CONCEPTUAL PLAN & ENVIRONMENTAL MANAGEMENT...
Transcript of CONCEPTUAL PLAN & ENVIRONMENTAL MANAGEMENT...
Project : Affordable housing EWS LIG project (Expansion) Conceptual Plan &
Environmental Management Plan Developer : Anukampa Homes Pvt Ltd
EIA Coordinator Authorized Signatory
CONCEPTUAL PLAN &
ENVIRONMENTAL MANAGEMENT PLAN
INTRODUCTION & PROJECT SUMMARY:
The proposed project involves vertical expansion of EWS LIG affordable housing project coming
up at village Muhana, Tehsil Sanganer, District Jaipur (Raj). The project is developed by
Anukampa Homes Pvt. Ltd.
The total plot area o f the project is 11,981.07 sq. m. Gross built up area envisaged for the project
is 31,219.95 sq. m. (Existing: 19,140.54 sq. m, Proposed: 12,079.41 sq.m) (> 20,000 sq. m.). Thus, the
project requires prior Environmental Clearance under Item 8 (a) {Building & Construction
projects} of Schedule- EIA Notification 2006 and subsequent amendments thereafter from the
State Level Environmental Impact Assessment Authority, Rajasthan.
The proposed project will constitute of 12 blocks comprising of 705 EWS & LIG units (existing-
441 and proposed-264).
Table: Salient features of the project
Items Details
Project address Khasra No. 1407, 1408, 1413, 1414, P. No. B, Village Muhana, Tehsil Sanganer,
Jaipur (Raj)
Type of project Affordable Housing EWS LIG Project (Expansion)
Screening
category
The project is categorized under 'B-2' under item 8(a) of Schedule – Gazette
Notification dated Sep 14th, 2006 and subsequent amendments there off.
Total Plot area 11,981.07 sq. m
Gross Built up
area
31,219.95 sq. m.
(Existing: 19,140.54 sq. m, Proposed: 12,079.41 Sq.m)
Ground coverage 3531.15 sq. m. (29.52%)
Green Area 1224.58 sq. m. (10.22%)
Dwelling units 705 nos. dwelling units
Flat type Existing Proposed Total units
LIG 234 144 378
EWS 207 120 327
Total 441 264 705
Project : Affordable housing EWS LIG project (Expansion) Conceptual Plan &
Environmental Management Plan Developer : Anukampa Homes Pvt Ltd
EIA Coordinator Authorized Signatory
Maximum height
& number of
floors
Type No. of Floors Height (in m.)
Existing Proposed Total Up to Terrace
Level
Up to Mumty/
Machine room
LIG Block A-F 4 3 7 23.70 --
EWS Block A-E 4 3 7 -- 14.84m
EWS Block F 3 - 3 12.10m --
Parking facilities Required Parking : 705 scooters (existing 441 + proposed 264)
Proposed Parking : 729
Power
requirement &
source
Connected load : 3312 KW
Max. demand : 1711 KW
Source : JVVNL
Power backup DG sets of capacity 200 kVA (1 no.)
Water
requirement &
source
Water demand Fresh Recycled Total
Existing 146 88 234
Proposed 88 29 117
Total 234 117 351
Source: Fresh water: PHED Supply
Sewage treatment
& disposal
Sewage treatment facility : STP of 300 KLD capacity
Sewage discharge : 100 KLD (supplied to farmers)
IDENTIFICATION OF THE PROJECT PROPONENTS:
Anukampa homes Pvt Ltd, the real estate giant in Rajasthan with special strength, exuberates
quality and excellence with over 35 year of expertise and experience. It has created some of the
most pioneering episodes of real estate promotion and residential town planning. From a very
modest beginning to the accomplishment of numerous projects in varied sectors, the group has left
an indelible mark in the real estate industry and technology. Anukampa Group has created a niche
for themselves by adopting quality system standards that match the best in the world. Their
magnificent apartments have emerged as the most sought after destination for luxurious living
amidst stimulating environment.
Legal information:
Name of the company : Anukampa Homes Pvt. Ltd.
Director : Prashant Gupta
Registered address : Anukampa Homes Pvt. Ltd.
401, Anukampa Mansion-II, M.I. Road, Jaipur (Raj)
Project : Affordable housing EWS LIG project (Expansion) Conceptual Plan &
Environmental Management Plan Developer : Anukampa Homes Pvt Ltd
EIA Coordinator Authorized Signatory
REGULATORY COMPLIANCE:
The project is coming up on a land duly converted for group housing purposes. Patta issued on
dated 14.08.2007 for plot area of 23,333.77 sq. yards (19,501.69 sq. m.) in favour of M/s Deep
Valley Infra Developers {Annexure I (a)}.
The land was purchased by Anukampa Homes Pvt. Ltd. on dated 03.10.2008 {Annexure I (b)}
Later, the land was later sub-divided into two parcels admeasuring 9004.53 sq. yards (7520.62
sq. m.) (Plot no. A) & 14329.24 sq. yards (11,981.07 sq. m.) (Plot no. B) vide JDA letter no.
/ / -11/ / 13/ - 4007 dated 09.09.2013 {Annexure I (c)}
The proposed EWS & LIG housing project is coming up at Plot no. B admeasuring 11,981.07
sq. m.
Building plans for Phase I Having built up area of 19,140.54 sq. m (<20,000 sq. m.) were
approved by JDA vide letter dated 16.04.2015 (Annexure VI).
NOC from Airport Authority of India has been obtained vide letter no. AAI/RHQ/ NR/ ATM/
NOC/ 2015/61/1296-99 dated 03.03.2015 (Annexure V).
Application for obtaining assurance of water supply from PHED has been submitted.
LOCATION OF THE PROJECT & INFRASTRUCTURE FACILITIES:
The proposed project is located at Khasra No. 1407, 1408, 1413, 1414, P. No. B, Village Muhana
Tehsil Sanganer, Jaipur, Rajasthan.
Details of other infrastructural facilities (aerial distance):
Nearest Railway Station : Sanganer RS (20 km NE)
: Jaipur RS (13.59 Km NNE)
Nearest Airport : Jaipur Airport (7.86 Km ENE
Project : Affordable housing EWS LIG project (Expansion) Conceptual Plan &
Environmental Management Plan Developer : Anukampa Homes Pvt Ltd
EIA Coordinator Authorized Signatory
PROJECT DETAILS:
The project will constitute of 12 blocks EWS and LIG (Block A-F) with 705 nos. of dwelling units
(EWS: 327 nos., LIG: 378 nos. The details are tabulated as under:
EWS LIG Grand
Total Existing Proposed Total Existing Proposed Total
Dwelling units 207 120 327 234 144 378 705
No. of blocks 6 Nil 6 6 Nil 6 12
No. of floors
Block A-E G+4 3 G+7 G+4 3 G+7
Block F G+3 Nil G+3 G+4 3 G+7
Project : Affordable housing EWS LIG project (Expansion) Conceptual Plan &
Environmental Management Plan Developer : Anukampa Homes Pvt Ltd
EIA Coordinator Authorized Signatory
Block wise details:
Existing
Block Type No of Blocks No of units in each Block Total no of units
1. LIG Block A-F 6 39 234
2. EWS Block A-D 4 39 156
3. EWS Block E 1 39 39
4. EWS Block F 1 12 12
Total (A) 441
Proposed
Block Type No of Blocks No of units in each Block Total No of units
1. LIG Block A-F 6 24 144
2. EWS Block A-D 4 24 96
3. EWS Block E 1 24 24
4. EWS Block F No change No change No change
Total (B) 264
Grand Total (A) + (B) 705
PARKING REQUIREMENT:
Basis of calculations: 1 two wheeler / unit
a. Existing:
No. of units : 441
Total two wheeler parking required : 441 ……… (A)
b. Proposed:
No. of units : 264
Total two wheeler parking required : 264 ……… (B)
c. Total parking required: (A) + (B) : 705 two wheeler parking
d. Total parking provided : 729 two wheeler parking
Project : Affordable housing EWS LIG project (Expansion) Conceptual Plan &
Environmental Management Plan Developer : Anukampa Homes Pvt Ltd
EIA Coordinator Authorized Signatory
POWER REQUIREMENT:
Power requirement for the proposed project is given as under:
S. No. Description
1. Source of supply JVVNL
2. Electrical Load Connected load : 3312 KW
Max. demand : 1711 KW
3. Transformer Number 1 no.
Capacity 2000 kVA, 33/0.433 kV
4. DG Sets Number 1
Capacity 200 kVA
Fuel Used HSD (sulphur content: 0.05%)
Fuel Consumption 40 ltr/hr
Electrical Demand Break Up:
S.
No.
No.
of
units
Light
load/ unit
(KW)
Power
load/ unit
(KW)
Connected
load (KW)
DF Demand
load
(KW)
Light
load
Power
load
Apartment
1. 1 BHK (EWS) 327 1.50 2.00 1144.5 0.70 0.40 605
2. 1 BHK (LIG) 378 2.00 3.00 1890 0.70 0.40 983
A. Total (1-2) 705 3034.5 1588
1. Parking, lobby,
staircase lighting
1 58 0.00 58 0.80 -- 46.4
4. Lifts 13 0.00 5.50 71.50 -- 0.55 39.3
5. Boring Pumps 2 0.00 10.00 20.00 -- 0.65 13.00
6. Plumbing Pumps 1 0.00 15.00 15.00 -- 0.80 12.00
7. Fire Fighting 13 0.00 7.50 97.50 -- 0.00 0.00
8. STP 1 0.00 15.00 15.00 -- 0.80 12.00
B. Total (1-9) 277 122.7 say
123
Grand Total
(A+B)
3311.5 say
3312
1711
Selection of transformers:
Project : Affordable housing EWS LIG project (Expansion) Conceptual Plan &
Environmental Management Plan Developer : Anukampa Homes Pvt Ltd
EIA Coordinator Authorized Signatory
Total load requirement : 1711 KW
Applying a power factor of 0.9 : 1901 kVA
Hence, 1 nos. 2000 kVA, 33/0.433 kV transformer will be provided
Selection of DG Sets:
Total essential load requirement (after diversity) : 123 kW
Applying a power factor of 0.9 : 137 kW
Considering 80% loading of the rated DG capacity
Minimum rating of DG set required : 171.25 kW
Hence, 1 nos. 200 kVA DG set will be provided.
There will be complete power backup through DG sets of capacity of 200 kVA used in case of
power cut or failure. DG set will be provided with an effective safe stack height of 24 m for proper
dispersion of pollutants to contain the emissions within the permissible limits. The fuel requirement
will be about 40 l/hr of HSD (as and when used).
CRITERIA OF WATER DEMAND:
The daily water requirement will be 351 KLD (fresh water: 234 KLD + recycled/reused water
demand: 117 KLD).
Criteria of water demand are given as under:
Particulars Population Fresh water Treated water total
Residential 3525 @65 LPCD: 229 KLD @21 LPCD: 74 KLD 303 KLD
Existing 2205 143 KLD 46 KLD 189 KLD
Proposed 1320 86 KLD 28 KLD 114 KLD
Visitors 530 @9 LPCD: 5 KLD @6 LPCD: 3 KLD 8 KLD
Existing 330 3 KLD 2 KLD 5 KLD
Proposed 200 2 KLD 1 KLD 3 KLD
Landscaping &
general washing
- -- 30 KLD 30 KLD
234 KLD 132 KLD 278KLD
Project : Affordable housing EWS LIG project (Expansion) Conceptual Plan &
Environmental Management Plan Developer : Anukampa Homes Pvt Ltd
EIA Coordinator Authorized Signatory
WATER BALANCE (TOTAL)
Fresh water
234 KLD
Residential
229 KLD
STP treated
water
117 KLD
Visitors
5 KLD
Landscaping & General
washing 40 KLD
255 KLD
Waste water
S
T
P
Capacity
300 KLD
Sludge &
evaporation
losses
38 KLD
Drain/ Supplied
to farmers
100 KLD
Recycled/ reused
183
3
69
Daily water demand: 351 KLD
{234KLD (fresh) + 117 KLD (recycled/ reused water)}
Flushing
77 KLD
Source: Fresh Water: PHED Water Supply/ bore wells
Treated Waste water: STP Treated Water
LIGHT & ELECTRICITY DETAILS:
RECOMMENDED LUX LEVELS:
The recommended values of illumination (in Lux) as per the National Building Code of India
(2005) are as under:
S. No. Space Illumination Level (Lux)
i. Entrance 150-200-300
ii. Lifts 50-100-150
iii. Corridor, passageways, stairs 50-100-150
iv. Covered car par
Floor
Ramp and Corner
Entrance and exits
5-20
30
50-100-150
v. Outdoor car park 5 – 20
Project : Affordable housing EWS LIG project (Expansion) Conceptual Plan &
Environmental Management Plan Developer : Anukampa Homes Pvt Ltd
EIA Coordinator Authorized Signatory
IDENTIFICATION, PREDICTION AND EVALUATION OF IMPACTS:
Environmental impact can be defined as any alteration of environmental conditions, adverse or
beneficial, caused or induced by the action or set of actions under consideration.
Various operations involved in the project have been studied in details to identify, predict and
evaluate impacts on various environmental components. The identified impacts were quantified
using mathematical models to a possible extent so as to estimate the future environmental scenario.
AIR ENVIRONMENT:
Air pollution has long been recognized as a brain storming issue worldwide. The onset of
technological and scientific innovations in various fields and diverse activities of human race for
its elegance have put extra load on the atmosphere by way of releasing air pollutants like
particulate matter (PM10, PM2.5), sulphur dioxide (SO2), oxides of nitrogen (NOX), carbon
monoxide (CO), unburned hydrocarbon (HC) and other organic as well as inorganic pollutants
including trace metals responsible for causing health consequences. Entry of pollutants into the
atmosphere occurs in the form of gases or particles. Continuous mixing, transformation and trans-
boundary transportation of air pollutants make air quality of a locality unpredictable. The growth
of population, industry and number of vehicles and make the problem of air pollution still worse.
Rapid industrialization and vehicular traffic especially in the urban areas of India is a great threat
to air quality.
AMBIENT AIR QUALITY DATA:
Details of monitoring report are given as under:
Ambient air monitoring report
Instrument used: Respirable Dust Sampler (SLE-RDS 103 & SLE-GA 133) & Fine Particle Sampler APM 550)
Sampling date-02.10.2015, Duration: 24 hrs.
Parameter Observation Permissible (maximum) protocol
In µg/m3
PM10 (µg/m3) 76.5 100 IS 5182(Part 23):2006
PM2.5 (µg/m3) 45.2 60 As per CPCB Guidelines
SO2 (µg/m3) 8.7 80 IS 5182 (Part 2):2001
NOx (µg/m3) 17.6 80 IS 5182 (Part VI):2006
CO (mg/m3) 370 2000 IS 5182 (Part 10)1999
* Monitoring reports enclosed as Annexure IV.
Project : Affordable housing EWS LIG project (Expansion) Conceptual Plan &
Environmental Management Plan Developer : Anukampa Homes Pvt Ltd
EIA Coordinator Authorized Signatory
Instrument Sensitivity:
Instrument Range and Sensitivity
Respirable Dust Sampler
(RDS)
(PM-10)
0.40 – 1.5 m3/min
±0.02 m3/min
(Other gases)
0 – 3 LPM
± 0.2 LPM
Fine Particulate Sampler (PM – 2.5) : ±0.03 DGM m3
CONSTRUCTION PHASE:
SOURCES OF POLLUTION:
1. Vehicular Exhaust:
The major source of pollution in construction phase will be vehicles carrying construction
material. Pollution load from the same is calculated as:
Pollution Load = No. of trucks × Emission Factors × Deterioration Factor
Due to movement of average 05 trucks short term pollution load is given in table:
Parameter Emission Factor
(g /km)*
Deterioration Factor
(g /km)*
Pollution Load
(g/km)
CO 4.5 1.33 29.92
NOx 1.21 1 6.05
SPM 0.8 1.595 6.38
SO2 0.15 1 0.75
HC 1.21 1 6.05
* Source : CPCB Publication, 1998
2. Emissions from Construction equipments:
The fugitive dust emission sources are:
Excavation
Haul road movements
Construction
Material Handling
Finishing
Project : Affordable housing EWS LIG project (Expansion) Conceptual Plan &
Environmental Management Plan Developer : Anukampa Homes Pvt Ltd
EIA Coordinator Authorized Signatory
Emissions factors for construction equipment are given in table below:
Equipment Emissions Factors (g/hr)
CO VOC NOX SOX PM10
Excavator 214.09 43.99 516.18 3.31 27.21
Backhoe/ Front end loader 190.05 56.69 370.13 1.58 37.64
Rubber tired crane 161.02 39.00 464.02 2.67 23.58
Hydraulic Crane 161.02 39.00 464.02 2.67 23.58
Concrete Vibrator 72.57 13.60 122.46 0 4.53
Paving Equipment 186.42 48.53 412.31 1.95 29.93
Roller/ Compactor 165.10 34.92 316.15 1.90 23.13
*Source: SCAQMD CEQA Hanbook
MITIGATION MEASURES:
S. No. Guidance on Practices to reduce emission
1. Water Application Water will be applied by variety of methods, for instance trucks, hoses,
sprinklers, etc to mitigate dust generation from the construction site.
2. Dust Suppressants Dust suppressants which are more effective than water, will be applied
judiciously.
3. Design Travelled distances will be minimized for delivery of materials
Green building materials viz. fly ash bricks, RMC’s, etc. will be used
to the best possible extent.
4. Storage Piles Storage pile activity will be conducted downwind
Enclosures/ coverings will be used for storage piles
Properly shape storage piles will be considered.
5. Vehicles &
Equipments
Engines & exhaust systems will be properly maintained.
Low sulphur diesel (HSD) will be used.
Idling time will be eliminated/ reduced to the maximum
Evaporative losses will be minimized
6. Material Handling
& Transfer
systems
Mud and dirt track-out and carryout will be controlled properly.
Material drop will be minimized at the transfer point and enclosure
Foam suppression systems will be utilized.
Loads on haul trucks will be secured.
PM emissions from spills will be prevented.
Material handling operations will be minimized.
7. Road Surfaces On-site vehicle restrictions will be established.
Unpaved roads will be properly maintained.
Project : Affordable housing EWS LIG project (Expansion) Conceptual Plan &
Environmental Management Plan Developer : Anukampa Homes Pvt Ltd
EIA Coordinator Authorized Signatory
POST CONSTRUCTION PHASE:
The emission sources are mainly due to the diesel generator set of capacity 200 kVA and increase
in number of vehicles.
SOURCES OF POLLUTION:
A. DG sets:
Calculation of stack height of D.G. sets
i. DG Set of capacity 200 kVA:
The stack height of DG set is calculated as under:
H = 0.2 (√capacity of the DG set in kVA)
= 0.2 x (√200)
= 0.2 x 14.14 = 2.82 m
However, a safe stack height of 24 m above the roof of DG house will be provided.
B. Vehicular emissions:
There will be increase of 729 scooters due to the proposed project.
MANAGEMENT PLAN
SOURCES MANAGEMENT
• Exhaust from D.G. sets
of capacity 200 kVA
• DG set conforming to the CPCB standards will be deployed.
• D.G. set will be provided with effective stack height of 24 m above the
roof of DG set.
• Low-sulphur-content fuel (HSD - Sulphur content 0.05%) will be used.
• Emission due to
vehicular exhausts
especially congestions
during peak traffic
hours.
• Sufficient width of driveways to ensure smooth traffic movements.
• Provisions of fully internalized parking including the parking facilities
for the visitors.
• Guided traffic ways within the project site.
• Speed humps will be installed for speed restrictions inside the project
area.
Project : Affordable housing EWS LIG project (Expansion) Conceptual Plan &
Environmental Management Plan Developer : Anukampa Homes Pvt Ltd
EIA Coordinator Authorized Signatory
WATER ENVIRONMENT:
GROUND WATER ANALYSIS REPORT*
Date of sampling: 02.10.2015
S.
No.
Parameters Value Found Standards as per IS 10500:2012
Desirable
limits
Permissible
Limits in absence
of alternate
source
Test Methods
1. pH 7.15 6.5-8.5 NR IS : 3025(Part 11):2002
2. Color, Hazen Unit <1 <5 <15 IS:3025 (Part 5):1983
3. Odour Agreeable Agreeable Agreeable IS:3025 (part 5)2002
4. Turbidity (NTU) <1 NTU 01NTU 05NTU IS:3025(Part 10)2002
5. Total Dissolve
Solids
5977.0 mg/l <500 mg/l 2000 mg/l IS:3025(Part 16)2006
6. Total hardness as
Ca CO3
72.0 mg/l <200 mg/l 600 mg/l IS:3025 (Part 21):2009
7. Calcium (Ca) 14.40 mg/l <75 mg/l 200 mg/l IS:3025 (part 40)2003
8. Magnesium (as
Mg)
8.75 mg/l <30 mg/l 100 mg/l IS:3025 (Part 40)2003
9. Total Alkalinity (as
CaCO3)
324.0 mg/l <200 mg/l 600 mg/l IS:3025 (Part 23)2003
10. Nitrate (as NO3) 13.28 mg/l <45 mg/l NR IS:3025 (Part 34)2003
11. Chloride (as Cl) 63.98 mg/l <250 mg/l 1000 mg/l IS:3025 (Part 32)2003
12. Sulphate (as SO4) 47.83 mg/l <200 mg/l 400 mg/l IS:3025(Part 24)2003
13. Iron (as Fe) 0.04 mg/l <0.3 mg/l NR IS:3025(Part 53)2003
14. Fluoride (as F) 1.25 mg/l <1.0 mg/l <1.5 mg/l IS:3025(part 60)2008
15. Free Residual
chloride)
<0.1 mg/l <10.2 mg/l 1.0 mg/l IS:3025 (part 26)1986
*Monitoring report enclosed as Annexure IV.
CONSTRUCTION PHASE:
WATER CONSERVATION TECHNIQUES:
Best construction practices will be adopted to reduce the water demand for construction activities:
Use of curing water: Spraying of curing water and after liberal curing, all concrete structures
will be covered with gunny bags, followed by spraying of water.
Use of polymer dispersion and air entraining agents to reduce the construction water demand.
Project : Affordable housing EWS LIG project (Expansion) Conceptual Plan &
Environmental Management Plan Developer : Anukampa Homes Pvt Ltd
EIA Coordinator Authorized Signatory
Admixtures will be used to reduce water demand during construction.
Discouraging the washing of vehicles and equipment on the construction site. Workers will
not allow to wash their personal vehicles on site. Vehicles and equipment that regularly leave
the construction site should be washed offsite.
MANAGEMENT PLAN:
SOURCES MANAGEMENT
Generation of sewerage Temporary septic tank followed by soak-pit will be provided.
Un-captured run-off
from the site may
contaminate ground
water aquifers.
The rain-water entering into the pit will be screened for the removal of
heavy silt and other materials.
Provisions will be made to ensure the construction vehicles stick to the
access track to prevent mud & dirt being deposited on roads.
Fence will be constructed around the site to trap sediments whilst
allowing the water to flow through.
Up slope water will be diverted with turf and due care will be taken not
to mix mortar in locations that will drain into storm water system.
Unsanitary conditions
during rainy season.
The civil contractor will be made responsible for site sanitation and will
be bound by the management to adhere to healthy level of sanitation.
There will be no stagnant water at site, as the runoff from the relevant
areas will be systematically drained into the storm water line. There
will be provision of cleaning the storm water line periodically.
POST CONSTRUCTION PHASE:
The daily water demand for the project will be 351 KLD. Daily fresh water demand will be 234
KLD (85,410 cu. m./annum). The fresh water demand will be met from PHED water supply.
A. WATER CONSERVATION TECHNIQUES:
Following water conservation techniques have been proposed for the project:
Dual plumbing system will be adopted to utilize the treated waste water for flushing
(77KLD), landscaping and general washing (40 KLD). This will help in reducing the
fresh water demand by 33%.
Dual flushing fixtures will be used to allow different volumes of water for solid and
liquid flushing which will help in conserving the water demand for flushing significantly.
Project : Affordable housing EWS LIG project (Expansion) Conceptual Plan &
Environmental Management Plan Developer : Anukampa Homes Pvt Ltd
EIA Coordinator Authorized Signatory
Landscape design & management of irrigation systems:
o Native & xeriscaping plant species: Choose native plant species that need less
water.
o Creating Hydrozones: Grouping of plant according to their water needs to provide
adequate water to all plants without over or under-watering.
o Maintain Healthy Soil: Healthy soils are the basis for a water-smart landscape; they
effectively cycle nutrients, minimize runoff, retain water, and absorb excess nutrients,
sediments, and pollutants.
o Mulching: Incorporate mulch around shrubs and garden plants to help reduce
evaporation, inhibit weed growth, moderate soil temperature, and prevent erosion.
Adding organic matter and aerating soil can improve its ability to hold water.
o Avoid watering during the heat of the day. Water early in the morning to reduce the
evaporation rate
o Drought tolerant species will be selected.
o Turfs will be avoided to the extent possible.
o Central shut off valve will be provided
o Sprinkler landscaping system will be used to conserve water
B. WASTE WATER GENERATION & TREATMENT
Approximate 255 KLD waste water will be generated which will be treated in STP based on
phytorid technology with capacity of 300 KLD. Physico chemical characteristics of influent
and effluent are given as:
Parameters Influent (mg/ltr) Treated effluent (mg/ltr)
BOD 200-1000 <20 mg/l
COD 500-2500 < 60 mg/l
pH 5-8 6-8
Nitrogen 10-40 1-2
Phosphorus 10-40 1-2
TSS 150-350 10-15
Project : Affordable housing EWS LIG project (Expansion) Conceptual Plan &
Environmental Management Plan Developer : Anukampa Homes Pvt Ltd
EIA Coordinator Authorized Signatory
STORM WATER MANAGEMENT:
Construction Phase:
S. No. Contaminant Sources Impact Mitigation
1. Sediment &
Floatables
Streets, lawns, driveways,
roads, construction
activities,
During construction, sediment fencing or other
erosion control devices will be used to mitigate
the short-term adverse impacts of
sedimentation.
2. Oil & Grease Roads, driveways, parking
lots etc.
Oil & Grease trap will be provided to remove
oil & grease, suspended matter, and ensure the
quality of water.
Storm water control and rain water harvesting will be done as per the standards laid down by
CGWA & BIS. Following measure will be adopted for the same:
Construction Sequencing: Construction sequencing (involves disturbing only part of a site at a
time to prevent erosion from dormant parts) has been done at site. Grading activities and
construction are completed and soils are effectively stabilized on one part of the site before grading
and construction commence at another part.
Compost Blankets: A compost blanket is a layer of loosely applied composted material placed on
the soil in disturbed areas to reduce storm water runoff and erosion. This material fills in small rills
and voids to limit channelized flow, provides a more permeable surface to facilitate storm water
infiltration, and promotes re-vegetation.
Post Construction Phase:
a. Design:
For good design of rainwater harvesting, following points are to be kept under consideration:
Ideal location with good ground slope.
The location has adequate subsurface permeability of the aquifer to accommodate maximum
recharge of rainwater through injection well.
Rate of filtration should exceed average rainfall intensity.
Clogging of filtration media should be cleaned periodically.
Project : Affordable housing EWS LIG project (Expansion) Conceptual Plan &
Environmental Management Plan Developer : Anukampa Homes Pvt Ltd
EIA Coordinator Authorized Signatory
Ground water pollution does not take place.
b. Baseline:
The average annual rainfall (based on last 10 years rainfall data) is 597mm.
Rain Fall Data (last 10 years):
S. No. Year Annual Average Rainfall No. of Rainy Days
1 2014 606 40
2 2013 757 35
3 2012 907 28
4 2011 646 38
5 2010 750 40
6 2009 377 28
7 2008 572 32
8 2007 553 34
9 2006 407 27
10 2005 392 19
Total 5967 321
Average 597 32
Source: Water Resource Department, Rajasthan
Rainfall data recorded at Sanganer rain gauge station.
c. Calculation of No. of RWH Structures:
The rain water harvesting structures are calculated on the basis of peak intensity of rainfall
recorded as 60 mm/hr considering 15 minutes of peak rainfall. The same has been done to
avoid flooding of the area.
S.
No
Type of
Structure/ Surface
Area [A]
(sq. m.)
Run off
Coefficient
[C]
Intensity
of rainfall
(m/hour) [I]
Total discharge
[Q = CIA]
(m3/hr)
1. Roof Top 3531.15 0.9 0.06 190.7
2. Landscape 1224.58 0.3 0.06 22.0
3. Paved 7225.24 0.75 0.06 325.13
Grand Total (1-3) 11981.07 537.8 say 538
Project : Affordable housing EWS LIG project (Expansion) Conceptual Plan &
Environmental Management Plan Developer : Anukampa Homes Pvt Ltd
EIA Coordinator Authorized Signatory
Total Rain Water Flow : 538 m3/hr
Considering 15 minutes of peak rainfall,
Runoff volume : 135 m3/hr
Volume of each pit : 27m3 (3 m x 3 m x 3.3 m)
Total no. of rain water harvesting pits required : Total run-off volume/volume of each pit
: 135/27 = 5 nos.
Therefore, 5 Nos. rain Water Harvesting pit of size 3 m length x 3 m width x 3 m depth with PVC
slotted pipe upto minimum depth of 30 m as following figure.
d. Design of Rain Water Harvesting Structure:
The dimensional parameters of Desilting/Settlement chamber would be 3 m (length) x 3 m
(width) x 1.30 (depth). In Desilting chamber, 0.30 m depth below outflow is kept for silt
deposition. The filtration tank dimension would be 3 m (length) x 3 m (width) x 1 m (depth)
with 0.15 m dia recharge well of 30 m depth depending upon the formation for recharge in
aquifer through vadose zone. Each structure will be capable of handling rainwater volume @
27 m3/day and such structures will accommodate up to total rainfall volume of 47.28 m3 in
any rainfall event at peak rainfall occurrence.
Project : Affordable housing EWS LIG project (Expansion) Conceptual Plan &
Environmental Management Plan Developer : Anukampa Homes Pvt Ltd
EIA Coordinator Authorized Signatory
e. Calculation of annual recharge:
S.
No
Type of
Structure/ Surface
Area [A]
(sq. m.)
Run off
Coefficient
[C]
Intensity
of rainfall [I]
(m/annum)
Total discharge
[Q= CIA]
(m3/ annum)
1. Roof Top 3531.15 0.9 0.597 1897.2
2. Landscape 1224.58 0.3 0.597 219.3
3. Paved 7225.24 0.75 0.597 3235.1
Grand Total (1-3) 11981.07 5351.6 say 5350
Total Annual Recharge to Ground Water Regime of the area through rainwater harvesting structure
would be 5350 m3/ annum.
SOIL ENVIRONMENT: SOIL ANALYSIS
Location: Project Site ; Date of sampling: 02.10.2015
Parameters Results
Color Light Brown
pH (1:10) 8.30
Conductivity (1:10)( µS/cm) 226.0µS/cm
Moisture (%) 9.4 %
Chlorides as Cl (%) 0.006 %
Sulphate as SO4 0.003 %
Total Carbonates (%) 0.4 %
Total Organic Matter (%) 0.65 %
Nitrogen as N (%) 0.22 %
Phosphorous as P(%) 0.005 %
Potassium as K (%) 0.13 %
*Monitoring report is enclosed as Annexure IV.
WASTE MANAGEMENT:
CONSTRUCTION PHASE:
About 1873 MT (Existing: 1148 MT + Proposed: 725 MT) of the construction waste will be
generated. Details of the same is given as under:
Project : Affordable housing EWS LIG project (Expansion) Conceptual Plan &
Environmental Management Plan Developer : Anukampa Homes Pvt Ltd
EIA Coordinator Authorized Signatory
S. No. Particulars Approx. Qty, (MT) Disposal
Existing Proposed
1. Wood 551 348 Sold to vendors
2. Dry Wall 230 145 Disposal site.
3. Concrete 103 65 Disposal site.
4. Metal Scrap 23 15 Sold to vendors
5. Cardboard 172 109 Sold to vendors
6. Plastics 23 15 Sold to vendors
7. Electronic Scrap 23 15 Disposal site.
8. Misc.(Paint, Ceramic etc) 23 15 Disposal site.
POST CONSTRUCTION PHASE:
The solid waste generated from the project considering full occupancy will be mainly domestic
waste and estimated quantity of the same will be approx 1410 kg/day. The solid waste generated
will be first segregated as plastic, glass, paper, and other waste separately and disposed off as per
MSW Rules.
Waste Type Estimated Quantity
Compostable Waste 1128 kg/day
Plastic 152 kg/day
Paper waste 96 kg/day
Metal Cans 8 kg/day
Glassware 18 kg/day
Project : Affordable housing EWS LIG project (Expansion) Conceptual Plan &
Environmental Management Plan Developer : Anukampa Homes Pvt Ltd
EIA Coordinator Authorized Signatory
Misc. 8 kg/day
Total 1410 kg/day
ENERGY CONSERVATION CALCULATIONS:
Total flat light load can be reduced by 40% by use of LED lamps in place of fluorescent/
incandescent lamps.
Total landscape and street light load will be met through solar powered fixtures.
Total geyser load can be reduced by 10% by using solar power.
Lift load can be reduced by 23% by use of VF drives.
All capacitors will be provided with Harmonic Filters to avoid distortion in Voltage.
Automatic Power Factor correction panel with capacitor will be used for Common Load &
Fixed Capacitor for Transformer to minimize the losses.
Emphasis will be given on low maintenance, low wattage and longer life in selection of chokes
and lamps for all common area and external light fixtures.
SOCIO-ECONOMIC ENVIRONMENT
STUDY AREA:
The study area of 1.0 km radius comprises of the habitation of Muhana and Madau villages. Social
infrastructure of schools, hospitals and recreational activities are available in the vicinity.
POPULATION
The total population of the study area is 8887, the males constitute of 52 per cent and females are
47.98 per cent. The 0-6 population constitute of 15.38 per cent. The sex ratio of the study area is
859 females over thousand males. The child sex ratio is 854 girls on thousand boys. In each
household approximately 4 to 6 persons live together.
TABLE: POPULATION OF THE STUDY AREA
VILLAGE
NAME MALE FEMALE
MALE
(0-6)
FEMALE
(0-6) HOUSEHOLD
Mandau 760 710 129 123 250
Muhana 3863 3554 598 517 1107
Total 4623 4264 727 640 1357
8887
*Sources: CENSUS OF INDIA 2011
Project : Affordable housing EWS LIG project (Expansion) Conceptual Plan &
Environmental Management Plan Developer : Anukampa Homes Pvt Ltd
EIA Coordinator Authorized Signatory
LITERACY
The literate population of the study area is 5512 which constitute to be 62.02 per cent. The male
literacy with respect to male population is 59 per cent and female literacy totals 40.98 per cent with
respect to female population in the study area
TABLE : LITERACY STATUS OF THE STUDY AREA
VILLAGE NAME MALE FEMALE
Mandau 527 385
Muhana 2726 187
Total 5512
*Sources: Census of India, 2011
ECONOMIC DEVELOPMENT
The total working population of the study area is 3573 accounting to be 40.20 per cent. From the
total working population the main workers constitute of 83.87 per cent and marginal working
population is 16.12 per cent. The female working population is 31.5 per cent with respect to female
population of the study area. The majority of the main population in the study area is engaged in
agriculture and related activities. In the study area people are also occupied in other works like
government services, private jobs, manufacturing, retailing etc.
TABLE:EMPLOYMENT STATUS OF THE STUDY AREA
VILLAGE
NAME
MAIN WORKING
POPULATION
MARGINAL WORKING
POPULATION
NON-WORKING
POPULATION
MALE FEMALE MALE FEMALE MALE FEMALE
Mandau 312 224 39 39 409 447
Muhana 1709 752 166 332 1988 2470
Grand total 2997 576 5314
Total Working
Population
3573 5314
*Sources: Census of India, 2011
SOCIO ECONOMIC IMPACT ASSESSMENT
The proposed project showcases the EWS LIG affordable housing development in the study area.
The proposed project will fulfill the housing requirements of urban masses. It will also help in
generating revenue for state government and development authorities.
Project : Affordable housing EWS LIG project (Expansion) Conceptual Plan &
Environmental Management Plan Developer : Anukampa Homes Pvt Ltd
EIA Coordinator Authorized Signatory
The proposed project will create direct employment opportunities to at least 200 people during the
construction phase. The project is targeted for the economic weaker section and low income group
people, the project will cater to the good quality affordable housing demands of the city. Increased
income security will contribute to the empowerment of the most vulnerable sections of the society
TABLE : IMPACT IDENTIFY IN THE PROJECT AREA
IMPACT DEGREE OF IMPACT DESCRIPTION
Employment
Generation Positive & Long Term
Direct Employment: At the construction phase 200
employees will be given employment.
Indirect Employment: The housing project will bring indirect
employment in the study area as there will be increase in
grocery shops, departmental store, vendors, iron shops etc.
Increase in
Local
Amenities
Long Term
The local amenities in the study area will increase. It is a sign
of development in the study area such as new water
connections, electricity connections, phones etc.
Cultural Mix Long Term Influx of people is expected which will bring cultural mix.
Increase in
Government
revenues &
taxes
Positive & Long Term Increase in local amenities will lead to increment in revenues
& taxes by government.
Permanent
Housing to
increase
Quality of life
Positive & long Term
The occupants will be able to save as their will be housing
security. Children will be able to get steady education.
Higher level of satisfaction.
Construction
Phase Negative & Short Term
The construction phase might create negative impacts around
the site area such as litter, noise, influx of people from
outside
EXPENDITURE ON ENVIRONMENTAL MEASURES:
S. No. Particulars Capital Cost
(in lacs)
Annual recurring
cost (in lacs)
1. Acoustic enclosures & stack attached to DG sets 1 0.1
2 STP 25 2
3 Rain water harvesting 7.5 --
4 Solid waste management 5 1
5 Pollution monitoring 0.5 0.5
6 Fire fighting & emergency handling 35 1
7 Green Belt 5 1
Project : Affordable housing EWS LIG project (Expansion) Conceptual Plan &
Environmental Management Plan Developer : Anukampa Homes Pvt Ltd
EIA Coordinator Authorized Signatory
TOTAL
**********