the site targeting provisional turbine locations and areas of peat identified on the BGS 1:50000 scale superficial deposits map. A small area of deeper peat was recorded on the western boundary of the site, with a maximum depth recorded of 3.8 m, however no turbines are to be located in this area. Generally, peat was found to be shallow across the remainder of the site and modified within the plantation forestry areas, consistent with the BGS 1:50000 scale mapping. Peat deposits are known to be in the range 1.6 m to 2.9 m on Calkin Rig49. The peat probe locations and results are illustrated by Figure 10.
3.7.2 Potential Significant Effects / Issues to be Scoped Out
It is acknowledged that there is the potential for an increase in the rate of runoff associated with the proposed development, and /or accidental events including the discharge of silt contaminated surface water or hydrocarbon/chemical spill from construction areas into the River Esk catchment. However the proposed Hopsrig wind farm would be designed to incorporate good practice measures to control surface water run-off rate and water quality, and to implement good practice pollution prevention and environmental management measures. As a result, there would be no likely significant direct or indirect effects. As such, we would seek to scope out a detailed impact assessment chapter for Hydrology and Hydrogeology from the Environmental Statement (ES). We
46 SEPA, 2011. RBMP Interactive Map. [online] Available at: <http://gis.sepa.org.uk/rbmp/> [Accessed 2 February 2016]. 47 SEPA, 2015. Flood Maps. [online] Available at: <http://map.sepa.org.uk/floodmap/map.htm> [Accessed 2 February 2016]. 48 British Geological Survey, n.d. [online] Available at <http://mapapps.bgs.ac.uk/geologyofbritain/home.html> [Accessed 2 February 2016]. 49 Muirhall Energy Ltd (2015) Loganhead Wind Farm Environmental Statement, Figure 8.3: Peat Depth.
Scoping Report
Hopsrig Wind Farm
RUK12-22427_3_Scoping Report
21
would however propose to provide information on hydrology and hydrogeology to the extent necessary to satisfy SEPA’s requirements for information on:
pollution prevention and environmental management – we will include outline details of a proposed Construction Environmental Management Plan within the description of the proposed development;
engineering in the water environment - we will provide a water crossing schedule and information on flood risk as an appendix to the project description;
information on peat characteristics, extent, proposed excavation, surplus and re-use options would be provided in a stage 1 peat management plan in line with SEPA guidance50 as an appendix to the Proposed Development Chapter; and
Ground Water Dependent Terrestrial Ecosystems (GWDTE) - we will provide a technical appendix to address the hydrogeology effects on GWDTE as an appendix to the Ecology chapter in line with SEPA LUPS guidance 4 and 31.
Given that there are no PWSs within 250 m of proposed tracks or turbines there will be no requirement for detailed risk assessment for PWS abstractions (in line with SEPA LUPS guidance 4 and 31).
Only areas alongside the Boyken Burn are mapped as being at risk from flooding within the site on the SEPA Flood Map. Therefore, a Drainage Impact Assessment and Flood Risk Assessment are not considered necessary.
3.8 Traffic, Transport and Access
The traffic, transport and access assessment will consider the likely significant effects of the proposed development on the transport network as a result of an intensification in traffic levels as a consequence of construction traffic.
The assessment will be carried out in accordance with the relevant policy and guidance documents including the Guidelines for Traffic Impact Assessment51, IEMA Guidelines for the Environmental Assessment of Road Traffic52 (“the IEMA Guidelines”), Transport Assessment Guidance53; and the Design Manual for Roads & Bridges (DMRB)54.
A review of published transport plans and planning policies for the area will be undertaken.
Other more specific records will also be sourced, such as data on traffic levels, accident records and details of any vehicle route weight restrictions.
A site visit will also be used to inform the traffic, transport and access assessment.
50 Developments on Peatland: Guidance on the Assessment of Peat Volumes, Reuse of Excavated Peat and Minimisation of Waste, Version 1 (2012) Scottish Renewables & SEPA 51 The Institution of Highways and Transportation, 1994. Guidelines for Traffic Impact Assessment. London: The Institution. 52 Institute of Environmental Assessment, 1993. Guidelines for the Environmental Assessment of Road Traffic, Guidance Note 1.Institute of Environmental Assessment. 53 Transport Scotland, 2012. Transport Assessment Guidance. [pdf] Glasgow: Transport Scotland. Available from: <http://www.transport.gov.scot/sites/default/files/private/documents/tsc-basic-pages/Planning_Reform_-_DPMTAG_-_Development_Management__DPMTAG_Ref__17__-_Transport_Assessment_Guidance_FINAL_-_June_2012.pdf> [Accessed 2 February 2013]. 54 Highways Agency, 2008. Design Manual for Roads Bridges. [pdf] Highways Agency. Available at:
<http://www.standardsforhighways.co.uk/dmrb/> [Accessed 2 February 2016].
Scoping Report
Hopsrig Wind Farm
RUK12-22427_3_Scoping Report
22
3.8.1 Baseline
The traffic, transport and access study area will be defined by the preferred abnormal and general construction traffic routes to the proposed development site.
Direct access to the site would be taken from the B709. This access point would cater for abnormal loads and general construction traffic.
At this time the preferred access route from the trunk road network (T) to the site for abnormal loads has yet to be confirmed, however abnormal vehicles would likely access the site from one of two options as shown on Figure 11. Both options use the A74 motorway (T) and B723 to Boreland. At Boreland, one option continues north east on the B723 to Eskdalemuir and then continues south east to Bentpath on the B709. The second option continues south east at Boreland on an unnamed minor road beyond Corrie Common before heading north east to meet the B709 west of Bentpath. The delivery port for turbine components is not yet known. Port options include: Ayr, King George IV Docks, Immingham or Newcastle. A detailed assessment of route options will be undertaken including swept path analysis.
General construction traffic routes to the site would be dependent on the location of suppliers. However, it is anticipated that general construction traffic would route to the site from larger urban areas via the A7 (T) and then the B709, accessing the site from the southeast.
The main sensitive receptor to increased traffic levels and any significant environmental effects as a result of the proposed development is likely to be the population of Langholm to the southeast, and residents at Bentpath to the north. There are also isolated properties adjacent to the B709 that could be classed as sensitive receptors which will also be considered.
Following the identification of the preferred abnormal and construction traffic routes, a desk top review, swept path analysis and a site visit will be used to confirm the traffic, transport and access study area and sensitive receptors.
3.8.2 Potential Significant Effects
It is considered potential significant effects could arise in the construction phase of the development. The main potential effects considered are:
Traffic congestion due to an increase in Heavy Goods Vehicle (HGV) traffic related to material and component delivery;
Traffic congestion due to an increase in non-HGV traffic; and
Abnormal road wear and tear.
3.8.3 Issues to be Scoped Out
Operation
Once the proposed development is operational, there will be little traffic associated with the proposed development apart from occasional maintenance vehicles which will have negligible effect. It is therefore proposed not to undertake any detailed assessment of the operational phase of the proposed development in respect of traffic, transport and access.
Decommissioning
Development consent is sought for a 25 year period, after which time the proposed development is expected to be decommissioned. Traffic associated with decommissioning would include HGVs, Light Goods Vehicles (LGVs), abnormal loads and private cars. The number of vehicle trips associated with decommissioning would be significantly less than those associated with
Scoping Report
Hopsrig Wind Farm
RUK12-22427_3_Scoping Report
23
construction. At this stage it is not possible to quantify decommissioning traffic volumes as the precedent for decommissioning has not yet been established. It is also not possible to quantify the effect of decommissioning traffic as the baseline conditions will change over the planning permission period.
Traffic, transport and access impacts and effects associated with decommissioning will therefore not be addressed in the ES.
3.8.4 Additional Baseline Information Collection
It is likely that there will be a requirement to commission traffic surveys at two locations along the B709. These traffic surveys would take the form of Automatic Traffic Counts and would cover a one week period. The traffic surveys would be undertaken outwith school holidays.
Baseline traffic flow data will be obtained for routes within the study area from relevant sources including Transport Scotland, Department for Transport (DfT) and Dumfries & Galloway Council (where available) for the A/M74 (T), A7 (T), B709 and any other routes included in the study area. Should existing information not be available for the B709, two-way traffic counts will be commissioned on the local road network (B709) at two locations – one to the north (Bentpath) of the site access and one to the south (Langholm).
3.8.5 Effects Evaluation
The collated traffic flow data is expected to confirm existing traffic levels including LGVs and HGVs within the study area. These figures will be combined with the forecast levels of proposed development traffic in order to identify the likely significant effects within the study area taking cognisance of IEMA Guidelines. In accordance with the IEMA Guidelines, the method used for assessing environmental effects of increased traffic will be based on a comparison between predicted traffic flows on potentially affected roads with and without proposed development traffic, in percentage terms. In addition to this, the overall carrying capacity of the road in question will be considered in undertaking the assessment.
The traffic, transport and access assessment will seek to provide a robust (worst case) assessment of impacts and effects associated with the proposed development.
The main transport constraints relating to the proposed development relate to the transportation of abnormal loads and the impact of general construction traffic on the settlement of Langholm. An assessment of abnormal loads will be undertaken to identify the preferred route to site, from the nearest suitable port and to assess what mitigating measures may be required on the public road network.
The assessment will identify the potential traffic and associated environmental effects on sensitive receptors and mitigation will be proposed where necessary. Mitigation would likely take the form of a Construction Traffic Management Plan (CTMP) inclusive of a Green Travel Plan for construction staff.
3.8.6 Cumulative effects
The anticipated cumulative effects of the potential for overlapping construction programmes for the proposed development in addition to other proposed developments will be considered. The mechanism to mitigate any cumulative effects is the implementation of a CTMP.
It is important to note that a cumulative assessment in respect of traffic, transport and access effects is dependent on the likelihood of more than one wind farm being under construction at the
Scoping Report
Hopsrig Wind Farm
RUK12-22427_3_Scoping Report
24
same time as the proposed development. This is especially pertinent to the peak construction periods associated with the importation of stone which would be dependent on the outputs of local quarries.
3.9 Noise
3.9.1 Baseline
There are a number of noise sensitive properties (dwellings) situated around the site. The local area is rural in nature and existing background noise levels are expected to be fairly low. Background noise monitoring has previously been undertaken for existing wind farm developments in the area and it may be possible to re-use some of this data to assess the proposed development.
3.9.2 Potential Significant Effects
Based on initial modelling results, there is the potential for significant effects from construction noise however such effects would be temporary and short term and would probably be limited to a small number of properties (if any). Noise emitted during the operational phase of the development is not expected to be significant as achievement of the relevant noise limits will form a key part of the site design. The significance of the effects will be assessed and presented as part of the ES.
3.9.3 Issues to be Scoped Out
Properties where noise from the proposed development is more than 10 dB below existing wind turbine noise levels will be scoped out of the assessment as noise from the proposed development will be having a negligible impact at the properties.
3.9.4 Additional Baseline Information Collection
Prior to the noise monitoring survey, a desk based survey will be undertaken with the most up to date layout to determine which noise sensitive receptors will be included within the noise monitoring exercise. Consultation will be undertaken with the Dumfries and Galloway Council’s Environmental Health Department to agree the number and position of the proposed monitoring locations.
3.9.5 Effects Evaluation
Operational Noise
ETSU-R-97 ‘The Assessment of Rating of Noise from Windfarms' details a methodology for establishing noise limits for proposed wind farm developments and these limits should not be exceeded. ETSU-R-97 states that noise limits should be set relative to existing background noise levels at the nearest receptors and that these limits should reflect the variation in background noise with wind speed. Separate noise limits apply for quiet daytime and for night-time periods. Quiet daytime limits are chosen to protect a property’s external amenity, and night time limits are chosen to prevent sleep disturbance indoors, with windows open.
A background noise survey is not required for situations where predicted wind turbine noise levels at the nearest noise sensitive properties is limited to an LA90,10min of 35 dB(A) up to wind speeds of 10 m/s at 10 m, as the protection of the amenity of those properties can be controlled through a simplified noise condition as detailed in ETSU-R-97. ETSU-R-97 states that:
Scoping Report
Hopsrig Wind Farm
RUK12-22427_3_Scoping Report
25
‘For single turbines or wind farms with very large separation distances between the turbines and the nearest properties, a simplified noise condition may be suitable. If the noise is limited to an LA90,10min of 35 dB(A) up to wind speeds of 10 m/s at 10 m height, then this condition alone would offer sufficient protection of amenity, and background noise surveys would be unnecessary.’
An assessment undertaken in accordance with ETSU-R-97 and current good practice will be included within the ES, predicted wind turbine noise will be compared to the limits established in accordance with ETSU-R-97. Achievement of the noise limits will be a key design criteria during the site design process. In order to assess operational noise impacts in accordance with ETSU-R-97, the following steps are required:
specify the location of the wind turbines;
identify the locations of the nearest, or most noise sensitive neighbours;
measure the background noise levels as a function of on site wind speed at the nearest neighbours, or a representative sample of the nearest neighbours;
determine the quiet daytime and night-time noise limits from the measured background noise levels at the nearest neighbours;
specify the noise emission characteristics of three candidate wind turbines suitable for the proposed development;
calculate the noise emission levels due to the operation of the wind turbines as a function of on site wind speed at the nearest neighbours; and
compare the calculated wind turbine noise emission levels with the derived noise limits and assess compliance with ETSU-R-97.
Construction Noise
Noise emitted during the construction phase will be temporary and short term in nature and can be minimised through careful construction practices. The effective control of these impacts can be achieved by way of a suitable planning condition. Construction noise can be controlled post planning consent (should consent be granted) through the use of two legislative instruments which address the effects of environmental noise with regard to construction noise, vibration, and nuisance:
The Environmental Protection Act 1990 (EPA); and
The Control of Pollution Act 1974 (CoPA).
The CoPA provides two means of controlling construction noise and vibration. Section 60 provides the Local Authority with the power to impose at any time operating conditions on the site. Section 61 allows the Applicant to negotiate a set of operating procedures with the Local Authority prior to commencement of site works.
A construction noise assessment will be undertaken to determine the potential noise impacts during the construction phase of the proposed development. The construction noise assessment will be undertaken in accordance with the methodology outlined in British Standard (BS) 5228: Part 1: 2009 and ISO9613:1996 (‘Acoustics - Attenuation of sound during propagation outdoors -Part 2: General method of calculation’). Impacts will be assessed using criteria contained within BS5228-1: 2009 and, where appropriate, mitigation measures will be proposed.
An assessment of the potential noise emissions during the decommissioning phases of the development will also be undertaken as part of the construction noise assessment. The impacts of the decommissioning phase will be assessed and, where appropriate, mitigation measures will be proposed.
Scoping Report
Hopsrig Wind Farm
RUK12-22427_3_Scoping Report
26
3.9.6 Cumulative effects
A cumulative noise assessment is required where there is potential for an increase in noise effects from the operation of two or more wind farms at any property/properties surrounding a development. In this regard, the following turbine developments have been identified as potentially relevant when considering potential cumulative effects:
Ewe Hill Wind Farm (Consented);
Craig Wind Farm (4 Turbines Operational, 1 consented, and 1 proposed);
Crossdykes Wind Farm (Application); and
Loganhead Wind Farm (Application).
The assessment will be undertaken in accordance with current best practise and the schemes above will be reviewed and accounted for as part of the ES.
3.10 Forestry
The changes to the commercial forestry on site will be considered as part of the project description, rather than as a receptor which requires a separate technical EIA assessment. A separate factual Technical Appendix will be provided on forestry, whereas the indirect effects of forestry removal on landscape, visual, ecology and ornithology will be considered in the respective technical chapters.
The forestry baseline will be established in order to describe the crops existing at time of preparation of the ES. This will include species composition; age class; yield class (if available); other relevant crop information; and baseline felling and restocking plans (if available).
The output would be the production of finalised baseline data including species, planting year, yield class (where available), felling and restocking proposals (where available). The baseline data, in particular the restocking plan, would be used for comparison with the wind farm forestry proposals.
The development of a “Wind Farm Forest Design Plan” to replace the existing plan and to incorporate the wind farm infrastructure would be a key component of the design process. This would be an iterative process as the wind farm layout is refined and will be finalised once the wind farm layout has been fixed.
The revised Wind Farm Forest Design Plan will show which woodlands are to be felled and when they are to be felled during the life of the proposed development. It would take into account existing crops; silvicultural constraints; site conditions; the baseline Forest Design Plans; landowner objectives; wind farm requirements; and other constraints identified during the EIA process.
The felling proposals would consider the full range of options available including conventional felling and restocking; felling with no replanting; keyholing; early staged felling; restructuring felling; delayed felling; compensatory planting, long term retentions and natural reserves.
The Wind Farm Forest Design plan will provide proposals for restocking, including which species are to be planted and where during the life of the proposed development. Restocking options would include delayed restocking; revised species; and/or stocking densities.
The plan would identify the proposed method of crop clearance, subsequent replanting and aftercare requirements. It would identify changes to the pattern of timber harvesting and the effects on timber production. The plan would also provide information on the use of forestry
Scoping Report
Hopsrig Wind Farm
RUK12-22427_3_Scoping Report
27
wastes that are to be retained and reused at the site. The proposed reuse of forestry wastes would be quantified and justified.
The proposals will take into account The Scottish Government’s Control of Woodland Removal Policy55, the UK Forestry Standard56 and other legislation, policy and guidance as relevant. The proposals will also identify the extent of any net loss of woodland.
55 Forestry Commission Scotland, 2009. The Scottish Government’s Policy on Control of Woodland Removal. [pdf] Forestry Commission Scotland. Available at: <http://www.forestry.gov.uk/pdf/fcfc125.pdf/$FILE/fcfc125.pdf> [Accessed 2 February 2016]. 56 Forestry Commission, 2011. The UK Forestry Standard: The governments’ approach to sustainable forest management, 3rd ed. [pdf]
Edinburgh: Forestry Commission. Available at: <http://www.forestry.gov.uk/pdf/FCFC001.pdf/$FILE/FCFC001.pdf> [Accessed 2 February 2016].
Scoping Report
Hopsrig Wind Farm
RUK12-22427_3_Scoping Report
28
4. ISSUES SCOPED OUT OF THE EIA
The following issues are proposed to be scoped out of the EIA.
4.1 Aviation and Defence
The Applicant commissioned a NATS technical and operational assessment for the proposed development. The En-route radar technical assessment indicates that the proposed development would be likely to cause false primary plots, and a reduction in the radar’s probability of detection for real aircraft. The operational impact on Prestwick Centre ATC, without further mitigation, has been deemed unacceptable. Where there is an identified need, the Applicant would enter into a radar mitigation contract to provide a technical solution to potential interference with radar. On the basis that a technical mitigation solution is implemented, there would be no significant effects on aviation. No further assessment is required as part of the EIA process and a summary of consultation will be presented in the ES rather than a detailed technical assessment.
The site is also located inside the Ministry of Defence (MOD) Low Flying Area 16 and Tactical Training Area 20 (T) – a high priority area for military tactical training. The Applicant will consult with the Defence Infrastructure Organisation (DIO)) on behalf of the MOD to determine the need for any specific mitigation e.g. a scheme of non-visible (infrared) aviation lighting.
The site is located 15.3 km from the centre of the Eskdalemuir seismic monitoring station at its closest point (see Figure 12). As the site is located over 15 km from the centre of the Eskdalemuir seismic monitoring station, the proposed development would not compromise the operations at the station.
4.2 Socioeconomics
The proposed development would bring the potential for significant beneficial economic effects at a local level in relation to the temporary and long term increase in employment opportunities during construction and less so through operation.
The potential effects on visual amenity for tourism and recreational locations will be fully assessed in ES as part of the landscape and visual assessment. However, it should be noted that there is no evidence to support the suggestion that the presence of a wind farm would result in a significant adverse effect on tourism or recreation resources57. The proposed development is located in a preferred area for large typology wind turbines according to Dumfries and Galloway landscape capacity study.
The construction of the proposed development would not entail significant road works, closures or diversions which would have potential to adversely affect access to tourism assets and no potential for significant effects is identified.
The economic effects are not considered to give rise to significant effects on a regional or national level, and as such will not be considered in an impact assessment chapter of the ES. However, a separate factual statement on the socio-economic benefits will be provided as part of the ES, and the community benefit potential of the proposed development will be set out.
4.3 Air Quality
The proposed development is not considered likely to give rise to significant impacts on air quality. The main activities would be limited to construction works (dust from soil stripping and
57 Renewables UK, 2010. Wind Farms and Tourism Fact Sheet 03. [pdf] Renewables UK. Available at:
<http://www.helensburghrenewables.co.uk/wp-uploads/2013/02/ReUK-Tourism.pdf>.
Scoping Report
Hopsrig Wind Farm
RUK12-22427_3_Scoping Report
29
earthworks, from excavation, potentially including occasional blasting, and from vehicles running over unsurfaced ground) and exhaust emissions from fixed and mobile construction plant and construction vehicles. Construction works would be localised, short term, intermittent and controllable through the application of good construction practice. Fixed and mobile plant would be limited in size and number, and operate for short periods.
The contributions of exhaust emissions (NO2 and PM10) from construction vehicles are likely to be low, and orders of magnitude below current Air Quality Objectives. Therefore, it is proposed that the EIA will not address air quality impacts.
4.4 Shadow Flicker
Scottish Government web-based advice on onshore wind turbines (previously known as PAN45) states that ‘where separation is provided between wind turbines and nearby dwellings (as a general rule 10 rotor diameters), “shadow flicker” should not be a problem.’ Local policy58 also looks for a 10 rotor diameter separation to the nearest dwellings. The potential for shadow flicker effects will be addressed through the proposed development design process (and reported in the design/alternatives section of the ES), either by specifying a software based turbine mitigation during critical time periods to prevent shadow flicker, or through the proposed turbine layout to provide a 10 rotor diameter separation from residential properties. On this basis, no shadow flicker assessment will be provided.
4.5 Ice Throw
The maximum potential distance of ice falling from turbines can be approximated using the formula 1.5 x (blade diameter + hub height)59. For the proposed development, the maximum distance from a turbine where ice could be expected to fall is therefore in the region of 270 m. As such, the risk to public safety is considered to be very low because the distance from the turbines to the nearest public road, residential property or core path would be greater than 270 m.
In line with current guidance60, however, a permanent warning sign at the site entrance is proposed to alert the public to this issue. No detailed assessment is proposed as part of the ES.
58 Dumfries and Galloway Council, 2015. Local Development Plan, Supplementary Guidance, Part 1 Wind Energy Development:
Development Management Considerations. [pdf] Dumfries and Galloway Council. Available at: <http://www.dumgal.gov.uk/CHttpHandler.ashx?id=11890&p=0> [Accessed 01/02/2016]. 59 Seifert, H., Westerhellwg, A. and Kroning, J., 2003. Risk Analysis of Ice Throw from Wind Turbines. [pdf] Available at: <http://www.windaction.org/posts/13298-risk-analysis-of-ice-throw-from-wind-turbines#.VrDHV01yaUl> [Accessed 2 February 2016]. 60 Scottish Renewables, Scottish Natural Heritage, SEPA and Forestry Commission Scotland, 2010. Good Practice During Wind Farm
Construction. [pdf] Available at: <http://www.snh.org.uk/pdfs/strategy/renewables/Good%20practice%20during%20windfarm%20construction.pdf> [Accessed 2 February 2016].
Scoping Report
Hopsrig Wind Farm
RUK12-22427_3_Scoping Report
30
5. NEXT STEPS
In forming its opinion, the Scottish Ministers will seek the views of various organisations with an interest in the proposed development, inviting comments on the proposed scope of and approach to the EIA proposed herein.
In submitting your comments on this report, we would be grateful if you could send a copy of your response to the address below.
Peter Bruce
Ramboll Environ
5th Floor
7 Castle Street
Edinburgh
EH2 3AH
Email: [email protected]
Telephone: 0131 297 2650
G F
G F
G F
G F
G FG F
G F
G F
G FG F
G F
G FG F
G F
G FG F
G F
G F
G FG F
G F
G F
G F
G F
G F
G F
G F
G F
G F
G F
G F
G F
G F
G F
G F
G FG F
G F
G F
G FG F
G F
G F
G F
G F
G F
G F
G F
G F
G F
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
T9
T8
T7
T6T5
T4
T3
T2
T1
T16
T15
T14
T13
T12
T11
T10
T18
T17
CT9
CT8
CT7
CT6
CT5
CT4
CT3
CT2
CT1
CT1
5
CT1
4
CT1
3 CT1
2
CT1
1
CT1
0
LH9
LH8
LH7
LH6
LH5
LH4 LH
3
LH2
LH1
LH13
LH12
LH11
LH10
EW9
EW8
EW7
EW6
EW5
EW4
EW3
EW2
EW39
EW38
EW37
EW36
EW35
EW32
EW25
EW24
EW17
EW16
EW14
EW13
EW11
EW10
Issu
eD
raw
n by
Sca
le
Dat
e
Site
Proj
ect
No.
Title
Clie
nt
1RM
Mar
ch 2
016
Figu
re 1
: Site
Layo
ut
Scop
ing
Rep
ort
UK12
-224
27 @A
31:
30,0
00
Key
Site
Bou
ndar
y
!(Tu
rbin
e Lo
catio
n -
Hop
srig
G FTu
rbin
e Lo
catio
n -
Cro
ssdy
kes
G FTu
rbin
e Lo
catio
n -
Ewe
Hill
G FTu
rbin
e Lo
catio
n -
Loga
nhea
d
Rep
rod
uce
d f
rom
Ord
nan
ce S
urv
ey
Ma
p D
ata
wit
h t
he
per
mis
sio
n o
f th
e C
ontr
oll
er o
f H
MS
O,
Cro
wn
Co
pyr
igh
t R
eser
ved
Lic
ence
No
. E
S 1
00
02
24
32
Path: P:\CONTRACT\UK224xx\UK12-22427 Hopsrig Wind Farm Ltd (Buccleuch Estates)_ Hopsrig EIA\GIS\MapFiles\Figures\ScopReport\UK1222427_Fig1_SiteLoc_E.mxd
01,
000
m
N
Hop
srig
Win
d Fa
rm L
td
Hop
srig
Win
d Fa
rmLa
ngho
lm
020
km
Har
esta
nes
Ewe
Hill
Hig
hlee
Hill
Cly
de W
ind
Farm
(Ext
ensi
on)
Cly
de (N
orth
, Cen
tral
and
Sou
th)
Auc
henc
airn
Har
esta
nes
Exte
nsio
n
Whi
tela
w B
rae
Min
sca
Birn
eykn
owe
Win
dy E
dge
Solw
ayba
nk
Min
nyga
p
Cro
ssdy
kes
Cly
de (N
orth
, Cen
tral
and
Sou
th)
Dal
swin
ton
Loga
nhea
d
Bla
ckw
ood
Lang
hope
Rig
Hal
lbur
n
Dun
cow
Com
mon
Wes
t Sca
les
Cra
ig
Issu
eD
raw
n by
Sca
le
Dat
e
Site
Proj
ect
No.
Title
Clie
nt
1D
D
Mar
ch 2
016
Figu
re 2
: Cum
ulat
ive
Situ
atio
n
Scop
ing
Rep
ort
UK12
-224
27 @A
31:
275,
000
Key
Site
Bou
ndar
y
Stud
y Are
a -
10km
Stud
y Are
a -
20km
Stud
y Are
a -
30km
Stud
y Are
a -
35km
Win
dfa
rm -
Sta
tus
Inst
alle
d
Appr
oved
Appl
icat
ion
Appe
al
Scop
ing
Re
prod
uce
d f
rom
Ord
nan
ce S
urv
ey
Ma
p D
ata
wit
h t
he
per
mis
sio
n o
f th
e C
ontr
oll
er o
f H
MS
O,
Cro
wn
Co
pyr
igh
t R
ese
rve
d
Lice
nce
No
. E
S 1
00
02
243
2
Path: P:\CONTRACT\UK224xx\UK12-22427 Hopsrig Wind Farm Ltd (Buccleuch Estates)_ Hopsrig EIA\GIS\MapFiles\Figures\ScopReport\UK1222427_Fig2_Cumulatives_B.mxd
010
km
N
Hop
srig
Win
d Fa
rm L
td
Hop
srig
Win
d Fa
rmLa
ngho
lm
STC
15ST
C13
BD
R6
BD
R28
BD
R22
STC
21
BD
R29
BD
R4
BD
R25
BD
R22
BD
R29
BD
R4
STC
12
LOC
HLO
CH
DG
W22
LOC
H
BD
R10
LOC
H
DG
W11
LOC
HLO
CH
BD
R10
DG
W10
BD
R28
DG
W21
BD
R8
BD
R8
LOC
H
STC
14
BD
R7
BD
R28
BD
R11
DG
W22
LOC
H
BD
R26
LOC
H
BD
R5
BD
R11
BD
R29
STC
18
STC
18
LOC
H
DG
W11
LOC
H
DG
W8
DG
W5
LOC
H
DG
W21
BD
R10
BD
R10
LOC
HLO
CH
DG
W11
DG
W22
DG
W11
DG
W20
DG
W20
DG
W11
DG
W20
DG
W17
DG
W17
DG
W11
DG
W22
DG
W22
BD
R22
BD
R26
LOC
HLO
CH
LOC
H
LOC
HLO
CH
BD
R28
BD
R11
LOC
H
DG
W20 D
GW
20
DG
W22
DG
W11
BD
R22
DG
W21
LOC
H
DG
W20
DG
W6
DG
W17
DG
W17
LOC
H
DG
W17 D
GW
17
DG
W6
DG
W21
DG
W7
LOC
H
BD
R5
DG
W22
LOC
H
BD
R4
DG
W22
DG
W22
DG
W23
UR
BA
N
UR
BA
ND
GW
5D
GW
8
DG
W14
LOC
H
DG
W7
LOC
HLO
CH
LOC
HLO
CH
DG
W17
DG
W7
DG
W3
DG
W7
DG
W3
LOC
H
DG
W15
DG
W24
DG
W15
LOC
HLO
CH
LOC
H
DG
W6
DG
W20
DG
W8
LOC
H
DG
W2
LOC
H
DG
W1
LOC
H
LOC
H
LOC
H
ISLD
DG
W24
DG
W14
DG
W5
LOC
H
DG
W5
DG
W16
DG
W17
DG
W8
LOC
H_I
SLD
DG
W24
DG
W24
DG
W24
LOC
H
Issu
eD
raw
n by
Sca
le
Dat
e
Site
Proj
ect
No.
Title
Clie
nt
1D
D
Mar
ch 2
016
Figu
re 3
: La
ndsc
ape
Cha
ract
er T
ypes
Scop
ing
Rep
ort
UK12
-224
27 @A
31:
275,
000
Key
Site
Bou
ndar
y
Stu
dy A
rea
- 10k
m
Stu
dy A
rea
- 20k
m
Stu
dy A
rea
- 30k
m
Stu
dy A
rea
- 35k
m
Re
prod
uce
d f
rom
Ord
nan
ce S
urv
ey
Ma
p D
ata
wit
h t
he
per
mis
sio
n o
f th
e C
ontr
oll
er o
f H
MS
O,
Cro
wn
Co
pyr
igh
t R
ese
rve
d
Lice
nce
No
. E
S 1
00
02
243
2
Path: P:\CONTRACT\UK224xx\UK12-22427 Hopsrig Wind Farm Ltd (Buccleuch Estates)_ Hopsrig EIA\GIS\MapFiles\Figures\ScopReport\UK1222427_Fig3_LandscCharTypes_B.mxd
010
km
N
Hop
srig
Win
d Fa
rm L
td
Hop
srig
Win
d Fa
rmLa
ngho
lm
Lan
dsc
ape
Ch
ara
cter
Typ
es
BDR10
- G
rass
land
with
Roc
k O
utcr
ops
BDR11
- G
rass
land
with
Hill
sBD
R22
- U
plan
d Va
lley
with
Past
oral
Flo
orBD
R25
- U
plan
d Va
lley
with
Woo
dlan
dBD
R26
- P
asto
ral U
plan
d Fr
inge
Val
ley
BDR28
- W
oode
d U
plan
d Fr
inge
Val
ley
BDR29
- L
owla
nd V
alle
y w
ith
Farm
land
BDR4
- Sou
ther
n U
plan
ds w
ith S
catt
ered
For
est
BDR5
- Sou
ther
n U
plan
ds F
ores
t Cov
ered
BDR6
- Che
viot
Upl
ands
BDR7
- Che
viot
Foo
thill
sBD
R8
- Ro
lling
Far
mla
ndD
GW
1 -
Peni
nsul
aD
GW
10 -
Upp
er D
ale
(Val
ley)
DG
W11
- U
plan
d G
lens
DG
W14
- D
rum
lin P
astu
res
DG
W15
- C
oast
al P
late
auD
GW
16 -
Flo
w P
late
auD
GW
17 -
Upl
and
Frin
geD
GW
2 -
Peni
nsul
a w
ith G
orse
y Kno
lls
DG
W20
- F
ooth
ills
DG
W21
- F
ooth
ills
With
For
est
DG
W22
- S
outh
ern
Upl
ands
DG
W23
- S
outh
ern
Upl
ands
with
For
est
DG
W24
- C
oast
al G
rani
te U
plan
dsD
GW
3 -
Coa
stal
Fla
tsD
GW
5 -
Nar
row
Woo
ded
Riv
er V
alle
ysD
GW
6 -
Intim
ate
Past
oral
Val
leys
DG
W7
- Lo
wer
Dal
e (V
alle
y)D
GW
8 -
Mid
dle
Dal
e (V
alle
y)IS
LD -
Coa
stal
Isl
and
LOCH
- I
nlan
d Lo
chLO
CH
_ISL
D -
Loc
h Is
land
STC12
- U
plan
d Riv
er V
alle
ysST
C13
- B
road
Val
ley
Upl
and
STC14
- U
plan
d G
len
STC15
- F
ooth
ills
STC18
- P
late
au M
oorl
ands
STC21
- S
outh
ern
Upl
ands
URBAN
- U
rban
Solway Coast
Solw
ay
Coas
t
Nor
thP
enni
nes
02. T
alla
-H
art f
ell
Nith
Estu
ary
East
Stew
artr
yC
oast
SCO
T'S
MIN
ING
CO
MPA
NY
HO
USE
MO
NTE
VIO
T
DR
UM
LAN
RIG
CA
STLE
RA
EHIL
LS
MA
XWEL
TON
(GLE
NC
AIR
NC
AST
LE)
DA
LSW
INTO
N
CO
WH
ILL
TOW
ER
BR
OO
KLA
ND
S
KIN
MO
UN
T
AR
BIG
LAN
D
BA
RN
HO
UR
IEM
ILL
Tort
horw
ald
Rid
ge
Thor
nhill
Upl
ands
Mof
fat
Hill
s
Lang
holm
Hill
s
Terr
egle
sR
idge
Solw
ayC
oast
Solw
ayC
oast
Solw
ayC
oast
Issu
eD
raw
n by
Sca
le
Dat
e
Site
Proj
ect
No.
Title
Clie
nt
1D
D
Mar
ch 2
016
Figu
re 4
: La
ndsc
ape
Des
igna
tions
and
Cla
ssifi
catio
nsSc
opin
g Rep
ort
UK12
-224
27 @A
31:
275,
000
Key
Site
Bou
ndar
y
Stud
y Are
a -
10km
Stud
y Are
a -
20km
Stud
y Are
a -
30km
Stud
y Are
a -
35km
Nat
iona
l Sce
nic
Area
s
Wild
Lan
d Ar
eas
2014
Gar
dens
and
Des
igne
dLa
ndsc
apes
Spec
ial L
ands
cape
Area
s -
Sco
ttis
hBo
rder
s
Regi
onal
Sce
nic
Are
a-
Dum
frie
s an
dG
allo
way
Area
of
Out
stan
ding
Nat
ural
Bea
uty
Wor
ld H
erita
ge S
ite -
Had
rian
s W
all
Re
prod
uce
d f
rom
Ord
nan
ce S
urv
ey
Ma
p D
ata
wit
h t
he
per
mis
sio
n o
f th
e C
ontr
oll
er o
f H
MS
O,
Cro
wn
Co
pyr
igh
t R
ese
rve
d
Lice
nce
No
. E
S 1
00
02
243
2
Path: P:\CONTRACT\UK224xx\UK12-22427 Hopsrig Wind Farm Ltd (Buccleuch Estates)_ Hopsrig EIA\GIS\MapFiles\Figures\ScopReport\UK1222427_Fig4_LandscDesignations_B.mxd
010
km
N
Hop
srig
Win
d Fa
rm L
td
Hop
srig
Win
d Fa
rmLa
ngho
lm
!(
!( !(
!(!(!(
!(!( !( !(
!(!(!(
!( !(!(
!(!(
_ _
_
_
_
_
_
_
_
_
_
_
_
_
_
1 2
3
4
5
6
7
8
9
1011
12
13
14
15
Issu
eD
raw
n by
Sca
le
Dat
e
Site
Proj
ect
No.
Title
Clie
nt
1D
D
Mar
ch 2
016
Figu
re 5
: ZTV
and
View
poin
t Lo
catio
ns
Scop
ing
Rep
ort
UK12
-224
27 @A
31:
275,
000
Key
Site
Bou
ndar
y
!(Tu
rbin
e Lo
catio
n
Rad
ii Fr
om O
uter
Turb
ine
at 1
0km
Inte
rval
s
Stu
dy A
rea
- 35k
m
1_Vi
ewpo
int L
ocat
ion
Re
prod
uce
d f
rom
Ord
nan
ce S
urv
ey
Ma
p D
ata
wit
h t
he
per
mis
sio
n o
f th
e C
ontr
oll
er o
f H
MS
O,
Cro
wn
Co
pyr
igh
t R
ese
rve
d
Lice
nce
No
. E
S 1
00
02
243
2
Path: P:\CONTRACT\UK224xx\UK12-22427 Hopsrig Wind Farm Ltd (Buccleuch Estates)_ Hopsrig EIA\GIS\MapFiles\Figures\ScopReport\UK1222427_Fig5_ZTVandViewpoints_E.mxd
010
km
N
Hop
srig
Win
d Fa
rm L
td
Hop
srig
Win
d Fa
rmLa
ngho
lm
Num
ber o
f Tur
bine
sVi
sibl
e at
Bla
de T
ipLe
vel (
135m
)
1 - 3
4 - 6
7 - 9
10 -
12
13 -
16
17 -
18
1.
The
ZTV
an
alys
is
does
no
tta
ke i
nto
acco
unt
the
scre
enin
gef
fect
of
vege
tati
on,
build
ings
an
dot
her
surf
ace
feat
ures
2. P
redi
cted
vis
ibili
ty b
ased
on
avi
ewer
ey
e he
ight
2m
ab
ove
grou
nd3.
V
isib
ility
ca
lcul
ated
us
ing
Ord
nanc
e S
urve
y Te
rrai
n 5
DTM
on
a 5m
Gri
d4.
Eff
ect
of e
arth
cur
vatu
re a
ndlig
ht r
efra
ctio
n is
incl
uded
1
Issu
eD
raw
n by
Sca
le
Dat
e
Site
Proj
ect
No.
Title
Clie
nt
1D
D
Mar
ch 2
016
Figu
re 6
: Ec
olog
ical
and
O
rnitho
logi
cal
Des
igna
tions
Scop
ing
Rep
ort
UK12
-224
27 @A
31:
160,
000
Key
Site
Bou
ndar
y
20km
Stu
dy A
rea
Spe
cial
Are
a of
Con
serv
atio
n
Spe
cial
Pro
tect
ion
Are
a
RA
MS
AR
Site
of S
peci
al S
cien
tific
Inte
rest
Nat
iona
l Nat
ure
Res
erve
Anc
ient
Woo
dlan
dIn
vent
ory
Loca
l Nat
ure
Res
erve
Impo
rtant
Bird
Are
a
Rep
rod
uce
d f
rom
Ord
nan
ce S
urv
ey M
ap D
ata
wit
h t
he p
erm
issi
on o
f th
e C
ontr
olle
r of
HM
SO
, Cro
wn
Co
pyri
gh
t R
eser
ved
Lic
en
ce N
o. E
S 1
00
02
24
32
Path: P:\CONTRACT\UK224xx\UK12-22427 Hopsrig Wind Farm Ltd (Buccleuch Estates)_ Hopsrig EIA\GIS\MapFiles\Figures\ScopReport\UK1222427_Fig6_EcolAndOrnithDesignations_B.mxd
05
km
N
Hop
srig
Win
d Fa
rm L
td
Hop
srig
Win
d Fa
rmLa
ngho
lm
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
T17
T18
T1
T2
T3
T4T5
T6
T7
T8
T9
T10
T11
T12
T13
T14
T15
T16
2
3
2223
24
252627
28
29
30
31
3334
35
3637
38
39
40
46
474849
5455
6364
197
198
199
200
201
202
203
204
205
206
207
208
209
210
211
212
Issu
eD
raw
n by
Sca
le
Dat
e
Site
Proj
ect
No.
Title
Clie
nt
1D
D
Mar
ch 2
016
Figu
re 7
: Cul
tura
lH
eritag
e Ass
ets
with
inth
e Site
Scop
ing
Rep
ort
UK12
-224
27 @A
31:
17,5
00
Key
Site
Bou
ndar
y
!(Tu
rbin
e Lo
catio
n
Sch
edul
ed M
onum
ents
List
ed B
uild
ings
Boy
ken
Bur
n A
SA
!(H
erita
ge C
onst
rain
ts
Re
prod
uce
d f
rom
Ord
nan
ce S
urv
ey
Ma
p D
ata
wit
h t
he
per
mis
sio
n o
f th
e C
ontr
oll
er o
f H
MS
O,
Cro
wn
Co
pyr
igh
t R
ese
rve
d
Lice
nce
No
. E
S 1
00
02
243
2
Path: P:\CONTRACT\UK224xx\UK12-22427 Hopsrig Wind Farm Ltd (Buccleuch Estates)_ Hopsrig EIA\GIS\MapFiles\Figures\ScopReport\UK1222427_Fig7_CultHerSitesWithinSite_C.mxd
01,
000
m
N
Hop
srig
Win
d Fa
rm L
td
Hop
srig
Win
d Fa
rmLa
ngho
lm
!(
!(
!(
!(
!(
!(!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(!(
T17
T18
T1
T2
T3
T4T5
T6
T7
T8T9
T10
T11
T12 T1
3 T14
T15
T16
1
111213
1415
16
24
26
27
28
43
44
45
46
49
58
59
62
63
64
65
6774
78
80
81
82
83
85
9193
95
98
99
100
101
102
103
105
106
107
108
109
110
111
112
113
116
118 11
9
120
121
122
123
124
125
126
127
128
129
130
2
3
2223
24
2526
2728
293031
33 3435
3637
38
3940
4647
4849
5455
63 6419
7
198
199
200
201
202
203
204
205
206
207
208
209
210
211
212
Issu
eD
raw
n by
Sca
le
Dat
e
Site
Proj
ect
No.
Title
Clie
nt
1D
D
Mar
ch 2
016
Figu
re 8
: Cul
tura
lH
eritag
e Ass
ets
with
in5k
m S
tudy
Are
aSc
opin
g Rep
ort
UK12
-224
27 @A
31:
50,0
00
Key
Site
Bou
ndar
y
5km
Stu
dy A
rea
!(Tu
rbin
e Lo
catio
n
!(H
erita
ge A
sset
s
Sch
edul
ed M
onum
ents
List
ed B
uild
ings
Boy
ken
Bur
n
Con
serv
atio
n A
reas
Num
ber o
f Tur
bine
sVi
sibl
e at
Bla
de T
ipLe
vel (
135m
)
1 - 3
4 - 6
7 - 9
10 -
12
13 -
16
17 -
19
Re
prod
uce
d f
rom
Ord
nan
ce S
urv
ey
Ma
p D
ata
wit
h t
he
per
mis
sio
n o
f th
e C
ontr
oll
er o
f H
MS
O,
Cro
wn
Co
pyr
igh
t R
ese
rve
d
Lice
nce
No
. E
S 1
00
02
243
2
Path: P:\CONTRACT\UK224xx\UK12-22427 Hopsrig Wind Farm Ltd (Buccleuch Estates)_ Hopsrig EIA\GIS\MapFiles\Figures\ScopReport\UK1222427_Fig8_CultHerSitesWithin5km_C.mxd
03
km
N
Hop
srig
Win
d Fa
rm L
td
Hop
srig
Win
d Fa
rmLa
ngho
lm
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
! (
! (
! (
! (
! (
! (! (
! (
! (
! (! (
! (
! (
! (
! (
! (
! (! (
T9T8
T7
T6T5
T4
T3
T2
T1T1
6T1
5
T14
T13
T12
T11
T10
T18
T17
Issu
eD
raw
n by
Sca
le
Dat
e
Site
Proj
ect
No.
Title
Clie
nt
1D
D
Mar
ch 2
016
Hop
srig
Win
d Fa
rm L
td
Hop
srig
Win
d Fa
rmLa
ngho
lm
Figu
re 9
: H
ydro
logi
cal
Con
stra
ints
Scop
ing
Rep
ort
UK12
-224
27 @A
31:
30,0
00
Key
Site
Bou
ndar
y
! (Tu
rbin
e Lo
catio
n
Stud
y Are
a -
2km
Wat
erbo
dy
Wat
erbo
dy -
50m
Buff
er
!(Pr
ivat
e W
ater
Sup
ply
Priv
ate
Wat
er S
uppl
y-
250m
Buf
fer
Re
prod
uce
d f
rom
Ord
nan
ce S
urv
ey
Ma
p D
ata
wit
h t
he
per
mis
sio
n o
f th
e C
ontr
oll
er o
f H
MS
O,
Cro
wn
Co
pyr
igh
t R
ese
rve
d
Lice
nce
No
. E
S 1
00
02
243
2
Path: P:\CONTRACT\UK224xx\UK12-22427 Hopsrig Wind Farm Ltd (Buccleuch Estates)_ Hopsrig EIA\GIS\MapFiles\Figures\ScopReport\UK1222427_Fig9_HydrCons_C.mxd
01,
000
m
N
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
E
EE
E
E
E EEE
E
E
E
EE
E
E E
EE
EE
EE
E
E
E
E E
E
EE
E
E
EE
E
E
E
EE
EE
E
EE
EE E
E
E
E
E
EE
E
E
EE
EE E
E
E
EE
E
E
E
E
E
E
EE
E
EE
E
E
EE
EE
E EE
EE
E
EE
E
E EE
EEEE
E
E
E
EE
E
EEE
EE
E
EE
E
E
EE
E E
EE
EE
EE
EE
E E
E
EEE
E
EE
E
E
E
E
E
EE
EE
EEE
E
E
EE
EE
E
E
E
EE
E
EE
EE
EE
E
E
E
E
E
E
EE
E
E
E
EE
E
E
E
E
E
E
E
E
E
E
E
EE
EE
E
E
E
EE
E
E
E
EE
E
E E
E
E
EE
EE E E
EE
EEE
EEE
E
EE
E
EEE
EEE
E
E
E
EE
EE
E
E
EE
E
E
EE
E
EE
E
E
EE
EE
E
EE
EE
E
EE
E
E
E
E
EE
E
E
EE
E
EE
E
EE
E
E
E
E
E
E
E
E
E
EE
EE
E E E
E
EE
E
E
E
E
EE
E
EE
E
EE
EE
E
E
E
E
E
E
E
EE E
EE
E
E
EE
E
E
E
EE
E
E
E
E
EE
EE
E
EE
EE
EE
E
E
T9
T8
T7
T6T5
T4
T3
T2
T1
T16
T15
T14
T13
T12
T11
T10
T18
T17
Issu
eD
raw
n by
Sca
le
Dat
e
Site
Proj
ect
No.
Title
Clie
nt
1RM
Mar
ch 2
016
Figu
re 1
0: P
eat
Prob
eLo
cation
s an
d Re
cord
edPe
at D
epth
Scop
ing
Rep
ort
UK12
-224
27 @A
31:
20,0
00
Key
Site
Bou
ndar
y
!(Tu
rbin
e Lo
catio
n -
Hop
srig
EP
eat S
urve
y P
robe
Loca
tions
Peat
dep
th (m
)
0 - 0
.5
0.5
- 1
1.0
- 1.5
1.5
- 2.0
2.0
- 2.5
2.5
- 3.0
3.0
- 3.5
3.5
- 4.0
Pea
t (B
GS
50k
Sup
erfic
ial)
Re
prod
uce
d f
rom
Ord
nan
ce S
urv
ey
Ma
p D
ata
wit
h t
he
per
mis
sio
n o
f th
e C
ontr
oll
er o
f H
MS
O,
Cro
wn
Co
pyr
igh
t R
ese
rve
d
Lice
nce
No
. E
S 1
00
02
243
2
Path: P:\CONTRACT\UK224xx\UK12-22427 Hopsrig Wind Farm Ltd (Buccleuch Estates)_ Hopsrig EIA\GIS\MapFiles\Figures\ScopReport\UK1222427_Fig10_Peat_A.mxd
01,
000
m
N
Hop
srig
Win
d Fa
rm L
td
Hop
srig
Win
d Fa
rmLa
ngho
lm
Issu
eD
raw
n by
Sca
le
Dat
e
Site
Proj
ect
No.
Title
Clie
nt
1RM
Mar
ch 2
016
Figu
re 1
: Abn
orm
alLo
ad R
oute
Opt
ions
Scop
ing
Rep
ort
UK12
-224
27 @A
31:
90,0
00
Key
Site
Bou
ndar
y
Abn
orm
al L
oad
Rou
te 3
Abn
orm
al L
oad
Rou
te 6
Re
prod
uce
d f
rom
Ord
nan
ce S
urv
ey
Ma
p D
ata
wit
h t
he
per
mis
sio
n o
f th
e C
ontr
oll
er o
f H
MS
O,
Cro
wn
Co
pyr
igh
t R
ese
rve
d
Lice
nce
No
. E
S 1
00
02
243
2
Path: P:\CONTRACT\UK224xx\UK12-22427 Hopsrig Wind Farm Ltd (Buccleuch Estates)_ Hopsrig EIA\GIS\MapFiles\Figures\ScopReport\UK1222427_Fig12_AbnormalAccess_A.mxd
05
km
N
Hop
srig
Win
d Fa
rm L
td
Hop
srig
Win
d Fa
rmLa
ngho
lm
_̂
Issu
eD
raw
n by
Sca
le
Dat
e
Site
Proj
ect
No.
Title
Clie
nt
1D
D
Mar
ch 2
016
Figu
re 1
: Site
Lay
out
with
15
km
Esk
dale
mui
r Se
ism
ic
Mon
itoring
Sta
tion
Buffer
Scop
ing
Rep
ort
UK12
-224
27 @A
31:
125,
000
Key
Site
Bou
ndar
y
_̂E
skda
lem
uir S
eism
icM
onito
ring
Sta
tion
Esk
dale
mui
r - 1
5km
Buf
fer
Re
prod
uce
d f
rom
Ord
nan
ce S
urv
ey
Ma
p D
ata
wit
h t
he
per
mis
sio
n o
f th
e C
ontr
oll
er o
f H
MS
O,
Cro
wn
Co
pyr
igh
t R
ese
rve
d
Lice
nce
No
. E
S 1
00
02
243
2
Path: P:\CONTRACT\UK224xx\UK12-22427 Hopsrig Wind Farm Ltd (Buccleuch Estates)_ Hopsrig EIA\GIS\MapFiles\Figures\ScopReport\UK1222427_Fig11_Eskdalemuir_B.mxd
03
km
N
Hop
srig
Win
d Fa
rm L
td
Hop
srig
Win
d Fa
rmLa
ngho
lm
Scoping Report
Hopsrig Wind Farm
Consultee List
Scottish Ministers (care of Energy Consents and Deployment Unit, Scottish Government) - Competent Authority
Dumfries and Galloway Council - Local Planning Authority
Scottish Environment Protection Agency (SEPA)
Scottish Natural Heritage (SNH)
Historic Environment Scotland
Forestry Commission Scotland
Marine Scotland (freshwater fisheries)
Transport Scotland
Scottish Water
Langholm, Ewes, and Westerkirk Community Council
Eskdalemuir Community Council
Middlebie and Waterbeck Community Council
Association of Salmon Fishery Boards
Galloway Fisheries Trust
Civil Aviation Authority - Airspace
Defence Infrastructure Organisation
NATS Safeguarding
RSPB Scotland
Mountaineering Council of Scotland
Scottish Wildlife Trust
Glasgow Prestwick Airport
Scottish Rights of Way and Access Society (ScotWays)
Garden History Society in Scotland
Turbine Coordinates by email only
OFCOM
Atkins
BT
Joint Radio Company
Argiva
Scoping Report
Hopsrig Wind Farm
Relevant LVIA Legislation Policy and Guidance
The LVIA will be prepared in accordance with the Guidelines for Landscape and Visual Impact Assessment (GLVIA 3) Landscape Institute and the Institute of Environmental Management and Assessment (2013). It will also take account of the following:
Scottish Natural Heritage, (December 2014), Visual Representation of Wind Farms Version 2.1;
Scottish Natural Heritage (June 2014), Map of Wild Land Areas;
Scottish Natural Heritage (May 2014), Siting and Designing Windfarms in the Landscape, Version 2;
Scottish Natural Heritage (March 2012), Assessing the Cumulative Impact of Onshore Wind Energy Developments;
Landscape Institute (March 2011), Photography and photomontage in landscape and visual impact assessment, Advice Note 01/11, edited by the Landscape Institute;
Scottish Natural Heritage (February 2007), Assessing the Impact on Wild Land; Interim Guidance Note;
Scottish Natural Heritage (2002), Policy Statement No.02/03: Wildness in Scotland's Countryside;
Scottish Natural Heritage and the Countryside Agency, (2002) Topic Paper 6: Techniques and Criteria for Judging Capacity and Sensitivity;
Department of Landscape University of Sheffield and Land Use Consultants (2002), Landscape Character Assessment Guidance for England and Scotland, The Countryside Agency and Scottish Natural Heritage;
Dumfries and Galloway Council (September 2014), Dumfries and Galloway Local Development Plan;
Dumfries and Galloway Council (September 2014), Dumfries and Galloway Local Development Plan Supplementary Guidance: Part 1 Wind Energy Development: Development Management Considerations;
Dumfries and Galloway Proposed Local Development Plan: Technical Paper ‘Regional Scenic Areas (January 2013);
Dumfries and Galloway Council (Carol Anderson and Alison Grant, for D&GC) (2011), Windfarm Landscape Capacity Study;
Land Use Consultants, (1998), Dumfries and Galloway Landscape Assessment, Scottish Natural Heritage Review No. 94;
Ash Consultants, (1998), Scottish Borders Landscape Assessment, Scottish Natural Heritage Review No. 112; and
Cumbria County Council, (1995), Cumbria Landscape Classification.
The assessment will also take cognisance of relevant national and local landscape planning policy.
Viewpoint Selection
The candidate viewpoints identified following an initial ZTV analysis based on the scoping layout for Hopsrig Wind Farm are listed in the table below and illustrated on the ZTV shown on Figure 5. The final selection of viewpoints for assessment will be agreed with Dumfries and Galloway Council and SNH during the consultation process.
Scoping Report
Hopsrig Wind Farm
Table 1: Proposed candidate viewpoints
No Viewpoint Name
Landscape Receptors
Visual receptors
Distance from the nearest turbine
Direction Elevation (m AOD)
1 Kirk Cleuch Hill
Southern Uplands
Hill walkers 8.3 km North 313 m
2 River Esk Valley
Narrow Wooded River Valleys
Walkers/ road users
1.9 km North 125 m
3* Bentpath A709
Narrow Wooded River Valleys/ Langholm Hills RSA
Settlement 1.6 km North east 113 m
4 Meljon Muit Southern Uplands/ Langholm Hills RSA
Hill walkers 5.1 km North east 441 m
5** Arkleton Hill Southern Uplands/ Langholm Hills RSA
Hill walkers 10.6 km North east 433 m
6* Langholm Monument
Southern Uplands/ Langholm Hills RSA
Walkers of Whita Hill Walk
9.2 km South east 350 m
7* B7068 Foothills Road users 7.0 km South east 163 m
8** Bowness on Solway
Coastal Margins/Cumbria AONB/ WHS
walkers 25.5 km South 0 m
9* Kirtleton Foothills settlement 8.3 km South 144 m
10** Bankshill Upland Fringe settlement 9.4 km South west
11** A709 Torthorwald Ridge
Lower Dale/ Torthorwald Ridge RSA
road users 22.2 km South west 84 m
12** Corrie Common
Foothills settlement 6.5 km South west 242 m
13** Castle O’erForest Hill Fort
Foothills with Forest
walkers 4.5 km North west 261 m
14** Ettrick Pen Southern Uplands with Forest
Hill walkers 19.4 km North west 689 m
15 A709, south of Davington
Narrow Wooded River Valleys
Settlement/ road users
13.2 km North west 206 m
* Loganhead Wind Farm ES (LVIA) viewpoint;
**Both Loganhead and Crossdykes Wind Farms ES (LVIA) viewpoint
Scoping Report
Hopsrig Wind Farm
Consultees are invited to comment on the above list and provide additional receptors related to this assessment, where these are considered relevant.
Cumulative Context
A provisional list of cumulative schemes within 35 km of the proposed development are listed in Table 2 below and shown in Figure 3.5.
Table 2: Cumulative Scope
Wind Farm
Details Approximatedistance from
Hopsrig
Directionfrom
Hopsrig
ProposedCumulative
ScopeNo of
turbines Tip
Height (m)
Hubheight
(m)
Existing / Operational / Under Construction / Consented
Craig 4 100 60 346 m South east
included
Ewe Hill 22 112.5 71 Abut* South included
Minsca 17 120 80 6.4 km South west
included
Solwaybank 15 126.5 80 5.8 km South included
Hallburn 6 126.5 80 22.8 km South east
included
Harestanes 68 115-125 70-80 23.2 km North west
included
Minnygap 10 125 80 23.9 km North west
included
Clyde Wind Farm (North, Central and South)
152 125 80 34.8 km North west
excluded
Dalswinton 16 125 80 30.7 km West excluded
Langhope Rig 10 121.2 80 30.7 km North east
excluded
Planning Applications
Loganhead 17 130 79.5 Abut* East included
Crossdykes 16 130 80 Abut* West included
Auchencairn 16 121 80 32 km West excluded
Harestanes Extension
7 126.5 80 26.6 km North west
excluded
Birneyknowe 15 132 80 29.8 km North east
excluded
Blackwood 5 120-140 80-100 33.7 km West excluded
Scoping Report
Hopsrig Wind Farm
Table 2: Cumulative Scope
Whitelaw Brae 14 126.5 80 34.6 km North west
excluded
Scoping
Duncow Common 6 125 80 28.4 km South west
excluded
Highlee Hill 13 176 117 32.4 km North east
excluded
West Scales 5 131 80 19.7 km South excluded
Appeal (considered to represent planning application stage development)
Windy Edge 17 121.5 80 17.9 km North east
included
* we will include distances in due course
LVIA Visualisations
The written assessment will be accompanied by a number of plans including maps plotting blade tip and hub height ZTVs and cumulative ZTVs will be produced and as figures in the ES. Other information is likely to include graphical information on landscape character, designations and the location of visual receptors and recreational and transportation routes.
The SNH Guidance recommends that a ZTV should be presented on a single piece of A1 paper folded within the ES, using OS 1:50,000 as the base map. The Guidance does not specify the ratio of scale. For example the ZTV map on A1, in order to capture a 35 km study area, can only fit on a scale of 1:130,000. A map on this scale is not legible and therefore would not appear to be an effective tool for assessment. We have found that on the 1:50, 000 OS base the legible scale is 1:95,000, which fits on A0 showing a 35 km study area.
Based on an initial examination of cumulative data, it is assumed that there will be 10 paired CZTVs, which would result in an excessive production of Figures on A0. Therefore we propose producing the whole set of CZTVs @ 1: 280,000 on A3 showing a 35 km study area and only providing the CZTVs in scale @ 1:95,000 A0 with the existing Craig and consented Ewe Hill Wind Farm.
In order to avoid excessive figure production and to meet with SNH Guidance we propose the following ZTVs figure production:
Hopsrig Blade Tip/Hub height/comparative ZTVs @ 1:95,000 A0 showing 35 km study;
Hopsrig Blade Tip/Hub height/comparative ZTVs @ 1: 280,000 A3 showing 35 km study area;
Hopsrig cumulative ZTVs @ 1: 280,000 A3 showing 35 km study area. Taking account of the current cumulative situation we would propose producing the whole set of CZTVs @ 1: 280,000 on A3 showing 35 km study area; and
CZTV in bigger scale @ 1:95,000 A0 showing 35 km study area, with the existing/consented Craig/Ewe Hill Wind Farms.
The requirements for wireline presentation:
The proposed turbines will be shown in blue, the existing and consented turbines in black and application turbines in green;
Different schemes will be annotated on the wirelines;
Scoping Report
Hopsrig Wind Farm
Fainter colour will be used for schemes at scoping than the colour which will be used for existing, consented or application stage schemes; and
The proposed turbines will be numbered on wirelines.
Based on the above outlined scope two cumulative scenarios will be presented (each viewpoint will be illustrated by two cumulative wirelines) and assessed in relation to the proposed development:
Cumulative Baseline: Hopsrig Wind Farm with operational and consented wind farms; and
Future Cumulative Baseline: Hopsrig Wind Farm with operational, consented and application stage wind farms.
Scoping Report
Hopsrig Wind Farm
Relevant Ecological Legislation Policy and Guidance
The assessment will be undertaken in line with the following European legislation:
Directive 2000/60/EC of the European Parliament and of the Council establishing a framework for the Community action in the field of water policy (“Water Framework Directive”);
Directive 92/43/EEC on Conservation of Natural Habitats and of Wild Fauna and Flora (as amended) (Habitats Directive); and
The Environmental Impact Assessment Directive 85/337/EEC (as amended).
In addition, the following national legislation and policy will be considered as part of the assessment:
Town and Country Planning (Environmental Impact Assessment) (Scotland) Regulations (2011);
The Wildlife and Countryside Act 1981 (as amended);
Nature Conservation (Scotland) Act 2004 (as amended );
The Wildlife and Natural Environment (Scotland) Act 2011;
The Protection of Badgers Act 1992;
UK Post-2010 Biodiversity Framework / UK Biodiversity Action Plan (UKBAP);
Scottish Biodiversity List; and
Dumfries and Galloway Local Biodiversity Action Plan.
The following guidance will be considered as part of the assessment:
Croose, E., Birks, J.D.S. & Schofield, H.W. (2013) Expansion zone survey of pine marten (Martes martes) distribution in Scotland. Scottish Natural Heritage Commissioned Report No. 520;
Gent, T. and Gibson, S. (2003) Herpetofauna Workers’ Manual. JNCC;
Gurnell, J., Lurz, P. McDonald, R. & Pepper, H. (2009) Practical Techniques for Surveying and Monitoring Squirrels. Forestry Commission Practice Note, October 2009;
Hundt, L. (2012) Bat Surveys – Good Practice Guidelines 2nd Edition: Surveying for Onshore Windfarms. Bat Conservation Trust;
Institute of Ecology and Environmental Management (IEEM) Guidelines for Ecological Impact Assessment in the United Kingdom (2006);
JNCC (2013) Guidelines for the Selection of Biological Sites of Special Scientific Interest (SSSIs);
Joint Nature Conservation Committee (2010) Handbook for Phase 1 Habitat Survey – a technique for environmental audit. JNCC;
Natural England (2014a) Natural England Technical Information Note TIN 051. Bats and Onshore Wind turbines – Interim Guidance – Third Edition;
Natural England (2014b) EPS Mitigation Licensing: Latest Developments. Natural England EPS Newsletter, April 2014;
Natural England (2015) Great crested newts: surveys and mitigation for development projects. Species standing advice note. Available via: https://www.gov.uk/guidance/great-crested-newts-surveys-and-mitigation-for-development-projects
Planning Circular 3 2011: The Town & Country Planning (Environmental Impact Assessment) (Scotland) Regulations 2011;
Policy Advice Note PAN 1/2013 - Environmental Impact Assessment (Scottish Executive 2013);
Scoping Report
Hopsrig Wind Farm
Reynolds, P. and Harris, M. (2005) Inverness Badger Survey 2003. Scottish Natural Heritage, Commissioned Report No. 096 (ROAME No. F02LE01);
Rose, F. (2006) A Wild Flower Key, for the British Isles and North West Europe. Warne, London;
Sargent, G. and Morris, P. (2003) How to Find and Identify Mammals. The Mammal Society, London;
Scottish Government (2001) European Protected Species, Development Sites and the Planning System: Interim guidance for local authorities on licensing arrangements;
Scottish Natural Heritage (March 2012) Assessing the cumulative impact of onshore wind energy developments;
Scottish Natural Heritage (2013) Planning for Development: What to consider and include in Habitat Management Plans;
Scottish Renewables, SNH, SEPA, FCS, Historic Scotland (Scotland) (2015, Version 3) Good Practice During Windfarm Construction;
SEPA Land Use Planning System Guidance Note 31: Guidance on Assessing the Impacts of Windfarm Development Proposals on Groundwater Abstractions and Groundwater Dependent Terrestrial Ecosystems, Version 2, October 2014, LUPS-GU31;
SEPA Land Use Planning System Guidance Note 4: Planning guidance on on-shore windfarm developments, Version 7, May 2014, LUPS-GU4;
Stace, C. (2010) New Flora of the British Isles (3rd Edition), Cambridge University Press; and
Strachan, R., Moorhouse, T. and Gelling, M. (2011) The Water Vole Conservation Handbook. Third Edition, Wildlife Conservation Research Unit, Department of Zoology, University of Oxford.
Scoping Report
Hopsrig Wind Farm
Relevant Ornithological Legislation Policy and Guidance
The assessment will be undertaken in line with the following European legislation and guidance:
Directive 2009/147/EC on the Conservation of Wild Birds (Birds Directive);
Directive 92/43/EEC on Conservation of Natural Habitats and of Wild Fauna and Flora (as amended) (Habitats Directive);
The Environmental Impact Assessment Directive 85/337/EEC (as amended); and
Wind energy developments and Natura 2000 (EC 2011).
In addition the following national legislation, policy and guidance will be considered as part of the assessment:
The Wildlife and Countryside Act 1981 (as amended);
The Nature Conservation (Scotland) Act 2004 (as amended);
The Town and Country Planning (Environmental Impact Assessment) (Scotland) Regulations 2011;
The Conservation (Natural Habitats &c.) Regulations 1994 (as amended) (The Habitats Regulations);
SERAD (Scottish Executive Rural Affairs Department) (2000). Habitats and Birds Directives, Nature Conservation; Implementation in Scotland of EC Directives on the Conservation of Natural Habitats and of Wild Flora and Fauna and the Conservation of Wild Birds (‘the Habitats and Birds Directives’). Revised Guidance Updating Scottish Office Circular No 6/1995;
UK Post-2010 Biodiversity Framework / UK Biodiversity Action Plan (UKBAP);
Dumfries and Galloway Local Biodiversity Action Plan;
Birds of Conservation Concern (BoCC) 4 ‘Red List’ (Eaton et al. 2015);
Scottish Natural Heritage (2000) Windfarms and birds: calculating a theoretical collision risk assuming no avoidance action. SNH Guidance Note. SNH;
Scottish Natural Heritage (2006) Assessing significance of impacts from onshore windfarms on birds outwith designated areas;
Scottish Natural Heritage (2009) Environmental Statements and Annexes of Environmentally Sensitive Bird Information; Guidance for Developers, Consultants and Consultees;
Scottish Natural Heritage (2012) Cumulative effects of windfarms;
Scottish Natural Heritage (2013, revised 2014) Recommended bird survey methods to inform impact assessment of onshore wind farms; and
Scottish Natural Heritage (2013) Assessing connectivity with Special Protection Areas.
Scoping Report
Hopsrig Wind Farm
Relevant Cultural Heritage Legislation, Policy and Guidance
Legislation concerning the protection and conservation of the historic environment includes:
Ancient Monuments and Archaeological Areas Act61; as modified by the Historic Environment (Amendment) (Scotland) Act62
Planning (Listed Buildings and Conservation Areas) (Scotland) Act63; and
Town and Country Planning (Scotland) Act64, as amended in the Planning (Listed Buildings and Conservation Areas) (Scotland) Act65 and as modified by the Historic Environment (Amendment) (Scotland) Act66.
Relevant planning policy and guidance concerning the historic environment includes:
The National Planning Framework for Scotland (NPF3)67;
Scottish Planning Policy (SPP)68;
Scottish Historic Environment Policy (SHEP)69;
Planning Advice Note 2/2011 (PAN 2)70;
Chartered Institute for Archaeologists (CIfA) Standard and Guidance for Historic Environment Based Desk-Based Assessment71;
The Dumfries and Galloway Local Development Plan72; and
Managing Change in the Historic Environment: Setting73.
Cultural Heritage Gazetteer - available upon request.
The full gazetteer will be provided to Dumfries and Galloway Council (archaeology) and Historic Environment Scotland.
61 The Ancient Monuments and Archaeological Areas Act 1979. (c.46). London: HMSO. 62 Historic Environment (Amendment) (Scotland) Act 2011. London: HMSO. 63 Planning (Listed Buildings and Conservation Areas) (Scotland) Act 1997. (c.9). London: HSMO. 64 Town and Country Planning (Scotland) Act 1997. (c.9). London: HSMO. 65 Planning (Listed Buildings and Conservation Areas) (Scotland) Act 1997. (c.9). London: HSMO. 66 Historic Environment (Amendment) (Scotland) Act 2011. London: HMSO 67 The Scottish Government, 2014. Scotland’s Third National Planning Framework. [pdf] The Scottish Government. Available at: <http://www.gov.scot/Resource/0045/00453683.pdf> [Accessed 2 February 2016]. 68 The Scottish Government, 2014. Scottish Planning Policy. [pdf] The Scottish Government. Available at: <http://www.scotland.gov.uk/Resource/0045/00453827.pdf> [Accessed 2 February 2016]. 69 Historic Scotland, 2011. Scottish Historic Environment Policy. [pdf] Historic Scotland. Available at: http://www.historic-
scotland.gov.uk/shep-dec2011.pdf [Accessed 2 February 2016]. 70 The Scottish Government, 2011. PAN2/2011 Planning and Archaeology. [pdf] The Scottish Government. Available at: http://www.gov.scot/Resource/Doc/355385/0120020.pdf [Accessed 2 February 2016]. 71 Chartered Institute for Archaeologists, 2014. Standards and Guidance for historic environment desk-based assessment. [pdf]
Chartered Institute for Archaeologists. Available from: <http://www.archaeologists.net/sites/default/files/CIfAS&GDBA_2.pdf>[Accessed 2 February 2016]. 72 Dumfries and Galloway Council, 2014a. Dumfries and Galloway Council Local Development Plan. [pdf] Dumfries and Galloway
Council. Available at: <http://www.dumgal.gov.uk/CHttpHandler.ashx?id=11287> [Accessed 2 February 2016 73 Historic Scotland, 2010. Managing Change in the Historic Environment: Setting. [pdf] Historic Scotland. Available at: <http://www.historic-scotland.gov.uk/setting-2.pdf> [Accessed 2 February 2016].