FLNG 1500 Kris Martinick

100
Page:1 www.wison.com | www.wison-offshore.com Bringing The FLNG Hull & The Topside Together Wison Offshore & Marine. February 2014

Transcript of FLNG 1500 Kris Martinick

Page 1: FLNG 1500 Kris Martinick

Page:1www.wison.com | www.wison-offshore.com

Bringing The FLNG Hull & The Topside Together

Wison Offshore & Marine.February 2014

Page 2: FLNG 1500 Kris Martinick

Page:2www.wison.com | www.wison-offshore.com

Business SegmentsFocusing on the Energy Industry and Hi-tech Sectors

Using coal as feed stock, Wison Energy provides high quality industrial gases via clean coal technology.

Wison Group

Specializing in petrochemicals, coal chemicals and refining industries

Development of

emerging chemical and

LNG related businesses.

A word-class EPC Contactor focused providing solutions on international oil and gas EPC Projects.

Clean Energy Emerging BusinessOffshore & Marine Engineering Services

The Wison Group employs approximately 3,000 people worldwide

Page 3: FLNG 1500 Kris Martinick

Page:3www.wison.com | www.wison-offshore.com

Caribbean FLNG Project – Setting the Stage

Page 4: FLNG 1500 Kris Martinick

Page:4www.wison.com | www.wison-offshore.com

Caribbean FLNG Project Background� Pacific Rubiales Energy (PRE) via its

subsidiary Pacific Stratus Energy Colombia Corp. (PSE), signed a natural gas/ LNG Liquefaction, Storage and Loading Services Agreement with Belgium based EXMAR NV:− EXMAR will build, operate and maintain a Floating

Liquefaction & Storage Unit (FLNG) to be located on the Colombian Caribbean coast.

− PSE will have exclusive rights to supply and liquefy up to 0.5 mmtpa of LNG over a 15 year period, under a tolling structure.

� The source of the gas is PSE’s La Creciente Field.

� PSE will build an 18 inch pipeline to transport gas from the field to the coast (88 Km).

Page 5: FLNG 1500 Kris Martinick

Page:5www.wison.com | www.wison-offshore.com

The FLNG Solution

� Selected FLNG solution is a non-propelled barge moored to an offshore jetty.

� FLNG is to be located 4 Km offshore in 14 m water depth.

� FLNG storage and process requirements are:- Storage - 16,000 m3

- Liquefaction - 0.5mmtpa

� Alongside FLNG is 170,000 m3 LNG Floating Storage Unit (FSU).

Regasification option:

� 65% of Colombia’s electricity comes from hydropower.

� In some years (la Nina) water shortages may require importing LNG to generate power to maintain supply.

Page 6: FLNG 1500 Kris Martinick

Page:6www.wison.com | www.wison-offshore.com

� Wison is the primary EPCIC contractor to EXMAR for the barge-based FLNG.

� Wison’s Scope:− FLNG Project Management,

Engineering, Procurement, Construction, Commissioning, Transportation, Installation and Start-up of the Facility.

� Major subcontractors : - Black & Veatch: Topside

LNG Equipment Design, Procurement & Commissioning

- TGE: Cargo Tanks & Cargo Handling Systems

FLRSU Project Details and Wison Scope

Page 7: FLNG 1500 Kris Martinick

Page:7www.wison.com | www.wison-offshore.com

Transportation & Installation

� Following yard commissioning, FLNG will be loaded onto transport vessel for dry transport to Colombia.

� FLRSU will be offloaded at inshore location and wet-towed to final installation site.

� Permanent mooring brackets will be installed while temporarily moored at site.

� Gas export hoses will be installed from jetty to FLNG.

Voyage: ~13,000 n.miles

Page 8: FLNG 1500 Kris Martinick

Page:8www.wison.com | www.wison-offshore.com

Barge FLNG Applications

� Complete LNG plant in a single module.� Near-shore processing in sufficient depth to transfer

to LNGC.� Eliminates/reduces need for a cryogenic load

out jetty.� Storage on board, onshore LNG tanks not

required.� Both on-shore and off-shore feed gas.� Gravity based structures.� Ports or on land.

Wison 3 MTPA Barge Design

Page 9: FLNG 1500 Kris Martinick

Page:9www.wison.com | www.wison-offshore.com

Wison will deliver the first LNG Regasification Unit installed off India’s eastern coast in the Kakinada Anchorage Port, Andhra Pradesh for the VGS Group

� Newbuild barge-based FRU� Regasification capacity of 4.47 MTA

− 750MMscf/d nominal− 1,000MMscf/d maximum

� Designed to accommodate future regasification expansion to 8.94 MTA with addition of another 750MMscf/d module

� Regasification module supplied by Hamworthy� Storage on a separate unit (FSU)• Moored via dolphin mooring system in 20m of

water

Kakinada Floating Regasification Unit (FRU)

• Barge Particulars:

- Length: ≈≈≈≈ 128.4 m

- Breadth: ≈≈≈≈ 47.00 m

- Depth: ≈≈≈≈ 9.00 m

- Draft (design): ≈≈≈≈ 3.00 m

Page 10: FLNG 1500 Kris Martinick

Page:10www.wison.com | www.wison-offshore.com

FLNG – Gas Processing

Page 11: FLNG 1500 Kris Martinick

Page:11www.wison.com | www.wison-offshore.com

Floating LNG Production Unit Characteristics� Process simplicity / simplified operation� Compact� Modularize� Scalable & expandable� Flexibility in design for

− Feed gas variation− Ambient temperature

� Marinisation� Availability� Safety

Page 12: FLNG 1500 Kris Martinick

Page:12www.wison.com | www.wison-offshore.com

FLNG Block Flow – Topsides Requirement

BLOCK FLOW DIAGRAM

FEED GAS

CO2

VENT H2O

FUEL

LNG

CONDENSATE

LPG

INLET

RECEPTION

LIQUID

SEPARATORTREATING

DEHYDRATION

/Hg REMOVALLIQUEFACTION

LNG FLASH/

FUEL

COMPRESSOR

LPG/

CONDENSATE

FRACTIONATION

LNG STORAGE

POWER

GENERATION

(OPTION)

FLARESWARM FLARE

CRYOGENIC FLARE

WATERTREATING/

DISTRIBUTIONFIRE UTILITY

POTABLE

NITROGEN

CONSUMABLES STORAGELUBE OILS

CHEMICALSMISC.

EMERGENCY

POWER

EFFLUENT

TREATING

HOT OIL

OR

STEAM

PLANT AIRINSTRUMENT

AIR

REFRIGERANT

MAKEUP/

STORAGE

Page 13: FLNG 1500 Kris Martinick

Page:13www.wison.com | www.wison-offshore.com

PRICO® SMR Liquefaction Technology

� Black & Veatch’s patented PRICO® Single Mixed Refrigerant technology is the simplest form of mixed refrigerant cycle.

� B&V has considerable experience in the field:

- 27 global LNG plants in operation

- 11 plants under construction

� Process is scalable over wide capacity range but core process remains the same.

� Compact layout with modular philosophy lends itself to use offshore.

� Simplicity of process results in relatively low cost.

� Simplified operations lead to quick startup.

Page 14: FLNG 1500 Kris Martinick

Page:14www.wison.com | www.wison-offshore.com

Dealing With The Gas

� Slug catcher on inlet. � CO2 must be less than 50ppm before entering the main heat exchanger.

� Membrane and amine systems.� Dealing with CO2

� N2 is dealt with in the BOG.� Heavies removed in the BAHX.

� LPGs, condensate stabilisation, NGLs. � Product Storage.� Inlet Booster compression.

Page 15: FLNG 1500 Kris Martinick

Page:15www.wison.com | www.wison-offshore.com

Main Exchanger – BAHX “Cold Box”� Aluminum plate fin exchangers (cores) in

parallel� Strictly use external connections� No valves or equipment in cold box� Cold box is for insulation / support only� Plate fins are highly efficient and reliable� More than half with 30+ years of service (no

repairs)� Design vetted by ExxonMobil – approved

offshore applications� Down flow condensing / up flow boiling� Refrigerant & feed gas condensing flowing

downward� Low pressure refrigerant boils in up flow� Simplified hydraulics – working with gravity� Cold end down� Upon shutdown, cold liquid stays in

cryogenic area of the core� No cold liquid flows in to warm part of the

exchanger� No special precautions in case of shut down

Page 16: FLNG 1500 Kris Martinick

Page:16www.wison.com | www.wison-offshore.com

PRICO LIQUEFACTION MODULESCapacity (MMTPA)

# of Modules

# ofTrains Turbine Driver

BAHX Cores-Coldbox

0.5 One One LM 2500+ 4 cores box –one box

1.0 One One 2 X LM2500+ in parallel 8 cores-box –one box

1.0 Two Two One LM2500+ each Module, each train

4 cores- box/per train

1.0 One One One TRENT 60 8 cores-box –one box

2.0 Two One 2 X LM2500+ in parallel each Module

8 cores-box/per train – Two

boxes2.0 Two One One TRENT60, each

Module8 cores-box/per

train – Two boxes

2.0 Two Two One TRENT60 each module, each train

8 cores-box/per train – Two

boxes

16

Development of Floating LNG Production Units May 2011

Page 17: FLNG 1500 Kris Martinick

Page:17www.wison.com | www.wison-offshore.com

Mixed Refrigerant System� Components

� Nitrogen (from plant system)� Methane (treated feed or BOG)� Ethylene or ethane (imported)� Propane (imported)� ISO-pentane (imported)

� Refrigerant “recipe” developed for feed cases

� Modified “on the fly”� General inventory – 1 MMTPA

� Ethylene (20 m3)� Propane (35 m3)� IsoPentane (56 m3)

� Flexible refrigerant makeup options � Fixed storage vessels� Sea-tainers (euro tainers)� Fractionation

Page 18: FLNG 1500 Kris Martinick

Page:18www.wison.com | www.wison-offshore.com

Marinisation

Page 19: FLNG 1500 Kris Martinick

Page:19www.wison.com | www.wison-offshore.com

Marinisation� Process operability

� Process performance� Equipment performance

� Mechanical design� Motion accelerations and deck deflection

� Safety

Key Equipment for Marinisation� Refrigeration compressor and turbine drivers� Refrigerant exchanger – main heat exchanger – cold box� Gas treating and fractionation

Page 20: FLNG 1500 Kris Martinick

Page:20www.wison.com | www.wison-offshore.com

Marinisation Offshore Saftey

� Material selection� Isolation philosophy� Spill containment philosophy� Relief and blow down analysis� Blast analysis� Flare radiation / gas dispersion analysis� Dropped object analysis� Fire and gas detection� Fire fighting and protection philosophy� Overall control philosophy� HAZID / HAZOP� Material handling / maintenance

Page 21: FLNG 1500 Kris Martinick

Page:21www.wison.com | www.wison-offshore.com

Storage & Hull Impacting the Topside

Page 22: FLNG 1500 Kris Martinick

Page:22www.wison.com | www.wison-offshore.com

Storage & Hull Interaction

� No storage in the barge – topside sets the size

Page 23: FLNG 1500 Kris Martinick

Page:23www.wison.com | www.wison-offshore.com

Storage & Hull Interaction

� Type C – Storage in the barge – typically 3-60,000 m3 - Tanks may set length.

Page 24: FLNG 1500 Kris Martinick

Page:24www.wison.com | www.wison-offshore.com

Self Contained Tanks – Type C

Page 25: FLNG 1500 Kris Martinick

Page:25www.wison.com | www.wison-offshore.com

FLNG GA Drawing – Plan View

View shows locations of 3 LNG Storage Tanks inside hull

Page 26: FLNG 1500 Kris Martinick

Page:26www.wison.com | www.wison-offshore.com

LNG Tank Installation Complete

Page 27: FLNG 1500 Kris Martinick

Page:27www.wison.com | www.wison-offshore.com

Storage & Hull Interaction

� Atmospheric storage – Membrane, Moss or SPB typically 30,000 m3 and up.

Page 28: FLNG 1500 Kris Martinick

Page:28www.wison.com | www.wison-offshore.com

The Containment Systems – Membrane

� Membrane Tanks

Page 29: FLNG 1500 Kris Martinick

Page:29www.wison.com | www.wison-offshore.com

Self Contained Tanks – Type B

� Moss � SPB

Page 30: FLNG 1500 Kris Martinick

Page:30www.wison.com | www.wison-offshore.com

LNG Offloading

� Side by Side – STS (Ship to Ship)

− Loading Arm

− Hoses

� Tandem

− Stern discharge

− Aerial hose

− Floating hose in development

� LNG Carriers

Page 31: FLNG 1500 Kris Martinick

Page:31www.wison.com | www.wison-offshore.com

Caribbean FLNG Project

Page 32: FLNG 1500 Kris Martinick

Page:32www.wison.com | www.wison-offshore.comwww.wison.com | www.wison-offshore.com

� Fully operational in 2006

‒ Located at the bank of the Yangtze River (76 km from the open sea)

‒ Occupies 640,000 square meters and maintains 735 meters of river front

� Annual throughput capacity of 70,000 Tonnes

� Staffing:

‒ Normal: 2,300 (700 direct employees plus 1,600 contractors)

‒ Peak: 3,500 (including contractors)

Nantong Yard

Page:32

Page 33: FLNG 1500 Kris Martinick

Page:33www.wison.com | www.wison-offshore.com

Project Schedule – Key Milestones

MILESTONE DATE

Project Start Date April 2012

FLRSU Strike Steel December 2012

FLSRU Keel Laying Start July 2013

Topside Construction Start October 2013

FLRSU Equipment Installation Start November 2013

Hull Construction Complete November 2013

FLRSU Mechanical Completion July 2014

FLRSU Provisional Acceptance Ex-Yard September 2014

FLSRU Sail to Colombia on Dry Tow Vessel December 2014

FLSRU Moored at Offshore Jetty January 2015

FLRSU Final Commissioning Start January 2015

FLRSU Final Commissioning End April 2015

Provisional Acceptance on Site – Project End April 2015

Page 34: FLNG 1500 Kris Martinick

Page:34www.wison.com | www.wison-offshore.com

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

WHI’s Dry Dock (260m x 68m)

Page 35: FLNG 1500 Kris Martinick

Page:35www.wison.com | www.wison-offshore.com

NO.1 LIFTING BLOCK HB04/05/06C

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 36: FLNG 1500 Kris Martinick

Page:36www.wison.com | www.wison-offshore.com

NO.1 LIFTING BLOCK HB04/05/06C

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 37: FLNG 1500 Kris Martinick

Page:37www.wison.com | www.wison-offshore.com

NO.2 LIFTING BLOCK HB01/02/03C

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 38: FLNG 1500 Kris Martinick

Page:38www.wison.com | www.wison-offshore.com

NO.2 LIFTING BLOCK HB01/02/03C

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 39: FLNG 1500 Kris Martinick

Page:39www.wison.com | www.wison-offshore.com

NO.3 LIFTING HT11

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 40: FLNG 1500 Kris Martinick

Page:40www.wison.com | www.wison-offshore.com

NO.3 LIFTING BLOCK HT11

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 41: FLNG 1500 Kris Martinick

Page:41www.wison.com | www.wison-offshore.com

NO.4 LIFTING BLOCK HB04/05/06P

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 42: FLNG 1500 Kris Martinick

Page:42www.wison.com | www.wison-offshore.com

NO.4 LIFTING BLOCK HB04/05/06P

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 43: FLNG 1500 Kris Martinick

Page:43www.wison.com | www.wison-offshore.com

NO.5 LIFTING BLOCK HB04/05/06S

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 44: FLNG 1500 Kris Martinick

Page:44www.wison.com | www.wison-offshore.com

NO.5 LIFTING BLOCK HB04/05/06S

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 45: FLNG 1500 Kris Martinick

Page:45www.wison.com | www.wison-offshore.com

NO.6 LIFTING BLOCK HB07/08C

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 46: FLNG 1500 Kris Martinick

Page:46www.wison.com | www.wison-offshore.com

NO.6 LIFTING BLOCK HB07/08C

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 47: FLNG 1500 Kris Martinick

Page:47www.wison.com | www.wison-offshore.com

NO.7 LIFTING BLOCK HB09/10C

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 48: FLNG 1500 Kris Martinick

Page:48www.wison.com | www.wison-offshore.com

NO.7 LIFTING BLOCK HB09/10C

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 49: FLNG 1500 Kris Martinick

Page:49www.wison.com | www.wison-offshore.com

NO.8 LIFTING BLOCK E101C

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 50: FLNG 1500 Kris Martinick

Page:50www.wison.com | www.wison-offshore.com

NO.8 LIFTING BLOCK E101C

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 51: FLNG 1500 Kris Martinick

Page:51www.wison.com | www.wison-offshore.com

NO.9 LIFTING BLOCK HT21

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 52: FLNG 1500 Kris Martinick

Page:52www.wison.com | www.wison-offshore.com

NO.10 LIFTING BLOCK HB01/02/03P

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 53: FLNG 1500 Kris Martinick

Page:53www.wison.com | www.wison-offshore.com

NO.11 LIFTING BLOCK HB01/02/03S

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 54: FLNG 1500 Kris Martinick

Page:54www.wison.com | www.wison-offshore.com

NO.12 LIFTING BLOCK HB07/08/09/10P

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 55: FLNG 1500 Kris Martinick

Page:55www.wison.com | www.wison-offshore.com

NO.13 LIFTING BLOCK HB07/08/09/10S

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 56: FLNG 1500 Kris Martinick

Page:56www.wison.com | www.wison-offshore.com

NO.14 LIFTING BLOCK E102C

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 57: FLNG 1500 Kris Martinick

Page:57www.wison.com | www.wison-offshore.com

NO.15 LIFTING BLOCK E101P

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 58: FLNG 1500 Kris Martinick

Page:58www.wison.com | www.wison-offshore.com

NO.16 LIFITNG BLOCK E101S

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 59: FLNG 1500 Kris Martinick

Page:59www.wison.com | www.wison-offshore.com

NO.17 LIFTING BLOCK F101P/S

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 60: FLNG 1500 Kris Martinick

Page:60www.wison.com | www.wison-offshore.com

NO.18 LIFTING BLOCK HS04/05/06P

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 61: FLNG 1500 Kris Martinick

Page:61www.wison.com | www.wison-offshore.com

NO.19 LIFTING BLOCK HS04/05/06S

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 62: FLNG 1500 Kris Martinick

Page:62www.wison.com | www.wison-offshore.com

NO.20 LIFTING BLOCK HS07/08/09/10P

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 63: FLNG 1500 Kris Martinick

Page:63www.wison.com | www.wison-offshore.com

NO.21 LIFTING BLOCK HS07/08/09/10S之前

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 64: FLNG 1500 Kris Martinick

Page:64www.wison.com | www.wison-offshore.com

NO.21 LIFTING BLOCK HS07/08/09/10S

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 65: FLNG 1500 Kris Martinick

Page:65www.wison.com | www.wison-offshore.com

NO.22 LIFTING BLOCK HS01/02/03P

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 66: FLNG 1500 Kris Martinick

Page:66www.wison.com | www.wison-offshore.com

NO.23 LIFTING BLOCK HS01/02/03S

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 67: FLNG 1500 Kris Martinick

Page:67www.wison.com | www.wison-offshore.com

NO.24 LIFTING BLOCK F201P/S

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 68: FLNG 1500 Kris Martinick

Page:68www.wison.com | www.wison-offshore.com

NO.25 LIFTING BLOCK E201C

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 69: FLNG 1500 Kris Martinick

Page:69www.wison.com | www.wison-offshore.com

NO.26 LIFTING BLOCK E202C

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 70: FLNG 1500 Kris Martinick

Page:70www.wison.com | www.wison-offshore.com

NO.27 LIFTING BLOCK F301P/S

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 71: FLNG 1500 Kris Martinick

Page:71www.wison.com | www.wison-offshore.com

NO.28 LIFTING BLOCK E201/301/401P

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 72: FLNG 1500 Kris Martinick

Page:72www.wison.com | www.wison-offshore.com

NO.29 LIFTING BLOCK E201/301/401S

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 73: FLNG 1500 Kris Martinick

Page:73www.wison.com | www.wison-offshore.com

TGE TANK LIFTING

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 74: FLNG 1500 Kris Martinick

Page:74www.wison.com | www.wison-offshore.com

NO.30 LIFTING BLOCK HD07/08/09

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 75: FLNG 1500 Kris Martinick

Page:75www.wison.com | www.wison-offshore.com

NO.31 LIFTING BLOCK HD04/05/06

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 76: FLNG 1500 Kris Martinick

Page:76www.wison.com | www.wison-offshore.com

NO.32 LIFTING BLOCK HD01/02/03

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 77: FLNG 1500 Kris Martinick

Page:77www.wison.com | www.wison-offshore.com

MAIN GENERATOR INSTALLATION

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 78: FLNG 1500 Kris Martinick

Page:78www.wison.com | www.wison-offshore.com

NO.33 LIFTING E401C

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 79: FLNG 1500 Kris Martinick

Page:79www.wison.com | www.wison-offshore.com

NO.34 LIFTING BLOCK L101/201/301/401P/S

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 80: FLNG 1500 Kris Martinick

Page:80www.wison.com | www.wison-offshore.com

NO.35 LIFTING FN

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 81: FLNG 1500 Kris Martinick

Page:81www.wison.com | www.wison-offshore.com

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

NO.36 LIFTING WP

Page 82: FLNG 1500 Kris Martinick

Page:82www.wison.com | www.wison-offshore.com

HULL ASSEMBLY COMPLETE

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 83: FLNG 1500 Kris Martinick

Page:83www.wison.com | www.wison-offshore.com

HULL MAIN DECK TOPVIEW

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 84: FLNG 1500 Kris Martinick

Page:84www.wison.com | www.wison-offshore.com

TOPSIDE PIPE RACK INSTALLATION

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 85: FLNG 1500 Kris Martinick

Page:85www.wison.com | www.wison-offshore.com

TOPSIDE EQUIPMENT INSTALLATION

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 86: FLNG 1500 Kris Martinick

Page:86www.wison.com | www.wison-offshore.com

TOPSIDE TOWER EQUIPMENT INSTALLATION

EXMAR FLRSU PROJECT – BUILDING METHODOLOGY

Page 87: FLNG 1500 Kris Martinick

Page:87www.wison.com | www.wison-offshore.com

Block Assembly Mar 2013

Page 88: FLNG 1500 Kris Martinick

Page:88www.wison.com | www.wison-offshore.com

Block Assembly Mar 2013

Page 89: FLNG 1500 Kris Martinick

Page:89www.wison.com | www.wison-offshore.com

Block Assembly Mar 2013

Page 90: FLNG 1500 Kris Martinick

Page:90www.wison.com | www.wison-offshore.com

Fabrication of Piping Rack Mar 2013

Page 91: FLNG 1500 Kris Martinick

Page:91www.wison.com | www.wison-offshore.com

Hull Construction June 2013

Page 92: FLNG 1500 Kris Martinick

Page:92www.wison.com | www.wison-offshore.com

Keel Laying July 2013.

Page 93: FLNG 1500 Kris Martinick

Page:93www.wison.com | www.wison-offshore.com

Tank Delivery and Installation Oct 2013

Page 94: FLNG 1500 Kris Martinick

Page:94www.wison.com | www.wison-offshore.com

Setting the Last Deck Nov 2013

Page 95: FLNG 1500 Kris Martinick

Page:95www.wison.com | www.wison-offshore.com

Block Erection in Dock Pipe Rack General Assembly

Hull Completion

Page 96: FLNG 1500 Kris Martinick

Page:96www.wison.com | www.wison-offshore.com

Topsides Installation

Page 97: FLNG 1500 Kris Martinick

Page:97www.wison.com | www.wison-offshore.com

Accommodation Block General Assembly

Topside Equipment Platform

Topsides Facilities

Page 98: FLNG 1500 Kris Martinick

Page:98www.wison.com | www.wison-offshore.com

GE Compressor Lifting Topside Equipment Installation

Compressor Installation

Page 99: FLNG 1500 Kris Martinick

Page:99www.wison.com | www.wison-offshore.com

Summary & Conclusions� For an FLNG unit the storage

volume requirement as well as the tank type selected has a significant effect on the topside lay-out and how the equipment is configured.

� The type of offloading equipment selected impacts the lay-out of the topside as well as set some of the crane coverage requirements.

� Safety studies are required for an FLNG unit to become reality. These impact spacing, lay-out principles and cryogenic spill protection as well as mechanical handling etc.

Page 100: FLNG 1500 Kris Martinick

Page:100www.wison.com | www.wison-offshore.com

www.wison-offshore.com

THANK YOU

Wison Offshore & Marine (Hong Kong) Ltd.Australian OfficeLevel 24, Allendale Square77 St Georges TerracePerth, WA, 6000

Wison Offshore & Marine (USA), Inc.1400 Broadfield Boulevard, Suite 150, Houston, Texas, USATel:+1 281 676 2650Fax: +1 281 676 2086

Wison Offshore & Marine, Ltd.699 Zhongke Road, Zhangjiang Hi-tech Park, Shanghai, ChinaTel:+86 21 2030 6789Fax: +86 21 5855 7211

www.wison-offshore .com