Transcript of Mg flng welcome 2010 mar
WELCOME TO FLNG FORUM 2010:24 MARCH
PRESENTED BY MUKES GUPTA – MD CANADOIL ENGINEERING
© 2010 Canadoil Group © MGwww.canadoilgroup.com
WHY CHINA IS SUCH AN IMPORTANT PLACE TO ORGANIZE THIS FORUM!
REMEMBER
ZHENG HE SAILED FROM CHINA TO SOUTH PACIFIC, INDIAN OCEAN, AFRICA, PERSIAN GULF IN 7 EPIC VOYAGE FROM 1405 TO 1433 (SOME 80 YEARS BEFORE COLUMBUS VOYAGE)(SOME 80 YEARS BEFORE COLUMBUS VOYAGE)
CONSTRUCTED SOME OF THE LARGEST SHIPS IN NANJING – 3 SHIPYARDS STILL EXIST!
ZHENG HE’S TREASURE SHIP WAS 400 FT LONG AS COMPARED TO COLUMBUS’S 85 FT!
WHY CHINA CAN BECOME WORLD LEADER IN THE FLNG BUSINESS!
LABOR WORK FORCE – NEED MILLIONS OF LABOR WORK FORCE NEED MILLIONS OF MANHOURS OF WORK TO BUILD FLNG
COST OF LABOR IN CHINA MANY TIMES COST OF LABOR IN CHINA MANY TIMES LESS AS COMPARED TO EUROPE / USA
NEED LARGE SHIPYARDSNEED LARGE SHIPYARDS
NEED LARGE CONSUMER DEMAND TO INVEST
NEED LARGE RESOURCES MATERIAL, ,STEEL, MONEY, MANAGEMENT & MAINLY MANPOWER
NEED GROWING ECONOMY WITH FUNDS WILLING TO INVEST
CURRENT SCENARIO………LNG MARKET PERSPECTIVE
SEVERAL NEW LNG TERMINALS WILL START BETWEEN NOW AND 2012 BUT MANY PROPOSED LNG SEVERAL NEW LNG TERMINALS WILL START BETWEEN NOW AND 2012 BUT MANY PROPOSED LNG PRODUCTION CAPACITY IS NOT LIKELY TO MATERIALIZE
LACK OF INVESTMENT IN NEW LNG PRODUCTION DUE TO ESCALATING PLANT COST AND FINANCIAL MELTDOWNMELTDOWN
SHORTAGE OF LARGE GAS FIELDS NEAR SHORE & LACK OF SUITABLE PLANT SITE
LEADING LNG PRODUCING NATIONS HV DECLARED MORATORIUM TO USE FOR DOMESTIC PURPOSE ONLY
OPERATION OF CURRENT LNG CARRIERS ARE AT RECORD LEVELS
INCREASING DEMAND FOR LNG & SHORTAGE OF GAS LIKELY
TYP. US LNG IMPORT FORECAST….. SHORTFALL OF 150 MILLION TPY OF LNG EXPECTED
BY 2012 WORLDWIDE
THERE ARE SEVERAL HUNDREDS “STRANDED” NAT THERE ARE SEVERAL HUNDREDS STRANDED NAT GAS FIELDS IN THE WORLD TO SUPPORT 1MTPY LNG PLANT FOR NEXT 10 YEARS OR MORE
100’S OF PROSPECTIVE FLNG PLANTS IN RANGE OF 1 100’S OF PROSPECTIVE FLNG PLANTS IN RANGE OF 1 MTPY IDENTIFIED
EACH PLANT WILL BE 2 to 3 BILLION $+ INVESTMENT $HENCE MORE THEN 100 BILLION $ INVESTMENT EXPECTED
ISSUES FOR FLNG…….
There are a number of issues that need to be carefully examined when considering a floating LNG facilitya floating LNG facility• Location & sea condition• Survival in storm conditionsE i h f ili i i i & h• Ensuring smooth facility operation in motion & rough sea
• Suitable sites having available large quantity of Gas which can be trapped subsea• Availability of skilled manpower to build & operate, material and equipments / package modules suitable for operation in marine environment, suppliers, Certifying agency….. • Whether we really need such huge FLNG terminals or whether a smaller version y gcan be more productive and economical• Access for export / import vessels (tugs & pilotage)• Type of plant liquefaction / regasification• Type of plant, liquefaction / regasification• Type of vessel & containment• Mooring of the facilityM th d f t f f• Method of transfer of cargo
• Deck congestion
DIFFERENT PARTNERSHIP POSSIBLE RELATED TO FLNG – NEEDS A STRATEGY & VISION TO DEVELOP A SUCCESSFUL PROJECT BENEFITING ALL STAKEHOLDERS VISION TO DEVELOP A SUCCESSFUL PROJECT BENEFITING ALL STAKEHOLDERS
(A)GAS SUPPLIER
(B)GAS TRADING CO
(C)LNG SHIPPING CO
(D)LNG BUYERGAS SUPPLIER GAS TRADING CO. LNG SHIPPING CO. LNG BUYER
LIQUEFACTION AND STORAGE SERVICE
(E)(H)
LNG USER (POWER
(J)SHIP BUILDER (YARD)
Leasing arrangement (d il b i )
(PLANT COMPANY)
(I)LIQUEFACTION PLANT
OWNER
(G) (daily rate basis) (I)OPERATING COMPANY
(K)MODULE SUPPLIER
(F) EPCIC contract – LumpSum (L)
LIQUEFACTION PLANT EPC CONTRACTOR
(F) pTurnKey (LSTK)OTHER CONTRACTOR
& SUPPLIER
SIMPLIFIED LNG PROCESS BLOCK DIAGRAM (TYPICAL)( )
TYPICAL ONSHORE LNG PLANT SCHEME…….CASE STUDY
CURRENT ATTEMPT OF GIANT FLNG CONCEPT HAS SOME RISK!
QATAR GAS OFFSHORE & AMINE FILTERATION MODULE……CASE STUDYQ
TEMPORARY FLARE PACKAGE SUITABLE TO FIT & USE ON 3 DIFF PLATFORMS
ASSEMBLY OF MODULES……MODULARIZATION IDEAS
DESIGNING GAS/ LNG FACILITIES FOR LOCATION ONDESIGNING GAS/ LNG FACILITIES FOR LOCATION ON FLOATER……
AMINE SWEETENING MODULE
ONSHORE PLANT CONVERTED TO MODULE TO BE SHIPPED…….CASE STUDY
WEIGHT REDUCTION ANALYSIS & OPTIMIZATION OF MODULES FOR OFFSHORE PLATFORM ………..CASE STUDY ZORA PLATFORM
WEIGHT REDUCTION ON THE OFFSHORE ..…..CASE STUDY ZORA PLATFORM
IDEA OF FLOATING GAS TO LIQUID PLANT TO AVOID ENERGY WASTE IN QLIQUEFACTION & REGASSIFICATION
LET FLNG PROVIDE SAFE AND ADEQUATE ENERGY TO MASSES AT LOW COST
FCNGFLOATING PIPE TO CARRY CNG
FLOATING POWER PLANT
CARRY CNG
COPY RIGHT 2010 ©…………. [email protected]
Use of LNG helps in reducing Carbon footprint and save environment!
LET US BEGIN THE FLNG FORUM WITH A PRAYER!
SINCE 1000’S OF YEARS, IT IS CUSTOMARY TO BEGIN SUCH GATHERING BY INVOKING A PRAYER & BLESSING. IN THIS PRAYER WE SEEK LORD’S BLESSINGS FOR A GROUP STUDY THAT IS FREE WE SEEK LORD S BLESSINGS FOR A GROUP STUDY THAT IS FREE OF OBSTACLES CARRIED OUT WITH HEALTHY MIND & BODY WITH CONCENTRATION IN A CONDUCIVE ENVIRONMENT WITH EASY COMMUNICATION FREE OF ARGUMENTS & HATRED. OM PEACE PEACE PEACEOM PEACE PEACE PEACE
ACKNOWLEDGEMENTS (PHOTOGRAPHS; ARTICLES & PRESENTATION….)· ABS· ABS
· Shel l
FPC· FPC
· Technip
· FlexLNG
· QG
· ConocoPhillips
· Saipem
· DNV
· Aker
· Waller Marine
· EnerSea Votrans
· E & P (Brian)
· Asim Deshpande & Michael EconomidesEconomides
· CE & CG Team (Bill / Milind) & others