Case Study Presentation- Bostons Big DIg

15
CASE STUDY BOSTON’S BIG DIG Ajay Gupta Engineering Cost Estimation Techniques. EMGT - 709

description

Case Study Presentation

Transcript of Case Study Presentation- Bostons Big DIg

Page 1: Case Study Presentation- Bostons Big DIg

CASE STUDYBOSTON’S BIG DIG

Ajay Gupta

Engineering Cost Estimation Techniques.

EMGT - 709

Page 2: Case Study Presentation- Bostons Big DIg

Big Dig: Project Summary

Demolition of Existing Central Artery and Replace it with 3.5 Mile underground tunnel.

Ted Williams Tunnel: Connects I-90, I-93, and Logan International Airport.

Leonard P. Zakim Bunker Hill Bridge: I-93 Bridge over the Charles River.

Rose Kennedy Greenway in the space vacated by the previous I-93 elevated roadway.

Page 3: Case Study Presentation- Bostons Big DIg

BEFORE

AFTER

Page 4: Case Study Presentation- Bostons Big DIg

Central Artery Before and after

Before: 2003 After: 2005

Page 5: Case Study Presentation- Bostons Big DIg

Why Big Dig ?

1959 Early 1990

Page 6: Case Study Presentation- Bostons Big DIg

Funding Sources

Big Dig…

InterstateHighwayProgram

IntermodalSurface

TransportationEfficiency Act (ISTEA)

National EconomicCrossroads

TransportationEfficiency

Act (NEXTEA)

TransportationEfficiency

Act (TEA) - 21

Mass.Highway Dept.

formerly (Mass. Dept. of

Public Works)

Mass. Transportation

Authority

Mass. Turnpike Authority

Mass. Port

Authority

State Bonds(Issuing authorityunknown)

Federal

State

Page 7: Case Study Presentation- Bostons Big DIg

Original Cost Estimate: 1982 Dollars

Estimated cost $2.5 Billion

Project Features:

New Charles River Crossing

Joint Venture Contract

Right of Way/ S. Boston

Extend I-93 South

Tunnel Covers

Utilities Relocation

Workmen’s Compensation

Other

Source: Final Environmental Impact Statement,1985

Completion Date: 1998Completed - 2007

Actual Cost $8.08 BillionActual Cost $14.6 Billion

In 2003 Dollars

Page 8: Case Study Presentation- Bostons Big DIg

Cost Estimation Revision 1

Revise Cost Estimates in 1992 Dollars

• Original Estimate $2,564

• Features Added $471

– I-90 and I-93 HOV Lanes  

– South Boston Haul Road  

– Material disposal/ hazardous materials  

– Deleted interchange  

– Other  

• Scope change to existing project features $2,151

Total In million Dollars $5,186

Escalation to 1992 Dollars: $2,553

Subtotal $7,739

Page 9: Case Study Presentation- Bostons Big DIg

Cost History in Million Dollars

1985

EIS

1987

ICE

1989

ICE

1991

ICE

1991

APF

1992

APF

1992

APF

w/ N

CRC

1994

CSU

6 w/ I

nflat

ion

1994

CSU

6 19

97 R

ebas

elin

e

2000

CSU

7

2001

CSU

8

2002

CSU

8

2002

CSU

90

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

2,5643,175

4,4365,193

5,7806,443

7,740

10,468 10,841

14,07514,475 14,625 14,625

2,5643,175 3,409 3,708 3,963 4,317

5,1875,597 5,810

7,658 7,886 7,972 8,000

Chart Title

2003 Dollars 1982 Dollars

Source: Completing the “Big Dig”: Managing the Final Stages of Boston’s Central Artery/Tunnel Project (2003).

Page 10: Case Study Presentation- Bostons Big DIg

Project Escalation: 7 years behind schedule

1989 PMS REV. 1

1990 PMS REV. 2

1991 PMS REV. 3

1992 PMS REV. 4

1993 PMS REV. 5

1994 PMS REV. 6

2000 PMS REV. 7

2001 PMS REV. 8

2002 PMS REV. 9

1994 1996 1998 2000 2002 2004 2006

1998

1998

1998

2001

2004

2004

2004

2004

2005

Source: Completing the “Big Dig”: Managing the Final Stages of Boston’s Central Artery/Tunnel Project (2003).

Page 11: Case Study Presentation- Bostons Big DIg

Reasons For the Cost Growth

15%

8%

7%

5%

3%2%

5%

55%

Mitigation

Scope Growth

Accounting Changes

Traffic

Schedule Maintenance

Contigency for Unknowns

Other

Inflation

Source: Completing the “Big Dig”: Managing the Final Stages of Boston’s Central Artery/Tunnel Project (2003).

Page 12: Case Study Presentation- Bostons Big DIg

Mitigations

Opportunity to turn complaint into benefits

Rats

Fish

Fire Boats

Memorials

Parks

Final mitigation costs $3 Billion.

Page 13: Case Study Presentation- Bostons Big DIg

Final number.

$22 billion and wont be paid until 2038.

Including interest on debt.

Interim borrowing.

Principal repayment.

Possible future growth of the bottom line for construction and support contracts.

Commonwealth’s taxpayers and toll payers will foot a bill for the remaining $9 billion over the life of the bonds. This sum is equivalent to $1,500 for each of the Commonwealth’s six million citizens.”

Page 14: Case Study Presentation- Bostons Big DIg

Conclusion

The original estimate was developed in 1982 dollars, without allowance for inflation or mitigation.

Mitigation costs are expected to be very high. Requirements for significant mitigation were identified in the original 1985 cost estimates, but the costs were not identified.

Other factors that increase costs and delay schedules should and could have been anticipated and addressed through additional planning and design, site analysis, and cost and schedule contingencies.

Other Projects could benefit from the lesson learnt from Big Dig.

Page 15: Case Study Presentation- Bostons Big DIg

THANK YOU !