Drouin Recreation Plan - Shire of Baw Baw...Drouin township to the year 2030. This Plan was adopted...
Transcript of Drouin Recreation Plan - Shire of Baw Baw...Drouin township to the year 2030. This Plan was adopted...
Drouin Recreation Plan
Drouin Recreation Plan
Progress Report
September 2018
2
Table of Contents
1. Introduction ................................................................................. 3
2. Facilities Plan .............................................................................. 4
Drouin Township 4
Bellbird Park (includes Indoor Stadium Concept Plan) 6
Drouin Recreation Reserve 12
Balmoral Park 15
3. Financial and Implementation Plan............................................ 18
3
1. Introduction
The Drouin Recreation Plan was developed to provide a policy position and clear direction for the provision of sport and recreation facilities and opportunities for the Drouin township to the year 2030. This Plan was adopted by Council on 12 August 2009. During 2013/2014, Council undertook a review of recreation masterplans, with the amended document being adopted by Council on 10 December 2014. The Recreation Strategy 2017-2027 contains the following recommendation “E9- Review all Recreation Reserve Master Plans every four (4) years to update outstanding recommendations and to ensure they are still relevant.” A review of these documents every four years coincides with the term of office for Councillors. A review mechanism also ensures they remain current and able to meet the changing needs and expectations of Council, clubs and the broader community. This document shows original masterplans for each site (2009), updated masterplan maps where appropriate (2014), discusses known current issues and provides a progress report on projects in the implementation plan. During 2018/2019, a review of recreation master plans will be undertaken with community and stakeholder consultation, assessment of merit of identified projects, prioritisation of projects and further consultation at the Draft stage. This plan considers the sport and recreation opportunities at Council reserves and schools within Drouin with a particular focus on sport and recreation facilities located at the following active reserves in Drouin:
• Bellbird Park
• Drouin Recreation Reserve
• Balmoral Park
4
2. Facilities Plan
Drouin Township
6
Bellbird Park (includes Indoor Stadium Concept Plan)
Master Plan Review Summary
Between 2009 and 2014, the following progress was made on the Plan:
• New synthetic sports facility with competition lighting
• Major upgrade of oval including drainage, irrigation, a sand-based surface and turf wicket
• New timber floor on court 2 of the Bellbird Park Stadium
• Drainage installed on both the senior and junior soccer fields
• Security lighting in car parks
• Feasibility assessment and construction specifications completed for irrigation of sports grounds with treated effluent from Gippsland Water sewerage treatment facility.
• Walking path link around the wetland
• Council purchased land at Lardner to develop a municipal equestrian facility, with the intent that the Drouin Pony Club and West Gippsland Adult Riders will relocate to this site.
• Ecological assessment of native vegetation
• Redevelopment of picnic/ BBQ and play facilities Between 2014 and 2018, the following progress has been made on the Plan:
• On 27 May 2015, Council resolved to rezone Lots 85 and 86 Blackwood Court and Lots 69 and 70 Forrest Street, Drouin to Public Park and Recreation Zone. These sites are now known as Blackwood Court Reserve and Forrest Street Reserve.
• The Drouin Pony Club and West Gippsland Adult Riders relocated to the new Baw Baw Equestrian Centre at Lardner.
• The soccer change rooms were refurbished to include female change, first aid room, umpires room and improved accessibility.
• New drainage and automatic irrigation systems were installed across all grass playing surfaces at Bellbird Park, utilising reclaimed water.
• New gate entrance and spectator area has been built to the east side of the synthetic facility.
• Cricket nets have been expanded to include four fully enclosed nets with retractable netting to provide a multi-purpose space and one public net.
• The Baw Baw Shire Indoor Stadium Feasibility Study was completed including an option for an additional two courts at Bellbird Park.
• A funding application is pending for the provision of match lights for both the senior and junior soccer pitches.
• Funding has been received to install new lighting to the oval to achieve training standard (50 lux), with the capacity to upgrade to 100 lux in the future. This project is to be delivered in the 2018-2019 financial year.
Current issues/ opportunities that we are aware of and will be subject to discussion as part of the 2018/2019 review include:
• Suggestion of fencing between soccer field and car park • A proposal by hockey and soccer for a new shared pavilion with views of both the
synthetic field and senior soccer pitch. Suggestion that this would include a
7
function space (200 people) with flexible walls to accommodate two clubrooms or one larger space for functions, further 2 change rooms for hockey (at Rumble pavilion or other), two canteens/ kitchens/ pantries, internal and external toilets and a veranda with views.
• Proposed strategic facilities plan for hockey
The original and amended versions of the masterplan follow, along with plans for the Indoor Stadium.
Bellbird Park Master Plan Summary:
Hockey / Soccer Facility (Eastern Section)
• Soccer �eld 1 with sports �eld �oodlighting for training
• Hockey hybrid synthetic �eld 1 with sports �eld �oodlighting
• New multi purpose shared sports pavilion to service both soccer and
hockey.
• Remove the access road o� Lampard Road.
• Create access road to the Bellbird Park sporting precinct o� Settlement
Road
• Junior soccer �eld, natural grass.
• Retain/expand existing car park with security lighting to
accommodate requirements of soccer and hockey �elds. Retain trees
in the car park where possible with a priority for retaining signi�cant
trees
• Multi purpose �eld 1 to accommodate hockey competition and soccer
training / junior competition. Surface to be natural (or a low quality
synthetic) with a long term view to install a second hybrid sports �eld
and consideration for sports �eld lighting.
• Multi purpose �eld 2 the size of a soccer �eld to accommodate soccer
and hockey competition. Natural grass.
• Multi purpose �eld 3 the size of a hockey �eld to to accommodate
soccer and hockey. Natural grass.
• Appropriate sub drainage works to address the excessive water on the
sports �elds.
• Retain this built structure as a storage facility for hockey and soccer if
there is a use for it.
• Following botanist's report about signi!cance and condition of trees,
signi!cant trees and maximum vegetation will be retained wherever
possible. Also recommend increased planting right across this portion
of Bellbird Park.
• Consideration of minor play/picnic opportunities for hockey and soccer
families to complement the district level playground and facilities in a
central location of Bellbird Park.
• Indicate continuous and increased landscape bu"er along Lampard
Road.
Sports Field / Indoor Stadium (Western section)
• Additional car parking with security lighting.
• Security car parking lighting.
• Developments and improvements to the Indoor Stadium as per the
Bellbird Park Indoor Stadium Concept Plan.
• Consider the recommendations from the Bellbird Park Water
Conservation Feasibility Study.
• Extend the vegetation to create a link and connection. Investigate
potential for vegetation o�set planting.
• Establish a path network throughout Bellbird Park including the
vegetation area.
• Retain equestrian facilities at Bellbird Park until the future site for the
Drouin Pony Club, Warragul Pony Club and other equestrian activities
is determined.
• Convert the site occupied by the Drouin Pony Club to open space area
with appropriate landscaping and vegetation when the Club is
relocated to a new site (yet to be determined).
Existing Infrastructure
Proposed Infrastructure
Proposed Car Parking
Vehicle Access
Upgraded and Proposed
Pedestrian Paths
Proposed Sports Facility
Proposed Vegetation
Existing Sport Facility
Green Open Space
Existing Equestrian Facility
Proposed Pond Expansion
Floodlighting
• Potential for future turf wicket should a demonstrated need be
identi�ed and subject to a sustainable water supply.
• Relocate and upgrade playground to district level with associated BBQ
and picnic facilities
• Investigation of the option to close Settlement Road at both ends of
Bellbird Park or create a shared space for local vehicles and pedestrians.
• Expanded pond area for 14,000 cubic metres storage - Stormwater
Harvesting - Direct Pond Extraction
J U N E 2 0 0 9
Drouin Recreation Plan:
Bellbird Park
N
0 10 20 50 100m
1
1
2
2
4
5
4
6
5
7
6
8
7 9
8
11
11
10
11
12
13
14
15
16
17
18
19
20
21
22
23
2119
20
17
18
9
3
3
22
23
10
16
16
27
SHILLINGLAW ROAD
LAMPARD ROAD
SE
TT
LE
ME
NT
R
OA
D
24
25
26
27
12
13
14
15
24
25
26
Squash
3x Cage Store
Change
T/S
Gymnasium
Control
Office
Store
KitchenFoyer M.P
Room
F MEntry
Spectators
New Pigeonholes
for ball storage
Remodel Kitchen St.
Circulation
M
Ba
r /
Kit
che
n
Office
Remodel Kitchen
to make bigger
F
Upper
Squash
Down
UPPER LEVEL
Viewing
Gallery
Ve
ran
da
h
View
Existing Viewing
Area
Function Room 1
Exisiting
Sports
Ground
Squash
Squash
Change
SquashExisting Sports
Court 1
Existing Sports
Court 2
Store
Function Room 2
T/S
Manager’s
Office
Extend space to double
potential function space
Sports
Association
Office
F
Disabled
Amenities
Circulation
Kitchen
Bi-Fold Doors
T/S
Change
Timekeepers &
ScoreboardV
era
nd
ah
Open Social/
meeting space
M
F
Ex. Public Toilets
View
View
Storage
Future glass wall
to squash courts
Store
Date: 04 June 2009
Scale 1:250
Drg. No. SK04
Job No. 5154
Drouin Recreation Plan
Bellbird Park Stadium Masterplan
Copyright
Architects
Victoria Australia
East Melbourne 3002
www.sutersarchitects.com.au
Facsimile 613 9418 3344
Telephone 613 9418 3333
Level 6 232 Victoria Parade
0 1 5 10 20
metres
Baw Baw Shire Council Indoor Stadium Feasibility Study Update Modelling Draft Report 30/05/18 Page 40
5.6.2 Bellbird Park Court Extension
12
Drouin Recreation Reserve
Master Plan Summary
Between 2009 and 2014, the following recommendations were implemented:
▪ Redevelopment of netball courts 1 and 2 including new lighting and shelters
▪ New pavilion for football and netball change rooms, canteen, gym and public toilets. Old buildings have been demolished.
▪ Oval irrigation system and minor drainage and resurfacing works
▪ New BBQ rotunda
▪ Pedestrian path links including the Path of Achievement
▪ Electronic scoreboard
Between 2014 and 2018, the following progress has been made on the Plan:
▪ A water fountain has been added to the rotunda ▪ Oval lighting was upgraded to match standard (100 lux) ▪ Funding has been received to upgrade netball courts 3-6 ▪ Old cricket nets have been decommissioned with space now available for parking
and a new cricket net has been installed
•
1
1
2
2
4
4
16
VICTORIA STREET
SINCLAIR
STREET
GR
AN
T S
TR
EE
T
• Implement the current master plan (2007) with the
following conditions.
• Future review of the use of this stadium to maximise
multi-use of indoor facilities.
• Existing netball courts to be extended to comply with
Netball Australia requirements.
• Proposed car park
• Pedestrian access to the reserve from Victoria Street
• Playground to remain in current location.
• Pedestrian and vehicle access should be via a lockable
gate to enable access control. Vehicle access road to
be sealed.
• Existing buildings to be replaced with a single building
• Existing cricket nets
• Retain public open space and allow informal overflow
car parking
• Relocate fence
• Scoreboard - use this facility for storage or remove
Upgraded and Proposed
Pedestrian Paths
Upgraded Sports Facility
Proposed Vegetation
Existing Sport Facility
Green Open Space
Relocated Fence
Existing Infrastructure
Proposed Car Parking
Vehicle Access
Existing Infrastructure to
be replaced
Drouin Recreation Reserve Master Plan Summary:
M A Y 2 0 0 9
Drouin Recreation Plan:
Drouin Recreation Reserve
N
0 5 10 25 50m
1
2
3
2
1
4
6
7
8
9
3
3
3
3
3
3
5
4
5
6
7
8
10
11
12
9
12
11
10
15
Balmoral Park
Master Plan Summary
Between 2009 and 2014, the following progress was made on the Plan: ▪ The two asphalt tennis courts were redeveloped with a plexipave surface ▪ New fencing for four courts (courts 5-8) ▪ Renewed synthetic surface on four courts ▪ All courts now lit, with new lighting for courts 1-4 ▪ Funding for renewal of the remaining two synthetic courts was announced in
November 2014. ▪ In 2014, the Drouin Tennis Club participated in an independent assessment of a
potential multi-sport club (bowling, golf and tennis) to operate out of the golf club site in Drouin.
Between 2014 and 2018, the following progress has been made on the Plan:
▪ Courts 3 and 4 have been renewed ▪ Lighting on courts 5-8 has been upgraded to meet competition standard ▪ New fencing for remaining courts 1-4
Current issues/ opportunities that we are aware of and will be subject to discussion as part of the 2018/2019 review include:
▪ Preliminary designs for a pavilion refurbishment to include an accessible toilet, kitchen/ canteen upgrade, increased clubroom space, an office and storage. Please refer to the design below.
O C T O B E R 2 0 0 8
Drouin Recreation Plan:
Balmoral Park Tennis Facility
N
0 5 10 20m
Existing Sports Facility
Proposed Vegetation
Existing Infrastructure
Master Plan Summary:
1
5
5
1
2
3
4
6
7
2
3
4
6
7
BE
NN
ETT S
TR
EE
T
31 Bennett Street Drouin
as noted @ A3Alterations & Additionsfor Drouin Tennis Pavilion
PRELIMINARY DRAWINGS ONLYNOT TO BE USED FOR CONSTRUCTION
Preliminary Design Rev B
C:\Users\Graeme\Archicad\Drawings\2016\1613 Drouin Tennis Club\1-Model\1613 Drouin Tennis Club Proposed Rev B.pln
GRAEME PARKERCONSULTING
86 CHARLES STWARRAGUL, VIC, 3820phone: 5623 2534fax: 5623 2534mob: 0488 142 227email: [email protected]: http://buildingdesigned.wix.com/warragul
REV
PRO
JEC
T:
REVISION DESCRIPTION DATE
REVPROJECT No:
DRAWN BY:
SCALE:DATE:
G. PARKER
30/04/2016
1613DRAWING No:
PD-2/07
Design and Documents under copyright.Do not reproduce without written
ALL DIMENSIONS AND LEVELSTO BE CHECKED AND VERIFIEDBEFORE WORK COMMENCES
authorisation from Graeme Parker.PLOT DATE: 28/05/2016
DP-AD 28770
PRELIMINARY DRAWINGS ONLYNOT TO BE USED FOR CONSTRUCTION
1000
x 1
000
1000
x 1
000
400 x 1600
920
920
920
920
920
920
920
920
920
PROPOSED FLOOR PLANSCALE 1:100
f.w.
f.w.
ME
TER
BO
X
METERBOX
f.w.
NorthPD-4
SouthPD-5
EastPD-4
WestPD-5
230 3030 230 10060 230
3370
9024
1023
050
0023
0
10000 3260 16060
6100
5230
4200
3260 10520 5540
6100
3180
2050
1500
19320
1133
0
2830 7230 90 3090 90 2260 240
5140
9041
1090
5200
230 6000 90 7230 90 1700 90 1800 20 92020
900 230
3030 230 2740 5450
230
5640
1620
2011
3590
1620
2011
3520
900
9021
6024
020
1090
5640
230
5000
230
1087
023
0
90 3170
19320
13780
5640
230
90 3333 90 3333 90 3333 90 3333 90 2680 90 2680 90
0.0
-100.0
-550.0
50mm DIA. GALV. STEEL HANDRAILS TOSTAIR, RAMP & LANDINGS 50mm DIA
STAUCHONS OR SIMILAR APPROVEDDESIGNED BY OTHERS
50mm DIA. GALV. STEEL HANDRAILS TOSTAIR, RAMP & LANDINGS 50mm DIASTAUCHONS OR SIMILAR APPROVEDDESIGNED BY OTHERS
CLUBROOMS
KITCHEN
SINKOVEN
REF
UNISEXDISWC
SHWR
STO
RA
GE
PROPOSED MULTIUSE ADDITION
PROPOSEDADDITION
PROPOSEDUNDERCOVER
AREA
DENOTES EXISTING WALLS DEMOLISHED & EXISITNG WINDOWS TO BE REMOVED
DENOTES EXISTING WALLS TO REMAIN
DENOTES PROPOSED STUD WALLS
DENOTES PROPOSED MASONRY WALLS
WALL LEGEND
PROPOSEDCONCRETE HIT UP PAD
2.1x
1.8
RO
LLE
R D
OO
R
NGL -55
0
PROPOSEDUNDERCOVER
AREA
CL 2850
CL3220
REL
OC
ATEOFFICE
DP
EXISITNG CONDITIONS
CONCRETE RAMP DOWNMAX. GRADIENT 1:14
CONCRETE RAMP UPMAX. GRADIENT 1:14
TACTILE INDICATORS ARE TO BEPROVIDED TO THE TOP AND BOTTOMOF STAIRS & RAMPS AS PER AS1428.1.
HANDRAIL & KERB
HANDRAIL & KERB
HANDRAIL & KERB
HANDRAIL & KERB
UPCONCRETE
STAIR
STAIR DETAILSFL-FL 450mm
3 RISERS @ 150mmGOING MIN 250mm
CANTEEN
REF
REF
AM
BU
LAN
TW
C
WC
MALE
FEMALE
URINAL
AIRLOCK
SHWR
AM
BU
LAN
TW
C
V'DAH
100m
m S
TEP
SLAB CONSTRUCTION:100mm THICK CONCRETE SLAB.
MESH. 30mm TOP COVER.0.2 POLYTHENE MOISTURE BARRIERS BENEATH
(REFER ENGINEERS DESIGN FOR DETAILS)
LATHAM ASBRALOY CAST IN PLACESTAIR TREAD NOSINGS INSTALLED TOMANUFACTURERS SPECIFICATIONS
AERA ANALYSIS
010203
AreaExisitng Floor AreaProposed Addition AreaProposed Covered Area
Area sqm97.9773.1076.46
247.53 m²
N
18
3. Financial and Implementation Plan
The implementation of the Drouin Recreation Plan will be dependent on available funding and the priorities of funding partners. This Plan is one of many recreation plans across the municipality and represents only a small section of Council’s total asset groups. In order to reduce the overall financial commitment required from Baw Baw Shire, external funding opportunities and contributions will be explored from all potential stakeholders including clubs / associations, developers, schools, Committees of Management, Government Departments and associated authorities. The financial commitments outlined below are indicative estimates only and may change following detailed design works. Cost escalations should be considered. The actions were prioritised as part of the 2014 consultation process into high, medium or low priority rankings. As part of the 2018 review, incomplete and any new projects will be scored and prioritised on a Shire-wide basis using the ‘Facility Prioritisation Assessment Framework’ from the Recreation Strategy 2017-2027. Projects have been colour coded indicating those actions that have been completed (green), in progress (orange) and not commenced (red).
19
Actions
High
Medium
Low
Indicative
Cost/ Comment
Bellbird Park
Eastern Section
Detailed design, including botanist and vegetation plan for Bellbird Park
Complete
Develop multi-purpose field – hybrid facility with floodlighting (masterplan ref no. 2)
Complete $902,137
Develop path network connecting sporting fields, car park and new pavilion
Complete
Redevelopment of casual picnic/BBQ and play facilities
Complete
Refurbish existing change room to add female change and disabled toilet
Complete $195,000
Replace soccer clubrooms $460,000
Provide connectivity between Reserve and Blackwood Court and Forrest/ Boronia Streets
✓ No longer required- zoned
PPRZ
Upgrade soccer field lights to meet training standard, with the capacity to upgrade to match lights in the future
✓ Funded to match standard for both
soccer pitches. To be delivered
in 18/19. Approx $420,000
Future expansion of existing car park as required to cater for growth
✓ $150,000
Retain multi-purpose fields in natural grass, with a long term view to install a hybrid surface and consideration of lighting
✓ -
Undertake sub drainage works to address the excessive water on sports fields
Complete
Move gate entrance and spectator area of synthetic facility to east
Complete $20,389
Update/ refurbish hockey pavilion to meet relevant sports standards, including social facilities
✓ $650,000
Undertake maintenance of vegetation ✓ Ongoing- operating budget
Sub Total $1,280,000
Western Section
Security lighting to existing car park Complete
Relocate and develop district playground with picnic and BBQ facilities
Complete
Extension of the path network Complete
20
Actions
High
Medium
Low
Indicative
Cost/ Comment
Irrigation of oval Complete
Resurfacing of oval Complete $561,133
Future turf wicket on oval Complete $28,058
Purchase new land and relocate equestrian activities as per the Equestrian Strategy
Complete $602,000
Additional car parking with security lighting Complete $61,573
Implement recommendations from the Bellbird Park Water Conservation Feasibility Study
Complete $950,000
Upgrade oval lighting to training standard Funded- to be delivered in
18/19 $228,200
Convert the site occupied by equestrian to open space, which can cater for future growth and need for sporting fields if required
Complete
Future expansion of cricket net facilities Complete $174,000
Sub Total -
Stadium
Replace floor of Court 2 Complete $186,295
Investigate feasibility of further indoor sports courts Complete $49,600
Detailed design of Indoor Stadium Concept Plan ✓ $100,000
Stadium upgrade construction ✓ $2,000,000
Bellbird Park Stadium Upgrade $2,100,000
Total Bellbird Park Completed Works $4,563,180
Total Bellbird Park Outstanding Works $3,380,000
Drouin Recreation Reserve
Site preparation and demolition Complete
Netball courts (1 and 2) redevelopment
Complete $209,345
Oval irrigation
Complete $73,278
New pavilion
Complete $1,115,252
21
Actions
High
Medium
Low
Indicative
Cost/ Comment
New pedestrian paths
Complete $62,304
Plaques for path of achievement Complete
New netball shelters and relocation of existing Complete
Relocation of mesh fencing and new fencing Complete
Gates- pedestrian and vehicular Complete
Scoreboard Complete
Oval surface upgrade, including drainage ✓ $435,000
Lighting upgrade to remaining 4 netball courts to match standard
✓ $70,000
Extend group of 4 existing netball courts to comply with Netball Victoria requirements and consider seating. Stage 1- Courts 3 & 4 Stage 2- Courts 5 & 6
Funded $600,000
Lighting upgrade to oval to training standard
Complete $151,542
Vehicle access road to be sealed and include drainage
✓ $400,000
Water fountain for rotunda Complete
Gravel overflow car park off Victoria Street with a defined in and out
✓ $75,000
Seal and line mark car park near netball and badminton
✓ $145,000
Decommission cricket nets
Complete with one new net constructed
$46,535
Total Drouin Recreation Reserve Completed Works
$2,258,256
Total Drouin Recreation Reserve Outstanding Works
$1,125,000
Balmoral Park
Replace tennis court fencing- courts 5-8
Complete $22,825
Upgrade two asphalt tennis courts to acrylic
Complete $27,992
Installation of floodlighting to remaining four tennis courts
Complete
$27,800
Replace tennis court surfaces at the end of their current life (courts 3 and 4)
Complete
$35,859
22
Actions
High
Medium
Low
Indicative
Cost/ Comment
Replace and/ or repair tennis court fencing- courts 1-4
Complete
$22,000
Pavilion refurbishment ✓ $80,000
Upgrade lighting to courts 5-8 and ensure all meet competition standard
✓ $85,000
Total Balmoral Reserve Completed Works
$221,476
Total Balmoral Reserve Outstanding Works
$80,000
Total Drouin Recreation Plan Completed Works
$7,042,912
61%
Total Drouin Recreation Plan Outstanding Works
$4,585,000
39%
Legend
Project completed
Project commenced- refer to comments for detail
Project not started