Delta-DOR SIG: Report of the Fall 2007 Meeting Heppenheim, Germany October 5th, 2007 Roberto Maddè...
-
Upload
berniece-russell -
Category
Documents
-
view
214 -
download
1
Transcript of Delta-DOR SIG: Report of the Fall 2007 Meeting Heppenheim, Germany October 5th, 2007 Roberto Maddè...
Delta-DOR SIG:Report of the Fall 2007
Meeting
Heppenheim, GermanyOctober 5th, 2007
Roberto MaddèESA/ESOC
SEA Area MID-TERM REPORTSUMMARY TECHNICAL STATUS
1. Delta-DOR SIG
Goal: Standarising cross-support for Delta-DOR measurements – Organise a WG for that
Working Status: Active _X_ Idle ____
Summary progress: agreement reached on WG charter; definition of TOC for the books to be written
Progress since last meeting: WB finalised
Problems and Issues: none
status: OK CAUTION PROBLEM
Comment: Need to start a WG on the subject.
Agreements reached.
Executive Summary
The Charter for the proposed WG has been discussed and finalised
The TOC of the proposed Magenta and Green Books has been discussed and agreed; responsibilities and roles for the Magenta Book preparation have been distributed and agreed.
The support of 3 agencies to the proposed WG has been assessed (NASA and JAXA have to formally state their support)
Roles and responsibilities for the Magenta Book have been agreed
The schedule and milestones for the books preparation have been agreed
Suggestions coming from NASA, JAXA and ESA presentations have been collected and will be inserted in the coming books, as required
Summary of Goals and Deliverables
• Delta-DOR Operations White Book has been reviewed and completed, with the received RIDs.
• New deliverables have been spotted, if the SIg is turned into a WG:• A Magenta Book - The Proposed Recommended
Practice (Magenta Book) will address aspects of the technique that would require standardization in order to enable Delta-DOR interoperability among space agencies
• A Green Book - The Proposed Green Book will contain all the descriptive material which is needed, in order to introduce the technique
• Validation of inter-operability between the NASA Delta-DOR system and the ESA Delta-DOR system has continued.
• Plans for inter-operability between NASA and JAXA and ESA and JAXA have been drafted
Progress Achieved – agreed schedule
Date Milestone
October 2007 WG kick-off (if approved)
April 2008Draft “Delta-DOR recommended practice for cross support” Magenta
Book for the CCSDS 2008 Spring meeting
August 2008Revised draft “Delta-DOR recommended practice for cross support”
Magenta Book for Agency review
Fall 2008
Second issue of “Delta-DOR recommended practice for cross support” after Agency review for CCSDS 2008 Fall Meeting
Discussion on “Delta-DOR technical characteristics and performance” Green Book and work distribution
December 2008Finalised review and issue “Delta-DOR recommended practice for cross
support” Magenta Book
April 2009Draft “Delta-DOR technical characteristics and performance” Green Book
for CCSDS 2009 Spring meeting
July 2009Revised draft “Delta-DOR technical characteristics and performance”
Green Book
Fall 2009Finalised review and issue “Delta-DOR technical characteristics and
performance” Green Book for CCSDS 2009 Fall meeting
Progress Achieved – Magenta Book TOC
ESA will be the Editor of the 2 foreseen books Table of contents for the Magenta Book:
General introduction Introductory chapter, derived from current ch. 2 of the
WB End-to-end description, based on current ch. 3 of the
WB Interfaces description and references to existing/to be
updated Blue Books (RM) Configuration of the Delta-DOR measurement
Station and spacecraft parameters Orbit ephemeris parameters Scheduling Data transfer procedures Correlation process parameters Operational validation aspects
Interagency data exchange procedures Interoperability validation process Quasar catalogue implementation, validation and
maintenance
Progress Achieved – Green Book TOC
Draft table of contents of the Green Book: Overview of the process Theoretical background System rationale and trade-offs Description of existing systems Achievable performance Delta-DOR related techniques
Phase referencing Same Beam Interferometry
The table of contents will be finalised in the Fall 2008 Meeting
Roles and responsibilities will be defined in the Fall 2008 Meeting
Open Issues
The planned work can be done provided that the current SIG is turned into a WG
Risk Management Update
No risk has been highlighted Resources may be an issue, in the future
Cross Area WG / BOF Issues
Interactions with MOIMS, SLS and CSS are anticipated
However, concerning SLS interface, for the preparation of the proposed books, it is foreseen to: First discuss within the WG, including feedback with transponder, Ground station and spectrum management specialists
Later, discuss with SLS-RNG MOIMS-NAV: the current OEM and TDM formats
appear adequate for the SIG/WG scopes CSS: first a Common Data Format (CDF) may be
defined, within the WG, and then contacts can be set up