Baker Road WWTP PPCP & MSP Update Maintenance and … · 2020. 2. 25. · GM BluePlan Baker Road...
Transcript of Baker Road WWTP PPCP & MSP Update Maintenance and … · 2020. 2. 25. · GM BluePlan Baker Road...
1
Baker Road WWTP PPCP & MSP UpdateTM#3 Review
February 20th, 2020
10:30 am – 12:00 pm
GM BluePlan Baker Road WWTP PPCP & MSP Update – Meeting #4 February 20th, 2020
2GM BluePlan Baker Road WWTP PPCP & MSP Update – Meeting #4 February 20th, 2020
Agenda
1. Meeting Objectives
2. Model Scope
3. Existing Model
4. Model Update Approach and Data Review
5. Data Gap Analysis
6. Next Steps
3GM BluePlan Baker Road WWTP PPCP & MSP Update – Meeting #4 February 20th, 2020
MEETING OBJECTIVES
4GM BluePlan Baker Road WWTP PPCP & MSP Update – Meeting #4 February 20th, 2020
Discussion
• The primary focus of today is to
– understand model methodology and how data will be
used
– Discuss Key Data Gaps
• Discussion on
– Methodology
– Sources of data
– Gaps
5GM BluePlan Baker Road WWTP PPCP & MSP Update – Meeting #4 February 20th, 2020
MODEL UPDATE APPROACH
6GM BluePlan Baker Road WWTP PPCP & MSP Update – Meeting #4 February 20th, 2020
Model Scope
• All-pipes
• Dynamic dry and wet weather
• Calibrated to observed data
• Facility process controls and CSOs accurately
represented
7GM BluePlan Baker Road WWTP PPCP & MSP Update – Meeting #4 February 20th, 2020
Existing Models
Municipality Model Use in PPCP
Region 2016 MSP Model Trunk and facilities
Lincoln All-pipes model Local network
Grimsby Roberts Road sub-model Network and wet
weather RTK
parameters
West Lincoln No model
8GM BluePlan Baker Road WWTP PPCP & MSP Update – Meeting #4 February 20th, 2020
Approach Summary
1. Network Update
2. Facilities Update
3. Catchment Delineation and Flow Loading
4. Calibration
5. Validation
9GM BluePlan Baker Road WWTP PPCP & MSP Update – Meeting #4 February 20th, 2020
Model Update Process
Flow Monitoring
Program
Flow Analysis
Baseline Dry
Weather Flows
Baseline Wet
Weather Flows
Model Update
& Calibration
WWF –
RTK Parameters
WWF –
Validation Data
Validated WW
Model
Full Pipe Network
Update
Updated WW
Model
Region MSP
+Lincoln
Model
Grimsby and
West Lincoln
GIS
10GM BluePlan Baker Road WWTP PPCP & MSP Update – Meeting #4 February 20th, 2020
Network Review
Ownership% Pipes
Missing Diameter
% Pipes
Missing Inverts
% Pipes
Missing From MH
% Pipes
Missing To MH
Grimsby 1% 13.8% 100% 100%
Lincoln 0% 0% 0% 0%
West Lincoln 3% 10% 0% 0%
Ownership% MHs Missing Rim
Elevation
Grimsby 28.7%
Lincoln 0%
West Lincoln 14.4%
11GM BluePlan Baker Road WWTP PPCP & MSP Update – Meeting #4 February 20th, 2020
Network Update
• Cross-Reference Existing Model Network against:– GIS infrastructure*
– Existing Local models*
• Identify Discrepancies & Missing Network
• Update Discrepancies to Reflect Current Network– Connectivity
– Diameter
– Material
• Extend Model Network*
Not in Model
No Discrepancy
Attribute Discrepancy
12GM BluePlan Baker Road WWTP PPCP & MSP Update – Meeting #4 February 20th, 2020
Facilities Review
WWTP
•Secondary bypass logic needs clarity
•>120 MLD?
SPS
•Pump curves where available
•Missing drawdown testing
CSOs
•Configuration
•Key elevations need confirmation
13GM BluePlan Baker Road WWTP PPCP & MSP Update – Meeting #4 February 20th, 2020
CSO Review - Examples
Grimsby- Murray & Lakeside Drive - CSO
Map Data © 2020 Google
Appendix C in TM#3
MSP model
• Overflow invert elevation 78.89 m
• Diameter = 375 mm
• No “outfall” in model
14GM BluePlan Baker Road WWTP PPCP & MSP Update – Meeting #4 February 20th, 2020
Baker Road WWTP - CSO
Map Data © 2020 Google
MSP model
• Side flow weir from
Lake Street, 1050 mm
pipe to Baker Road
outfall
• Also effluent pipe in
model?
• MH invert 77.69 m
• Weir height = 1.2 m
Need to review
overflow
configuration!Weir GIS invert 77.69 m
Outfall
elevation
66.961 m
15GM BluePlan Baker Road WWTP PPCP & MSP Update – Meeting #4 February 20th, 2020
Wastewater Modelling Approach – Facilities Update
Review Key Facilities and Identify New/Modifications
• Existing models
• ECAs
• Facility drawings
Existing Facilities
• Confirm existing model → with ECAs
• Review if discrepancies (see new/upgrade)
• Update facility configuration, pump curves, geometry, etc. as required
Consolidate Available Facility Control Data
• Existing models
• SCADA
Model Review Workshop
• Staff feedback
• Meeting #6 - June 2020
16GM BluePlan Baker Road WWTP PPCP & MSP Update – Meeting #4 February 20th, 2020
Flow Monitoring- TM #2 Implementation
In addition to historic
Town/Region monitoring
17GM BluePlan Baker Road WWTP PPCP & MSP Update – Meeting #4 February 20th, 2020
• Region rain gauges
• RGs ideally 5km
radius for event
calibration
accuracy
• Lincoln Rain gauge
for Vineland,
Campden and
Jordan Station?
Rain Gauges
18GM BluePlan Baker Road WWTP PPCP & MSP Update – Meeting #4 February 20th, 2020
Precipitation Analysis
• Will also discuss in LOS
workshop
• Need consensus on IDF
curve to use for design
storm scenarios
19GM BluePlan Baker Road WWTP PPCP & MSP Update – Meeting #4 February 20th, 2020
Dry Weather Flow
• Dry Weather Flow (DWF) is the normal (in a typical dry day) amount of flow through a sanitary sewer during periods with no rainfall or snow melt including groundwater infiltration (GWI).– Base sanitary flow (BSF): Sewage
generated from domestic, commercial, and industrial uses.
– Groundwater infiltration (GWI): Groundwater that enters the wastewater system and is a “constant” flow source
20GM BluePlan Baker Road WWTP PPCP & MSP Update – Meeting #4 February 20th, 2020
Dry Weather Flow Loading
• Develop pipe sewershed
– Parcels allocated to closed sewer
– Limit to parcels fronting sewers
– Limit area to 100m buffer
• Validate
– Identify billed parcels not allocated & verify
– Manual review major water users
• Allocated Base Sanitary Flows Based on Billing
– Base Sanitary Flows – 90% of water billing
21GM BluePlan Baker Road WWTP PPCP & MSP Update – Meeting #4 February 20th, 2020
Dry Weather Flow Loading
• Confirm Actual Demands – Monitoring Catchment
– PS & FM
• Groundwater Infiltration
– Applied globally by catchments – L/s/ha
– Adjusted to match observed dry weather flow by monitoring catchment
– Allow for seasonal adjustments – Support F-5-5 analysis
• Develop Catchment Based Diurnal Curve
22GM BluePlan Baker Road WWTP PPCP & MSP Update – Meeting #4 February 20th, 2020
Wet Weather Flow
• Wet-Weather Flow (WWF): Wet-weather flow is
comprised of two parts base flow and rainfall
derived inflow and infiltration (RDII)
– Rainfall inflow: Flow that enters the wastewater system
from service connections such as downspouts, storm and
combined sewers, surface runoff, etc.
– Rainfall infiltration: Flow that enters the sanitary sewer
through sewer defects such as cracks or joint failures
(infiltration includes groundwater seepage through
sanitary sewer pipes, manholes and services).
23GM BluePlan Baker Road WWTP PPCP & MSP Update – Meeting #4 February 20th, 2020
Wet weather - Unit Hydrograph (RTK) Method
• Unit hydrograph represented by
three triangles
– Slow Response
• groundwater or slow infiltration
– Medium Response
• infiltration with medium time
response
– Fast Response:
• direct inflow and rapid infiltration
• Apply unique RTK hydrographs
for each monitoring catchment R
T T*K
24GM BluePlan Baker Road WWTP PPCP & MSP Update – Meeting #4 February 20th, 2020
Model Calibration
• Dry Weather Flow Calibration –Pump Station Catchment– Match average/peak dry weather flows
• Adjust diurnal pattern
• Adjust %billing and GWI ratio
– ± 5 -10% accuracy
• Wet Weather Flow Calibration –Pump Station Catchment (Dynamic)– Identify wet weather flow events
• Minimum total depth of 15 mm
• Minimum intensity of 5 mm/hr
– Match peak/total wet weather flows
• Adjust RTK hydrograph parameters
– +15% to -10% accuracy
0
2
4
6
8
10
12
14
16
18
200
50
100
150
200
250
300
350
400
450
500
12:00 AM12:00 PM12:00 AM12:00 PM12:00 AM12:00 PM12:00 AM12:00 PM12:00 AM12:00 PM
Pre
cip
ita
tio
n (
mm
)
Flo
w (
Ls)
Total Flow Model Flows Rain
CE1 CE2
Peak Flow (L/s) Monitor 31.5 29.9
Model 29.7 30.0
Variation
(nominal)
-1.7 0.1
Variation (%) -5% 0%
Total Volume (m3) Monitor 3,727 3,116
Model 3,865 3,213
Variation (%) 4% 3%
25GM BluePlan Baker Road WWTP PPCP & MSP Update – Meeting #4 February 20th, 2020
Calibration Example
26GM BluePlan Baker Road WWTP PPCP & MSP Update – Meeting #4 February 20th, 2020
Wet Weather Calibration Example
27GM BluePlan Baker Road WWTP PPCP & MSP Update – Meeting #4 February 20th, 2020
Model Validation
• Matching Observed Overflows
– At CSO
– WWTP secondary bypassing
• Replication Basement flooding events
– Sewer surcharging in flooding area
– Needs historic records
• Daily total plant influent flows – F-5-5
28GM BluePlan Baker Road WWTP PPCP & MSP Update – Meeting #4 February 20th, 2020
WWTP Flow Validation (example)
Modelled 2016 Observed- WWTP FM WWTP Records
MonthsSum of Volume 2016
[ML]
Average Flow
[L/s]Sum of Volume 2016 [ML] Average Flow [L/s] Sum of Volume 2016 [ML]
Apr 648.700* 395.380* 1,222.000 471.451 1,212.706
May 796.320 297.312 830.855 310.206 828.009
Jun 643.195 248.146 643.413 248.230 638.699
Jul 710.800 265.382 644.944 240.795 640.299
Aug 708.793 264.633 656.441 245.087 652.650
Sep 773.418 298.386 696.181 268.588 691.159
Oct 819.586 305.998 824.168 307.709 818.144
Total 4,452.113 279.976 4,296.002 298.867 4,268.960
29GM BluePlan Baker Road WWTP PPCP & MSP Update – Meeting #4 February 20th, 2020
GAP ANALYSIS
30GM BluePlan Baker Road WWTP PPCP & MSP Update – Meeting #4 February 20th, 2020
Action Items
Category Data Missing Remedial Action Who and When
Network GIS sewer (diameter
greater than 200 mm)
and manhole elements
will be imported into the
model.
Automated spatial scripts and interpolation of
missing data will be used in areas where less than 3
consecutive inverts or diameters are missing
GMBP
Field work/drawings needed for inverts in Grimsby Grimsby
End of March
Facilities WWTP Region to confirm secondary bypassing trigger.
Based on received data, flows exceeding 120 MLD
bypass secondary treatment.
Region
End of March
SPS Our understanding is Region is conducting current
drawdown testing for all stations, including stations
with historic drawdown data, and will have results
prior to model calibration, by April 2020.
Region
End of April
ECA capacities will be used for ideal state. Where
pump curves are not available, the ECA capacity
will be assumed.
Region
End of April
CSOs, CSO Tanks, and
By-Passes
Review and approve CSO configurations, key
element elevations and bypass operational
triggers found in Appendix B.
Region and LAMs
End of March
31GM BluePlan Baker Road WWTP PPCP & MSP Update – Meeting #4 February 20th, 2020
Action Items
Category Data Missing Remedial Action Who and When
Flow and
Loading Data
Flow Monitoring data
inadequate in West
Lincoln and Grimsby
The flow monitoring program recommended in
Tech Memo #2 will be implemented.
Region has approved
FM program. GMBP to
implement in March
Rain Gauge Locations Lincoln to confirm and provide data for Vineland,
Campden, Jordan Station
Lincoln
End of March
Validation Data
Sewage Water Quality Characterization of untreated sewage water
quality required for F-5-5. Region to provide by
April 2020.
Region
End of April
Basement Flooding LAMs to provide basement flooding shapefiles,
tables with address points, or figures with known
basement flooding. Event date with basement
flooding incident is preferable. By end of April
LAMs
End of April
32GM BluePlan Baker Road WWTP PPCP & MSP Update – Meeting #4 February 20th, 2020
NEXT STEPS
33GM BluePlan Baker Road WWTP PPCP & MSP Update – Meeting #4 February 20th, 2020
Next Steps
• Flow Monitoring Program
• Growth Information and
Scenarios
• Policy and Level of Service
• Model Development
Tech MemoTechnical Memorandum #: Growth Scenario
21-Feb
Meeting #4/TCS#3Review of flow Monitoring Program (kick off)Planning Scenario Review
2-Mar
Meeting #5 / TSC #4Policy ReviewLevels of Service
11-May
Tech MemoTechnical Memorandum #5A: Hydraulic Modelling Development
29-May
Meeting #6 / TSC #5Operations workshop #2
Flow analysis summaryModel calibration review
8-Jun