CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.

40
CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE

Transcript of CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.

Page 1: CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.

CVE 4070

Construction EngineeringConstruction EstimatingProf. Ralph V. Locurcio, PE

Page 2: CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.

Estimating Construction Work

Page 3: CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.

Estimating defined… A complex process involving the collection

of available information on the scope of a project, the expected resource consumption, and future changes in resource costs.

This information is synthesized in a visualization of the construction process and translated into an approximation of the final cost.

Page 4: CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.

Components of an estimate…

Systematic analysis of: Project components Equipment needed Construction methods Temporary work items Support activities Externalities

Page 5: CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.

Qualifications of an estimator… Extensive knowledge of:

Construction processes & methods Materials & methods Contracts & work practices Construction documents & details Background business factors Design & code requirements Verbal & written communications Good common sense & judgment

Page 6: CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.

Estimating Process Decision to bid Form the estimating team Estimate work plan

Type of estimate Procedures Documentation

Risk & contingency analysis Review & check the estimate Finalize the estimate

Page 7: CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.

Estimating & Bidding

KickoffMeeting

WorkPlan

EstablishStandards

UpdateDatabase

PrepareEstimate

DocumentEstimate

ReviewEstimate

Adjust Estimate?

SubmitBid

ProjectExecution

ProjectCompletion

Yes

No

Revise

Lessons Learned

Feedback to improve data base

Reality C

heck Yes

No

Page 8: CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.

Key Estimating Activities

Read the Plans, Specs & Contract

Conduct Site Visit

Decide Construction

MethodPrepare Schedule

Plan for Subcontracts

Plan for EquipmentMaterial Take-Offs

Estimate costs

Determine contingency

Analyze Risk Factors

Finalize Bid

Page 9: CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.

Two broad types of estimates… Conceptual

Used for early decisions & feasibility Rough estimate using minimal data Relies heavily on past data Level of accuracy about 70%

Detailed Used for major decisions; i.e. bids & budgets Based on final design documents Level of accuracy up to 95%

Page 10: CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.

Design 1 & 2 Estimates

Design 1 Design cost = detailed Construction cost = conceptual

Design 2 Design cost = actual Construction cost = detailed

Page 11: CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.

Conceptual Estimates-1

Based on historical data

Accuracy = +30%

Used for planning when no design exists

Used to check validity of detailed estimate

Sometimes called “parametric” estimates

Page 12: CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.

Conceptual estimates-2

Based on prior experience: Cost per SF or CF... volume Weight check… weight of equipment Cost-capacity factor- ratio of Q/$ Comparative cost of structure – $/unit

Feasibility estimates Appropriations estimates Time & location adjustments

Page 13: CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.

Comparative cost of structure… Basis is cost per unit based on past

experience with similar units. Compare structures of like construction, (e.g.

school: steel, concrete, quality, local labor, weather)

Develop cost per unit, e.g. A$/pupil = A Cost/A pupils =

$1,000,000/100 = $10k/pupil

Apply to new construction: B Cost = B pupils x A$/pupilB Cost = 200 x $10k = $2,000,000

Page 14: CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.

Examples:

Schools: $/pupil Bridges: $/feet of span Stadium: $/seat Hospital: $/beds Offices: $/ft2

Warehouses: $/ft3

Page 15: CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.

Variations of comparative cost…

Floor area… cost/ft2 … but Total horizontal area… all floors equal Finished floor area… $ based on type finish Cubic foot of volume… floor height varies

Plant cost ratio… process plant ratiodifferentiates machine ft2 from admin ft2

Page 16: CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.

Cost of equipment method…

Cost of equipment is dominant factor Estimate based on % of cost allocated to

equipment relative to total cost of facility Estimated cost is proportional to known cost of

equipment

Must adjust for time & location

Page 17: CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.

Plant Cost Ratio Method

Methods: Panel… hist data on “typical” panels Bay… hist data on “typical” bays Plant component… equip cost + other TPC = ET/(1-PT)

Where ET=equip total/(1-% all other costs) TPC = $$$ equip/(1-30%) = $500,000/.70 = $714,285

Page 18: CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.

Time & Location adjustments…

Cost indexing Based on similar “group” of key items Compare “group” over time or location Final cost based on ratio x calculated cost:

Est Cost = T2/T1 x Calc Cost

$500,000 = 1.00/.96 x $500,000 = $520,000 Costs have escalated by 4% from T1 to T2

Est Cost = (T2/T1)(L2/L1) x Calc Cost

$520,000 = 1.00/1.25 x $520,000 = $416,000Costs at L1 were 25% more expensive than L2

Page 19: CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.

Cost forecasting… “The future ain’t what it used to be”…

Yogi Berra Need to project costs to mid-point of the

construction year(s) for budgeting

Generally average past 2-5 years cost data & project forward @ 3-5% per year (inflation)

(Year 1) (Year 2)

$416,000 x 1.03 = $428,480 x 1.03 = $441,334

Page 20: CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.

Detailed estimates…

Based on three primary factors:

A. Quantities… resources

B. Constructability… methods

C. Risk… externalities

Page 21: CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.

A. Quantity factors…

Technology in project - complexity Milestone deadlines for work - timing Material & equipment - availability Staffing needed – skill & availability Contract terms – allocation of risk Amount of competition – markets Market fluctuation in materials, labor, equipment

Page 22: CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.

B. Constructability factors… Construction quality – skill required Allowable tolerances – productivity Complexity of design – learning curve Flexibility of methods – special terms Quality of plans & specs – unknowns

Page 23: CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.

C. Risk factors… Unspecified material or workmanship Differing site conditions Error in bidding Changes in cost over time Subcontractor error or failures Weather & environmental issues Strikes & labor issues Utilities & support issues

Page 24: CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.

Accuracy increases over time…

% Accuracy

% D

esi

gn

5%

5

%

5

0%

95

%

0 5 30 70 95 100

100

90

60

30

Page 25: CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.

Estimating process…

1. Determine project characteristics:Scope, Constructability, Risk

2. Examine the project design & site3. Structure the estimate 4. Determine elements of cost 5. Calculate estimate

Page 26: CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.

Examine Project Design… Technical specifications Referenced standards Project drawings Testing and performance Special methods or procedures Physical elements & site characteristics Errors & omissions

Page 27: CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.

Structure the estimate… Structure often follows specification template Ensure nothing left out Need a plan for completing the project Logical flow of resources & materials Productivity factors

Page 28: CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.

CSI Master Format-1

Page 29: CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.

CSI Master Format-2

Page 30: CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.

Determine elements of cost… Labor- craft & skill resources; sub-contractors;

union labor; wage rates; training; “effective” labor rates; productivity factors (weather, complexity, experience, management)

Material- price, shipping, availability, storage, relation to specifications

Equipment- purchase vs. lease, single use, down time, cost of maintenance

Capital- interest rates, payment flow, retainage Time- overhead costs, required completion date,

Page 31: CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.

Calculate the estimate… Material take-off from plans

1. Quantities of all construction materials2. Compare with specifications

Labor cost for construction or installation1. Effective labor rates2. Team composition & duration

Construction equipment schedule1. On hand vs. lease or purchase2. Time on job

Follow elements of cost1. Ensure all items are covered

Page 32: CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.

Babcock MS Project critique…

Score your own schedule Make sure your name is on the sheet Staple both together Turn-in

Page 33: CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.
Page 34: CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.

Scoring 1. Schedule must use MS Project 15

2. Schedule must be on 1-2 page; landscape format 15

3. Must use task sequencing & overlap per your Flow Diagram 15

4. All activities must be labeled with activity names to the right of the bar 5

5. All activities must show % complete to left of bar 5

6. All work must start on Janurary 12, 2015 10

7. All activities must be completed NLT April 10, 2015 10

8. All activity bars must be colored blue & use cross hatch pattern 5

9. Include 3 "phase" activities with black bars 5

10. Include the project title & your name in the heading 5

11. You must add the durations and show durations on the schedule 5

12. You may make adjustments to the schedule per your flow chart 5

Extra credit 100

13. Use of lead or lag precedence 10

14. Use of multi-colored bars 10

Note: The following items are required for full credit:

Page 35: CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.
Page 36: CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.
Page 37: CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.

Last Slide

Page 38: CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.
Page 39: CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.

Ethics Paper – due Nov 27

NSPE Rules of Professional Conduct Read all rules Summarize each of the obligations in one

paragraph Pick a case study: 1,7,58,59,60

Write a 2-page paper applying NSPE to the issues presented in the case

What errors were made, how should the engineer behave in the case

Page 40: CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.

Registration info for Spring

CVE 4074/5074 – see CRN 13795 Leading Construction Operations Syllabus:

1- Personal Leadership- your leadership style2- Organizational Leadership- corporate style3- Team Leadership- leading a team4- Includes segment on ethics5- Includes professional communications