Considerations in Planning the Construction Staging ppt

download Considerations in Planning the Construction Staging ppt

of 58

Transcript of Considerations in Planning the Construction Staging ppt

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    1/58

    CONSIDERATIONS INPLANNING THE

    CONSTRUCTION STAGING

    2008 PICE NATIONAL CONVENTION

    CAGAYAN DE ORO CITY

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    2/58

    CONSIDERATIONS INPLANNING THE

    CONSTRUCTION STAGING

    Henry P. Turalde

    Camarines Sur Polytechnic CollegesPICE Iriga - Rinconada Chapter

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    3/58

    Presentation Outline

    Introduction

    Site Limitation

    Utilities

    Safety

    Traffic Control

    Access to Work

    Impacts During Construction Nature Protection

    Conclusion

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    4/58

    Quotable Quotes

    A mans judgment is

    no better than

    his information

    - Bits and Pieces

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    5/58

    Introduction

    Every project is

    unique, and so,

    poses unique

    problems thatrequire special

    details for its

    resolve.

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    6/58

    Introduction

    Every project is

    unique, and so,

    poses unique

    problems thatrequire special

    details for its

    resolve.

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    7/58

    Introduction

    To avoid potential

    troubles during

    construction,

    constructors have towork on the solutions

    before the problem

    comes. With future

    events unknown, that iseasier said than done.

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    8/58

    Construction Staging

    Construction staging is the logistics of space

    allocation for equipment movements and

    materials storage, worksite access, temporary

    works, provisions for construction workrequirements, including the schematic

    organization of the staging areas.

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    9/58

    Construction staging involves strategically dividing the whole

    area into different parts, treating each part as one separate

    job site, as in first phase, second phase and so on.

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    10/58

    Construction activities progress from one part to the next,

    and then to the next, until all parts or phases have been

    completed

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    11/58

    In urbanized area or existing facility, construction staging

    involves enclosing specific areas while undergoing operations

    and shifting enclosure as work progresses.

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    12/58

    Construction staging needs planning of the combinations of

    various construction elements procedures, methods,

    equipments, technology and available space for each phase.

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    13/58

    Construction Staging

    The important factors in planning the

    construction staging are:

    S U S T A I N

    S- site limitationsU- utilities

    S- safety

    T- traffic controlA- access to work area

    I - impacts during construction

    N- nature protection

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    14/58

    S - Site limitationsExisting Site Condition

    Terrain and landscape affects themovement, supply and transportof materials and workers.

    Residents in the vicinity can besource of labor.

    Trees, soil, ground and naturalenviron can be source ofmaterials.

    Its climatic condition mayinfluence critical scheduling asstorm occurrence can causeflooding.

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    15/58

    S - Site limitationsExisting structures and underground utilities

    Existing buildings & structures, utilities within project siteincluding power lines, pipelines, buried cables and sewers.

    Existence can delay the work:

    Block the movement of workers, equipments & materials

    Block the line of sight of the surveying equipments

    May conflict with newproject

    May require revision ofproject design or relocationof the existing utilities

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    16/58

    S - Site limitationsSpace Allocation

    Staging Area

    A designated area

    where vehicles,supplies and

    equipments are

    positioned for access

    to construction site.

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    17/58

    S - Site limitationsSpace Allocation

    Temporary Works

    Towers, trestles, scaffolds and

    temporary structures

    The stability and reliability of the

    temporary works is the bottom

    line of the quality of the finish

    work.

    Once done, immediatelydismantled to give way to other

    necessities.

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    18/58

    S - Site limitationsSpace AllocationSite Office and Other

    Requirements Whenever possible,

    provision on site for fieldoffices, toilets, showerrooms, mess hall and restrooms including sleepingquarters shall be providedon site or in the

    neighborhood. This cansave transportation timeand cost.

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    19/58

    S - Site limitationsSpace AllocationSpace Allocation for Waste:

    Appropriate stockpilesize and location will

    facilitate activities,reduce damage tosensitive areas.

    Orderliness and safetyof the site, the qualityof the work finish aredirectly related towaste management.

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    20/58

    U - UtilitiesConstruction staging plan should consider

    essential utility needs for the project:

    Energy Requirements

    Water Requirements Drainage Requirements

    Communications

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    21/58

    U - UtilitiesEnergy Requ irements

    In construction, energy is a

    primary commodity. Without

    sufficient energy supply, project

    can not progress as intended.

    Construction staging should

    consider power and energy

    requirement on site, hourly fuel

    demand of the mobile equipmentsand vehicles, power demand of the

    tools and machines in the yard,

    and others.

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    22/58

    U - UtilitiesWater Requirements

    Water supply is a very important

    commodity in the construction

    site.

    Water is used in the concrete

    works, earthworks, washing and

    sanitary facilities.

    Construction staging should

    consider the details of water

    supply scheme, including its

    hourly supply and demand

    inventory.

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    23/58

    U - UtilitiesDrainage Requirements Drainage provision should be

    considered particularly whenthere is dewatering operation.

    Improper sewerage system cancreate chaos in the community.

    With field offices and quarters,drainage system is important.

    In the absence of a properdrainage system in the area,portable sanitary facilitiesmaybe employed.

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    24/58

    U - UtilitiesCommunicat ions

    Communication facility is also

    a basic necessity in the

    construction site.

    The choice of system the site

    would use may depend on the

    type of works involved in the

    project.

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    25/58

    S - Safety Construction staging should

    always consider safety inevery activity.

    In a construction site

    involving various workerswith diverse activities,materials, tools andequipments; the work place

    itself is a potential hazard.

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    26/58

    S - SafetyAccidents

    can delay,

    demobilize,

    demoralizeand degrade

    construction

    projects.

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    27/58

    Murphys Law:Left to themselves,

    things tend to go from bad to worse.

    Hence, a construction sitehas the normal tendency

    to become 4Ds:dirty

    disorderly

    dense (crowded)

    and dangerous

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    28/58

    Practical Ways to keep Construction

    Site from becoming 4Ds: 5Ss of Good Housekeeping:

    Sort (arrange)

    Systematize (organize)

    Sweep (clean)

    Sanitize (free from dirt and germs)

    Self-discipline (practice consistently)

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    29/58

    Hierarchy of Safety:

    1. ELIMINATEthe hazard2. If not practical, PREVENT

    3. If not practical, CONTROL

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    30/58

    Last line of

    control/defense

    2. Administrative Control:

    Exposure time limitations Safe work practices

    Alarms and warning signs

    Training and education

    3. (Point of contact)Personal Protective

    Equipment

    Three areas where hazards can be controlled:

    SOURCE RECEIVERPATH

    1.(Pre-contact) Engineering Control : Elimination/minimization

    Enclosure of the hazard

    Redirection of hazard

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    31/58

    Engineering Controls

    If . . .The work environment can be physicallychanged to prevent employee exposure to

    existing and potential hazard,

    Then. . .The hazard can be eliminated withan engineering control

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    32/58

    Administrative Controls

    If .. .The wayemployees do the job

    can be changed, and

    exposure to potential

    hazard is removed,

    Then. . .The hazard

    can be eliminated with

    administrative control

    & others

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    33/58

    S - SafetySummary of PPEs for the safety of construction personnel:

    Head protection hard hat, bump cap;

    Eye and face protection safety glasses, safety goggles, face

    shields;

    Ear protection ear plug, ear muffs, canal caps; Respiratory protection filtration respirator, air-purifying respirator,

    air-supplying respirator;

    Hand and arm protection gloves, hand pads, sleeves;

    Foot and leg protection foot guards, safety shoes, boots, leggings;

    Fall protection safety belts, safety harness, lanyards;

    Torso or body protection vests, jackets, aprons, cover-alls, full-

    body suits.

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    34/58

    S - SafetyBasic requirements to effectively

    promote safety in a job site

    (acronym: SAFE ESCAPE):

    Safety personnel

    Ample lighting Fire protection system

    Electrical hazards checked

    Efficient material storage

    Structural soundness

    Controlled access

    Adequate ventilation

    Personal protective equipment (PPE)

    Excellent housekeeping

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    35/58

    T - Traffic control Construction activities

    within a transportation

    facility area would

    result to traffic

    disruption. Construction staging

    must prepare a traffic

    flow scheme for the

    immediate relief ofvehicles traveling the

    area during the

    execution period.

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    36/58

    T - Traffic control Alternative route or

    traffic diversion route

    must be provided using

    standard trafficengineering system.

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    37/58

    T - Traffic control Ineffective traffic

    control scheme

    would result to

    encroachment of

    traffic to the worksite, causing delay to

    operations, or

    effecting damage to

    finished works.

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    38/58

    A - Access to work area Access to work area is a basic requirement.

    Controlled access to delicate job or restricted area is

    a major concern.

    Site access should include access road to the area,

    ingress and egress, and probably, isolation of somespecific work areas.

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    39/58

    A - Access to work areaACCESS ROAD

    Temporary access road

    need to be constructed to

    transport materials,

    equipment and personnelto the work area.

    Access roads should be

    properly maintained

    throughout the duration ofthe project.

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    40/58

    A - Access to work areaINGRESS AND EGRESS

    Controlling entrance and exit of a

    construction area is not only for

    safety and security, but also for

    resource and quality management. The site that is protected from

    external influence is cleaner, more

    orderly and undisturbed.

    Intrusion to job site may disturb the

    delicate setting of materials (e.g.,

    concrete, tiles) and the quality of

    finish (e.g., painting).

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    41/58

    I - Impacts during construction One of the most

    crucial concerns in the

    construction site are

    the impacts duringconstruction operation

    particularly when

    massive earthworks

    and heavily powered

    equipments areinvolved.

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    42/58

    I - Impacts during constructionDISRUPTION OF

    PEDESTRIAN ACCESS

    The disruption of a

    pedestrian access route,

    may create severe impactto pedestrians.

    Whenever a pedestrian

    access route is blocked by

    the project, an alternate

    circulation path shall beprovided as long as safety

    warrants.

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    43/58

    I - Impacts during constructionCONSTRUCTION NOISE

    Controlling construction

    noise can pose special

    problems for contractors.

    Construction noisemakers can move from

    one location to another

    and vary in its intensity

    throughout the work day.

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    44/58

    I - Impacts during constructionConstruction noise can be

    controlled, as follows:

    Incorporate noise control

    in all phases of project

    planning and design,

    Buy Quiet Rent Quiet

    Equipment

    maintenance,

    Barrier protection,

    Work activity scheduling,

    Work quiet awareness.

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    45/58

    I - Impacts during constructionNoise

    When its not feasible

    to reduce the noise

    or its durationuse ear protective

    devices such as ear

    plug, ear muffs, canal

    caps or others.

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    46/58

    I - Impacts during constructionCONSTRUCTION

    VIBRATION

    Construction activities cause

    varying degrees of ground

    vibration. Buildings and structures in the

    vicinity may react to vibration.

    Work which employs

    equipment that generateserious vibration impact must

    be used with extra care.

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    47/58

    I - Impacts during constructionCONSTRUCTION

    VIBRATION

    Vibration effects can range

    from causing annoyance

    to people inside thebuildings, to minor

    (cosmetic) damage to

    walls and ceilings, to major

    structural damage. Special care to old

    buildings close to the site

    must be observed.

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    48/58

    I - Impacts during constructionConstruction Vibration Mitigation Design considerations and project lay-out:

    Route heavily loaded trucks away from residential streets.

    Operate earthmoving equipment on the construction lot as far

    away from vibration-sensitive sites . Sequence of operations:

    Phase demolition, earthmoving and ground-impact operations

    so as not to occur in the same time period.

    Avoid night time activities.

    Alternative construction method:

    Avoid impact pile driving in vibration-sensitive areas.

    Select demolition methods not involving impact.

    Avoid vibratory rollers and packers near sensitive areas.

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    49/58

    I - Impacts during constructionDUST

    Common to construction site is the

    presence of dust.

    Also common to construction site is

    exposed soil. When wind picks up

    the dry exposed soil and carries itoff, dust become airborne.

    Dust can cause the following:

    create health problems

    degrade the environment

    create problems with visibility

    damage or dirty property

    create unsafe working conditions

    D t C t l M

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    50/58

    Dust Control Measures

    Dust prevention for construction activities generally seek to

    minimize soil disturbance and eradication of loose soil

    fines or uncovered earth surface by the following manner: Minimize disturbed surface by reducing excavation size or

    number.

    Limit dusty work on windy day.

    Pave haul road and storage areas. If costly, pave just the

    entrance/exit, then gravel the remainder.

    Water or sweep the roadway often.

    Limit driving speed on unpaved surfaces to 15 kph.

    Prevent transport of dusty materials by rinsing vehicles and tightly

    covering loaded trucks. Enclose storage and handling areas.

    Keep storage piles covered when not in use. Limit the working

    face of the pile to the downwind side.

    Clean up dusty spills immediately.

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    51/58

    N - Nature protectionAs part of construction

    planning, detailed

    construction staging

    should be sequentially

    prepared incorporatingthe environmental

    protection requirements.

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    52/58

    N - Nature protectionConstruction staging can

    ensure that all land used for

    quarrying activity is restored to

    its equivalent condition or better

    than the original condition

    before the commencement of

    the operations.

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    53/58

    N - Nature protection

    Construction staging can

    prevent disturbance of

    vegetation or causerehabilitation of disturbed

    vegetation.

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    54/58

    N - Nature protectionConstruction staging

    plan can avoid pollution

    of the air, thwart the

    contamination of water

    resources and cause aneffective waste disposal

    in the construction area

    and its periphery.

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    55/58

    Conclusion

    Construction staging is crucial

    in the over-all performance of

    the construction operations.

    It is as important as the

    construction work itself.

    Most of the construction-related

    problems in project execution

    are direct or indirect result of

    insufficient consideration of theimportant elements in planning

    the construction staging.

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    56/58

    Conclusion

    The important factors in planning theconstruction staging are:

    S U S T A I N

    S- site limitationsU- utilities

    S- safety

    T- traffic controlA- access to work area

    I - impacts during construction

    N- nature protection

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    57/58

    POINTS TO PONDER:

    WHEN SOMETHINGGOES WRONG, ITSMORE IMPORTANT TODECIDE WHOS GOINGTO FIX IT THANWHOS GOING TOBLAME.- Anonymous

  • 7/30/2019 Considerations in Planning the Construction Staging ppt

    58/58

    THANK YOU.