Bertha STP Repair Plan May2014-1
Transcript of Bertha STP Repair Plan May2014-1
-
8/18/2019 Bertha STP Repair Plan May2014-1
1/15
June 2014Seattle Tunnel Partners, WSDOT’s
contractor for the SR 99 TunnelProject, is building a pit to access
and repair Bertha, the SR 99
tunneling machine. The following
images illustrate STP’s
conceptual plan for resuming
tunneling.
Repairing the
SR
TUNNELING
MACHINE
-
8/18/2019 Bertha STP Repair Plan May2014-1
2/15
November:
STP provides
WSDOT with
a full list of
repairs
April May June July Aug. Sept. Oct. Nov. Dec. Jan. Feb. March
2014 2015
April 21: STP announces new schedule
Late May: Underground wall
construction begins
Late July: Access pit
excavation begins
October: STP begins
repairs to seal system
and replacement of
main bearing February:
Testing ofmachine
begins
March 2015:
Tunneling
resumes
June 16:
STP/Hitachi
announce
repair plan
Seattle Tunnel Partners’ repair schedule
Seattle Tunnel Partners’ repair plan – June 2014 2
-
8/18/2019 Bertha STP Repair Plan May2014-1
3/15
Looking southeast
toward the site wherecrews are bui lding a120-foot-deep circular
pit to access and repairBertha. Contractor
Seattle Tunnel Partners
built the white walls onthe west side of the SR
99 Alaskan Way Viaductto minimize noise during
construction.
Access pit site today, above ground
CONCEPTUAL
3Seattle Tunnel Partners’ repair plan – June 2014
-
8/18/2019 Bertha STP Repair Plan May2014-1
4/15
This underground view
shows Bertha’s currentlocation between SouthJackson and South Main
streets in Seattle. The redline shows the path
Bertha will take once she
resumes tunneling. Thesections of gray on both
sides of Bertha areunderground walls built to
protect the Alaskan WayViaduct and nearbybuildings from settlement
during the initial section ofthe tunnel drive.
Access pit site today, below ground
CONCEPTUAL
4Seattle Tunnel Partners’ repair plan – June 2014
-
8/18/2019 Bertha STP Repair Plan May2014-1
5/15
CONCEPTUAL
The dark gray areas in
this image show wheregrout was injectedbetween segments of
existing undergroundwalls on the east and
west sides of Bertha.
The grout furtherstabilizes the ground
and is one of many toolsSTP will use to keep
water out of the access pit. The grout injectionwas completed on
schedule in May 2014.
Step 1: Inject grout between existing piles
CONCEPTUAL
5Seattle Tunnel Partners’ repair plan – June 2014
-
8/18/2019 Bertha STP Repair Plan May2014-1
6/15
-
8/18/2019 Bertha STP Repair Plan May2014-1
7/15
CONCEPTUAL
Step 2: Relocate utilities (after)This image shows where
sewer, electrical,telecommunications andwater lines are being
relocated to make roomfor construction of the
access pit. Utility
relocation started onschedule in May 2014.
7Seattle Tunnel Partners’ repair plan – June 2014
-
8/18/2019 Bertha STP Repair Plan May2014-1
8/15
CONCEPTUAL
Step 3: Inject grout behind the machineSTP crews injected a
wall of grout near theback of the machine’sshield to seal water out
of the access pit. Thiswork was completed on
schedule in May 2014.
8Seattle Tunnel Partners’ repair plan – June 2014
-
8/18/2019 Bertha STP Repair Plan May2014-1
9/15
CONCEPTUAL
Step 4: Build the access pit’s walls STP crews are installing
concrete columns thatwill form theunderground walls of the
circular access pit. Madeup of 73 columns, the pit
will be about 120 feet
deep and more than 80feet wide. Underground
wall construction startedon schedule in May
2014.
9Seattle Tunnel Partners’ repair plan – June 2014
-
8/18/2019 Bertha STP Repair Plan May2014-1
10/15
Step 4: Build the access pit’s walls STP crews are installing
concrete columns thatwill form theunderground walls of the
circular access pit. Madeup of 73 columns, the pit
will be about 120 feet
deep and more than 80feet wide. Underground
wall construction startedon schedule in May
2014.
CONCEPTUAL
10Seattle Tunnel Partners’ repair plan – June 2014
-
8/18/2019 Bertha STP Repair Plan May2014-1
11/15
Step 5: Lower groundwater, tunnel into wallSTP crews will install
wells to lowergroundwater near theaccess pit. This will
make i t easier for themachine to tunnel
through the soil and into
the pit wall.
CONCEPTUAL
11Seattle Tunnel Partners’ repair plan – June 2014
-
8/18/2019 Bertha STP Repair Plan May2014-1
12/15
Step 6: Excavate, then tunnel into access pit After the access pit has
been excavated, Berthawill tunnel into the pit. Aconcrete cradle will hold
Bertha in place whileshe is being repaired.
CONCEPTUAL
12Seattle Tunnel Partners’ repair plan – June 2014
-
8/18/2019 Bertha STP Repair Plan May2014-1
13/15
Step 7: Install a crane above the access pit A large crane wil l be
installed above theaccess pit to l ift piecesto the surface for repair.
The crane will be similarto the one used to
assemble Bertha in her
launch pit beforetunnel ing started in July
2013.
CONCEPTUAL
13Seattle Tunnel Partners’ repair plan – June 2014
-
8/18/2019 Bertha STP Repair Plan May2014-1
14/15
Step 8: Remove pieces, make repairsCrews will repair Bertha
at the surface beforereassembling her in theaccess pit. STP will
thoroughly test Berthabefore tunneling
beneath downtown.
CONCEPTUAL
14Seattle Tunnel Partners’ repair plan – June 2014
-
8/18/2019 Bertha STP Repair Plan May2014-1
15/15
STP plans to resume tunneling in March 2015
CONCEPTUAL
15