FINAL DESIGN FOR
YORKTOWN HIGH SCHOOLINTERNAL MODIFICATIONSSchool Board Consent ItemMarch 8, 2018
Q U I N N E V A N S A R C H I T E C T S
2QUINN EVANS ARCHITECTS|Washington, DC
PROJECT SCHEDULE
EXHIBIT A
FINAL DESIGN1ST FLOOR – OVERALL PLAN
10. CONVERT COPY ROOM & WORKROOM INTO TEACHER COLLABORATION SPACE (PLC)
11. CONVERT COMPUTER ALCOVE INTO CLASSROOM
12. PROVIDING ACCESSIBLE BATHROOM IN MULTI-USE CLASSROOM
13. CONVERT STORAGE INTO BIKE STORAGE
14. ADD CHARGING STATIONS AND WALK-UP COUNTERS IN CAFETERIA
15. ADD CHARGING STATIONS AND WALK-UP COUNTERS IN ATRIUM
16. ADD FOLD-UP DIVIDER CURTAINS IN MAIN GYM
17. ADD FOLD-UP DIVIDER CURTAIN IN AUX. GYM
18. REPLACE EXISTING GYM LOCKERS
3QUINN EVANS ARCHITECTS|Washington, DC
EXHIBIT B
FINAL DESIGN2nd FLOOR – OVERALL PLAN
20. PROVIDE TEACHER WORKROOM AND DROP-IN AT NEIGHBORHOOD COMMONS
21. CONVERT OFFICES & CONFERENCE ROOM INTO MULTI-USE SMALL GROUP ROOM
22. ADD CHARGING STATIONS & WALK-UP COUNTERS IN NORTH CORRIDOR
23. RE-PURPOSE OFFICES & CREATE ADDITIONAL OFFICE
24. ADD CHARGING STATIONS AND WALK-UP COUNTER IN EAST CORRIDOR
25. CONVERT TEACHER WORKROOM & CLASSROOM INTO SCIENCE CLASSROOM
26. PROVIDE LOUNGE SEATING IN SCIENCE COMMONS
4QUINN EVANS ARCHITECTS|Washington, DC
EXHIBIT C
FINAL DESIGN3rd FLOOR – OVERALL PLAN
30. CONVERT TEACHER WORKROOM AND OFFICES INTO CLASSROOM
31. CONVERT TEACHER WORKROOM INTO CLASSROOM
32. CREATE MEETING ROOM & DROP-IN AT COMMONS
33. CONVERT EXISTING COMPUTER LAB & CLASSROOM INTO TWO CLASSROOMS
34. ADD CHARGING STATIONS & WALK-UP COUNTER IN EAST CORRIDOR
35. PROVIDE LOUNGE SEATING IN SCIENCE COMMONS
36. ADD OFFICE & LARGE MEETING ROOM IN TEACHER LOUNGE
37. CONVERT WORKROOM & OFFICE INTO PROFESSIONAL LEARNING CENTER & DROP-IN
5QUINN EVANS ARCHITECTS|Washington, DC
EXHIBIT D
PROJECT ESTIMATE & FUNDING
PROJECT ESTIMATE CONSTRUCTION COSTS $2,175,000 OWNER (SOFT) COSTS $1,500,000 CONTINGENCY $ 325,000 TOTAL PROJECT COST $4,000,000
PROJECT FUNDING CAPITAL RESERVE $4,000,000
6QUINN EVANS ARCHITECTS|Washington, DC
EXHIBIT E
RECOMMENDATIONS
APPROVE GENERAL LOCATION AND EXTENT OF INTERNAL MODIFICATIONS
APPROVE NEW BUILDING CAPACITY OF 2,189 SEATS
REAFFIRM $4 MILLION IN TOTAL FUNDING AVAILABLE FROM THE CAPITAL RESERVE
DIRECT STAFF TO SOLICIT BIDS FOR THE CONSTRUCTION WORK
7QUINN EVANS ARCHITECTS|Washington, DC
EXHIBIT F