CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.
FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.
Transcript of FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.
FINAL PROJECTCVE 4073 – Construction Cost Engr.
Prof. Locurcio12/04/2014
Group Members
• Aline Franqui• Bianca Farias• Gabriel Silva (PM)• Gilberto Pierozan• Julian Miyamoto• Junior Badziak• Lara Barroso
Outline Introduction
Technical approach
Tasks Responsabilities
Bid Breakdown by major components
Bid Summary
Introduction Since the past to our current age, mankind have
always tried to let a legacy behind. In construction, we can make this wish last for ages. But nothing of it would have happened if there were no planning or management skills.
In this project we could taste how the real world is, and how to be prepared to challenges to come.
Technical Approach We divided the work by lottery!
As PM I assumed that since everyone have done all the homeworks, nobody would have problem.
We’ve scheduled meetings twice a month So, as a group, we could see the progress of our
work.
After all the work was done, we revised the work from our collegues, to make sure it was correct
Task Responsabilities
Concrete
l Footing l Slab
l Footing
Footing
l Footing l Slab
Slab and Final Cost
#5 Rebars
Wood & Plastic
Dimensions of the elements used for Wood & Plastic and Thermal & Moisture
Studs
Headers
Blocking / OSB - CDX
Total price for Wood & Plastic = $7,084.90
Thermal & Moisture
Total price for Thermal & Moisture = $1,570.34
Plumbing
Plumbing
VTR – vent tub riser
LAV – lavatory
WC – water closet
TUB – tub shower
CO – cleanout adapter
KIT SK – kitchen sink
Plumbing
8’
11.5’
10.5’
11.5’5’
8’
Plumbing
Hot water line: pass through tubs, lavatories and kitchen. Cold water line: pass through tubs, lavatories, water closets and kitchen. For tubs and wc: 1” pipeFor lavatories and kitchen: ½” pipe
Roof
Roof main dimensions
Calculate the area on the plane, and then use the
following to have the inclined area:
34
54
4
(1+slope2)0.5
Roof Materials
Roof Calculation
HVAC
HVAC
Electrical
Electrical Wiring and Fixtures Take-off
Openings
Finishes
Finishes Calculation
Finishes Calculation
Bid Summary
Summary SheetDescription Material cost Equip. Cost Labor cost Total Cost
Earthwork $3,737.52 $4,439.94 $3,826.49 $12,003.95 Concrete (Foundation) $6,017.25 $14.18 $2,260.39 $8,291.82 Wood, plastics and composites $2,716.42 $446.72 $2,595.58 $5,758.72 Openings $2,016.19 $- $546.00 $2,562.19 Plumbing and fixtures $299.05 $- $1,445.78 $1,744.82 Roof (with truss package on total cost) $5,020.98 $- $3,228.39 $11,249.37 HVAC System $4,159.46 $- $851.21 $5,010.67 Electrical $6,803.22 $- $8,392.86 $15,196.08 Fire Suppression $52.00 $- $29.00 $81.00 Thermal, moistures protection $757.61 $- $812.73 $1,570.34 Finishes $11,408.05 $8,094.97 $19,503.03 Specialties $2,500.00 $2,500.00 Documentation $2,000.00
Labor Taxes (25%) $8,020.85
Sales Taxes (6%) $2,729.26 Subtotal $98,222.11 O&P (10%) $9,822.21
TOTAL COST $108,044.32
Questions?