FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

54
FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014

Transcript of FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

Page 1: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

FINAL PROJECTCVE 4073 – Construction Cost Engr.

Prof. Locurcio12/04/2014

Page 2: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

Group Members

• Aline Franqui• Bianca Farias• Gabriel Silva (PM)• Gilberto Pierozan• Julian Miyamoto• Junior Badziak• Lara Barroso

Page 3: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

Outline Introduction

Technical approach

Tasks Responsabilities

Bid Breakdown by major components

Bid Summary

Page 4: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

Introduction Since the past to our current age, mankind have

always tried to let a legacy behind. In construction, we can make this wish last for ages. But nothing of it would have happened if there were no planning or management skills.

In this project we could taste how the real world is, and how to be prepared to challenges to come.

Page 5: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

Technical Approach We divided the work by lottery!

As PM I assumed that since everyone have done all the homeworks, nobody would have problem.

We’ve scheduled meetings twice a month So, as a group, we could see the progress of our

work.

After all the work was done, we revised the work from our collegues, to make sure it was correct

Page 6: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

Task Responsabilities

Page 7: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

Concrete

Page 8: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.
Page 9: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

l Footing l Slab

Page 10: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.
Page 11: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

l Footing

Page 12: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

Footing

Page 13: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

l Footing l Slab

Page 14: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

Slab and Final Cost

Page 15: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

#5 Rebars

Page 16: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

Wood & Plastic

Page 17: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

Dimensions of the elements used for Wood & Plastic and Thermal & Moisture

Page 18: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

Studs

Page 19: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

Headers

Page 20: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

Blocking / OSB - CDX

Total price for Wood & Plastic = $7,084.90

Page 21: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

Thermal & Moisture

Page 22: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

Total price for Thermal & Moisture = $1,570.34

Page 23: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

Plumbing

Page 24: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.
Page 25: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

Plumbing

VTR – vent tub riser

LAV – lavatory

WC – water closet

TUB – tub shower

CO – cleanout adapter

KIT SK – kitchen sink

Page 26: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

Plumbing

8’

11.5’

10.5’

11.5’5’

8’

Page 27: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

Plumbing

Hot water line: pass through tubs, lavatories and kitchen. Cold water line: pass through tubs, lavatories, water closets and kitchen. For tubs and wc: 1” pipeFor lavatories and kitchen: ½” pipe

Page 28: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.
Page 29: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.
Page 30: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

Roof

Page 31: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

Roof main dimensions

Calculate the area on the plane, and then use the

following to have the inclined area:

34

54

4

(1+slope2)0.5

Page 32: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

Roof Materials

Page 33: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

Roof Calculation

Page 34: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

HVAC

Page 35: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

HVAC

Page 36: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

Electrical

Page 37: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.
Page 38: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.
Page 39: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.
Page 40: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.
Page 41: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.
Page 42: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.
Page 43: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.
Page 44: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.
Page 45: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

Electrical Wiring and Fixtures Take-off

Page 46: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.
Page 47: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

Openings

Page 48: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.
Page 49: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

Finishes

Page 50: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

Finishes Calculation

Page 51: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

Finishes Calculation

Page 52: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

Bid Summary

Page 53: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

Summary SheetDescription Material cost Equip. Cost Labor cost Total Cost

Earthwork $3,737.52 $4,439.94 $3,826.49 $12,003.95 Concrete (Foundation) $6,017.25 $14.18 $2,260.39 $8,291.82 Wood, plastics and composites $2,716.42 $446.72 $2,595.58 $5,758.72 Openings $2,016.19 $- $546.00 $2,562.19 Plumbing and fixtures $299.05 $- $1,445.78 $1,744.82 Roof (with truss package on total cost) $5,020.98 $- $3,228.39 $11,249.37 HVAC System $4,159.46 $- $851.21 $5,010.67 Electrical $6,803.22 $- $8,392.86 $15,196.08 Fire Suppression $52.00 $- $29.00 $81.00 Thermal, moistures protection $757.61 $- $812.73 $1,570.34 Finishes $11,408.05 $8,094.97 $19,503.03 Specialties $2,500.00 $2,500.00 Documentation $2,000.00

Labor Taxes (25%) $8,020.85

Sales Taxes (6%) $2,729.26 Subtotal $98,222.11 O&P (10%) $9,822.21

TOTAL COST $108,044.32

Page 54: FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014.

Questions?