CPSMExam
description
Transcript of CPSMExam
CCCEEERRRTTT MMMAAAGGGIIICCC
Demo Edition
Certified Professional in Supply Management (CPSM)
Exam: CPSM
CPSM
1 http://www.certmagic.com
QUESTION: 1A temporary endeavor undertaken to create a unique product or service is called:
A. ProjectB. BuildC. EnterpriseD. Development
Answer: A
QUESTION: 2The process of coordinating the organization, planning, scheduling, controlling,monitoring and evaluating of activities so that the objectives of a project are met isknown as:
A. Project Life cycleB. Project ExecutiveC. Project ManagementD. Project Organization
Answer: C
QUESTION: 3According to Project Management Institute, which of the following is NOT theprocess group of project?
A. InitiatingB. OrganizingC. ExecutingD. Closing
Answer: B
QUESTION: 4Contract statement of work is the output of which process group?
A. PlanningB. OrganizingC. MonitoringD. Closing
CPSM
2 http://www.certmagic.com
Answer: A
QUESTION: 5Organizations less familiar with the discipline of project management usually beginby creating task forces or committees within each role to tackle problem, known as:
A. Procurement ManagementB. Functional structureC. Procedural structureD. Performance Management
Answer: B
CPSM
3 http://www.certmagic.com