FLNG from front-end studies up to smooth execution Dominique... · FLNG from front-end studies up...
Transcript of FLNG from front-end studies up to smooth execution Dominique... · FLNG from front-end studies up...
-
FLNG from front-end studies up to smooth execution
Dominique GADELLE Vice President Upstream / LNG Technip FranceParis, March 11th, 2015
1
-
Table of contents
I. The (F)LNG Industry
II. Why go offshore ?
III. The challenges
Engineering
Procurement
Project management
IV. Ongoing open sea FLNG projects
V. Conclusion
2
-
I. The (F)LNG Industry
33
-
Sources: EIA, BP Energy Outlook 2030, January 2013
Natural Gas: A good combination of compromises
Worldwide use of primary energy
Gas demand will witness a surge in demand by 2030
Industry and power generation are the main gas markets
0
100
200
300
400
500
600
700
800
2010 2020 2030
Qu
ad
rillio
n o
f B
tu
World energy consumption
23%25% 27%
+40%
50
100
150
200
250
300
350
400
450
500
2010 2020 2030
Billio
ns o
f cu
bic
feet
per
day
Gas demand
+50%
Gas share in
worldwide
energy demand
4
-
Sources: BP Energy Outlook 2035, January 2014
Natural gas demand continues its steady growth
Gas demand to grow 1.9% p.a. 2012-2035
Industry and power generation remain the main gas markets although transportation sector is growing fast
5
-
Long term natural gas and LNG trade
0
500
1000
1500
2000
2500
3000
3500
70 72 74 76 78 80 82 84 86 88 90 92 94 96 98 '00 '02 '04 '06 '08 '10 '12
Bil
lio
n c
m/y
(B
CM
)
NG consumption - 3350 BCM
(1990 to 2012, 2.8%/y)
NG international trade - 1022 BCM
(1990 to 2012, +5.6%/y)
LNG trade - 313 BCM
(1990 to 2012 +6.9%/y)
Source : Cedigaz/BP
6
-
236.9 million tons of LNG traded
41% supplied from the Middle East
Qatar: 77 MTPA, 1/3 of the global market
75% of global LNG demand came from Asia
End 2013
86 liquefaction trains in operation in 17 countries
Total production capacity: 286 MTPA (utilization 83%)
LNG industry key figures end 2013
Sources: GII GNL 2013
7
-
8
-
17%
27%
5%
3%
5%
4%
8%
15%4%
13%
17%
3%
2%
5%
32%
40%
Mismatch between gas reserves and demand
1 Simplified trade movements
% of gas consumption by region from 2013 BP energy outlook 2030
% of proved gas reserves by region, including unconventional gas from CEDIGAZ 2012 edition
Major gas trade movements LNG1
Major gas trade movements pipeline1
9
-
LNG: 60% of international gas trade growth
Transportation distance
LNG
Cost
Pipeline cost: function of distance
LNG cost: concentrated at the terminals, low marginal cost per kilometer
Sources: Cedigaz
10
-
11
II. Why go offshore ?
11
-
Why FLNG ?
No immediate delivery infrastructure nor local market
Insufficient reserves for dedicated onshore LNG plant
Technical difficulties for deeper and further offshore reserves
Difficulty in landing gas onshore
Enable oil fields development
Monetize associated gas rather than re-injection or flaring
Stand-alone gas fields
opportunities
Associated gas
disposal opportunities
Increasing gas demand in Asia
Cost optimization in areas with high construction costs
Deeper and further offshore reserves
Pipeline too complicated or too long
Economics
Environment
Potential redeployment
Sustainable
development
Floating LNG offers the best CAPEX for large lean gas fields or
stranded gas fields
12
-
Upstream
Pipelines
Onshore treatment &
liquefaction
Transport
Regasification
Distribution
FLNG is a game changer for the LNG industry
The LNG
supply chain
FLNG: Upstream + offshore
treatment, liquefaction &
offloading on transport
13
-
III. The challenges
14
Engineering
Procurement
Project management
14
-
From onshore to offshore
Onshore LNG
FLNG
Volume and weight optimization is the key to move offshore. It is a challenge for Space & organization
Motion management
Weight control & center of gravity management
Safety
15
-
0.00330.165
0.495
5.0
7.8
micro mini mid large maximum construit
MTPA
Qatargas LNG
Trains
largest ever built
Hanas LNG plant QatarGas LNG trains 4 & 5
Onshore liquefaction plant capacity
16
-
0
1
2
3
4
5
6
7
8
9
1960 1965 1970 1975 1980 1985 1990 1995 2000 2005 2010 2015
Yemen
Qatar mega
Trains
MTPA
Historical trend of (F)LNG plants
Onshore LNG plant
Offshore LNG plant
Petronas FLNG1
Yamal
Prelude
Capacity range of FLNG projects under study or
execution
Comparison onshore LNG & FLNG plants capacity
17
-
Layout comparison: onshore LNG plant vs FLNG
Prelude FLNG:
production 3.6 MTPA LNG
488 x 74 = 3.61 Ha
1 Ha/MTPA GNL
Yemen LNG:
production 6.7 MTPA LNG
47 Ha
7 Ha/MTPA GNL
18
-
An FLNG is built on industrial experienceNatural gas liquefaction Subsea field development Large FPSOs
and innovation in open sea LNG transfer
19
-
Subsea design and installation is part of an FLNG project
Products
Flexible pipe
Umbilicals
Rigid pipelines
Services
Inspection,
repair & maintenance
Flexible / rigid pipelaying
Deep water installation
& construction
Architecture
2020
-
FLNG the main challenges
LNG tank sloshing over 25 years without dry docking
Offloading LNG between two vessels in the open sea
Importing large quantities of HP feed gas through a swivel
Equipment and piping loads due to motion
Maintenance
Marine environment (salt, humidity)
Marinization of gas processing facilities
Compact designs
Designing for motion
Feed gas - sulphur free; high methane content preferred
Safety - escalation, cryogenic spill management
Local content
Synergy with domestic gas schemes (except for LPG)
Logistics / accommodation
Insurance - storms, piracy
Expansion capacity
Marine/
mechanical
Process/
Safety
Non technical
Engineering Procurement
Project management
Other more critical challenges can only be discovered at detailed design
& fabrication stages21
-
Large FPSO experience is useful for FLNG
0
10 000
20 000
30 000
40 000
50 000
60 000
70 000
80 000
1975 1980 1985 1990 1995 2000 2005 2010 2015 2020
Akpo FPSO, Nigeria, 320 x 60m
FPSOs installed, by topsides weight, 1977 to 2013
Sources: Infield Systems Database
Girassol FPSO, Total
Dalia FPSO, Total
Akpo FPSO, Total
P-58 & P-62 FPSOs,
Petrobras
FLNGs topsides
weight forecasts
Largest size and weight FPSOs
Engineering Procurement
Project management
To
psid
es
weig
ht,
in
to
nn
es
22
-
FLNGs use FPSOs construction strategy
Modularization expertise Akpo FPSO
Engineering Procurement
Project management
23
-
but there are still differences to take into account
Engineering Procurement
Project management
Piping & Layout
Equipment size
Large-bore
Heavy walls
Special grade piping unknown in the shipbuilding / offshore industry
Constructability
Detailed design to be adapted for pancake / flip-over construction method
Access to the deck during integration
Turret Mooring System integration
Long distance to walk for the workers
24
-
Field
facilities
Liquefaction
Methane
rich gas
Refrigerant
LNG
Pipeline
ReceptionFuel gas
(8 - 12% of
feedstock)
LNG Train
Methane
20C, 50 bars
-162C, 1 bar
Ethane, Propane, Butane, Pentane
Sulphur
Pipeline
reception
Acid gas
removal
DehydrationMercury
removal
NGL
recovery
Sulphur
recovery
LNG storage
loading
N2 rejection
Liquefaction
Refrigeration
loop
Fractionation
Power plant
Cooling water
Fire fighting systems
Nitrogen generation
Flare
Water treatment
Utility production for the plant
Condensate
stabilisation
Condensate
storage
LPG storage
Engineering Procurement
Project managementFrom wells to LNG, a complex process
CO2 purification
and reinjection
MEG / Water
Not present offshore
Can be foreseen
25
-
What are the key parameters or technologies ?
26
Optimized scheme selection methodology
LNG rate
CO2 content
LPG
extraction
Heating
media
Refrigerant
drivers
Liquefaction
technology
Cooling
media
Efficiency of
liquefaction
Power
demand
Fuel gas
demand
FLNG auto-
consumption
Engineering Procurement
Project management
26
-
Leading liquefaction processes
Expander process - Nitrogen based cycles
Pros
Safety (Inert gas refrigerant)
Less sensitive to motion (all gas)
No HC refrigerant storage
Cons
Very low efficiency of liquefaction
Large number of equipment
High deck area per unit of capacity
Proven in air separation industry
Used for re-liquefaction of boil-off gas
onboard QMax & QFlex LNG carriers
References in liquefaction Train capacity circa 1 MTPA
Engineering Procurement
Project management
Courtesy of Air Products
27
-
DMR : Dual Mixed Refrigerant
Pros
High efficiency of liquefaction
Small layout area of the precooling
exchanger (vs C3-MR)
Balance of power between the two
refrigeration cycles
Simplification for compactness
Cons
Amount of liquid HC (safety)
Refrigerant make-up and storage
required (safety)
Sensitive to motion
Industrial references
Train capacity 2.5 MTPA+
Leading liquefaction processes
Engineering Procurement
Project management
Courtesy of Air Products
28
-
FLNG capacity limit = Hull sizePrelude FLNG : 488 m
Akpo FPSO : 320 m
4 FIFA soccer fields,
105mx65m
Prelude FLNG
Engineering Procurement
Project management
29
-
Example of Floating LNG layout
Source: 2009 Technip R&D Study
30
Engineering Procurement
Project management
30
-
Installation of motion sensitive equipment close to center
of gravity to limit accelerations
Critical gas / liquid separators and columns designs are
validated through CFD studies performed to ensure even
velocity profiles and flow distribution in compact
equipment and to study sloshing effect on liquid
inventories
Marinization studies for critical equipment (cryogenic heat
exchangers, columns ) supported by licensors and
vendors studies
Marinization of process equipment
Engineering Procurement
Project management
31
-
LNG Storage
Key parameters or technologies to be considered
LNG storage capacity governed by size of shuttle LNG carriers
Sloshing behavior
Previous experience
Inspection / maintenance over 30 year operations without dry-docking
Competitiveness: schedule, cost, shipyards competition
2 technologies available
Membrane
NO96 Invar
Mark III stainless steel
Dominate the LNGC market
Space efficient
SPB tanks
Aluminium: fabrication by IHI; integration by shipyard
Stainless steel: fabrication & integration by shipyard
Engineering Procurement
Project management
32
-
LNG offloading
Engineering Procurement
Project management
Side by Side Tandem
Minor modification of carrier
High transfer flow rate
Strength
Sensitive to perpendicular waves (beam sea)
Tug assistance + thrusters
Safety issue (escalation)
Weakness
High availability
Safety distance
No tug assistance if DP
Strength
Major modification of carrier
Limited flow rate
Weakness
2 technologies for LNG offloading
33
-
What are the key parameters or technologies to be evaluated ?
F-LNG layout
Hazard segregation and protection principles
Environmental emissions control
Availability study of the facility
What will be the basis for making the decision ?
HazId, HazOp reviews and HSE studies will allow to identify hazard, risk and
environmental impacts and facility availability will help to make the decision
Safety
Engineering Procurement
Project management
Safety is ensured with blast walls and gaps between modules
34
-
Equipment specifications & partnerships with suppliers
Engineering
Procurement Project management
Equipment with new specifications & requirements
Adjustment to the marine environment (sloshing)
Larger, heavier & more complex
Impact on constructability
Acceleration and related loads due to vessel movements
The support of industry leading suppliers is one of the keys to the
success of our projects
Some equipment is specifically designed for FLNG facilities
New higher quality standards to minimize work offshore
Larger / heavier equipment impact on logistics
35
-
Management of the interfaces during detailed design
Hull (including LNG storage)
Topsides
Pro
du
cti
on
ris
ers
Subsea control
systems
Tu
rre
t&
mo
ori
ng
Equipment
suppliers
Um
bil
ica
ls
Engineering
Procurement
Project management
Interfaces between topsides and hull are
critical:
Main deck layout is a mix of piping & equipment
Some topsides equipment are located in the hull
Blast & spill protection of the substructure
All interfaces are managed and controlled by the topsides designer
36
-
A combination of skills
Onshore
Offshore
Subsea
Engineering
Procurement
Project management
The FLNG Technology is based on Onshore, Offshore & Subsea
expertise. Ideally the three segments shall be available in the same
operating center
37
-
A multi-center execution plan
Shell & TSC project directorates
IT / methods
Project controls
Procurement of tagged items and equipment
Topsides engineering
Substructure interface management
Construction coordination
Hull engineering
Construction
Module integration up to mechanical completion
Procurement of steel and other selected bulk
Construction management
Onshore commissioning
Goeje, South Korea
Paris, France
Support on topsides engineering
Kuala Lumpur, Malaysia
Tow, hook-Up &
commissioning
Offshore
Subsea engineering & installation
Support for regulatory requirements
Offshore hook-up & commissioning support
Perth, Australia
Support on topsides engineering
Chennai, India
Engineering
Procurement
Project management
TMS design
Monaco
TMS construction
Dubai, UAE
Example: Prelude FLNG
38
-
39
IV. Ongoing open sea FLNG projects
39
-
Two open sea FLNG under construction
Shell FLNG
LNG capacity: 3.6 MTPA
Prelude FLNG in Australia under
construction
Steel cutting of the hull in
October 2012
Steel cutting of the topsides in
January 2013
Hull launching in November 2013
Petronas FLNG
LNG capacity: 1.2 MTPA
Offshore Malaysia
Execution started in June 2012
Steel cutting of the hull in June
2013
Hull launching in April 2014
40
-
Shell Floating Liquefied Natural Gas contracts
Master AgreementThe design, construction and
installation of multiple FLNG
facilities over 15 years
Generic FLNG FEED
Prelude FLNG FEEDOffshore Western Australia
Prelude FLNG EPCIContract under which the FLNG
would be built when the project
would receive the final
investment decision
Prelude FLNG NTP
Prelude FLNG subsea
Agreement to strengthen
FLNG collaboration
Technip leader in a consortium with Samsung
41
2009
2009
2010
2010
2011
2012
2012
-
Shell Prelude FLNG
First FLNG project ever sanctioned
First of two FLNG projects for Technip
First FLNG under the TP / SHI Frame Agreement with Shell
Largest floating structure ever built
Largest multi-centers offshore projectever (Paris, KL, Perth, Chennai)
200 km from the nearest point on the mainland
200 250 m water depth
Length: 488 m, width: 74 m
Weight:
Steel: 260 000 tonnes
Displacement (tanks full): 600 000 tonnes
Comparison Eiffel tower iron structure = 7 300 tonnes
Prelude
Steel: 36 Eiffel towers
Displacement (tanks full): 82 Eiffel towers
Annual production
3.6 MTPA LNG capacity
1.3 MTPA condensate
0.4 MTPA LPG
Total liquid production: 110 000 boe /day
42
-
Prelude FLNG is being built in SHIs shipyard in Geoje, South Korea
One of the largest dry docks in the world
A yard equipped with a 8 000 t capacity floating crane
The first steel cutting of the hull started in October 2012
The first steel cutting of the topsides started in January 2013
Prelude EPCIC construction
43
-
Petronas FLNG 1
Partnership: Daewoo Shipbuilding & Marine Engineering
Second FLNG project worldwide, also located in Asia-Pacific
A challenging project
Location: Malaysia
Production: 1.2 MTPA of LNG
Petronas FLNG 1: a mid-scale project but
a fast-track schedule
44
-
3 open-sea projects at construction phase
FLNG project Country F.I.D.Distance
fromshore (km)
Waterdepth
(m)Meteo Operator
Capacity
MTPA
Prelude FLNG Australia 05 / 2011 210 250Benign
(Cyclones)Shell 3.6
Petronas FLNG1 Malaysia 06 / 2012 162 70 Benign Petronas 1.2
Petronas FLNG2 Malaysia 01 / 2014 112 1200 Benign Murphy 1.5
FLNG projects in progress
FLNG project Country F.I.D.Distance
fromshore (km)
OperatorCapacity
MTPA
Exmar FLNGbarges 1 & 2
Colombia 01 / 2012 Quay side Exmar 0.5
2 nearshore projects at construction phase
45
-
FLNG possible areas of development
Better security offshore
Remote fields and deep water
Remote fields
Sensitivity to construction on the
coastline
High cost of onshore construction
Pre-Salt Associated Gas
Difficult access to land
Remote fields and deep water
Brazil
Africa
Nearshore
Offshore East coast
High cost of onshore construction
Canada & Alaska
Australia
Many small fields
Presence of subsea trenches
Asia / Pacific
Remote fields
Arctic Circle
High cost of construction
Sensitive political environment
Eastern Mediterranea
46
-
LNG FLNG
High demand for LNG worldwide
Marketing flexibility versus pipelines
Technology readily available under license
with well developed service industry
Good returns through long term sales
agreements
Access to resources for IOCs
Ideal for reserves located far offshore in deep
water
Economically attractive in areas with high
onshore construction costs
Potential for reduction of overall field
development time
Development of small fields with relocation
Monetize offshore associated gas versus re-
injection or flaring
LNG and FLNG investment drivers
47
-
48
V. Conclusion
Floating LNG is reaching maturity
Numerous challenges are met in the design, engineering
and construction phases of an FLNG facility
Several IOCs & NOCs have expressed interest for this
technology and many areas worldwide offer a good
environment for FLNG developments
As of March 2015: 3 open-sea FLNG FIDs among which
2 executed by Technip
48
-
and coming soon
http://www.technip.com/fr/activite/offshore/gnl-flottant
49
http://www.technip.com/fr/activite/offshore/gnl-flottant
-
Thank you
www.technip.com50