CONCEPTUAL PLAN AND ENVIRONMENTAL...

27
PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN PROMOTER: VEETRAG BUILDCON PVT. LTD. DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363 ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR NOVEMBER’ 2017 CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN INTRODUCTION The existing project is promoted by Veetrag Buildcon Pvt. Ltd. The project is at Khasra no. 66/2, 66/10 & 628/65, Village Pal, Bye pass road, Jodhpur, Rajasthan. The plot area of the project is 28416.21 Sq.m. and Gross Built up Area is 101359.805 Sq.m. (It is a Violation Case: As 6277.92 Sq.m. additional has been constructed at the site without taking prior environmental Clearance.). Environmental Clearance for the project name “Group Housing” had already been granted vide letter No. F1(4)/SEIAA/SEAC-Raj/Sectt/Project/Cat8(A)b2(616)13-14 dated 31.07.2014 for the following capacity: Approved Total plot area : 28416.21 Sq.m. Approved Built up area : 96458.30 Sq.m. COST ESTIMATION The estimated cost of the project is Rs. 150 crores approx. This includes cost of the land as well as development cost. AREA STATEMENT The project Gross B.U.A is increasing by 6277.92 Sq.m. due to change in the flat design and planning. However, the project capacity will remain same; the project features are tabulated as below: S. No Particular As Per Issued EC Prorposed Now Comments 1 Plot Area 28416.21 28416.21 Sq.m No change 2 B.U.A. 96458.30 Sq.m 97736.48 Sq.m Increased 3. Number of Block Eleven Eleven No change 4 Floors Tower: 11 B+S+13 in all 11 Tower (B.U.A=96458.30 Sq.m) Tower No. 1,2,3,4: B+S+16 & Tower No. 5,6,7,8,9,10,11 B+S+14 (B.U.A=97736.48 Sq.m) EWS/LIG (B.U.A=3623.325 Sq.m) B.U.A Increased by 4901.505 Sq.m 5 Facility 520 flats 538 flats

Transcript of CONCEPTUAL PLAN AND ENVIRONMENTAL...

Page 1: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT

PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN

PROMOTER: VEETRAG BUILDCON PVT. LTD.

DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363

ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

NOVEMBER’ 2017

CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN

INTRODUCTION

The existing project is promoted by Veetrag Buildcon Pvt. Ltd. The project is at Khasra no. 66/2, 66/10 &

628/65, Village Pal, Bye pass road, Jodhpur, Rajasthan. The plot area of the project is 28416.21 Sq.m. and

Gross Built up Area is 101359.805 Sq.m. (It is a Violation Case: As 6277.92 Sq.m. additional has been

constructed at the site without taking prior environmental Clearance.).

Environmental Clearance for the project name “Group Housing” had already been granted vide letter No.

F1(4)/SEIAA/SEAC-Raj/Sectt/Project/Cat8(A)b2(616)13-14 dated 31.07.2014 for the following

capacity:

Approved Total plot area : 28416.21 Sq.m.

Approved Built up area : 96458.30 Sq.m.

COST ESTIMATION

The estimated cost of the project is Rs. 150 crores approx. This includes cost of the land as well as

development cost.

AREA STATEMENT

The project Gross B.U.A is increasing by 6277.92 Sq.m. due to change in the flat design and planning.

However, the project capacity will remain same; the project features are tabulated as below:

S.

No

Particular As Per Issued EC Prorposed Now Comments

1 Plot Area 28416.21 28416.21 Sq.m No change

2 B.U.A. 96458.30 Sq.m 97736.48 Sq.m Increased

3. Number of Block Eleven Eleven No change

4 Floors Tower: 11

B+S+13 in all 11 Tower

(B.U.A=96458.30 Sq.m)

Tower No. 1,2,3,4:

B+S+16

&

Tower No. 5,6,7,8,9,10,11:

B+S+14

(B.U.A=97736.48 Sq.m)

EWS/LIG

(B.U.A=3623.325 Sq.m)

B.U.A Increased by

4901.505 Sq.m

5 Facility 520 flats 538 flats

Page 2: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT

PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN

PROMOTER: VEETRAG BUILDCON PVT. LTD.

DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363

ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

NOVEMBER’ 2017

EWS - 82 (EWS) + 04 (LIG)

BUILT UP AREA DETAILS

APPROVED BUILT UP AREA DETAILS

S. No. Tower No. of

Floors

No. of Flats Built up Area (Sq.m.)

1. Tower-1 S+13 26 555.60

2. Tower-2 S+13 26 555.60 3. Tower-3 S+13 52 6007.40 4. Tower-4 S+13 52 6007.40 5. Tower-5 S+13 52 6007.40 6. Tower-6 S+13 52 6007.40 7. Tower-7 S+13 52 6007.40 8. Tower-8 S+13 52 6007.40 9. Tower-9 S+13 52 6007.40 10. Tower-10 S+13 52 6007.40 11. Tower-11 S+13 52 6007.40

Mumty machine room area 660.0 Total 520 69546.87

Commercial Block 2600

Club Area 1250

Basement area 18061.69

Total Built up Area 91458.56

INCREASED BUILT UP AREA DETAILS

S. No. Tower No. of

Floors

No. of Flats Built up Area (Sq.m.)

12. Tower-1 S+16 30 6556.44

13. Tower-2 S+16 30 6556.44 14. Tower-3 S+16 56 7211.40 15. Tower-4 S+16 56 7211.40 16. Tower-5 S+14 52 6873.95 17. Tower-6 S+14 52 6873.95 18. Tower-7 S+14 52 6873.95 19. Tower-8 S+14 52 6873.95 20. Tower-9 S+14 52 6873.95 21. Tower-10 S+14 52 6873.95 22. Tower-11 S+14 54 6385.40

Mumty machine room area 660.0 Total 538 75824.79

Commercial Block 2600

Club Area 1250

Basement area 18061.69

EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623

Total Built up Area 101359.48

Page 3: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT

PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN

PROMOTER: VEETRAG BUILDCON PVT. LTD.

DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363

ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

NOVEMBER’ 2017

PARKING REQUIREMENT

Total Parking Required: 1135 ECS

Open Parking: 407 ECS

Stilt Parking: 156 ECS

Basement: 552 ECS

Club: 20 ECS

Total Parking required for EWS/LIG: 98 Scooters

POWER REQUIREMENT

Demand Load: 3198.8 KW

Connected Load: 5955.2 KW

Source: Electricity Board: JVVNL

Selection of Transformers:

Two transformers will be installed of capacity 2500 kVA each.

Selection of DG sets (For common areas only):

02 nos. D.G Set of capacity 300 kVA will be installed for common areas.

WATER DEMAND

The daily water requirement for the project is 292 KLD (fresh water demand: 210 KLD and the

treated wastewater demand: 82 KLD). The water demand will be met from ground water. Basis for

water demand is given as:

Page 4: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT

PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN

PROMOTER: VEETRAG BUILDCON PVT. LTD.

DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363

ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

NOVEMBER’ 2017

Fresh water

210KLD

Recycle/

Reuse

treated

wastewater

82 KLD

Flats :203 KLD

Flushing : 66 KLD

227 KLD

Waste water

S

T

P

Capacity

300 KLD

162 KLD

Sludge &

Evaporation

losses

11 KLD

STP treated wastewater

WATER BALANCE

Daily Water Demand = 210 + 82 = 292 KLD

53 KLD

Excessive

treated

wastewater

59 KLD

Filter back wash @ 15 cu.m. / hr for 15 min.:4 KLD

3 KLD

Landscaping : 5 KLD

General Washing : 4 KLD3 KLD

6 KLDCommercial Community Facility & Visitors : 7KLD

IDENTIFICATION, PREDICTION AND EVALUATION OF IMPACTS

Environmental impact can be defined as any alteration of environmental conditions, adverse or

beneficial, caused or induced by the action or set of actions under consideration.

Various operations involved in the “Group Housing” have been studied in details to identify, predict

and evaluate impacts on various environmental components. The identified impacts were quantified

using mathematical models to a possible extent so as to estimate the future environmental scenario.

A. AIR ENVIRONMENT

AMBIENT AIR MONITORING REPORT

TEST RESULT

Parameter Test Method Results Units

Limits as per

Environment

(Protection) Act.

Particulate Matter (PM10) IS:5182 Part-

XXIII 81.38 µg /m3 100.0

Particulate Matter (PM2.5) CPCB Volume – 1

/ Gravimetric 40.16 µg /m3 60.0

Sulphur Dioxide(SO2) IS:5182 Part-II 11.23 µg /m3 80.0

Nitrogen Dioxide(NO2) IS:5182 Part-VI 19.42 µg /m3 80.0

Carbon monoxide (as CO) IS:5182 Part-X <1.15 mg/m3 4.0

Page 5: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT

PROJECT : GROUP HOUSING

PROMOTER: VEETRAG BUILDCON PVT. LTD.

DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017

ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

NOVEMBER’ 2017

CONSTRUCTION PHASE

SOURCES

1. Vehicular Exhaust

The major source of pollution in construction phase

Pollution load from the same is calculated as:

Pollution Load = No. of trucks × Emission Factors ×

Due to movement of average 05 trucks short term pollution load is given in table:

Parameter Emission Factor

CO

NOx

SPM

SO2

HC

* Source: CPCB Publication, 1998

2. Emissions from Construction equipments

The fugitive dust emission sources are:

• Haul road movements

• Construction

• Material Handling

• Finishing

MITIGATION MEASURES

SOURCES

Dust & emissions from vehicular

POLLUTION LOAD DUE TO CONSTRUCTION

CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN

PROMOTER: VEETRAG BUILDCON PVT. LTD.

EESPL/VBPL/002/EC/INFRA/2017-18/363

ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

The major source of pollution in construction phase was vehicles carrying construction material.

Pollution load from the same is calculated as:

Pollution Load = No. of trucks × Emission Factors × Deterioration Factor

Due to movement of average 05 trucks short term pollution load is given in table:

Emission Factor (g

/km)*

Deterioration Facor

(g /km)*

Pollution Load (g/km)

4.5 1.33

1.21 1

0.8 1.595

0.15 1

1.21 1

: CPCB Publication, 1998

2. Emissions from Construction equipments

The fugitive dust emission sources are:

MANAGEMENT

Dust & emissions from vehicular • Regular sprinkling of water on the haul road.

CO

61%

NOx

12%

SPM

13%

SO2

2%

HC

12%

POLLUTION LOAD DUE TO CONSTRUCTION

VEHICLES

CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN

vehicles carrying construction material.

Deterioration Factor

Due to movement of average 05 trucks short term pollution load is given in table:

Pollution Load (g/km)

29.92

6.05

6.38

0.75

6.05

MANAGEMENT

Regular sprinkling of water on the haul road.

Page 6: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT

PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN

PROMOTER: VEETRAG BUILDCON PVT. LTD.

DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363

ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

NOVEMBER’ 2017

exhaust. • Speed restriction of all vehicles.

• PUC certified vehicles were deployed.

The dust emission sources are:

• Haul road movements

• Construction

• Material Handling

• Finishing

• Water spraying to prevent dust pollution from different

sources of construction.

• All transportation vehicles were suitably covered with

tarpaulin & overloading of the vehicles was avoided.

• Covering of the construction site on all four sides to a

considerable height to prevent dust emissions and other

pollutants to the surrounding environment.

• Ensuring vehicles stick to the access track to prevent mud

and dirt being deposited on roads.

POST CONSTRUCTION PHASE

SOURCES

02 nos. D.G Set of capacity 300 kVA will be installed for power backup for common area.

Impact on Air Quality

The impact on air quality is assessed based on emissions of the proposed DG set and vehicular

emissions. NOx and CO will be the important pollutants emitting from these sources.

Prediction of impacts on air environment has been carried out employing mathematical model based on

a steady state Gaussian plume dispersion model designed for multiple point sources for short term. In

the present case, AERMOD Version 7.1.0 dispersion model for different stability state Gaussian plume

dispersion, designed for multiple point and line sources for short term and developed by United States

Environmental Protection Agency [USEPA] has been used for simulations from point and line sources.

MANAGEMENT PLAN

SOURCES MANAGEMENT

• Exhaust from D.G. set – • EPA/CPCB certified DG set was deployed.

• D.G. set was provided with effective stack height as per the norms

of CPCB above the roof of the D.G. house.

• Low sulphur content fuel (HSD - Sulphur content 0.05%) is being

used.

• Emission due to

vehicular exhausts

especially congestions

• Sufficient width of driveways (max 6.3 m.) to ensure smooth

traffic movements.

• Provisions of fully internalized parking including the parking

Page 7: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT

PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN

PROMOTER: VEETRAG BUILDCON PVT. LTD.

DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363

ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

NOVEMBER’ 2017

during peak traffic

hours.

facilities for the visitors.

• Guided traffic ways within the project site.

• Speed humps are installed for speed restrictions inside the project

area.

• The area will cover 5256.69 Sq. m. under tree plantation and

Herbs & shrubs which will help to contain the emission within

permissible norms.

B. WATER ENVIRONMENT

GROUND WATER ANALYSIS REPORT

RESULTS

Essential test as per IS:10500-2012

S. No. Parameter Test Method Results Units Desirable

Limit

Extended

Limit

1. pH IS:3025(Part-11) 7.68 - 6.5 – 8.5 -

2. Colour IS:3025(Part-4) <5.00 Hazen 5 25

3. Odour IS:3025(Part-5) Agreeable - - -

4. Taste IS:3025(Part-8) Agreeable - - -

5. Turbidity IS:3025(Part-10) 2.9 NTU 5 10

6. Total Hardness(as

CaCO3)

IS:3025(Part-21) 178.33 mg/l 200 600

7. Chloride(as Cl) IS:3025(Part-32) 92.15 mg/l 250 1000

8. Calcium (as Ca) IS: 3025 (P- 40) 40.22 mg/l 75 200

9. Iron (as Fe) IS:3025(Part-52) 0.08 mg/l 0.3 1

10. Nitrate (as NO3) IS: 3025 (P- 34) 4.1 mg/l 45 No

Relaxation

11. Total Dissolved Solid IS:3025(Part-16) 387 mg/l 500 2000

12. Alkalinity ( as Ca CO3) IS: 3025 (P- 23) 131.17 mg/l 200 600

13. Sulphate (as SO4) IS: 3025 (P- 24) 60.35 mg/l 200 400

MICROBIOLOGICAL REQUIREMENT

RESULTS

S.No. Parameter Test Method Results Required as per IS-

10500:2012

Page 8: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT

PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN

PROMOTER: VEETRAG BUILDCON PVT. LTD.

DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363

ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

NOVEMBER’ 2017

1. Escherichia coli IS-1622 Absent Absent/100ml

2. Coliform Bacteria IS-1622 Absent Absent/100ml

*Analysis report enclosed as Annexure V

Management Plan:

S.

No.

Particulars Investigated environmental

impacts

Measures for minimizing and / or

offsetting adverse impacts

identified and their Mitigation

measures

1. Details of Investigated Environmental impacts due to

i. Project

constructio

n

Groundwater contamination

due to domestic waste water

release from labors camp.

Open defecation / other allied

activity.

Dust emissions due to vehicular

movement.

Impact of water movement on

and off site and its associated

erosions, sedimentation and

potential pollution effects.

Septic tanks followed by soak pits to prevent

groundwater contamination.

Provide adequate number sanitation facility and

awareness to workers on the subject.

Controlled water sprinkling @ of 1.0 – 1.5 L /

sq.m. at the interval of 1 hr is recommended

(water requirement subjected climatic / site

conditions).

Soil and water management structures will be in

place prior to the commencement of

construction works, and any advance activities

likely to generate erosion and sedimentation

impacts.

Silt fencing with sausage, Temporary silt fencing

will be installed at selected locations across the

site.

Stockpiles will not be located in proximity to

existing or proposed drainage lines and storm

water inlets.

ii. Regular

operations

Waste water leakage

Odor generation

Seepage to groundwater

Generation of large volume of

wastewater than anticipated

Check valve, flange, at regular defined interval,

and regular maintenance of WWTP log book

WWTP

Plat locally available active fragrance plants

around WWTP

Regular physico-chemical monitoring of

groundwater.

At least 10 % higher capacity of WWTP is

recommended

Rainwater contamination

Wastewater will be flow in closed system; hence possibility of

rainwater contamination will be minimum.

Regular cleaning of drains / associated structure

Page 9: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT

PROJECT : GROUP HOUSING

PROMOTER: VEETRAG BUILDCON PVT. LTD.

DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017

ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

NOVEMBER’ 2017

Disease vector generation

Sludge Management

Excessive fresh water usage

Others water usage measures

2. Unhygienic

condition, safe

drinking water

during

construction &

operation phase

One toilet facility (@ per 25 workers), One Urinal facility (@ per 50 workers) and

one hand washing (@ per 50 workers) facility will be provided.

Potable water will be provided (@ 5 L / person) and placed in / at various

locations readily accessible to all.

The employer will notify each employee of the location of the sanitation facilities

and water and will allow each employee reasonable opportun

workday to use them. And also will inform the importance good hygiene practices,

communicable diseases, and retention of urine / wastewater.

3. Assessment of significance of impacts (Criteria for determining significance, Assigning

Impact source Source

Drainage

Plantation

areas

Consumption

Liter 7

%

0

10

20

30

40

50

60

70

liter

CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN

PROMOTER: VEETRAG BUILDCON PVT. LTD.

EESPL/VBPL/002/EC/INFRA/2017-18/363

ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

Disease vector generation Take necessary suitable action, like sprinkling of

near WWTP site, regular monitoring for generation of vector in

WWTP water.

• Sludge pretreatment and utilization as manure

• Excessive sludge may be sent to public space plantation

Excessive fresh water usage Uses of water efficient fixtures were considered, which will help

in achieve approximately 36 % reduction in fresh water demand.

Details of the same are as represented in given below graph:

Electromagnetic Current Water meter will be installed at various

locations to monitor the water usage;

• Raw water collection points

• WWTP Inflow

• WWTP out Flow

• And others

One toilet facility (@ per 25 workers), One Urinal facility (@ per 50 workers) and

one hand washing (@ per 50 workers) facility will be provided.

Potable water will be provided (@ 5 L / person) and placed in / at various

locations readily accessible to all.

The employer will notify each employee of the location of the sanitation facilities

and water and will allow each employee reasonable opportun

workday to use them. And also will inform the importance good hygiene practices,

communicable diseases, and retention of urine / wastewater.

Assessment of significance of impacts (Criteria for determining significance, Assigning

Source Project activity GW

Sewer networks 3

Roads 2

Landscape / greenbelt 2

Fertilizer application 2-4

BathingFlushing (Dual

3 L & 6 L)Washing @ 7.5

LPMOther use

20 21 15

53 62

CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN

Take necessary suitable action, like sprinkling of Bleach Powder

site, regular monitoring for generation of vector in

Sludge pretreatment and utilization as manure

Excessive sludge may be sent to public space plantation

Uses of water efficient fixtures were considered, which will help

in achieve approximately 36 % reduction in fresh water demand.

in given below graph:

Current Water meter will be installed at various

One toilet facility (@ per 25 workers), One Urinal facility (@ per 50 workers) and

one hand washing (@ per 50 workers) facility will be provided.

Potable water will be provided (@ 5 L / person) and placed in / at various

The employer will notify each employee of the location of the sanitation facilities

and water and will allow each employee reasonable opportunities during the

workday to use them. And also will inform the importance good hygiene practices,

communicable diseases, and retention of urine / wastewater.

Assessment of significance of impacts (Criteria for determining significance, Assigning significance)

GW FL WR CW

N/A 5 N/A

N/A 2 N/A

N/A 1 N/A

4 N/A 1-4 N/A

Other useTotal reduction

(%)

23

36

Page 10: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT

PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN

PROMOTER: VEETRAG BUILDCON PVT. LTD.

DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363

ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

NOVEMBER’ 2017

Table: Environmental Monitoring Plan

(Responsibility: competent EHS / authorized person)

S.No. WATER ENVIRONMENTAL MONITORING PROGRAM

Cost estimate*

(Rs. approx.)

i. Groundwater / Surface water / Rain water / others

S.No. Sample Collection Points S1 S 2 S 3 Freq. Rs.*

1. Ground water monitoring plan

1. Upstream (Ref. point WWTP) 6 M 2,500

2. Downstream (Ref. point

WWTP)

6 M 2,500

3. Near WWTP 6 M 2,500

4. Total 7,500

2. Rain water

5 Rain water (run-off) RWH /

Collection point

Se 2,500

Se 2,500

Total 5,000

ii. Wastewater Treatment Plant (WWTP)

S.No. Sample Collection Points S1 S 2 S 3 Freq. Rs.*

Diffuse Source Pesticide / herbicide application 2-4 N/A 2-3 N/A

Drainage 2 N/A 4 N/A

Planting/ground preparation 2 N/A 2-5 N/A

Felling - N/A - N/A

Other diffuse sewage sludge reuse / recycling to

land

2-4 N/A 5 N/A

atmospheric deposition N/A N/A - N/A

Point

Source

Wastewater Wastewater primarily domestic 1 N/A 5 N/A

Storm water and emergency overflow 1 N/A 5 N/A

Wastewater primarily septic tanks 3-4 N/A 4 N/A

Impacts scoring: 1 = minimum relevance, 5 = maximum relevance, N/A = Not Applicable, ;GW: Ground

water, WR: Water reservoir (rain water collection pits), FL: Flowing Water, CW: Coastal Water; Note:

Degree of relevance based on known history of occurrences

Page 11: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT

PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN

PROMOTER: VEETRAG BUILDCON PVT. LTD.

DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363

ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

NOVEMBER’ 2017

3. WWTP (STP - performance evaluation program)

1. Equalization tank cum collection tank 3 M 2,500

2. Biological reactor (each tank) 3 M 2,500

3 Treated water tank 3 M 2,500

4 Total 7,500

4. Regular WWTP (STP regular monitoring program)

5 Equalization tank cum collection tank 6 M 2,500

6 Treated water tank 6 M 2,500

Total 5,000

5. WWTP (STP -Sludge monitoring plan)

7 Sludge physico- chemical analysis 6 M 3,000

8 Sludge leachate physico-chemical analysis 6 M 3,000

Total 6,000

*EC/CTO/CTE compliance reports will be regularly submitting to State Pollution Control Board /

concerned agencies, Water Cess yearly,

M: Monthly; S: Sample; Se: Seasonal ; Freq.: Frequency : Note: monitoring for all key parameters as

described by CPCB

RAINWATER HARVESTING SCHEME

06 Rain Water Harvesting pits of size 3 m length x 3 m width x 3 m depth with PVC slotted pipe upto

minimum depth of 30 m are provided.

Total Annual Recharge to Ground Water Regime of the area through rainwater harvesting structure

would 51,474.00 m3/ annum.

However, Rain Water Harvesting pit of size 3 m length x 3 m width x 3 m depth with PVC slotted pipe

upto minimum depth of 30 m as following figure.

Page 12: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT

PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN

PROMOTER: VEETRAG BUILDCON PVT. LTD.

DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363

ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

NOVEMBER’ 2017

C. LAND ENVIRONMENT

SOIL ANALYSIS REPORT

RESULTS

S.No. PARAMETERTS TEST METHOD RESULT UNIT

1. pH(1:10 suspension) IS:2720(Part-26) 7.56 -

2. Electrical Conductivity mS/cm IS:2720(Part-21) 135.12 mS/cm

3. Water holding Capacity STP/SOIL 37.25 % by mass

4. Porosity STP/SOIL 46.31 % by mass

5. Sand STP/SOIL 54.16 % by mass

6. Clay STP/SOIL 32.10 % by mass

7. Silt STP/SOIL 13.74 % by mass

8. Bulk Density STP/SOIL 1.56 mg /m³

9. Moisture Content STP/SOIL 6.38 % by mass

10. Calcium (as Ca) STP/SOIL 375.3 mg/kg

11. Magnesium(as Mg) STP/SOIL 216.10 mg/kg

12. Sodium (as Na) STP/SOIL 178.33 mg/kg

13. Potassium(as K) STP/SOIL 109.12 mg/kg

14. Cation Exchange Capacity STP/SOIL 7.23 Meq/100gm

Page 13: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT

PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN

PROMOTER: VEETRAG BUILDCON PVT. LTD.

DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363

ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

NOVEMBER’ 2017

15. Sodium Absorption Ratio STP/SOIL 1.65 -

16. Nitrogen STP/SOIL 0.078 % by mass

17. Phosphorus(P2O5) STP/SOIL 9.81 mg/kg

18. Zinc (Zn) STP/SOIL 3.17 mg/kg

19. Organic Matter STP/SOIL 0.69 % by mass

Soil analysis report is enclosed as Annexure V.

D. NOISE ENVIRONMENT

NOISE MONITORING REPORT

RESULTS

S. No Test Parameters Results Units Requirement (as per CPCB Guidelines Limits in

dB (A) Leq

1.

Lday

(6.0 AM TO 10.0 PM)

51.3

dB(A)

Category of Area/ Zone Day Time Night Time

Industrial Area 75 70

2. Lnight

(10.0 PM TO 6.0 AM)

39.9 dB(A)

Commercial Area 65 55

Residential Area 55 45

Silence Zone 50 40

CONSTRUCTION PHASE:

During construction phase following will be the tentative sources of noise:

Name of Source Noise level at 16 m from

source {dB (A)}

Noise level at 1 m from source

{dB (A)}

Back hoe/Loader 81 105

Dump truck 83 107

Generator Not considered 75 (as prescribed by CPCB)

To understand the combined effect of these noise levels on the nearby community, Custic 3.2 (Lakes

Environmental – USEPA approved) scientific model has been used to estimate the noise levels at

different distances from the proposed project. All the major noise generating machineries like D.G.

Sets, Pumps, Trucks, vibrators, drilling machine, etc., are considered in this model. The noise level at

project boundary due to different sources is calculated based on the following formula:

Lp2 = Lp1 – 20 log (r2 / r1) – Ae1, 2

where, Lp1 and Lp2 are sound levels at points located at distance r1 / r2 from the source and Ae1,2 is the

excess attenuation due to environmental conditions. The resultant noise level is obtained by adding

existing maximum levels to that of predicted level.

Page 14: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT

PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN

PROMOTER: VEETRAG BUILDCON PVT. LTD.

DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363

ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

NOVEMBER’ 2017

Further due to natural attenuation effects, by proper green belt development, design / maintenance of

machines, providing PPE’s to workers, etc., the impact on noise levels will be minimal.

MANAGEMENT PLAN

SOURCES MANAGEMENT

Major sources of noise

pollution:

• Vehicular traffic

• Heavy moving

machinery

• Operation of D.G.

sets, etc.

• The construction area was shielded with help of tarpaulin sheets.

• Complete construction work especially heavy earth work was done

during day time.

• Traffic planning and management made adequate to ensure

uninterrupted traffic movement in the area so as to minimize the noise

due to congestion.

• The vehicles were regularly maintained and optimum use of the same

will be made.

• Moving parts of the machines were maintained properly so as to avoid

metal-to-metal impact noise.

• The D.G. sets used are eco friendly with minimum noise.

• Ear plugs were provided to the workers.

POST CONSTRUCTION PHASE

SOURCES MANAGEMENT

• Vehicular

noise

• Operation of

D.G. sets.

• EPA/CPCB certified DG set conforming to the standards for noise will be used.

• D.G. set will be housed in an inbuilt acoustic enclosure, which will help to

contain the noise within the permissible standards.

• The driveways will have sufficient width so that there is no congestion of

vehicles during peak hours which lead to increase in the noise levels.

• Adequate parking including provisions of visitors parking.

• Entry & exits will be manned with trained & efficient security to ensure

smooth flow of vehicles.

• There is less starting and stopping and the vehicles are speed restricted to

ensure the noise within the permissible limits.

• The area will cover 5256.69 Sq.m area under landscape, which will help to

absorb noise.

E. BIODIVERSITY

Biotic component comprises of both plant animal communities which interact not only within and

between them self but also with a biotic i.e. physical and chemical components of the environment.

Page 15: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT

PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN

PROMOTER: VEETRAG BUILDCON PVT. LTD.

DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363

ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

NOVEMBER’ 2017

Generally a biological community is being dependent on the environmental conditions and resources

of its location may change if there are many major changes in the environment. The number of

variables like temperature, humidity, atmospheric conditions, soil, topography, etc. is responsible for

maintaining the homeostasis of the environment and a change in any one or more of these variables

may tend to destabilize the ecosystem. In such cases the change may be mostly irreversible.

Therefore, the need to assess the changes of the animal and plant resources is primary requisite as

these living things determine the environmental healthiness of any given ecosystem or environment.

Biological impact assessment generally includes listing of plants and animals present at the project

site. The identified species are then checked for their status according to IUCN list of threat

categories viz., endemic, endangered, vulnerable, rare, indeterminate and insufficiently known.

As part of this assignment, a flora and fauna study has been conducted for the proposed housing

Project at Jodhpur, Rajasthan. Field study was undertaken in the month of September 2017. The

proposed site and habitats adjacent to the site were surveyed for flora and fauna species.

1. Objective of Study

The present work was undertaken with the following objectives:

• To collect the baseline terrestrial biodiversity status regarding flora and fauna in the project

area.

• To evaluate the dominant species of plant and animal. Secondary data also is collected from the

local residents.

• To identify the endangered / threatened / scheduled species in the study area (both flora and

fauna). The conservation plan will be given if any wildlife species of schedule -I is present

there.

• To mark the ecologically sensitive areas such as national parks/ sanctuaries.

• To suggestion and recommendation for plantation and green belt.

• To assess the effect of construction and operation of the project on existing ecology.

On the basis of onsite observations a checklist of flora and fauna was prepared

2. FLORAL STUDY

Trees:

Herbs and Grasses

S.No Species name Binomial name Family

1 Neem Azadirachta indica Meliaceae

2 Khejari Prosopis cineraria Fabaceae

S.No Species name Binomial name Family

3 Peli Kanteli Argimone maxicana Papavaraceae

Page 16: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT

PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN

PROMOTER: VEETRAG BUILDCON PVT. LTD.

DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363

ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

NOVEMBER’ 2017

Shrubs

S.No Species name Binomial name Family

1 Aak Calotropis procera Asclipiadaceae

2 vilayati babool Prosopis juliflora Fabaceae

3 Sharpunkha Tephrosia purpurea Fabaceae

3. FAUNA

Faunal studies were also conducted during September 2017. During the survey of the study site, no

threatened/ endemic species in and around the study area were observed.

Major Features in the Study Area:

Feature Name / Status

National Park / Sanctuary Nil

Biosphere Reserve /Tiger Reserve/ Elephant Reserve /any other Reserve Nil

Habitat for migratory birds Nil

Corridor for animals of Schedule I & II of the Wildlife (Protection) Act, 972 Nil

A) PIECES: No sustain water body observed at the site of study area.

B) AMPHIBIA: Not observed.

C) REPTILIA

Particulars

S.

No.

Common name Binomial name Family Schedule

IW(P)A / IUCN

Reptilian 1 Oriental Garden Lizard Calotes versicolor Agamidae LC

2 Yellow-Green House

Gecko

Hemidactylus

flaviviridis

Agamidae LC

D) AVIS OR AVIFUANA

Site specific avifaunal species observed during the site visit:

S.No Common Name Binomial Name Family Schedule

IW(P)A / IUCN

1 Common Myna Acridotheres tristis Sturnidae IV

2 House crow Corves splendens Corvidae IV

4 Kanteli Solanum zanthocarpum Solanaceae

5 Onth Kantalo Echinops echinatus Asteraceae

6 Raimuniya Lantana camera Verbenaceae

Page 17: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT

PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN

PROMOTER: VEETRAG BUILDCON PVT. LTD.

DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363

ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

NOVEMBER’ 2017

3 House Sparrow Passer domesticus Passeridae IV

4 Pigeon Columba livia Columbidae IV

E) MAMMALIA

Particulars S. No Common Name Binomial Name Family Schedule

Mammals 1 Five stripped palm squirrel Funambulus pennantii Sciuridae IV

A Endangered species Not observed during the study period.

B Endemic species Not observed during the study period.

C Migratory species Avifaunal species may be migratory.

D Aquatic fauna NIL

5. Plantation for Green belt development

The greenbelt development plan aims at overall improvement in the environmental conditions of the

region. Green belt planning will be done with ecological perspectives for project. Nature of pollutants,

availability of space and dominant wind directions should be considered. This will help in reducing the

concentration of pollutants and will also be effective in attenuating noise levels.

Moreover, keeping in view the characteristics of soil, water quality and topography of the area the

following additional aspects should also be considered. Plant species should have such characteristics:

� Fast growing and perennial species;

� Locally available species which are tolerable to soil and climate of area;

� Low water requirement and heat tolerant;

� Pest resistant species;

� Tolerance to inorganic chemicals;

6. Suggested plants

Table 1. Following listed species are suggested to develop greenbelt around the project

site:

S.No.

Suitable Tree species

Common Name Binominal Name

1 Neem Azadirachta indica

2 Ardu Ailanthus excelsa

3 Gulmohar Delonix regia

4 Khejari Prosopis cineraria

Page 18: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT

PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN

PROMOTER: VEETRAG BUILDCON PVT. LTD.

DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363

ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

NOVEMBER’ 2017

5 Pipal Ficus religiosa

6 Banyan tree Ficus bengalensis

7 Imli Tamarindus indica

8 Arjun Terminalia arjuna

9 Ashok Polyalthia logifolia

10 Amaltas Cassia fistula

Total

Shrub:

S.No. Common Name Botanical Name

1 Bougainvillea Bougainvillea glabra

2 Chandni Tabernaemontana divaricata

3 Champa Plumeria alba

4 Thunja /Morpankhi Thuja occidentalis

5 Kaner Nerium oleander

6 Gudhal Hibiscus rosa-sinensis Linn.

Herbs:

S.No. Common Name Botanical Name

1 Rose Rosa macdub

2 Genda Tagetes patula

Suggestion of other Indoor Herbs

Areca Palm

This leafy plant can be grown anywhere in the house

in indirect sunlight. The plant can grow as high as 30

feet outdoors but it is restricted to about seven feet at

indoor locations. Put it in a small container and the

crowded roots will help in limiting the size of the

plant. It also works effectively as an effective

humidifier. Water enough to keep the soil moist and

let it dry a little between watering in winter.

English Ivy

This green plant filters out formaldehyde found in

some household cleaning products. The plant needs

bright light to look fresh and might attract pests if they

do not receive enough light.

Aloe Vera Aloe plants like to be dry and warm, not wet and cold,

so water only when we see that the soil in the pot is

Page 19: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT

PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN

PROMOTER: VEETRAG BUILDCON PVT. LTD.

DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363

ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

NOVEMBER’ 2017

dry. It is a widely-known fact that aloe Vera can be

used to achieve a great complexion.

Indian Basil

Commonly known as Tulsi. This plant has a number of

medicinal properties. Requires regular sunlight, so the

best place to keep this plant would be a sunny

window.

Dracaena

This plant does not require direct sunlight and can

grow up to 12 feet in height can place it near a sheer

curtain or a window

Spider Plant

The plant derived this unique name due to its

uniquely-shaped leaves, which dangle like spiders on a

web. The plant is also completely safe if you have pets.

If you see the plant turning a little brown, do not

worry. It is normal and it will get back to its green self

soon

Snake Plant

This plant is also called mother-in-law’s tongue or

Saint George’s sword. It is one of the top air-purifying

plants identified by NASA. This plant is one of the

easiest to grow and requires no extra attention.

Weeping Fig

This leafy plant helps against emissions from curtains,

carpets and furniture. The weeping fig initially takes

time to grow, but once it is in complete form, it can

grow up to 10 feet. Its Long lasting plant.

7. Post Plantation Care

• Water in trees at least once a week, barring rain, and more frequently during hot weather.

• Keep the soil moist but not soaked;

• Overwatering causes leaves to turn yellow or fall off.

• Other follow-up care may include minor pruning of branches damaged during the planting

process.

• Prune sparingly immediately after planting and wait to begin necessary corrective pruning

until after a full season of growth in the new location.

• Tree guard should be around the saplings until the plant reaching at mature stage.

• Fertilizers and pesticides/insecticides should be given proper time.

Page 20: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT

PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN

PROMOTER: VEETRAG BUILDCON PVT. LTD.

DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363

ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

NOVEMBER’ 2017

• Construction workers shall be made aware regarding the importance of natural resources.

With suitable monitoring, pep talks, meetings and guidance provided.

8. IMPACT OF PROJECT ACTIVITIES ON BIODIVERSITY DIRECT, INDIRECT AND

CUMULATIVE IMPACT ON FLORA

• Direct Impact:

Clearing of project site for construction activities –Sparse vegetation of trees, shrub and herbs

which are commonly distributed throughout and none of rare, endangered or threatened or

endemic species was observed during survey / reported. These will be cleared during site

preparation. Therefore, the impact will be negligible and not very significant. Only one tree will be

cut during the clearing and construction time of project.

• Indirect Impact

• Construction activity is likely to affect the movement of the animal

• Increase in noise may affect the feeding, breeding and movement of animals. Felling of trees

may affect the avifauna.

• Likely settling of dust to be generated by movement of vehicles and other construction

activities on leaves may results in to stunted growth of vegetation and may also affect the

capacity of production.

• Large numbers of labour population will influx the area during construction phase.

• Dumping of huge quantity of excavated earth material may lead to loss of flora in the project

area

• The soil erosion due to natural and anthropogenic activities may cause major threat to survival

of vegetation.

• Cumulative Impact

• Indirect and cumulative impacts are associated with various construction activities such as

clearing of vegetation movement of vehicles, construction equipments & machineries etc,

interferences due to influx of labours etc.

• The losses of land for various project units will also not adversity affect the fauna as similar

habitat is present throughout the project immediate influenced area. Therefore, impact due

to loss of habitat for birds, reptiles and mammals of the project area is not expected.

• Impacts on surrounding fauna due to movement of vehicles, machinery, equipments and

work force may slightly interfere in animal movements.

• Intermittent settlements any adverse impacts on wildlife are ruled out.

Mitigation measures

Page 21: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT

PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN

PROMOTER: VEETRAG BUILDCON PVT. LTD.

DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363

ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

NOVEMBER’ 2017

1. EFFECTIVE REMOVAL OF POLLUTANTS

1) Plants grow under conditions of adequate nutritional supply (for healthy and better growth),

2) Absence of water stress (to maintain openness of stomatal apertures and form of epidermal

structures),

3) Well-exposed to atmospheric conditions of light and breeze (i.e. away from engineering structures

hindering free flow of air) to maintain free interaction with gases.

• Plant leaves function as efficient gas exchange systems. Their internal structure allows rapid

diffusion of water-soluble gases. These characteristics allow the plant to respire and

photosynthesize, and they can also remove pollution from the air. Characters of plants

including shapes of crowns considered necessary for effecting absorption of pollutant gases

and removal of dust particles are as follows:

1) Tolerance towards pollutants in question, at concentrations, that are not too high ( to be

instantaneously lethal) They are good absorbers of sulphur dioxide. Roadside hedges can

reduce traffic generated air borne lead

2) Longer duration of foliage,

3) Freely exposed foliage , through

• Adequate height of crown,

• Openness of foliage in canopy,

• Big leaves( long and broad laminar surfaces),

• Large number of stomatal apertures,

• Stomata well- exposed ( in level with the general epidermal surface)

2. REMOVAL OF SUSPENDED PARTICULATE MATTER

1) Height and spread of crown,

2) Leaves supported on firm petioles,

3) Abundance of surfaces on bark and foliage, through

• Roughness of bark,

• Epidermal outgrowth on petioles,

• Abundance of auxiliary hairs,

• Hairs or scales on laminar surfaces,

• Stomata protected (by wax, arches/rings, hairs etc.)

The plant species should be capable of sorption of dust pollutants and barrier of noise pollution.

Combined deficiency of a variety of species will be contributed to reach the goals of restrict the

pollution.

Page 22: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT

PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN

PROMOTER: VEETRAG BUILDCON PVT. LTD.

DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363

ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

NOVEMBER’ 2017

3. MITIGATION OF IMPACT

The mitigation measures of biological impacts are aimed at (in order of preference):

i) Avoid impact,

ii) Minimize impact,

iii) Rectify impact,

iv) Compensate for impact.

Setting aside or exclusion of critically important areas, compensatory afforestation, creation of green

belts, rehabilitation of species or individuals are basic actions taken for mitigation of impact. While

creating green belt and undertaking the afforestation works, it is required to plant indigenous/local

plants and as for as possible exotics should not be introduced. The cost of eco-restoration of the site

should be included in the project cost. This is desirable on two counts:

i) It ensures allocation of fund for undertaking the rehabilitation of the area during and also after the

project period is over.

ii) It also acts as deterrent in selection of site for the project by bringing in the cost of eco-restoration

which can be enormous in cases where activities are proposed on a critical ecosystems.

9. CONCLUSION

The present study is with the objective to minimize adverse environmental impacts as discussed. The

study covers all possible environmental issues involved in the project and the necessary mitigation

measures. It was observed that diversity of trees; shrub and herbs were in better at site. Native and

local species will be planted in post construction phase. Faunal diversity of the site was also very low.

Therefore, we can say that the biological diversity of the study site not much more impacted by the

present proposed infrastructure development and the sustainable environment scenario can be

retained by the proper plantation in post construction period.

F. THE SOCIO ECONOMIC ENVIRONMENT

OBJECTIVES

The broad objectives of the socio-economic impact assessment are:

1. To study the socio-economic status of the people living in the study area.

2. To assess the impact on socio-economic environment due to the project concerned.

3. To evaluate the community development measures proposed to be taken up by the Project

Proponent, if any.

The studies carried out are descriptive and exploratory in nature.

Page 23: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT

PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN

PROMOTER: VEETRAG BUILDCON PVT. LTD.

DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363

ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

NOVEMBER’ 2017

Habitation

The location of the proposed Group Housing Project, District Jodhpur is in Pal. The nearest human

settlements are as follows in the study area periphery of the project.

• Pal 1.75 km S

The habitation is Semi - Urban.

Population of the Study area:

The households with a family size of 5 approx, as per the Census of India, 2011. The male population

constitutes 53.92% and female population constitute of 46.07%.

Population Profile:

Study Area Household Population Males Females

Pal Village (OG) WARD NO.-0066

(Rural MDDS CODE:085023) 3681 20621 11119 9502

*Census of India, 2011

Gender Ratio

The gender ratio is 854 in the study area, much below the district Jodhpur gender ratio of 915 as per

Census of India, 2011.

For children below 6 years the gender ratio is 855 in the study area much low as compared to the 891

Child sex ratio of Jodhpur District. The Child percentage of 6 years below is 14.09% of the total

population.

Study Area Population below 06

years Males Females

Pal Village (OG) WARD NO.-

0066 (Rural MDDS

CODE:085023) 2906 1566 1340

*Census of India, 2011

Literacy Rate of the Study area:

The average literacy rate is 52.02%. The total male literacy rate with respect to the male population is

58.17% and female literacy rate with respect to female population is 45.04%.

Literacy Profile:

Page 24: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT

PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN

PROMOTER: VEETRAG BUILDCON PVT. LTD.

DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363

ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

NOVEMBER’ 2017

Study Area Population Literates Male Literates Females Literates

Pal Village (OG) WARD

NO.-0066 (Rural MDDS

CODE:085023) 10749 6469 4280

*Census of India, 2011

Work Population:

The work participation rate is 32.06%. The total main workers constitute 28.65% with men 23.81% and

female with 4.83%.

The total marginal work population is 3.41% with male population 2.04% and female population with

1.37%.

The total non-working population constitutes of 67.94% with males as 28.06% and females with 39.87%.

Study Area Main Workers Marginal Workers Non-workers

Total Male Fem Total Male Female Total Male Female

Pal Village (OG)

WARD NO.-0066

(Rural MDDS

CODE:085023) 5906 4910 996 705 421 284 14010 5788 8222

*Census of India, 2011

Scheduled Tribes Population

The ST Population is 3.48% of the total population. The male – female population in ST constitutes

1.77% for males and 1.71% for female population indicating female population slightly higher as

compared to men.

Study Area Population Males Females Pal Village (OG) WARD NO.-

0066 (Rural MDDS

CODE:085023) 718 365 353

*Census of India, 2011

SOCIAL INFRASTRUCTURE:

The nearest human settlements are as follows in the study area periphery of the project.

• Pal 1.75 km S

The 500 metres in the remaining periphery has scattered housing amidst vacant plots. Market Place 800

m E. Bus Stand 820 m NNW.

Page 25: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT

PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN

PROMOTER: VEETRAG BUILDCON PVT. LTD.

DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363

ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

NOVEMBER’ 2017

Medical Facility: - Rajkiya Upswastha Kendra 2.35 km S, Gen. Hospital of Chopasni School by Hammar

Singh Rathore 2.28 km NNE, and many other private clinics in 3.0 km ;

Schools:- Rajkiya Uchh Madhyamik Vidhyalaya Pal 2.10 km S, Sanskar International School 1.99 km NW;

Senior Secondry Eng. Medium School 2.29 km NNE; IIHT Jodhpur School 2.24 km NNE; MD Saran Public

Sr. Sec. School Pal Jodhpur 2.56 km S; DPs 2.31 km SE;

Other: Sant Shri Asaram ji 1.46 km S, Hindi Film city 1.47 km S; Shergarh Rawla Prince Highway Jodhpur

370 m ESE; St. Sebastian Church , Pal 1.91 km SSW; Pashu Mela Ground 2.55 km S;

Table: Socio-economic snapshot of nearest habitation:

Transportation was available in all the

aspects :

Bus Govt. Roadways / Private - Tractors, Scooters,

Motor Cycles, (Public transport available).

Roads were observed to be : Pucca, Painted & Cemented

Electricity Supply has been : Irregular

Main Food : Chapatti, Sabji, Dal

Festivals : Holi, Diwali, Gangore, Raksha Bandhan.

Caste / Religion: The principal communities are the largely Hindus with

Agarwals, Jains, Brahmins, and Muslims and minorities of

Christians.

Material Assets of the family : A Two Wheeler / Four Wheeler; Cable Disc ; TV;

Refrigerator

Resources of potable water Government Supply (PHED)& Hand pumps

Nature of Diseases Sun Stroke/ Cold / Cough

IMR & MMR For the State of Rajasthan: As per the RHS Bulletin (March 2012, M/O Health & F.W.,

GOI) The Total Fertility Rate of the State is 3.1. The Infant

Mortality Rate is 47 (SRS 2013) and Maternal Mortality

Ratio is 255 (SRS 2010-12).

Source: field survey and observations.

Socio-Economic observations

Page 26: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT

PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN

PROMOTER: VEETRAG BUILDCON PVT. LTD.

DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363

ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

NOVEMBER’ 2017

The group housing project is amidst the developing area of Jodhpur and is around scattered housing of

Jodhpur. As per the FGD, the need of the nearest habitations is regarding medical facilities. The group

exclaimed its requirement for the various issues and Infrastructural development:

• A modern dispensary as the villagers commutes to Jodhpur City even for minor treatments like

Fever, Stomach-ache etc.

• Government run health programmes are organized in the locality in the study area.

• Cottage industries should receive encouragement.

• Tap water supply is main sources of drinking water and other household use.

CORPORATE SOCIAL RESPONSIBILITY/ENTREPRENEUR SOCIAL RESPONSIBILITY

The CSR would be applicable for every company having net worth of Rs. 500 crore or more, or turnover

of Rs. 1000 crore or more or a net profit of Rs. 5 crore or more during a year, such Companies shall be

required to ensure that every year at least 2% of its average net profits during the three immediately

preceding financial years is spent on CSR activities as may be approved and specified by the company.

Corporate / Entrepreneur Social Responsibility:-

The project is committed towards CSR/ ESR with respect to its applicability with, The Companies Act

2013.

S. No. Activity As per Schedule VII : Budget in INR

Year I Year II Year III

1.

Scholarship to Economically Weaker Sections / Below

Poverty Line Family Students for promotion towards

higher education in Government Schools

50000 - -

2. Rural Development for infrastructure along with

Green Belt in local area. 100000 - -

3. Health Camps for the local residents in Government

Dispensaries 30000

30000 -

4. Local road Maintenance , Road Safety and Traffic

Training -

45000 45000

Total 180000 75000 45000

The project will fulfill its corporate social responsibilities only as per its applicability w.r.t. to Section 135 of The

Companies Act, 2013.

Capital Cost: INR 300000

Page 27: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT

PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN

PROMOTER: VEETRAG BUILDCON PVT. LTD.

DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363

ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

NOVEMBER’ 2017

G. EXPENDITURE ON ENVIRONMENTAL MEASURES

S. No. Particulars Capital Cost

(lacs)

Annual recurring

cost (lacs)

1 Acoustic enclosures & stack attached to DG sets 4 1

2 STP 30 5

3 Rain water harvesting 20 2

4 Solid waste management 6 1

5 Pollution monitoring 2 0.5

6 Fire fighting & emergency handling 35 3

7 Green Belt 5 0.5

8 Training in the area of environment &

occupational health.

1 0.10

TOTAL 103 13.10

***************