CONCEPTUAL PLAN AND ENVIRONMENTAL...
Transcript of CONCEPTUAL PLAN AND ENVIRONMENTAL...
![Page 1: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT](https://reader033.fdocuments.net/reader033/viewer/2022042008/5e711987bf7fbd06606d5184/html5/thumbnails/1.jpg)
PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN
PROMOTER: VEETRAG BUILDCON PVT. LTD.
DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR
NOVEMBER’ 2017
CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN
INTRODUCTION
The existing project is promoted by Veetrag Buildcon Pvt. Ltd. The project is at Khasra no. 66/2, 66/10 &
628/65, Village Pal, Bye pass road, Jodhpur, Rajasthan. The plot area of the project is 28416.21 Sq.m. and
Gross Built up Area is 101359.805 Sq.m. (It is a Violation Case: As 6277.92 Sq.m. additional has been
constructed at the site without taking prior environmental Clearance.).
Environmental Clearance for the project name “Group Housing” had already been granted vide letter No.
F1(4)/SEIAA/SEAC-Raj/Sectt/Project/Cat8(A)b2(616)13-14 dated 31.07.2014 for the following
capacity:
Approved Total plot area : 28416.21 Sq.m.
Approved Built up area : 96458.30 Sq.m.
COST ESTIMATION
The estimated cost of the project is Rs. 150 crores approx. This includes cost of the land as well as
development cost.
AREA STATEMENT
The project Gross B.U.A is increasing by 6277.92 Sq.m. due to change in the flat design and planning.
However, the project capacity will remain same; the project features are tabulated as below:
S.
No
Particular As Per Issued EC Prorposed Now Comments
1 Plot Area 28416.21 28416.21 Sq.m No change
2 B.U.A. 96458.30 Sq.m 97736.48 Sq.m Increased
3. Number of Block Eleven Eleven No change
4 Floors Tower: 11
B+S+13 in all 11 Tower
(B.U.A=96458.30 Sq.m)
Tower No. 1,2,3,4:
B+S+16
&
Tower No. 5,6,7,8,9,10,11:
B+S+14
(B.U.A=97736.48 Sq.m)
EWS/LIG
(B.U.A=3623.325 Sq.m)
B.U.A Increased by
4901.505 Sq.m
5 Facility 520 flats 538 flats
![Page 2: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT](https://reader033.fdocuments.net/reader033/viewer/2022042008/5e711987bf7fbd06606d5184/html5/thumbnails/2.jpg)
PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN
PROMOTER: VEETRAG BUILDCON PVT. LTD.
DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR
NOVEMBER’ 2017
EWS - 82 (EWS) + 04 (LIG)
BUILT UP AREA DETAILS
APPROVED BUILT UP AREA DETAILS
S. No. Tower No. of
Floors
No. of Flats Built up Area (Sq.m.)
1. Tower-1 S+13 26 555.60
2. Tower-2 S+13 26 555.60 3. Tower-3 S+13 52 6007.40 4. Tower-4 S+13 52 6007.40 5. Tower-5 S+13 52 6007.40 6. Tower-6 S+13 52 6007.40 7. Tower-7 S+13 52 6007.40 8. Tower-8 S+13 52 6007.40 9. Tower-9 S+13 52 6007.40 10. Tower-10 S+13 52 6007.40 11. Tower-11 S+13 52 6007.40
Mumty machine room area 660.0 Total 520 69546.87
Commercial Block 2600
Club Area 1250
Basement area 18061.69
Total Built up Area 91458.56
INCREASED BUILT UP AREA DETAILS
S. No. Tower No. of
Floors
No. of Flats Built up Area (Sq.m.)
12. Tower-1 S+16 30 6556.44
13. Tower-2 S+16 30 6556.44 14. Tower-3 S+16 56 7211.40 15. Tower-4 S+16 56 7211.40 16. Tower-5 S+14 52 6873.95 17. Tower-6 S+14 52 6873.95 18. Tower-7 S+14 52 6873.95 19. Tower-8 S+14 52 6873.95 20. Tower-9 S+14 52 6873.95 21. Tower-10 S+14 52 6873.95 22. Tower-11 S+14 54 6385.40
Mumty machine room area 660.0 Total 538 75824.79
Commercial Block 2600
Club Area 1250
Basement area 18061.69
EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623
Total Built up Area 101359.48
![Page 3: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT](https://reader033.fdocuments.net/reader033/viewer/2022042008/5e711987bf7fbd06606d5184/html5/thumbnails/3.jpg)
PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN
PROMOTER: VEETRAG BUILDCON PVT. LTD.
DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR
NOVEMBER’ 2017
PARKING REQUIREMENT
Total Parking Required: 1135 ECS
Open Parking: 407 ECS
Stilt Parking: 156 ECS
Basement: 552 ECS
Club: 20 ECS
Total Parking required for EWS/LIG: 98 Scooters
POWER REQUIREMENT
Demand Load: 3198.8 KW
Connected Load: 5955.2 KW
Source: Electricity Board: JVVNL
Selection of Transformers:
Two transformers will be installed of capacity 2500 kVA each.
Selection of DG sets (For common areas only):
02 nos. D.G Set of capacity 300 kVA will be installed for common areas.
WATER DEMAND
The daily water requirement for the project is 292 KLD (fresh water demand: 210 KLD and the
treated wastewater demand: 82 KLD). The water demand will be met from ground water. Basis for
water demand is given as:
![Page 4: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT](https://reader033.fdocuments.net/reader033/viewer/2022042008/5e711987bf7fbd06606d5184/html5/thumbnails/4.jpg)
PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN
PROMOTER: VEETRAG BUILDCON PVT. LTD.
DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR
NOVEMBER’ 2017
Fresh water
210KLD
Recycle/
Reuse
treated
wastewater
82 KLD
Flats :203 KLD
Flushing : 66 KLD
227 KLD
Waste water
S
T
P
Capacity
300 KLD
162 KLD
Sludge &
Evaporation
losses
11 KLD
STP treated wastewater
WATER BALANCE
Daily Water Demand = 210 + 82 = 292 KLD
53 KLD
Excessive
treated
wastewater
59 KLD
Filter back wash @ 15 cu.m. / hr for 15 min.:4 KLD
3 KLD
Landscaping : 5 KLD
General Washing : 4 KLD3 KLD
6 KLDCommercial Community Facility & Visitors : 7KLD
IDENTIFICATION, PREDICTION AND EVALUATION OF IMPACTS
Environmental impact can be defined as any alteration of environmental conditions, adverse or
beneficial, caused or induced by the action or set of actions under consideration.
Various operations involved in the “Group Housing” have been studied in details to identify, predict
and evaluate impacts on various environmental components. The identified impacts were quantified
using mathematical models to a possible extent so as to estimate the future environmental scenario.
A. AIR ENVIRONMENT
AMBIENT AIR MONITORING REPORT
TEST RESULT
Parameter Test Method Results Units
Limits as per
Environment
(Protection) Act.
Particulate Matter (PM10) IS:5182 Part-
XXIII 81.38 µg /m3 100.0
Particulate Matter (PM2.5) CPCB Volume – 1
/ Gravimetric 40.16 µg /m3 60.0
Sulphur Dioxide(SO2) IS:5182 Part-II 11.23 µg /m3 80.0
Nitrogen Dioxide(NO2) IS:5182 Part-VI 19.42 µg /m3 80.0
Carbon monoxide (as CO) IS:5182 Part-X <1.15 mg/m3 4.0
![Page 5: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT](https://reader033.fdocuments.net/reader033/viewer/2022042008/5e711987bf7fbd06606d5184/html5/thumbnails/5.jpg)
PROJECT : GROUP HOUSING
PROMOTER: VEETRAG BUILDCON PVT. LTD.
DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR
NOVEMBER’ 2017
CONSTRUCTION PHASE
SOURCES
1. Vehicular Exhaust
The major source of pollution in construction phase
Pollution load from the same is calculated as:
Pollution Load = No. of trucks × Emission Factors ×
Due to movement of average 05 trucks short term pollution load is given in table:
Parameter Emission Factor
CO
NOx
SPM
SO2
HC
* Source: CPCB Publication, 1998
2. Emissions from Construction equipments
The fugitive dust emission sources are:
• Haul road movements
• Construction
• Material Handling
• Finishing
MITIGATION MEASURES
SOURCES
Dust & emissions from vehicular
POLLUTION LOAD DUE TO CONSTRUCTION
CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN
PROMOTER: VEETRAG BUILDCON PVT. LTD.
EESPL/VBPL/002/EC/INFRA/2017-18/363
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR
The major source of pollution in construction phase was vehicles carrying construction material.
Pollution load from the same is calculated as:
Pollution Load = No. of trucks × Emission Factors × Deterioration Factor
Due to movement of average 05 trucks short term pollution load is given in table:
Emission Factor (g
/km)*
Deterioration Facor
(g /km)*
Pollution Load (g/km)
4.5 1.33
1.21 1
0.8 1.595
0.15 1
1.21 1
: CPCB Publication, 1998
2. Emissions from Construction equipments
The fugitive dust emission sources are:
MANAGEMENT
Dust & emissions from vehicular • Regular sprinkling of water on the haul road.
CO
61%
NOx
12%
SPM
13%
SO2
2%
HC
12%
POLLUTION LOAD DUE TO CONSTRUCTION
VEHICLES
CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN
vehicles carrying construction material.
Deterioration Factor
Due to movement of average 05 trucks short term pollution load is given in table:
Pollution Load (g/km)
29.92
6.05
6.38
0.75
6.05
MANAGEMENT
Regular sprinkling of water on the haul road.
![Page 6: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT](https://reader033.fdocuments.net/reader033/viewer/2022042008/5e711987bf7fbd06606d5184/html5/thumbnails/6.jpg)
PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN
PROMOTER: VEETRAG BUILDCON PVT. LTD.
DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR
NOVEMBER’ 2017
exhaust. • Speed restriction of all vehicles.
• PUC certified vehicles were deployed.
The dust emission sources are:
• Haul road movements
• Construction
• Material Handling
• Finishing
• Water spraying to prevent dust pollution from different
sources of construction.
• All transportation vehicles were suitably covered with
tarpaulin & overloading of the vehicles was avoided.
• Covering of the construction site on all four sides to a
considerable height to prevent dust emissions and other
pollutants to the surrounding environment.
• Ensuring vehicles stick to the access track to prevent mud
and dirt being deposited on roads.
POST CONSTRUCTION PHASE
SOURCES
02 nos. D.G Set of capacity 300 kVA will be installed for power backup for common area.
Impact on Air Quality
The impact on air quality is assessed based on emissions of the proposed DG set and vehicular
emissions. NOx and CO will be the important pollutants emitting from these sources.
Prediction of impacts on air environment has been carried out employing mathematical model based on
a steady state Gaussian plume dispersion model designed for multiple point sources for short term. In
the present case, AERMOD Version 7.1.0 dispersion model for different stability state Gaussian plume
dispersion, designed for multiple point and line sources for short term and developed by United States
Environmental Protection Agency [USEPA] has been used for simulations from point and line sources.
MANAGEMENT PLAN
SOURCES MANAGEMENT
• Exhaust from D.G. set – • EPA/CPCB certified DG set was deployed.
• D.G. set was provided with effective stack height as per the norms
of CPCB above the roof of the D.G. house.
• Low sulphur content fuel (HSD - Sulphur content 0.05%) is being
used.
• Emission due to
vehicular exhausts
especially congestions
• Sufficient width of driveways (max 6.3 m.) to ensure smooth
traffic movements.
• Provisions of fully internalized parking including the parking
![Page 7: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT](https://reader033.fdocuments.net/reader033/viewer/2022042008/5e711987bf7fbd06606d5184/html5/thumbnails/7.jpg)
PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN
PROMOTER: VEETRAG BUILDCON PVT. LTD.
DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR
NOVEMBER’ 2017
during peak traffic
hours.
facilities for the visitors.
• Guided traffic ways within the project site.
• Speed humps are installed for speed restrictions inside the project
area.
• The area will cover 5256.69 Sq. m. under tree plantation and
Herbs & shrubs which will help to contain the emission within
permissible norms.
B. WATER ENVIRONMENT
GROUND WATER ANALYSIS REPORT
RESULTS
Essential test as per IS:10500-2012
S. No. Parameter Test Method Results Units Desirable
Limit
Extended
Limit
1. pH IS:3025(Part-11) 7.68 - 6.5 – 8.5 -
2. Colour IS:3025(Part-4) <5.00 Hazen 5 25
3. Odour IS:3025(Part-5) Agreeable - - -
4. Taste IS:3025(Part-8) Agreeable - - -
5. Turbidity IS:3025(Part-10) 2.9 NTU 5 10
6. Total Hardness(as
CaCO3)
IS:3025(Part-21) 178.33 mg/l 200 600
7. Chloride(as Cl) IS:3025(Part-32) 92.15 mg/l 250 1000
8. Calcium (as Ca) IS: 3025 (P- 40) 40.22 mg/l 75 200
9. Iron (as Fe) IS:3025(Part-52) 0.08 mg/l 0.3 1
10. Nitrate (as NO3) IS: 3025 (P- 34) 4.1 mg/l 45 No
Relaxation
11. Total Dissolved Solid IS:3025(Part-16) 387 mg/l 500 2000
12. Alkalinity ( as Ca CO3) IS: 3025 (P- 23) 131.17 mg/l 200 600
13. Sulphate (as SO4) IS: 3025 (P- 24) 60.35 mg/l 200 400
MICROBIOLOGICAL REQUIREMENT
RESULTS
S.No. Parameter Test Method Results Required as per IS-
10500:2012
![Page 8: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT](https://reader033.fdocuments.net/reader033/viewer/2022042008/5e711987bf7fbd06606d5184/html5/thumbnails/8.jpg)
PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN
PROMOTER: VEETRAG BUILDCON PVT. LTD.
DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR
NOVEMBER’ 2017
1. Escherichia coli IS-1622 Absent Absent/100ml
2. Coliform Bacteria IS-1622 Absent Absent/100ml
*Analysis report enclosed as Annexure V
Management Plan:
S.
No.
Particulars Investigated environmental
impacts
Measures for minimizing and / or
offsetting adverse impacts
identified and their Mitigation
measures
1. Details of Investigated Environmental impacts due to
i. Project
constructio
n
Groundwater contamination
due to domestic waste water
release from labors camp.
Open defecation / other allied
activity.
Dust emissions due to vehicular
movement.
Impact of water movement on
and off site and its associated
erosions, sedimentation and
potential pollution effects.
Septic tanks followed by soak pits to prevent
groundwater contamination.
Provide adequate number sanitation facility and
awareness to workers on the subject.
Controlled water sprinkling @ of 1.0 – 1.5 L /
sq.m. at the interval of 1 hr is recommended
(water requirement subjected climatic / site
conditions).
Soil and water management structures will be in
place prior to the commencement of
construction works, and any advance activities
likely to generate erosion and sedimentation
impacts.
Silt fencing with sausage, Temporary silt fencing
will be installed at selected locations across the
site.
Stockpiles will not be located in proximity to
existing or proposed drainage lines and storm
water inlets.
ii. Regular
operations
Waste water leakage
Odor generation
Seepage to groundwater
Generation of large volume of
wastewater than anticipated
Check valve, flange, at regular defined interval,
and regular maintenance of WWTP log book
WWTP
Plat locally available active fragrance plants
around WWTP
Regular physico-chemical monitoring of
groundwater.
At least 10 % higher capacity of WWTP is
recommended
Rainwater contamination
Wastewater will be flow in closed system; hence possibility of
rainwater contamination will be minimum.
Regular cleaning of drains / associated structure
![Page 9: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT](https://reader033.fdocuments.net/reader033/viewer/2022042008/5e711987bf7fbd06606d5184/html5/thumbnails/9.jpg)
PROJECT : GROUP HOUSING
PROMOTER: VEETRAG BUILDCON PVT. LTD.
DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR
NOVEMBER’ 2017
Disease vector generation
Sludge Management
Excessive fresh water usage
Others water usage measures
2. Unhygienic
condition, safe
drinking water
during
construction &
operation phase
One toilet facility (@ per 25 workers), One Urinal facility (@ per 50 workers) and
one hand washing (@ per 50 workers) facility will be provided.
Potable water will be provided (@ 5 L / person) and placed in / at various
locations readily accessible to all.
The employer will notify each employee of the location of the sanitation facilities
and water and will allow each employee reasonable opportun
workday to use them. And also will inform the importance good hygiene practices,
communicable diseases, and retention of urine / wastewater.
3. Assessment of significance of impacts (Criteria for determining significance, Assigning
Impact source Source
Drainage
Plantation
areas
Consumption
Liter 7
%
0
10
20
30
40
50
60
70
liter
CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN
PROMOTER: VEETRAG BUILDCON PVT. LTD.
EESPL/VBPL/002/EC/INFRA/2017-18/363
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR
Disease vector generation Take necessary suitable action, like sprinkling of
near WWTP site, regular monitoring for generation of vector in
WWTP water.
• Sludge pretreatment and utilization as manure
• Excessive sludge may be sent to public space plantation
Excessive fresh water usage Uses of water efficient fixtures were considered, which will help
in achieve approximately 36 % reduction in fresh water demand.
Details of the same are as represented in given below graph:
Electromagnetic Current Water meter will be installed at various
locations to monitor the water usage;
• Raw water collection points
• WWTP Inflow
• WWTP out Flow
• And others
One toilet facility (@ per 25 workers), One Urinal facility (@ per 50 workers) and
one hand washing (@ per 50 workers) facility will be provided.
Potable water will be provided (@ 5 L / person) and placed in / at various
locations readily accessible to all.
The employer will notify each employee of the location of the sanitation facilities
and water and will allow each employee reasonable opportun
workday to use them. And also will inform the importance good hygiene practices,
communicable diseases, and retention of urine / wastewater.
Assessment of significance of impacts (Criteria for determining significance, Assigning
Source Project activity GW
Sewer networks 3
Roads 2
Landscape / greenbelt 2
Fertilizer application 2-4
BathingFlushing (Dual
3 L & 6 L)Washing @ 7.5
LPMOther use
20 21 15
53 62
CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN
Take necessary suitable action, like sprinkling of Bleach Powder
site, regular monitoring for generation of vector in
Sludge pretreatment and utilization as manure
Excessive sludge may be sent to public space plantation
Uses of water efficient fixtures were considered, which will help
in achieve approximately 36 % reduction in fresh water demand.
in given below graph:
Current Water meter will be installed at various
One toilet facility (@ per 25 workers), One Urinal facility (@ per 50 workers) and
one hand washing (@ per 50 workers) facility will be provided.
Potable water will be provided (@ 5 L / person) and placed in / at various
The employer will notify each employee of the location of the sanitation facilities
and water and will allow each employee reasonable opportunities during the
workday to use them. And also will inform the importance good hygiene practices,
communicable diseases, and retention of urine / wastewater.
Assessment of significance of impacts (Criteria for determining significance, Assigning significance)
GW FL WR CW
N/A 5 N/A
N/A 2 N/A
N/A 1 N/A
4 N/A 1-4 N/A
Other useTotal reduction
(%)
23
36
![Page 10: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT](https://reader033.fdocuments.net/reader033/viewer/2022042008/5e711987bf7fbd06606d5184/html5/thumbnails/10.jpg)
PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN
PROMOTER: VEETRAG BUILDCON PVT. LTD.
DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR
NOVEMBER’ 2017
Table: Environmental Monitoring Plan
(Responsibility: competent EHS / authorized person)
S.No. WATER ENVIRONMENTAL MONITORING PROGRAM
Cost estimate*
(Rs. approx.)
i. Groundwater / Surface water / Rain water / others
S.No. Sample Collection Points S1 S 2 S 3 Freq. Rs.*
1. Ground water monitoring plan
1. Upstream (Ref. point WWTP) 6 M 2,500
2. Downstream (Ref. point
WWTP)
6 M 2,500
3. Near WWTP 6 M 2,500
4. Total 7,500
2. Rain water
5 Rain water (run-off) RWH /
Collection point
Se 2,500
Se 2,500
Total 5,000
ii. Wastewater Treatment Plant (WWTP)
S.No. Sample Collection Points S1 S 2 S 3 Freq. Rs.*
Diffuse Source Pesticide / herbicide application 2-4 N/A 2-3 N/A
Drainage 2 N/A 4 N/A
Planting/ground preparation 2 N/A 2-5 N/A
Felling - N/A - N/A
Other diffuse sewage sludge reuse / recycling to
land
2-4 N/A 5 N/A
atmospheric deposition N/A N/A - N/A
Point
Source
Wastewater Wastewater primarily domestic 1 N/A 5 N/A
Storm water and emergency overflow 1 N/A 5 N/A
Wastewater primarily septic tanks 3-4 N/A 4 N/A
Impacts scoring: 1 = minimum relevance, 5 = maximum relevance, N/A = Not Applicable, ;GW: Ground
water, WR: Water reservoir (rain water collection pits), FL: Flowing Water, CW: Coastal Water; Note:
Degree of relevance based on known history of occurrences
![Page 11: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT](https://reader033.fdocuments.net/reader033/viewer/2022042008/5e711987bf7fbd06606d5184/html5/thumbnails/11.jpg)
PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN
PROMOTER: VEETRAG BUILDCON PVT. LTD.
DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR
NOVEMBER’ 2017
3. WWTP (STP - performance evaluation program)
1. Equalization tank cum collection tank 3 M 2,500
2. Biological reactor (each tank) 3 M 2,500
3 Treated water tank 3 M 2,500
4 Total 7,500
4. Regular WWTP (STP regular monitoring program)
5 Equalization tank cum collection tank 6 M 2,500
6 Treated water tank 6 M 2,500
Total 5,000
5. WWTP (STP -Sludge monitoring plan)
7 Sludge physico- chemical analysis 6 M 3,000
8 Sludge leachate physico-chemical analysis 6 M 3,000
Total 6,000
*EC/CTO/CTE compliance reports will be regularly submitting to State Pollution Control Board /
concerned agencies, Water Cess yearly,
M: Monthly; S: Sample; Se: Seasonal ; Freq.: Frequency : Note: monitoring for all key parameters as
described by CPCB
RAINWATER HARVESTING SCHEME
06 Rain Water Harvesting pits of size 3 m length x 3 m width x 3 m depth with PVC slotted pipe upto
minimum depth of 30 m are provided.
Total Annual Recharge to Ground Water Regime of the area through rainwater harvesting structure
would 51,474.00 m3/ annum.
However, Rain Water Harvesting pit of size 3 m length x 3 m width x 3 m depth with PVC slotted pipe
upto minimum depth of 30 m as following figure.
![Page 12: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT](https://reader033.fdocuments.net/reader033/viewer/2022042008/5e711987bf7fbd06606d5184/html5/thumbnails/12.jpg)
PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN
PROMOTER: VEETRAG BUILDCON PVT. LTD.
DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR
NOVEMBER’ 2017
C. LAND ENVIRONMENT
SOIL ANALYSIS REPORT
RESULTS
S.No. PARAMETERTS TEST METHOD RESULT UNIT
1. pH(1:10 suspension) IS:2720(Part-26) 7.56 -
2. Electrical Conductivity mS/cm IS:2720(Part-21) 135.12 mS/cm
3. Water holding Capacity STP/SOIL 37.25 % by mass
4. Porosity STP/SOIL 46.31 % by mass
5. Sand STP/SOIL 54.16 % by mass
6. Clay STP/SOIL 32.10 % by mass
7. Silt STP/SOIL 13.74 % by mass
8. Bulk Density STP/SOIL 1.56 mg /m³
9. Moisture Content STP/SOIL 6.38 % by mass
10. Calcium (as Ca) STP/SOIL 375.3 mg/kg
11. Magnesium(as Mg) STP/SOIL 216.10 mg/kg
12. Sodium (as Na) STP/SOIL 178.33 mg/kg
13. Potassium(as K) STP/SOIL 109.12 mg/kg
14. Cation Exchange Capacity STP/SOIL 7.23 Meq/100gm
![Page 13: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT](https://reader033.fdocuments.net/reader033/viewer/2022042008/5e711987bf7fbd06606d5184/html5/thumbnails/13.jpg)
PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN
PROMOTER: VEETRAG BUILDCON PVT. LTD.
DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR
NOVEMBER’ 2017
15. Sodium Absorption Ratio STP/SOIL 1.65 -
16. Nitrogen STP/SOIL 0.078 % by mass
17. Phosphorus(P2O5) STP/SOIL 9.81 mg/kg
18. Zinc (Zn) STP/SOIL 3.17 mg/kg
19. Organic Matter STP/SOIL 0.69 % by mass
Soil analysis report is enclosed as Annexure V.
D. NOISE ENVIRONMENT
NOISE MONITORING REPORT
RESULTS
S. No Test Parameters Results Units Requirement (as per CPCB Guidelines Limits in
dB (A) Leq
1.
Lday
(6.0 AM TO 10.0 PM)
51.3
dB(A)
Category of Area/ Zone Day Time Night Time
Industrial Area 75 70
2. Lnight
(10.0 PM TO 6.0 AM)
39.9 dB(A)
Commercial Area 65 55
Residential Area 55 45
Silence Zone 50 40
CONSTRUCTION PHASE:
During construction phase following will be the tentative sources of noise:
Name of Source Noise level at 16 m from
source {dB (A)}
Noise level at 1 m from source
{dB (A)}
Back hoe/Loader 81 105
Dump truck 83 107
Generator Not considered 75 (as prescribed by CPCB)
To understand the combined effect of these noise levels on the nearby community, Custic 3.2 (Lakes
Environmental – USEPA approved) scientific model has been used to estimate the noise levels at
different distances from the proposed project. All the major noise generating machineries like D.G.
Sets, Pumps, Trucks, vibrators, drilling machine, etc., are considered in this model. The noise level at
project boundary due to different sources is calculated based on the following formula:
Lp2 = Lp1 – 20 log (r2 / r1) – Ae1, 2
where, Lp1 and Lp2 are sound levels at points located at distance r1 / r2 from the source and Ae1,2 is the
excess attenuation due to environmental conditions. The resultant noise level is obtained by adding
existing maximum levels to that of predicted level.
![Page 14: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT](https://reader033.fdocuments.net/reader033/viewer/2022042008/5e711987bf7fbd06606d5184/html5/thumbnails/14.jpg)
PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN
PROMOTER: VEETRAG BUILDCON PVT. LTD.
DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR
NOVEMBER’ 2017
Further due to natural attenuation effects, by proper green belt development, design / maintenance of
machines, providing PPE’s to workers, etc., the impact on noise levels will be minimal.
MANAGEMENT PLAN
SOURCES MANAGEMENT
Major sources of noise
pollution:
• Vehicular traffic
• Heavy moving
machinery
• Operation of D.G.
sets, etc.
• The construction area was shielded with help of tarpaulin sheets.
• Complete construction work especially heavy earth work was done
during day time.
• Traffic planning and management made adequate to ensure
uninterrupted traffic movement in the area so as to minimize the noise
due to congestion.
• The vehicles were regularly maintained and optimum use of the same
will be made.
• Moving parts of the machines were maintained properly so as to avoid
metal-to-metal impact noise.
• The D.G. sets used are eco friendly with minimum noise.
• Ear plugs were provided to the workers.
POST CONSTRUCTION PHASE
SOURCES MANAGEMENT
• Vehicular
noise
• Operation of
D.G. sets.
• EPA/CPCB certified DG set conforming to the standards for noise will be used.
• D.G. set will be housed in an inbuilt acoustic enclosure, which will help to
contain the noise within the permissible standards.
• The driveways will have sufficient width so that there is no congestion of
vehicles during peak hours which lead to increase in the noise levels.
• Adequate parking including provisions of visitors parking.
• Entry & exits will be manned with trained & efficient security to ensure
smooth flow of vehicles.
• There is less starting and stopping and the vehicles are speed restricted to
ensure the noise within the permissible limits.
• The area will cover 5256.69 Sq.m area under landscape, which will help to
absorb noise.
E. BIODIVERSITY
Biotic component comprises of both plant animal communities which interact not only within and
between them self but also with a biotic i.e. physical and chemical components of the environment.
![Page 15: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT](https://reader033.fdocuments.net/reader033/viewer/2022042008/5e711987bf7fbd06606d5184/html5/thumbnails/15.jpg)
PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN
PROMOTER: VEETRAG BUILDCON PVT. LTD.
DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR
NOVEMBER’ 2017
Generally a biological community is being dependent on the environmental conditions and resources
of its location may change if there are many major changes in the environment. The number of
variables like temperature, humidity, atmospheric conditions, soil, topography, etc. is responsible for
maintaining the homeostasis of the environment and a change in any one or more of these variables
may tend to destabilize the ecosystem. In such cases the change may be mostly irreversible.
Therefore, the need to assess the changes of the animal and plant resources is primary requisite as
these living things determine the environmental healthiness of any given ecosystem or environment.
Biological impact assessment generally includes listing of plants and animals present at the project
site. The identified species are then checked for their status according to IUCN list of threat
categories viz., endemic, endangered, vulnerable, rare, indeterminate and insufficiently known.
As part of this assignment, a flora and fauna study has been conducted for the proposed housing
Project at Jodhpur, Rajasthan. Field study was undertaken in the month of September 2017. The
proposed site and habitats adjacent to the site were surveyed for flora and fauna species.
1. Objective of Study
The present work was undertaken with the following objectives:
• To collect the baseline terrestrial biodiversity status regarding flora and fauna in the project
area.
• To evaluate the dominant species of plant and animal. Secondary data also is collected from the
local residents.
• To identify the endangered / threatened / scheduled species in the study area (both flora and
fauna). The conservation plan will be given if any wildlife species of schedule -I is present
there.
• To mark the ecologically sensitive areas such as national parks/ sanctuaries.
• To suggestion and recommendation for plantation and green belt.
• To assess the effect of construction and operation of the project on existing ecology.
On the basis of onsite observations a checklist of flora and fauna was prepared
2. FLORAL STUDY
Trees:
Herbs and Grasses
S.No Species name Binomial name Family
1 Neem Azadirachta indica Meliaceae
2 Khejari Prosopis cineraria Fabaceae
S.No Species name Binomial name Family
3 Peli Kanteli Argimone maxicana Papavaraceae
![Page 16: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT](https://reader033.fdocuments.net/reader033/viewer/2022042008/5e711987bf7fbd06606d5184/html5/thumbnails/16.jpg)
PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN
PROMOTER: VEETRAG BUILDCON PVT. LTD.
DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR
NOVEMBER’ 2017
Shrubs
S.No Species name Binomial name Family
1 Aak Calotropis procera Asclipiadaceae
2 vilayati babool Prosopis juliflora Fabaceae
3 Sharpunkha Tephrosia purpurea Fabaceae
3. FAUNA
Faunal studies were also conducted during September 2017. During the survey of the study site, no
threatened/ endemic species in and around the study area were observed.
Major Features in the Study Area:
Feature Name / Status
National Park / Sanctuary Nil
Biosphere Reserve /Tiger Reserve/ Elephant Reserve /any other Reserve Nil
Habitat for migratory birds Nil
Corridor for animals of Schedule I & II of the Wildlife (Protection) Act, 972 Nil
A) PIECES: No sustain water body observed at the site of study area.
B) AMPHIBIA: Not observed.
C) REPTILIA
Particulars
S.
No.
Common name Binomial name Family Schedule
IW(P)A / IUCN
Reptilian 1 Oriental Garden Lizard Calotes versicolor Agamidae LC
2 Yellow-Green House
Gecko
Hemidactylus
flaviviridis
Agamidae LC
D) AVIS OR AVIFUANA
Site specific avifaunal species observed during the site visit:
S.No Common Name Binomial Name Family Schedule
IW(P)A / IUCN
1 Common Myna Acridotheres tristis Sturnidae IV
2 House crow Corves splendens Corvidae IV
4 Kanteli Solanum zanthocarpum Solanaceae
5 Onth Kantalo Echinops echinatus Asteraceae
6 Raimuniya Lantana camera Verbenaceae
![Page 17: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT](https://reader033.fdocuments.net/reader033/viewer/2022042008/5e711987bf7fbd06606d5184/html5/thumbnails/17.jpg)
PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN
PROMOTER: VEETRAG BUILDCON PVT. LTD.
DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR
NOVEMBER’ 2017
3 House Sparrow Passer domesticus Passeridae IV
4 Pigeon Columba livia Columbidae IV
E) MAMMALIA
Particulars S. No Common Name Binomial Name Family Schedule
Mammals 1 Five stripped palm squirrel Funambulus pennantii Sciuridae IV
A Endangered species Not observed during the study period.
B Endemic species Not observed during the study period.
C Migratory species Avifaunal species may be migratory.
D Aquatic fauna NIL
5. Plantation for Green belt development
The greenbelt development plan aims at overall improvement in the environmental conditions of the
region. Green belt planning will be done with ecological perspectives for project. Nature of pollutants,
availability of space and dominant wind directions should be considered. This will help in reducing the
concentration of pollutants and will also be effective in attenuating noise levels.
Moreover, keeping in view the characteristics of soil, water quality and topography of the area the
following additional aspects should also be considered. Plant species should have such characteristics:
� Fast growing and perennial species;
� Locally available species which are tolerable to soil and climate of area;
� Low water requirement and heat tolerant;
� Pest resistant species;
� Tolerance to inorganic chemicals;
6. Suggested plants
Table 1. Following listed species are suggested to develop greenbelt around the project
site:
S.No.
Suitable Tree species
Common Name Binominal Name
1 Neem Azadirachta indica
2 Ardu Ailanthus excelsa
3 Gulmohar Delonix regia
4 Khejari Prosopis cineraria
![Page 18: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT](https://reader033.fdocuments.net/reader033/viewer/2022042008/5e711987bf7fbd06606d5184/html5/thumbnails/18.jpg)
PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN
PROMOTER: VEETRAG BUILDCON PVT. LTD.
DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR
NOVEMBER’ 2017
5 Pipal Ficus religiosa
6 Banyan tree Ficus bengalensis
7 Imli Tamarindus indica
8 Arjun Terminalia arjuna
9 Ashok Polyalthia logifolia
10 Amaltas Cassia fistula
Total
Shrub:
S.No. Common Name Botanical Name
1 Bougainvillea Bougainvillea glabra
2 Chandni Tabernaemontana divaricata
3 Champa Plumeria alba
4 Thunja /Morpankhi Thuja occidentalis
5 Kaner Nerium oleander
6 Gudhal Hibiscus rosa-sinensis Linn.
Herbs:
S.No. Common Name Botanical Name
1 Rose Rosa macdub
2 Genda Tagetes patula
Suggestion of other Indoor Herbs
Areca Palm
This leafy plant can be grown anywhere in the house
in indirect sunlight. The plant can grow as high as 30
feet outdoors but it is restricted to about seven feet at
indoor locations. Put it in a small container and the
crowded roots will help in limiting the size of the
plant. It also works effectively as an effective
humidifier. Water enough to keep the soil moist and
let it dry a little between watering in winter.
English Ivy
This green plant filters out formaldehyde found in
some household cleaning products. The plant needs
bright light to look fresh and might attract pests if they
do not receive enough light.
Aloe Vera Aloe plants like to be dry and warm, not wet and cold,
so water only when we see that the soil in the pot is
![Page 19: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT](https://reader033.fdocuments.net/reader033/viewer/2022042008/5e711987bf7fbd06606d5184/html5/thumbnails/19.jpg)
PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN
PROMOTER: VEETRAG BUILDCON PVT. LTD.
DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR
NOVEMBER’ 2017
dry. It is a widely-known fact that aloe Vera can be
used to achieve a great complexion.
Indian Basil
Commonly known as Tulsi. This plant has a number of
medicinal properties. Requires regular sunlight, so the
best place to keep this plant would be a sunny
window.
Dracaena
This plant does not require direct sunlight and can
grow up to 12 feet in height can place it near a sheer
curtain or a window
Spider Plant
The plant derived this unique name due to its
uniquely-shaped leaves, which dangle like spiders on a
web. The plant is also completely safe if you have pets.
If you see the plant turning a little brown, do not
worry. It is normal and it will get back to its green self
soon
Snake Plant
This plant is also called mother-in-law’s tongue or
Saint George’s sword. It is one of the top air-purifying
plants identified by NASA. This plant is one of the
easiest to grow and requires no extra attention.
Weeping Fig
This leafy plant helps against emissions from curtains,
carpets and furniture. The weeping fig initially takes
time to grow, but once it is in complete form, it can
grow up to 10 feet. Its Long lasting plant.
7. Post Plantation Care
• Water in trees at least once a week, barring rain, and more frequently during hot weather.
• Keep the soil moist but not soaked;
• Overwatering causes leaves to turn yellow or fall off.
• Other follow-up care may include minor pruning of branches damaged during the planting
process.
• Prune sparingly immediately after planting and wait to begin necessary corrective pruning
until after a full season of growth in the new location.
• Tree guard should be around the saplings until the plant reaching at mature stage.
• Fertilizers and pesticides/insecticides should be given proper time.
![Page 20: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT](https://reader033.fdocuments.net/reader033/viewer/2022042008/5e711987bf7fbd06606d5184/html5/thumbnails/20.jpg)
PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN
PROMOTER: VEETRAG BUILDCON PVT. LTD.
DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR
NOVEMBER’ 2017
• Construction workers shall be made aware regarding the importance of natural resources.
With suitable monitoring, pep talks, meetings and guidance provided.
8. IMPACT OF PROJECT ACTIVITIES ON BIODIVERSITY DIRECT, INDIRECT AND
CUMULATIVE IMPACT ON FLORA
• Direct Impact:
Clearing of project site for construction activities –Sparse vegetation of trees, shrub and herbs
which are commonly distributed throughout and none of rare, endangered or threatened or
endemic species was observed during survey / reported. These will be cleared during site
preparation. Therefore, the impact will be negligible and not very significant. Only one tree will be
cut during the clearing and construction time of project.
• Indirect Impact
• Construction activity is likely to affect the movement of the animal
• Increase in noise may affect the feeding, breeding and movement of animals. Felling of trees
may affect the avifauna.
• Likely settling of dust to be generated by movement of vehicles and other construction
activities on leaves may results in to stunted growth of vegetation and may also affect the
capacity of production.
• Large numbers of labour population will influx the area during construction phase.
• Dumping of huge quantity of excavated earth material may lead to loss of flora in the project
area
• The soil erosion due to natural and anthropogenic activities may cause major threat to survival
of vegetation.
• Cumulative Impact
• Indirect and cumulative impacts are associated with various construction activities such as
clearing of vegetation movement of vehicles, construction equipments & machineries etc,
interferences due to influx of labours etc.
• The losses of land for various project units will also not adversity affect the fauna as similar
habitat is present throughout the project immediate influenced area. Therefore, impact due
to loss of habitat for birds, reptiles and mammals of the project area is not expected.
• Impacts on surrounding fauna due to movement of vehicles, machinery, equipments and
work force may slightly interfere in animal movements.
• Intermittent settlements any adverse impacts on wildlife are ruled out.
Mitigation measures
![Page 21: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT](https://reader033.fdocuments.net/reader033/viewer/2022042008/5e711987bf7fbd06606d5184/html5/thumbnails/21.jpg)
PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN
PROMOTER: VEETRAG BUILDCON PVT. LTD.
DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR
NOVEMBER’ 2017
1. EFFECTIVE REMOVAL OF POLLUTANTS
1) Plants grow under conditions of adequate nutritional supply (for healthy and better growth),
2) Absence of water stress (to maintain openness of stomatal apertures and form of epidermal
structures),
3) Well-exposed to atmospheric conditions of light and breeze (i.e. away from engineering structures
hindering free flow of air) to maintain free interaction with gases.
• Plant leaves function as efficient gas exchange systems. Their internal structure allows rapid
diffusion of water-soluble gases. These characteristics allow the plant to respire and
photosynthesize, and they can also remove pollution from the air. Characters of plants
including shapes of crowns considered necessary for effecting absorption of pollutant gases
and removal of dust particles are as follows:
1) Tolerance towards pollutants in question, at concentrations, that are not too high ( to be
instantaneously lethal) They are good absorbers of sulphur dioxide. Roadside hedges can
reduce traffic generated air borne lead
2) Longer duration of foliage,
3) Freely exposed foliage , through
• Adequate height of crown,
• Openness of foliage in canopy,
• Big leaves( long and broad laminar surfaces),
• Large number of stomatal apertures,
• Stomata well- exposed ( in level with the general epidermal surface)
2. REMOVAL OF SUSPENDED PARTICULATE MATTER
1) Height and spread of crown,
2) Leaves supported on firm petioles,
3) Abundance of surfaces on bark and foliage, through
• Roughness of bark,
• Epidermal outgrowth on petioles,
• Abundance of auxiliary hairs,
• Hairs or scales on laminar surfaces,
• Stomata protected (by wax, arches/rings, hairs etc.)
The plant species should be capable of sorption of dust pollutants and barrier of noise pollution.
Combined deficiency of a variety of species will be contributed to reach the goals of restrict the
pollution.
![Page 22: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT](https://reader033.fdocuments.net/reader033/viewer/2022042008/5e711987bf7fbd06606d5184/html5/thumbnails/22.jpg)
PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN
PROMOTER: VEETRAG BUILDCON PVT. LTD.
DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR
NOVEMBER’ 2017
3. MITIGATION OF IMPACT
The mitigation measures of biological impacts are aimed at (in order of preference):
i) Avoid impact,
ii) Minimize impact,
iii) Rectify impact,
iv) Compensate for impact.
Setting aside or exclusion of critically important areas, compensatory afforestation, creation of green
belts, rehabilitation of species or individuals are basic actions taken for mitigation of impact. While
creating green belt and undertaking the afforestation works, it is required to plant indigenous/local
plants and as for as possible exotics should not be introduced. The cost of eco-restoration of the site
should be included in the project cost. This is desirable on two counts:
i) It ensures allocation of fund for undertaking the rehabilitation of the area during and also after the
project period is over.
ii) It also acts as deterrent in selection of site for the project by bringing in the cost of eco-restoration
which can be enormous in cases where activities are proposed on a critical ecosystems.
9. CONCLUSION
The present study is with the objective to minimize adverse environmental impacts as discussed. The
study covers all possible environmental issues involved in the project and the necessary mitigation
measures. It was observed that diversity of trees; shrub and herbs were in better at site. Native and
local species will be planted in post construction phase. Faunal diversity of the site was also very low.
Therefore, we can say that the biological diversity of the study site not much more impacted by the
present proposed infrastructure development and the sustainable environment scenario can be
retained by the proper plantation in post construction period.
F. THE SOCIO ECONOMIC ENVIRONMENT
OBJECTIVES
The broad objectives of the socio-economic impact assessment are:
1. To study the socio-economic status of the people living in the study area.
2. To assess the impact on socio-economic environment due to the project concerned.
3. To evaluate the community development measures proposed to be taken up by the Project
Proponent, if any.
The studies carried out are descriptive and exploratory in nature.
![Page 23: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT](https://reader033.fdocuments.net/reader033/viewer/2022042008/5e711987bf7fbd06606d5184/html5/thumbnails/23.jpg)
PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN
PROMOTER: VEETRAG BUILDCON PVT. LTD.
DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR
NOVEMBER’ 2017
Habitation
The location of the proposed Group Housing Project, District Jodhpur is in Pal. The nearest human
settlements are as follows in the study area periphery of the project.
• Pal 1.75 km S
The habitation is Semi - Urban.
Population of the Study area:
The households with a family size of 5 approx, as per the Census of India, 2011. The male population
constitutes 53.92% and female population constitute of 46.07%.
Population Profile:
Study Area Household Population Males Females
Pal Village (OG) WARD NO.-0066
(Rural MDDS CODE:085023) 3681 20621 11119 9502
*Census of India, 2011
Gender Ratio
The gender ratio is 854 in the study area, much below the district Jodhpur gender ratio of 915 as per
Census of India, 2011.
For children below 6 years the gender ratio is 855 in the study area much low as compared to the 891
Child sex ratio of Jodhpur District. The Child percentage of 6 years below is 14.09% of the total
population.
Study Area Population below 06
years Males Females
Pal Village (OG) WARD NO.-
0066 (Rural MDDS
CODE:085023) 2906 1566 1340
*Census of India, 2011
Literacy Rate of the Study area:
The average literacy rate is 52.02%. The total male literacy rate with respect to the male population is
58.17% and female literacy rate with respect to female population is 45.04%.
Literacy Profile:
![Page 24: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT](https://reader033.fdocuments.net/reader033/viewer/2022042008/5e711987bf7fbd06606d5184/html5/thumbnails/24.jpg)
PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN
PROMOTER: VEETRAG BUILDCON PVT. LTD.
DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR
NOVEMBER’ 2017
Study Area Population Literates Male Literates Females Literates
Pal Village (OG) WARD
NO.-0066 (Rural MDDS
CODE:085023) 10749 6469 4280
*Census of India, 2011
Work Population:
The work participation rate is 32.06%. The total main workers constitute 28.65% with men 23.81% and
female with 4.83%.
The total marginal work population is 3.41% with male population 2.04% and female population with
1.37%.
The total non-working population constitutes of 67.94% with males as 28.06% and females with 39.87%.
Study Area Main Workers Marginal Workers Non-workers
Total Male Fem Total Male Female Total Male Female
Pal Village (OG)
WARD NO.-0066
(Rural MDDS
CODE:085023) 5906 4910 996 705 421 284 14010 5788 8222
*Census of India, 2011
Scheduled Tribes Population
The ST Population is 3.48% of the total population. The male – female population in ST constitutes
1.77% for males and 1.71% for female population indicating female population slightly higher as
compared to men.
Study Area Population Males Females Pal Village (OG) WARD NO.-
0066 (Rural MDDS
CODE:085023) 718 365 353
*Census of India, 2011
SOCIAL INFRASTRUCTURE:
The nearest human settlements are as follows in the study area periphery of the project.
• Pal 1.75 km S
The 500 metres in the remaining periphery has scattered housing amidst vacant plots. Market Place 800
m E. Bus Stand 820 m NNW.
![Page 25: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT](https://reader033.fdocuments.net/reader033/viewer/2022042008/5e711987bf7fbd06606d5184/html5/thumbnails/25.jpg)
PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN
PROMOTER: VEETRAG BUILDCON PVT. LTD.
DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR
NOVEMBER’ 2017
Medical Facility: - Rajkiya Upswastha Kendra 2.35 km S, Gen. Hospital of Chopasni School by Hammar
Singh Rathore 2.28 km NNE, and many other private clinics in 3.0 km ;
Schools:- Rajkiya Uchh Madhyamik Vidhyalaya Pal 2.10 km S, Sanskar International School 1.99 km NW;
Senior Secondry Eng. Medium School 2.29 km NNE; IIHT Jodhpur School 2.24 km NNE; MD Saran Public
Sr. Sec. School Pal Jodhpur 2.56 km S; DPs 2.31 km SE;
Other: Sant Shri Asaram ji 1.46 km S, Hindi Film city 1.47 km S; Shergarh Rawla Prince Highway Jodhpur
370 m ESE; St. Sebastian Church , Pal 1.91 km SSW; Pashu Mela Ground 2.55 km S;
Table: Socio-economic snapshot of nearest habitation:
Transportation was available in all the
aspects :
Bus Govt. Roadways / Private - Tractors, Scooters,
Motor Cycles, (Public transport available).
Roads were observed to be : Pucca, Painted & Cemented
Electricity Supply has been : Irregular
Main Food : Chapatti, Sabji, Dal
Festivals : Holi, Diwali, Gangore, Raksha Bandhan.
Caste / Religion: The principal communities are the largely Hindus with
Agarwals, Jains, Brahmins, and Muslims and minorities of
Christians.
Material Assets of the family : A Two Wheeler / Four Wheeler; Cable Disc ; TV;
Refrigerator
Resources of potable water Government Supply (PHED)& Hand pumps
Nature of Diseases Sun Stroke/ Cold / Cough
IMR & MMR For the State of Rajasthan: As per the RHS Bulletin (March 2012, M/O Health & F.W.,
GOI) The Total Fertility Rate of the State is 3.1. The Infant
Mortality Rate is 47 (SRS 2013) and Maternal Mortality
Ratio is 255 (SRS 2010-12).
Source: field survey and observations.
Socio-Economic observations
![Page 26: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT](https://reader033.fdocuments.net/reader033/viewer/2022042008/5e711987bf7fbd06606d5184/html5/thumbnails/26.jpg)
PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN
PROMOTER: VEETRAG BUILDCON PVT. LTD.
DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR
NOVEMBER’ 2017
The group housing project is amidst the developing area of Jodhpur and is around scattered housing of
Jodhpur. As per the FGD, the need of the nearest habitations is regarding medical facilities. The group
exclaimed its requirement for the various issues and Infrastructural development:
• A modern dispensary as the villagers commutes to Jodhpur City even for minor treatments like
Fever, Stomach-ache etc.
• Government run health programmes are organized in the locality in the study area.
• Cottage industries should receive encouragement.
• Tap water supply is main sources of drinking water and other household use.
CORPORATE SOCIAL RESPONSIBILITY/ENTREPRENEUR SOCIAL RESPONSIBILITY
The CSR would be applicable for every company having net worth of Rs. 500 crore or more, or turnover
of Rs. 1000 crore or more or a net profit of Rs. 5 crore or more during a year, such Companies shall be
required to ensure that every year at least 2% of its average net profits during the three immediately
preceding financial years is spent on CSR activities as may be approved and specified by the company.
Corporate / Entrepreneur Social Responsibility:-
The project is committed towards CSR/ ESR with respect to its applicability with, The Companies Act
2013.
S. No. Activity As per Schedule VII : Budget in INR
Year I Year II Year III
1.
Scholarship to Economically Weaker Sections / Below
Poverty Line Family Students for promotion towards
higher education in Government Schools
50000 - -
2. Rural Development for infrastructure along with
Green Belt in local area. 100000 - -
3. Health Camps for the local residents in Government
Dispensaries 30000
30000 -
4. Local road Maintenance , Road Safety and Traffic
Training -
45000 45000
Total 180000 75000 45000
The project will fulfill its corporate social responsibilities only as per its applicability w.r.t. to Section 135 of The
Companies Act, 2013.
Capital Cost: INR 300000
![Page 27: CONCEPTUAL PLAN AND ENVIRONMENTAL ...environmentclearance.nic.in/writereaddata/Online/TOR/13...EWS/LIG (G+9), No. of Flats: EWS(81) & LIG (4) 3623 Total Built up Area 101359.48 PROJECT](https://reader033.fdocuments.net/reader033/viewer/2022042008/5e711987bf7fbd06606d5184/html5/thumbnails/27.jpg)
PROJECT : GROUP HOUSING CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN
PROMOTER: VEETRAG BUILDCON PVT. LTD.
DOCUMENT NO.: EESPL/VBPL/002/EC/INFRA/2017-18/363
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR
NOVEMBER’ 2017
G. EXPENDITURE ON ENVIRONMENTAL MEASURES
S. No. Particulars Capital Cost
(lacs)
Annual recurring
cost (lacs)
1 Acoustic enclosures & stack attached to DG sets 4 1
2 STP 30 5
3 Rain water harvesting 20 2
4 Solid waste management 6 1
5 Pollution monitoring 2 0.5
6 Fire fighting & emergency handling 35 3
7 Green Belt 5 0.5
8 Training in the area of environment &
occupational health.
1 0.10
TOTAL 103 13.10
***************