GLAST LAT Project DOE Review, February 18, 2005
4.1.7 DAQ & FSW V1 1
GLAST Large Area Telescope:GLAST Large Area Telescope:
G. HallerSLAC
[email protected](650) 926-4257
Gamma-ray Large Gamma-ray Large Area Space Area Space TelescopeTelescope
DOE Review DOE Review 4.1.7 DAQ 4.1.7 DAQ
![Page 2: DOE Review 4.1.7 DAQ](https://reader035.fdocuments.net/reader035/viewer/2022081508/56815009550346895dbde1fe/html5/thumbnails/2.jpg)
GLAST LAT Project DOE Review, February 18, 2005
4.1.7 DAQ & FSW V1 2
ContentsContents
• Overview - Production & Testing - Schedule– TEM/TPS Flight Units – PDU Flight Units – GASU Flight Units– SIU/EPU Flight Units
• Testbed• Installation & Test Support• Budget
![Page 3: DOE Review 4.1.7 DAQ](https://reader035.fdocuments.net/reader035/viewer/2022081508/56815009550346895dbde1fe/html5/thumbnails/3.jpg)
GLAST LAT Project DOE Review, February 18, 2005
4.1.7 DAQ & FSW V1 3
LAT ElectronicsLAT Electronics
3 Event-Processor Units (EPU) (2 + 1 spare)
– Event processing CPU– LAT Communication Board– SIB
ACD
empty
EPU-3
EPU-2EPU-1
empty empty
Power Dist. Unit*
GASU*
empty
empty
SIU*SIU*
Spacecraft Interface Units (SIU)*
– Storage Interface Board (SIB): Spacecraft interface, control & telemetry
– LAT control CPU– LAT Communication
Board (LCB): LAT command and data interface
16 Tower Electronics Modules & Tower Power Supplies
* Primary & Secondary Units shown in one chassis
Power-Distribution Unit (PDU)*
– Spacecraft interface, power
– LAT power distribution
– LAT health monitoring
Global-Trigger/ACD-EM/Signal-Distribution Unit*
TKR
CAL
TKR Front-End Electronics (MCM)ACD Front-End Electronics (FREE)
CAL Front-End Electronics (AFEE)
![Page 4: DOE Review 4.1.7 DAQ](https://reader035.fdocuments.net/reader035/viewer/2022081508/56815009550346895dbde1fe/html5/thumbnails/4.jpg)
GLAST LAT Project DOE Review, February 18, 2005
4.1.7 DAQ & FSW V1 4
TEM/TPS Mounted to CAL TEM/TPS Mounted to CAL
LAT GRID with 16 CAL/TEM/TPS Modules
TEM
TPS
CAL
TKR not shown
![Page 5: DOE Review 4.1.7 DAQ](https://reader035.fdocuments.net/reader035/viewer/2022081508/56815009550346895dbde1fe/html5/thumbnails/5.jpg)
GLAST LAT Project DOE Review, February 18, 2005
4.1.7 DAQ & FSW V1 5
Tower Electronics Module (TEM) before coating/staking
• Tower Electronics Module: Main DAQ module, one on each tower
– Controls and reads out data from TKR MCM and CAL AFEE front-end electronics
– Assembles CAL and TKR event fragments to tower event
Tower Electronics Module/Tower Power SupplyTower Electronics Module/Tower Power Supply
• Tower Power Supply module, one on each tower– Input 28V– Generates low-noise voltages for
• TKR (2.65V analog, 2.65V Digital)• CAL (3.3V analog, 3.3V digital)• TEM (3.3V and 2.5V digital)• TKR Bias (20V-140V programmable)• CAL (20V to 90V programmable)
Tower Power Supply (TPS) before coating/staking
Shown upside-down
TEM
TPS
![Page 6: DOE Review 4.1.7 DAQ](https://reader035.fdocuments.net/reader035/viewer/2022081508/56815009550346895dbde1fe/html5/thumbnails/6.jpg)
GLAST LAT Project DOE Review, February 18, 2005
4.1.7 DAQ & FSW V1 6
TEM/TPS Status & ScheduleTEM/TPS Status & Schedule
• Status– Three Flight Tower-Electronics Modules/Tower Power Supplies
received• Fully assembled• Thermal-cycled• Vibration tested (one of them to qualification levels)• One unit finished thermal-vacuum testing• One unit in thermal-vacuum testing• Both units finished EMI/EMC testing• No issues/problems
– Balance of 19 TEM/TPS in surface-mount assembly at vendor• Schedule
– 2/17/05 First TEM/TPS to I&T– 2/25/05 Second TEM/TPS to I&T– 4/1/05 Third TEM/TPS to I&T– 4/22/05 Fourth TEM/TPS to I&T
• One week lag between delivery of consecutive assemblies– 7/26/05 Last TEM/TPS to I&T
![Page 7: DOE Review 4.1.7 DAQ](https://reader035.fdocuments.net/reader035/viewer/2022081508/56815009550346895dbde1fe/html5/thumbnails/7.jpg)
GLAST LAT Project DOE Review, February 18, 2005
4.1.7 DAQ & FSW V1 7
PDU & GASU Mounted on LAT PDU & GASU Mounted on LAT
GASU
PDU
![Page 8: DOE Review 4.1.7 DAQ](https://reader035.fdocuments.net/reader035/viewer/2022081508/56815009550346895dbde1fe/html5/thumbnails/8.jpg)
GLAST LAT Project DOE Review, February 18, 2005
4.1.7 DAQ & FSW V1 8
EM PDU enclosure with primary/redundant PDU circuit cards, no coating/staking
• Primary and Redundant Circuits in one Enclosure– Receives Primary and Redundant 28-V from spacecraft– Each, primary and redundant PDU can select between
primary and redundant spacecraft power– Filters 28V– Turns on/off 28V to 16 towers and 3 EPU’s under
program control– Protects PDU and down-stream circuits from over-
current and under-voltage • Over-current via poly-switches• Under-voltage via custom circuit in each power-
on branch – Receives command/clock from GASU– Digitizes voltages/temperatures from > 150 sources
• Includes temperatures from radiators, GRID; used for thermal control
– Reads back data to SIU via GASU– Provides PDU DAQ voltage and temperature analog
data to spacecraft for monitoring
Power Distribution Module (PDU)Power Distribution Module (PDU)
![Page 9: DOE Review 4.1.7 DAQ](https://reader035.fdocuments.net/reader035/viewer/2022081508/56815009550346895dbde1fe/html5/thumbnails/9.jpg)
GLAST LAT Project DOE Review, February 18, 2005
4.1.7 DAQ & FSW V1 9
PDU Status and SchedulePDU Status and Schedule
• Status– Design/documentation complete– Enclosures fabricated– All parts received (except recalled International Rectifier
regulator, due end of February)– Assembly contract awarded– All parts kitted and audited by assembly vendor– Assembly started
• Schedule for Flight Unit– 5/15/05 Precoat PDU assembly ready for electrical test– 5/30/05 Complete assembly ready for environmental test– 7/1/05 Flight PDU to I&T
![Page 10: DOE Review 4.1.7 DAQ](https://reader035.fdocuments.net/reader035/viewer/2022081508/56815009550346895dbde1fe/html5/thumbnails/10.jpg)
GLAST LAT Project DOE Review, February 18, 2005
4.1.7 DAQ & FSW V1 10
PDU enclosure with primary/redundant PDU circuit cards, no coating/staking
• Primary and Redundant Circuits in one Enclosure– Contains two types of circuit card assemblies
• GASU Power Supply CCA• GASU DAQ Board CCA
– GASU Power Supply• Receives 28-V supply voltages for
– Primary and redundant DAQ board, generates 3.3V and 2.5v
– ACD FREE cards» Filtering
for 28-V» 3.3V regulation
– GASU DAQ Board• Contains 9 FPGA’s• Includes Command Response Unit, Fan-out and
fan-in of commanding to 16 TEMs, PDU, EPU’s, ACD
• Includes Global Trigger Logic• Includes LAT Event-Builder Logic• Includes command/control/read-back for ACD
sub-system• Includes power-control for ACD FREE Boards
GASUGASU
![Page 11: DOE Review 4.1.7 DAQ](https://reader035.fdocuments.net/reader035/viewer/2022081508/56815009550346895dbde1fe/html5/thumbnails/11.jpg)
GLAST LAT Project DOE Review, February 18, 2005
4.1.7 DAQ & FSW V1 11
GASU Status and ScheduleGASU Status and Schedule
• Status– Design/documentation complete– Enclosures fabricated– All components/parts received – Assembly contract awarded– Parts being kitted– Flight assembly to start 3/10/05
• Schedule for Flight Unit– 5/20/05 Precoat GASU assembly ready for electrical test– 6/10/05 Complete assembly ready for environmental test– 7/13/05 Flight GASU to I&T
![Page 12: DOE Review 4.1.7 DAQ](https://reader035.fdocuments.net/reader035/viewer/2022081508/56815009550346895dbde1fe/html5/thumbnails/12.jpg)
GLAST LAT Project DOE Review, February 18, 2005
4.1.7 DAQ & FSW V1 12
SIU/EPUSIU/EPU
Enclosure Backplane
Power-SupplyCPU
SIB
LCB
• Spacecraft Interface Unit (SIU)• Event Processor Unit (EPU)• Difference is boot code loaded into RAD750 CPU
![Page 13: DOE Review 4.1.7 DAQ](https://reader035.fdocuments.net/reader035/viewer/2022081508/56815009550346895dbde1fe/html5/thumbnails/13.jpg)
GLAST LAT Project DOE Review, February 18, 2005
4.1.7 DAQ & FSW V1 13
SIU/EPU Status and ScheduleSIU/EPU Status and Schedule
• Status– Design/documentation complete– Enclosures fabricated– All components/parts received except BAE RAD750 CPU
• Uses recalled International Rectifier regulator• Boards to be sent back to BAE• Reworked boards expected 3 weeks after they receive
components; June 05– Assembly contract out for RFP
• Schedule– 6/1/05 Precoat cCPI boards ready for electrical test– 7/28/05 Complete assembly ready for environmental test– 8/19/05 First Flight SIU/EPU to I&T– 8/24/05 Second flight SIU/EPU to I&T– 8/27/05 Third flight SIU/EPU to I&T– 8/30/05 Fourth flight SIU/EPU to I&T– 9/2/05 Last flight SIU/EPU to I&T
![Page 14: DOE Review 4.1.7 DAQ](https://reader035.fdocuments.net/reader035/viewer/2022081508/56815009550346895dbde1fe/html5/thumbnails/14.jpg)
GLAST LAT Project DOE Review, February 18, 2005
4.1.7 DAQ & FSW V1 14
Testbed and I&T SupportTestbed and I&T Support
• Testbed– Upgrade of engineering modules to reflect flight designs– Scheduled over next 6 months– Labor to support upgrade– Labor to support testing of electronics and flight software
using data generated via front-end simulator boards– Labor to support test-stands for flight electronics
qualification and acceptance testing• I&T Support
– Design/fabrication/testing of virtual spacecraft simulator for I&T
– Support for integration and testing of DAQ modules on instrument
![Page 15: DOE Review 4.1.7 DAQ](https://reader035.fdocuments.net/reader035/viewer/2022081508/56815009550346895dbde1fe/html5/thumbnails/15.jpg)
GLAST LAT Project DOE Review, February 18, 2005
4.1.7 DAQ & FSW V1 15
Management & EGSEManagement & EGSE
• Management– Sub-system manager– Technical writer– Support for environmental test – Travel– Computer for test-stations (HW & SW) maintenance– Shipping charges for flight hardware
• EGSE (Electrical Ground Support Equipment)– Maintenance/repair of test-stations supplied to sub-
systems
![Page 16: DOE Review 4.1.7 DAQ](https://reader035.fdocuments.net/reader035/viewer/2022081508/56815009550346895dbde1fe/html5/thumbnails/16.jpg)
GLAST LAT Project DOE Review, February 18, 2005
4.1.7 DAQ & FSW V1 16
Costs & CommitsCosts & Commits
Explanation:
Dataflow Electronics = TEM/TPS Flight Units
ACD GASU FU & GLT FU = GASU
Power Conditioning = PDU
SIU & LAT Communication Card = SIU