Construction Assessment Hearing October 3, 2002 Shawnee Middle School Cafeteria
description
Transcript of Construction Assessment Hearing October 3, 2002 Shawnee Middle School Cafeteria
1
Construction Assessment Hearing October 3, 2002
Shawnee Middle School Cafeteria
2
Overview of Tonight’s Meeting:
I. Review the objective of tonight’s meeting.
II. Review the history of the project.III. Review the proposed sewer layout.IV. Review the statutory procedures.V. Review the project cost and financing.VI. Review the tentative schedule.VII. Review easement acquisitions. VIII. Questions and answers.
3
This meeting will provide for public participation on the consideration of the construction assessments for the Oakview Subdivision
Area.
This project consists of providing sanitary sewer service to the Oakview Subdivision Area, Zurmehly Road, Wapak Road, and Nancy Sue Drive.
Discussion items will include cost of sewer lines and locations, tentative cost for construction and schedules.
I. Meeting Objective
4
II. Project History
April , 1999 Allen County Health Department completes evaluationsof 13 on lot home systems.
April 27, 1999 Water test samples were collected from ditches.
June 10, 1999 Second set of water test samples were collected fromditches. Testing Table
August, 1999 Letters were mailed by Allen County Health Department to homeowners of the Oakview Subdivision explaining pollution problem in the ditches.
November 17, 1999 Ohio Environmental Protection Agency (OEPA) contacted the Board of County Commissioners and informed the board to submit a Permit To Install (PTI) within six month outlining the sewerage improvements necessary to alleviate the pollution problem in the Oakview Subdivision.
5
II. Project History (continued)
December 7, 1999 Informational Meeting is held to explain the details of the project.
December 15, 2000 OEPA issued Draft Orders to sewer the project area. Consent Orders
February 24, 2000 Detailed Planning Hearing was held to discuss and explain the project.
May 23, 2001 Construction Assessment Hearing.
August 29, 2002 Board of County Commissioners dismiss the proceedings of the May 23, 2002 Construction Assessment Hearing, set a new hearing
date for September 18, 2002.
September 5, 2002 Board of County Commissioners revise Construction Assessment Hearing date to October 3, 2002.
October 3, 2002 Second Construction Assessment Hearing.
6
Proposed Party Boundary
Proposed Sewer
Proposed Pump Station Site
III. Proposed Oakview Subdivision Sewer Layout
Proposed Force Main
Existing Pump Station Site
7
III. Proposed Sewer Layout (cont.) Zurmehly Rd.
15” Sanitary Sewer
12” Sanitary Sewer
N
4309
4325
4355
4377
4411
4439
4467
4545
4560
4590
4665
4673
466646
90
4748
4774
4803
4840
4849
4871
Amanda Lakes #3Subdivision Existing
PumpStation
Zurmehly Rd.
8
12” Sanitary Sewer
III. Proposed Sewer Layout (cont.) Zurmehly Rd.
N
4933
4949
4963
4981
5029
4990
5122
5073
5123
5210
5260
5175
1300
5277
3185
3245
S.R
. 501
Zurmehly Rd.
Nancy Su
e
8” Sanitary Sewer
9
12” Sanitary Sewer
III. Proposed Sewer Layout (cont.)
Nancy Sue Dr.
8” Sanitary Sewer
N
1300 5175
1318
1330
1338
1344
1358
1372
1319
1331
1345
1357
1371
Nan
cy Sue D
rive
Zurmehly Rd.
10
12” Sanitary Sewer
III. Proposed Sewer Layout (cont.) S.R. 501
4” Force Main
N
5277
3245
3257
3275
3297
3319
3345
33633385
3397
3270
3278
3306
3360
3368
3450 3425
3475
S.R
. 501
11
III. Proposed Sewer Layout (cont.) Fort Amanda Rd.
8” Sanitary Sewer
N
1227
5653 1226
55955567
5529
1201
Fort Amanda Rd. Waysid
e Drive
Forest D
rive
Fairgreen
Drive
12
III. Proposed Sewer Layout (cont.)
Fairgreen Dr.
8” Sanitary Sewer
N 12281227
12401239
1252 1251
1256 1271
1262 1277
1284 1283
1292 1291
1302 1301
1306 1307
5653
Fairgreen
Drive
Ft. Amand Rd.
13
III. Proposed Sewer Layout (cont.)
Fairgreen Dr.
8” Sanitary Sewer
N
1313
1312
1326
1340
1337
1352
1368
1376
3899
1355
1369
1387
Fairgreen
Drive
Maple Dr.
14
III. Proposed Sewer Layout (Cont.)
Forest Dr.
8” Sanitary Sewer
N
5595
5567
12265653
1244
1254
1260
1268
1276
1284
1239
1251
1261
1265
1271
1283
1295
Forest D
rive
Parkway St.
Ft. Amanda Rd.
15
8” Sanitary Sewer
Lift Station
4” Force Main
III. Proposed Sewer Layout (cont.)
Forest Dr.N
1307
1321
1323
1345
1365
1385
1391
1308
1316
1322
3850
3853
1360
1370
1380
Forest D
rive
Maple Dr.
16
8” Sanitary Sewer
III. Proposed Sewer
Layout (cont.) Wayside Drive
N
1201
1207
1215
1231
1259
1267
1271
3285
5529
1216
1228
1258
1266
3826
Waysid
e Drive
Parkway St.
Ft. Amanda Rd.
17
8” Sanitary Sewer
III. Proposed Sewer Layout (cont.) Parkway St.
N3825
12713826
1283
1271
Parkway Street
Waysid
e Dr.
Forest D
r.
18
III. Proposed Sewer Layout (cont.) Maple Drive
8” Sanitary Sewer
N3850
3853
1313
1337
Maple Drive
Fairgreen D
r.
Forest D
r.
19
III. Proposed Sewer Layout (cont.) Forest Drive
8” Sanitary Sewer
N
1376
3889
1387
3863 1391
1380
1385
Forest Drive
20
III. Proposed Sewer Layout (cont.) Force Main Location
4” Force Main 8” Sanitary Sewer
Lift Station 12” Sanitary Sewer
N 3364
3360
1365
3306
3278
S.R
. 501 F
ores
t D
r.
21
IV. Statutory ProcedureA. Conduct Detailed Planning Assessment (DPA) Hearing.
B. Legislation approving DPA.
C. Complete construction plans.
D. Finalize DPA costs, and mail billings to property owners.
E. Conduct a Construction Assessment Hearing.
F. Five day wait for written objections.
G. Respond to all written objections.
H. Ten day wait for filing of all appeals to Probate Court.
I. Settle all appeals.
J. Dismiss proceedings of first Construction Assessment Hearing.
K. Conduct a second Construction Assessment Hearing.
L. Five day wait for written objections.
M. Respond to all written objections.
N. Ten day wait for filing of all appeals to Probate Court.
O. Settle all appeals.
P. Proceed to the construction of the project.
Q. Complete construction of the project.
R. Finalize cost of construction and mail billings to property owners.
S. Notify property owners to connect to project.
T. Certify assessments to the tax duplicate of the property owners.
22
1. Final Detailed Planning Assessment (DPA)
DPA – 5 year Assessment with interest:
FinalEngineering $69,300.00Soils $ 9,152.75Miscellaneous Expense $ 0.00Advertising $ 674.62Note Interest $ 7,620.00
Total DPA Cost $86,747.37
Final DPA billed to each property owner:$86,747.37 / 137 households = $633.20
Note ~ Will appear on the first half taxes of 2003.
V. Cost to Property Owners and Financing
23
2. Estimated Construction Assessment (CA)
CA – 20 year Assessment with interest:Engineering (Administrative, Bidding, and Soils) $120,000.00Construction $1,145,000.00Legal $10,000.00Note & Bond Issuance Fees $20,000.00Advertising $1,000.00Permits $10,000.00Interest on Notes $75,000.00Easement Acquisition $10,000.00Contingency $110,000.00Total Principal For Assessments $1,501,000.00
V. Cost to Property Owners and Financing (cont.)
24
V. Cost to Property Owners and Financing (cont.)2. Estimated CA with OPWC Financing
= ($1,501,000.00 - $225,000.00 (have received $188,000.00 to date)) ÷ 135
=$9,451.85
Not to Exceed Total Assessments Billed to Property Owners:
= DPA + CA = $633.20 + $8,525.93 = $9,159.13
The County will commit up to $75,000.00, and the Township will commit up to $50,000.00 to bring the assessment down to:
=( $1,276,000.00 - $75,000.00 - $50,000.00) ÷ 135 = $8,525.93
Note: The County and the Township will decrease their amount of commitment in a proportionate manner in the event the total project cost is reduced.
25
V. Cost to Property Owners and Financing (cont.)2. Estimated CA (cont.):
Half Year Tax payments are as follows:
Note ~ CA may be paid in cash or placed on taxes for twenty years with interest.
Term of Loan Interest Rate Half Year Tax Payment Sum of all Payments
20 yrs. 4 ½ % $325.00 $13,000.00
25 yrs. 5.0 % $300.00 $15,000.00
30 yrs. 5 ½ % $314.00 $18,840.00
3. Miscellaneous Non-Assessed Cost to Property Owners
a.) Abandonment of existing private sewage system/tank and installation of sanitary sewer lateral to the project. Approximate cost - $700.00 to $1,000.00.
26
3. Miscellaneous Non-Assessed Cost to Property Owners (cont.)b.) Once a property owner has connected to the project he or she will
receive a quarterly sewer bill form the County to pay for operation, maintenance, and future major capital expenditures for the sewer district. The breakdown of the County sewer billing is as follows:
V. Cost to Property Owners and Financing (cont.)
Month’s Billed Billing Date Due Date Cost
Jan-Feb-Mar May June $75.00
Apr-May-June Aug Sept $75.00
July-Aug-Sept Nov Dec $75.00
Oct-Nov-Dec Feb March $75.00
4. Financial Assistance The County has CDBG funds that are available on a limited basis to assist LMI households for the cost of connecting to the sanitary sewer (abandonment of septic tank, and construction of service lateral). Application needs to be made to the County CDBG Coordinator so that eligibilty and, order assistance may be determined. Ohio Rural Development has grant assistance for property owners ages 62 yrs., and older with good credit (www.rurdev.usda.gov, “Housing and Community Facilities”, 419-222-0242, Cindy Craley)
27
VI. Easement Acquisition
The County is requesting all property owners who have, or will be contacted for acquisition of easements to donate the easement to the project. The cost of acquisition of easements is factored back into the overall cost of the project. Therefore, all property owners in the project will pay for the added cost of easement acquisition.
We have a list of all easements yet to be acquired. I would request you get with us at the end of this meeting to negotiate the acquisition of the easement on your property.
28
VII. Tentative Schedule
Informational Meeting 12/17/1999DPA Hearing 2/24/2000First CA Hearing 5/23/2001Second CA Hearing 10/03/2002Begin Construction 12/04/2002Construction- Substantially Complete 6/30/2003 Complete Grading/Seeding 7/30/2003Assessment Billing 8/2003Project Wrap-Up Meeting 8/2003Tax Certification 10/1/2003
29
VIII. Questions & Answers
Note: Please State Your Name and Address, for the record, before asking your question.