Construction Update 2 June 2016 - Bonita Springs...
Embed Size (px)
Transcript of Construction Update 2 June 2016 - Bonita Springs...
-
Construction Update 2 June 2016
Project Update
The City of Bonita Springs Downtown Improvements Project has been underway since September 2015. The project is being built in phases that include construction of two to three blocks at a time. When construction is completed, the road segments will be re-opened and construction will move to the next phase. Construction begins with underground utilities installing stormwater drainage and a new gas line. Then the electric and communications lines are installed underneath the Old 41 right-of-way between Tennessee Street to Terry Street. Lastly, crews rebuild the roadway. The final installation of lighting, street furniture, landscaping and some sidewalk reconstruction will occur later in the project when the Florida Power & Light (FPL) underground facilities are put in service and the existing FPL poles are removed.
If you have any questions or concerns during construction, please contact the project public information consultant:
Kris Cella, Cella Molnar & Associates, Inc. 1631 Hendry Street, Fort Myers, FL 33901
(239) 337-1071, [email protected]
City of Bonita Springsc/o Cella Molnar & Associates, Inc.1631 Hendry Street Fort Myers, FL 33901
Visit the project website atwww.BonitaSpringsDowntownImprovements.com
The City of Bonita Springs Downtown Improvements
Project moves to phase two!
The contractor is Wright Construction Group and the project is expected to be complete in fall 2017.The City and the project team are committed to keeping the public informed of construction activities and working with the public to solve any issues that arise during construction. The project website is being updated with new information about construction as it becomes available.
El contratista es Wright Construction Group y se espera que el proyecto sea completado en el otoo del 2017.Tanto la Ciudad, como el equipo del proyecto, se han comprometido a mantener al pblico informado acerca de las actividades de construccin, y a trabajar con el pblico para resolver cualquier conflicto que surja durante la construccin. La pgina web del proyecto ser actualizada frecuentemente con los detalles del proyecto, a medida que estn disponibles.
Si tiene alguna duda o preocupacin durante el proceso de construccin, por favor comunquese con el
Consultor en Informacin Pblica:
Kris Cella, Cella Molnar & Associates, Inc. 1631 Hendry Street, Fort Myers, FL 33901
(239) 337-1071, [email protected] la pgina web del proyecto
www.BonitaSpringsDowntownImprovements.com
Actualizacin del Proyecto
Las mejoras de proyecto en el centro de la ciudad de Bonita Springs se han llevado a cabo desde septiembre del 2015. El proyecto se ha construido en fases que incluyen la construccin de dos o tres cuadras a la vez. Cuando se termine el trabajo en una rea, ese segmento de la carretera ser abierto, y la construccin continuar en la prxima zona. La construccin comienza con la instalacin de servicios subterrneos de drenaje de aguas pluviales y una nueva lnea de gas. Luego, la electricidad y lneas de comunicacin son instaladas debajo de la carretera Old 41 justo entre la calle Tennessee y la calle Terry. Por ltimo, los trabajadores reconstruyen la calle. La instalacin final de la iluminacin, el mobiliario urbano, la jardinera y la reconstruccin de la acera, se llevarn a cabo ms adelante cuando las instalaciones subterrneas de empresa Florida Power & Light (FPL) estn en servicio y los postes existentes de la misma sean removidos.
El Proyecto de Mejoras en el Centro de Bonita Springs
pasa a la fase dos!
-
Phase 1 is OpenThe first phase of construction along Old 41 from Wilson Street to Childers Street is complete (with the exception of FPL pole removal and final sidewalk construction) and open to traffic. Wilson Street and Reynolds streets are paved and open to traffic. Felts Avenue is also paved between Wilson and Reynolds streets.
Construction on Phase 2 began in February (work occurs concurrently on Felts Avenue and the adjoining side streets). The contractor extended this phase on Old 41 from the Pennsylvania Avenue/Ragsdale Street intersection to include Old 41 south to Hampton Street. Completion of the roadway portion of this phase is expected by mid-summer 2016. Future phases move south on Old 41 Road, with work continuing on the side street, then the next phases of construction will move north of the Imperial River.
After all the phases are complete, FPL poles are removed, light pole bases are installed and sidewalk is completed, the final lift of asphalt will be installed on Old 41 Road. Finally, new signs will be installed and street markings will be added.
Help Us Help YouThe project team continues to reach out to the businesses and keep them informed. To provide better directions and visibility for the businesses, 3 X 6 foot banners are developed and placed in visible locations for the travelling public. A Business Assistance Guide was provided to the businesses along the corridor at the beginning of the project. To promote the businesses in Phase 1 construction, a full page advertisement was published in the Bonita Banner on Wednesday, December 16, 2015. A second advertisement is being developed for businesses in Phase 2.
La Primera Fase est abierta
La primera fase de construccin a lo largo de la carretera Old 41 desde la calle Wilson hacia la calle Childers est completada y abierta al trfico, con la excepcin de la eliminacin del poste de FPL y la construccin final de la acera. Las calles Wilson y Reynolds estn pavimentadas y abiertas al trfico. La avenida Felts, entre las calles Wilson y Reynolds, tambin est pavimentada.
La construccin de la Fase 2 inici en febrero (el trabajo se lleva a cabo simultneamente en la avenida Felts y las calles laterales). El contratista extendi esta fase desde la avenida Pennsylvania/calle Ragsdale hacia el norte de la calle Hampton. La finalizacin de la porcin de la calle en esta fase est pautada para mediados del verano del 2016. Fases futuras se mueven hacia el sur en la carretera Old 41, con trabajo continuo en la calle lateral. A seguidas, las prximas fases de construccin se movern al norte del ro Imperial.
Cuando todas las fases estn completadas, los postes de FPL sern removidos, se instalarn las bases de luces para el poste y la acera se ha completar, se instalar la ltima capa de asfalto en la carretera Old 41. Por ltimo, los letreros nuevos sern instalados y las sealizaciones de la calle sern aadidas.
Aydenos a Ayudarle
El equipo del proyecto contina acercndose a las empresas para mantenerlas informadas. Para proporcionar mejores instrucciones y visibilidad para las empresas, se han elaborado letreros de 3 x 6 pies, los cuales estn ubicados en localidades visibles para el pblico que transita. Al inicio del proyecto, una Gua de Asistencia para Negocios fue entregada a los negocios ubicados a lo largo del corredor. Para promover los negocios en la Fase 1 de construccin, un anuncio de pgina completa fue publicado en el peridico Bonita Banner el mircoles 16 de diciembre del 2015. Para la Fase 2, un segundo anuncio para los negocios est siendo elaborado.