Asbestos in SoilGreg HoltStapleton Redevelopment ProgramCity and County of DenverOctober 3, 2008
-
Stapleton Redevelopment Stapleton Airport closed in 1995Largest Brownfield Urban Project4000 Acres2900 acres Developable1100 acres Open SpaceRedevelopment began in 1998Three programs: EnvironmentalDemolitionAirfield Pavement Removal
-
Development
Land Transfer Environmental StandardsStapleton Numeric Criteria-SNCCity, EPA and State of ColoradoCertification from Property OwnerNFA/NAD for Environmental SitesApproximately 120 NFAs receivedMaster Developer Chosen
-
Asbestos Under Regulation 8125 Building abated prior to demolition50% of the Fuel Distribution System Utilities:WaterElectricCommunication/ Telephone
-
Asbestos in SoilLowery and BuckleyRegulation Change - May 2006Land Transfer RequirementsIndustry ChangesEnvironmental Site AssessmentsSophistication of Asbestos Abatement ContractorsClose out reports / NFA Requests
-
Highline Canal Phase 1 Filing 16HistoryCity Purchased the land for airport expansion mid 1950s Lateral of the Highline canal Canal backfilled with mixed wasteOverall site was backfilled for runway expansion-mid 1960s
-
Filing 16 TimelineEnvironmental Assessments- 6/04 and 1/05Site Characterization- Summer 2005Work Plan Approved by CDPHE - Fall 2005Insurance Acceptance of Claim Fall 2005Project Bid - November 2005Contractor Selected - January 2006NTP March 2006Abatement April 2006- Current
-
Filing 16 2006
-
Filing 16 - 2008
-
Filing 16 TimelineWork Plan Approved by CDPHE - Fall 2005Joint meeting with CDPHE - March 2006Original Work Plan amended 3 timesDevelopment of site wide work planCreation of Clearance Protocol -Fall 2006Suspension of Work Plan- October 2008
-
Filing 16Original Scope of WorkEst. 120,000 yds 70,000 yds Non- Friable ACM50,000 yds Friable ACMArea approximately 40 acresDuration 180 daysActual Est. 730,000 yds480,000 yds Non- Friable ACM250,000 yds Friable ACMArea increased to 105 acresDuration 29 months
-
Filing 16
-
Filing 16
-
Filing 16
-
Filing 16
-
Filing 16
-
Filing 16
-
Filing 16
-
Filing 16Suspension of WorkWhy?City reached Sitewide Cap on costsInsurance reimbursement Slow in paymentsPayments in arrears.
-
Filing 16Suspension of WorkSite StatusCanal Cleared88% of the total site has been cleared15% of the site has been backfilledRemaining area is under a stockpile.
-
Filing 16Suspension of WorkSite SecuritySite StabilizationProtection of Human Health and EnvironmentAir Monitoring
-
Filing 16Insurance ReimbursementOriginal Scope of Work$7,000,000.00
Estimate to Completion$50,000,000.00
-
StapletonAsbestosOne site complete - closure report and NFA submittedTwo sites complete awaiting submittalTwo sites in progressFive sites not started
-
StapletonLessons learnedSite size- Unit pricingType of equipment to be usedWetting methods
Material FriableNon-FriableMixture
Mechanical meansUse of excavators, graders, other heavy equipment
Soil preparationMethods to achieve adequately wet
-
Stapleton