HIGHT_The Nicoll Highway Collapse
-
Author
seniorista-gunawan -
Category
Documents
-
view
253 -
download
5
Embed Size (px)
Transcript of HIGHT_The Nicoll Highway Collapse

The Nicoll Highway CollapseThe Nicoll Highway Collapse
D W Hi htD. W. HightT.O. Henderson + A.R. Pickles
S. Marchand

ContentContent• Background and construction sequence• Observations up to the point of collapse, including
monitoringmonitoring• The collapse• Post-collapse investigations• Design errors• Jet grout layers• Ground conditions and the buried valley• Ground conditions and the buried valley• The need for a trigger• Back analyses of the collapse• Relative vertical displacement and forced sway• The bored piles• Collapse mechanism and its trigger• Collapse mechanism and its trigger• Lessons to be learnt

C824210m 2-cell cut &
cover tunnels
34m Diameter Temporary Staging Area (TSA) Shaft -
35m deep
3-level cut & cover Station (BLV)
550m 2-cell cut & cover tunnel and
siding (BLS)
C824
Collapse siteM3 area
3-level cut & cover Station (NCH)
200m cut & cover stacked 4-cell
scissors crossover tunnel
25m - 30m deep
30m - 33m deep
35m 2-cell cut and cover tunnel
C825
M3 area370m stacked 2-cell cut & cover tunnel
20m - 25m deep
800m twin bored tunnel
C824 - 2km of cut and cover construction
mostly in soft clay - up to 35m deep
Ci l Li St 1Ci l Li St 1Circle Line Stage 1Circle Line Stage 1

Reclamation dates
G ld Mil
The Concourse
Plaza HotelM d k
Beach Road
1930-1940’sGolden Mile
Tower
Golden Mile Complex
Plaza Hotel
NCH station Merdeka Bridge
1930-1940 sreclamation
Nicoll Highway
Cut and Cover tunnels
1970’sreclamation
TSAshaft
Kallang
reclamation
Kallang Basin
Courtesy of Richard Davies

31700
54+900 ABH32
31650
RTH
ING
(m)
M354+900
M2
54+812
M3010MC3007
MC3008
ABH30
ABH34
ABH35
ABH83
ABH85
AC-1
AC-2
AC-3
AC-4
NO
R
MC2026
ABH27
ABH28ABH29
ABH31 ABH33
ABH81
ABH82
ABH84
31550 31600 31650 31700 31750 31800
EASTING (m)
31600
M2064 M2065
MC2025
ABH27
EASTING (m)
Pre- and post-tender site investigation

SOUTH NORTHABH 31 ABH 32
M304M309100 Fill
U
Fill
Upper estuarineUpper estuarine
Upper
M304M309
90
UpperMarine
Clay
MarineClay
Upper F2
80
Upper F2 Upper F2
LowerMarine
LowerMarine
70
Clay Clay
Base marine clay LowerTop of OA
o eestuarine
Lower F2
OldOld
Alluvium
Typical section in M3Alluvium
Alluvium

0 0 4 0 8 1 2 1 6 2Cone resistance, qc (MPa)
0 20 40 60 80 100Undrained shear strength (kPa)
0 0.4 0.8 1.2 1.6 20
AC1AC2AC3AC4
0 20 40 60 80 1000
AC1AC2AC3AC4
10
AC4
10
AC4
Nkt=12
20
Dep
th (m
)
20
Dep
th (m
)30 30
40 40
Piezocone data for M3 area

Construction details and sequenceConstruction details and sequence

Fill
SOUTH NORTH
Upper
Upper E
Fill
Formation levelapprox 33m bgl
Marine Clay
Upper F2
Temporary diaphragmwalls,0.8m
Driven kingpost
Sacrificial JGP
LowerMarine Clay
gp
Permanent bored pilessupportingrail boxes Sacrificial JGP
Permanent JGPLower E
10 levels of steel struts at 3m +3.5m vertical
centres
Lower F2
OA SW2 (N=35)
OA SW1 (N 72)OA SW1 (N=72)
OA (CZ)

General Excavation sequence for M3 – up to level for removal of sacrificial JGP and installation of 10th level strut

Tidal sea
TSA Shaft
Utility crossingsM3
Curved wallsM2
Nicoll Highway
24/3/04

Support beam
ShaftKingpost
M3
C channel stiffener
No waler
C channel stiffener
Jacking point
M2Walers
Non-splayed strut
Splayed strut
M2Walers

Two Struts Bearing Direct on Single panel
Single Strut with Splays Struts on Walers - No Splays
g yBearing on Waler for Single
panel
Gaps in Diaphragm Wall for 66kV Crossing

South side 13 March 04South side 13 March 04

Events and observations prior to collapseEvents and observations prior to collapseEvents and observations prior to collapseEvents and observations prior to collapse


Plate stiffener
C channelstiffener
Replacement of plate stiffeners at strutReplacement of plate stiffeners at strut--waler connectionwaler connection

Strut bearing
C channel
Strut bearing directly on Dwall
C channel
connection

Excavation for the 10th level of struts, including removal of the sacrificial JGPExcavation for the 10 level of struts, including removal of the sacrificial JGP

Observations on the morning of the collapse

North wall
14 2 6 73
M305M304M303M302M301
335 336 338 339 340334333 337
H H HKP 182KP 181 KP 183
1 5 5 5 7 7
M306 M307 M308 M309 M310
1 Order in which distortion to waler noted
Excavation to 10th complete
Excavation in progress
Location of walers, splays and Dwall gaps

S335 9S335-9
Strut 335-9 south wall

S338 9S338-9
Strut 338Strut 338--9 north wall9 north wall


Instrumentation and results of monitoringInstrumentation and results of monitoringInstrumentation and results of monitoringInstrumentation and results of monitoring

M2/M3 plan at 9M2/M3 plan at 9thth levellevel
M3
TSA Shaft
M2
TSA Shaft
I 65
All struts at S335 instrumented for load
measurementsGWV24
I 104I 104

5000Excavation Front
Beyond S335 at the
4000
4500SG3358 Total ForceSG3359 Total Force Excavation Front
Approaches S335 at the end of Day Shift on
start of Day Shift on 18th April 2004
3000
3500
y17th April 2004
Excavation Front for 10th Level Advancing
from S338
d (k
N)
2000
2500
stru
t loa
d
1000
1500
Excavation Front for 10th Level Between easu
red
0
500
20th April19th April18th April17th April16th April15th April
S336 and S335 M
0102030405060708090100110120130140
Hours before collapse

Change in Measured Load at Strut 335
5000
4000
4500
5000
336(N) & 337(N)
Waler Buckling Observed
Support Bracket at 335(S) Drops Off335(N)
Waler Buckling Observed
3000
3500
4000
(kN
)
2000
2500
3000
trut l
oad
1500
2000Strut Load 335-9
Strut Load 335-8
338(N) & 335(S)easu
red
s
500
1000 338(N) & 335(S)
Waler Buckling ObservedMe
06.00 7.00 8.00 9.00 10.00 11.00 12.00 13.00 14.00 15.00 16.00
Time on 20April 2004

Observed trends in 8th and 9th strut loads
Loadf9
th
Observed
nsta
llatio
n of
Observed8th
9th
Excavation approaches
In
m m
9th
+ passes beyond S335
5 18 20
9am
3.30
p
April 2004

The trends were consistent with there being gyielding of the 9th level strut-waler connection when the excavation passed beneath but with
f th i ifi t h i l d i ithno further significant changes in load in either the 9th or 8th level struts until the collapse was initiatedinitiated

0 200 400
Horizontal displacement (mm)
0I 104
400 200 0
Horizontal displacement (mm)
0I 65
10
I 10410 April
10
I 6510 April
10 10
Behind South Wall North Wall
20
epth
(m)
20
epth
(m)
30
De
30
De
40 40
50 50

0 200 400
Horizontal displacement (mm)
0I 104
400 200 0
Horizontal displacement (mm)
0I 65
10
I 10410 April15 April
10
I 6510 April16 April
10 10
Behind South Wall North Wall
20
epth
(m)
20
epth
(m)
30
De
30
De
40 40
50 50

0 200 400
Horizontal displacement (mm)
0I 104
400 200 0
Horizontal displacement (mm)
0I 65
10
I 10410 April15 April17 April
10
I 6510 April16 April17 April
10 10
Behind South Wall North Wall
20
epth
(m)
20
epth
(m)
30
De
30
De
40 40
50 50

0 200 400
Horizontal displacement (mm)
0I 104
400 200 0
Horizontal displacement (mm)
0I 65
10
I 10410 April15 April17 April20 April
10
I 6510 April16 April17 April20 April
10 10
Behind South Wall North Wall
20
epth
(m)
20
epth
(m)
30
De
30
De
40 40
50 50

500
400
nt, m
m
I104 maxI65 max
300
disp
lace
men
South wall
200
m h
oriz
onta
l
N th ll
100Max
imu North wall
5-Jul 9-Aug 13-Sep 18-Oct 22-Nov 27-Dec 31-Jan 6-Mar 10-Apr0
Comparison of inclinometer readings I65 and I10420042003

• S338-9 stood for 8 days under load and was 20m• S338-9 stood for 8 days under load and was 20m from excavation front
• S335 9 stood for 2 5 days under load and was over• S335-9 stood for 2.5 days under load and was over 8m from excavation front
B th S335 9S & S338 9N b kl d ithi 10 i t• Both S335-9S & S338-9N buckled within 10 minutes
• Load in S335-8 and S335-9 was almost constant b t 18 A il d i iti ti f llbetween 18 April and initiation of collapse
• All C-channel connections failed downwards at both ends
• The south wall was pushing the north wall back
Key observations
The south wall was pushing the north wall back

The collapseThe collapse

3.33pm

3.33pm

3.34pm

3.34pm

3.34pm

3.41pm

3.46pm

Post-collapse investigationsPost collapse investigations
Design errors

Errors• Misinterpretation of BS5950 with regard to stiff
b i l hbearing length• Omission of splays
Effects• Design capacity of strut-waler connection was 50% ofDesign capacity of strut waler connection was 50% of
required design capacity where splays were omitted
Errors in structural design of strutErrors in structural design of strut--waler connectionwaler connection

• Capacity based on BS5950:1990 = 2550 kN• Capacity based on BS5950:1990 = 2550 kN
• Average ultimate capacity based on physicalAverage ultimate capacity based on physical load tests = 4100 kN
9 % f• Based on mill tests, 95% of connections had capacity of 3800 kN- 4400kN
• Predicted 9th level strut load in 2D analyses which ignored bored piles was close to ultimate capacity therefore collapse wasultimate capacity therefore collapse was considered by the COI to be inevitable
Inevitability of collapse

• Method A and Method B refer to two alternative ways of modelling undrained soil behaviour in Plaxis (Pickles, 2002)2002)
• Method A is an effective stress analysis of an undrained blproblem
• Assumes isotropic elastic behaviour and a Mohr-C fCoulomb failure criterion
• As a result mean effective stress p’ is constant until yieldp y
• Method A was being applied to marine clays which were of low over-consolidation or even under-consolidatedof low over consolidation or even under consolidated because of recent reclamation
• Method B is a total stress analysis
Methods A and BMethod B is a total stress analysis

t
Cu from Method A
Cu from Method B
p’
The shortcomings of Method A

105 105
Method A Method B
90
95
100
90
95
100
75
80
85
RL
(m)
75
80
85
RL
(m)
60
65
70
60
65
70
55-0.050 0.000 0.050 0.100 0.150 0.200 0.250 0.300
Wall Disp. (m)
Exc to RL 100.9 for S1 Exc to RL 98.1 for S2 Exc to RL 94.6 for S3
Exc to RL 91.1 for S4 Exc to RL 87.6 for S5 Exc to RL 84.6 for S6
55-0.050 0.000 0.050 0.100 0.150 0.200 0.250 0.300
Wall Disp. (m)
Exc to RL 100.9 for S1 Exc to RL 98.1 for S2 Exc to RL 94.6 for S3
Exc to RL 91.1 for S4 Exc to RL 87.6 for S5 Exc to RL 84.6 for S6
M3 S th W ll Di l t
Exc to RL 81.6 for S7 Exc to RL 78.3 for S8 Exc to RL 75.3 for S9
Exc to RL 72.3 for S10
Exc to RL 81.6 for S7 Exc to RL 78.3 for S8 Exc to RL 75.3 for S9
Exc to RL 72.3 for S10
M3 - South Wall DisplacementMethod A versus Method B

95
100
105
100
105
Method A Method B
75
80
85
90
95
RL
(m)
75
80
85
90
95
RL
(m)
55
60
65
70
75
55
60
65
70
75
-300
0
-250
0
-200
0
-150
0
-100
0
-500 0
500
1000
1500
2000
2500
3000
3500
4000
Bending Moment (kNm/m) -300
0
-250
0
-200
0
-150
0
-100
0
-500 0
500
1000
1500
2000
2500
3000
3500
4000
Bending Moment (kNm/m)
M3 - South Wall bending momentsMethod A versus Method BMethod A versus Method B

M th d A Method Bg ( )
220622002400260028003000
_ S1
2383
200022002400260028003000
Method A Method B
8001000120014001600180020002200
Stru
t Loa
d (k
N/m
)_ S1
S2
S3
S4
S5
S6
S7 800100012001400160018002000
Stru
t Loa
d (k
N/m
)
S1
S2
S3
S4
S5
S6
0200400600 S8
S9
0200400600 S7
S8
S9
M3 – strut forcesMethod A versus Method B

• Method A over-estimates the undrained shear strength of normally and lightly overconsolidated lclays
• Its use led to a 50% under-estimate of wall displacements and of bending moments and an under-estimate of the 9th level strut force of 10%
• The larger than predicted displacements mobilised the capacity of the JGP layers at an earlier stage p y y gthan predicted
Method AMethod A

St t l d i• Structural design errors
• Removal of splays at some strut locationsp y
• Introduction of C-channel waler connection detail
• Use of Method A in soil-structure interaction analysis
C ll i it bl f th• Collapse was an inevitable consequence of the design errors which led to the applied loads on the struts increasing with time and equalling the capacity of the strut-waler connectionof the strut-waler connection
COI view on the principal causes ofthe collapse

St t l d i• Structural design errors
• Removal of splays at some strut locationsp y
• Introduction of C-channel waler connection detail
• Use of Method A in soil-structure interaction analysis
C ll i it bl f th• Collapse was an inevitable consequence of the design errors which led to the applied loads on the struts increasing with time and equalling the capacity of the strut-waler connectionof the strut-waler connection
COI view on the principal causes ofthe collapse

Post-collapse investigationsPost collapse investigations
Jet grout

Excavation of sacrificial JGP in Type H

JGP quality in 100mm cores from borehole M1 in Type KJGP quality in 100mm cores from borehole M1 in Type K

Shear wave velocity measurements in JGP at Type K

5 Shear wave section
4
Pressuremeter section
3
ckne
ss (m
)
2
JGP
thic
Design thickness
1
0 2 4 6 8
0
Thicknesses of JGP in Type K

Post-collapse investigationsPost collapse investigations
Ground conditions andsoil propertiessoil properties

BN3
P33
P36
P40P41/P47P42/P48
31700
54+900 AN1
BN2E
CN3
DN2E
DN3AN2
BN2WCN2
TSAN2
P45P52
P54
31650
RTH
ING
(m)
M354+900
M2
54+812
66KVNI
AN1
BN1E
BN1Ea
BS1Ea
CL-1a
CL-2CL-3g
CN1DN1E
BN1W
DN1W
DN2W
EN1
EN2
FN1
FN2
NO
R
66KVSAS1
BS1EaBS1Eb
BS2E
CFVN
CL 3g
CS1CTSN
DS1ESPTSa
TSAS2b
AS2
BS1W
CPTNCPTNa
CS2
DS1W
ES1
FS1
TSAS2
31550 31600 31650 31700 31750 31800
EASTING (m)
31600BS3E
DS2E
DS3E
AS3
BS2W
BS3W
CS3
DS2W
DS3W
ES2
ES3
FS2
EASTING (m)BS4E
BS4Ea
DS4E
BS4W
CS4
DS4W
PostPost--collapse ground investigationcollapse ground investigation

0 0.4 0.8 1.2 1.6 2Cone resistance, qt (MPa)
00 0.4 0.8 1.2 1.6 2
Cone resistance, qt (MPa)
0
10
BN1Wqt
u2fs
10
BS2Wqt
u2fs
North South
20
Dep
th (m
)
20
epth
(m)
30
D
30
De
400 0.4 0.8 1.2 40
0 0 4 0 8 1 2Pore pressure, u2 (MPa)
0 0.02 0.04 0.06 0.08Friction, fs (MPa)
0 0.4 0.8 1.2Pore pressure, u2 (MPa)
0 0.02 0.04 0.06 0.08Friction, fs (MPa)
CPT profiles north and south of collapse area

100
φ=28.5o
50
Ko=0.5
φ=34.2o
0Pa)
0 50 100 150 200s' (kPa)
0
t (kP
-50
P-8P-9
-100
P-24 P-26
φ=35o
Kisojiban’s CAU tests onKisojiban’s CAU tests onUpper and Lower Marine ClayUpper and Lower Marine Clay

50 55 60 65 70 75 80 85 90 95 100 105
Tender SI boreholesTender SI CPTsDetailed design SIDetailed design SI CPTsPost collapse SIPost collapse SI CPTs
BN3
P33
P36
P40 P41/P47
P42/P48
31700
Post collapse SI CPTsBoreholes for bored pilesMagnetic logging boreholes
BN2E
CN3
DN2E
DN3
AN2
BN2WCN2
TSAN2
P45P52
P54
31650ING
(m)
M354+900
M2M3010MC3007
ABH30
ABH32
ABH34
ABH35ABH83
ABH85
AC 1
AC-2
AC 3
AC-4
66KVNI
AN1
BN1EBN1Ea
CL-1a
CN1
DN1E
BN1W
DN1W
DN2W
EN1
EN2
FN2WN1WN10
WN11WN12
WN13WN14
WN15WN16
WN17WN18
WN19
WN2
WN20
WN21WN22
WN23WN24
WN25WN26
WN28
WN3
WN30A
WN4WN5
WN6WN7A
WN8
WN9
31650
NO
RTH
I
54+812 MC3008
ABH28
ABH29
ABH31 ABH33
ABH81
ABH82
ABH84
AC-1AC-3
66KVS
AS1
BS1EaBS1Eb
CFVN
CL-2CL-3g
CS1CTSN
DS1E
SPTSa
TSAS2b
BS1W
CPTNCPTNa
DS1W
ES1
FN1
TSAS2
WN27WN29
WN30A
WN31WN32
WN33WN34
WN35WN36WN37
WN38WN39
WN40
WS1
WS10WS14WS15WS16
WS17
WS18WS19
WS2
WS20WS21
WS22WS23
WS24WS25
WS26WS27
WS28WS29
WS3
WS30WS31
WS32
WS34WS36
WS4A
WS5WS6
WS7WS8
WS9
WS11WS11A
WS11BWS11C
WS12WS12A
WS12BWS12C
WS13WS13A
WS13BWS13C
31550 31600 31650 31700 31750 31800
31600
M2064 M2065
MC2025
MC2026
ABH27
BS2E
BS3E
DS2E
AS2
AS3
BS2W
BS3W
CS2
DS2W
ES1
ES2
FS1
FS2
WS32WS33WS35A
WS37WS38
31550 31600 31650 31700 31750 31800
EASTING (m)BS4E
BS4Ea
DS3E
BS4W
CS3
CS4
DS3WES3
Evidence for a buried valley in the Old AlluviumDS4E
DS4W

100
110
90
(mR
L)
70
80
ELEV
ATI
ON
(
Bottom of F2 Clay in Marine ClayDetailed design site investigation
50
60
Detailed design site investigationBottom of F2 Clay in Marine ClayPost collapse site investigationsTop of OLD ALLUVIUMPost collapse site investigations
Section along north wall

100
110
90
100
RL)
70
80
ELEV
ATI
ON
(mR
60
E
50
Section along south wall

Tender SI boreholesTender SI CPTsDetailed design SI boreholesDetailed design SI CPTs
BN377.02
P33
P36
P42/P48
86.07
86 90
31700
Detailed design SI CPTsPost collapse SI boreholesPost collapse SI CPTsBoreholes for bored pilesMagnetic logging boreholes
BN2E
CN3
DN2E
DN3
82.61
82.27
81.91
P40 P41/P47
P45P52
P54
86.3986.30 86.84
86.90
86.2085.98
86.58
31650HIN
G (m
)
M354+900
M2KP181 KP182 KP183
WN1
WN10WN11WN12WN13WN14WN15WN16WN17WN18WN19
WN2
WN20WN21WN22WN23WN24
WN25WN26WN27
WN29
WN3
WN30AWN31
WN4WN5WN6WN7AWN8WN9 82.16
81.2180.9580.6680.3780.7279.8681.8680.8180.3180.88
82.31
80.9479.9379.9180.1580.9580.3679.57
79.72
81.2581.3881.4381.4281.3881.0581.25
66KVNI
AN1
BN1EBN1Ea
CL 2CL-3g
CN1
DN1E
DN2E
81.88
82.91
80.6881.5783.13
81.86
81.94
M301082.55MC300780.65
ABH32
ABH35ABH83
ABH8583.41
81.6983.39
81.69
AC-1
AC-2
AC-3
AC-481.7379.98
338 M305M304
M303
M302
M210M20931650
NO
RTH 54+812
KP181WN31WN32
WN33WN34
WN35WN36WN37
WN38
WN39
WN40
WS1
WS10WS15WS16
WS17WS18WS19
WS2
WS20WS21WS22WS23WS24WS25WS26WS27WS28WS29
WS3
WS30WS31WS32
WS34WS35A
WS37WS38
WS4AWS7WS8WS9
78.3477.5177.71
78.0280.58
80.5380.66
81.4378.35
80.83
81.06
83.19
78.20
72.2881.3981.39
81.4581.2881.38
75.20
80.8481.4879.9380.0379.9981.5979.7678.2578.5279.57
76.59
78.7879.1079.25
79.2379.69
80.6581 26
76.7773.8472.6172.70
66KVS
AS1
BS1EaBS1Eb
BS2E
CFVN
CL-2
CS1CTSNDS1E
SPTSa
TSAS2b
71.09
75.98
74.6074.72
81.97
78.0480.22
82.0182.17 81.09
71.52
82.16
ABH29
ABH31 ABH33
ABH81
ABH82
ABH84
81.23
82.07 80.51
80.13
80.37
82.57
80.7681.69M301M211
M210M209
M310M309M308M307
M213
M212 & M306missing
31550 31600 31650 31700 31750 31800EASTING (m)
31600
81.26 BS2E
BS3E
DS2E
82.28
81.29
80.68
M206479.00
MC202581.70
ABH2780.69
-14 -12 -10 -8 -6 -4 -2 0 2 4 6 8 10 12
BS4EBS4Ea
DS4E
80.3380.96
79.24
Distortion to upper F2 layer caused by the collapse

Buried valley in the Old Alluvium

Buried valley in the Old Alluvium

Coincidence between buried valley anddistortion to upper F2 layer

• There was a buried valley crossing the site of the collapse diagonally from south-west to north-east
• The presence and setting of the buried valley explain the asymmetric conditions and the different collapse on the north and south sideson the north and south sides
• The buried valley coincides with the major ground distortion on the south side and was clearly influential in the collapse
• Below the Lower Marine Clay the buried valley was infilled with estuarine organic clays on the south sideinfilled with estuarine organic clays on the south side and fluvial clays on the north side
• Gas exsolution almost certainly occurred in the deep y porganic clays as a result of stress relief, reducing their strength further
The buried valleyThe buried valley

CN3
DN3
GA
ABH-32ABH-34
ABH-85EN2
CN2AN2
TSAN2
WN1
BN2W
BN1W
DN2W
66KVN
BN2E
I-67
AN1
CN1
DN2E
AS MAIN
94.9MC3007 MC3008
M3010
ABH 31
ABH-30 AC-2AC-4
AC-3
AC-1
ABH-83
FN2
EN1
FN1
WN1
WN10
WN20
WN30
WN36 WS166KVS
WN26WN28
WN29
WN33WN34
WN35
WN24WN25
WN27
WN31WN32
DN1W
BN1W
BS1W
I-65
I-102
BN1Ea BN1E66KVN
CL-1A
CL-2
CL-3GKP181
KP182KP183
I 67
DN1E
BS1Ea
BS1Eb
ABH-35
SEA WALL
ABH-33ABH-31
ABH-28
ABH-27
ABH-29
ABH-81
ABH-82
ABH-84
MC2026
FS1ES1
DS1E
CS1 TSAS2
WS34 WS30
WS20WS10
WN40
WS38
66KVS
CPTN
CFVNCPTNa
SPTSa
WS35WS36
WS37
WN39
WN38
WN37
TSAS2B
WS32WS31
WS29WS28
WS26WS27
WS33
DS1W
BS1W
AS2
AS1
I-104
I-103
I-66
BS2E
M2064
ABH-26
ABH 27
ABH-80
FS2
ES2
DS2E
CS2
DS3ECS3
AS3
DS3W
BS2W
DS2W
BS3W
I-64 M2065
BS3E
ES3
BS4E
DS3W
Post-collapse geometry and sequence of excavationsuperimposed on buried valley

GAS WN1BN1W 66KVN ICN1AS MAIN ABH-30 AC
WN10
WN20N1WI-65
BN1Ea BN1E66KVN
DN1E66kV Cable
MC3007M3010
AC-3
ABH-83
WN20
WN245CL-1A
CL 3GKP181
KP182KP183
ABH-31ABH 84
WS166KVS
SPTSaBS1WI-104
CL-2
CL-3G
BS1Ea
BS1Eb
ABH-29
ABH-82
ABH-84
DS1E
CS1
WS20WS10
SPTSa
DS1W
AS1
LL
ABH 29 CS1WS26
DS1W
Sequence of excavation in relation to buried valley

• The buried valley was crossed without collapse developing
• Strut forces would have been a maximum in the buried valley and would have varied across the valley
• The collapse was not, therefore, inevitable
• An external influence (trigger) is required to explain the timing of the collapse and why it occurred afterthe timing of the collapse and why it occurred after crossing the buried valley
Significance of crossing the buried valley without Significance of crossing the buried valley without collapsecollapse

• S338-9 stood for 8 days under load and was 20m from excavation frontfrom excavation front
• S335-9 stood for 2.5 days under load and was over 8m from excavation front8m from excavation front
• Both S335-9S & S338-9N buckled within 10 minutes
• Load in S335-8 and S335-9 was almost constant between 18 April and initiation of collapse
• All C-channel connections failed downwards at both ends
• The south wall was pushing the north wall back
Key observations

• 3D effects cannot explain why the collapse was initiated at 9am – S338 was 20-24m from theinitiated at 9am S338 was 20 24m from the excavation face and had stood for 8 days without distress, S335 was 8-12m from the excavation face
• Time effects cannot explain why the collapse was initiated at 9am – there was no evidence of loadinitiated at 9am there was no evidence of load increases in the monitoring
Potential triggersPotential triggers

Load
g of
9th
er
f9th
Yiel
din
Observed
Trig
g
nsta
llatio
n of
Observed
Minor additional loading<2mm yielding in 9th
8th
9th
Excavation approaches
In
m m
9th
+ passes beyond S335
5 18 20
9am
3.30
p
April 2004

Post-collapse investigationsPost collapse investigations
Back analyses of the collapse

• Analyses by Dr Felix Schroeder and Dr Zeljko Cabarkapa using Imperial College Finite Element p g p gProgram (ICFEP)
• 2D section through M307 (I104) and M302 (I65)• 2D section through M307 (I104) and M302 (I65)
• Bored piles are not modelled (enhanced JGP)p ( )
• Upper and Lower Marine Clays, F2 and lower Estuarine Clay modelled using Modified Cam ClayClay modelled using Modified Cam Clay
• Coupled consolidationp
• Fill and OA sand modelled using Mohr Coulomb. OA-CZ clay/silt modelled as Tresca
Geotechnical analysesclay/silt modelled as Tresca

W ll EI d d t ll f ki b d• Wall EI reduced to allow for cracking, based on reinforcement layout
• Bending moment capacities set according to reinforcement layout and ultimate strengths of steel and concrete as supplieda d co c ete as supp ed
• JGP treated as brittle material
• 9th level strut capacity set and strut allowed to strain soften 72 hours after excavation to 10th level.
Geotechnical analyses

North South
F2 F2
Upper Marine Clay Upper Marine Clay
Estuarine EstuarineFill Fill
+102.9+98.58+96.58
+84.58+81.58
+102.9+98.58+97.07
+85.57+82.07
OA (Sand) - OA-CZ
OA (Sand) - OA-CZOA (Clay/Silt) - OA-SW-1
F2
Lower Marine ClayLower Marine Clay+71.00
+67.00+63.00 +63.57
+61.57+57.57
OA (Clay/Silt) - OA-CZ OA (Clay/Silt) - OA-CZ
Stratigraphy assumed for ICFEP analyses


North wall 9th South wall
95
100
95
100
85
90
85
90
measuredpredicted
80
85
80
85
predicted
n (m
RL)
measured
predicted
70
75
70
75
Ele
vatio
60
65 65
55
60
50 0 50 100 150 200 250 300 35055
60
450 -400 -350 -300 -250 -200 -150 -100 -50 0 50
Horizontal displacement (mm) Horizontal displacement (mm)

North wall 10th South wall
95
100
95
100
85
90
85
90
measuredpredicted
80
85
80
85
n (m
RL)
measuredpredicted
predicted
70
75
70
75
Ele
vatio
60
65 65
55
60
50 0 50 100 150 200 250 300 35055
60
450 -400 -350 -300 -250 -200 -150 -100 -50 0 50
Horizontal displacement (mm) Horizontal displacement (mm)

Predicted trends in 7th, 8th and 9th strut loadsed cted t e ds , 8 a d 9 st ut oads
4000
4500
3000
3500
4000
m)
1500
2000
2500 Strut 7Strut 8Strut 9
9
8rce
(kN
/m
500
1000
1500
7
Pro
p fo
r
0280.00 281.00 282.00 283.00 284.00 285.00 286.00
( )
6 hoursTime (days) 6 hours

Observed trends in 8th and 9th strut loads
Loadf9
th
Observed
nsta
llatio
n of
Observed8th
9th
Excavation approaches
In
m m
9th
+ passes beyond S335
5 18 20
9am
3.30
p
April 2004

• The analyses matched reasonably well the build up in• The analyses matched reasonably well the build up in horizontal wall movements, and the trends in the forces in the 7th, 8th and 9th level struts
• To match movements and forces at all stages it was necessary to model the jet grout as a brittle material
• The upper JGP was predicted to pass its peak strength during excavation to the 6th level and the lower JGP toduring excavation to the 6th level and the lower JGP to pass its peak strength during excavation to the 9th level
Th 9 h l l h d i i d i i• The 9th level strut reached its capacity during excavation to the 10th level
Key findings from geotechnical analyses

• The collapse had to be initiated by allowing the 9th level strut to strain soften – a ductile failure of the connection was not associated with a collapse
• The bending moment capacity of the south wall was reached on the first stage of excavation below the 9th l l b t hi did t f i th ll til thlevel, but a hinge did not form in the wall until the sacrificial JGP layer had been removed
Key findings from geotechnical analyses

Trigger required to initiate collapseTrigger required to initiate collapseTrigger required to initiate collapseTrigger required to initiate collapse
Relative vertical displacement between the kingposts and Dwall panels

)
100
Top of southern wall-nolimitTop of southern wall-OA1Top of southern wall-OA2 8thw
all (
mm
)
Up
0
50p
9th
10th
ent o
f Dw
-50
00 5 10 15 20 25 30 35
ispl
acem
-100
Verti
cal d
i
Down
Excavation depth (m)
V
Predicted settlement of south wall during excavation


500
300
400
Run 4apfnolimit
Run 4apfnolimit_OA1
Run 4apfnolimit_OA2
ts (m
m)
200
plac
emen
t
0
100
-5 0 5 10 15 20 25 30
rtica
l dis
p
-200
-100
North Wall South Wall
Ver
Distance (m)Distance (m)
Predicted vertical displacement of lower JGP layerafter excavation to 10th level

20
2
Strut 262no backfill
10
(mm
)
Nor
th w
all
th w
all
ngpo
st
Typical relative Typical relative displacements of displacements of
strut betweenstrut between0
and
kin
gpos
t
1
3
7A
Soutkin
strut between strut between walls and kingpostwalls and kingpost
l bet
wee
n w
all 2
3
3
7B
-10fe
renc
e in
leve
4
6A
-20
Diff
1
5
6A
7A
-30
4 57B

• Calibrated FE analyses predict downwardCalibrated FE analyses predict downward displacement of Dwall and upward displacement of kingpost when sacrificial JGP layer excavated
• Survey data supports upward vertical displacement of centre of strut relative to ends
Relative vertical displacementRelative vertical displacement

KP184KP183KP182KP181KP180
339340
335 336 337 338
Sacrificial JGP
9th level
Excavation front
Lower JGP
Kingposts in long section

Post-collapse investigationsPost collapse investigations
Structural steel physical testsand numerical analyses.
The effect of relative verticalThe effect of relative vertical displacement

5000
12mm stiffenerplates
Waler
4000
3000
(kN
)
2000Axia
l loa
d (
1000
0 10 20 30 40 500
Axial displacement (mm)
Comparison of tests on connections with plate and C channel stiffeners

5000
12mm stiffenerplates
Waler
4000
3000
(kN
)
C channel
2000Axia
l loa
d (
Waler
stiffener
1000
C channel stiffener has similar capacityto double plate stiffener but becomesbrittle after an initial ductile response
0 10 20 30 40 500
Unforced sway
Comparison of tests on connections with plate and C channel stiffeners
Axial displacement (mm)

5000Test result
4000
3000
ad (k
N)
C channelstiffener
2000Axia
l loa Waler
1000
0 10 20 30 40 500
Adjusted axial displacement (mm)
Calibration of FE model of strutCalibration of FE model of strut--waler connectionwaler connection

5000Test resultFE prediction
4000
FE prediction
3000
ad (k
N)
C channelstiffener
2000Axia
l loa Waler
1000
0 10 20 30 40 500
Adjusted axial displacement (mm)
Calibration of FE model of strutCalibration of FE model of strut--waler connectionwaler connection

5000Test resultFE prediction
Ductile plateau 10-15mm
4000
FE prediction
3000
ad (k
N)
C channelstiffener
2000Axia
l loa WalerYield
1000
Ductile plateau allows failure to develop at both ends
0 10 20 30 40 500
Adjusted axial displacement (mm)
Calibration of FE model of strutCalibration of FE model of strut--waler connectionwaler connection

50008m strut
4000
3000
oad
(kN
)
2000Axia
l l
Waler
C channelstiffener
1000
0 10 20 30 40 50Axial displacement (mm)
0
Effect of strut length (bending restraint) on brittleness of connection
p ( )

50008m strut18m strut
4000
3000
al lo
ad (k
N)
2000Axia
Waler
C channelstiffener
Reduced restraint increases brittlenessd d d til l t
1000and reduces ductile plateau8m strut – effective kingpost
18m strut – ineffective kingpost
0 10 20 30 40 50Axial displacement (mm)
0
Effect of strut length (bending restraint) on brittleness of connection

Test on C channel stiffened connection by Nishimatsu

Test on C channel stiffened connection by Nishimatsu

5000axial load only
4000
3000
oad
(kN
)
2000Axia
l l
Waler
C channelstiffener
1000
0 10 20 30 40 50Axial displacement (mm)
0
Effect of relative vertical displacement
p ( )

5000axial load onlyaxial load+RVD
4000
3000
oad
(kN
)
2000Axia
l l
Waler
C channelstiffener
1000RVD reduces ductile plateau, increases brittleness, makes
stable situation unstable
0 10 20 30 40 50Axial displacement (mm)
0
Forced sway
Effect of relative vertical displacement
p ( )

P
Force, P D til
P
Force, P Ductile
strain

Effect of brittleness of strut to waler connection
2500
Ductile2000
Run 4apf2100dropRun 4apf2100drop4Run 4apf2100drop3
Ductile
1000
1500
p(
)
p pRun 4apf2100drop2Run 4apf2100
e (k
N/m
)
500
rop
forc
e
00.0 0.2 0.4 0.6 0.8 1.0 1.2 1.4 1.6 1.8 2.0
P
Total axial strain (%)Total axial strain (%)

Effect of brittleness of strut to waler connection
2500R 4 f2100
2000
500Run 4apf2100Run 4apf2100drop2Run 4apf2100drop3Run 4apf2100drop4Run 4apf2100drop
Ductile – no collapse
1500
e (k
N/m
)
500
1000
rop
forc
e
0-15 -10 -5 0 5 10 15 20 25
6 hours 9 days 21 daysP
Time since reaching excavation level of 72.3m RL (days)

P
Force, P D til
P
Force, PNo collapse
Ductile
hours to collapse Several days to collapse
strain
hours to collapse y

Th l ti ti l di l t b t th• There was relative vertical displacement between the diaphragm wall, which settled when the sacrificial JGP was removed, and the kingpost, which rose, i.e. gprelative vertical displacement between the ends and centre of the strut (RVD)
• The strut-waler connection was ductile-brittle. The ductile plateau explains why both ends could failp p y
• The brittleness of the connection determines the time taken for the collapse to develop
Trigger required to initiate collapseTrigger required to initiate collapse

• RVD reduces the length of the ductile plateau and• RVD reduces the length of the ductile plateau and increases the brittleness
RVD k t bl it ti t bl• RVD can make a stable situation unstable
• RVD can shorten the time to collapse
• Why downward failure at both ends?Why downward failure at both ends?
• Why collapse after crossing the buried valley?
Trigger required to initiate collapseTrigger required to initiate collapse

• Free• Fixed• Forced sway
Downward failure at both endsDownward failure at both ends


Trigger required to initiate collapseTrigger required to initiate collapseTrigger required to initiate collapseTrigger required to initiate collapse
Post-collapse positions of the Dwall panels



GAS WN1BN1W 66KVN ICN1AS MAIN ABH-30 AC
WN10
WN20N1WI-65
BN1Ea BN1E66KVN
DN1E66kV Cable
MC3007M3010
AC-3
ABH-83
WN20
WN245CL-1A
CL 3GKP181
KP182KP183
ABH-31ABH 84
WS166KVS
SPTSaBS1WI-104
CL-2
CL-3G
BS1Ea
BS1Eb
ABH-29
ABH-82
ABH-84
DS1E
CS1
WS20WS10
SPTSa
DS1W
AS1
LL
ABH 29 CS1WS26
DS1W
Post-collapse geometry superimposed on buried valley

31650
CL-2
31640
66KVSBS1Ea
SPTSa19.6
13.5
7.5
9.27
TUNNELSOUTH WALL
31640
THIN
G (m
)
WS10
WS14WS15WS16
WS8WS9
WS1
1W
S11A
WS1
1BS1
1C
WS1
2W
S12A
WS1
2B12
C
WS1
3W
S13A
WS1
3B3C
11
14.7
12 1 915.
2.5
16 2613.
2.5
31630
NOR
T
CS1
WS17 WS
WS1
WS1 112
WS11EWS12E
WS11DWS12D
Post collapse SI boreholesMagnetic logging boreholesUnsuccessful magnetic logging boreholes2005 boreholes
WS11F
WS13F
WS13E
31670 31680 31690 31700
EASTING (m)
31620
Coincidence between inability to advance boreholes and missing Dwall panels
EASTING (m)

WS11E,11F,
12E,13FWS11-13A-D
Obstruction created by missing Dwall panels

2 3
M3061
Gap1
M306M212
1
M306Gap M306M212
1. Panels M306 and M212, each side of the gap, and panel 213 fail by toe kick-in and rotate backrotate back.
2. Soil flows through resulting gap between M306 and M307, rotating panel 307.
3 S il fl th h lti b t3. Soil flows through resulting gap between M307 and M308, rotating panel 308, etc.
Sequence of south wall panel movements

3044
5 305
rag
rag
drag
303
3
4dr
agdr
ag
drdr d
301
302
2
1 2a 3a 4a
306
1 2a 3a 4a
Sequence of south and north wall panel movements

Fill
SOUTH NORTH
Upper
Upper E
Fill
Marine Clay
Upper F2Differing restraintDiffering restraint
LowerMarine Clay
Sacrificial JGP
Differing restraintDiffering restraintimposed by bored imposed by bored
piles at northpiles at northand south wallsand south walls
Lower E
Sacrificial JGP
Permanent JGP
Lower F2
OA SW2 (N=35)
OA SW1 (N 72)OA SW1 (N=72)
OA (CZ)

• The bored piles had a major influence on the displacements of the Dwall panels during the collapse and on their post-collapse positions
• The bored piles restricted toe movements on the• The bored piles restricted toe movements on the south side and prevented failure as the buried valley was crossed
• Loads carried by the bored piles contributed to the under reading of the strain gaugesunder-reading of the strain gauges
Significance of the bored pilesSignificance of the bored piles


North wall
14 2 6 73
M305M304M303M302M301
335 336 338 339 340334333 337
H H HKP 182KP 181 KP 183
1 5 5 5 7 7
M306 M307 M308 M309 M310
1 Order in which distortion to waler noted
Excavation to 10th complete
Excavation in progress
Location of walers, splays and Dwall gaps

GAS WN1BN1W 66KVN ICN1AS MAIN ABH-30 AC
WN10
WN20N1WI-65
BN1Ea BN1E66KVN
DN1E66kV Cable
MC3007M3010
AC-3
ABH-83
WN20
WN245CL-1A
CL 3GKP181
KP182KP183
ABH-31ABH 84
WS166KVS
SPTSaBS1WI-104
CL-2
CL-3G
BS1Ea
BS1Eb
ABH-29
ABH-82
ABH-84
DS1E
CS1
WS20WS10
SPTSa
DS1W
AS1
LL
ABH 29 CS1WS26
DS1W
Repositioned bored piles at 66kV crossingRepositioned bored piles at 66kV crossing

• Upward displacement of KP 180 and 181• Upward displacement of KP 180 and 181 accentuated by toe displacement of M306 and M212, where bored piles had been re-positioned and dditi l t t ibladditional toe movement was possible
• Resulting RVD fed back into buried valley• Resulting RVD fed back into buried valley
Relative vertical displacementRelative vertical displacement

KP184KP183KP182KP181KP180
335
335337 338
336335
336 339340
Upper JGP
9th level
Excavation front
Lower JGP
Kingposts in long section

• C channel stiffened connection undergoes brittle failure
• Critical length of strut and of load in strut result in minimal lateral restraint to connection
• Restraint from rising kingpost results in downward force on connection
• RVD results in reduction in ductility of connection and• RVD results in reduction in ductility of connection and increase in brittleness
• RVD makes a stable situation with overstress blunstable
• RVD results in downward failure of connection
• RVD was the trigger for the failure
Failure mode of connection and RVDFailure mode of connection and RVD

Overall conclusions
• The use of Method A in the numerical analyses to model near normally consolidated soils is fundamentally incorrect
• Its use led to under prediction of wall displacements and• Its use led to under-prediction of wall displacements and bending moments and so to a reduction in the redundancy in the system. The JGP was strained beyond its peak and a plastic hinge formed in the wall as excavation of the sacrificial JGP was underway

Overall conclusions
• There were errors in the design of the strut-waler connection resulting in a design capacity that was 50% of the required capacity where splays were omittedcapacity where splays were omitted
• The collapse initiated some time after the excavation crossed th b i d ll h f th d d i d t tthe buried valley, where forces on the under-designed strut-waler connections would have been a maximum
• An additional perturbation or trigger was necessary to explain the timing of the collapse, the downward failure of the walers at both ends and the trends in the monitoring data

Overall conclusions
• The permanent bored piles in combination with the JGP played a significant role in preventing the collapse as the p y g p g pvalley was crossed
• The collapse was triggered when working in the vicinity of• The collapse was triggered when working in the vicinity of the 66kV cable crossing
• At this location, the permanent bored piles had been repositioned and the JGP layout had been modified, allowing the wall toe to kick-in and cause additional uplift of g pthe local kingposts

Overall conclusions
• This additional upward displacement of the kingposts relative to the wall fed back into the system, introducing forced sway failurefailure
• Downward movement of the walls has been predicted by analysis; the potential for relative upward movement of theanalysis; the potential for relative upward movement of the kingposts has been confirmed by surveys
Forced s a fail re red ced the strain o er hich the• Forced sway failure reduced the strain over which the connection remained ductile, increased the brittleness of the connection and allowed a stable situation to become unstable
• Forced sway failure can explain the timing of the collapse, the form of the observed distortions, the trends in the monitoring data and the speed at which the collapse developeddata, and the speed at which the collapse developed

Overall conclusions
• The collapse was not caused by hydraulic base heave and was not related to poor workmanshipheave and was not related to poor workmanship
• Wall rotation, which had been linked with inadequate , qpenetration of the wall into the OA, was not the cause of the collapse
• Several factors had to act in combination to cause the collapsethe collapse

Unforgiving site
• Deepest excavation in marine clay in Singapore –shortcomings in use of Method A not previously apparent because of depth dependence
• Ground conditions – buried valley in OA infilled with soft fluvial and organic clay, rapid variation in depth of marine clay along
d th ti lti i t i tiand across the excavation resulting in an asymmetric section
• Curvature of walls in plan requiring more frequent use of p q g qwalings
• Presence of 66kVA crossing• Presence of 66kVA crossing
• Need to adopt sacrificial JGP layer, removal of which caused p y ,step increase in 9th level strut load and step increase in wall settlement

Lessons learnt
• JGP is a brittle material
• The mass properties of JGP need to be more carefully evaluated
• Coring of JGP is not an adequate check
• The use of numerical modelling of soils in design should be carried out by specialists and its incompatibilities with current codes needs to be removedcurrent codes needs to be removed
• The potential for brittle failure of C channel connections t b i dmust be recognised

Lessons learnt
• Temporary and permanent works should be subject to independent checks
• The effects of relative displacement between kingposts and walls should be considered in the design of strutted gexcavations
• Forced sway failure and its consequences should be y qrecognised as a potential mechanism in design
• Monitoring did not warn of the impending collapseMonitoring did not warn of the impending collapse