Engineerin Economics Chapter (Eng. Eco) 015

download Engineerin Economics Chapter (Eng. Eco) 015

of 20

Transcript of Engineerin Economics Chapter (Eng. Eco) 015

  • 7/29/2019 Engineerin Economics Chapter (Eng. Eco) 015

    1/20

    Module No. 15

    Project ManagementMuhammad Shahid Iqbal

    Engineering

    Economics

  • 7/29/2019 Engineerin Economics Chapter (Eng. Eco) 015

    2/20

    What is a Project?

    A project is a sequence of unique, complex and connected

    activities having one goal or purpose that must be completed

    by a specific time, wthin budget and according to

    specification

    A project consists of interrelated activities which are to be

    executed in a certain order. The activities are interrelated in a

    logical sequence, which is known as precedence relationship.

    An activity cannot be started untill all its immediate

    preceding activities are completed.

    Some of the examples of the projects are given as:

  • 7/29/2019 Engineerin Economics Chapter (Eng. Eco) 015

    3/20

    Some Examples of Simple Projects

    Research Papers

    Tree Planting Campaigns

    Relief Collections

    Examinations

    Relocating

    Weddings

    Painting

    Parties

  • 7/29/2019 Engineerin Economics Chapter (Eng. Eco) 015

    4/20

    Some Examples of Complex Projects

    Bridges

    Ocean Liners

    Commercial Aircraft

    Olympic Games

    Nuclear Power

    Stations

    Man on the Moon

    Dams

    Skyscrapers

  • 7/29/2019 Engineerin Economics Chapter (Eng. Eco) 015

    5/20

    Major Projects in Pakistan

    Tarbela and Mangla

    Dams, Kalabagh

    Dam (?)

    Habib Bank Plaza, Muslim Commercial

    Bank Building

    Karakorum Highway, Islamabad-Lahore

    Motorway, Islamabad-Peshawar

    Motorway.

  • 7/29/2019 Engineerin Economics Chapter (Eng. Eco) 015

    6/20

    Major Projects in Pakistan

    Jinnah Intl Airport,

    Allama Iqbal

    International Airport,

    Karachi Nuclear

    Power Project,

    Chashma Nuclear

    Power Plant

    Turkmenistan to

    Pakistan Gas Pipeline,

    Iran to India (via

    Pakistan) Gas Pipeline

    Faisal Masjid

  • 7/29/2019 Engineerin Economics Chapter (Eng. Eco) 015

    7/20

    Major Projects in Pakistan

    (The Karakorum Highway, M1, M2 Motorways)

  • 7/29/2019 Engineerin Economics Chapter (Eng. Eco) 015

    8/20

    Project Management

    Project Management can be defined as : a method and a setof techniques based on the accepted principles ofmanagement used for planning, estimating and controllingwork activities to reach a desired end result on time

    within budget and according to specification. Project management is generally applied for constructing

    public utilities, large industrial projects and organizingmega events.

    Project management is considered to be an important field

    in production scheduling mainly because many of theindustrial activities can also be viewed as projectmanagement problems, like launching satellites,fabrication of boilers, construction of railway coaches,organizing R & D activities.

  • 7/29/2019 Engineerin Economics Chapter (Eng. Eco) 015

    9/20

    Many of the projects can be repeated by the same org. orby different organizations.

    The project schedule which is prepared for one projectcannot be applied for other projects without any

    modification because time estimates can be different dueto environment conditions.

    Project is represented in the form of a network for thepurpose of analytical treatment to get the solution forscheduling and controlling its activities.

    A network consists of a sets of arcs which are connectedmeaningfully through a set of nodes.

    The precedence relationship among various activities of aproject can be represented using a network.

    Project Management

  • 7/29/2019 Engineerin Economics Chapter (Eng. Eco) 015

    10/20

    Project Activity Sequencing & Scheduling

    Project Activity Sequencing is the prerequisite for

    developing the project schedule.

    The project schedule determines the planned start and finish

    dates for all project activities.

    It requires duration estimates for each project activity, and

    is most conveniently depicted pictorially in the form of a

    bar chart (the Gantt Chart), or the more informationaland

    much more complex - form of a Network Diagram

    There are two network diagramming techniques which are

    used in project management

    the precedence diagramming method

    the arrow-on-node method.

  • 7/29/2019 Engineerin Economics Chapter (Eng. Eco) 015

    11/20

    The Precedence Diagramming Method

    Precedence diagramming is a method of constructing

    project schedule network diagrams using boxes or

    rectanglesknown as nodesto represent individual

    project activities, and connects them with arrows to depict

    the dependencies between the project activities

    Activity A Activity B Activity C Activity A precedesActivity B whichprecedes ActivityC

    Activity X

    Activity Y

    Activity Z

    Activity X precedesboth Activities Yand Z

  • 7/29/2019 Engineerin Economics Chapter (Eng. Eco) 015

    12/20

    Phases of Project Management

  • 7/29/2019 Engineerin Economics Chapter (Eng. Eco) 015

    13/20

    Project Network Diagrams: The Node

    ACTIVITYDESCRIPTION

    ACTIVITYIDENTIFIER

    ACTIVITYDURATION

    ES EF

    LS LF

    SLACK

    The CRITICAL PATH of a project is the

    sequence of activities that determine the

    project completion date any delay in an

    activity or activities comprising the critical

    path will delay the project by a

    corresponding amount of time

    EARLY START: When can the activitystart at the earliest?

    EARLY FINISH: When can the activityfinish at the earliest?

    LATE FINISH: When can the activityfinish at the latest?

    LATE START: When can the activitystart at the latest?

    SLACK: The time forwhich the activity canbe delayed (also called

    float)

  • 7/29/2019 Engineerin Economics Chapter (Eng. Eco) 015

    14/20

    Koll Business Information Center

    Activity Description Preceding Activity

    Activity Duration

    A Approval of Application None 5

    B Construction Plans A 15

    C Traffic Study A 10

    D Service Availability Check A 5

    E Staff Report B, C 15F Commission Approval B, C, D 10

    G Wait for Construction F 170

    H Occupancy E, G 35

    Project Network Diagram Example: (Network

    Components and Details)

  • 7/29/2019 Engineerin Economics Chapter (Eng. Eco) 015

    15/20

    The Basic

    Network

    Structure

    Merge

    Activities

    Burst

    Activities

    A

    Approval of

    Application

    C

    Traffic Study

    D

    Service Avail-

    ability Check

    E

    Staff Report

    F

    Commission

    Approval

    B

    Construction

    Plans

    H

    Occupancy

    G

    Wait for

    Construction

    Project Network Diagram Example:

    (Graphical Depiction of the Network Components)

  • 7/29/2019 Engineerin Economics Chapter (Eng. Eco) 015

    16/20

    Project Network Diagram Example:

    (Determining the Forward Pass)

    Application

    Approval

    Construction

    Plans

    Traffic

    Study

    Service

    Check

    Commission

    Approval

    Staff

    Report

    Wait for

    Construction

    Occupancy

    A

    B

    C

    D

    F

    E

    G

    H

    5

    15

    10

    5

    10

    15

    170

    35

    50

    205

    155

    105

    3020

    3520

    20030

    235200

    Forward PassES + Duration = EF

    20

    15

    10

    20

    15

    200

    35

    5

    5

    5

    30

  • 7/29/2019 Engineerin Economics Chapter (Eng. Eco) 015

    17/20

    Application

    Approval

    A

    5

    Project Network Diagram Example:

    (Determining the Backward Pass)

    Construction

    Plans

    B

    15

    Traffic

    Study

    C

    10

    Service

    Check

    D

    5

    Commission

    Approval

    F

    10

    Staff

    Report

    E

    15

    Wait for

    Construction

    G

    170

    Occupancy

    H

    35

    50

    205

    155

    105

    3020

    3520

    20030

    235200

    Backward PassLS + Duration = LF

    50 10 20

    205

    2015

    3020

    200185

    20030

    235200

    20

    20

    20

    200

    5

    10

    15

    30

    200185

    185

  • 7/29/2019 Engineerin Economics Chapter (Eng. Eco) 015

    18/20

    Application

    Approval

    A

    5

    Project Network Diagram Example:

    (Determining Slack and the Critical Path)

    Construction

    Plans

    B

    15

    Traffic

    Study

    C

    10

    Service

    Check

    D

    5

    Commission

    Approval

    F

    10

    Staff

    Report

    E

    15

    Wait for

    Construction

    G

    170

    Occupancy

    H

    35

    50

    205

    155

    105

    3020

    3520

    20030

    235200

    50 10 20

    205

    2015

    3020

    200185

    20030

    235200

    Slack = LS ESSlack = LF - EF

    0

    0

    5

    10

    0

    165

    0

    0

  • 7/29/2019 Engineerin Economics Chapter (Eng. Eco) 015

    19/20

    3. Gantt Chart

    A scheduling chart developed by Hanry Gantt that

    shows actual and planned output over a period of time.

    A bar graph with time on the horizontal axis andactivities to be accomplished on the vertical axis

    Shows the expected and actual progress of various

    tasks

  • 7/29/2019 Engineerin Economics Chapter (Eng. Eco) 015

    20/20

    Copy-edit manuscriptDesign sample pagesDraw artworkPrint first pagesPrint final pagesDesign cover

    1 2 Month

    Reporting Date

    Activity3 4

    Actual progressGoals