Appendix A Feasibility Level Design, 30,000 TPD Tailings ... · PDF fileAppendix A.3.1...

18
Appendix A Feasibility Level Design, 30,000 TPD Tailings Storage Facility And Tailings Distribution and Water Reclaim Systems Copper Flat Project Sierra County, New Mexico Golder Associates Inc., Revised, June 2016

Transcript of Appendix A Feasibility Level Design, 30,000 TPD Tailings ... · PDF fileAppendix A.3.1...

Page 1: Appendix A Feasibility Level Design, 30,000 TPD Tailings ... · PDF fileAppendix A.3.1 Gradation Moisture/Density Test Reports ... Appendix F.2 Dam and TSF Underdrain Collection Pond

Appendix A

Feasibility Level Design, 30,000 TPD Tailings Storage Facility

And

Tailings Distribution and Water Reclaim Systems

Copper Flat Project

Sierra County, New Mexico

Golder Associates Inc.,

Revised, June 2016

Page 2: Appendix A Feasibility Level Design, 30,000 TPD Tailings ... · PDF fileAppendix A.3.1 Gradation Moisture/Density Test Reports ... Appendix F.2 Dam and TSF Underdrain Collection Pond

Revised June 2016 iv 1531453

p:\abq projects\2015 projects\1531453 themac dp permit support\work product\fs report 2015\final\1531453_themac_30000 tpd fs_rpt_20160527rev.docx

Drawing 21 Cyclone Plant Area General Arrangement Plan Drawing 22 Surge Pond Plan Cross-Section and Details Drawing 23 General Process Flow Diagram Drawing 24 Tailing Delivery and Distribution Piping Plan Drawing 25 Tailing Distribution Plan and Profile (1 of 2) Drawing 26 Tailing Distribution Plan and Profile (2 of 2) Drawing 27 Water Reclaim System Piping Plan Drawing 28 Water Reclaim System Details Drawing 29 Secondary Containment Details and Sections

List of Appendices

Appendix A Site Exploration Appendix A.1 Test Pit Logs Appendix A.2 Drill Hole Logs Appendix A.3 Geotechnical Test Results

Appendix A.3.1 Gradation Moisture/Density Test Reports Appendix A.3.2 Triaxial Test Reports Appendix A.3.3 Permeability Test Reports Appendix A.3.4 Consolidation Test Reports

Appendix B Tailings Test Results Appendix B.1 Cyclone Test Results, Full Scale Cyclone Performance Simulation Appendix B.2 Tailings Gradations Appendix B.3 Cyclone Underflow Test Results Appendix B.4 Cyclone Overflow and Whole Tailings Test Results

Appendix B.4.1 Cyclone Overflow Test Reports Appendix B.4.2 Whole Tailings Test Reports

Appendix C FSconsol Model Output Appendix D Underdrain Design Calculations

Appendix D.1 Drain Pipe Spacing Calculations Appendix D.2 Drain Pipe Deflection Calculations

Appendix E TSF Underdrain Collection Pond Inflow Estimation Appendix F Hydrologic Calculations

Appendix F.1 Impoundment Diversion Ditch Calculations Appendix F.2 Dam and TSF Underdrain Collection Pond Area Hydrologic Calculations

Appendix G Water Balance Calculations Appendix H Stability Analysis Supporting Data and Computer Output

Appendix H.1 Maximum Embankment Section Appendix H.2 Stability Section B-B’ Appendix H.3 Stability Section D-D’

Appendix I Foundation Settlement Potential Evaluation Appendix I.1 Settlement Potential, Copper Flat Tailings Embankment Foundation Appendix I.2 Settlement & Geomembrane Strain Analysis

Appendix J Drawings

Page 3: Appendix A Feasibility Level Design, 30,000 TPD Tailings ... · PDF fileAppendix A.3.1 Gradation Moisture/Density Test Reports ... Appendix F.2 Dam and TSF Underdrain Collection Pond

Revised June 2016 33 1531453

p:\abq projects\2015 projects\1531453 themac dp permit support\work product\fs report 2015\final\1531453_themac_30000 tpd fs_rpt_20160527rev.docx

7.0 TAILINGS DELIVERY AND DISTRIBUTION SYSTEM DESIGN

7.1 General System Description

The tailings delivery and distribution system design consists of pipeline system that delivers whole tailings

from the processing plant to the tailings storage facility. Whole tailings will be separated into fine material

and sand material in the cyclone plant. The sand fraction will be transported to the TSF and used for dam

construction while fine material will be deposited into the TSF. The tailings surge system is designed for

tailings management in case of unanticipated shutdown of any of the tailings stations or surges or overflows

from station sumps. Return or reclaim water will be collected from the TSF surface pond and TSF

underdrain water collection pond and transported back to the process plant. A general process flow diagram

for the tailing delivery and distribution system is provided on Drawing 23.

Process equipment for the tailings delivery and distribution system will be located in four main stations as

listed below:

Cyclone Station: including the cyclone cluster, slurry pumps, slurry transfer sumps, gland seal water system, and electrical equipment;

Surge Discharge System: including the surge pond evacuation pumps and lined secondary containment ditches;

TSF Return Water Pond Barge Station: including a floating barge and barge mounted vertical turbine pumps and electrical equipment; and

TSF Underdrain Collection Pond Pump Station: including vertical turbine pumps in a permanent structure and electrical equipment.

Tailings distribution will include whole tailings transport from the process area to the cyclone station and

sand and fine tailings transport to the TSF. Return water will include tailing drainage water and TSF return

water transported to the process plant. The major pipelines are listed below, and their interactions are

shown in the overall system process flow diagram on Drawing 23.

Cyclone Feed Line

Cyclone Overflow Line

Cyclone Underflow Line

Cyclone Whole Tailings Bypass Line

TSF Return Water Line

TSF Underdrain Collection Return Water Line

Main Surge Discharge Line

The major pipelines will be installed within secondary containment ditches lined with a minimum 60-mil

HDPE geomembrane liner placed over six inches of liner bedding fill. The secondary containment ditches

and associated pipelines will be constructed in accordance with the requirements listed in 20.6.7.23

Page 4: Appendix A Feasibility Level Design, 30,000 TPD Tailings ... · PDF fileAppendix A.3.1 Gradation Moisture/Density Test Reports ... Appendix F.2 Dam and TSF Underdrain Collection Pond

Revised June 2016 36 1531453

p:\abq projects\2015 projects\1531453 themac dp permit support\work product\fs report 2015\final\1531453_themac_30000 tpd fs_rpt_20160527rev.docx

and consolidation can occur under managed deposition is primarily a function of rate of tailings rise. It is

also influenced by tailings properties, climatic conditions, surface water management, and operator effort.

7.4 Management of Upset Flows

Potential upset flows from the process area, cyclone plant, and TSF will be controlled through a series of

secondary containment ditches, the surge pond, and the TSF underdrain collection pond (see Section 6.5).

The secondary containment ditches and associated pipelines will be constructed in accordance with the

requirements listed in 20.6.7.23 NMAC. The secondary containment ditches will run from the process area

to the TSF (the main ditch), from the main ditch to the cyclone area, and from the cyclone area to the surge

pond. The secondary containment ditches are designed to contain and transport flows via gravity that are

related to potential upset conditions and direct precipitation onto the ditches associated with the 25-year

24-hour storm event (2.88 inches). Maximum upset flow conditions would be associated with overtopping

of the process water reservoir (as estimated by M3, the design contractor for the process water reservoir).

This maximum upset flow was assumed to be 18,000 gpm over a 30-minute period, at which point the

process area pumps would be shut down. The secondary containment ditches are designed for these

maximum upset flows, direct precipitation, and an additional 2 feet of freeboard. The main ditch is designed

to flow to the TSF by gravity for the first six years. After year six, gravity flow to the TSF is no longer possible

because of the increased height of the TSF and upset flows will then discharge to the surge pond via gravity

in a lined ditch through year 11.1. The alignment of the secondary containment ditches is shown on

Drawings 2, 3, 10, 11, 12, 21, and 24 through 26. Details of the secondary containment ditches are provided

in Drawing 29.

Surge pond cross sections and details are shown on Drawing 22. The surge pond liner system will consist

of a liner bedding fill layer overlain with a minimum 60-mil HDPE geomembrane liner. The surge pond is

located at an elevation of 5,340 feet and is sized for a surge retention time of half an hour with and additional

reserve capacity of over one million gallons. The pond is sized for the retention of approximately 1,610,000

gallons of slurry with an additional 2 feet of freeboard. The use of the surge pond will be intermittent and

temporary and the pond will be empty under normal operating conditions. The pond will be equipped with

dedicated hard-wired pumps that will automatically evacuate its contents. Emergency power for the pumps

will be provided by the emergency diesel power generation system located on-site in the event of a power

outage. The process facility control room will be equipped with emergency alarms that notify the operator

of an upset condition allowing the operator to make necessary adjustments in the process, as needed. The

pumps at the surge pond will be automatically activated upon the pond reaching a predetermined level.

Water and solids collected from the surge pond will be discharged through a 12-inch HDPE DR17 pipeline

to the top of the TSF. The solids handling pump is designed to evacuate the surge pond within 12 hours.

Page 5: Appendix A Feasibility Level Design, 30,000 TPD Tailings ... · PDF fileAppendix A.3.1 Gradation Moisture/Density Test Reports ... Appendix F.2 Dam and TSF Underdrain Collection Pond

Revised June 2016 47 1531453

p:\abq projects\2015 projects\1531453 themac dp permit support\work product\fs report 2015\final\1531453_themac_30000 tpd fs_rpt_20160527rev.docx

11.0 TAILINGS DAM FOUNDATION SETTLEMENT POTENTIAL

11.1 Analysis Approach

The TSF will consist of an earthen starter dam constructed to a height of approximately 50 feet with the

remainder of the dam constructed with sand recovered from the cyclone plant. A geotechnical investigation

was performed in the embankment footprint, which included standard penetration testing and sample

collection from the surface to a depth of 50 feet. Drilling indicated that in general, the tailings embankment

foundation consists primarily of alluvial deposits that include silt, sand and gravel, which are underlain by

clay.

Representative samples of the foundation strata were analyzed in Golder’s geotechnical laboratory for

index properties, gradation, and Atterberg limits. Selected samples were remolded in the laboratory, and

the remolded samples were subjected to one-dimensional consolidation testing.

Settlement calculations were developed for the post-construction embankment, which represents the worst-

case condition. Staged settlement was not analyzed because settlement of the embankment will be

adequately mitigated by continuous fill placement during ongoing embankment construction. Settlement

calculations were performed using the computer model SETTLE3D v. 2.0, a computer program developed

by Rocscience, Inc., for the analysis of settlement and consolidation under foundations and embankments.

A detailed description of the settlement potential investigation, settlement calculations and supporting

information are contained in Appendix I.1. Drill holes and the location of cross-sections used to evaluate

subsurface conditions are shown on Drawing 3. Drawings 5 and 7 present geologic cross sections B-B’ and

D-D’, respectively, which were developed to evaluate settlement perpendicular to the dam axis. The cross-

sections also include information derived from the former geotechnical study conducted on behalf of

Quintana by Sergent Hauskins and Beckwith (SHB, 1980). Drill hole logs are contained in Appendix A.2.

A differential settlement and geomembrane strain analysis was subsequently conducted by Golder and is

included in Appendix I.2. Cross sections were developed to intercept the various geologic materials

underlying the TSF site. The engineering properties of the foundation materials were derived from the 1980

Sargent, Hauskins and Beckwith (SHB) geotechnical study, the geotechnical investigation conducted as

part of the TSF design report and experience with similar foundation materials.

11.2 Settlement Potential Analysis Results

Laboratory consolidation testing was conducted on remolded specimens of the fine fraction of samples

recovered from the embankment foundation. As such, the settlement prediction does not account for the

presence of the coarse fraction in the foundation soils, and associated inter-particle contact and support of

Page 6: Appendix A Feasibility Level Design, 30,000 TPD Tailings ... · PDF fileAppendix A.3.1 Gradation Moisture/Density Test Reports ... Appendix F.2 Dam and TSF Underdrain Collection Pond

Revised June 2016 48 1531453

embankment moist unit weight of 130 pcf. Tailings testing completed after the settlement potential study

p:\abq projects\2015 projects\1531453 themac dp permit support\work product\fs report 2015\final\1531453_themac_30000 tpd fs_rpt_20160527rev.docx

foundation loads. Settlement predictions based on the laboratory consolidation tests are therefore

conservative.

Results of the settlement potential analysis are shown graphically on geologic sections B-B’ and D-D’. The

maximum calculated settlement beneath the embankment is approximately 2.1 feet in the area of the

maximum dam (and tailings beach) foundation loads. Settlement decreases at a relatively uniform rate as

the weight of post-construction loading decreases towards the outer toe of the embankment.

Settlement prediction based on the laboratory consolidation testing of the fine fraction of foundation

samples is conservative. SPT testing conducted during drilling showed the foundation strata to generally

be very dense to hard. On the basis of SPT test results, actual post-construction consolidation settlement

of less than 1 foot is anticipated.

Dam construction will be more or less continuous during the life of the facility. The effects of foundation

settlement include the potential for the loss of dry freeboard for stormwater storage. The potential loss of

freeboard can be mitigated by elevating the dam crest with managed/targeted placement of cyclone

underflow sand.

The analyses did not indicate the potential for differential settlement that could impact the integrity of the

TSF geomembrane liner. Sections B-B’ and D-D’ indicate predicted settlement varies uniformly across

areas subject to changing foundation loads.

The impoundment underdrain will pass beneath the dam in a steel pipe placed in a ditch backfilled with

concrete near section F-F’ (Drawing 9). The settlement will not adversely impact the impoundment

underdrain outlet pipe. There is adequate grade and elevation change along the outlet pipe alignment to

accommodate predicted settlement.

A basalt outcrop identified by SHB (SHB, 1980) may lie beneath or in the vicinity of the impoundment

underdrain pipe inlet near the upstream toe of the dam. The outcrop occurred in an area that was disturbed

during Quintana dam construction activities, and was not observed during the recent site exploration. If the

inlet to the underdrain pipe bears on basalt, local differential settlement could occur along the pipe

alignment, which could induce stress on the outlet pipe. If, during construction, a basalt outcrop is identified

at the location of the inlet, an alignment change may be warranted to avoid the pipe bearing on basalt.

It should be noted that the settlement potential investigation was performed for a previously completed

design study, and evaluated an embankment geometry that differs from that presented in this report. The

new embankment is higher and the depth of embankment fill overlying the foundation is greater for this

30,000 tons per day design; however, the original analyses assumed a higher, more conservative

Page 7: Appendix A Feasibility Level Design, 30,000 TPD Tailings ... · PDF fileAppendix A.3.1 Gradation Moisture/Density Test Reports ... Appendix F.2 Dam and TSF Underdrain Collection Pond

Revised June 2016 49 1531453

p:\abq projects\2015 projects\1531453 themac dp permit support\work product\fs report 2015\final\1531453_themac_30000 tpd fs_rpt_20160527rev.docx

was conducted indicates a post embankment fill placement moist unit weight of approximately 113 pcf. The

foundation loads imposed by the higher embankment fill, when corrected for the moist unit weight

determined by laboratory testing, are lower than those used in the settlement potential analysis. Therefore,

the results of the settlement investigation presented above are conservative relative to the current design.

As part of future detailed engineering studies, settlement calculations will be updated for final design

conditions; however, the conclusions are anticipated to be consistent with those presented herein.

The results of the differential settlement and geomembrane strain analysis indicates that, in general,

settlement potential across the TSF is predicted to be limited. As such, the potential for tearing of the HDPE

liner due to potential differential settlement within the entire area of the TSF is considered to be low. The

maximum settlement is estimated to be 0.72 feet, while the maximum tensile strain on the HDPE liner due

to differential settlement is estimated to be 0.02 percent. The allowable tensile strain on an 80 mil HDPE

geomembrane liner is 10 percent and the predicted tensile strain is well within acceptable conditions.

Therefore, Golder does not expect tearing of the HDPE liner due to differential settlement to be an issue.

Page 8: Appendix A Feasibility Level Design, 30,000 TPD Tailings ... · PDF fileAppendix A.3.1 Gradation Moisture/Density Test Reports ... Appendix F.2 Dam and TSF Underdrain Collection Pond

APPENDIX I.1 SETTLEMENT POTENTIAL, COPPER FLAT TAILINGS EMBANKMENT FOUNDATION

Page 9: Appendix A Feasibility Level Design, 30,000 TPD Tailings ... · PDF fileAppendix A.3.1 Gradation Moisture/Density Test Reports ... Appendix F.2 Dam and TSF Underdrain Collection Pond

APPENDIX I.2 SETTLEMENT & GEOMEMBRANE STRAIN ANALYSIS

Page 10: Appendix A Feasibility Level Design, 30,000 TPD Tailings ... · PDF fileAppendix A.3.1 Gradation Moisture/Density Test Reports ... Appendix F.2 Dam and TSF Underdrain Collection Pond

Page 1 of 7

1.0 OBJECTIVE

2.0 METHODOLOGY

2.1 Settlement Analysis

Unit WeightPoisson's

RatioEffective Modulus

(lb/ft3) (-) (lb/ft2)0 97 0.49 10,000,000

1 110 0.30 4,000,000

2 110 0.30 4,000,000

3 130 0.30 5,000,000

4 160 0.30 100,000,000

5 104 0.30 790,600

6 106 0.30 671,400

7 125 0.30 100,000,000

8 175 0.30 100,000,000

SETTLEMENT & GEOMEMBRANE STRAIN ANALYSIS

Estimate the tensile strain caused by differential settlement of the in-situ subsurface materials inferred below the proposed Copper Flat tailing facility.

The proposed geomembrane liner system may experience tensile strain because of differential settlement caused from the loading (tailings and embankment) of the subsurface soils.

Settlement was calculated using the finite element software SigmaW from the 2012 GeoStudio package. Cross sections A and B (both shown in plan view on Figure 1 and in profile view in Figure 2) showing the proposed tailing facility and tailings embankment layout/dimensions, inferred subsurface soils and boundaries were imported into the software for analyses. Geotechnical properties for each subsurface material layer were selected from previous reports (Refs. 1 and 2) and from experience with similar soils. The geotechnical properties were incorporated into the software and used for the settlement analyses. Table 1 below provides a list of the geotechnical subsurface material layers and properties.

Bedrock

Material No. Material Name

Geotechnical Properties

Table 1: Geotechnical Subsurface Material Layers and Properties

Tailings/Embankment

Well-Graded Gravel

Well-Graded Sand with Silt and Gravel

Conglomerate

Basalt

Lean Clay, Fat Clay, Silty Clay

Silt

Caliche

Made By: JLChecked by: GMReviewed by: MP

Feasibility Study Copper Flat ProjectVolume 1 - Tailings Storage Facility

Golder Differential Settlement AnalysisJune 2016

Page 11: Appendix A Feasibility Level Design, 30,000 TPD Tailings ... · PDF fileAppendix A.3.1 Gradation Moisture/Density Test Reports ... Appendix F.2 Dam and TSF Underdrain Collection Pond

Page 2 of 7

Feasibility Study Copper Flat ProjectVolume 1 - Tailings Storage Facility

Golder Differential Settlement Analysis

2.1 Tensile Strain from Differential Settlement

Where: e = Tensile strain in liner system between Points A and B

L1 = Distance between Points A and B, pre-settlement

L2 = Distance between Points A and B, post-settlement

s = Horizontal distance between Points A and B

3.0 CALCULATIONS AND RESULTS

3.1 Tensile Strain from Differential Settlement

The tensile strain of a base liner system caused by differential settlement can be estimated by the following equation:

The settlement results for Cross Section A and Cross Section B are illustrated below. Points for liner strain evaluation were selected at locations where peaks or valleys were observed in the results. The liner strain evaluations due to differential settlement of the subsurface materials are summarized in Table 2 and Table 3.

Settlement results from the SigmaW runs were used to calculate the induced strain in the geomembrane liner system along Cross Section A and B shown in Figure 1 and Figure 2.

Illustration: Liner Differential Settlement

Point A

Point BL1

L2

Pre-settlement

Post-settlement

horizontal distance = s

𝜀𝜀 =𝐿𝐿2 − 𝐿𝐿1𝐿𝐿1

𝐿𝐿 = 𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸.𝐴𝐴 − 𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸.𝐵𝐵 2 + 𝑠𝑠2

June 2016

Page 12: Appendix A Feasibility Level Design, 30,000 TPD Tailings ... · PDF fileAppendix A.3.1 Gradation Moisture/Density Test Reports ... Appendix F.2 Dam and TSF Underdrain Collection Pond

Page 3 of 7

Feasibility Study Copper Flat ProjectVolume 1 - Tailings Storage Facility

Golder Differential Settlement Analysis

Illustration: Settlement Profile - Cross Section A(refer to Figure 2 for location along horizontal distance)

A

B

C D

E

F

G H

I

J

K

L

M

N

-0.8

-0.7

-0.6

-0.5

-0.4

-0.3

-0.2

-0.1

0

0.1

0.2

0.3

0.4

0.5

0.60 1000 2000 3000 4000 5000 6000 7000 8000

Sett

lem

ent (

ft)

Horizontal Distance (ft)

Tailings Embankment Cross Section A(NOT TO SCALE)

June 2016

Page 13: Appendix A Feasibility Level Design, 30,000 TPD Tailings ... · PDF fileAppendix A.3.1 Gradation Moisture/Density Test Reports ... Appendix F.2 Dam and TSF Underdrain Collection Pond

Page 4 of 7

Feasibility Study Copper Flat ProjectVolume 1 - Tailings Storage Facility

Golder Differential Settlement Analysis

Pre-settlement,

feet

Post-settlement,

feet

A 5383.4 5383.4 0.00B 5311.7 5311.0 0.72B 5311.7 5311.0 0.72C 5275.5 5275.1 0.40D 5267.5 5267.1 0.40E 5251.8 5251.3 0.53E 5251.8 5251.3 0.53F 5230.0 5229.6 0.45F 5230.0 5229.6 0.45G 5230.2 5229.9 0.30H 5239.6 5239.3 0.29I 5197.3 5197.1 0.20I 5197.3 5197.1 0.20J 5185.2 5185.1 0.11J 5185.2 5185.1 0.11K 5180.4 5180.1 0.34K 5180.4 5180.1 0.34L 5176.7 5176.5 0.22L 5176.7 5176.5 0.22M 5173.3 5173.0 0.29M 5173.3 5173.0 0.29N 5168.5 5168.5 0.00

350.00 350.352 350.358 0.0017%

150.00 155.850 155.826 Under Compression

700.00 700.339 700.337 Under Compression

200.00 200.000 200.000 0.0001%

Tensile Strain

525.019520.00 524.920 0.0188%

580.00 581.129 581.109

Points

Elevations

Horizontal Distance (s),

feetPre-settlement Dist. (L1), feet

Post-settlement

Dist. (L2), feet

Under Compression

Table 2: Liner Integrity Analysis Results - Cross Section A

650.00 650.113 650.111 Under Compression

125.00 125.046 125.048 0.0015%

113.00 113.102 113.090 Under Compression

250.00 250.046 250.051 0.0018%

225.00 225.030 225.028 Under Compression

Settlement, feet

Maximum Tensile Strain due to Differential Settlement = 0.0188%

June 2016

Page 14: Appendix A Feasibility Level Design, 30,000 TPD Tailings ... · PDF fileAppendix A.3.1 Gradation Moisture/Density Test Reports ... Appendix F.2 Dam and TSF Underdrain Collection Pond

Page 5 of 7

Feasibility Study Copper Flat ProjectVolume 1 - Tailings Storage Facility

Golder Differential Settlement Analysis

Illustration: Settlement Profile - Cross Section B(refer to Figure 2 for location along horizontal distance)

A

B

C

D E

F

GH

I

J

-1.2

-1.1

-1

-0.9

-0.8

-0.7

-0.6

-0.5

-0.4

-0.3

-0.2

-0.1

0

0.1

0.2

0.3

0.4

0.5

0.60 1000 2000 3000 4000 5000

Sett

lem

ent (

ft)

Horizontal Distance (ft)

Tailings Embankment Cross Section B(NOT TO SCALE)

June 2016

Page 15: Appendix A Feasibility Level Design, 30,000 TPD Tailings ... · PDF fileAppendix A.3.1 Gradation Moisture/Density Test Reports ... Appendix F.2 Dam and TSF Underdrain Collection Pond

Page 6 of 7

Feasibility Study Copper Flat ProjectVolume 1 - Tailings Storage Facility

Golder Differential Settlement Analysis

Pre-settlement,

feet

Post-settlement,

feet

A 5280.2 5280.2 0.00

B 5226.4 5226.0 0.43

C 5213.7 5213.4 0.34

D 5229.7 5229.3 0.37

E 5239.3 5239.0 0.35

F 5211.6 5211.3 0.29

F 52116.0 52115.7 0.29

G 5196.2 5195.2 0.96

G 5196.2 5195.2 0.96

H 5197.3 5196.4 0.89

H 5197.3 5196.4 0.89

I 5198.6 5197.4 1.16

I 5198.6 5197.4 1.16

J 5199.3 5199.3 0.00

4.0 DISCUSSION AND CONCLUSIONS

It is understood that the liner system will consist of HDPE 80 mil geomembrane liner between a liner bedding fill layer and tailings. The minimum allowable tensile strain for geomembrane is 10% (Refs. 3). Based on the analysis performed herein and available information at the time of this calculation, the estimated tensile strain along Cross Section A and Cross Section B are less then the allowable tensile strain. The allowable strain is presented in Table 4.

Cross SectionMax. Tensile Strain from Differential Settlement Liner Component Allowable Tensile Strain

Tensile Strain less than

Allowable?

Table 4: Summary of Allowable Liner Strains

The potential strain of the geomembrane liner system was analyzed for overall differential settlement along two cross sections (Cross Section A and B) within the proposed Copper Flat tailing facility. Based on the available information, experience with similar subsurface materials and conservative assumptions, the maximum liner strain is estimated to be 0.02%, from differential settlement which is less than the allowable strain for geomembrane liners.

Yes

Yes

847.00 848.707 848.734 0.0032%

30.00 34.000 33.986 Under Compression

79.00 83.716 83.696 Under Compression

530.000 530.003 0.0005%

46922.440 0.0014%

160.00 160.004 160.004 0.0003%

195.00 195.004 195.003 Under Compression

46921.770430.00

A 0.0188%Geomembrane 10%

B 0.0032%

Points

Elevations

Horizontal Distance (s),

feetPre-settlement Dist. (L1), feet

Post-settlement

Dist. (L2), feet Tensile Strain

Table 3: Liner Integrity Analysis Results - Cross Section B

Settlement, feet

Maximum Tensile Strain due to Differential Settlement = 0.0032%

530.00

June 2016

Page 16: Appendix A Feasibility Level Design, 30,000 TPD Tailings ... · PDF fileAppendix A.3.1 Gradation Moisture/Density Test Reports ... Appendix F.2 Dam and TSF Underdrain Collection Pond

Page 7 of 7

Feasibility Study Copper Flat ProjectVolume 1 - Tailings Storage Facility

Golder Differential Settlement Analysis

5.0 REFERENCES1. -

2. -

3. -

GeoStudio File Names DescriptionFull Cross Section A.gsz Cross Section A Settlement Analysis

Full Cross Section B.gsz Cross Section B Settlement Analysis

AttachmentsFigure 1: Cross Section Location Plan

Figure 2: Geologic Cross Sections

Golder 2013, Feasibility Study Copper Flat Project, Sierra County, New Mexico, Volume 1 - Tailings Storage Facility, report dated July 2013, Golder Project No. 103-92557.011

SHB (Sergent, Hauskins and Beckwith), 1980. Tailings Dam and Disposal Area - Quintana MineralsCorporation - Copper Flats Project - Golddust, New Mexico. October 14, 1980

Robert M. Koerner (2005) Designing with Geosynthetics, Fifth Edition, Pearson/Prentice Hall.

June 2016

Page 17: Appendix A Feasibility Level Design, 30,000 TPD Tailings ... · PDF fileAppendix A.3.1 Gradation Moisture/Density Test Reports ... Appendix F.2 Dam and TSF Underdrain Collection Pond

A

2

B

2

PROPOSED ULTIMATE TAILINGS

STORAGE FACILITY FOOTPRINT

N 11974000 N 11974000

E 8

74

00

0E

8

74

00

0

N 11976000 N 11976000

N 11978000 N 11978000

N 11972000 N 11972000

N 11970000 N 11970000

E 8

76

00

0E

8

76

00

0

E 8

72

00

0E

8

72

00

0

E 8

70

00

0E

8

70

00

0

5

2

0

0

5

2

0

0

5

3

0

0

5

3

0

0

5

4

0

0

5

4

0

0

5400

5

4

0

0

5500

5

5

0

0

5

2

0

0

5300

BH-1

BH-2

BH-3

BH-4

BH-5

BH-9

BH-10

BH-11

BH-15

BH-16

BH-17

BH-21

BH-22

BH-24

BH-25

BH-28

BH-6

BH-7

BH-8

BH-12

BH-13

BH-14

BH-18

BH-19

BH-20

BH-23

BH-26

BH-27

TP-2

TP-3

TP-4

TP-5

TP-7

TP-8

TP-9

TP-11

TP-16

TP-21

TP-22

TP-23

TP-26

TP-27

TP-28

TP-29

TP-30

TP-1

TP-10

TP-12

TP-13

TP-14

TP-15

TP-17

TP-18

TP-19

TP-20

TP-24

TP-25

TP-31

TP-32

01 in

1531453

CONTROL

0001

FIGURE

1

A

2016-05-11

JHR

JS

JL

GM

COPPER FLAT

SIERRA COUNTY, NEW MEXICO

CROSS-SECTION LOCATION PLAN

TITLE

PROJECT NO. REV.

PROJECT

CLIENT

IF

T

HIS

M

EA

SU

RE

ME

NT

D

OE

S N

OT

M

AT

CH

W

HA

T IS

S

HO

WN

, T

HE

S

HE

ET

S

IZ

E H

AS

B

EE

N M

OD

IF

IE

D F

RO

M: A

NS

I B

CONSULTANT

PREPARED

DESIGNED

REVIEWED

APPROVED

YYYY-MM-DD

Path: \\tucson\cadd\C

HE

VR

ON

\Q

UE

ST

A\99_P

RO

JE

CT

S\1653370_Q

trD

am

Isnp\0002_E

AP

\02_P

RO

DU

CT

IO

N\D

WG

\ | F

ile N

am

e: 1531453_0001_F

IG

_001.dw

g

0

FEET

250 500

1'' = 500'

LEGEND

EXISTING GROUND CONTOUR (ft -MSL)

CROSS-SECTION CALLOUT

SECTION ID

DRAWING SHEET LOCATION

3600

A

2

HOLLOW STEM AUGER (HSA) BOREHOLE

TEST PIT

BH-11

TP-8

June 2016

Page 18: Appendix A Feasibility Level Design, 30,000 TPD Tailings ... · PDF fileAppendix A.3.1 Gradation Moisture/Density Test Reports ... Appendix F.2 Dam and TSF Underdrain Collection Pond

ELEV

ATIO

N (F

T)

ELEV

ATIO

N (F

T)

50505100515052005250530053505400545055005550

50505100515052005250530053505400545055005550

0 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 3000 3200 3400 3600 3800 4000 4200 4400 4600 4800 5000 5200 5400 5600 5800 6000 6200 6400 6600 6800 7000 7200 74007481

ULTIMATE IMPOUNDMENT SURFACE

EXISTING GROUNDPHASE 1

PHASE 2PHASE 3

PHASE 4

EXISTING EMBANKMENTTAILINGS

ELEV

ATIO

N (F

T)

ELEV

ATIO

N (F

T)

5050510051505200525053005350540054505500

5050510051505200525053005350540054505500

0 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 3000 3200 3400 3600 3800 4000 4200 4400 4600 4800 5000 5200 5400 5600 5800 5896

ULTIMATE IMPOUNDMENT SURFACE

EXISTING GROUNDPHASE 1PHASE 2

PHASE 3PHASE 4

EXISTING EMBANKMENT AND DIVIDER BERM

01

in

1531453CONTROL0001

FIGURE

2A

2016-05-11

JHR

JS

JL

GM

COPPER FLAT

SIERRA COUNTY, NEW MEXICO

GEOLOGIC CROSS-SECTIONS TITLE

PROJECT NO. REV.

PROJECT

CLIENT

IF T

HIS

MEA

SUR

EMEN

T D

OES

NO

T M

ATC

H W

HAT

IS S

HO

WN

, TH

E SH

EET

SIZE

HAS

BEE

N M

OD

IFIE

D F

RO

M: A

NSI

B

CONSULTANT

PREPARED

DESIGNED

REVIEWED

APPROVED

YYYY-MM-DD

Path

: \\tu

cson

\cad

d\TH

EMAC

\Cop

perF

lat\9

9_PR

OJE

CTS

\153

1453

_NM

Cop

perC

orpS

uppo

rt\00

01_S

ectio

ns\0

2_PR

OD

UC

TIO

N\D

WG

\ |

File

Nam

e: 1

5314

53_0

001_

FIG

_002

.dw

g

A2

SCALE 1'' = 500' CROSS-SECTION A

B2

SCALE 1'' = 500' CROSS-SECTION B

0

FEET

250 500

1'' = 500'

WELL-GRADED GRAVEL

BASALT

WELL-GRADED SAND WITH SILT AND GRAVEL

CONGLOMERATE

SILT

CALICHE

LEAN CLAY, FAT CLAY, SILTY CLAY

BEDROCK

LEGEND

June 2016