Chapter 2 ELECTRICAL POWER SUPPLY AND DISTRIBUTION IN BUILDINGS 2.1 TRANSMISSION AND DISTRIBUTION OF...
-
Upload
constance-weaver -
Category
Documents
-
view
238 -
download
1
Transcript of Chapter 2 ELECTRICAL POWER SUPPLY AND DISTRIBUTION IN BUILDINGS 2.1 TRANSMISSION AND DISTRIBUTION OF...
Chapter 2ELECTRICAL POWER SUPPLY AND DISTRIBUTION IN BUILDINGS
2.1 TRANSMISSION AND DISTRIBUTION OF ELECTRICITY
Power network (grid): Combination of power transmission and distributionsystems at various stages at various standard voltage levels.
Stages of a Power network :(i) Generation Electrical energy is generated from power stations generally at 11 kV or 15 kV three phase and at standard frequency.
(ii) Primary Transmission Power enters to step-up substation, where the voltage is stepped up to higher voltages for transmission at 132 kV or 220 kV to a complex network comprising transmission lines or cables known as national grid.
2
(iii) Secondary TransmissionFrom the primary transmission substation the power is transmitted at 66 kV or 33 kV through sub-transmission lines to different load centres. The sub-transmission lines terminate at the secondary transmission substations to step down the voltage from 66 kV to 33 kV.
(iv) Primary DistributionThe power is distributed at 33 kV to main load centres inside a city through either primary distribution cables or lines, then further stepped down to 11 kV at primary distribution substations.
(v) Secondary DistributionClose to consumers the voltage stepped down to 415 V and 240 V at local secondary distribution substations and finally delivered to domestic, commercial and small-scale industrial customers through either lines or underground cables.
3
Underground lateral distribution(415 V/240 V
Local garage(415 V)
Houses(240 V)
Shops(240 V)
Local (secondary) distributionS/S (11 kV/415 V, 240 V)
Small Industrialestate (11 kV)
Heavy industrial estate(11 kV/ 2400 V, 415 V )
Primary distribution S/S33 kV D/11 kY Y
Secondary transmissionline (66 kV)
Overhead transmisssion line (220 kV or 132 kV)
Step-up S/S(11 kV/220 kV)
Generating Station (11 kV)
Primary transmission S/S (220 kV/66 kV)
Primary distribution (33 kV)
Secondary distribution (11 kV)
S/S-Substation
Secondary transmissionS/S (66 kV/33 kV)
Figure 2.1 Simplified diagram of a power system from power station to consumer services.
4
The reason for transmitting power at high voltages is due to conductor resistance.
If the transmission would be at low voltages, transmission line I2R power losses become high because of high current. (Vtr is low → I is high → IV is high → I2R is high)If the transmission would be at high voltages, transmission line I2R power losses become low because of reduced current. (Vtr is high → I is low → IV is low → I2R is low)and ● conductor diameter would be reduced and ● efficiency of transmission will get increase.At various stages of a power system power equipment and voltages are standardized. This allows to reduce;
● construction cost, ● running cost and● maintenance cost,
These overall effectively reduce turning-off time of equipment in use and hence, of the system.
5
2.2 ELECTRICAL DISTRIBUTION IN BUILDINGS
The purpose of electrical installation in buildings is to ●supply and ● distribute
electric power according to the requirements of the building.
Secondarydistribution
S/S
Low-voltage distributioncabinet or junction
point
Underground 11-kV cable
Underground230 / 400 V supply cable
SecondaryDistributionS/S
SecondaryDistributionS/S
Functional building
Industrial buildingResidential buildings
Figure 2.2 Distribution system for residential, functional and industrial loads.
6
Secondary Distribution SubstationThe local secondary power distribution substations are either - indoor or outdoor type - located along roadside blocks close to the buildings or - within buildings in substation chambers and - wired to the distribution boards via underground - cables and - busbar trunks. In every secondary distribution substation voltage transformation
at various stages of the power system network is performed by step- down transformers, which are equipped with;
- Connecting and coupling busbars - Low-voltage protective devices - Circuit breakers integrated to relaying systems. All these equipment are installed in substation distribution boards (or panels), which are located closed to the secondary distribution transformer and within the substation (room) chamber.
Figure 2.3 Simplified low-voltage secondary distribution system to buildings from a local secondary distribution transformer.
7
Secondary distributionsubstation
Load levelSupply level
Undergroundsupply cable
Localgarage
HousesShops
Meter and distributionboards (TPN)Meter and distribution
boards (TPN or SPN)
HV cable system
LV distribution with cable systemLV Installation with cable system
Secondary distributionsubstation panel (switchboard)
JB-Joint box
Underground service cable
8
Most of domestic or small scale commercial consumers with power requirements up to 200 kW - 300 kW is usually supplied from local distribution system of the electric authority as
- SPN (Single-phase and neutral) or - TPN (Three-phase and neutral)
Power suppliedfrom 11 kV
primarydistribution
network
R
Y
B
N
N
CB
11 kV/415 V, 240 Vdelta/wye connected (local) transformer
Protective and switchingdevices for secondary loads
E
Protective earthing (PE)
Secondaryloads:residential,commercialetc
All connections to (E) terminalsin DB via armour (PE) of cables.
Secondary distribution sub-station (room) chamber
Figure 2.3 Simplified local secondary distribution substation with /Y connected 11 kV/415 V, 240 V transformer supplying residential buildings
Secondary Distribution Substation
9
The reason for connecting the secondary side of the transformer in wye (Y) form because of the need for a neutral for single-phase distribution at load levels. To achieve this, the neutral point of the secondary winding is solidly connected to ground via ‘earth electrode’.
The neutral point of the transformer is connected to neutral terminal (N) together with line (L) conductor in customer DB to provide power to customers.
The neutral point of the transformer is also connected to earth terminal (E) in customer DB via protective earth (PE) conductor.
The supply to premises is taken by underground cables or overhead lines terminating at service cut-out within a premise.
- Underground cables are usually brought through ducts below floor level and
- Overhead lines by towers.
10
2.3 DISTRIBUTION SYSTEMS IN BUILDINGS
Distribution in a large scale residential buildings (Fig.2.4).
Secondary distributionpower station
DB
HeatingLightingLift andWater pump
Socketoutlets
WashingmachineCooker
Lighting
Conventional installationsor final circuits in
residential buildings
Loadlevel
Maindistribution
level
Power supplylevel
Distribution boards toflats or other
building services
Main distribution board (cubicle)
Busbar trunking system or cable
Busbar trunking system or cableInstallation with cable system
PowerDB
Final circuits
415 V /240 V
11 kV
11 kV / 415 Vpower transformer
Substationdistribution panel
Figure 2.4 Supply arrangement in a residential building.
11
Secondary distributionpower station
Conventional installationsin service buildings
Load levelMaindistribution
level
Power supply level
Distribution boards, busbartrunking, cable installations tosystem services
Main distribution panel(cubicle)
Sub-distribution level
Busbar trunking system or cable/line systems
Busbar trunking system or cable systemsInstallation with cable systems
Installation with cable systems
Main distributionboard
Sub-distributionboard
11 kV
415 V / 240 V
Figure 2.5 Supply arrangement in an industrial or functional building.
Distribution in an industrial or functional building (Fig.2.5).
12
At all levels of the distribution in buildings solid connections to various service cables or busbar trunking systems are established by main and sub-main distribution boards. These provide;
- easy installation - easy maintenance and - safe operation
at every levels of installation systems.
At main distribution level (Figs.2.4 and 2.5) main distribution boards are used for;
- Safety disconnection - Coupling busbar sections - Protecting busbars
At sub-distribution level (Fig.2.4), subdistribution boards are used for:- Safety disconnection for maintenance- Switching lighting and power loads- Protecting all electrical cables and busbars and loads.- Control, metering and measuring purposes.
13
Both distribution boards are equipped with;- Circuit breakers and tie circuit breakers - Isolators- MCCBs- Fuses
14
DistributionBoard
Sub-distributionBoard
Secondary Distribution Substation
SubstationPanel
11 kV / 415 VTransformer
Main DistributionBoard (Block 1)
Distribution Board
Trunking System
RaisingMain
Main DistributionBoard (Block 2)
Figure 2.6 Supply arrangement in an industrial building
15
2.4 INTAKE TO SMALL SCALE BUILDINGS
Basic elements of TPN distribution board to a small scale customer:
Power supply authority provides low-voltage supply to premises via underground cables in populated areas and via overhead lines at remote sites or in rural area from a local 11 kV- 415 V and 240 V secondary distribution substation.)
Customer intake boards:
▪ Meter Board (MB) equipped with:
- kWh meter
- Protective devices PD to protect main supply cable
to customer DB
▪ Distribution Board (DB) equipped with:
- Isolators
- RCCB (Residual Current Circuit Breaker)
- MCB (Miniature Circuit Breakers)
16
are used for:
- Protecting persons and property
- Protecting cables, lines and loads
- Safety disconnection for maintenance and repair
- Monitoring, signalling and controlling
▪ Customer intake boards are used for:
- Protecting persons and property
- Protecting cables, lines and loads
- Safety disconnection for maintenance and repair
- Monitoring, signalling and controlling
17
Meter board (MB)
Underground supply cable system in duct
Customer distribution board (DB)
Power meter
Final circuitsfeedingsocket-outlets,air-conditioningsystemswater heaters,heating systems,etc.
Consumer'sEquipment
Supplier'scut -out box
Supply authorityequipment (sealed)
Protectivedevices
Main supplycable
Four-corePVC cable
R
Y
B
N
Isolatorswitch
Final circuitsfeedingsocket-outlets,air-conditioningsystemswater heaters,heating systems,etc.
Protectivedevices
MCCB
Figure 2.7 Supply intake and connections to a small-scale residential or commercial premise.
18
Meter board (MB): The supply is taken from the service cut-out to the consumer's distribution board through meter board installed with;
- service cut-out fuse box - power (kWh) meter and
- overcurrent protective device (PD). The service cut-out box may sometimes be located within MB.
The power meter and the service cut-box belong to the supply authority and are also sealed to prevent unauthorised changes to be made on
elements and connections Overcurrent protective device: It is an optional device, and is
installed just after the meter in order to protect supply cable to DB. It is a circuit breaker enclosed in a moulded plastic case, known as
moulded case circuit breaker (MCCB). Under any type fault conditions or maintenance beyond MB, it interrupts the consumer's circuit and
avoids unnecessary operation of cut-out fuses.
(iii) Consumer distribution board (DB) In domestic and small scale industrial premises;
- DB supplies final circuits to serve various types of loads, e.i., it distributes power to final circuits.
19
DB is equipped with; - The isolating switch is double-pole for single phase and three-pole for three-phase installations. - One or two residual-current circuit breakers (RCCB) and - Minature circuit breakers (MCB) or fuses to protect
consumer's load and final circuits.
Protectivedevices
N
N
NIsolatorswitch
ERCCB
GR-2: Final circuitsserving lighting loads,all lamps, small fansetc.
GR-1: Final circuits servingfor power loads: socket-outletcircuits, air-conditioner,motors, etc.
Figure 2.8 General layout of a consumer distribution board.
The supply intake to a premise should be arranged in such away that the cut-out box and meter should be outside the premise for - easy replacement of fuses and meter reading without entering the premise
20
Radial circuit of 13-Asocket outlets
Looped in lighting final circuits
4.0 mm2
2.5 mm2
2.5 mm2
Spur
6 A
30 A
20 A
30 A
2.5 mm2
Spur
DB
Two-wayswitching
Double-poleswitch WH W ater heater as
single-point loadMain supplycable from MB.
Ring circuit of 13-Asocket outlets
1.5 mm2
13-A socket outlets
21
POWER INTAKE TO A MULTI-METERED BUILDING
In small-scale multi-floor residential distribution systems positioning MB; MB of each flat are usually installed at the main entrance of the
building (in main hall or stairway) enclosed in a cabinet or board. MB should not be installed along escapes routes and be
preferable to be concealed. Adequate spacing should be allowed for ventilation and for maintaining the devices. It is advisable to reserve adequate space for additional meter installations. To install cables serving DBs to each flat at each floor, Location of MBs should be at a central position of the building (Fig. 2.12). MBs must be positioned to facilite easy reading at a height between 1.0m and 1.80 m above the finished floor level. It should be protected with a lockable door.
A separate MB is required installed next to customer MBs for common services such as general lighting in stairways, corridor, halls, and intercome services etc. The cables supplying costumer DBs from MBs should always be TPN.
22Figure 2.12 Meter and distribution boards in mult-metering residents.
In multifloor high rise office buildings subjected to single meter reading, raising-main busbar duct-system is the convenient method to supply consumers DBs (see Chapter 13).
kWh kWh kWhkWh kWhkWhkWh
Meter Board
Servicecutout box
Ground
1st
2nd
Main supplycables to flatsinstalled throughconduits
DB for commonservices
Costomer DB
MCB or fuse
Floor levels
23
Safety rules applied to installation of MBs and DBs.The minimum clearance from any fitting related to plumbing such as water tabs, basins, sinks, metal drainage boards etc., shall be 2 m. No water sprinkler system should be installed in the close vicinity of MBs. MBs must have an identification symbol for the space they serve in the case of multi-meter buildings. They must have an identification schedule for final circuits.