FLORENCE ROCHE ELEMENTARY SCHOOL FEASIBILITY STUDY … · 2020-01-16 · FEASIBILITY STUDY...
Transcript of FLORENCE ROCHE ELEMENTARY SCHOOL FEASIBILITY STUDY … · 2020-01-16 · FEASIBILITY STUDY...
FLORENCE ROCHE ELEMENTARY SCHOOL
FEASIBILITY STUDY
Groton-Dunstable, MA
OPM Monthly Project Update Report
December 2019
ELIGIBILITY PERIOD FORMING THE PROJECT
TEAM FEASIBILITY STUDY
Florence Roche Elementary School Feasibility Study
December 2019
Page 2 of 3
I. EXECUTIVE SUMMARY
The Groton-Dunstable School District is in MSBA Module 3 – The Feasibility Study. Leftfield
Project Management have been selected as the Owner’s Project Manager and the
contract has been executed. Studio G Architects (SGA) have been selected as the
Designer. The Florence Roche Feasibility Study Website is up and running. SGA has been
working with the School Building Committee and Leftfield on the Educational Visioning and
Community Outreach. The Educational Leadership Team Kickoff Meeting occurred on
10/29/19. The project team has started to investigate various options to be studied as part
of the feasibility phase.
II. TASKS COMPLETED DURING DECEMBER 2019
Administrative, Owner, OPM and Design Activities
The following tasks were completed in the month of December 2019:
-12/2019 Leftfield continued management of the MSBA ProPay Process
-12/2019 The District, SGA & Leftfield worked on the Florence Roche Elementary
School Preliminary Design Program (PDP)
-12/08/2019 Leftfield submitted the November 2019 Monthly Report.
-12/08/2019 Leftfield uploaded the November 2019 monthly report to the project
website.
-12/10/2019 Leftfield & SGA attended the Groton-Dunstable School Building
Committee Meeting.
-12/10/2019 SGA facilitated an Educational Visioning Session with the Groton-
Dunstable School District
-12/19/2019 Leftfield issued the Meeting Minutes from the 11/12/2019 Groton-
Dunstable School Building Committee Meeting.
-12/19/2019 Leftfield uploaded the Groton-Dunstable School Building Committee
Meeting Agenda from the 12/10/2019 meeting to the project website.
III. TASKS PLANNED FOR JANUARY 2020
Administrative, Owner, OPM and Design Activities
The following tasks are planned for the month of January 2020:
-1/2020 Leftfield will continue management of the MSBA ProPay Process
-1/2020 The District, SGA & Leftfield worked on the Florence Roche Elementary
School Preliminary Design Program (PDP)
-1/06/2020 Leftfield will submit the December 2019 Monthly Report.
-1/06/2020 Leftfield will upload the December 2019 monthly report to the project
website.
Florence Roche Elementary School Feasibility Study
December 2019
Page 3 of 3
-1/14/2020 Leftfield & SGA will attend the Groton-Dunstable School Building
Committee Meeting.
-1/16/2020 Leftfield will issue the Meeting Minutes from the 1/14/2020 Groton-
Dunstable School Building Committee Meeting.
-1/16/2020 Leftfield will upload the Groton-Dunstable School Building Committee
Meeting Agenda from the 1/14/2020 meeting to the project website.
-1/21/2020 Leftfield & SGA will attend the Groton-Dunstable School Building
Committee Meeting.
-1/23/2020 Leftfield will issue the Meeting Minutes from the 1/21/2020 Groton-
Dunstable School Building Committee Meeting.
-1/23/2020 Leftfield will upload the Groton-Dunstable School Building Committee
Meeting Agenda from the 1/21/2020 meeting to the project website.
IV. MSBA OPM REPORTING SYSTEM
The MSBA OPM Report for December 2019 will be submitted on January 6, 2020.
V. PROJECT BUDGET AND CASH FLOW OVERVIEW
The Project Budget and Cash Flow Overview is attached.
VI. PROJECT SCHEDULE
The Project Schedule is attached.
VII. ATTACHMENTS
1. MSBA Monthly Report, dated 1/6/2020
2. Budget Tracking Report, dated 1/4/2020
3. Project Cashflow Report, dated 1/4/2020
4. Florence Roche Schedule, dated 1/4/2020
OPM Activities (Reporting Period) 1. -12/2019: Leftfield continued management of the MSBA ProPay Process 2. -12/2019: The District, SGA & Leftfield worked on the Florence Roche Elementary School Preliminary Design Program (PDP)3. -12/08/2019: Leftfield submitted the November 2019 Monthly Report.4. -12/08/2019: Leftfield uploaded the November 2019 monthly report to the project website.5. -12/10/2019: Leftfield & SGA attended the Groton-Dunstable School Building Committee Meeting.6. -12/10/2019: SGA facilitated an Educational Visioning Session with the Groton-Dunstable School District7. -12/19/2019: Leftfield issued the Meeting Minutes from the 11/12/2019 Groton-Dunstable School Building Committee Meeting.8. -12/19/2019: Leftfield uploaded the Groton-Dunstable School Building Committee Meeting Agenda from the 12/10/2019 meeting to the project website.
Project Budget Status On behalf of the District, Leftfield is managing the MSBA Propay Process. No budget concerns at this time.Potential Issues There are no potential issues to report at this time.
Contract Summary Payment Summary
Original Contract Amount $205,000 Total Contract Amount $205,000Contract Amendments (to Date) 0 Invoices Paid (to Date) $75,971Value of Contract Amendments (to Date) $0 Invoices Received (Reporting Period) $10,853Total Contract Amount $205,000 Contract Amount Remaining $118,176
Contract Amendments as Percentage of Original Contract Amount 0.0%
OPM Leftfield, LLC Progress Report as of Date 12/31/2019
District Name Groton-Dunstable MSBA ID 201706730010
School Name Florence Roche School Project Name
OPM Firm Name Leftfield, LLC School Building Committee Representative Dr. Laura Chesson
Project Director David Saindon Total Project Budget (ProPay) $750,000
Designer Firm Name Studio G. Architects, Inc. Encumbered (Reporting Period) $42,703
Principal Gail Sullivan Encumbered (to Date) $116,118
General Contractor Firm Name Total Project Invoices Received (to Date) $158,821
General Contractor Contact Name Project Completion Percentage 25%
Leftfield, LLC David Saindon Progress Report as of Date 12/31/2019
Contract Summary Payment Summary
Original Contract Amount $456,000 Total Contract Amount $456,000Contract Amendments (to Date) 0 Invoices Paid (to Date) $51,000Value of Contract Amendments (to Date) $0 Invoices Received (Reporting Period) $31,850Total Contract Amount $456,000 Contract Amount Remaining $373,150
Contract Amendments as Percentage of Original Contract Amount 0.0%
DESIGNER Studio G. Architects, Inc. Progress Report as of Date 12/31/2019
MBE/WBE Requirements
MBE Requirement 0%
MBE Actual 0%
WBE Requirement 0%
WBE Actual 0%
Page 1
RFIs and Submittals
RFIs Issued (Reporting Period) 0Total RFIs Issued (to Date) 0Remaining Open RFIs – Past 30 Days 0Notes
Remaining Open RFIs – Past 60 Days 0Notes
Remaining Open RFIs – Past 90 Days 0Notes
Submittals Received (Reporting Period) 0Total Submittals Received (to Date) 0Submittals Reviewed (Reporting Period) 0Total Submittals Reviewed (to Date) 0Comments (Remaining Open Submittals)
Designer Activities (Reporting Period) SGA attended the 12/10/2019 Building Committee Meeting. SGA worked on the PDP. SGA facilitated the Educational Visioning Session on 12/10/19.
30 Day Look Ahead SGA will continue to work on the PDP. SGA will attend the Building Committee meetings on 1/14/2020 and 1/28/2020.
Commissioning Consultant N/ACommissioning Consultant Status Not selected yet.
Phase Feasibility Study Phase Scheduled Completion Date 2/4/2020
Schedule Assessment
Notice to Proceed Date MBE RequirementPhysical Progress MBE ActualSubstantial Completion Date (Original) WBE Requirement Substantial Completion Date (Revised) WBE Actual Construction Progress (Reporting Period)
30 Day Look Ahead
Overall Schedule Assessment
Problems Identified (Schedule or Construction)
Quality Control
Safety Compliance
Number of Claims (to Date)
Value of Claims (to Date)
Comments
Recorded Manpower (Reporting Period)
Commissioning Consultant
Commissioning Consultant Status
Pending Change Orders
Change Order Status
Contract Summary Payment Summary
Original Contract Amount Total Contract Amount
Change Orders (to Date) Invoices Paid (to Date)
Value of Change Orders (to Date) Invoices Received (Reporting Period)
Total Contract Amount Contract Amount Remaining
Contract Type
Change Orders as Percentage of Original Contract Amount 0.0%
GENERAL CONTRACTOR Progress Report as of Date 12/31/2019
Page 2
The undersigned hereby certifies that, to the best of his/her knowledge, the information contained in this monthly report and attached hereto are true and accurate.
Project Director/Project Manager
______________________________________ Print Name
______________________________________ Signature
______________________________________ Date
Certification
Page 3
MSBA ID: 201706730010Florence Roche Elementary School Feasibility Study Current Budget
Project Director / Manager: David Saindon / Brian Dakin
Period Ending 12/31/2019
MSBA Reimbursement Package 8
Includes CM Requisition / CO # N/A
Budget Committed Remaining % Complete CTC Anticipated Variance
Changes Costs Expended Unspent Budget (against committ'd) (beyond committed) C @ C (Under)/Over
[A] [B] [C] [D] [E] [F]=[D]-[E] [G]=[C]-[D] [H]=[E]/[J] [I] [J]=[D]+[I] [K]=[C]-[J]
0001 0000 Owner's Project Manager $190,000 $15,000 $205,000 $205,000 $75,971 $129,029 $0 $0 $205,000 $0
0001 0000 Feasibility Study (Leftfield, LLC) $190,000 $15,000 $205,000 $205,000 $75,971 $129,029 $0 37% $0 $205,000 $0
0002 0000 Designer $500,000 ($44,000) $456,000 $456,000 $82,500 $373,500 $0 $0 $456,000 $0
0002 0000 Feasibility Study $500,000 ($44,000) $456,000 $456,000 $82,500 $373,500 $0 18% $0 $456,000 $0
0003 0000 Environmental & Site Feasibility Study $15,000 $44,000 $59,000 $59,000 $350 $58,650 $0 $0 $59,000 $0
0003 0000 Subconsultants $15,000 $43,500 $58,500 $58,500 $0 $58,500 $0 0% $0 $58,500 $00003 0000 Scan Existing Plans $0 $500 $500 $500 $350 $150 $0 70% $0 $500 $0
0004 0000 OTHER $45,000 ($15,000) $30,000 $0 $0 $0 $30,000 $30,000 $30,000 $0
0004 0000 Owner's Contingency/Other $45,000 ($15,000) $30,000 $0 $0 $0 $30,000 $30,000 $30,000 $0
FEASIBILITY STUDY AGREEMENT TOTALS $750,000 $0 $750,000 $720,000 $158,821 $561,179 $30,000 $30,000 $750,000 $0
Florence Roche Elementary School Feasibility Study - BUDGET TRACKING
FSA BudgetRev. FSA Budget
1/4/2020 C:\Users\eilee\Dropbox\Groton_Dunstable Elementary\3 - Budget\3a - Project Budgets\Florence Roche Budget Tracking_01_03_2020 Page 1 of 1
Groton-Dunstable - Florence Roche Elementary School Feasibility Study
1/4/2020
Projected Cashflow
Date Reimb. No.Forecasted
Value
Submitted
ValueBalance
750,000$
Jul-19 1 -$ 10,853$ 739,147$
Aug-19 2 -$ 10,853$ 728,294$
Sep-19 3 -$ 10,853$ 717,441$
Oct-19 4 -$ 10,853$ 706,588$
Nov-19 5 -$ 10,853$ 695,735$
Dec-19 6 -$ 10,853$ 684,882$
Jan-20 7 50,853$ $ - 684,882$
Feb-20 8 50,853$ $ - 684,882$
Mar-20 9 50,853$ $ - 684,882$
Apr-20 10 50,853$ $ - 684,882$
May-20 11 50,853$ $ - 684,882$
Jun-20 12 50,853$ $ - 684,882$
Jul-20 13 50,853$ $ - 684,882$
Aug-20 14 50,853$ $ - 684,882$
Sep-20 15 50,853$ $ - 684,882$
Oct-20 16 50,853$ $ - 684,882$
Nov-20 17 50,853$ $ - 684,882$
Dec-20 18 50,853$ $ - 684,882$
Jan-21 19 45,005$ $ - 684,882$
Feb-21 20 7,929$ $ - 684,882$
Mar-21 21 7,929$ $ - 684,882$
Apr-21 22 7,929$ $ - 684,882$
May-21 23 2,929$ $ - 684,882$
Jun-21 24 2,925$ $ - 684,882$
684,882$ 65,118$ 750,000$
Remaining To Be
Submitted
Submitted To
Date Value
Estimated Cost
@ Completion
Starting balance >>
C:\Users\eilee\Dropbox\Groton_Dunstable Elementary\3 - Budget\3a - Project Budgets\Florence Roche Budget Tracking_01_03_2020
ID %
Complete
Task Name Duration Start Finish
1 100% Procure OPM (MOD 2) 67 days Tue 2/26/19 Wed 5/29/19
8 100% Procure Architect (MOD 2) 133 days Tue 5/14/19 Thu 11/14/19
30 100% Develop schedule/work plan 10 days Thu 10/17/19Wed 10/30/19
31 100% GDRSD BC approves work plan 5 days Thu 10/31/19 Wed 11/6/19
32 100% MSBA/District kick off meeting - November 22nd 1 day Fri 11/22/19 Fri 11/22/19
33 49% FEASIBILITY STUDY (MOD 3) 177 daysWed 10/23/19 Wed 6/24/20
34 63% Educational Programming 50 days Tue 10/29/19 Fri 1/3/20
35 100% Ed. Visioning kick off meeting 1 day Tue 10/29/19 Tue 10/29/19
36 100% Community Engagement / Listening Meeting (Visioning
Workshop 1)
1 day Sat 11/16/19 Sat 11/16/19
37 100% Educational Working Group (EWG) Meeting 1 1 day Tue 11/26/19 Tue 11/26/19
38 100% Educational Working Group (EWG) Meeting 2 1 day Tue 12/10/19 Tue 12/10/19
39 100% EDUCATIONAL PLAN; Ed plan statement of teaching
philosophy, methods and goals. Page 6.
15 days Tue 12/10/19 Mon
12/30/19
40 100% Initial space summary ("ISS") - 645 students 30 days Tue 10/29/19 Fri 12/6/19
41 100% ISS explanation for variances between Ed program and
MSBA guild lines. Page 7.
2 days Mon 12/9/19 Tue 12/10/19
42 0% BC recommends ISS and Educational Program for School
Committee approval
10 days Mon 12/9/19 Fri 12/20/19
43 0% School Committee approves ISS and Educational Program 10 daysMon 12/23/19 Fri 1/3/20
44 0% Security Program; narrative 10 days Tue 12/10/19Mon 12/23/19
45 74% Introduction Deliverables - PDP 32 days Mon 11/4/19Mon 12/16/19
46 50% Existing conditions summary 30 days Mon 11/4/19 Thu 12/12/19
47 90% Capital budget statement (narrative) 30 days Mon 11/4/19 Thu 12/12/19
48 90% Project directory 10 days Mon 11/4/19 Fri 11/15/19
49 85% Updated project schedule 5 days Tue 12/10/19Mon 12/16/19
50 86% Evaluation of existing conditions 102 daysWed 10/23/19 Wed 3/11/20
51 100% Legal title/development restrictions/determine historic
concerns (local + MHC)
30 days Wed
10/23/19
Mon 12/2/19
52 100% Code review/building systems analysis 45 daysWed 10/23/19Mon 12/23/19
53 100% Determine need for geotechnical + geoenvironmental
explorations; TBD
45 days Wed
10/23/19
Mon
12/23/19
54 100% Hazardous material survey/analysis 30 daysWed 10/23/19 Mon 12/2/19
55 100% Phase 1 - ESA (project sites tbd) 30 daysWed 10/23/19 Mon 12/2/19
56 100% Preliminary Evaluation of Alternatives (include analysis of
district assignment practices and available space; tuition
agreements with adjacent school districts;
rental/acquisition of existing buildings that could be utilized
for school operations. Pg 9.
30 days Wed
10/23/19
Mon 12/2/19
57 100% Provide data utilized to determine PDP "short list" of
options. Page 10.
30 days Wed
10/23/19
Mon 12/2/19
58 80% Designer presents "test fits" for options 60 daysWed 10/23/19 Mon 1/13/20
59 85% Comparative cost analysis on all options 60 daysWed 10/23/19 Mon 1/13/20
60 100% BC considers/recommends Preliminary Design Program
options (short list)
30 days Tue 12/3/19 Mon 1/13/20
61 0% School Committee approved Preliminary Design Program
options (short list)
5 days Tue 1/14/20 Mon 1/20/20
62 0% Obtain approvals from the School Building Committee and
School Committee to submit the PDP to the MSBA
5 days Tue 1/21/20 Mon 1/27/20
63 80% Compile local actions and approval certification 5 days Tue 1/28/20 Mon 2/3/20
64 0% ** Submit PDP to the MSBA ** 1 day Tue 2/4/20 Tue 2/4/20
65 0% MSBA PDP review 15 days Wed 2/5/20 Tue 2/25/20
66 0% Receive MSBA PDP comments 1 day Wed 2/26/20 Wed 2/26/20
67 0% District returns responses to MSBD PDP comments 10 days Thu 2/27/20 Wed 3/11/20
68 0% Preferred Schematic Report (PSR) Development of short list
options
117
days
Tue 1/14/20 Wed 6/24/20
69 0% Updated summary on activities to date 10 days Tue 4/7/20 Mon 4/20/20
70 0% Updated project schedule 5 days Tue 4/7/20 Thu 5/7/20
71 0% Summary of existing conditions and alternatives 10 days Tue 4/7/20 Mon 4/20/20
72 0% Summary of Districts preferred solution 10 days Tue 4/7/20 Mon 4/20/20
73 0% Provide copy of MSBA prelim. PDP review and
corresponding District response.
1 day Thu 3/12/20 Thu 3/12/20
74 0% Evaluation of Alternatives (short list) 72 days Tue 1/14/20 Wed 4/22/20
75 0% Site analysis 20 days Tue 1/14/20 Mon 2/10/20
76 0% Evaluation of potential impacts based on each option 40 days Tue 2/11/20 Mon 4/6/20
77 0% Conceptual site and building plans 20 days Tue 1/14/20 Mon 2/10/20
78 0% Structural systems outline 20 days Tue 2/11/20 Mon 3/9/20
79 0% Utility analysis 20 days Tue 2/11/20 Mon 3/9/20
80 0% Narrative on major building systems 20 days Tue 2/11/20 Mon 3/9/20
81 0% Permitting requirements 20 days Tue 2/11/20 Mon 3/9/20
82 0% Proposed project design and construction schedule
including phasing logic
20 days Tue 2/11/20 Mon 3/9/20
83 0% Construction cost estimate (uniformat II-level 2) on short
list of options
15 days Tue 2/11/20 Mon 3/2/20
84 0% Summary of preliminary design pricing (MSBA format) 2 days Tue 4/7/20 Wed 4/8/20
85 0% BC selects and recommends preferred option to School
Committee
1 day Tue 4/21/20 Tue 4/21/20
86 0% School Committee approves preferred option 1 day Wed 4/22/20 Wed 4/22/20
87 0% Preferred Solution 97 days Tue 2/11/20 Wed 6/24/20
88 0% Updated educational program - address MSBA PDP comments5 days Thu 4/23/20 Wed 4/29/20
89 0% Summary of key components of the Districts Ed. Program 5 days Tue 3/24/20 Mon 3/30/20
90 0% Updated space summary 5 days Tue 3/24/20 Mon 3/30/20
91 0% Updated space summary - describe variations from
initial, MSBA review of PDP.
5 days Tue 3/31/20 Mon 4/6/20
92 0% Sustainability acknowledgment letter 1 day Tue 3/24/20 Tue 3/24/20
93 0% Building Plans 30 days Tue 2/11/20 Mon 3/23/20
94 0% Site Plans 25 days Tue 2/11/20 Mon 3/16/20
95 0% Estimate preferred solution construction cost 15 days Tue 3/24/20 Mon 4/13/20
96 0% Estimated total project cost 5 days Tue 4/14/20 Mon 4/20/20
97 0% List of other municipal projects planned or in progress 1 day Tue 4/14/20 Tue 4/14/20
98 0% Town not-to-exceed total project budget 1 day Tue 4/14/20 Tue 4/14/20
99 0% Description of local process for authorization and funding 5 days Tue 4/14/20 Mon 4/20/20
Procure OPM (MOD 2)
Procure Architect (MOD 2)
Develop schedule/work plan
GDRSD BC approves work plan
MSBA/District kick off meeting - November 22nd
FEASIBILITY STUDY (MOD 3)
Educational Programming
Ed. Visioning kick off meeting Ed. Visioning kick off meeting
Community Engagement / Listening Meeting (Visioning Workshop 1)
Educational Working Group (EWG) Meeting 1
Designer/District
EDUCATIONAL PLAN; Ed plan statement of teaching philosophy, methods and goals. Page 6.
Initial space summary ("ISS") - 645 students
ISS explanation for variances between Ed program and MSBA guild lines. Page 7.
BC recommends ISS and Educational Program for School Committee approval
School Committee approves ISS and Educational Program
District
Introduction Deliverables - PDP
Existing conditions summary
Capital budget statement (narrative)
Project directory
Updated project schedule
Evaluation of existing conditions
Legal title/development restrictions/determine historic concerns (local + MHC)
Code review/building systems analysis
Determine need for geotechnical + geoenvironmental explorations; TBD
Hazardous material survey/analysis
Phase 1 - ESA (project sites tbd)
Preliminary Evaluation of Alternatives (include analysis of district assignment practices and available space; tuition agreements with adjacent school districts; rental/acquisition of existing buildings that could be utilized for school operations. Pg 9.Preliminary Evaluation of Alternatives (include analysis of district assignment practices and available space; tuition agreements with adjacent school districts; rental/acquisition of existing buildings that could be utilized for school operations. Pg 9.
Provide data utilized to determine PDP "short list" of options. Page 10.
Designer presents "test fits" for options
Comparative cost analysis on all options
BC considers/recommends Preliminary Design Program options (short list)
School Committee approved Preliminary Design Program options (short list)
Obtain approvals from the School Building Committee and School Committee to submit the PDP to the MSBA
Compile local actions and approval certification
** Submit PDP to the MSBA **
MSBA PDP review
Receive MSBA PDP comments
District returns responses to MSBD PDP comments
Preferred Schematic Report (PSR) Development of short list options
Updated summary on activities to date
Updated project schedule
Summary of existing conditions and alternatives
Summary of Districts preferred solution
Provide copy of MSBA prelim. PDP review and corresponding District response.
Evaluation of Alternatives (short list)
Site analysis
Evaluation of potential impacts based on each option
Conceptual site and building plans
Structural systems outline
Utility analysis
Narrative on major building systems
Permitting requirements
Proposed project design and construction schedule including phasing logic
Construction cost estimate (uniformat II-level 2) on short list of options
Summary of preliminary design pricing (MSBA format)
BC selects and recommends preferred option to School Committee
School Committee approves preferred option
Preferred Solution
Updated educational program - address MSBA PDP comments
Summary of key components of the Districts Ed. Program
Updated space summary
Updated space summary - describe variations from initial, MSBA review of PDP.
Sustainability acknowledgment letter
Building Plans
Site Plans
Estimate preferred solution construction cost
Estimated total project cost
List of other municipal projects planned or in progress
Town not-to-exceed total project budget
Description of local process for authorization and funding
7/1 8/12 9/23 11/4 12/16 1/27 3/10 4/21 6/2 7/14 8/25 10/6 11/17 12/29 2/9 3/22 5/3 6/14 7/26 9/6 10/18 11/29 1/10 2/21 4/4 5/16 6/27 8/8 9/19 10/31 12/12 1/23 3/6 4/17 5/29 7/10 8/21 10/2 11/13 12/25 2/5 3/19 4/30 6/11 7/23 9/3 10/15 11/26
July 1 October 1 January 1 April 1 July 1 October 1 January 1 April 1 July 1 October 1 January 1 April 1 July 1 October 1 January 1 April 1 July 1 October 1 January 1 April 1 July 1 October 1
Florence Roche Elementary School Feasibility Study
FEASIBILITY-SCHEMATIC SCHEDULE
Sat 1/4/20
Page 1 of 1