Appendix 7
PROJECT SUMMARY SHEETS
Table of Contents
I. AGRICULTURE AND NATURAL RESOURCES PROJECTS ............................................ 2
Loan 3159-PAK, 3160-PAK (COL): Trimmu and Panjnad Barrages Improvement Project 3
Loan 3239-PAK(COL): FATA Water Resources Development Project 10
Loan 3599-PAK: Jalalpur Irrigation Project 16
Loan 3470-PAK: Pehur High Level Canal Extension 21
Loan 3700-PAK/Grant 0597-PAK: Balochistan Water Resources Development Project 26
TA 9255-PAK: Institutional Transformation of the Punjab Irrigation Department 33
TA 9343-PAK: Third Party Monitoring for FATA Water Resources Development 35
TA 9463-PAK: Revitalizing the Ecosystem of Ravi River Basin 38
TA 9442-PAK: Khyber Pakhtunkhwa Water Resources Development Project 41
TA 9458-PAK: Preparing Greater Thal Canal Irrigation Investment Program 44
TA 9576-PAK: Climate-Resilient Water Resources Management 47
TA 9614-PAK: Preparing Kurram Tangi Integrated Water Resources Development Project 50
II. ENERGY............................................................................................................................52
Loan 3090/3091/3092-PAK (COL): Jamshoro Power Generation Project 53
Loan 8311-PAK(AFD): Power Transmission Enhancement Investment Program Tranche IV 62
Loan 3328-PAK/3329-PAK(COL): Second Power Distribution Enhancement Investment Program 66
Loan 3419-PAK/Loan 3420-PAK (COL): Second Power Transmission Enhancement Investment Program, Tranche I 71
Loan 3476-PAK: Access to Clean Energy Investment Program 76
Loan 3577- PAK: MFF Power Transmission Enhancement Investment Program II T2 80
Loan 3677/G0578 - PAK: MFF Power Transmission Enhancement Investment 84
Program II T3 84
TA 9185-PAK: Hydropower Development Investment Program (Supplementary) 89
TA 9247-PAK: Access to Clean Energy Investment Program 91
TA 9357-PAK: Update on Energy Sector Plan 93
TA 9672-PAK: Developing an Electricity Market 96
TA 9674-PAK: Preparing Lower Palas Hydropower Project 98
TA 9756-PAK: Preparing Sustainable Energy Projects 100
III. TRANSPORT SECTOR PROJECTS ............................................................................... 102
Loan 3134/G-0451-PAK: National Highway Network Development in Balochistan 103
Loan 3300/G0440-PAK: National Motorway M-4 Gojra-Shorkot Section II Project 107
Loan 3395/G0482-PAK/8308-PAK (AIIB): National Motorway M-4 Shorkot-Khanewal Section III Project 113
Loan 3305-PAK: Sindh Provincial Road Improvement Project 118
Loan 3344/3345-PAK(COL): CAREC Regional Improving Border Services Project 124
Loan 3378-PAK: Post-Flood National Highways Rehabilitation Project 130
Loan 3264-PAK: Flood Emergency Reconstruction and Resilience Project 134
Loan 3574-PAK: Central Asia Regional Economic Cooperation Corridor Development Investment Program-Tranche 1 139
Appendix 7
Loan 3601-PAK/Loan 3602-PAK(COL): Khyber Pakhtunkhwa Provincial Roads Improvement Project 142
Loan 3756-PAK: Khyber Pakhtunkhwa Provincial Roads Improvement Project- Additional Financing 146
Ongoing 146
TA 8990-PAK: Enabling Economic Corridors through Sustainable Transport Sector Development 149
TA 8912-PAK: Capacity Building of Institutions Handling Disasters 154
TA 9153-PAK: Central Asia Regional Economic Cooperation Railway Connectivity Investment Program 157
IV. WATER AND OTHER URBAN INFRASTRUCTURE SERVICES .................................... 159
Loan 3543/8336(AFD)-PAK: Peshawar Sustainable Bus Rapid Transit Corridor Project 160
Loan 3799/Grant 0649/Loan 8367-PAK(GFC): Karachi Bus Rapid Transit Project 166
Loan 6008-PAK: Karachi Bus Rapid Transit Project - Project Design Advance (PDA) 168
Loan 3562-PAK: Punjab Intermediate Cities Improvement Investment Project 172
Loan 6015 /6016-PAK: Khyber Pakhtunkhwa Cities Improvement Project - Project Readiness Financing 178
TA 9223-PAK: Provincial Strategy for Inclusive and Sustainable Urban Growth 183
TA 9400-PAK: Khyber Pakhtunkhwa Intermediate Cities Improvement Project 186
TA 9465-PAK: Punjab Intermediate Cities Improvement Investment (Phase 2) 188
V. PUBLIC SECTOR MANAGEMENT ................................................................................. 191
Loan 3049-PAK (COL): Social Protection Development Project 192
Loan 3469-PAK/Grant 0518-PAK: Supporting Public Private Sector Partnership in Sindh Province 197
Loan 3473/3474-PAK: Grant 0519-PAK: National Disaster Risk Management Fund 203
Loan 0639-PAK: National Disaster Risk Management Fund – Additional Financing 212
Loan 3636-PAK/Grant 0562-PAK: Enhancing Public-Private Partnerships in Punjab 215
TA 9239-PAK: Enhancing Public Private Partnership in Pakistan 220
TA 9246-PAK: National Disaster Risk Management Fund 223
TA 9410-PAK: Sindh Secondary Education Improvement Project 225
TA 9392-PAK: Preparing Health Sector Assessment 228
TA 9467-PAK: Strengthening the Federal Public-Private Partnership Framework and Enabling Reforms for Infrastructure Financing Support 231
TA 9469-PAK: Enhancing Public-Private Partnerships in Punjab 235
TA 9488-PAK: Supporting Economic Corridor Development through Strategic Planning Frameworks 237
TA 9580-PAK: Preparing the Trade and Competitiveness Program 240
TA 9588-PAK: Promoting Investments and Economic Growth through International Trade 242
TA 9688-PAK: Economic Management Support 245
TA 9730-PAK: Improving Workforce Readiness in Punjab 247
TA 9676-PAK: Capacity Building for Structural Transformation, Country Programming, and Portfolio Management 249
TA 9788-PAK: Supporting Development of Additional Financing for Social Protection Development Project 252
TA 9789-PAK: Financial Markets Development Program 255
I. AGRICULTURE AND NATURAL RESOURCES PROJECTS Loans
1. Loan 3159-PAK, 3160-PAK(COL): Trimmu and Panjnad Barrages Improvement Project
2. Loan 3239-PAK: FATA Water Resources Development Project
3. Loan 3599-PAK: Jalalpur Irrigation Project
4. Loan 3470-PAK: Pehur High Level Canal Extension
5. Loan 3700-PAK/ 0597-PAK/ 9197-PAK: Balochistan Water Resources Development Project
Technical Assistances (TAs)
1. TA 9255-PAK: Institutional Transformation of the Punjab Irrigation Department
2. TA 9343-PAK: Third Party Monitoring for Federally Administered Tribal Areas Water Resources Development
3. TA 9463-PAK: Revitalizing the Ecosystem of Ravi River Basin
4. TA 9442-PAK: Khyber Pakhtunkhwa Water Resources Development Project
5. TA 9458-PAK: Greater Thal Canal Irrigation Investment Program
6. TA 9576-PAK: Climate-Resilient Water Resources Management
7. TA 9614-PAK: Preparing Kurram Tangi Integrated Water Resources Development Project
3
Agriculture and Natural Resources Sector
Loan 3159-PAK, 3160-PAK (COL): Trimmu and Panjnad Barrages Improvement Project
Loan 3159-PAK, 3160-PAK (COL): Trimmu and Panjnad Barrages Improvement Project A. Loan Basic Data
$ Million Approval
Date Signing
Date Effective
Date Closing Date
Closing Date (Revised)
Elapsed Time % Project
Rating as of
30 Sep 19
22-Sep-14 5-Dec-14 21-Jan-15 31-Mar-21 77
Approved Amount
Net Loan Amount
Financing EA/IA Project Officer
Project Analyst
50.00 50.00 OCR Irrigation Department
Punjab A. Zafar U. Amin On Track
87.72 89.72 COL
B. Loan Financial Progress (As of 30 Sep 2019)
Loan 3159-PAK
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
38.51 11.49 77 0.0 0.0
Disbursements (Cumulative)
Un-disbursed Disbursement Performance %
Disbursements for 2019
Loan Balance EA’s Projections Actual
24.59 25.41 49 6.3 5.73
Loan 3160-PAK (COL)
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
72.66 17.06 81 1.0 0.56
Disbursements (Cumulative)
Un-disbursed Disbursement Performance %
Disbursements for 2019
Loan Balance EA’s Projections Actual
44.07 45.65 49 11.7 12.89
C. Project Description 1. The project will rehabilitate and upgrade the 80–90 years old Trimmu and Panjnad barrages to (i) provide reliable irrigation water to 1.74 million hectares (ha) through six main canals; (ii) primarily benefit 600,000 farming families (about 4.0 million people) in seven districts in Punjab; and (iii) help reduce risk of communities against floods (150,000 people), droughts, and pressure on groundwater abstraction. 2. The expected impact of TPBIP will be the sustained agricultural production and farm income in the barrages command area. The expected project outcome will be the safe and secured Trimmu and Panjnad barrages deliver reliable irrigation water supplies to their canals. 3. The project outputs will be (i) rehabilitated and upgraded Trimmu barrage; (ii) rehabilitated and upgraded Panjnad barrage; and (iii) improved capacity of the communities and PID. The
4
Agriculture and Natural Resources Sector
Loan 3159-PAK, 3160-PAK (COL): Trimmu and Panjnad Barrages Improvement Project
outputs will be achieved through (a) increasing flood capacities of the barrages, (b) improving stability of the existing structures against climate variability, erosion and sedimentation, (c) training of the communities and PID staff in flood risk management and integrated water resources management, and (d) social activities such as Public Park and upgraded basic health unit and girl’s school. Each barrage will be provided with construction supervision and safeguard monitoring teams to monitor implementation of land acquisition and resettlement plan (LARP) and environmental management plans. The details have been provided in the design and monitoring framework (DMF). D. Project Monitoring Framework (Current Status)
Outputs Performance Indicators with Baseline
Status with Key Activities
Rehabilitated and upgraded Trimmu Barrage.
Trimmu barrage water supply capacity (to the associated canals) is maintained at 577.14 m3/s in 2020 (2014 baseline: 577.14 m3/s)
Overall Contract Progress is 91% till 30 Sep 2019.
Water losses through the gates reduced to zero by 2020 (2014 baseline: 15.3 m3/s)
All 51 gates of main barrage are replaced. All 10 gates of Trimmu-Sidhnai Link and 5 gates of Haveli Canal are replaced and operational.
Trimmu barrage flood capacity is increased to 24,777 m3/s by 2020 (2014 baseline: 12,743 m3/s)
Additional bays progress is 95% up till 30 Sep 2019
One women’s basic health unit upgraded by 2020 (2014 baseline ‘none’).
Health Unit has been identified and consultations with Health Department has been conducted. Health Department has provided a list of 26 items which will be purchased by Health Department. MOU has been signed between PMO and Health department on 30 May 2019. PMO will transfer the funds for the purchase of these items as per cost estimate shared by Health Department after approval of revised PC-1. This will be completed before 31 December 2019.
Rehabilitated and upgraded Panjnad barrage.
Punjnad barrage water supply capacity (to the associated canals) is maintained at 408.7 m3/s in 2020 (2014 baseline: 408.7 m3/s)
Contract Awarded in April 2018. Letter of commencement issued in July 2018. Work on going at good pace. Current physical progress is 52% against target of 52.7% uptil 30 Sep 2019
Water losses through the gates are reduced to zero by 2020 (2014 baseline: 14.2 m3/s) Punjnad barrage flood capacity is increased to 24,495 m3/s by 2020 (2014 baseline: 19,822 m3/s)
Contract Awarded in April 2018. Letter of commencement issued in July 2018. Work on going at good pace. Current physical progress is 52% against target of 52.7% uptil 30 Sep 2019
One girl’s primary school is upgraded to a high school by 2020
PMO has decided to construct a new building of middle school in the area instead of upgradation of the old building.
5
Agriculture and Natural Resources Sector
Loan 3159-PAK, 3160-PAK (COL): Trimmu and Panjnad Barrages Improvement Project
Outputs Performance Indicators with Baseline
Status with Key Activities
(2014 baseline: ‘none’) PMO has sent a consent letter to Education department. On request of PMO, Secretary has sent a reminder to Chief Executive Officer, District Education Department to furnish feasibility report of the School as per laid down criteria of Government of the Punjab. Education department has responded that this upgradation is not feasible. PMO will send another letter to Education department to reconsider the request for upgradation.
Improved capacities of the communities and PID.
50 women trained at vocational center by 2020 (2014 baseline: zero).
MOU has been signed between PMO and TEVTA Lahore in June 2018. Vocational Training will be given to 125 women in Trimmu and 125 in Panjnad against the DMF original target of 50. GAP is revised as well. Gender Expert is on board and field visits have been completed. The list of trainees at Trimmu Barrage has been finalized and 50% payment of Rs. 4,504,675 has been made to TEVTA by PMO on February 6, 2019. Remaining 50% of payment will be made upon approval of revised PC-1. The training regarding Flood Risk Management for males and females are completed at Trimmu. Similarly, trainings for Drafting & Pattern making and home-based business for females has been completed at Trimmu. Awareness training program is yet to be conducted and will be completed before 30 December 2019. After this, trainings will be started at Panjand Barrage in January 2020
PID uses revised guidelines for O&M of the barrages by 2020 (2014 baseline: ‘no’)
O&M Manual will be finalized with operational testing and commissioning for Trimmu Barrage expected in June 2020 and for Panjnad in June 2021.
At least 10 PID’s PMO staff and local population use skills in IWRM and FRM approaches by 2020 (2014 baseline: zero)
13 assistant executive engineers trained at IHE Delft. Flood Risk management training is completed for 80 locals (including women) living in the adjoining areas of the barrages prone to floods.
Executing agency’s SPRU and PEA operationalize IWRM and FRM approaches in PID by 2020 (2014 baseline: ‘no’)
IWRM and FRM approaches will be
comprehensively covered under ADB
approved Capacity Development Technical
Assistance 9255-PAK: Institutional
Transformation of the Punjab Irrigation
Department to a Water Resources
Department
6
Agriculture and Natural Resources Sector
Loan 3159-PAK, 3160-PAK (COL): Trimmu and Panjnad Barrages Improvement Project
E. Cumulative Contract Award and Disbursement Performance Loan 3159-PAK
Loan 3160-PAK (COL)
7
Agriculture and Natural Resources Sector
Loan 3159-PAK, 3160-PAK (COL): Trimmu and Panjnad Barrages Improvement Project
F. Contract Award and Disbursement Targets and Achievements in 2019 Loan 3159-PAK
Loan 3160-PAK(COL)
0.0 0.0
0.0 0.0 0.0
0.3
0.7
1.0
-
0.1
0.5 0.5 0.5 0.5 0.5
0.6 0.6
0
0
0
1
1
1
1
2019 Contract Awards L3160($76.8 million through Dec 2018)
EA Projections Actual
3.7
5.4
7.0
8.7 9.0 9.4 9.710.4
11.011.7
1.6
3.8 4.3
7.4 7.4
11.4 11.8 12.9
0.0
2.0
4.0
6.0
8.0
10.0
12.0
14.0
2019 Disbursements L3160($31.2 million through Dec 2018)
EA Projections Actual
8
Agriculture and Natural Resources Sector
Loan 3159-PAK, 3160-PAK (COL): Trimmu and Panjnad Barrages Improvement Project
G. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
Current Status
1. Completion of Trimmu Barrage remaining works
PMO shall provide an assessment of barrage completion, given that contract period has ended EOT decision
- December 2019 all major works (except for closure). - Closure works and full operational testing by April 2020 End August 2019
Current physical progress is 91%. Revised completion date is 30 April 2020.
2. Two decisions are to be made on following additional works: (i) Trimmu Barrage (Irrigation colony works and two bridges) (ii) Panjnad Barrage (Irrigation colony works and upgrading bridge)
As per Loan Review Mission 29 April-6 May, it was agreed that PID/PMO will approve the revise PC-1 from PDWP. Advertise the IFB
PMO, PID, P&D/1st week of September 2019 PMO/1st week of September 2019
PMO has prepared PC-1 and will submit for PDWP through P&D by 15 Oct 2019. Bidding documents are being prepared. PMO will issue IFB upon approval of PC-1
3. Request for utilization of surplus loan and extension in project
ADB will send draft processing documents to PMO
ADB/31 Aug 2019 This was agreed during LRM. Formal request is not required
4. Islam Barrage consultant contract award is on critical path to start Islam Barrage bidding in December 2019 and works by June 2020
Expedite consultant recruitment for Islam barrage as per agreed CRAM and award the contract
PMO/Nov 2019 PMO submitted Submission-3 to ADB on 9 October 2019 which is under review by ADB
5. Remaining payments to affected persons
Complete the payment Issuance of EMA report to validate disbursement of compensation to the land downers
15 Sep 2019/ PMO through LAC 30 Sep 2019/ EMA/PMO
PMO has provided the cost of land to the LAC who, after completing the remaining land acquisition process, is expected to announce the land award in November 2019, following which payment to 4 landowners will be completed.
9
Agriculture and Natural Resources Sector
Loan 3159-PAK, 3160-PAK (COL): Trimmu and Panjnad Barrages Improvement Project
H. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. Revision of PC-1 and
procurement of 2 NCB
packages
Expedite Revision of PC-1 and initiate
procurement process for 2 NCB packages
PMO/31 Oct 2019
2. Finalize Consultant
Recruitment
Contract Signing with Consultant for Islam
Barrage
PMO/10 Nov 2019
3. Remaining payments to
affected person
Complete payment process to the
remaining 4 landowners
PMO/30 Oct 2019
4. Islam Barrage Approval Get ADB’s approval from Board ADB/9 Dec 2019
10
Agriculture and Natural Resources Sector
Loan 3239-PAK(COL): FATA Water Resources Development Project
Loan 3239-PAK(COL): FATA Water Resources Development Project
A. Loan Basic Data $ Million
Approval Date
Signing Date
Effective Date
Closing Date Closing Date
(Revised) Elapsed Time % Project
Rating as of
30 Sep 2019
15-Dec-14
17-Apr-15
7-Aug-2015
30-Sep-20 -
83
Approved Amount
Net Loan Amount
Financing EA/IA Project Officer
Project Analyst
42.97 40.186 COL FATA
Secretariat A. Zafar U. Amin
Actual Problem
B. Loan Financial Progress (As of 30 Sep 2019)
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
12.41 27.77 31 9.0 2.29
Disbursements (Cumulative)
Un-disbursed Disbursement Performance %
EA’s Disbursements for 2019
Loan Balance Projections Actual
9.81 30.37 24 3.0 1.99
C. Project Description 1. The Project will address low farm productivity, high poverty incidence, and pervasive food insecurity in the Federally Administered Tribal Areas (FATA). It will increase agriculture production and household incomes by providing reliable irrigation to non-irrigated rain fed farmlands and non-cultivated lands. The project includes the construction of new irrigation infrastructure, improved on-farm water management through activities such as terracing and land leveling, and watershed management. The Project will also strengthen the project area’s natural resource base by improving selected watersheds, which will enhance the recharging of underground aquifers and reduce the impact of floods. The project will benefit 116,751 households, or about 1.4 million people, in the project area and improve about 9,700 hectares (ha) of land. 2. The project impact will be increased farm incomes in the project areas (Bajaur, Khyber, and Mohmand agencies), thereby reducing poverty and increasing household food security. The project outcome will be improved agricultural productivity of selected watersheds and conservation of their associated natural resource base. 3. Project outputs consist of (i) construction of new irrigation infrastructure, including nine small concrete gravity dams (each with a maximum height of 15 meters), 31 diversion weirs, and 95 kilometers of main and secondary irrigation channels; (ii) improved on-farm water management through construction of 144 kilometers of lined watercourses, terracing and land leveling on a command area of 4,615 ha, and installation of rain and stream gauges to measure water availability; (iii) improved watershed management on 5,050 ha through afforestation of the degraded watersheds and, where appropriate, the construction of check dams; and (iv) efficient project management and evaluation, including establishment of a project management unit and
11
Agriculture and Natural Resources Sector
Loan 3239-PAK(COL): FATA Water Resources Development Project
three project implementation units, timely procurement of goods, works and recruitment of consulting services, and effective financial management. D. Project Monitoring Framework (Current Status)
Outputs Performance
Indicators with Baseline
Status with Key Activities
1. Construction of new irrigation infrastructure.
By 2020 the command area receiving secure irrigation supply increased to 4,291 ha (2014 baseline = 1,294 ha)
The command area receiving secure irrigation supply in 25 selected sub-projects is 1,811 ha (39% of the target given in PC-1 and PAM of 4,615 ha). Of this, 12 sub-projects are awarded for (1,000 ha), while procurement of 11 sub-projects 724 (ha) is completed, however contract signing is yet to be done which got delay due to transfer of Project Directors. Procurement of other packages will be expedited upon approval of PC-1s.
District Target (ha)
Designed (ha)
Detailed Design
Completed and PC-1 approved
(ha)
Detailed Design
Completed but PC-1
not approved
(ha)
Detail Design
and PC-1 in
progress (ha)
Designed Progress
%
Bajaur 2,816 2242 567 606 1069 79.6% Khyber 1,079 435 125 37 273 40.3%
Mohmand 720 477 157 320 0 66% Total 4,615 3152 849 963 1342 68.3%
2. Improved on-
farm water management
Average irrigation requirements reduced to 3.70 mcm/ha from land leveling by 2020
The land development and levelling are finalized in 8 sub-projects measuring 45.60 ha and 62.27 ha respectively. CRVA and improved hydrological studies have been completed. Keeping in view changes (significant) in precipitation provided in CRVA study will be considered by the consultants for climate stations locations identification. Precipitation and temperature changes will be considered for flow gauging stations locations identification while other parameters such as accessibility, availability of bridges, source of seasonal and perennial water and suitability of sites will be considered by the consultants for flow gauging stations installation. The process of identification and selection of sites for gauges stations was to be completed by end of January 2019 but still pending. The PMU will coordinate with DI&H to avoid overlap with the approved sites in their PC-1. Meeting with DG MET Department was held on 8 August 2019.
Water measuring gauges installed and provide real time information
3. Improve Watershed-management
At least 5,050 ha of targeted watersheds have effective vegetation cover (2014 baseline = 0 ha)
Workplan for Watershed management activities during current financial year 2018-19 in Khyber, Mohmand and Bajaur has been submitted by the Forest Department FATA office. District wise watershed targets vs achieved are shown in below table;
District
Target (ha)
Identified (ha)
Progress (ha)
Progress
%
Bajaur 3159 2,540 266 8.42%
Khyber 757 311 115 15.2%
Mohmand 1134 908 225 19.84%
Total 5050 3,759 606 12%
12
Agriculture and Natural Resources Sector
Loan 3239-PAK(COL): FATA Water Resources Development Project
Outputs Performance
Indicators with Baseline
Status with Key Activities
4. Efficient project management and evaluation
Over 90% of contracts are awarded and completed on time and within budget Quarterly progress reports, annual reports, and audit reports are submitted within 4 weeks of due date
Contract of 12 sub-projects are awarded, while for 11 sub-projects procurement has been completed. Contracts have been signed on 25 July 2019. Bidding process of new-subprojects will be initiated after approval of PC-1 from PDWP. The ADB and EA conservatively estimated CAD forecast based on current pace and probable sequence of sub-projects design delivery, award and implementation, and additionally factoring in possible slippages that may encounter due to site selection delays. The procurement plan will be updated in Q3 2019 (with CAD forecast) after expected completion of site selection process and feasibility studies.
Quarterly Progress Reports/annual and audit reports are being submitted in compliance with ADB’s requirement.
E. Cumulative Contract Award and Disbursement Performance
13
Agriculture and Natural Resources Sector
Loan 3239-PAK(COL): FATA Water Resources Development Project
F. Contract Award and Disbursement Targets and Achievements in 2019
G. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
Current Status
1. Dedicated Project Director
The Additional Chief Secretary assured that the current PD (having multiple portfolios) will continue to administer the project and maximize his input to the project, till suitable replacement is found.
PMU/Merged Area Secretariat
Still the current PD is on additional charge, however he has taken multiple positive steps to improve the project performance.
2. Project has significantly been delayed and cannot be completed by the closing date
PSC meeting was held on 23 July 2019 and agreed to review the extension of time and surplus loan utilization by November 2019.
PMU/P&DD KP Secretariat/Nov 2019
ADB will hold a loan review mission in October 2019 to assess the progress including the extension of loan.
3. Site identification
The PSC has (i) given 2 months for identification of remaining sites, and (ii) directed subsequent revision in PC-1 from CDWP
PIU/PMU/Consultants/end Sep 2019 PMU/P&DD/Oct-Nov 2019
Site identification process is still delayed and behind the targets. So far 3634 ha (79%) is identified and 981ha (21%) is yet to be identified. Revised PC-1 is being prepared by PMU and will be submitted for approval by end of October 2019
0.7
1.4
2.1 2.1 2.1 2.1 2.2 2.2 2.32.5
2.83.0
- - - 0.1 0.1 0.1
2.0 2.0 2.0
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
2019 Disbursements L3239($7.8 million through Dec 2018)
EA Projection Actual
0.0 0.0
1.8
3.7
5.5 5.7 5.8 6.0
7.0
8.0
9.0
-- - -
0.7
2.3 2.3
0
1
2
3
4
5
6
7
8
9
10
2019 Contract Awards L3239($11.7 million through Dec 2018)
EA Projection Actual
14
Agriculture and Natural Resources Sector
Loan 3239-PAK(COL): FATA Water Resources Development Project
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
Current Status
4. Slow Progress on ongoing contracts
1. Improve IPCs process 2. take contractual action on poor performing sub-projects (and in case of termination, send proposal to ADB prior to termination)
PMU/PIU/continuous Progress on awarded progress is very slow. PMU to take contractual actions against non-performing contractors. LRM in October will review.
5. Pending contract signing
Sign pending contracts for 11 sub-projects
PMU/by 31 July 2019 Contracts for 6 packages have been signed. Contract signing for 1 package is on hold due to conflict of scope with other identified sub-project. PMU will award the contract after due diligence regarding scope of work
6. PC-1 approvals and expedite procurement
Get PC-1 approvals for all-subprojects which are ready and initiate procurement process
PMU/Merged Area Secretariat/PDWP by mid-Sept 2019
5 subprojects have been approved from PDWP for which administrative approval is awaited to initiate the procurement process.
H. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. Loan extension and
surplus loan
ADB will hold a loan review mission in
October 2019 and discuss the loan
extension and surplus loan cancellation
and or utilization.
The matter will be discussed on the
agenda of the next PSC.
ADB-PMU/18-25
Oct 2019
PSC/Nov 2019
2. Remaining site
identification 21%
Site identification to complete not later
than 31 Dec. The scope that gets finalized
by 31 Dec will be prepared. Project will be
finalized based on this.
PMU/ 31 Dec 2019
3. Revision in PC-1 Receive revision in PC-1 from CDWP Nov 2019/PMO, KP
P&D
4. Initiate Procurement of
approved 5 sub-projects
PMU to initiate and expedite procurement
process of recently approved 5
subprojects from PDWP after taking
PMU/20 Dec 2019
15
Agriculture and Natural Resources Sector
Loan 3239-PAK(COL): FATA Water Resources Development Project
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
required administrative approval and
award contracts in Dec 2019
5. Expedite procurement of 2
on-going Dam Projects
PMU to complete procurement of 2 Dams
projects by mid Nov 2019
PMU/15 Nov 2019
6. Extremely slow progress
on ongoing contracts
PMU will terminate contracts if
fundamental breach of contracts is
established.
PMU/15 Nov 2019
16
Agriculture and Natural Resources Sector
Loan 3599-PAK: Jalalpur Irrigation Project
Loan 3599-PAK: Jalalpur Irrigation Project
A. Loan Basic Data $ Million
Approval Date
Signing Date
Effective Date
Closing Date Closing Date
(Revised) Elapsed Time %
Project Rating as of
30 Sep 2019
24-Nov-17 13- Apr-18 31 May 18 30-Sep-24 28 Approved Amount
Net Loan Amount
Financing EA/IA Project Officer
Project Analyst
274.63 274.63 OCR Punjab
Irrigation Deptt.
A. Shimasaki
E. Alano Actual Problem
B. Loan Financial Progress (As of 30 Sep 2019)
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
9.64 264.99 4 96.0 4.73
Disbursements (Cumulative)
Un-disbursed Disbursement Performance %
Disbursements for 2019
Loan Balance EA’s Projections Actual
4.13 270.50 2 10.23 1.58
C. Project Description 1. The Jalalpur Irrigation Project is located along right bank of River Jhelum in Punjab, Pakistan. It will create new non-perennial irrigation services for enhanced agricultural production on 68,263 ha in Pind Daden Khan and Khushab districts. The project will increase kharif crop intensity by 90%, crop yield by 141%-12% depending on the crop and reduce land degradation. The primary beneficiaries are 384,000 people. The project has the following three outputs: (i) construct an intake structure, a 117-km main canal, 23 distributaries canals, 10 minor canals, 72 cross-drainage structures, 18 flood-carrier channels and 253 associated structures, (ii) construct 485 watercourses, form and train 485 water user associations (WUAs), provide precision land leveling, high-efficiency irrigation systems (HEIS), and 20 water storage ponds with solar pumping stations, train the farmers on climate-smart irrigation practices, and (iii) establish 664 agricultural demonstration farms, provide 6,000 farm households with advisory services and training on climate-smart irrigated agriculture practices and more profitable farm management, provide farmers with private agriculture support services for marketing and supply chain management of high-value agriculture, and help farmers develop links between growers and the market. 2. The project impact is “growth of agriculture sector enhanced, and food security ensured”. The project outcome is “agricultural production in the project area increased”.
17
Agriculture and Natural Resources Sector
Loan 3599-PAK: Jalalpur Irrigation Project
D. Project Monitoring Framework (Current Status)
Outputs Performance Indicators with Baseline Status with Key Activities
1. Jalalpur irrigation distribution system established
By 2022:
1a. An intake structure with a design discharge capacity of 38.2 m3/s, 117 km-long main canal, 23 distributaries, 10 minor canals, 72 cross-drainage structures, 18 flood- carrier channels, and more than 250 associated structures for kharif season irrigation constructed (2017 baseline: 0)
1b. Guideline and sustainable O&M plan for the Jalalpur irrigation system approved by the Punjab Irrigation Department (PID) (2017 baseline: NA)
1c. Flood disaster risk management plan approved by the PID (2017 baseline: NA)
1d. M&E system using satellite remote sensing technology to assess irrigation efficiency, crop growing, and the abiana certified as fully functional by the PID (2017 baseline: NA)
Activities will be started after the mobilization of the project implementation consultant team.
2. Water-use capacity improved in project areas
By 2023:
2a. 485 watercourses covering all project areas for kharif season irrigation constructed (2017 baseline: 0)
2b. 485 WUAs formed and their capacities improved for sustainable O&M of watercourses and efficient water use during kharif season (2017 baseline: 0)
2c. 12,140 ha of the project area flattened (2017 baseline: 0)
2d. HEISs covering 809 ha of the project area installed (2017 baseline: 0)
2e. More than 6,000 households improved water-use skills, at least 30% of whom are women (2017 baseline: 0)
Activities will be started after the mobilization of the project implementation consultant team.
3. Farm management capacity improved in project areas
By 2023:
3a. More than 6,000 households improved their capacities on irrigated agriculture practices, at least 30% of whom are women (2017 baseline: 0)
3b. More than 6,000 households improved their capacities on profitable farming systems, at least 30% of whom are women (2017 baseline: 0)
3c. More than 6,000 farmers accessed private agriculture support services in the project area (2017 baseline: 0)
Activities will be started after the mobilization of the project implementation consultant team.
18
Agriculture and Natural Resources Sector
Loan 3599-PAK: Jalalpur Irrigation Project
E. Cumulative Contract Award and Disbursement Performance
F. Contract Award and Disbursement Targets and Achievements in 2019
0.0 0.0 0.0 0.0 0.0 0.0
1.2
2.4
3.7
5.9
8.0
10.2
- 0.4 0.4 0.5 0.5
0.8
1.3 1.6 1.6
0.0
2.0
4.0
6.0
8.0
10.0
12.0
2019 Disbursement: L3599($2.5 million through Dec 2018)
EA Projection Actual
0.0 0.0 2.1 4.2 6.3
18.5
30.8
43.0
60.7
78.3
96.0
- - - -5.0 4.7 4.6 4.7 4.7
0
20
40
60
80
100
120
2019 Contract Awards : L3599($4.8 million through Dec 2018)
EA Projection Actual
19
Agriculture and Natural Resources Sector
Loan 3599-PAK: Jalalpur Irrigation Project
G. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
Current Status
1. LARP
Implementation
(Impact $96
million)
1. Ensure timely fund transfer to revenue department 2. Implement 5 segments of LARP as per agreed timelines and announce Section 11 (award of compensation) 3. LARP Progress review at the level of Secretary PID
PID / Aug 2019 PMO / Segment 1 (Aug 2019) Segment 2 (Oct 2019) Segment 3 (Nov 2019) Segment 4 (Sep 2019) Segment 5 (Dec 2019) PID / Fortnightly
Total Fund required amounting to PKR 2,514.4 million by Land Acquisition Collector (LAC) Jehlum and PD Khan have been provided. Out of PKR 529.6 million, 142.2 million have been provided to Land Acquisition Collector (LAC) Khoshab. PKR 267 million will be provided during the week. A demand of PKR 100 million has been raised which is expected to release soon. Remaining funding will be arranged in due course of time. PMO confirms that the Secretary Irrigation does conduct regular meetings with the DC to follow-up on the progress in the LAA procedures.
2. Procurement
P1: Approval of TBER P2: Send TBER to ADB
ADB / 12-16 Aug 2019 PMO / 9 Aug 2019
P1: Clarifications on PBER were requested by ADB on 9 Oct 2019. P2: Clarifications on 2nd TBER were requested by ADB on 10 Oct 2019. P3: Deadline for opening of the technical bids has been extended to 22 October 2019.
20
Agriculture and Natural Resources Sector
Loan 3599-PAK: Jalalpur Irrigation Project
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
Current Status
3. Staffing
Recruit Key Staff
Third week of Aug 2019 / PMO, PID and P&DD
No new appointments yet. PMO started hiring process.
4. Over delays in
Irrigation
Component has
reduced the
Command Area
Development
implementation
period
Draft implementation plan will be submitted to PSC and ADB and will be included in the agenda of the next PSC meeting.
End of August / PIO, PMO
The Plan has not been shared with ADB
H. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. Delay in Procurement of
Civil Works
Continue cooperation between PMO and
ADB team on ICB packages:
• P1: Submit reply for PBER
• P2: Submit reply for TBER
P3: Submission of first TBER.
PMO to expedite procurement of civil
works packages and award the contracts
for Lot 1 and Lot 2 in 2019
PMO/PID/ 31 Dec
2019
2. Staffing • Recruit Key Staff for PMO
• Recruit Key Staff for PIO
PID
PAD
3. Expedite LARP
implementation in five
segments of LARP
PMO to continuous follow up with DC
office to expedite LARP implementation
activities. In TPR, PMO and PID will
confirm the
(i) Section 11 of Segment 2, 3, 4 and 5
(ii) Commencement of Payments in
Segment 1,2,3,4,5
To be discussed in
TPR
4. Advance Accounts PAD to established separate advance
account
PAD/15 Nov 2019
5. Engage Consultants • Engage Project Support Consultants
Process 1st PIC contract variation
PID
6. Disbursement Explore options to increase disbursement • Increase mobilization advance
PID/ADB
21
Agriculture and Natural Resources Sector
Loan 3470-PAK: Pehur High Level Canal Extension
Loan 3470-PAK: Pehur High Level Canal Extension
A. Loan Basic Data $ Million
Approval Date
Signing Date
Effective Date
Closing Date Closing Date
(Revised) Elapsed Time %
Project Rating as of
30 Sep 2019
24-Nov-16 09-Jun-17 24-Aug-17 30-Sep-23 - 43 Approved Amount
Net Loan Amount
Financing EA/IA Project Officer
Project Analyst
86.41 86.41 OCR KPK Irrigation
Deptt. A. Zafar U. Amin On Track
B. Loan Financial Progress (As of 30 Sep 2019)
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
61.41 24.99 71 42.0 42.03
Disbursements (Cumulative)
Un-disbursed Loan Balance
Disbursement Performance %
EA’s Disbursements for 2019
Projections Actual
17.21 69.19 20 15.0 3.78
C. Project Description 1. The proposed project will develop a new irrigated area of over 8,727 hectares (ha) in Swabi and Nowshehra districts located in the Khyber Pakhtunkhwa Province (KPP). Water for agriculture in the project area currently depends on rainfall. As a result, cropping intensity and crop yields are low. The project will finance the extension of Pehur High Level Canal (PHLC) irrigation system, which will become a part of the Indus Basin irrigation system. This will increase agriculture production by increasing availability of water, improving water-use efficiency and farm management capacity in the project area. The population of the project area is about 75,000. 2. The project impacts, which are aligned with KPP Comprehensive Development Strategy, will be the following: (i) increased irrigated area, and (ii) ensured food security for 2010–2020. The outcome will be increased agricultural production in the project areas. 3. Output 1 of the project is “available agricultural water in project areas increased”. This includes the following components: (i) construction of the irrigation system in the Janda Boka–Malikabad area, (ii) construction of the irrigation system in the Indus Ambar area, and (iii) developments of efficient monitoring and evaluation system and sustainable PHLCE O&M plan and its guidelines. Output 2 of the project is “water-use skill and farm management capacity improved in project areas”. This output will further improve agricultural benefits resulting from output 1 and (i) construct watercourses, (ii) form and build capacity of water users’ associations, and (iii) train farmers for more profitable farming systems and efficient water use skills through demonstration activities and farmer field schools.
22
Agriculture and Natural Resources Sector
Loan 3470-PAK: Pehur High Level Canal Extension
D. Project Monitoring Framework (Current Status)
Outputs Performance Indicators with Baseline Status with Key Activities By December 2022, 1. Available agricultural water in project areas increased
1a. Water availability in IAA (7,411 ha) increased to 119 million m3 per year (2014 baseline: 51 million m3)b
Contracts for all Lots have been awarded. LARP for all Lots are approved. LARP implementation process has started. Commencement letters to contractors will be issued once LARP is implemented and verified by ERM followed by possession of land. M&E system specimen shared with PMO for preparing for the Project Consultants will prepare O&M Plan.
1b. Water availability in the JBMA (1,316 ha) increased to 20 million m3 per year (2014 baseline: 9 million m3)b 1c. The M&E system using satellite remote sensing technology to assess irrigation efficiency, crop growing, water productivity, and abiana fully operational (2014 baseline: 0) 1d. A guideline and sustainable plan of PHLCE O&M fully operational (2014 baseline: 0)
2. Water-use skill and farm management capacity improved in project areas
By December 2022, 2a. 100% of project areas fully irrigated (2014 baseline: 0%) 2b. 100% of on-farm irrigation canals fully operated and maintained by WUAs (2014 baseline: 0%) 2c. Over 4,000 households (about 50% of total estimated number of beneficial households) trained in improved water use skills (2014: 0) 2d. Over 2,500 households (about 30% of total estimated number of beneficial households) trained in profitable farming system with at least 10% women beneficiaries (2014: 0)
Not yet due Not yet due As it is a downstream activity KPAD will mobilize full staff by end of Q4 of 2019 As it is a downstream activity KPAD will mobilize full staff by end of Q4 of 2019
23
Agriculture and Natural Resources Sector
Loan 3470-PAK: Pehur High Level Canal Extension
E. Cumulative Contract Award and Disbursement Performance
F. Contract Award and Disbursement Targets and Achievements in 2019
4.9 5.5 5.5
19.7
61.7
0.4 0.8 0.9
13.417.2
-
10
20
30
40
50
60
70
80
90
100
Dec-17 Jun-20 Jun-23
Loan 3470: Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Loan Amount: US$ 86.41 M
Clo
sin
g D
ate
: 30-J
un-2
023
28.0
42.0 42.0 42.0 42.0 42.0 42.0 42.0 42.0 42.0 42.0
- -
12.7
41.8 41.0 41.8 42.0
0
5
10
15
20
25
30
35
40
45
2019 Contract Awards L3470($19.7 million through Dec 2018)
EA Projection Actual
1.7
3.3
5.0 5.0 5.0 5.0
6.7
8.3
10.0
11.7
13.3
15.0
0.3
3.9 3.8 3.8 3.8
0.0
2.0
4.0
6.0
8.0
10.0
12.0
14.0
16.0
2019 Disbursements L3470($13.4 million through Dec 2018)
EA Projection Actual
24
Agriculture and Natural Resources Sector
Loan 3470-PAK: Pehur High Level Canal Extension
G. Status of the Action Plan discussed in 2nd TPR Sr. No
Issue Action to be Taken Due Date
/ By Whom Current Status
1. Timely implementation of LARP
Expedite LARP implementation, followed by verification by ERM. Commencement of work is dependent on LARP implementation
Award LAA Section 11 Lot 3 / End of Aug 2019 DC and PMO
Section 11 for Lot 1 and Lot 2 have been notified. There was a gap of nearly two months between the Lot 1 and Lot 2 Section 11 announcement and start of payments. Lot-3 Section 11 will be notified in Nov 2019.
2. PMO Staffing
Complete remaining staff recruitment
Interviews in Aug 2019/PMO, KPID and P&DD Mobilization in Sep 2019/ KPID, PMO and P&DD
Recruitment process to fill vacant positions is ongoing. Director Social, M& E specialist have been recruited. DD safeguards position will be re-advertised.
3. PIO Staffing and establishment of PIO office
Completed PIO staff recruitment, procurement of office furniture and vehicles etc
End of Aug-Sep 2019/KPAD, PIO
PIO is still short of staff. This will be discussed with PIO and Sec Agriculture during LRM in Oct 2019
4. Expedite Progress
While LARP is under implementation, take advance contract management actions (joint surveys, shop drawings, camp, pipe fabrication yards, procurement of materials, approval of work program) PMO, contractors and consultants will submit draft program of works by end of August 2019 Meet yearly disbursements targets of $ 15 million for calendar year 2019 (so far $3.9 million achieved)
July-Sep 2019/ PMO, consultants, contractors End of August 2019 / PMO, contractors and consultants 10 Dec 2019 / PMO
Joint surveys have been started for all three lots. Contractor site camp locations have been identified. Consultant to issue shop drawings. Contractors have not submitted the draft workplan yet. This will be discussed during LRM in Oct 2019. Currently approx. $4 Million is achieved and $11 million yet to be done to achieve the yearly targets. PMO to take necessary steps and actions to meet the disbursement target of 2019.
25
Agriculture and Natural Resources Sector
Loan 3470-PAK: Pehur High Level Canal Extension
H. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. LARP Implementation
slowed down in Aug-Sep.
There was a gap of nearly
two months since early
August 2019 in Lot 1 and
Lot 2 Section 11
announcement and start of
payments. Lot-3 Section
11 will be notified in Nov
2019.
P&DD is requested to convene meeting
with relevant SMBR, commissioner, DC
and Irrigation Department to firm-up the
timelines.
PMO to prepare mouza wise LARP
payments and commencement of works.
P&DD/30 Oct 2019
PMO will provided
this to ADB mission
from 14-17 Oct/2019
2. Commencement of Civil
Works
PMO to issue commencement notice to
contractors and follow moza-wise LARP
and works synchronization (as land
becomes clear, payments are made and
verified by ERM and in case of pending
payments, PMO will submit a detailed
report to ADB with the list of affected
person with reasons justifying the delay in
payment process. This will be verified by
ERM to enable ADB to issue no objection
to proceed with execution of works in
those areas)
PMO
Lot 1/15 Nov 2019
Lot 2/30 Nov 2019
Lot 3/15 Dec 2019
3. Establishment of PIO and
staffing
KPAD and PIO to expedite the
establishment of its office and hire staff as
per PC-1. PIO to initiate the activities of
Output-2 in January 2020
PIO/KPAD/ 30 Dec
2019
4 Meet disbursements target Achieve additional $11 million in 2019 PMO by cut-off date
of 10 Dec 2019
5 Avoid time overrun PMO/PIO will prepare plans for fast-
tracking project
PMO will provided
this to ADB mission
from 14-17 Oct/2019
26
Agriculture and Natural Resources Sector
Loan 3700/G0597/G9197-PAK: Balochistan Water Resources Development Project
Loan 3700-PAK/Grant 0597-PAK: Balochistan Water Resources Development Project Grant 9197-PAK: Piloting High-Value Agriculture in Balochistan A. Loan Basic Data
$ Million
Approval Date
Signing Date
Effective Date
Closing Date Closing
Date (Revised)
Elapsed Time % Project
Rating as of
30 Sep 2019
31-Aug-18
5-Jan-19 7-Mar-19
L3700 30-Jun-24 G0597 31-Mar-24 9197 31-Mar-24
- 19 19 19
Approved Amount
Net Loan Amount
Financing EA/IA Project Officer
Project Analyst
100.0 - COL
Irrigation Dept, GoB Y. Zhou C.
Cabrales-Chiong
On Track 2.0 - HLTF
3.0 - JFPR
B. Loan Financial Progress (As of 30 Sep 2019) Loan 3700
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
4.76 95.24 5 5.0 4.76
Disbursements (Cumulative)
Un-disbursed Loan Balance
Disbursement Performance %
EA’s Disbursements for 2019
Projections Actual
0 100.0 0 2.3 0.0
Grant 0597
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
0 2.0 0 0 0
Disbursements (Cumulative)
Un-disbursed Loan Balance
Disbursement Performance %
EA’s Disbursements for 2019
Projections Actual
0 2.0 0 0 0
9197 (JFPR)
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
0 3.0 0 0 0
Disbursements (Cumulative)
Un-disbursed Loan Balance
Disbursement Performance %
EA’s Disbursements for 2019
Projections Actual
0 3.0 0 0 0
27
Agriculture and Natural Resources Sector
Loan 3700/G0597/G9197-PAK: Balochistan Water Resources Development Project
C. Project Description 1. The proposed Balochistan Water Resources Development Project is located in the Zhob and Mula river basins in the Balochistan. The project impact will be the increased farm income in the project area. The project outcome will be the increased agricultural production. The project outputs will be (i) irrigation infrastructure and watershed protection constructed and/ rehabilitated; (ii) command area expanded and improved; and (iii) institutional capacity strengthened. 2. The project will cost about $125.5 million and ADB will provide finance of $100 million and the government of Balochistan will provide the balance. The project will adopt an integrated water resources management approach for the irrigation development activities. The project will support implementation of the IWRM policy, and in turn supports and strengthens several principal elements of ADBs water policy, including: (i) improving the efficiency of water use and delivery; (ii) fostering water conservation and sustainability of infrastructure; and (iii) improving governance through beneficiary participation and capacity building. In addition to irrigation infrastructure, the project will help establish water resources information system for improved water resources management and monitoring, address watershed degradation by improving vegetative cover and undertaking physical interventions to reduce erosion in critical areas through integrated and participatory approaches. It will further seek to strengthen the capacity of and coordination between the agencies in charge of watershed management through the project implementation process. Improved on-farm water management is critical to raising cropping intensities and optimizing productivity increases from the investments in irrigation infrastructure. In addition, the project will support high value agriculture which is essential to improve farmers income in Balochistan. These aspects also form an integral part of the project design and will help to achieve benefits that would not be possible through investments in water resources infrastructure alone. 3. To address the GoB’s limited capacity and experience in data collecting and processing, the project will work in partnership with Pakistan Council for Water Resources to establish and maintain a water resources information system to strengthen GoB’s capacity to collect, transmit, process, and share hydrometeorology data for improved water management. The project design also explicitly recognizes the institutional, social, and cultural barriers to women’s empowerment and the impact this may have on access to and participation in water resources development activities. Female community organizers at the project’s implementing offices will collect data and information on the roles and responsibilities of women and assess their specific requirements. The possible effects of scheme development for women will be assessed and practical opportunities to develop and implement gender-specific interventions identified, particularly provision of efficient on-farm water and agronomic management and high value agricultural production. D. Project Monitoring Framework (Current Status)
Outputs Performance Indicators with Baseline Status with Key Activities
1.Irrigation Infrastructure and watershed protection constructed and/or rehabilitated
1a. About 15 irrigation schemes constructed and/or rehabilitated, of which 30% have facilities for women’s increased access to water for domestic use 1b. 276 km long irrigation and drainage canals constructed and/or rehabilitated 1c. About 4,145 ha of watersheds protected from water erosion
Detailed design for 1st set of subprojects will be completed by mid-February 2019 and related works contract will be
28
Agriculture and Natural Resources Sector
Loan 3700/G0597/G9197-PAK: Balochistan Water Resources Development Project
1d. Groundwater table monitoring in the project area conducted and reported
awarded by April 2020.
2. Command area established and/or improved
2a. About 11,603 ha of land improved and served by constructed or rehabilitated irrigation and khushkaba (rainwater harvesting) infrastructure 2b. About 5,989 ha of land developed under new irrigation infrastructure 2c. About 130 ha of high-value agriculture land pilot tested with drip irrigation system through the JFPR grant 2d. At least 22 women-led small-scale agribusinesses launched
Detailed design for 1st set of subprojects will be completed by mid-February 2019 and related works contract will be awarded by April 2020
3.Institutional capacity strengthened
3a. WRIS established and operational through technical assistance 3b. High-level technology hydrometeorological equipment used in the field validation of satellite-based WRIS data for monitoring of water resources in three river basins under the High-Level Technology Fund grant 3c. At least 40 trained staff from the Irrigation Department, the ACD, and the PMO and/or the PIO, of whom at least 30% are women, increased their project management and implementation skills
. The consulting services for WRIS is being recruited. The technical specifications for the equipment is being prepared. Training of PMO and PIO staff will commence in Q4, 2019
E. Cumulative Contract Award and Disbursement Performance L3700-PAK
0.0 4.8
0.00.0 -
20
40
60
80
100
120
Jun-19 Dec-21 Dec-24
L 3700: Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Loan Amount: US$ 100.00 M
Clo
sin
g D
ate
: 30-J
un
-2024
29
Agriculture and Natural Resources Sector
Loan 3700/G0597/G9197-PAK: Balochistan Water Resources Development Project
G0597-PAK
G9197-PAK
0.0 0.0
0.00.0 -
1
1
2
2
3
Jun-19 Dec-21 Jun-24
G 0597: Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Loan Amount: US$ 2.00 M
Clo
sin
g
Da
te:
31
-Ma
r-
0.0 0.0
0.00.0 -
1
1
2
2
3
3
4
Jun-19 Dec-21 Jun-24
G 9197: Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Loan Amount: US$ 3.00 M
Clo
sin
g D
ate
: 3
1-M
ar-
20
24
30
Agriculture and Natural Resources Sector
Loan 3700/G0597/G9197-PAK: Balochistan Water Resources Development Project
F. Contract Award and Disbursement Targets and Achievements in 2019 L3700-PAK
G0597-PAK
G9197-PAK
0.0 0.0 0.0 0.0 0.0
1.7
3.3
5.0 5.0 5.0 5.0
- - - - - -
4.7 4.7 4.8
0
1
2
3
4
5
6
2019 Contract Awards L 3700($0.0 million through Dec 2018)
Projected Actual
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.8
1.5
2.3
- - - - -
-
- - -0.0
0.5
1.0
1.5
2.0
2.5
2019 Disbursement L3700($0.0 million through Dec 2018)
Projected Actual
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
- - - - -
-
- - -0.0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1.0
2019 Disbursement G0597($0.0 million through Dec 2018)
Projected Actual
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
- - - - - - - - -
0
0
0
0
0
1
1
1
1
1
1
2019 Contract Awards G0597($0.0 million through Dec 2018)
Projected Actual
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
- - - - -
-
- - -0.0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1.0
2019 Disbursements G9197($0.0 million through Dec 2018)
EA Projection Actual
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
- - - - - - - - -
0
0
0
0
0
1
1
1
1
1
1
2019 Contract Awards G9197($0.0 million through Dec 2018)
EA Projection Actual
31
Agriculture and Natural Resources Sector
Loan 3700/G0597/G9197-PAK: Balochistan Water Resources Development Project
G. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
Current Status
1. Expedite
progress
since
consultant’s
contract
has been
signed and
have
mobilized
The Project Director
will send fortnightly
progress to ADB,
Secretary Irrigation
and PIO
Arrange a joint
stakeholders meeting
to expedite progress
and bring clarity on
next actions
Release funds for FY
Q1 2019
Process withdrawal
application
Open advance
account for PIO
PD, PMO/ Fortnightly
September 2019
Secretary BID / Aug 2019
PD, PMO / Aug 2019
PD, PIO / Sep 2019
Consultant contract CS-01
signed. QPR is being
prepared by PD and
Consultant firm for
submission by 31 Oct 2019
The technical working
group meeting comprising
Secretary BID, DG OFWM,
Chief Forest Conservator,
PD has been established
and conducted its
meetings
Advance account funds will
be released within Oct
2019
1st WA for advance
account has been
endorsed on 11 Oct 2019
and is being processed by
PRM-DU
Yet to be open
H. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. Vacancies of PMO and
PIO
Recruit remaining PMO and PIO positions
PMO and PIO, by
15 Nov 2019
2. Advance account for PIO
has not opened
Open advance account for PIO
ACD/PIO by 15 Nov
2019
3. Farmers’ and service
providers’ participation
criteria and their selection
Conduct field consultation and finalize
selection criteria and implementation
agreements for participation of farmers
PIO with assistance
of the consultants,
by 31 Oct 2019
32
Agriculture and Natural Resources Sector
Loan 3700/G0597/G9197-PAK: Balochistan Water Resources Development Project
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
and service providers in the high-value
agriculture component
4. Auditing for FY2018-2019 Submit request for deferring submission of
audited project financial statements due to
no disbursement during FY2018-2019
PMO, by 30 Nov
2019
33
Agriculture and Natural Resources Sector
TA 9255-PAK: Institutional Transformation of the Punjab Irrigation Department
TA 9255-PAK: Institutional Transformation of the Punjab Irrigation Department
A. TA Basic Data US$ (Thousand)
Approval Date
Signing Date
Closing Date
Closing Date
(Revised)
Time Elapse
%
Contract Award
(Cumulative)
Disbursements
(Cumulative)
5-Dec-16 27-Dec-16 31-Dec-19 - 92 JFPR: 11.77
TASF: 40.36 11.77 20.52
Approved Amount
Net Amount Financing Project Officer
Project Analyst
Counterpart Agencies
2,000.00 2,000.00 JFPR A. Tayyab
E. Abangan
Punjab Irrigation Dept 500.00 500.00 TASF
B. TA Description 1. The TA will contribute to establishing sustainable management of water resources in Punjab, through enhancing capacity of the Punjab Irrigation Department for its smooth transformation from a traditional irrigation water deliverer to a water resources department that comprehensively manage water resources. 2. Through the TA, the PID is expected to acquire improved capacity in (i) planning and management of water resources, including different water uses, water-related disasters, environmental flow in rivers, and groundwater; and (ii) developmental research and operational management. The TA will bring innovation to Punjab, such as development of Punjab’s Water Vision 2030 and water resources information system, basin-based water resources management approaches including water-related disaster risk management, and information and communication technology in resource management. C. Project Monitoring Framework (Current Status)
Outputs Performance Indicators Status with Key Activities
New WRD is functional
Organizational structure and business rules, licensing and cost recovery mechanisms and agreed transformation plan for the new WRD are available by Q1, 2018 GoPb endorsed new WRD starting Q3, 2018 Budget allocated to new WRD for FYb2020 by Q2, 2019 Newly recruited staff comprising up to 30% women by Q2, 2019
The TA activities are expected to be fully active after mobilization of a TA consultant team by December 2019
Capacity of WRD enhanced
Punjab’s Water Vision and Action Plan 2030 launched by Q4, 2018 WRIS and its operation manual available by Q3, 2018 At least 50 staff including women from WRD trained on governance, IWRM, WRDRM, ICTs, RS and GIS etc. by Q3, 2018
Same as above.
34
Agriculture and Natural Resources Sector
TA 9255-PAK: Institutional Transformation of the Punjab Irrigation Department
D. Cumulative Contract Award and Disbursement Performance
E. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
Current Status
No Issues
F. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
- - 1 1
199 199 199 238
521 1
11 1 32 32
-
250
500
750
1,000
1,250
1,500
1,750
2,000
2,250
2,500
Dec-16 Jun-17 Dec-17 Jun-18 Dec-18 Jun-19 Dec-19
(Th -
$)
TA 9255: Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Clo
sin
g: 3
1 D
ec 2
01
9
Net TA amount: $ 2,500 (Th)
35
Agriculture and Natural Resources Sector
TA 9343-PAK: Third Party Monitoring for Federally Administered Tribal Areas Water Resources Development
TA 9343-PAK: Third Party Monitoring for FATA Water Resources Development
A. TA Basic Data US$ (Thousand)
Approval Date
Signing Date
Closing Date
Closing Date
(Revised)
Time Elapse
%
Contract Award
(Cumulative)
Disbursements (Cumulative)
11-Jul-17 - 30-Sep-20 69 217.05 122.81 Approved Amount
Net Amount
Financing Project Officer
Project Analyst
Counterpart Agencies
225.00 225.00 TASF A. Zafar U. Amin FATA Secretariat
B. TA Description The proposed TA will provide resources for ADB administered third party monitoring to independently validate as well as complement Fata Water Resources Development Project ongoing support under loan financing. The TA is aligned with ADBs Country Partnership Strategy 2015-2019 for Pakistan, included in the ADB’s Country Operations Business Plan 2017-2019 and discussed with the EA. C. Project Monitoring Framework (Current Status)
Outputs Performance Indicators Status with Key Activities 1. FWRDP environmental and social safeguards compliance improved and externally validated
By 2020: At least 6 external biannual monitoring accomplished, and findings reported to ADB and EA and at least 25% sub-projects public consultation attended by third party monitoring agent.
Consultant recruited in October 2017. Inception report submitted and approved. Bi-annual reports are being submitted.
2. FWRDP construction cost, time and quality control improved and externally validated
All 40 sub-projects independently inspected during construction, for at least once in each quarter
Water Resources Specialist hired. Monitoring Specialist hired. All awarded projects are being inspected quarterly.
3. FWRDP technical and economic viability, and sustainability improved and externally validated
All 40 sub-projects preliminary survey, feasibility studies and detail design externally reviewed
Consultant recruited in October 2017. Inception report submitted. Technical reviews are being conducted as sites are getting identified and feasibility reports are being prepared.
36
Agriculture and Natural Resources Sector
TA 9343-PAK: Third Party Monitoring for Federally Administered Tribal Areas Water Resources Development
D. Cumulative Contract Award and Disbursement Performance
E. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
Current Status
1 Due to expected
delay in the main
project, TA budget
cannot support
activities if project is
extended
Rationalize TA activities during
the next loan review mission
scheduled after Project Steering
Committee meeting in July 2019
Aug-Sep 2019/
ADB
ADB will
rationalize the
consultants
inputs during
LRM in Oct
2019 keeping in
mind the loan
extension
- - -
126
209 209
169
207 217
-
13 19
60 63
116 123
-
25
50
75
100
125
150
175
200
225
250
Jun-17 Dec-17 Jun-18 Dec-18 Jun-19 Dec-19 Jun-20 Dec-20
(Th-
$)
TA 9343 :Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Clo
sin
g: 3
0 S
ep
20
20
Net TA amount: $ 225 (Th)
37
Agriculture and Natural Resources Sector
TA 9343-PAK: Third Party Monitoring for Federally Administered Tribal Areas Water Resources Development
F. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1 In case of loan extension,
the TA funds will be
insufficient to finance the
consultants input for the
extended period
ADB in consultation with the PMU will
rationalize the consultants input
To be discussed
from 18-25 Oct/2019
in LRM
38
Agriculture and Natural Resources Sector
TA 9463-PAK: Revitalizing the Ecosystem of Ravi Basin
TA 9463-PAK: Revitalizing the Ecosystem of Ravi River Basin
A. TA Basic Data US$ (Thousand)
Approval Date
Signing Date Closing
Date
Closing Date
(Revised)
Time Elapse
%
Contract Award (Cumulative)
Disbursements (Cumulative)
12-Dec-17
11-Jan-18
30-Sep-19
30-Jun-2020
71
PRCF:550.00 TASF:460.00 WFPF:164.70
PRCF:116.25 TASF:124.11 WFPF:30.06
Approved Amount
Net Amount Financing Project Officer
Project Analyst
Counterpart Agencies
550 460 200
1,210
550 460 200
1,210
PRCF TASF
WFPF A. Tayyab
L.A. Abenojar
Punjab Environment Protection Department
B. TA Description 1. The proposed knowledge and support technical assistance (TA) will operate for 18 months and will develop a plan to revitalize and build resilience in the Ravi River Basin in the province of Punjab, Pakistan. The river basin is being heavily polluted with urban, industrial, and agricultural waste, creating major human health, food, and water safety risks. These risks will continue to worsen without urgent action by the government and society. The TA will support activities to assess the pollution problem, identify and close institutional gaps, raise awareness, and develop a long-term plan to revitalize and build resilience in the basin, with detailed investment recommendations. 2. This TA is included in the country operations business plan, 2018-2020 of the Asian Development Bank (ADB) for Pakistan. It is in line with ADB's country partnership strategy, 2015-2019 for Pakistan, which includes support for wastewater treatment, river basin management, and pollution control. The TA was requested by the Punjab Environment Protection Department (EPD) through the Punjab Planning and Development Board and the Economic Affairs Division of the federal government in July 2017 and confirmed through an aide-memoire in November 2017. Support for the TA is included in the ADB Water Sector and Environment Thematic Group work plans. C. Project Monitoring Framework (Current Status)
Outputs Performance Indicators Status with Key Activities
Successfully document and assess ecosystem characteristics and the industrial pollution situation in the river basin and recommend water quality and pollution control knowledge management and data sharing systems.
Report on industrial/corporate stakeholder mapping and desk review of ecosystem characteristics. Report and meeting summaries with recommendations and techniques for knowledge management and data sharing system on water quality and pollution control.
On-going
39
Agriculture and Natural Resources Sector
TA 9463-PAK: Revitalizing the Ecosystem of Ravi Basin
Outputs Performance Indicators Status with Key Activities
Successfully undertake multi-stakeholder visioning exercises and training to support the planning process to revitalize the river basin.
Report on the recommendations emanating from city wide partnership sessions. Report with recommendations on the IPMC formation for the multi-stakeholder visioning report Report on the AWS sessions
On-going
Successfully provide inputs to the revitalization and resilience plan for the basin, focused on industrial pollution planning and nature-based pollution control.
Assessment report on industrial effluent treatment options and other recommendation for the revitalization plan and next steps.
On-going
D. Cumulative Contract Award and Disbursement Performance
-- - -
1,155 1,155 1155
- -
61
270 270
-
500
1,000
1,500
Jun-17 Dec-17 Jun-18 Dec-18 Jun-19 Dec-19 Jun-20 Dec-20
(Th -
$)
TA 9463: Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Clo
sin
g: 3
0 J
un
20
20
Net TA amount: $ 1,210 (Th)
40
Agriculture and Natural Resources Sector
TA 9463-PAK: Revitalizing the Ecosystem of Ravi Basin
E. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No issues
F. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No issues
41
Agriculture and Natural Resources Sector
TA 9442-PAK: Khyber Pakhtunkhwa Resources Development Project
TA 9442-PAK: Khyber Pakhtunkhwa Water Resources Development Project
A. TA Basic Data US$ (Thousand)
Approval Date
Signing Date Closing
Date
Closing Date
(Revised)
Time Elapse %
Contract Award
(Cumulative)
Disbursements (Cumulative)
6-Dec-17 1-Jan-18 31-Dec-19 23-Mar-20 79 992.24 438.72
Approved Amount
Net Amount Financing Project Officer
Project Analyst
Counterpart Agencies
1,200 1,200 TASF A.
Shimasaki C. Cabrales-
Chiong) Irrigation Department Khyber
Pakhtunkhwa
B. TA Description 1. The output of the TRTA will prepare the investment project through the following activities: (i) verify the engineering and agriculture outputs of the already available feasibility studies (one for Mulkoh subproject and another for Tanda subproject), and update these where necessary; (ii) conduct fresh feasibility study of the PMC subproject; and (iii) conduct due diligence covering (a)climate change risks (CCRs) and climate change impacts (CCIs); (b) economic and financial including the development of the guidance note to develop sustainable O&M plan for each IDS; (c) governance; (d) poverty, social, and gender; (f) social and environment safeguards; and (g) assessment of risks associated in implementation of the ensuing project. The activities will also include the preparation of two consultant service packages (one for the detailed design and another for the project implementation support) for KPID to recruit them. The detailed design consultants will be financed by KPP government’s own resources and therefore it will be recruited following Government’s guidelines. The terms of reference and cost estimates for the detailed design consultants are expected to be prepared by end of July 2018 based on the midterm inputs from TRTA consultants. The project implementation support consultant, to be financed under the ensuing project, will be recruited following ADB Procurement Policy (2017, as amended from time to time) and Procurement Regulations for ADB Borrowers (2017, as amended from time to time). 2. The TA is estimated to cost $1.3 million, of which $1.2 million will be financed on a grant basis by ADB's Technical Assistance Special Fund (TASF-6). The key expenditure items are listed in Appendix 1. The government will provide counterpart support in the form of counterpart staff, logistical support, provisions of available feasibility studies, and facilitation of consultation with stakeholders during the feasibility study, which is estimated at about 10% of the total TA cost. The government was informed that approval of TA does not commit ADB to finance any ensuing project.
42
Agriculture and Natural Resources Sector
TA 9442-PAK: Khyber Pakhtunkhwa Resources Development Project
C. Project Monitoring Framework (Current Status)
Outputs Performance Indicators Status with Key Activities Successfully submit the inception report which includes initial analysis of the proposed subprojects and proposals for necessary surveys and studies.
Inception report submitted and approved.
Draft inception report was submitted in time and revised and approved after the inception mission held September 2018.
Successfully submit the Mid-term report which includes detailed analysis of the proposed subprojects, safeguards issues, and outline terms of reference of the design and supervision consultants for ensuing project.
Mid-term report submitted and approved.
Draft mid-term report was submitted in January 2019. A workshop with EA was held to explain the mid-term report was held in March 2019.
Successfully submit draft final report. Draft final report submitted and approved.
Draft feasibility report for PMC subproject was submitted to ADB on 25 September 2019 and being reviewed. Surveys and studies for other subprojects are on-going.
Successfully submit final report. Final report submitted and approved.
D. Cumulative Contract Award and Disbursement Performance
--- -
990 990 992
- -
257
415 439
-
300
600
900
1,200
Dec-17 Jun-18 Dec-18 Jun-19 Dec-19 Jun-20
(Th -
$)
TA 9442: Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Clo
sin
g: 2
3 M
ar
20
20
Net TA amount: $ 1,200 (Th)
43
Agriculture and Natural Resources Sector
TA 9442-PAK: Khyber Pakhtunkhwa Resources Development Project
E. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No issues
F. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No issues
44
Agriculture and Natural Resources Sector
TA 9458-PAK: Preparing Greater Thal Canal Irrigation Investment Program
TA 9458-PAK: Preparing Greater Thal Canal Irrigation Investment Program
A. TA Basic Data US$ (Thousand)
Approval Date
Signing Date Closing
Date
Closing Date
(Revised)
Time Elapse %
Contract Award
(Cumulative)
Disbursements (Cumulative)
11-Dec-17 9-Jan-18 30-Sep-19 30-Sep-20 64 1,303.19 353.73
Approved Amount
Net Amount Financing Project Officer
Project Analyst
Counterpart Agencies
1,400 1,400 TASF N.
Totsuka S. Mariano
Irrigation Department of the Government of Punjab
B. TA Description 1. The TA will help ADB and the executing agency prepare an ensuing ADB-financed investment. The main canal and the first branch system of the Greater Thal Canal Irrigation System have been constructed by government financing in 2008. The proposed ADB-financing support will complete the construction of the rest of the branch systems with command area development for the entire system in a phased manner. An multitranche financing facility with a few tranches were originally planned, but ADB financing may comprise a few stand-alone projects. The first project will cover the construction of the second branch system and command area development for the existing main canal and the first branch system areas, may also be with the command area development of the second branch system area. 2. The WAPDA completed a feasibility study and detailed design for the entire scheme in 2008, and the Punjab Irrigation Department (PID) is preparing updated detailed design for the second branch system. The TRTA will develop overall investment planning for the entire scheme, and help preparation of the first project that include verification of the PID’s updated detailed design, estimating project cost estimate, assessing economic feasibility, safeguard due diligences, institutional assessment, risk assessment and other due diligences that are required for meeting ADB’s loan approval requirements. C. Summary of Major Outputs and Activities
Outputs Delivery Dates Status with Key Activities Overall investment planning
Sep 2019 1.1 Institutional assessment 1.2 Reviewing policy, legal and regulatory framework 1.3 Financial and institutional O&M capacity analysis 1.4 Developing baseline data platform for monitoring and evaluation using remote sensing satellite technology
Updated feasibility study
Aug 2019 2.1 Verification of existing detailed design 2.2 Design of non-structural components, including on-farm command area development capacity development 2.3 Safeguard and gender assessments 2.4 Update project cost estimate 2.5 Climate change risk assessment 2.6 Technical and economic feasibility assessment
45
Agriculture and Natural Resources Sector
TA 9458-PAK: Preparing Greater Thal Canal Irrigation Investment Program
Outputs Delivery Dates Status with Key Activities Due diligence reports Sep 2019 3.1 Verifying financing modality, and trancheing plan
for an MFF, and preparation of processing documents for the MFF. 3.2 Due diligence assessments including financial and procurement risks. 3.3 Implementation and financing plan preparation 3.4 Safeguard, gender and social document preparation, including EIA report and resettlement plan 3.5 Other necessary assessments for ADB’s Linked documents and develop data for inputs to PAM
Readiness support Dec 2019 3.1 Assist government’s project approval documents (PC-1) 3.2 Assist PID for procurement of first batch civil works and goods packages,
D. Cumulative Contract Award and Disbursement Performance
--- - -
1,269 1303
--
- -
-
166
354
-
300
600
900
1,200
1,500
Dec-17 Jun-18 Dec-18 Jun-19 Dec-19 Jun-20 Dec-20
(Th -
$)
TA 9458: Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Clo
sin
g: 3
0 S
ep
20
20
Net TA amount: $ 1,400 (Th)
46
Agriculture and Natural Resources Sector
TA 9458-PAK: Preparing Greater Thal Canal Irrigation Investment Program
E. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. PMO staff recruitment
delay (Same as the
Jalalpur project)
Advertisement has to be started. As soon as possible
/ PID
F. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No issues
47
Agriculture and Natural Resources Sector
TA 9576-PAK: Climate-Resilient Water Resources Management
TA 9576-PAK: Climate-Resilient Water Resources Management
A. TA Basic Data US$ (Thousand)
Approval Date
Signing Date Closing
Date
Closing Date
(Revised)
Time Elapse %
Contract Award
(Cumulative)
Disbursements (Cumulative)
31-Aug-18 27-Sep-18 31-Dec-22 - 25 111.70 -
Approved Amount
Net Amount Financing Project Officer
Project Analyst
Counterpart Agencies
2,000 2,000 JFPR Y. Zhou C. Cabrales-
Chiong Irrigation Department,
Government of Balochistan
B. TA Description 1. Balochistan is highly vulnerable to climate change impacts that threaten resource-poor farmers and women in rural communities. The Government of Balochistan (GOB) adopted the IWRM policy in 2006 with ADB’s support.2 The policy provides a comprehensive framework for the province to address water management and development using the basin approach, with water harvesting and groundwater recharging an integral part of watershed management. Since then, useful progress has been made in implementing the policies, but expected outcomes indicated in the policy have not been achieved due to lack of funds, weak institutional capacity, and poor data support. The effective implementation of the IWRM policy requires quantitative, reliable surface water and groundwater data, which are extremely limited in Balochistan. Moreover, there is no WRIS in Balochistan. The coverage and reliability of hydrological data are particularly poor, preventing well-informed planning and management of water resources. The province formerly had a network to monitor scarce and depleted groundwater resources in Pishin–Lora basin and surface water in major river basins, but most of the monitoring network is no longer functional because of inadequate funding support. 2. The TA is listed in the Pakistan country operations business plan, 2018–2020. The TA is estimated to cost $2,350,000 million, of which $2,000,000 will be financed on a grant basis by the Japan Fund for Poverty Reduction and administered by ADB. Balochistan lacks a provincial climate change policy, despite facing increased impacts from climatic variability coupled with extreme drought and flood events; meanwhile, the existing IWRM policy does not address potential risks, including droughts, floods, and groundwater depletion. The technical assistance (TA) will help strengthen Balochistan’s institutional capacity to address exposed climate change impacts and risks and build climate-resilient and sustainable WRM mechanisms that apply innovative, high-level WRIS technology. C. Summary of Major Outputs and Activities
Outputs Delivery Dates Key Activities with Milestones Knowledge, policy and regulatory frameworks enhanced and updated for improved, climate-resilient WRM
a. By Q2, 2019 b. By Q4 2020 c. By Q4 2020 d. By Q4 2020 e. By Q4 2021
1.1 Assess climate change impacts and prepare adaptation strategy 1.2 Update water balance study for all river basins of Balochistan 1.3 Review and update 2006 IWRM policy
48
Agriculture and Natural Resources Sector
TA 9576-PAK: Climate-Resilient Water Resources Management
Outputs Delivery Dates Key Activities with Milestones 1.4 Draft relevant laws and regulations enforcing the updated IWRM policy and Groundwater Rights Ordinance (1978) 1.5 Identify and prepare water sector plan investment priority
Design and infrastructure of WRIS, applying satellite remote-sensing technology, improved
a. By Q4 2018 b. By Q1 2019 c. By Q3 2019
2.1 Review and improve the WRIS architecture and interface design 2.2 Upload relevant data into the WRIS 2.3 Conduct training and facilitate use of WRIS by Irrigation Department and ACD staff
Institutional capacity and skills relating to efficient use of water for climate-resilient WRM increased
a. By Q1 2019 b. By Q2 2019 c. By Q3 2021
3.1 Design and conduct workshop and training programs for Irrigation Department and ACD staff, including field office staff, and communities in the project areas of Zhob and Mula river basins 3.2 Train at least 20 Irrigation Department and ACD staff to use the enhanced WRIS for planning and monitoring 3.3 Implement phased training programs for Irrigation Department and ACD farmers, including women
D. Cumulative Contract Award and Disbursement Performance
- -- - -
112
- -
- 0
-
500
1,000
1,500
2,000
Aug-18 Feb-19 Aug-19 Feb-20 Aug-20 Feb-21 Aug-21 Feb-22 Aug-22 Feb-23
(Th -
$)
TA 9576: Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Clo
sin
g: 3
1 D
ec 2
02
2
Net TA amount: $ 2,000 (Th)
49
Agriculture and Natural Resources Sector
TA 9576-PAK: Climate-Resilient Water Resources Management
E. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No issue
F. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No issue
50
Agriculture and Natural Resources Sector
TA 9614-PAK: Preparing Kurram Tangi Integrated Water Resources Development Project
TA 9614-PAK: Preparing Kurram Tangi Integrated Water Resources Development Project
A. TA Basic Data US$ (Thousand)
Approval Date
Signing Date Closing
Date
Closing Date
(Revised)
Time Elapse %
Contract Award
(Cumulative)
Disbursements (Cumulative)
5-Oct-18 5-Oct-18 28-Feb-19 31-Dec-19 80 77.65 72.45
Approved Amount
Net Amount Financing Project Officer
Project Analyst
Counterpart Agencies
225 225 TASF A. Tayyab C. Cabrales-
Chiong WAPDA
B. TA Description 1. The proposed KSTA aims to support WAPDA, as the proposed executing agency, to review existing data and studies, to identify essential design and information gaps and determine the scope and implementation arrangements for the additional investigations and other engineering, social and environmental analytical works that are necessary to ensure due diligence. The KSTA is likely to result in the comprehensive proposal for a subsequent transaction TA (TRTA) that would address the identified due diligence gaps and confirm the viability of the project for possible ADB financing. As the proposed TA will support identifying the critical knowledge gaps required for formulating and considering a TRTA, a KSTA would be an ideal vehicle 2. The TA is estimated to cost $225,000, which will be financed on a grant basis by ADB's Technical Assistance Special Fund (TASF-6). C. Project Monitoring Framework (Current Status)
Outputs Performance Indicators Status of Activities
Technical, social, and Environmental gaps in the existing project design identified
1.1 Relevant reports, drawings, and data collected and reviewed by December 2018 (Sept. 2018 Baseline: n.a.) 1.2 Gaps in technical, social, and environmental analyses identified by mid-January 2019 (Sept. 2018 Baseline: n.a.)
On going
Detailed scope of services identified to address the gaps in existing design along with the resources requirements and estimated costs, such as additional investigation, engineering analyses, and possible modification of detailed engineering design.
2.1 Plausible options (e.g., engineering analyses, use/types of mathematical and physical models, etc.) for analyses identified by end December 2018
(Sept. 2018 Baseline: n.a.)
2.2 Suitable methodologies and work plan identified for the prevailing local and project-specific constraints by end January 2019
(Sept. 2018 Baseline: n.a.)
On going
51
Agriculture and Natural Resources Sector
TA 9614-PAK: Preparing Kurram Tangi Integrated Water Resources Development Project
2.3 Detailed scope of additional engineering, social, and environmental analyses and investigation identified, along with cost estimates, work plan and relevant terms of reference for the consultants, by end February 2019 (Sept. 2018 Baseline: n.a.)
D. Cumulative Contract Award and Disbursement Performance
E. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No issues
F. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No issues
- -- -
122
78
0
-
43
72
-
50
100
150
200
250
Sep-18 Mar-19 Sep-19 Mar-20
(Th -
$)
TA 9614- Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Clo
sin
g: 3
1 D
ec 2
01
9
Net TA amount: $ 225 (Th)
52
II. ENERGY Loans 1. Loan 3090/3091-PAK3092-PAK(SF): Jamshoro Power Generation Project
2. Loan 8311-AFD: Power Transmission Enhancement Investment Program Tranche IV
3. Loan 3328-PAK/ Loan 3329-PAK(COL): MFF Second Power Distribution Enhancement Investment Program Tranche I
4. Loan 3419-PAK / Loan 3420-PAK (COL): MFF Second Power Transmission Enhancement Investment Program Tranche I
5. Loan 3476-PAK: Access to Clean Energy Investment Program
6. Loan 3577-PAK: MFF Power Transmission Enhancement Investment Program II-T2
7. Loan 3677-PAK/Grant 0578-PAK: MFF Power Transmission Enhancement Investment
Program II T3
Technical Assistance (TAs)
1. TA 9185-PAK: Hydropower Development Investment Program (Supplementary)
2. TA 9247-PAK: Access to Clean Energy Investment Program
3. TA 9357-PAK: Update on Energy Sector Plan
4. TA 9672-PAK: Developing an Electricity Market
5. TA 9674-PAK: Preparing Lower Palas Hydropower Project
6. TA 9756-PAK: Preparing Sustainable Energy Projects
53
Energy Sector
Loan 3090/3091/3092-PAK (COL): Jamshoro Power Generation Project
Loan 3090/3091/3092-PAK (COL): Jamshoro Power Generation Project
A. Loan Basic Data $ Million
Approval Date
Signing Date
Effective Date
Closing Date Closing Date
(Revised) Elapsed Time % Project
Rating as of
30 Sep 19
09-Dec-13 12-Feb-14 20-Nov-14 L3090: 31-Mar-19 L3091: 30-Jun-24 L3092: 31-Mar-19
L3090: 30-Jun-22 L3091: 30-Jun-27 L3092: 30-Jun-22
L3090: 68 L3091: 43 L3092: 68
Approved Amount
Net Loan Amount
Financing EA/IA Project Officer Project Analyst
L3090: 840.00 L3091: 30.00 L3092: 26.65
L3090:690.00 L3091:30.00 L3092:26.65
L3090:OCR L3091:OCR L3092:COL
GHCL (EA) JPCL (IA)
Asad Aleem D. Garcia Potential Problem
B. Loan Financial Progress – (As of 30 Sep 2019)
Loan 3090-PAK
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
540.43 149.57 78 5.0 0.0
Disbursements (Cumulative)
Un-disbursed Loan Balance
Disbursement Performance %
Disbursements for 2019
EA’s Projections Actual
64.57 625.43 9 56.58 8.21
Loan 3091-PAK
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
0.75 29.25 3 0.00 0.00
Disbursements (Cumulative)
Un-disbursed Loan Balance
Disbursement Performance %
Disbursements for 2019
EA’s Projections Actual
0.26 29.74 1 0.00 0.05
Loan 3092-PAK(COL)
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
16.90 9.75 63 7.0 0.00
Disbursements (Cumulative)
Un-disbursed Disbursement Performance %
Disbursements for 2019
Loan Balance EA’s Projections Actual
7.74 18.91 29 3.02 0.81
54
Energy Sector
Loan 3090/3091/3092-PAK (COL): Jamshoro Power Generation Project
C. Project Description 1. The project’s impact will be an enhanced energy supply in Pakistan. The project will (i) increase the capacity of the Jamshoro TPS by installing a 600-MW (net) supercritical coal-fired unit, using an 80/20 blend of imported sub-bituminous coal and domestic lignite when available; (ii) provide 5 years of operation and maintenance (O&M) support; (iii) improve compliance with international and national environmental standards by installing emission control devices for the existing units and remediating the site; (iv) enhance the capacity of GENCO Holding Company Limited (GHCL) and Jamshoro Power Company Limited (JPCL) by providing financial, technical, and operational training; and (v) promote education on coal-fired plant operation by providing on-the-job training, and integrating such training into technical school curriculum. The infrastructure developed will also support government’s plan to have an additional 600-MW unit at the same site. 2. The outcome will be a more efficient energy mix through diversification from expensive HFO to less expensive coal. D. Project Monitoring Framework (Current Status) Outputs Performance Indicators Status with Key Activities Jamshoro TPS capacity increased
Installation of one 600 MW (net) supercritical coal-fired unit and begin implementation of the 5-years O&M contract, by 2022
At the Government’s request, the loan and project agreements were amended in Mar 2018 on which: (i) JPCL is to deposit the full price of the land for ash disposal pond construction within 30 days from the signing of EPC contract and complete the land acquisition before commencement of civil works on ash pond; (ii) JPCL is to execute the power purchase agreement with CPPA-G within 12 months from the execution of EPC contract; (iii) JPCL is to execute the coal purchase agreement within 60 days of signing of EPC contract. These amendments deferred the earlier conditions and rationalized the contract award for EPC supercritical coal power plant. On 29 March 2018, EPC contract for a 600-MW supercritical power unit 1 and O&M (EPC-O&M, Lot 1) contract was awarded at the price of about $562 million and $89 million respectively. Subsequent to contract award, advance payments of $47.4 million was disbursed in June 2018 and $4.6 million in June 2019. To expedite payments, a supplementary appendix to Payment Schedules was issued in June 2019 allowing payments for the equipment already delivered on site and service already rendered which is more practical and achievable, as compared with the existing Price schedules on which prices are lumped and payments will only be made when full scope of equipment and services are delivered.
55
Energy Sector
Loan 3090/3091/3092-PAK (COL): Jamshoro Power Generation Project
Outputs Performance Indicators Status with Key Activities Of the deferred conditions stated above, Item (i) was complied with in May 2019 when JPCL deposited the required amount for land acquisition to the account of the Sindh government. Sindh government is currently undertaking negotiation and payment to the affected people. In parallel, JPCL is expected to commence design and preparatory works. JPCL is also expected to subsequently update LARP in this regard. Item (ii), on the other hand, is yet to commence. Initial electrical load flow and short circuit study calculations and GSUT calculation were rejected by NTDC and are yet to be revised. Item (iii) was complied with when a master coal purchase agreement was finalized and signed with qualified bidders in July 2018. Combined with Unit 1, an EPC contract for the second unit of 600-MW (EPC-O&M Lot 2) is procured under single responsibility amounting to about $313 million. Award of such contract is pending availability of financing. Islamic Development Bank ($150 million), OPEC Fund for International Development Fund ($72 million), Saudi Fund ($50 million) and Kuwait Fund ($50 million) expressed interests in financing on which the Government’s decision is awaited. To allow time for the Government’s deliberation, the EPC contractor agreed to extend the bid validity to 11 December 2019. Donor coordination meeting is required to reconcile all different terms and conditions among 4 potential co-financiers..
National environmental standards complied with by Jamshoro TPS
Bioremediation of the contaminated soil by 2024
It was agreed with the EA to combine this scope with the EPC-O&M contract for seamless contract execution and management. ADB issued no objection in Mar 2019 on JPCL’s proposal for EPC-O&M Lot 1 contractor to conduct site investigation in at least 45 locations with at least 300 samples. Following the change procedure in the contract, EPC contractor is preparing a final contract amendment. After the site investigation, EPC-O&M Lot 1 contractor will propose a cost estimate for the needed bioremediation.
56
Energy Sector
Loan 3090/3091/3092-PAK (COL): Jamshoro Power Generation Project
Outputs Performance Indicators Status with Key Activities Construction of hazardous
waste storage facility, effluent pipeline, landfill for colony waste and proper lined evaporation ponds by 2022.
Works on renovation of effluent evaporation pond (Lot 1) and construction of channel for discharging cooling water disposal channel (Lot 2) are completed. Construction of municipal waste disposal facilities (Lot 3) and construction of hazardous solid waste facility (Lot 4) is at 84% and 70% completion, respectively. Supply and construction of sewage treatment plant, on the other hand, is at 50% progress.
Installation of emission control devices (FGD) for the existing units by 2022.
The Ministry of Water and Power determined to either convert the oil unit into a gas fired unit, if gas is made available, or shut-down the existing units by the time of completion of coal fired power plant. However, the final decision should be made in consultation and agreement with Sindh EPA. It is noted that existing unit 1 – 4 are currently running on furnace oil due to the shortage of gas.
Executing agency and implementation agency staff capacity enhanced
At least 50 relevant staff (male and female) trained on project administration, safeguard, procurement, financial, and technical O&M aspects by 2022
Training manuals are yet to be prepared by the capacity development consultant, engagement of which was initiated in Sept 2017 . EOIs were received in December 2017 but JPCL determined to annul the EOI process due to absence of qualifying bidder. JPCL revised the TOR and will re-advertise the consulting assignment in end-Oct 2019.
Coal-fired power plant operation introduced in technical school curriculum
Inclusion of at least one subject related to coal-fired plant operation in a technical school by 2022
Not yet due. Appropriate curriculum design will be conducted by Capacity Development Consultant.
57
Energy Sector
Loan 3090/3091/3092-PAK (COL): Jamshoro Power Generation Project
E. Cumulative Contract Award and Disbursement Performance Loan 3090-PAK
Loan 3091-PAK
0.0 0.8 0.8 1.0 0.8 0.8 0.8 0.8 0.8 0.8 0.8
0.1 0.1 0.2 0.2 0.20.2 0.3
-
5
10
15
20
25
30
35
L 3091: Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Loan Amount: US$ 30.00 M
Clo
sin
g D
ate
: 30-J
un-2
027
58
Energy Sector
Loan 3090/3091/3092-PAK (COL): Jamshoro Power Generation Project
Loan 3092-PAK (COL)
F. Contract Award and Disbursement Targets and Achievements in 2019 Loan 3090-PAK
0.0
17.5 17.5 17.5 17.5 17.5 17.4 17.4 17.4 17.0 17.0
0.0
2.5
4.0 4.05.1 5.4
6.2 6.7 6.8 6.97.7
-
5
10
15
20
25
30
Dec-14 Dec-17 Jun-20
L 3092: Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Loan Amount: US$ 26.65 M
Clo
sin
g D
ate
: 30-J
un-2
022
0 0 0 0 0
2
3
5 5 5 5
0 0 0 0 0 0 0 0 0
0
1
2
3
4
5
6
2019 Contract Awards L3090($548.2 million through Dec 2018)
EA Projection Actual
0.0 0.0 0.0
18.9
37.7
56.6 56.6 56.6 56.6 56.6 56.6 56.6
- 0.1 1.5 1.6 1.6
7.0 6.8 6.8 8.2
0.0
10.0
20.0
30.0
40.0
50.0
60.0
2019 Disbursements L3090($56.4 million through Dec 2018)
EA Projection Actual
59
Energy Sector
Loan 3090/3091/3092-PAK (COL): Jamshoro Power Generation Project
Loan 3091-PAK
Loan 3092-PAK(COL)
G. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
Current Status
1. JPCL settled payment for the newly identified land plot. Title transfer is awaited.
Closely monitor the progress and provide support to expedite the process
30 September
2019
JPCL deposited the required amount for land acquisition to the account of the Sindh government in May 2019. Sindh government is currently undertaking
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
- - - - - - - - -0
0
0
0
0
1
1
1
1
1
1
2019 Contract Awards L3091($0.8 million through Dec 2018)
EA Projection Actual
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0 0.0 0.0 0.0 0.0 0.0
0.1
0.0
0.0
0.0
0.0
0.0
0.1
0.1
2019 Disbursements L3091($0.2 million through Dec 2018)
EA Projection Actual
0.5
1.0
1.5 1.5 1.5 1.5
2.0
2.5
3.0 3.0 3.0 3.0
-
0.3 0.5
0.7 0.8 0.8 0.8 0.8 0.8
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
2019 Disbursements L3092($6.9 million through Dec 2018)
EA Projection Actual
0.0
0.0 0.0 0.0 0.0 0.0 0.0 0.0
2.3
4.7
7.0
- - - - - - - - -0
1
2
3
4
5
6
7
8
2019 Contract Awards L3092($17.0 million through Dec 2018)
EA Projection Actual
60
Energy Sector
Loan 3090/3091/3092-PAK (COL): Jamshoro Power Generation Project
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
Current Status
negotiation and payment to the affected people.
2. Financing plan for Unit 2 EPC contract
EAD to convene a donor coordination meeting to reconcile different terms and conditions among financiers; JPCL is required to extend
the bid validity to hold the
proposal valid
31 October
2019
EPC-O&M Lot 2 bid validity has been extended for almost a year until 11 Dec 2019. EAD should immediately conclude discussions with Unit 2 financiers to secure Unit 2 contractor.
H. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. Unit 1 construction (i) Removal of existing natural gas station
and pipelines under the steam generator
foundation and major part of the power
block allocated to supercritical units.
(ii) Bioremediation of contaminated soil
(i) JPCL should
immediately
conclude discussion
with gas company to
relocate the
pipeline.
(ii) EPC-O&M Lot 1
contractor to
immediately
conclude soil
investigation and
commence
remediation
2. Coal transport Design of railway siding and coal
unloading as requested by PAK Railway
Authority (PRA) to accommodate “side
dump” rail car configurations thus,
affecting the overall plant layout.
JPCL to immediately
submit design for
PRA approval
3. FGD Installation Conclude whether FGD is still necessary.
Otherwise, cancel the financing for such
($32 million)
JPCL and EAD to
confirm by 30 Nov
2019 if there is still a
need to keep the
financing
4. EPC-O&M Lot 1 payments Unsettled payment breakdown on which
relevant registration for custom clearance
by JPCL is yet to be completed. With this,
JPCL to coordinate
with customs and
61
Energy Sector
Loan 3090/3091/3092-PAK (COL): Jamshoro Power Generation Project
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
the project implementation consultant
noted that delivery of equipment (boiler
and coal mill embedded parts etc.) was
postponed.
facilitate import
clearance
62
Energy Sector
Loan 8311-PAK (AFD): Power Transmission Enhancement Investment Program-Tranche IV
Loan 8311-PAK(AFD): Power Transmission Enhancement Investment Program Tranche IV A. Loan Basic Data
$ Million Approval
Date Signing
Date Effective
Date Closing Date
Closing Date (Revised)
Elapsed Time %
Project Rating as of
30 Sep 19
29-Sep-16 20-Jul-17 20-Jul-17 01-Aug-20 - 78 Approved Amount
Net Loan Amount
Financing EA/IA Project Officer
Project Analyst
88.16
86.21
AFD
NTDC
E.Z.Khattak
K. Shahzad On Track
B. Loan Financial Progress – (As of 30 Sep 2019)
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
75.62 10.59 88 0.3 0.28
Disbursements (Cumulative)
Un-disbursed Loan Balance
Disbursement Performance %
Disbursements for 2019
EA’s Projections Actual
60.84 25.37 71 11.83 2.7
C. Project Description 1. The Project is the fourth tranche of an $800 multi-tranche financing facility and aims to augment, rehabilitate and expand transmission system. Tranche 4 aimed to finance 10 subprojects covering (i) line bay extension and 281 kilometers (km) of 500-kilovolt (kV) transmission line from the 500-kV Muzaffargarh grid station for electricity evacuation from the 747-MW Guddu power plant; (ii) four new 220-kV grid stations and in/out transmission lines at Chakdara, D.I. Khan, Lalian, and Nowshehra; (iii) installation of a static var system (SVS) at 220-/132-kV Quetta industrial grid station; (iv) extension of 500-kV grid stations at Jamshoro and Gujranwala, and augmentation of 500-kV grid station at Rawat; and (v) the procurement of construction and operational equipment. Items (i) and (iii) are proposed for cancellation. 2. The Project impact will be enhanced power transmission operations and management, and the outcome will be an expanded and reliable 500-kV and 220-kV transmission system. D. Project Monitoring Framework (Current Status)
Outputs Performance Indicators Status with Key Activities Transmission lines and substations commissioned
Extension of the 500-kV grid stations at Jamshoro and Gujranwala, and augmentation of the 500-kV Rewat grid station by 2016.
ADB-71 (500kv G/S equipment) and ADB-73 (500kv G/S civil works): All contracts for equipment awarded and equipment delivered. All works are expected to be completed in Q4-2019. Retention money payment of 10% is pending upon receiving claim of contractor.
63
Energy Sector
Loan 8311-PAK (AFD): Power Transmission Enhancement Investment Program-Tranche IV
Outputs Performance Indicators Status with Key Activities Addition of 281 km of 500-kV
transmission line and extension of the 500-kV Muzaffargarh substation completed by 2016.
ADB-79 (500kv T/L equipment): All contracts awarded. ADB-80 (500kv T/L civil works): All 4 lots were cancelled from Loan 3203 and financed under MFF Second Power Transmission Enhancement Investment Program Tranche 1.
Addition of four new 220-kV grid stations and 195 km associated in/out transmission lines at Chakdara, D.I.Khan, Lalian, and Nowshehra completed by 2016.
ADB-70 (220kV G/S equipment): All contracts were awarded, and equipment/material delivered. ADB-72 (220kV G/S Civil works) Packages 1 and 2: All contracts awarded in Oct 16, with completion in Q3 2018, except Lalian S/S (Lot 2) which will be completed in Q4 2019 due to change of site. ADB-77 (220kV T/L equipment): All contracts awarded, and equipment/materials delivered. ADB-78 (220kv T/L civil works): Both lots awarded. Contract completion Q3 2019.
Establishment of a new static VAR system at 220-kV Quetta industrial grid station by 2016
ADB-74: For rebid –Cancelled under Loan 3203
Equipment for various grid stations ADB-75 (construction equipment): Cancelled. ADB-81 (Telecoms equipment): All contracts signed in Sep 2017, and Material delivered on site in Q3 2018.
64
Energy Sector
Loan 8311-PAK (AFD): Power Transmission Enhancement Investment Program-Tranche IV
E. Cumulative Contract award and Disbursement Performance
F. Contract award and Disbursement Targets and Achievements in 2019
0.2
0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3
-
0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3
0
0
0
0
0
0
0
0
2019 Contract Awards L8311($81.6 million through Dec 2018)
EA Projection Actual
1.4
2.9
4.35.1
5.96.7
7.68.5
9.310.2
11.011.8
-
2.7 2.7
2.7
2.7 2.7
2.7
0.0
2.0
4.0
6.0
8.0
10.0
12.0
14.0
2019 Disbursements L8311($58.1 million through Dec 2018)
EA Projection Actual
65
Energy Sector
Loan 8311-PAK (AFD): Power Transmission Enhancement Investment Program-Tranche IV
G. Status of the Action Plan discussed in 2nd TPR
Sr. No
Issue Action to be Taken Due Date / By Whom
Current Status
1. Lallian grid station- land owners refuse to provide the land.
NTDC to finalize land procurement activities and update ADB on the status ADB’s Safeguards Team will visit the site once the land is acquired.
31 October 2019 / NTDC
New site finalized, Land acquisition process to be started and works to be started in Q4 2019 or early 2020.
2. Utilization of Loan Savings
NTDC to provide the requisite information as requested by AFD.
31 August 2019 / NTDC
NTDC through EAD requested for utilization of loan savings. ADB on 15 October 2019 through its letter informed EAD about MFF availability end period till 31 December 2019. ADB will not support further extension of MFF and suggest NTDC to conclude all disbursement before 1 February 2020, which is loan closing date for AFD loan.
H. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. Lallian grid station- land
owners refuse to provide
the land.
NTDC to finalize land procurement
activities and update ADB on the status of
completion of works
31 October 2019 /
NTDC
2. Withdrawal application for
liquidation of advance.
NTDC to send withdrawal application for
those payments which have already been
made from imprest account for liquidation.
31 October 2019 /
MPM, NTDC
3. Conclude project activities
before 31 December 2019
NTDC to conclude project activities before
31 December 2019 which is end date of
ADB MFF. This will enable NTDC to claim
for disbursements before 1 February
2010, which is loan closure date for AFD.
31 December 2019 /
NTDC
66
Energy Sector
Loan 3328-PAK/Loan 3329-PAK (COL): Second Power Distribution Enhancement Investment Program Tranche I
Loan 3328-PAK/3329-PAK(COL): Second Power Distribution Enhancement Investment Program A. Loan Basic Data $ Million
Approval Date
Signing Date Effective
Date Closing Date
Closing Date
(Revised)
Elapsed Time % Project
Rating as of
30 Sep 19 25-Nov-15 19-Nov-16 17-May-17
30-Jun-19 30-Jun-24
30-Jun-24 -
L3328:45 L3329:45
Approved Amount
Net Loan Amount
Financing EA/IA Project Officer
Project Analyst
380.00 20.00
380.00 19.44
OCR COL
MoWP DISCOs
A. Tareen M. Favis Actual
Problem
B. Loan Financial Progress (As of 30 Sep 2019)
Loan 3328-PAK
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
0.00 380.00 0 120.0 0.00
Disbursements (Cumulative)
Un-disbursed Loan Balance
Disbursement Performance %
Disbursements for 2019
Projections Actual
1.31 378.69 0 0.3 0.30
Loan 3329-PAK (COL)
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
0.00 19.44 0 7.9 0.00
Disbursements (Cumulative)
Un-disbursed Loan Balance
Disbursement Performance %
Disbursements for 2019
EA’s Projections Actual
0.00 19.44 0 1.1 0.00
C. Project Description The proposed investment program's objective is to introduce advanced metering infrastructure (AMI) in Pakistan's different distribution companies (DISCOs). An MFF is proposed for this investment. There are nine DISCOs in Pakistan and the AMI roll-out to these DISCOs will be in phases. In the first phase (tranche 1), two of LESCO's circles and IESCO's Rawalpindi region have been selected for AMI roll-out. Once developed, the same will be replicated and implemented in the remaining technically and commercially feasible regions or circles of the nine DISCOs.
67
Energy Sector
Loan 3328-PAK/Loan 3329-PAK (COL): Second Power Distribution Enhancement Investment Program Tranche I
D. Project Monitoring Framework (Current Status)
Outputs Performance Indicators Status with Key Activities Smart Meters and communication equipment installed and functional.
At least 2.0 million customers (IESCO=0.8 million and LESCO=1.2 million) and all substations in the targeted regions of IESCO and LESCO are operating with Smart Meters by 2024. (2013 baseline: zero of similar type) Communication infrastructure commissioned in the targeted regions of IESCO and LESCO by 2024. (2014 baseline: None)
Targets deferred from 2019 to 2024 after Loan 3328 was extended and are still feasible. Bidding cancelled by Ministry of Energy in January 2018. On 1 November, EAD requested ADB to re-engage with IESCO and LESCO to resume project implementation. TBER for IESCO package was submitted to ADB on 29 May with subsequent clarifications. Supplementary TBER was received on 9 Aug and ADB’s
approval of the TBER with only one bidder was given on 3 September 2019. The lone responsive bidder’s price bid was opened on 23 September, and the PBER is awaited. Contract award is now projected in Q1 2020. Bids for the LESCO package were extended from 19 July to 27 August 2019. Bid opening was postponed indefinitely by court order stemming from a contractor’s complaint. Court hearing was scheduled on 10 Oct 2019. Contract award projected in Q2 2020.
Data management system implemented and operational.
Database and data management system developed and operational in the targeted regions by 2024. (2014 baseline: None) 200 (80 in IESCO and 120 in LESCO) personnel trained on data collection and data management system by 2024. (2014 baseline: None)
Operation manuals updated, and monitoring procedure improved.
Manual for theft detection updated by 2021. (2014 baseline: Old and outdated manual) Operational procedures for M&T Unit updated, testing laboratories upgraded and staff capacity on AMI developed in IESCO and LESCO by 2024. (2014 baseline: None or outdated)
Targets deferred from 2017 and 2019 to 2024 after Loan 3328 was extended and are still feasible. This output is in the TOR of the PICs for IESCO and LESCO. Hiring was cancelled by MoE in January 2018. On 1 November 2018, EAD requested ADB to re-engage with IESCO and LESCO to resume project implementation. Contract negotiations initiated and both PICs will be hired in October 2019. Accordingly, the work on OM update will be initiated.
New billing and CIS systems implemented and operational.
Billing system and CIS implemented and operational in the targeted regions by 2024. (2014 baseline: None) At least 700 personnel (250 in IESCO and 450 in LESCO) trained on Billing System and CIS by 2024. (2014 baseline: None)
Same as status of first output.
68
Energy Sector
Loan 3328-PAK/Loan 3329-PAK (COL): Second Power Distribution Enhancement Investment Program Tranche I
E. Cumulative Contract award and Disbursement Performance L3328 PAK
L3329 PAK (COL)
0.0 0.0 0.0 0.0 0.0 0.0
0.0 0.0 0.0 0.0 0.0 0.0 -
5
10
15
20
25
Jun-17 Dec-19 Dec-22
L 3329: Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Loan Amount: US$ 19.44 M C
losin
g D
ate
: 30-J
un-2
024
69
Energy Sector
Loan 3328-PAK/Loan 3329-PAK (COL): Second Power Distribution Enhancement Investment Program Tranche I
F. Contract award and Disbursement Targets and Achievements in 2019 L3328-PAK
L3329-PAK(COL)
G. Status of the Action Plan discussed in 2nd TPR
Sr. No
Issue Action to be Taken Due Date
/ By Whom
Current Status
1. Rebidding of AMI package for IESCO
ADB approves TBER, and IESCO submits FBER
August 2019 / ADB Sep 2019 / IESCO
Completed.TBER approved on 3 Sep, and price bid opened on 23 Sep Pending
2. Procurement of AMI package for LESCO
ADB approves LESCO’s request to extend bid
August 2019 / ADB Oct 2019 / LESCO
Done, bid opening postponed by
0 0 0
0
0
0 0 0 0 0 0 0
- - -
0.3 0.3 0.3 0.3 0.3 0.3
0.0
0.1
0.1
0.2
0.2
0.3
0.3
0.4
2019 Disbursements L3328($1.0 million through Dec 2018)
EA Projection Actual
0 0 0 0 0 0 0 0
40
80
120
- - - - - - - - -0
20
40
60
80
100
120
140
2019 Contract Awards L3328($0.0 million through Dec 2018)
EA Projection Actual
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.4
0.7
1.1
- - - - - - - - -0.0
0.2
0.4
0.6
0.8
1.0
1.2
2019 Disbursements L3329($0.0 million through Dec 2018)
EA Projection Actual
0.0 0.0
1.2
2.5
3.7
5.1
6.5
7.9 7.9 7.9 7.9
- - - - - - - - -0
1
2
3
4
5
6
7
8
9
2019 Contract Awards L3329($0.0 million through Dec 2018)
EA Projection Actual
70
Energy Sector
Loan 3328-PAK/Loan 3329-PAK (COL): Second Power Distribution Enhancement Investment Program Tranche I
submission deadline to 17 Sep 2019, and LESCO submits TBER
court order indefinitely Pending
3. Recruitment of project implementation consultant for IESCO
IESCO submits the following for ADB’s PCSS and disbursement: - signed contract - withdrawal application for advance payment
Aug 2019/ ADB and IESCO
Pending and submission substantially delayed. Must be submitted immediately.
4. Recruitment project implementation consultant for LESCO
LESCO submits revised Submission 2, and ADB approves them
August 2019 / IESCO and ADB
Done. Submission 3 approved in Aug.
5. Audit for FY 2016-2017 and FY 2017-2018
Submit the following to ADB: - first APFS to cover from loan
effectiveness to FY ending Sepe 2019, and AFS for FY 2019
- audited financial ratios for FY 2015 to 2018
- AFS for FY 2015 to 2018
Dec 2019 / IESCO and
LESCO July 2019 / IESCO July 2019 / LESCO
Not done Not done Not done
H. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. Rebidding of AMI package
for IESCO
IESCO submits FBER Oct 2019 / IESCO
2. Procurement of AMI
package for LESCO
LESCO opens technical bids and submits
TBER
Open: Oct/LESCO
TBER: Dec 2019 /
LESCO
3. Recruitment of project
implementation
consultants for IESCO and
LESCO
IESCO and LESCO submit the following for ADB’s PCSS and disbursement: - signed contract - withdrawal application for advance
payment
Oct 2019 / IESCO
and LESCO
4. Audit for FY 2016-2017
and FY 2017-2018
Submit the following to ADB: - first APFS to cover from loan
effectiveness to FY ending June 2019, and AFS for FY 2019
- audited financial ratios for FY 2015 to 2018
- AFS for FY 2015 to 2018
Dec 2019/IESCO and LESCO
Immediately/IESCO Immediately/LESCO
71
Energy Sector
Loan 3419-PAK/ Loan 3420-PAK (COL): Second Power Transmission Enhancement Investment Program
Loan 3419-PAK/Loan 3420-PAK (COL): Second Power Transmission Enhancement Investment Program, Tranche I A. Loan Basic Data $ Million
Approval Date
Signing Date
Effective Date Closing Date Closing Date
(Revised) Elapsed Time %
Project Rating as of
30 Sep 19
31-Aug-16 29-Nov-16 24- Feb-17 31-Dec-20 26-Aug-26
– L3419:71 L3420:31
Approved Amount
Net Loan Amount
Financing EA/IA Project Officer
Project Analyst
115.00 10.14
70.90 9.91
OCR COL
EAD/ MoF E.Z.Khattak K.Shahzad On Track
B. Loan Financial Progress (As of 30 Sep 2019)
Loan 3419-PAK
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
47.93 22.97 68 4.1 0.24
Disbursements (Cumulative)
Un-disbursed Loan Balance
Disbursement Performance %
Disbursements for 2019
EA’s Projections Actual
20.39 50.51 29 21.6 6.31
Loan 3420-PAK (COL)
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
8.55 1.35 86 0.00 0.11
Disbursements (Cumulative)
Un-disbursed Loan Balance
Disbursement Performance %
Disbursements for 2019
EA’s Projections Actual
1.27 8.64 13 0.2 0.21
C. Project Description The objective of the proposed multitranche financing facility (MFF) is to improve Pakistan's power transmission infrastructure and management. Tranche 1 outputs (subprojects) are for construction of new transmission lines, extension and augmentation of existing substations, and installation of shunt reactor and replacement of protection equipment at 11 grid stations. Tranche 1 includes assistance on the preparation of a safety manual, professional third-party project management and information system, capacity development program tailored for the investment program requirements, and an action plan to meet the government's quota for the employment of 10% women.
72
Energy Sector
Loan 3419-PAK/ Loan 3420-PAK (COL): Second Power Transmission Enhancement Investment Program
D. Project Monitoring Framework (Current Status)
Outputs Performance Indicators Status with Key activities
Rehabilitation, augmentation, and expansion of the high voltage transmission network
At least 390 km of new transmission lines constructed by 2021. Capacity of existing substations increased by at least 1,600 MVA through extension and augmentation of transformers by 2021. Installation of shunt reactor and replacement of protection equipment at 11 grid stations.
141 km transmission line (ADB 106-Lot 1, and ADB 108) completed in Q1 2019. Contract of ADB 105 (Lot 1) was signed in Sep 2018, technical data under approval and ADB 105 (Lot 2) will be proceeded for rebidding in Q4 2019. Contract for ADB 100 was signed in Dec 2018. Bidding documents of ADB-101A (rebidding of ADB-101 due to no responsive bidders) were issued on 19 Nov 18,opening on 17 Jan 19 and BER submitted on 24 Jul 2019. ADB provided NOL for annulment of tender on 2 September 2019 and proposed cancellation of this portion of loan or utilize the savings for other material/equipment to be purchased. Contract of ADB 102 (shunt reactors) was signed on 7 June 2018, material to be delivered in Q3 2019, and contract of ADB 103 (protection equipment) was signed in Aug 2018 and technical data under approval.
Operations and management of NTDC strengthened
Safety manual prepared by NTDC and submitted to NEPA by December 2017. A professional third-party project management and information system fully implemented by June 2018. Capacity development plan, tailored to meet MFF and Tranche 1 outcomes and outputs, incorporating target 10% women beneficiaries, approved by December 2017. Action plan to meet government mandated 10% quota is reserved for women from the share of provinces/regions except merit quota approved by December 2017.
Contract of Facility management consultant (FMC) was signed on 12 Dec 2017. FMC will prepare capacity development plan, project management and information system, and action plan to meet government mandated 10% quota reserved for women.
73
Energy Sector
Loan 3419-PAK/ Loan 3420-PAK (COL): Second Power Transmission Enhancement Investment Program
E. Cumulative Contract award and Disbursement Performance Loan 3419-PAK
Loan 3420-PAK (COL)
0.2
8.1
8.3
8.3 8.4 8.6
0.0 0.1
0.91.01.1 1.3
-
2
4
6
8
10
12
L 3420: Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Loan Amount: US$ 9.91 M
Clo
sin
g D
ate
: 2
6-A
ug-2
02
6
6.7
19.5 19.5
43.5
50.1 50.3
0.10.8
5.79.0
14.1
20.4
-
10
20
30
40
50
60
70
80
Jun-17 Dec-19
L 3419: Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Loan Amount: US$ 70.90 M
Clo
sin
g D
ate
: 31-D
ec-2
020
74
Energy Sector
Loan 3419-PAK/ Loan 3420-PAK (COL): Second Power Transmission Enhancement Investment Program
F. Contract award and Disbursement Targets and Achievements in 2019 L3419 - PAK
L3420 - PAK (COL)
G. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
Current Status
1. Rebidding of ADB-101A due to nonresponsive bidder in the 1st round bidding
To submit the bid evaluation report of ADB-101A
Completed BER submitted on 24 Jul 2019. ADB provided NOL for annulment of tender on 2 September 2019 and proposed cancellation of this
1.22.3
3.5
7.7
11.8 16.0
17.519.0
20.5 20.9 21.2 21.6
0.2 0.2 0.5 0.5
4.4
5.0 5.0
6.0 6.3
0.0
5.0
10.0
15.0
20.0
25.0
2019 Disbursements L3419($14.1 million through Dec 2018)
EA Projection Actual
0.1 0.1
1.4
2.8
4.1 4.1 4.1 4.1 4.1 4.1 4.1
-0.3 0.3 0.2 0.2 0.2
0.2 0.2 0.2
0
1
1
2
2
3
3
4
4
5
2019 Contract Awards L3419($50.1 million through Dec 2018)
EA Projection Actual
0.00.1
0.1
0.1
0.2
0.2 0.2 0.2 0.2 0.2 0.2 0.2
0.0 0.0
0.0 0.1
0.1
0.2 0.2
0.2
0.0
0.1
0.1
0.2
0.2
0.3
2019 Disbursements L3420($1.1 million through Dec 2018)
EA Projection Actual
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
-
0.1 0.1 0.1 0.1 0.1 0.1 0.1
0
0
0
0
0
0
0
2019 Contract Awards L3420($8.4 million through Dec 2018)
EA Projection Actual
75
Energy Sector
Loan 3419-PAK/ Loan 3420-PAK (COL): Second Power Transmission Enhancement Investment Program
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
Current Status
portion of loan or utilize the savings for other material/equipment to be purchased.
2. Rebidding of ADB-105 Lot 2 due to non-availability of land for Lalian substation
- To acquire the land of Lalian substation - To finalize rebidding mode and submit draft bidding documents of ADB-105 Lot 2
October 19 / NTDC
Still in process of land acquisition for Lalian.
3. Slow land acquisition for substation and compensation for ROW of transmission line significantly delayed project implementation
To fully functionalize the Directorate Land for centralizing land acquisition activities, finalize and adopt the standard operational procedure for right of way compensation
Immediate / NTDC
Ongoing.
H. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. Rebidding of ADB-105 Lot
2 due to non-availability of
land for Lalian substation
- To acquire the land of Lalian substation - To finalize rebidding mode and submit
draft bidding documents of ADB-105 Lot 2
October 19 / NTDC
2. Utilization of Savings To finalize variations of the on-going projects and calculate actual savings suggesting its utilization
15 Nov 2019 /
NTDC
76
Energy Sector
Loan 3476-PAK: Access to Clean Energy Investment Program
Loan 3476-PAK: Access to Clean Energy Investment Program A. Loan Basic Data $ Million
Approval Date
Signing Date
Effective Date
Closing Date
Closing Date (Revised)
Elapsed Time % Project
Rating as of
30 Sep 19
25-Nov-16 07-Feb-17 02-Mar-17 31-Dec-21 – 56 Approved Amount
Net Loan Amount
Financing EA/IA Project Officer
Project Analyst
325.00 325.00 OCR PEDO/ED E.Z. Khattak K.Shahzad Actual
Problem
B. Loan Financial Progress (As of 30 Sep 2019)
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
95.12 229.88 29 47.8 12.62
Disbursements (Cumulative)
Un-disbursed Loan Balance
Disbursement Performance %
Disbursements for 2019
EA’s Projections Actual
98.25 226.75 30 47.8 13.96
C. Project Description The proposed Asian Development (ADB) assistance will contribute to Pakistan's national goal of enhanced energy security. The program will be implemented over a period of 5-10 years and will support the provincial governments of Khyber Pakhtunkhwa (KPK) and Punjab (GoKPK and GoPb) to achieve increased access to sustainable and more reliable electricity services for vulnerable communities. This outcome will be achieved through four components: (i) expanding access to renewable energy, notably micro-hydropower (MHP) plants in rural off-grid areas of KPK, and decentralized solar plants for education and primary health care facilities (PHFs) in KPK and Punjab; (ii) providing women and girls with increased opportunities to obtain energy services and benefits; (iii) enhancing institutional capacity to foster sustainability; and (iv) promoting public sector energy efficiency in Punjab. D. Project Monitoring Framework (Current Status)
Outputs Performance Indicators Status with Key Activities
Renewable energy-based power plants installed
By 2021, power generation capacity from clean energy sources is increased by 182 MW. (DLI 2) (2016 baseline: 0 MW) By 2021, at least 26,587 sites have renewable energy-based power plants installed. (DLI 3) (2016 baseline: 0 installed)
Not due yet.
Opportunity for women and girls to obtain energy services and benefits increased
By 2021, girls’ schools account for at least 30% of schools with solar plant installed. (DLI 4) (2016 baseline: %, no school)
Not due yet.
77
Energy Sector
Loan 3476-PAK: Access to Clean Energy Investment Program
By 2021, households headed by women account for at least 7% of target households that are newly connected to electricity. (DLI 5) (2016 baseline: 0 households connected) By 2021, 500 PHFs used by women for delivery or antenatal care are equipped with solar plants. (2016 baseline: 0 facilities equipped) By 2021, 3,000 women are trained to equip them in using energy benefits. (2016 baseline: 0 women trained)
Institutional capacity to foster sustainability enhanced
By 2021, PEDO and EDP’s governance, financial management, and procurement functions are improved. (DLI 6) (2016 baseline: No dedicated procurement unit or internal audit function) By 2021, 100% of identified energy and finance department staff of both provinces are trained on technical issues, gender, project management, financial management, contract management, energy audit, environmental and social management, and climate risk management. (2016 baseline: 0 staff trained) Annual performance monitoring reports are produced on all indicators and PAP actions based on the internet-based PPMS starting in 2017. (DLI 7) (2016 baseline: no PPMS)
Not due yet.
Public sector energy efficiency promoted in Punjab
By 2019, energy audits are conducted on 100% of identified public sector buildings and a model net-zero energy building is constructed. (DLI 8) (2016 baseline: no energy audits, no net-zero energy building)
100% Energy Audits have been conducted. Land acquired for Energy building
78
Energy Sector
Loan 3476-PAK: Access to Clean Energy Investment Program
E. Cumulative Contract award and Disbursement Performance
F. Contract award and Disbursement Targets and Achievements in 2019
0.0
48.9 48.7 48.7
82.5 95.1
48.9 49.6 49.6
84.398.2
-
50
100
150
200
250
300
350
Jun-17 Dec-19
L 3476: Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Loan Amount: US$ 325.00 M
Clo
sin
g D
ate
: 31-D
ec-2
021
0.0 0.0 0.04.2
8.412.6 12.6
12.6 12.6
24.3
36.1
47.8
- - - 1.3 1.3
14.0 14.0 14.0 14.0
0.0
10.0
20.0
30.0
40.0
50.0
60.0
2019 Disbursements L3476($84.3 million through Dec 2018)
EA Projection Actual
0.0 0.04.2
8.412.6 12.6 12.6 12.6
24.3
36.1
47.8
- - - - -
12.6 12.6 12.6 12.6
0
10
20
30
40
50
60
2019 Contract Awards L3476($82.5 million through Dec 2018)
EA Projection Actual
79
Energy Sector
Loan 3476-PAK: Access to Clean Energy Investment Program
H. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
Current Status
1. Solarization of 5,000
schools and BHU’s
Bidding process to be
initiated
October 2019 /
EDP
Hiring of PMC in process
and will be completed by
Nov 2019. Bidding
process to be initiated in
Q1 2020.
2. Solarization of
Islamia university,
Bahawalpur
Load requirements are
to be finalized between
EDP and IUB for
initiating the
procurement process
August 2019 /
EDP
PMC to be hired in Q4
2020. MOU between
EDP and IUB almost
agreed and bidding
process to be initiated in
Q1 2020.
3. Hiring / Mobilization
of IVA by PEDO
Urgent evaluation and
approval for the
submitted bids
25 August 2019 /
PEDO
IVA hired in September
2019.
4. Construction of
remaining 674
MHPP
Finalize project
schedule and hire
consultants for
preparation of bidding
documents
31 August 2019 /
PEDO
Consultants hired in
September and bidding
will be initiated in
December
5. Solarization of
schools and BHUs
Finalize project
schedule and hire
consultants for
preparation of bidding
documents
31 August 2019 /
PEDO
Consultants hired and bid
submission date for
works is 24 Oct 2019
I. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. Disbursement against
results
Submission of Withdrawal Applications
with IVA report
31 October / EDP
2. Disbursement against
results
Submission of Withdrawal Applications
with IVA report
15 November /
PEDO
3. Approval of PC-1 EDP to expedite pending PC-1 for the
solarization of 4,200 schools and 2,400
primary healthcare facilities
31 December / EDP
80
Energy Sector
Loan 3577-PAK: MFF Power Transmission Enhancement Investment Program II 2
Loan 3577- PAK: MFF Power Transmission Enhancement Investment Program II T2
A. Loan Basic Data $ Million
Approval Date
Signing Date
Effective Date
Closing Date
Closing Date (Revised)
Elapsed Time % Project
Rating as of
30 Sep 19
29-Sep-2017 20-Mar-18 04-Apr-18 31-Dec-22 – 38 Approved Amount
Net Loan Amount
Financing EA/IA Project Officer
Project Analyst
260.00 260.00 OCR NTDC L. Zhang M. Tan Actual
Problem
B. Loan Financial Progress (As of 30 Sep 2019)
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
112.70 147.30 43 108.0 3.31
Disbursements (Cumulative)
Un-disbursed Loan Balance
Disbursement Performance %
Disbursements for 2019
EA’s Projections Actual
11.97 248.03 5 13.9 4.34
C. Project Description Tranche 2 will expand 220 kilovolts (kV) transmission system in Sindh and Balochistan provinces to remove transmission network bottlenecks in the system and to enable the network to handle the expected future loads. It will also adopt high level technology to upgrade supervisory control and data acquisition (SCADA) system cross the national grid to enable the transmission system operator, NTDC, to monitor and control the grid in real-time and prevent or reduce the duration of outages in the network, thus increase grid stability, reliability and resilience to accommodate more intermittent renewable energy. It will also feed computerized metering data complying with the Grid Code into the system for settlement (SFS) of the market operator, CPPA-G, to streamline revenue collection, billing and payment processes, and create a foundation for a future energy trading platform.
D. Project Monitoring Framework (Current Status)
Outputs Performance Indicators Status with Key Activities 1. 220kV transmission network augmented and expanded
1a. 660 km of new 220 kV transmission lines connecting Mirpur Khas New Substation, Hala Road Substation and T.M. Khan Substation (80 km), connecting Zhob Substation and D.I. Khan Substation (220 km), and connecting Guddu-Sikapur-Uchi-Sibbi (360 km) commissioned. (2016 baseline: 9,814 km of 220 kV transmission line) 1b. Additional 337 MW transmission capacity of Guddu-Sikapur-Uchi-Sibbi transmission line added. (2016 baseline: 337 MW transmission
Contracts of ADB 201 (220kV transmission lines, $113 million) were signed in Dec 2018. The contract of ADB-200 (220kV substations, Lot I-II, estimated cost of $26 million) will be awarded in Q4-2019 while the contract for ADB-201A (Plant of transmission line, $15 million), will be awarded in Q1 2020.
81
Energy Sector
Loan 3577-PAK: MFF Power Transmission Enhancement Investment Program II 2
capacity of existing Guddu-Sikapur-Uchi-Sibbi transmission line 1c. 820 MVA new substation capacity at Mirpur Khas New Substation (500 MVA) and Zhob Substation (320 MVA) commissioned. (2016 baseline: 24,063 MW of NTDC’s 220/132 kV grid stations) 2. 100% of transmission network covered by SCADA system (2016 baseline: less than 10% of total system covered)
2. SCADA/RMS system upgraded
2. 100% of transmission network covered by SCADA system (2016 baseline: less than 10% of total system covered)
Contract of ADB-202 (SCADA III) went for rebid (renamed as ADB-202R) and expected award is by Q2 2020.
E. Cumulative Contract Award and Disbursement Performance
0.0 0.0
113.2 112.7
0.0 0.17.6 12.0
-
50
100
150
200
250
300
Jun-18 Dec-18 Jun-19 Dec-19 Jun-20 Dec-20 Jun-21 Dec-21 Jun-22 Dec-22 Jun-23
L 3577: Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Loan Amount: US$ 260.00 M
Clo
sin
g D
ate
: 3
1-D
ec-2
02
2
82
Energy Sector
Loan 3577-PAK: MFF Power Transmission Enhancement Investment Program II 2
F. Contract Award and Disbursement Targets and Achievements in 2019
H. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
Current Status
1. Slow procurement for ADB-200, ADB-201A, and ADB-202
a) ADB 200; To sign contract of Lot 1 (Mirphur Khas) on or before 1 Aug 2019; to sign the contract for Lot 2 (Zhob substation and expansion of DI Khan substation) in Q3 2019; b) ADB-201A: To approve specification of U/G cable and glass insulators by NTDC’s Technical Committee in July 2019, and to issue the bidding documents for ADB 201A in July 2019 (DBD has been approved by ADB) c) ADB-202R: To submit the draft pre-bid meeting clarifications and draft amendment No 1 to bidding documents if applicable by 15 July 2019; to submit the TBER to ADB 40 days after bids closure
31 August 2019 / MPM 15 September / NTDC Technical Committee & MPM Prebid clarifications issued; TBER will be submitted to ADB by 15 October /MPM/PIU
a) Contract signing is expected in October 2019. b) Specifications yet approved, BD yet issued. c) Bid closing was extended to 16 Sept. TBER will be submitted to ADB by 30 Nov 2019.
2. Land acquisition for 220 kV Zhob substation
To acquire the land for Zhob substation in Q3 2019
Q3 2019/EHV2, ESIC
0.0 0.0 0.00.9
1.92.8 3.2 3.6 4.0
7.3
10.6
13.9
- - 0.2 0.2
4.0 4.0 4.0 4.0 4.3
0.0
2.0
4.0
6.0
8.0
10.0
12.0
14.0
16.0
2019 Disbursements L3577($7.6 million through Dec 2018)
EA Projection Actual
0.0 0.09.3
18.728.0 28.0 28.0 28.0
54.7
81.3
108.0
- - - - - - 3.3 3.3 3.3 0
20
40
60
80
100
120
2019 Contract Awards L3577($113.2 million through Dec 2018)
EA Projection Actual
83
Energy Sector
Loan 3577-PAK: MFF Power Transmission Enhancement Investment Program II 2
I. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. Slow procurement for
ADB-201A, and ADB-202R
Issuance of BD of ADB-201A after
NTDC’s Technical Committee’s approval
of U/G cable
Submission of TBER of ADB-202R
31 Oct 19/MPM
30 Nov 19/PMU
2. Slow contract awards Contract signing for ADB 200 (2 lots) 31 Oct 19/MPM
3. Slow implementation of
ADB 201 (Lots)
Contracts signed in Dec 2018, but only
advance payment paid.
Upon completion of detailed survey, LARP
should be finalized and implemented
immediately, before commencement of
civil works
4. Land acquisition for 220
kV Zhob substation
To acquire the land for Zhob substation in
Q3 2019
Dec 2019
84
Energy Sector
Loan 3677/Grant 0578-PAK: MFF Power Transmission Enhancement Investment Program II 3
Loan 3677/G0578 - PAK: MFF Power Transmission Enhancement Investment Program II T3
A. Loan Basic Data $ Million
Approval Date
Signing Date
Effective Date
Closing Date
Closing Date (Revised)
Elapsed Time % Project
Rating as of
30 Sep 19
28-Jun-2018 13 Dec-18 25-Feb-19 31-Dec-23 – 23 Approved Amount
Net Loan Amount
Financing EA/IA Project Officer
Project Analyst
280.00 4.00
280.00 4.00
OCR HLTF
NTDC K.Z. Khattak K. Shahzad Actual
Problem
B. Loan Financial Progress (As of 30 Sep 2019) Loan 3677
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
7.54 272.46 3 180.0 7.54
Disbursements (Cumulative)
Un-disbursed Loan Balance
Disbursement Performance %
Disbursements for 2019
EA’s Projections Actual
0.14 279.86 0 7.2 0.14
Grant 0578
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
0.00 4.00 0 3.2 0.00
Disbursements (Cumulative)
Un-disbursed Disbursement Performance %
Disbursements for 2019
Loan Balance EA’s Projections Actual
0.00 4.00 0 0.02 0.00
C. Project Description Tranche 3 will support the National Transmission & Despatch Company Limited (NTDC) in meeting the electricity demand of 1,150 MW efficiently and reliably at loan centers in Punjab Province by deploying high-level technologies and climate-change-resilient transmission systems. Tranche 3 will support installation of 500 kV substation in Lahore North, 500 kV switching station near Maira, 220 kV substation near Jauharabad, and 194 km of associated new transmission lines in Punjab and reconductoring of 44 km of transmission lines with high-temperature, low-sag (HTLS) conductors near Lahore. Tranche 3 will support the first large-scale grid-connected battery energy storage system (BESS) pilot project in Pakistan, which will provide subsecond frequency regulation. This pilot project will use wind power to help the NTDC comply with frequency requirements in the existing Grid Code and will supplement the functions of the supervisory-control and data-acquisition system being upgraded under Tranche 2. The BESS pilot project will recommend on the (i) revision of the Grid Code for better frequency compliance; and (ii) development of a commercial ancillary services market. Tranche 3 will promote the
85
Energy Sector
Loan 3677/Grant 0578-PAK: MFF Power Transmission Enhancement Investment Program II 3
deployment of HTLS conductors, which can operate at higher ambient temperatures within the required vertical clearance. Tranche 3 will also support the replacement of porcelain insulators with a fog-resistant type, such as glass or composite insulators, which are expected to perform better in heavily polluted areas. D. Project Monitoring Framework (Current Status)
Outputs Performance Indicators Status with Key Activities Transmission system capacity augmented and expanded
By 2023 1a. 150 km of new 500 kV transmission lines connecting Lahore North substation commissioned (2016 baseline: 5,17 km of 500 kV transmission line) 1b. 56 km of new 220 kV transmission lines associated Lahore North substation (44km) and Jauharabad substation (12 km) commissioned (2016 baseline: 9,814 km of 220 kV transmission line) 1c. 44 km of 220 kV transmission lines reconductored with HTLS conductors commissioned in Punjab (2016 baseline: 2 km of 220 kV transmission line of HTLS conductors in operation)
1d. 3,480 MVA new substation capacity at Lahore North substation (3,000 MVA) and Jauharabad substation (480 MVA) commissioned. (2016 baseline: 42,687 MW of NTDC’s grid stations)
1e. Installation of eight 500 kV line bays with four shunt reactors banks at Maira switching station, and replacement of transformer and shunt reactors at 2 substations 1f. NTDC PMU staff increased to 16, with 30% women (2017 baseline: 14 staff with 14% women)
-Tender ADB-301A is in evaluation stage. FBER with ADB and review of PC is ongoing. Issue NOL by 18 Oct 19. -Tender ADB-301B for Lahore North T/L (44km), contract signed, PCSS 0001 issued; Tender ADB-300C for T/L for Jauharabad (12km), IFB posted on 25 Sep 19 and bid opening on 6 Nov 19. - ADB-301C, to submit draft bidding documents to ADB after NTDC’s approval of U/G cable specification and finalization of route by 31 Oct 19.
- ADB-300A, bids opened on 25 April 19, to submit TBER to ADB by 31 Oct 19-Land acquisition issue also ongoing and SPF is in place to work out possible solution; ADB300C, IFB posted on 25 Sep 19 and bid opening on 6 Nov 19. -ADB-300B, Bids opened on 06 Aug 2019. -On-going.
Grid connected large scale battery energy storage system (BESS) installed
2a. 20MW/5MWh energy storage capacity added in NTDC system by 2023 (2016 baseline: 0) 2b. BESS O&M staff employed by 2019, with at least 3 women in technical positions
-not due yet. -consultant recruitment in process to start bidding process for BESS.
86
Energy Sector
Loan 3677/Grant 0578-PAK: MFF Power Transmission Enhancement Investment Program II 3
E. Cumulative Contract Award and Disbursement Performance Loan 3677
Grant: 0578
0.0 7.5
0.10.1 -
50
100
150
200
250
300
Jun-19 Dec-19 Jun-20 Dec-20 Jun-21 Dec-21 Jun-22 Dec-22 Jun-23 Dec-23 Jun-24
L 3677: Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Loan Amount: US$ 280.00 M
Clo
sin
g D
ate
: 31-D
ec-2
023
0.0 0.0
0.00.0 -
1
1
2
2
3
3
4
4
5
Jun-19 Dec-19 Jun-20 Dec-20 Jun-21 Dec-21 Jun-22 Dec-22 Jun-23 Dec-23 Jun-24
G 0578: Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Loan Amount: US$ 4.00 M
Clo
sin
g D
ate:
31-
Dec
-202
3
87
Energy Sector
Loan 3677/Grant 0578-PAK: MFF Power Transmission Enhancement Investment Program II 3
F. Contract Award and Disbursement Targets and Achievements in 2019 Loan 3677
Grant 0578
H. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date /
By Whom
Current Status
1. Land acquisition of Lahore North (ADB-300A)
Finalize the land acquisition process in light of report issued by ADB’s SPF and shared with NTDC on 12 Jul 19.
Oct 19/NTDC/EHV-I
SPF is in place to work out possible solution.
0.0 0.0 0.0 0.0 0.1 0.1 0.1 0.1 0.1
2.5
4.8
7.2
- - - - -
0.1
0.1 0.1 0.1 0.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
2019 Disbursements L3677($0.0 million through Dec 2018)
Projected Actual
0.0 0.0 6.2 12.3 18.5
39.5
60.5
81.5
114.3
147.2
180.0
- - - - - - - -
7.5
0
20
40
60
80
100
120
140
160
180
200
2019 Contract Awards L3677($0.0 million through Dec 2018)
Projected Actual
0.0 0.0 0.0
0.0
0.0
0.0 0.0 0.0 0.0 0.0 0.0 0.0
- - - - -
-
- - -0.0
0.0
0.0
0.0
0.0
0.0
2019 Disbursements G0578($0.0 million through Dec 2018)
Projected Actual
0.0 0.0 0.1 0.1 0.2 0.2 0.2 0.2
1.2
2.2
3.2
- - - - - - - - -
0
1
1
2
2
3
3
4
2019 Contract Awards G0578($0.0 million through Dec 2018)
Projected Actual
88
Energy Sector
Loan 3677/Grant 0578-PAK: MFF Power Transmission Enhancement Investment Program II 3
Sr.
No
Issue Action to be Taken Due Date /
By Whom
Current Status
2. Consultant recruitment for ADB-302 (Battery Storage project) under HLTF Grant
NTDC to finalize the TOR and re-issue EOI for consultant recruitment as procurement process is to be initiated by selected consultants
Sep 19/NTDC PMU
On 25 July, EA requested ADB’s assistance in recruiting the consultants (3 individuals) for BESS. ADB approved EA’s request on 8 Aug, and completed shortlisting and prepared draft contracts on 28 Aug. Upon EA’s BOD approval, the contracts will be signed and consultants will be mobilized in Q4 2019.
3. Slow land acquisition
To timely acquire the land for 500 kV Lahore North substation, 500 kV Maira switching station, and 220 kV Jauharabad substation, avoiding the issues encountered by Lalian substation project
Q4 2019/EHV1
I. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. Consultant recruitment for
ADB-302 (Battery Storage
project) under HLTF Grant
NTDC to sign the contract with selected
consultants as procurement process is to
be initiated by selected consultants
Q4 2019 / NTDC
PMU
2. Slow land acquisition To timely acquire the land for 500 kV
Lahore North substation, 500 kV Maira
switching station, and 220 kV Jauharabad
substation, avoiding the issues
encountered by Lalian substation project
Q4 2019/NTDC
3 Contract Awards To provided ADB with signed contracts for
ADB 300D, ADB 301E and ADB 301A
30 November /
NTDC
89
Energy Sector
TA 9185-PAK: Hydropower Development Investment Program (Supplementary)
TA 9185-PAK: Hydropower Development Investment Program (Supplementary)
A. TA Basic Data US$ (Thousand)
Approval Date
Signing Date
Closing Date
Closing Date
(Revised)
Time Elapse
%
Contract Award
(Cumulative)
Disbursements (Cumulative)
29-Sep-16 21-Oct-16 31-May-18 31-Dec-19 92 2,797.22 2,016.52 Approved Amount
Net Amount Financing Project Officer
Project Analyst
Counterpart Agencies
2,800.00 2,800.00 TASF A. Tareen E. Webb Pakhtunkhwa Energy
Development Organization
B. TA Description The project preparatory technical assistance (PPTA) is necessary to: (i) review the technical, economic and financial viability of the sub-projects and ascertain the project rationale, scope, cost, schedule, implementation arrangements, risks and mitigation measures; (ii) ensure the compliance with ADB’s Safeguard Policy Statement (2009) and identify mitigation measures; and (iii) assist the project executing agency in the IPP solicitation and selection process, PC-I approval and procurement of contractor and project implementation consultant. C. Cumulative Contract Award and Disbursement Performance
- -
1343
2338 2364 2364
2783 2798 2798
- -
133248
403
911
1149
1347
2017
-
300
600
900
1,200
1,500
1,800
2,100
2,400
2,700
3,000
Jun-16 Sep-16Dec-16Mar-17 Jun-17 Sep-17Dec-17Mar-18 Jun-18 Sep-18Dec-18Mar-19 Jun-19 Sep-19Dec-19Mar-20
(Th -
$)
TA 9185: Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Clo
sin
g: 3
1 D
ec 2
01
9
Net TA amount: $ 2,800 (Th)
90
Energy Sector
TA 9185-PAK: Hydropower Development Investment Program (Supplementary)
D. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No issues
E. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No issues
91
Energy Sector
TA 9247-PAK: Access to Clean Energy Investment Program
TA 9247-PAK: Access to Clean Energy Investment Program
A. TA Basic Data US$ (Thousand)
Approval Date
Signing Date
Closing Date
Closing Date
(Revised)
Time Elapse
%
Contract Award
(Cumulative)
Disbursements (Cumulative)
25-Nov-16 23-Dec-16 31-Dec-21 56 - - Approved Amount
Net Amount Financing Project Officer
Project Analyst
Counterpart Agencies
750.00 750.00 TASF E. Khattak K.
Shahzad KPK Energy Development Org. Energy Department, GoPunjab
B. TA Description The proposed Asian Development (ADB) assistance will contribute to Pakistan's national goal of enhanced energy security. The program will be implemented over a period of 5-10 years and will support the provincial governments of Khyber Pakhtunkhwa (KPK) and Punjab (GoKPK and GoPb) to achieve increased access to sustainable and more reliable electricity services for vulnerable communities. This outcome will be achieved through four components: (i) expanding access to renewable energy, notably micro-hydropower (MHP) plants in rural off-grid areas of KPK, and decentralized solar plants for education and primary health care facilities (PHFs) in KPK and Punjab; (ii) providing women and girls with increased opportunities to obtain energy services and benefits; (iii) enhancing institutional capacity to foster sustainability; and (iv) promoting public sector energy efficiency in Punjab.
C. Project Monitoring Framework (Current Status)
Outputs Performance Indicators Status with Key Activities Monitoring and evaluation system for program indicators improved. Safeguards management for the program improved. Ensuring quality of third-party disbursement-linked indictor verification.
Capacity of executing and implementing agencies developed in tracking the program DMF indicators and DLIs, program action plan, and compliance with the RBL program agreement. Capacity of executing and implementing agencies developed in complying with the program safeguards requirements. Sampling and cross-verification of DLIs and results of sampled sites done.
This TA is attached to our loan L-3476 against a Result Based Lending Project. the EA’s have failed to achieve any substantial progress in the first two years of loan effectiveness (2 March 2017, the loan become effective). The first disbursement against a DLI related to actual construction works (solarization of schools / mini hydro power plants) happened on 28 Sepe 2019. The technical / social safeguards expert for assessment of IVA report expected to be submitted by KP government in November 2019.
92
Energy Sector
TA 9247-PAK: Access to Clean Energy Investment Program
D. Cumulative Contract Award and Disbursement Performance
E. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. Please refer to loan 3476-
PAK
G. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. Please refer to loan 3476-
PAK
0 0 0 0 0 0 0 0
-
150
300
450
600
750
Dec-16 Jun-17 Dec-17 Jun-18 Dec-18 Jun-19 Dec-19 Jun-20 Dec-20 Jun-21 Dec-21
(Th -
$)
TA 9247: Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Clo
sin
g: 3
1D
ec 2
02
1
Net TA amount: $ 750 (Th)
93
Energy Sector
TA 9357-PAK: Update on Energy Sector Plan
TA 9357-PAK: Update on Energy Sector Plan
A. TA Basic Data US$ (Thousand)
Approval Date
Signing Date
Closing Date
Closing Date
(Revised)
Time Elapse
%
Contract Award
(Cumulative)
Disbursements (Cumulative)
21-Aug-17 12-Sep-17 15-May-18 31-Dec-19 89 624.38 463.86 Approved Amount
Net Amount Financing Project Officer
Project Analyst
Counterpart Agencies
1,050.00 1,050.00 TASF A. Aleem E.C.Webb EAD
B. TA Description The proposed knowledge and support technical assistance (TA) will assess the progress made during 2010-2016 on the recommendations of the Integrated Energy Sector Recovery Report of the Friends of Democratic Pakistan (FODP), analyze the lessons learned from the changing global realities, and propose recommendations as inputs for a new energy policy for the medium term (2018-2023). The findings will be designed to inform the Government of Pakistan on past progress and provide options for the future energy strategy of the country. The Asian Development Bank (ADB) is the lead and anchor development partner of the Government of Pakistan in the energy sector with an ongoing portfolio of $2.8 billion in investments in energy generation, transmission, distribution, energy efficiency, renewable energy development, and analytical and advisory assistance. The TA is consistent with ADB's country partnership strategy for Pakistan, 2015-2019 and is included in ADB's current country operations business plan, 2018-2020 for Pakistan. C. Project Monitoring Framework (Current Status)
Outputs Performance Indicators Status with Key Activities 1. Key energy sector analyses and recommendations for 2018–2023 prepared
By December 2019: 1a. Electricity subsector progress assessment and lessons learned during 2010–2018 are developed. (2017 baseline: not applicable) 1b. Gas subsector progress assessment and lessons learned during 2010–2018 are developed. (2017 baseline: not applicable 1c. New energy sector recommendations based on progress during 2010–2018 are developed. (2017 baseline: not applicable)
Consultants have been fielded since 1 November 2017. Inception report was finalized on 30 November2017 and diagnostic report has been shared with all stakeholders. Reports are being revised as per additional scope of the TA Government has requested to increase scope of the KSTA by adding formulation of energy and electricity plan for approval by CCI by end April 2018. Additional $300,000 in the TA approved. All targets will be achieved, as scheduled.
94
Energy Sector
TA 9357-PAK: Update on Energy Sector Plan
2. Stakeholder views on progress during 2013–2017 collected.
3. Electricity Policy (2018-2023) formulated
4. Electricity Plan developed to implement Electricity Policy
5. Support to Prime Minister’s Energy Task Force
6.Preparation of PBL (Energy Sector Resilience Program)
2a. At least one stakeholder coordination meeting on the report is convened by March 2018.
3a. Policy recommendation are approved by the government by 30 Sepe 2019.
4a. Sector entities begin implementation of Electricity Plan by January 2020. 5a. Sectoral experts are recruited to guide Task Force activities by December 2018.
3 Meetings conducted On track. Ongoing. Under process. Recruitment completed 1st subprogram expected to be approved in Q4 2019, consultants are assisting ABD in finalizing the policy matrix and program documentation for board approval.
D. Cumulative Contract Award and Disbursement Performance
- -
214
361
474
624 624
- -28
234 371
437 464
-
100
200
300
400
500
600
700
800
900
1,000
1,100
1,200
Jun-17 Sep-17 Dec-17 Mar-18 Jun-18 Sep-18 Dec-18 Mar-19 Jun-19 Sep-19 Dec-19 Mar-20
(Th -
$)
TA 9357: Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Clo
sin
g: 3
1 D
ec 2
01
9
Net TA amount: $ 1050 (Th)
95
Energy Sector
TA 9357-PAK: Update on Energy Sector Plan
E. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
Current Status
1. Preparation of policy-based lending in energy sector for the new government
Consultants are on board for the preparation of the document.
Q4 2019 Under preparation
F. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No issues
96
Energy Sector
TA 9672-PAK: Developing an Electricity Market
TA 9672-PAK: Developing an Electricity Market
A. TA Basic Data US$ (Thousand)
Approval Date
Signing Date
Closing Date
Closing Date
(Revised)
Time Elapse
%
Contract Award
(Cumulative)
Disbursements (Cumulative)
7-Dec-18 31-Dec-18 31-Jul-21 - 31 597.93 150.71 Approved Amount
Net Amount Financing Project Officer
Project Analyst
Counterpart Agencies
700.00 700.00 TASF Y.Inoue I.Borcena Central Power Purchasing
Agency
B. TA Description This knowledge and support technical assistance (TA) will support the introduction of market mechanisms of electricity sales and purchases in Pakistan based on the competitive trading bilateral contract model (CTBCM), developed by the predecessor TA, TA 8772-PAK. The introduction of competition in the electricity subsector will be the foundation of the sectors financial sustainability in the long-run through mechanisms that remain effective even through political changes. This TA is included in the Country Operations Business Plan 2019-2021.
C. Project Monitoring Framework (Current Status) Outputs Performance Indicators Status with Key
Activities 1. Key competitive market regulations developed
1a. Market development roadmap finalized by 2020 (2018 baseline: N/A) 1b. Updated commercial code for CTBCM is finalized by 2020 (2018 baseline: N/A)
Draft inception report by the consultants have been submitted and being reviewed.
2. Human resource capacity for implementing the new market design strengthened
2a. Market simulation methodology and processes developed by 2020 (2018 baseline: N/A) 2b. At least 4 employees are certified within CPPA-G as trainers on market modeling by 2020. (2018 baseline: 0) 2c. Business processes for CTBCM implementation developed by 2020 (2018 baseline: N/A)
(same as above)
3. Coordination capacity of CPPA-G improved
3a. Market Implementation Monitoring Group established by 2019 (2018 baseline: N/A) 3b. Subcommittees addressing identified key issues established by 2019 (2018 baseline: N/A) 3c. Standard operating procedures for coordination activities developed by 2019 (2018 baseline: N/A)
(same as above)
97
Energy Sector
TA 9672-PAK: Developing an Electricity Market
D. Cumulative Contract Award and Disbursement Performance
E. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No issues
F. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No issues
-- -
597 598
-- -
50
151
-
100
200
300
400
500
600
700
800
Dec-18 Mar-19 Jun-19 Sep-19 Dec-19 Mar-20 Jun-20 Sep-20 Dec-20 Mar-21 Jun-21 Sep-21
(Th -
$)
TA 9672 :Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Clo
sin
g: 3
1 J
ul
20
21
Net TA amount: $ 700 (Th)
98
Energy Sector
TA 9756-PAK: Preparing Sustainable Energy Projects
TA 9674-PAK: Preparing Lower Palas Hydropower Project
A. TA Basic Data US$ (Thousand)
Approval Date
Signing Date
Closing Date
Closing Date
(Revised)
Time Elapse
%
Contract Award
(Cumulative)
Disbursements (Cumulative)
7-Dec-18 7-Dec-18 30-Jun-19 145 - - Approved Amount
Net Amount Financing Project Officer
Project Analyst
Counterpart Agencies
225.00 225.00 TASF A. Aleem I.Borcena Water and Power Developing
Authority
B. TA Description The proposed transaction TA will initiate due diligence and update the feasibility study for a medium-sized run of river Lower Palas Hydropower Project (665-MW). The proposed TA will review the existing documentation and commence preparation of the project for ADB’s consideration in 2019. The TA will be complemented by a supplemental transaction TA to be approved in early 2019, which will pick up and conclude the remaining project preparatory work for ADB to consider and lead financing of this as well as one additional hydropower project (Patan Hydropower Development Project 2400-MW).
C. Project Monitoring Framework (Current Status)
Outputs Performance Indicators Status with Key Activities 1. Preparation of Project Engineering Design and Cost Estimates
1.1 Review of feasibility study report 1.2 Technical due diligence, scope, design, specifications, schedules and cost estimates 1.3 Updated feasibility study report 1.4 Climate change and vulnerability assessment 1.5 Preparation of PC 1 documents
No activity initiated under TA, the TA might be closed
2. Update Environment Impact Assessment and Resettlement Plan
2.1 Update and finalize Social and Environment Safeguards Reports per ADB guidelines
No activity initiated under TA, the TA might be closed
3. Preparation of Project Economic and Financial Analysis and Financial Management Assessment of WAPDA
3.1 Undertake project economic and financial analysis per ADB guidelines 3.2 Calculate willingness to pay, least cost analysis, and long run marginal cost 3.3 Finalize financial management assessment
No activity initiated under TA, the TA might be closed
4. Assessment of project financing structure and cofinancing options
3.1 Report on meetings with commercial cofinanciers, provision of guarantees and availability of counterpart financing for the projects.
No activity initiated under TA, the TA might be closed
5. Draft bidding documents
5.1 Preparatory Works for Procurement including formulation of specifications and bidding documents for turnkey contract 5.2 Prepare specifications and market research report for tunnel boring machines
No activity initiated under TA, the TA might be closed
99
Energy Sector
TA 9756-PAK: Preparing Sustainable Energy Projects
D. Cumulative Contract Award and Disbursement Performance
E. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No Issues
F. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No Issues
- -- - 0- -
-
- 0
-
50
100
150
200
250
Dec-18 Feb-19 Apr-19 Jun-19 Aug-19
(Th -
$)
TA 9674: Contract Award and Disbursement Performance to Date
Contract Awards DisbursementsC
losi
ng
: 30 J
un
2019
Net TA amount: $ 225 (Th)
100
Energy Sector
TA 9756-PAK: Preparing Sustainable Energy Projects
TA 9756-PAK: Preparing Sustainable Energy Projects
A. TA Basic Data US$ (Thousand)
Approval Date
Signing Date
Closing Date
Closing Date
(Revised)
Time Elapse
%
Contract Award
(Cumulative)
Disbursements (Cumulative)
28-Jun-19 26-Jul-19 30-Jun-21 13 - - Approved Amount
Net Amount Financing Project Officer
Project Analyst
Counterpart Agencies
2,500.00 2,500.00 TASF A. Aleem I. Borcena Ministry of Finance & Ministry
of Water
B. TA Description The Asian Development Bank (ADB), as the anchor development partner of the Government of Pakistan in the energy sector, leads development coordination and has provided assistance in energy generation, transmission, distribution, energy efficiency, renewable energy development, hydrocarbons (regional gas interconnection), and analytical and advisory assistance. The transaction TA facility (F-TRTA) will provide preparation support to a series of ensuing policy-based loans and investment lending projects, comprising (i) Energy Sector Resilience Program (subprograms 1, 2, and 3 amounting to $1 billion); (ii) Hydropower Development Project ($350 million); (iii) Power Transmission Strengthening multitranche financing facility ($800 million); (iv) Second Power Distribution Enhancement Investment Program tranche 2 ($300 million) and (v) Gas Sector Development Project ($150 million). In addition, funds will be provisioned for capacity support on energy policy advice, scope and sequencing of sector reforms and multiple analytical assessments to complement the proposed projects. All ensuing energy projects require preparation, due diligence, design, and readiness activities, which will be undertaken under this TA facility, thereby reducing transaction costs. This F-TRTA is listed in the 2019 pipeline in the approved country operations and business plan (COBP), 2019-2021 for Pakistan.
101
Energy Sector
TA 9756-PAK: Preparing Sustainable Energy Projects
C. Cumulative Contract Award and Disbursement Performance
D. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No Issues
- -0 0 0
0 00
-
500
1,000
1,500
2,000
2,500
3,000
Dec-18 Jun-19 Dec-19 Jun-20 Dec-20 Jun-21 Dec-21
(Th -
$)
TA 9756: Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Clo
sin
g: 3
0 J
un
20
21
Net TA amount: $ 2,500 (Th)
102
III. TRANSPORT SECTOR PROJECTS Loans 1. Loan 3134/G0451-PAK: National Highway Network Development in Balochistan
2. Loan 3300/G0440-PAK: National Motorway M-4 Gojra-Shorkot Section II Project
3. Loan 3395/G0482/8308(AIIB)-PAK: National Motorway M-4 Shorkot-Khanewal Section III Project
4. Loan 3305-PAK: Sindh Provincial Road Improvement Project
5. Loan 3344/3345-PAK: CAREC Regional Improving Border Services Project
6. Loan 3378-PAK: Post-Flood National Highways Rehabilitation Project.
7. Loan 3264-PAK: Flood Emergency Reconstruction and Resilience Project
8. Loan 3574-PAK: Central Asia Regional Economic Corridor Development Investment Program T1
9. Loan 3601-PAK/Loan 3602-PAK(COL): Khyber Pakhtunkhwa Provincial Roads Improvement Project
10. Loan 3756-PAK: Khyber Pakhtunkhwa Provincial Roads Improvement Project- Additional Financing
Technical Assistance (TAs)
1. TA-8990-Pak: Enabling Economic Corridors through Sustainable Transport Sector Development
2. TA 8912-PAK: Capacity Building of Institutions Handling Disasters
3. TA 9153-PAK: Central Asia Regional Economic Cooperation Railway Connectivity Investment Program
103
Transport Sector
Loan 3134/G0451-PAK: National Motorway M-4 Gojra-Shorkot Section II Project
Loan 3134/G-0451-PAK: National Highway Network Development in Balochistan
A. Loan Basic Data $ Million
Approval Date
Signing Date
Effective Date
Closing Date
Closing Date (Revised)
Elapsed Time % Project
Rating as of
30 Sep 19
L: 27-Jun-14 G:03-Nov-15
12-May-15 14-Jan-16
10 Aug 15 02-Feb-16
31-Dec-18 31-Dec-18
15-Jan-20 95 93
Approved Amount
Net Loan Amount
Financing EA/IA Project Officer
Project Analyst
122.60 72.40
122.60 72.40
OCR DFID Grant
NHA K. Ghafoor M. Irfan On Track
B. Loan Financial Progress (As of 30 Sep 2019) Loan - 3134-PAK
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
89.58 33.02 73 0.00 0.00
Disbursements (Cumulative)
Un-disbursed Disbursement Performance %
EA’s Disbursements for 2019
Loan Balance EA’s Projections Actual
83.97 38.63 68 13.9 1.91
Grant - 0451-PAK
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
64.95 7.45 90 0.00 0.00
Disbursements (Cumulative)
Un-disbursed Disbursement Performance %
Disbursements for 2019
Loan Balance EA’s Projections Actual
57.20 15.20 79 12.22 15.31
C. Project Description 1. The project will rehabilitate 79 km of the existing two-lane road of Zhob–Mughal Kot (N50) and 128 km of the existing two-lane road of Qila Saifullah – Waghum (N70) in Balochistan of Pakistan. 2. The impact will be accessible, affordable, and safe road network in Balochistan and the outcome will be reduced transport cost from Balochistan to the political and industrial centers of the country
104
Transport Sector
Loan 3134/G0451-PAK: National Motorway M-4 Gojra-Shorkot Section II Project
D. Project Monitoring Framework (Current Status)
Outputs Status with Key Activities
Two-lane roads of Zhob-Mughal Kot and Qila Saifullah – Waghum Rud rehabilitated
Target Indicators Achievements/Status Total of 201 km roads rehabilitated by 2018 with IRI no higher than 4 (Zhob- Mughal Kot = 81 km and Qila-Saifullah-Waghum Rud = 120 km)
• N50-I: Progress of works 98% achieved vs. 100 % planned.
• N50-II: Progress of works 93% achieved vs 100% planned.
• N-70-I: Progress of works 91.4% achieved vs 100% planned.
• N70-II: Progress of works 95.05 % achieved vs 100% planned.
• The project is expected to complete
within the (extended) loan closing date.
Community facilitation centers integrated into the improved mobility through rehabilitated project roads
5 community facilitation centers developed along the project roads by 2018
• Site for CFCs have been identified and handed over to NHA for construction.
Procurement process is significantly delayed due to revision required in the PC-1 of the project, currently pending at NHA.
E. Cumulative Contract Award and Disbursement Performance
0.0
143.0 149.3 149.3 151.1 151.1 151.1 152.9 152.9 154.5
0.2 0.1
28.6
49.7
87.3
115.2 119.0124.0
133.4141.2
-
50
100
150
200
250
Dec-15 Jun-16 Dec-16 Jun-17 Dec-17 Jun-18 Dec-18 Jun-19 Dec-19 Jun-20
L 3134-G0451: Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Loan Amount: US$ 195.00 M
Clo
sin
g D
ate
: 1
5-J
an-2
02
0
105
Transport Sector
Loan 3134/G0451-PAK: National Motorway M-4 Gojra-Shorkot Section II Project
F. Contract Award and Disbursement Targets and Achievements in 2019
G. Status of the Action Plan discussed in 2nd TPR
Sr. No
Issue Action to be Taken Due Date / By Whom
Current Status
1. Approval of Variation Order for N50-II and revision of PC-1 for Community Facilitation Centres.
NHA needs to expedite (i) the approval process and submit the VO for N50-II to ADB for its occurrence; and (ii) revise the PC-1 for its onward submission to Ministry of Planning, Development and Reforms (MPD&R).
10 Sep 2019 / NHA
• Variation order has been
approved.
• Revision of PC-1 for
CFCs is pending at NHA.
2. Approval of Addendum-5 and 6 of Supervision Consultant firm by NHA.
NHA to expedite the approval of Addendums.
31 Aug 2019/ NHA
Still pending at NHA.
3. Pending decision on execution of CFC component
NHA to decide way forward to complete the CFC component within the loan closing period
31 Aug 2019/ NHA
NHA will prepare a separate PC-1 for its approval by competent authorities.
4. Launching of cracked girders, Health and Safety Issue
NHA to (i) cordon off the bridge sites and isolate the work zone; (ii) conduct third party independent assessment for the integrity of the cracked girders (as already directed by the Chairman NHA on 19 October 2018); (iii) submit the assessment report to ADB; and (iv) suspend the works on bridge sites
31 Aug 2019/ NHA
The issue has been resolved.
0.0 0.0 0.0
2.8
5.6
8.4
11.1
13.9
16.7
19.9
23.0
26.1
- -0.3 0.3 1.6
9.5
14.0
17.2
17.2
0.0
5.0
10.0
15.0
20.0
25.0
30.0
2019 Disbursements L3134($123.9 million through Dec 2018)
EA Projection Actual
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
- - - - - - - - -0
0
0
0
0
1
1
1
1
1
1
2019 Contract Awards L3134($152.9 million through Dec 2018)
EA Projection Actual
106
Transport Sector
Loan 3134/G0451-PAK: National Motorway M-4 Gojra-Shorkot Section II Project
till the completion and acceptance of the assessment report by NHA and the ADB. NHA to ensure that the remedies and the recommendations of the third-party evaluation are compiled to.
5. Withdrawal of security personnel (Frontier Constabulary) from the project sites
Owing to high security risk area, safety of project site, contractors camp, project staff, and equipment must be given priority, hence NHA must take measures to avoid any untoward situation.
31 Aug 2019/ NHA
The issue is currently under discussion at NHA.
6. Pending approval of Extension of Time (EoT) for all lots.
NHA to expedite the approval of EoTs and submit to ADB for approval.
31 Aug 2019/ NHA
EoTs have been approved by NHA.
7. Processing and issuance of Taking Over Certificates (ToC).
NHA to process and issue the ToC for the remaining completed sections and lots, so that retention monies could be paid to the contractors.
10 Sep 2019/ NHA
This is currently under processing at NHA.
H. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. Approval of Addendum-5
and 6 of Supervision
Consultant firm by NHA.
NHA to expedite the approval of
Addendums.
Immediate
2. Revision of PC-1 for
Community Facilitation
Centres.
NHA to prepare a separate PC-1 for its
onward submission to Ministry of
Communications (MoC) and Ministry of
Planning, Development and Reforms
(MPD&R).
Immediate
3. Withdrawal of security
personnel (Frontier
Constabulary) from the
project sites
Owing to high security risk area, safety of
project site, contractors camp, project staff,
and equipment must be given priority,
hence NHA must take measures to avoid
any untoward situation.
Immediate
4. Processing and issuance of
Taking Over Certificates
(ToC).
NHA to process and issue the ToC for the
remaining completed sections and lots, so
that retention monies could be paid to the
contractors.
Immediate
107
Transport Sector
Loan 3300/G0440-PAK: National Motorway M-4 Gojra-Shorkot Section II Project
Loan 3300/G0440-PAK: National Motorway M-4 Gojra-Shorkot Section II Project
A. Loan Basic Data $ Million
Approval Date
Signing Date
Effective Date
Closing Date
Closing Date
(Revised)
Elapsed Time % Project
Rating as of
30 Sep 19
L: 30-Sep-15 G: 30-Sep-15
22-Oct-15 22-Oct-15
17-Dec-15 17-Dec-15
31-May-20 31-May-20
L: 86 G: 86
Approved Amount
Net Loan Amount
Financing EA/IA Project Officer
Project Analyst
178.00 92.00
178.00 92.00
OCR DFID Grant
NHA K.Ghafoor B. Paracha Potential Problem
B. Loan Financial Progress (As of 30 Sep 2019) Loan-3300-PAK
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
107.44 70.56 60 0.00 0.00
Disbursements (Cumulative)
Un-disbursed Disbursement Performance %
Disbursements for 2018
Loan Balance Projections Actual
98.44 79.56 55 11.6 1.67
Grant Financial Progress Grant 0440-PAK
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
67.76 24.24 74 0.00 0.00
Disbursements (Cumulative)
Un-disbursed Disbursement Performance %
Disbursements for 2019
Loan Balance EA’s Projections Actual
64.68 27.32 70 6.8 7.92
C. Project Description 1. The motorway M-4, connecting Faisalabad with Multan, will be a part of the north-south transport corridor. Its area of influence, which includes Faisalabad, Multan, and the entire Punjab Province, accounts for about 56% of the country's population and for 59% of the country's GDP. The M-4 will extend the already completed M-1, M-2, and M-3 motorways southward and shorten the distance between Multan and the twin cities of Islamabad and Rawalpindi in the north. The Faisalabad-Gojra section (58 km) of the M-4 was completed in 2014 under Asian Development Bank (ADB) financing, and the Khanewal-Multan section (57 km) completed in 2015 under financing from the Islamic Development Bank.
108
Transport Sector
Loan 3300/G0440-PAK: National Motorway M-4 Gojra-Shorkot Section II Project
2. The project will construct a 62-kilometer (km) four-lane, access-controlled motorway connecting Gojra and Shorkot in Punjab Province, and improve the institutional capacity of the National Highway Authority (NHA), particularly for managing safeguards and contracts. Achievement of the project’s full benefits will depend on the completion of the remaining 64 km Shorkot-Khanewal section financed by ADB, AIIB and DFID, which is currently at advanced stage of implementation. Upon completion, the new M-4 will provide a four-lane, access-controlled alternative to the existing narrow and congested routes, notably in the heavily trafficked Faisalabad and Khanewal-Multan-Muzaffargarh areas. This will facilitate north-south connectivity, improve quality and efficiency of road transport services, and promote inclusive economic growth. D. Project Monitoring Framework (Current Status)
Outputs Status with Key Activities
62 km of four-lane, access-controlled motorway connecting Gojra and Shorkot constructed and operational
Target Indicators Achievements/Status 62 km road section constructed to 120 km/hour design standard
Sections IIA and IIB have been completed and open to traffic.
11 km expressway connecting Sarai Saleh and Havelian constructed
11 km expressway constructed with pavement international roughness index of less than 2 m/km.
The project is near completion. NHA’s project team confirmed that the project would be opened to traffic by October 2019.
Safeguard and contract administration capacity of the NHA strengthened
Project environment and social safeguard requirements implemented with good quality
Ongoing process.
Contract management and execution carried out effectively without undue delay and unresolved disputes.
So far, no unresolved contractual dispute has been reported.
109
Transport Sector
Loan 3300/G0440-PAK: National Motorway M-4 Gojra-Shorkot Section II Project
E. Cumulative Contract Award and Disbursement Performance
F. Contract Award and Disbursement Targets and Achievements in 2019
12
34
56
8
11
13
15
17
18
0 0 0
2 2
8 810
10
0.0
2.0
4.0
6.0
8.0
10.0
12.0
14.0
16.0
18.0
20.0
2019 Disbursements L3300($153.5 million through Dec 2018)
EA Projection Actual
0 0 0 0 0 0 0 0 0 0 0
- - - - - - - - -
0
0
0
0
0
1
1
1
1
1
1
2019 Contract Awards L3300($175.3 million through Dec 2018)
EA Projection Actual
154.0 159.0 159.0 159.1 154.8 154.8 170.0
175.3 175.3 175.3
0.0
15.2
44.4
59.872.5
119.7
141.4153.5
162.0 163.1
-
50
100
150
200
250
300
Dec-15 Jun-16 Dec-16 Jun-17 Dec-17 Jun-18 Dec-18 Jun-19 Dec-19 Jun-20 Dec-20
L 3300-G0440 :Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Loan Amount: US$ 270.00 M
Clo
sin
g D
ate
: 3
1-M
ay-2
02
0
110
Transport Sector
Loan 3300/G0440-PAK: National Motorway M-4 Gojra-Shorkot Section II Project
G. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
Current Status
A. Loan
3300/Grant
0440-PAK:
M4 Sections
IIA and IIB
1. Proposal for
utilization of
surplus loan
proceeds.
NHA through MoC to
expedite the request for
cancellation from EAD.
Immediate/NHA/MoC/EAD ADB on the request of
Government has
approved the request.
2. Approval of
Addendum
No. 9 of
Construction
Supervision
Consultant.
NHA to expedite the
approval process.
Immediate/NHA Pending at NHA.
3. Outstanding
balance
payments to
M/s. IDC
NHA to expedite the
arrangement and process
the balance payments
from GoP resources.
Immediate/NHA Currently under
discussion at NHA.
4. Issuance of
Taking Over
Certificate
(ToC) by
NHA for the
completed
sections
which are
opened to
traffic.
NHA shall complete the
required process to issue
the ToCs and process the
retention monies as per
the Contract. ToCs shall
also be shared with ADB.
Immediate/NHA
Currently under
processing at NHA.
5. Resolution of
pending
complaints.
NHA’s project team to
assist in resolution of
complaints related to the
project, including those
related to Borrow Area
restoration, payment to
vendors, suppliers, sub-
contractors, etc.
Immediate/NHA
Under resolution
through NHA’s project
team.
B. Loan
3300/Grant
0440-PAK:
Balance
works of E-
35, P-III
111
Transport Sector
Loan 3300/G0440-PAK: National Motorway M-4 Gojra-Shorkot Section II Project
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
Current Status
1. Extension of
Time (EoT)
for Balance
works of E-
35, P-III (if
any).
NHA’s project team shall
process EoT (if any) and
seek ADB’s prior
approval.
Immediate/NHA Pending at NHA.
2. Pending
approval of
VO-7 by NHA
for M/s.
DOHWA.
NHA to process and
approve long outstanding
VO-7 and share with ADB
for prior approval.
Immediate/NHA ADB has shared its
comments with NHA
on VO-7, response on
which is pending.
3. Resolution of
tax
calculation
methodology
of SC
NHA To resolve the issue
arising out of different
methodology being used
for calculation of taxes of
SC M/s DOHWA
Immediate / NHA NHA and M/s. DOHWA
agreed to resolve the
issue through an
amendment in the
Consultancy Contract
after approval from the
competent authority.
4. Deduction of
10% penalty
NHA and DOHWA to
discuss this through the
Amicable Settlement
forum
Immediate / NHA NHA and M/s. DOHWA
agreed to resolve the
issue under the
proceedings of
amicable settlement.
5. Occupational
Health and
Safety
Standards.
NHA’s project team and
the Supervision
Consultant (SC) to
continue review the work
methodologies for all
construction activities,
OHS standards, and
ensure their compliance
and implementation.
Ongoing/NHA/SC Ongoing.
H. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
A. Loan 3300/Grant 0440-
PAK: M4 Sections IIA
and IIB
1. Approval of Addendum No.
9 of Construction
Supervision Consultant.
NHA to expedite the approval process. Immediate.
112
Transport Sector
Loan 3300/G0440-PAK: National Motorway M-4 Gojra-Shorkot Section II Project
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
2. Outstanding balance
payments to M/s. IDC
NHA to expedite the arrangement and
process the balance payments (if any) from
GoP resources.
Immediate.
3. Issuance of Taking Over
Certificate (ToC) by NHA.
NHA shall complete the required process to
issue the ToCs and process the retention
monies as per the Contract. ToCs shall
also be shared with ADB.
Immediate.
B. Loan 3300/Grant 0440-
PAK: Balance works of
E-35, P-III
1. Opening of balance section
to traffic by October 2019;
and mobilization of NH&MP
and O&M Contractor.
NHA to ensure that the section is opened
to traffic by October 2019; and both
NH&MP and O&M Contractor are
mobilized before opening of the section for
the traffic.
Before final date of opening of the section for the traffic.
2. Extension of Time (EoT)
for Balance works of E-35,
P-III (if any).
NHA’s project team shall process EoT (if
any) and seek ADB’s prior approval.
Immediate
3. Pending approval of VO-7
by NHA for M/s. DOHWA.
ADB has shared its comments with NHA on
VO-7,response on which is pending.
Immediate
113
Transport Sector
Loan 3395/G0482-PAK/8308-PAK (AIIB): National Motorway M-4 Shorkot-Khanewal Section III Project
Loan 3395/G0482-PAK/8308-PAK (AIIB): National Motorway M-4 Shorkot-Khanewal Section III Project
A. Loan Basic Data $ Million
Approval Date Signing Date Effective
Date Closing
Date
Closing Date
(Revised)
Elapsed Time %
Project Rating as of
30 Sep 19
L: 10-Jun-16 G: 10-Jun-16
AIIB: 24-Jun-16
20-Jun-16 20-Jun-16 25-Jun-16
01-Sep-16 01-Sep-16 02-Sep-16
31-Dec-20 31-Mar-20 31-Dec-20
- L: 72 G: 87
AIIB:72 Approved Amount
Net Loan Amount
Financing EA/IA Project Officer
Project Analyst
L: 100 G: 34
AIIB: 100
100.00 34.00 100.00
ADB DFID AIIB
NHA K.Ghafoor B. Paracha On Track
B. Loan/Grant Financial Progress (As of 30 Sep 2019) Loan-3395-PAK
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
68.50 31.50 68 0.00 0.00
Disbursements (Cumulative)
Un-disbursed Disbursement Performance %
Disbursements for 2019
Loan Balance EA’s Projections Actual
43.32 56.68 43 11.3 7.20
Grant 0482-PAK
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
29.35 4.65 86 0.00 0.00
Disbursements (Cumulative)
Un-disbursed Disbursement Performance %
Disbursements for 2019
Loan Balance EA’s Projections Actual
29.35 4.65 86 5.4 5.39
AIIB Financial Progress 8308-PAK
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
Projections Actual
75.53 24.47 76 0.00 0.00
Disbursements (Cumulative)
Un-disbursed Disbursement Performance %
Disbursements for 2019
Loan Balance EA’s Projections Actual
67.59 32.41 68 10.4 11.28
114
Transport Sector
Loan 3395/G0482-PAK/8308-PAK (AIIB): National Motorway M-4 Shorkot-Khanewal Section III Project
C. Project Description 1. The primary north-south transport corridor in Pakistan runs from Torkham on the northern border with Afghanistan and passes through primary production and population centers such as Peshawar, Islamabad, Faisalabad, Lahore, Khanewal, Multan, and Muzaffargarh, before reaching the port city of Karachi in the south. The corridor, which is about 1,800 km long, comprises national highways and motorways and connects the key centers of economic activity in the country. The corridor serves the economy of an area that accounts for 80%-85% of Pakistan's gross domestic product (GDP) and, in the regional context, forms an integral part of the Central Asia Regional Economic Cooperation (CAREC) corridors 5 and 6. After Pakistan’s accession to the CAREC Program in 2010, the corridors have become vital trading routes between landlocked Central Asian nations and Pakistan’s warm-water ports of Gwadar, Karachi, and Port Qasim on the Arabian Sea. 2. The national motorway M-4, connecting Faisalabad with Multan, will be a part of the north south transport corridor. Its area of influence, which includes Faisalabad, Multan, and the entire Punjab province, accounts for about 56% of the country's population and for 59% of the country's GDP. The M-4 will extend the already completed M-1, M-2, and M-3 motorways southward and shorten the distance between Multan and the twin cities of Islamabad and Rawalpindi in the north. The Faisalabad-Gojra section (58 km) of the M-4 was completed in 2014 with financing from the Asian Development Bank (ADB), while the Islamic Development Bank supported the completion of the adjoining Khanewal-Multan section (57 km) in 2015. Civil works for the Gojra-Shorkot section (62 km), cofinanced by ADB and the Government of the United Kingdom, commenced in April 2016. The proposed additional financing is applied to the construction of the remaining 64 km section between Shorkot and Khanewal. Upon completion, the new four-lane, access-controlled M-4 will provide a faster, safer, and more cost-effective alternative to the existing narrow and congested routes, notably in the heavily trafficked Faisalabad and Khanewal-Multan-Muzaffargarh areas. 3. The increase in scope and the additional financing do not change the development objectives of the current project. The project is consistent with the strategic goals and government priorities. The transport sector in Pakistan contributes about 10% to the GDP and employs about 2.3 million people (about 6% of the active labor force of Pakistan). Road transport dominates Pakistan's transport system, accounting for almost 96% of freight traffic in ton-kilometers and 92% of passenger traffic in passenger-kilometers. An improved north-south corridor will reduce the time and cost of moving goods and people along the entire logistic and supply chain. It will be instrumental in removing one of the key constraints to raising competitiveness, attracting private sector investment, increasing productivity, as well as deepening and diversifying the industrial base. The project will thus go a long way of providing sustainable jobs to a growing population. The project is also consistent with ADBs country partnership strategy, 2015-2019 for Pakistan, fits with ADB’s Midterm Review of Strategy 2020, supports the CAREC Transport and Trade Facilitation Strategy 2020, and is included in ADB’s country operations business plan, 2016-2018 for Pakistan.
115
Transport Sector
Loan 3395/G0482-PAK/8308-PAK (AIIB): National Motorway M-4 Shorkot-Khanewal Section III Project
D. Project Monitoring Framework (Current Status)
Outputs Status with Key Activities
126 km of four-lane, access-controlled motorway connecting Gojra, Shorkot, and Khanewal constructed and serviceable
Target Indicators Achievements/Status 126 km road section constructed to 120 km/hour design standard by 2019.
Section IIIA (Shorkot-Dinpur) has been completed and open to traffic. Section-IIIB: All road works have been completed with remaining few kms of fencing in progress. The project is expected to be opened to traffic by end of October 2019.
Safeguard and contract administration capacity of the NHA strengthened
Project environment and social safeguard requirements implemented with good quality
Ongoing process.
Contract management and execution carried out effectively without undue delay and unresolved disputes by 2019.
So far, no unresolved dispute has been reported.
E. Cumulative Contract Award and Disbursement Performance
197.7 197.7 191.1 191.1 191.1
176.4 176.4 173.4
19.2
34.7
65.1
88.7
100.1 116.2136.7
140.1
-
50
100
150
200
250
Dec-16 Jun-17 Dec-17 Jun-18 Dec-18 Jun-19 Dec-19 Jun-20 Dec-20 Jun-21
L 3395-8308-G0482 : Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Loan Amount: US$ 234.00 M
Clo
sin
g D
ate
: 3
1-D
ec-2
02
0
116
Transport Sector
Loan 3395/G0482-PAK/8308-PAK (AIIB): National Motorway M-4 Shorkot-Khanewal Section III Project
F. Contract Award and Disbursement Targets and Achievements in 2019
G. Status of the Action Plan discussed in 2nd TPR
Sr. No
Issue Action to be Taken Due Date Current Status
1. Proposal for utilization of surplus loan proceeds.
NHA through MoC to expedite the request for cancellation from EAD.
Immediate/NHA/MoC/EAD ADB on the request of Government has approved the request.
2. Issuance of Taking Over Certificate (ToC) by NHA for the completed sections which are opened to traffic.
NHA shall complete the required process to issue the ToCs and process the retention monies as per the Contract. ToCs shall also be shared with ADB.
Immediate/NHA
Currently under processing at NHA.
3. Occupational Health and Safety Standards.
NHA’s project team and the Supervision Consultant (SC) to continue review the work methodologies for all construction activities, OHS standards, and ensure their compliance and implementation.
Ongoing/NHA/SC Ongoing.
4. Opening of Section-IIIA without the deployment of NH&MP and mobilization of O&M Contractor.
ADB through its letter dated 22 April 2019 (i) reiterated that road safety is a primary concern for all; and (ii) advised NHA to close this section till the deployment of National Highways and Motorway
Immediate/NHA
NHA confirmed mobilization of NHA&MP and the O&M Contractor.
2.6
5.1
7.7
12.0
16.4
20.722.0
23.224.5 25.4 26.2 27.1
0.4 0.7
5.5
8.4
13.9
20.5 20.5 22.1
23.9
0.0
5.0
10.0
15.0
20.0
25.0
30.0
2019 Disbursements L3395($116.2 million through Dec 2018)
EA Projection Actual
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
- - - - - - - - -0
0
0
0
0
1
1
1
1
1
1
2019 Contract Awards L3395($176.4 million through Dec 2018)
EA Projection Actual
117
Transport Sector
Loan 3395/G0482-PAK/8308-PAK (AIIB): National Motorway M-4 Shorkot-Khanewal Section III Project
Police (NH&MP) and mobilization of Operation and Maintenance (O&M) Contractor.
5. Resolution of pending complaints.
NHA’s project team to assist in resolution of complaints related to the project, including those related to Borrow Area restoration, payment to vendors, suppliers, sub-contractors, etc.
Immediate/NHA
Ongoing.
H. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. Opening of Section-IIIB by
October 2019; and
mobilization of NH&MP and
O&M Contractor.
NHA to ensure opening of the section by
October 2019; and both NH&MP and the
O&M Contractor are mobilized before
opening of the section to the traffic.
Before final date of opening of the section for the traffic.
2. Issuance of Taking Over
Certificate (ToC) by NHA.
NHA shall complete the required process to
issue the ToC and process the retention
money as per the Contract. ToCs shall also
be shared with ADB.
Immediate.
118
Transport Sector
Loan 3305-PAK: Sindh Provincial Road Improvement Project
Loan 3305-PAK: Sindh Provincial Road Improvement Project
A. Loan Basic Data $ Million
Approval Date
Signing Date
Effective Date
Closing Date Closing
Date (Revised)
Elapsed Time %
Project Rating as of
30 Sep 19 12-Oct-15 30-Aug-16 5-Oct-16 30-Jun-20 - 84 Approved Amount
Net Loan Amount
Financing EA/IA Project Officer
Project Analyst
197.85 197.85 OCR PDD, Sindh K. Butt M. Irfan On Track
B. Loan Financial Progress (As of 30 Sep 2019)
$ Million
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
142.90 54.95 72 18.0 18.27
Disbursements (Cumulative)
Un-disbursed Loan Balance
Disbursement Performance %
Disbursements for 2019
EA’s Projections Actual
112.21 85.64 57 20.0 12.13
C. Project Description 1. The project will improve about 328 km provincial highways in Sindh. It will involve rehabilitation and upgrading some major inter-district connections to standard width of 7.3 m carriageway with appropriate drainage and safety facility, including institutional strengthening, road safety, and road asset management improvement components. A project preparatory technical assistance was provided1 to prepare the project. 2. The ownership of the network is shared by different government agencies. The Works & Services Department (WSD) of the Government of Sindh is responsible for the entire provincial and secondary road networks with total length of 14,460 km, the National Highway Authority (NHA) is managing national highway, and local district government is responsible for all local and access roads. The proposed project will help provincial road network improvement to enhance connectivity between provincial transport centers and cities with local markets and communities, provide much-needed access to education and health facilities, and contribute to poverty reduction by creation of jobs and employment opportunities.
3. The Project constitutes (i) rehabilitating and upgrading about 328 km of provincial highways; (ii) institutional strengthening of WSD on road asset management, Sindh road network master plan, emergency response equipment for traffic police, and training to WSD staff.
1 ADB provided project preparatory technical assistance for TA-8406 PAK: Provincial Road Improvement Project.
119
Transport Sector
Loan 3305-PAK: Sindh Provincial Road Improvement Project
D. Project Monitoring Framework (Current Status)
Outputs Status with Key Activities
About 328 km of provincial roads rehabilitated
By 2019, 328 km provincial highways are rehabilitated with international roughness index below 3.5 (2014 baseline: more than 7 on the average)
Two out of six civil works contracts from original scope of project have been completed and progress of works on remaining four contracts is more than 95%. At present the process of taking over certificate (TOC) is enduring. On 3 additional roads (80km) works are ongoing in full swing which will be completed within the loan closing date of 30 June 2020. Yooshin Engineering Corporation in association with Umer Munshi Associates (PVT) Ltd. & PEAS Consulting Services (sub-consultants) was selected as the Project Management Consultant (PMC) for the Project. The PMC contract was signed on 14 Nov 2016 and the EA issued letter to commence services on 14 Nov 2016.
Institutional capacity of WSD strengthened in road planning, maintenance, and road safety
More than 1,800 WSD staff trained by 2018
Not yet due.
Sindh road master plan approved by 2019
This is significantly behind schedule, and the PMU is struggling to implement this very important component. Consulting firm was recruited in Q3 2018.
RAMS upgraded and functioning by 2019
Significantly delayed: under implementation.
More than 70% of annual maintenance budget allocated based on the results generated by RAMS, by 2019
Not yet due. Significantly delayed
120
Transport Sector
Loan 3305-PAK: Sindh Provincial Road Improvement Project
E. Cumulative Contract Award and Disbursement Performance
F. Contract Award and Disbursement Targets and Achievements in 2019
G. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
Current
Status
1. Substantially completed contracts
Immediate mobilization of additional resources by the contractors on
15 Sep 2019/ PMU/Contractor
Partially Outstanding
1.53.0
4.5
7.1
9.6
12.2 13.0 13.7 14.516.3
18.220.0
3.4 4.7
5.9 7.7
9.7 9.9 10.0 11.0
12.1
0.0
5.0
10.0
15.0
20.0
25.0
2019 Disbursements L3305($100.1 million through Dec 2018)
EA Projection Actual
0 0
6
12
18 18 18 18 18 18 18
- - - - -
14.5 17.8 18.2 18.3
0
2
4
6
8
10
12
14
16
18
20
2019 Contract Awards L3305($127.1 million through Dec 2018)
EA Projection Actual
121
Transport Sector
Loan 3305-PAK: Sindh Provincial Road Improvement Project
need to complete/close.
subprojects 2,4,5, and 6; and effective supervision by the PMC in order to complete remaining (less than 5% works) at the earliest.
2 Issuance of Taking Over Certificate (TOC) for completed subproject
Submission of as built drawing by the contractors to PMU and verification of Road Roughness Index (RRI) before the issuance of Taking Over Certificate (TOC) for each subproject.
31 August 2019 /PMU and PMC
In Progress
3. Pending Variation Orders
PMU to send pending variation orders pertaining to all sub projects have savings after realizing the actual BOQ in their contracts for ADB’s approval.
31 August 2019 /PMU and PMC
In Progress
4. Preparation/Approval of Sindh Roads Networks Master Plan (SRNMP)
Significantly Delayed: It was agreed during Mission in April 2019 that PMU/Consultant will submit a revised program by 31 May 2019 with the backwards calculation up to the approval of SRNMP. It is still awaited and requested to prepare/share.
31 August/PMU and Consultant.
Outstanding
5. RAMS upgradation & and allocation of 70% of annual maintenance budget based on the results generated by RAMs by 2019 is significantly delayed.
Roads condition survey of 53,000km is significantly delayed. PMU/consultant is
required to submit a catch-up plan for survey by 15 August 2019 and complete survey within original allocated time
31 August/PMU Outstanding
Strengthening of RSDD/PMU by allocating adequate financial and human resources and restructuring
31 August/PMU Outstanding
Complete procurement of IT equipment for RSDD
Q3 2019/PMU Outstanding
Initiate the approval process for the allocation of road maintenance budget
based on the results generated by RAMS latest by 30 June
Q3 2019/PMU and C&W
Department
Outstanding
6. Feasibility Study & Detailed Design of Construction of Hyderabad Southern Bypass: Alignment and inception report
Consultant/PMU to complete the inception report and submit to PMU for
approval without any further delay.
I31 August /PMU and
Consultant
Done
Finalize alignment with consultation of all stakeholders.
31 August /PMU and Consultant
Outstanding
7. Cancelation of surplus loan proceeds and confirmation of MTR’s AM.
W&SD/P&DD to submit request for partial cancelation of $30 million loan proceeds to ADB through EAD by 30 June
31 August /W&SD/P&DD
Done
8. Provincial Roads Improvement Project, Phase II.
The Planning Commission sought a few clarifications from GoS related to the submitted concept paper. The P&DD
Sindh provided required information on 17 June 2019; and requested planning commission to consider concept paper for clearance during next CDWP/CCC
31 August /C&W/P&DD
In Progress
122
Transport Sector
Loan 3305-PAK: Sindh Provincial Road Improvement Project
meeting. P&DD is requested to follow-up with planning commission.
A formal request to ADB for financing though EAD.
EAD Outstanding
The preparation of project will be tasked to the consultant already
engaged under ongoing project (through VO). ADB principally agreed with the proposal to save time. It was further agreed that Project
Management Unit (PMU) will submit a formal request to ADB through P&DD for approval of the contract variation. PMU and ADB has already discussed/agreed to the VO’s details,
however, the formal submission is awaited.
PMU/P&DD In Progress
H. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date / By Whom
1. Substantially completed contracts need to complete/close.
Immediate mobilization of additional resources by the contractors on subprojects 2,4,5, and 6; and effective supervision by the PMC in order to complete remaining (less than 5% works) at the earliest.
Immediate/ PMU/Contractor
2.
Road Maintenance
under PPP
arrangement
Outsourcing of the operation and
maintenance of at least two road
sections rehabilitated under the project
to concessioner(s) through tolling
arrangement; and with the clear
performance indicators
P&DD, W&SD, PPP Cell GoS
/31 Dec 2019
3. Issuance of Taking Over Certificate (TOC) for completed subproject
Issuance of TOC for subprojects 1 and 3 by 25 Oct; and subprojects 2,4,5, and 6 by 30 November
30 November 2019 /PMU and PMC
4. Pending Variation Orders
PMU to send pending variation orders for ADB’s approval having savings after realizing the actual BOQ; or required re-appropriations
Immediate/PMU
5. Preparation/Approval of Sindh Roads Networks Master Plan (SRNMP)
Significantly Delayed: It was agreed during Mission in April 2019 that PMU/Consultant will submit a revised program by 31 May 2019 with the backwards calculation up to the approval of SRNMP. It is still awaited and requested to prepare/share.
Most Immediate/PMU and Consultant.
Payment of SRNMP is pending since July which needs to resolve immediately
PMU
123
Transport Sector
Loan 3305-PAK: Sindh Provincial Road Improvement Project
Sr.
No
Issue Action to be Taken Due Date / By Whom
6. Procurement of Emergency Equipment
Finalize the specifications and initiate the Procurement of Cutting Vehicle
PMU/Consultant/ 5 November 2019
7. RAMS upgradation & and allocation of 70% of annual maintenance budget based on the results generated by RAMs by 2019 is significantly delayed.
Roads condition survey of 53,000km is
significantly delayed. PMU/consultant is required to submit a catch-up plan for survey by 15 August 2019 and complete survey within original allocated time
TBC/PMU
Strengthening of RSDD/PMU by allocating adequate financial and human resources and restructuring
TBC/PMU
Complete procurement of IT equipment for RSDD
TBCPMU
Initiate the approval process for the allocation of road maintenance budget
based on the results generated by RAMS latest by 30 June
TBC/PMU and C&W Department
8. Feasibility Study & Detailed Design of Construction of Hyderabad Southern Bypass: Alignment & inception report
Consultant/PMU to complete the inception report and submit to PMU for
approval without any further delay.
PMU/Consultant/TBC
Finalize alignment with consultation of all stakeholders.
9. Provincial Roads Improvement Project, Phase II.
The Planning Commission sought a few clarifications from GoS related to the
submitted concept paper. The P&DD Sindh provided required information on 17 June 2019; and requested planning commission to consider
concept paper for clearance during next CDWP/CCC meeting. P&DD is requested to follow-up with planning commission.
C&W/P&DD/ TBC
A formal request to ADB for financing though EAD.
EAD/ TBC
124
Transport Sector
Loan 3344/3345-PAK(COL): CAREC Regional Improving Border Services Project
Loan 3344/3345-PAK(COL): CAREC Regional Improving Border Services Project
A. Loan Basic Data $ Million
Approval Date
Signing Date
Effective Date
Closing Date Closing Date
(Revised) Elapsed Time
% Project Rating as of
30 Sep 19
4-Dec-15 26-Oct-16 15-Dec-16 30-Jun-22 - 58 Approved Amount
Net Loan Amount
Financing EA/IA Project Officer
Project Analyst
150.00 100.53
150.00 97.96
OCR COL
FBR O. Samukhin A. Diamante Potential Problem
B. Loan Financial Progress (As of 30 Sep 2019)
Loan 3344-PAK
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
126.14 23.86 84 74.0 59.87
Disbursements (Cumulative)
Un-disbursed Loan Balance
Disbursement Performance %
Disbursements for 2019
EA’s Projections Actual
30.26 119.74 20 20.0 12.19
Loan 3345-PAK(COL)
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
93.62 4.34 96 41.00 46.96
Disbursements (Cumulative)
Un-disbursed Disbursement Performance %
Disbursements for 2019
Loan Balance EA’s Projections Actual
0.00 97.96 0 0.00 0.00
C. Project Description 1. The proposed project will remove the key bottleneck for movement of goods and people through Torkham, Chaman, and Wagha in Pakistan. As part of CAREC’s initiative for trade facilitation, the project will help CAREC countries take advantage of more efficient trade routes through Pakistan, and reciprocally, encourage Pakistan to play a strategic role in creating a larger regional market for intra-CAREC and inter-CAREC trade. The project will be designed as a sovereign project financing as the operation of BCPs in Pakistan is with the public-sector domain. 2. The expected impact of the project will be an increased value of export, import, and transit trade. The expected outcome will be reduced cross-border processing time for goods and cargos in Torkham, Chaman, and Wagha.
125
Transport Sector
Loan 3344/3345-PAK(COL): CAREC Regional Improving Border Services Project
D. Project Monitoring Framework (Current Status)
Outputs Status with Key Activities
Border crossing point infrastructure and facilities at Chaman, Torkham, and Wagha improved
Border point facilities certified as compliant to internationally accepted standards at Chaman, Torkham, and Wagha by 2021
The loan agreements were signed and became effective. The FBR Project Management Unit (PMU) was established in 2016. The project management consultant (PMC) and Construction Supervision Consultant (CSC) were mobilized in 2017. Direct contracting for BCPs Torkham and Chaman has been completed. Engineering Design and procurement of ICT & Security Equipment by NLC for BCP Torkham and Chaman is completed. Scope of the project works at BCP Wagha is ongoing.
Governance structure of national border point management regime produced and adopted; and organizational design, management structure, financial and administrative procedures, and financial modeling for the PLPA produced and adopted
PLPA established with transparent governance structure and clear vision and mandate statement by 2021
The EOI for consultant recruitment for establishing Pakistan Land Port Authority (PLPA) was published on 19 May 18 with extended date of submission of 3 July 2019. Owing to the limited response the EOI has been republished on 3 July 19 with revised date of receipt of 8 August 2019.
Knowledge and skills of border point operating agencies enhanced
Professionally qualified border point agencies and officials appointed by 2021
Same as above
E. Cumulative Contract Award and Disbursement Performance (L-3344 PAK)
0.0 3.7
13.4 13.5 13.5
70.3
126.1
0.00.1
0.2 0.8 1.2
18.1
30.3
-
20
40
60
80
100
120
140
160
Dec-16 Jun-17 Dec-17 Jun-18 Dec-18 Jun-19 Dec-19 Jun-20 Dec-20 Jun-21 Dec-21 Jun-22 Dec-22
L 3344: Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Loan Amount: US$ 150.00 MC
losi
ng D
ate:
30-
Jun-
2022
126
Transport Sector
Loan 3344/3345-PAK(COL): CAREC Regional Improving Border Services Project
F. Cumulative Contract Award and Disbursement Performance (L-3345 PAK)
G. Contract Award and Disbursement Targets and Achievements in 2019 (L-3344)
0.1 0.1 0.21.1
2.02.9
4.76.6
8.4
12.3
16.1
20.0
0.4 0.5 0.9 0.9 1.1
12.2
0.0
5.0
10.0
15.0
20.0
25.0
2019 Disbursements L3344($18.1 million through Dec 2018)
EA Projection Actual
0 0
14
27
4145
5054
61
67
74
- - - - - - -
59.7 59.9
0
10
20
30
40
50
60
70
80
2019 Contract Awards L3344($70.3 million through Dec 2018)
EA Projection Actual
0.0 0.0 0.0 0.0 0.0
50.8
93.6
-
20
40
60
80
100
120
Dec-16 Jun-17 Dec-17 Jun-18 Dec-18 Jun-19 Dec-19 Jun-20 Dec-20 Jun-21 Dec-21 Jun-22 Dec-22
L 3345: Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Loan Amount: US$ 97.96 M
Clo
sing
Da
te:
30
-Jun
-20
22
127
Transport Sector
Loan 3344/3345-PAK(COL): CAREC Regional Improving Border Services Project
H. Contract Award and Disbursement Targets and Achievements in 2019 (L-3345)
I. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
Current Status
1. LARP implementation Torkham
• Passenger Terminal • Trade Terminal
30 July 19/ FBR ASAP/ FBR
Still pending
2. Contract Award Chaman
• Bid Submission by NLC • BER Submission to ADB • No Objection to Contract Award • Contract Award
Contract has been awarded on 20 August 2019
3 LARP Implementation Chaman
• Disbursement to affected persons
• Verification by EMA • Submission of EMA report to
ADB • ADB Concurrence to EMA
report and issue NTP
• 30 August 19/ FBR
• 15 Sept 19/ EMA
• 22 Sept 19/ EMA
• 30 Sept 19/ ADB
Pending
4. Procurement of PLPA Consultants
• Receipt of EOI • Submission of Short List and
RFP to ADB • ADB Concurrence to
submission • Issue of RFP to short listed
firms
• 8 August 19/ FBR
• 24 August 19/ FBR
• 30 August 19/ ADB
• 5 Sept 19/FBR
Shortlisting in progress.
5. Procurement of Works Wagah
• Approval of PIC for additional Financing
• Draft BD Finalization • Invitation for bids
• 25 August 19/FBR
• 10 Sept 19/FBR
Revision of PC-I pending
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
- - - - - - - - -0.0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1.0
2019 Disbursements L3345($0.0 million through Dec 2018)
EA Projection Actual
0 0
14
27
41 41 41 41 41 41 41
- - - - - - -
46.8 47.0
0
5
10
15
20
25
30
35
40
45
50
2019 Contract Awards L3345($50.8 million through Dec 2018)
EA Projection Actual
128
Transport Sector
Loan 3344/3345-PAK(COL): CAREC Regional Improving Border Services Project
• Processing of additional financing
• Contract Award
• 30 Sept 19/FBR
• Nov 19/FBR • Mar 20/FBR
6. Staffing of PMU/ PMC/ CSC
• Appointment of Interim Project Director
• VO for separation of TL & Contract Manager PMC
• Replacement of TL CSC and Mobilization of new TL
• ASAP/ FBR • Immediate/
FBR • Sept 19/ FBR
J. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. LARP implementation BCP
Torkham
Release of payment to affected person for
passenger terminal
Initially 132 kanals of Army Lease land, for
which NOC was issued for
commencement of construction activities,
became disputed. As per the revenue
record 62 kanals is privately owned and
rest was leased to Army which also
expired and hence Army has de-leased it.
Private owner has taken the matter to
Court, however, are willing for off the court
settlement. Negotiations are underway
which needs to be expedited.
15 Nov 2019/FBR
and NLC
2. LARP Implementation
Chaman
During recent Mid Tern Review Mission, Chaman was visited and following timelines are agreed: • Provision of data of APs by SC (CNIC No
& Bank Accounts No)-25 October 19 • Disbursement of Compensation: 24
November 19 • Land handed over by SC to FBR: 31
December 19 • Transition Plan implementation: 31
January 2020
• Commencement of Construction
Activities: 1 February 2020
As mentioned/FBR
3. Procurement of PLPA
Consultants
Issuance of RFP to short listed firms PMU/ 5 Nov
4. Procurement of Works
Wagah
• Approval of PIC for additional Financing • Draft BD Finalization • Invitation for bids • Processing of additional financing • Contract Award
15 Nov / FBR
129
Transport Sector
Loan 3344/3345-PAK(COL): CAREC Regional Improving Border Services Project
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
5. Staffing of PMU/ PMC/
CSC
• Appointment of Director Coordination at Chaman
15 Nov / FBR
130
Transport Sector
Loan 3378-PAK: Post-Flood National Highways Rehabilitation Project
Loan 3378-PAK: Post-Flood National Highways Rehabilitation Project
A. Loan Basic Data $ Million
Approval Date
Signing Date
Effective Date
Closing Date Closing
Date (Revised)
Elapsed Time %
Project Rating as of
30 Sep 19 29-Mar-16 23-Jan-17 18-Apr-17 31 Mar 21 - 70 Approved Amount
Net Loan Amount
Financing EA/IA Project Officer
Project Analyst
196.90 196.90 OCR NHA K.Ghafoor I. Qamar Potential Problem
B. Loan Financial Progress (30 Sep 2019)
Loan - 3378-PAK
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
111.60 85.30 57 0.00 0.04
Disbursements (Cumulative)
Un-disbursed Disbursement Performance %
Disbursements for 2019
Loan Balance EA’s Projections Actual
60.65 136.25 31 46.86 18.98
C. Project Description The proposed rehabilitation project includes 212 kms of damaged highway sections and 33 damaged bridges located on the national highway network of Pakistan. It will restore critical physical infrastructure to sustain livelihoods and access to markets, as well as build post disaster traffic management capacity in the National Highway Authority (NHA). The project will contribute to the economic recovery of 2010 flood affected areas in Khyber Pakhtunkhwa, Punjab, and Sindh provinces. D. Project Monitoring Framework (Current Status)
Outputs Status with Key Activities
National highway network system (including bridges) repaired and rehabilitated
212 km of damaged national highways and 33 bridges repaired, rehabilitated, and reconstructed by the end of 2020
The loan and project agreements have been signed on 23 January 2017. The loan was declared effective on 18 April 2017. All eight civil works contracts and the Supervision Consultant’s contract under this Project have been awarded
Disaster Management Units (DMUs) established and staff trained
2a. DMUs in NHA’s headquarters and 10 regional offices operationalized by December 2018 (2015 baseline = 0)
Not yet due
131
Transport Sector
Loan 3378-PAK: Post-Flood National Highways Rehabilitation Project
2b. 12 NHA operations staff trained in post-disaster emergency traffic restoration management by the end of June 2018 (2016 baseline = 0) 2c. 3 NHA operations staff trained in managing procurement under emergency conditions by the end of June 2018 (2016 baseline = 0)
E. Cumulative Contract Award and Disbursement Performance
132
Transport Sector
Loan 3378-PAK: Post-Flood National Highways Rehabilitation Project
F. Contract Award and Disbursement Targets and Achievements in 2019
G. Status of the Action Plan discussed in 2nd TPR
Sr. No
Issue Action to be Taken Due Date / By Whom
Current Status
1. Delay in implementation of civil works
After the issuance of EOTs, Revised work plan are to submitted and rigorous follow-up and strict supervision and monitoring of contractor’s performance to expedite civil works and minimize time over run in all contracts is required.
31 Aug 2019/ NHA/ Supervision Consultant
Done.
2. Addressing the discrepancies in the design of civil work contracts awarded under Package 8
Design related issues pertaining to dealing with the Sarobi Nullah portion to be addressed
15 Sep 2019/ NHA/ Supervision Consultant
The issue has been addressed.
3. NHA to decide on Loan Savings and financing of left-over works.
NHA to consider proposing $25 million as cancellation of surplus loan proceeds from the civil works allocation category
31 Aug 2019/ NHA The request from the Government has been received and under processing at ADB.
4. Constitution of Dispute Board(s) for all Civil Work Contracts to resolve contractual issues expeditiously
NHA shall ensure that DBs are effective for all civil work contracts financed under Loan 3378-Pak as per provisions of FIDIC.
31 Aug 2019/NHA Under process
5. Procurement of Package 2 Lot-2
Prepare the procurement schedule of Package 2 Lot-2
31 Aug / NHA Pending
2.75.3
8.0
12.3
16.7
21.025.0
29.033.0
37.6
42.2
46.9
-
0.6 0.6 0.8 10.7
17.9 17.9 18.9 19.0
0.0
5.0
10.0
15.0
20.0
25.0
30.0
35.0
40.0
45.0
50.0
2019 Disbursements L3378($41.7 million through Dec 2018)
EA Projection Actual
0.0
0.0
0.0
0.0
0.0 0.0
0.0
0.0 0.0 0.0
0.0
- - -
0.0 0.0 0.0 0.0 0.0
0
0
0
0
0
0
0
0
0
2019 Contract Awards L3378($119.3 million through Dec 2018)
EA Projection Actual
133
Transport Sector
Loan 3378-PAK: Post-Flood National Highways Rehabilitation Project
6. Pending submission of Environmental and Social Safeguard Reports
Prepare Bi Annual Environmental (BAEMR) and Social Safeguards Monitoring (SMR) reports and submit to ADB for review, comments and approval for public disclosure.
31 Aug/ NHA Pending
H. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1 Procurement of Package 2
Lot-2
Prepare the procurement schedule of
Package 2 Lot-2
15 Nov / NHA
2 Pending submission of
Environmental and Social
Safeguard Reports
Prepare Bi Annual Environmental
(BAEMR) and Social Safeguards
Monitoring (SMR) reports and submit to
ADB for review, comments and approval
for public disclosure.
15 Nov / NHA
3 Disaster management
component
The component of the loan is yet to
commence.
15 Nov / NHA
134
Transport Sector
Loan 3264-PAK: Flood Emergency Reconstruction and Resilience Project
Loan 3264-PAK: Flood Emergency Reconstruction and Resilience Project
A. Loan Basic Data $ Million
Approval Date
Signing Date
Effective Date
Closing Date Closing Date
(Revised) Elapsed Time %
Project Rating as of
30 Sep 19
30-Jun-15 9-Jul-15 24-Aug-15 30-Dec-18 30-Apr-19 111 Approved Amount
Net Loan Amount
Financing EA/IA Project Officer
Project Analyst
218.04 193.04 OCR P&D Punjab
P&D AJK M. Shafi
M.A. Sheikh H. Ambreen
On Track
B. Loan Financial Progress (As of 30 Sep 2019)
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
174.31 18.73 90 1.2 1.31
Disbursements (Cumulative)
Un-disbursed Disbursement Performance %
Disbursements for 2019
Loan Balance EA’s Projections Actual
165.99 27.05 86 18.0 11.37
C. Project Description The project will contribute to the economic and social recovery of areas in Punjab Province and the northern districts of Haveli, Kotli and Poonch, through the rehabilitation and reconstruction of high-priority infrastructure damaged and weakened during the floods in September 2014. The project focuses on the transitional phase of the emergency response for the rehabilitation and reconstruction of priority roads, bridges, irrigation and flood protection infrastructure damaged by the floods. The project will also support ex ante disaster risk management (DRM) capacity building to mainstream resilience in development planning. Reconstruction of damaged and at-risk infrastructure in the flood-affected areas will use appropriate and cost-effective multi-hazard resistant design and construction standards to mitigate the potential impact of future disasters. The Project design is based on the findings of the damage assessment reports prepared by the respective Punjab Planning and Development Departments (P&D) in January 2015 and facilitated by the Asian Development Bank (ADB) and World Bank, in close coordination with the federal government and other donors.
135
Transport Sector
Loan 3264-PAK: Flood Emergency Reconstruction and Resilience Project
D. Project Monitoring Framework (Current Status)
Outputs Performance Indicators with Baseline
Status with Key Activities
Flood-damaged roads and bridges in Punjab Province and the districts of Haveli, Kotli, and Poonch reconstructed
By the end of 2018, 1,740 km of damaged provincial highways and district roads repaired, rehabilitated, and reconstructed.
Almost achieved. Will be verified during PCR mission.
By 2018, 173 km of roads and bridges include safety measures that are friendly to women, children, the elderly, and persons with disabilities.
Almost achieved. Will be verified during PCR mission.
Flood-resilient irrigation and flood management infrastructure in Punjab Province implemented
At least 90% of selected flood protection and irrigation structures damaged by the 2014 floods are reconstructed and made more resilient by 2018.
All approved scope was completed by 30 November 2018.
DRM strengthened 200 hectares of active slide area along major road corridors treated through bio-engineering interventions by 2018.
800 ha of landslides area were treated for stabilization.
Enhanced safety procedures for dams and flood protection structures Institutionalized in PID by 2018.
Completed. Manuals and protocols were developed and adopted by PID.
Land-slide risk mitigation measures include procurement of 30% of the forest nurseries owned by women.
Overachieved. More than 55 % plants were procured from women-owned nurseries.
Gender-disaggregated data and analysis of multihazard vulnerability and risk assessments available for 20 most vulnerable districts by 2018.
Partially done. MHVRA’s were completed however, printing of reports and atlases and user training could not be completed within the loan closing date. ADB approved financing of these activities under the attached TA by changing the TA scope and extending the TA completion date to 30 December 2019. Some gender-disaggregated data is available for the households surveyed in the field.
136
Transport Sector
Loan 3264-PAK: Flood Emergency Reconstruction and Resilience Project
E. Cumulative Contract Award and Disbursement Performance
F. Contract Award and Disbursement Targets and Achievements in 2019
10.0
60.0
81.0
145.3
165.6 168.7 169.1 171.3 171.9 174.3
6.9
32.0
52.263.1
120.2
135.6143.2
154.6163.6 165.9
-
50
100
150
200
250
Dec-15 Jun-16 Dec-16 Jun-17 Dec-17 Jun-18 Dec-18 Jun-19 Dec-19
L 3264: Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Loan Amount: US$ 193.04 M
Clo
sin
g D
ate
: 3
0-A
pr-
20
19
Clo
sin
g D
ate
: 30-A
pr-
2019
1.73.3
5.0
7.0
9.0
11.0
13.3
15.7
18.0 18.0 18.0 18.0
0.1 0.1
2.0
6.4 7.8
9.0 9.2
10.2 11.4
0.0
2.0
4.0
6.0
8.0
10.0
12.0
14.0
16.0
18.0
20.0
2019 Disbursements L3264($154.6 million through Dec 2018)
EA Projection Actual
0.8
1.2 1.2 1.2 1.2 1.2 1.2
1.2
1.2 1.2 1.2
- -
0.4
0.6 0.6 0.6
1.2 1.3
1.3
0
0
0
1
1
1
1
1
2019 Contract Awards L3264($171.3 million through Dec 2018)
EA Projection Actual
137
Transport Sector
Loan 3264-PAK: Flood Emergency Reconstruction and Resilience Project
H. Status of the Action Plan discussed in 2nd TPR
Sr. No
Issue Action to be Taken Due Date / By Whom
Current Status
1. Handing over of rehabilitated infrastructure
PIU C&W Punjab and PIU C&W AJK to hand over the rehabilitated / reconstructed roads under the project to the respective C&W departments for operations after completing all finishing works including punch lists etc. PIU Irrigation to complete handing over of subprojects to PIU and report to ADB
PIUs, C&W Punjab and AJK 31 August 2019 PIU PID, 30 Sep 2019
Not applicable for Punjab Handing over completed for AJK Handing over completed in irrigation subprojects
2. Account Closure All PIUs, and PCUs in Punjab and AJK will either fully spend the imprest advance, or refund the unspent advance to ADB after making all eligible payments under the Project.
31 August 2019 Not completed. There are still some liabilities to be cleared before the loan account closure. The winding up period was extended to 31 Oct 2019.
3. Project Completion Report
PCU AJK and PCU Punjab to provide first draft of the consolidated completion reports of their respective components to ADB
PCU Punjab PCU AJK 31 August 2019
PCR was not received.
4. DRM Strengthening in Punjab
PDMA to complete design and printing of MHVRA Atlas and Reports through own funding PCU P&DD Punjab to ensure full integration of MHVRA results with DCH, and mainstream PPMS as an integral part of PC-1 approval. P&DB Punjab to notify revised procedure for PC-1 approval using the system developed under FERRP.
PIU PDMA 30 September 2019 P&DB 30 September 2019
ADB revised TA scope to including financing of this activity. Not yet completed. This is now being done under the TA, as approved by ADB.
138
Transport Sector
Loan 3264-PAK: Flood Emergency Reconstruction and Resilience Project
Sr. No
Issue Action to be Taken Due Date / By Whom
Current Status
5. Sustainability of Project interventions
The Government of AJK committed to start toll collection at Azad Pattan – Rawalakot Road to generate O&M funds for future maintenance of the Funds. This needs to be started immediately as the road has been fully rehabilitated.
Immediately The toll collection has not been started yet
I. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. Payments against ADB
share
The final withdrawal application by each
project component shall be submitted to
ADB for processing before loan account
closing.
All PCUs/PIUs
31 October 2019.
2. Refund of Unspent
advance Fund
The unspent advance fund will be
refunded to ADB after clearing of all
eligible expenditure
PCU, Punjab
15 December 2019
3. Release of Counterpart
Funds for PDMA
Government of Punjab to release
counterpart funds of PKR15 million.
25 October 2019.
4. Ineligible payments of
$0.24 million from advance
fund by PDMA
The PDMA will pay ADB share of
equivalent amount from government funds
and submit reimbursement application to
ADB for liquidating against the payments
of taxes and duties from ADB’s advance
fund.
PDMA, Punjab
31 October 2019.
5. Borrowers Completion
Report
PCUs of Punjab and AJK components to
provided consolidated project completion
reports for all of their respective
components.
PCU Punjab, and
AJK
15 November 2019
139
Transport Sector
Loan 3574-Pak: Central Asia Regional Economic Cooperation Corridor Development Investment Program-Tranche 1
Loan 3574-PAK: Central Asia Regional Economic Cooperation Corridor Development Investment Program-Tranche 1
A. Loan Basic Data $ Million
Approval Date
Signing Date Effective
Date Closing
Date
Closing Date
(Revised)
Elapsed Time % Project
Rating as of
30 Sep 19 28-Sep-17 18-Dec-2017 31 Jan 2018 31-Dec-22 – 38 Approved Amount
Net Loan Amount
Financing EA/IA Project Officer
Project Analyst
180.00
180
OCR
NHA R. Idei G. Jurado
Actual Problem
B. Loan Financial Progress (As of 30 Sep 2019)
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
55.94 124.06 31 0.00 0.00
Disbursements (Cumulative)
Un-disbursed Disbursement Performance %
Disbursements for 2019
Loan Balance EA’s Projections Actual
4.79 175.21 3 13.8 4.69
C. Project Description The project proposed for financing under the requested PFR is: (i) building an additional 2-lane carriageway of 66 km along the existing 2-lane carriageway of Petaro-Sehwan road; (ii) building an additional 2-lane carriageway of 43 km along the existing 2-lane carriageway
of Ratodero-Shikarpur road; (iii) rehabilitating the existing 34 km 4-lane carriageway of Dara Adamkhel-Peshawar road;
and (iv) developing NHA’s capacity through due diligence advisory services and assistance with
project implementation.
D. Project Monitoring Framework (Current Status)
Outputs Status with Key Activities
Target Indicators Achievements/Status
1. CAREC Corridor along N55 constructed or rehabilitated
1a. 66 km from Petaro to Sehwan and 43 km from Ratodero to Shikarpur along N55 improved by 2022 with international roughness index no higher than 2.0m/km (2016
Additional 2 Lane Carriageway from Petaro to Sehwan – Contract awarded and work has commenced. Additional 2-Lane Carriageway for Ratodero-Shikarpur – contract for Ratodero-Shikarpur would require
140
Transport Sector
Loan 3574-Pak: Central Asia Regional Economic Cooperation Corridor Development Investment Program-Tranche 1
baseline: not applicable) 1b. 34 km from Dara Adamkhel to Peshawar along N55 improved by 2022 with international roughness index no higher than 2.0m/km (2016 baseline: 3.25)
rebidding due to delay in implementation of LARP. Rehabilitation and Improvement of Existing Carriageway from Dera Adam Khel-Peshawar (Section 3) 34.350 Km – Contract awarded and work has commenced. Design Review and Construction Supervision – Contract awarded and consultant has been mobilized
2. NHA capacity strengthened
2a. Due diligence works for subsequent tranches conducted and subsequent tranche projects prepared in compliance with ADB SPS (2009) and categorized as procurement- and design-ready
Recruitment of consultants for due diligence advisory services not yet started.
E. Cumulative Contract Award and Disbursement Performance
0.0 0.0
62.5 55.9
0.0 0.1 0.14.8
-
20
40
60
80
100
120
140
160
180
200
Jun-18 Dec-18 Jun-19 Dec-19 Jun-20 Dec-20 Jun-21 Dec-21 Jun-22 Dec-22 Jun-23
L 3574: Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Loan Amount: US$ 180.00 M
Clo
sin
g D
ate
: 3
1-D
ec-2
02
2
141
Transport Sector
Loan 3574-Pak: Central Asia Regional Economic Cooperation Corridor Development Investment Program-Tranche 1
F. Contract Award and Disbursement Targets and Achievements in 2019
G. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
Current Status
1. LARP of Ratodero-
Shikarpur
NHA to finalize the LARP
so the contract could be
awarded to winning
bidder.
Immediate/NHA Done
2. Slow progress on
Dera Adam Khel-
Peshawar (Section
3)
NHA to ensure that the
contractor submits the
bank guarantee at the
earliest so that
mobilization advance
could be processed.
Immediate/NHA/Contractor Pending
3. LARP
implementation on
Petaro to Sehwan
Section
NHA to expedite the
implementation of
pending LARP so that
work could be
progressed after
issuance of ADB’ NoC.
Immediate/ NHA Ongoing
H. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. LARP Implementation Petaro
Sehwan
IMR and EMR delayed 15 Nov / NHA
2. Slow Progress on Peshawar
Dara Adam Khel
NHA may consider issuing notice to correct 15 Nov / NHA
2.0
4.0
6.0 6.0 6.0 6.0
7.5
9.0
10.511.6
12.713.8
0.1 0.1
2.5 2.5 2.5
4.6 4.7 4.7 4.7
0.0
2.0
4.0
6.0
8.0
10.0
12.0
14.0
16.0
2019 Disbursement($0.1 million through Dec 2018)
EA Projection Actual
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
- - - - - - - - -0
0
0
0
0
1
1
1
1
1
1
2019 Contract Awards($62.5 million through Dec 2018)
EA Projection Actual
142
Transport Sector
Loan 3601-Pak/L3602(COL): Khyber Pakhtunkhwa Provincial Roads Improvement Project
Loan 3601-PAK/Loan 3602-PAK(COL): Khyber Pakhtunkhwa Provincial Roads Improvement Project
A. Loan Basic Data $ Million
Approval Date
Signing Date Effective Date Closing
Date
Closing Date
(Revised)
Elapsed Time %
Project Rating as of
30 Sep 19 28-Nov-2017 14-Mar-2018 24-Sep-2018 30-Sep-23 - 33
Approved Amount
Net Loan Amount
Financing EA/IA Project Officer
Project Analyst
121.50 18.50
121.50 18.50
OCR COL PHA J. Ning G. Jurado
Potential Problem
B. Loan Financial Progress (As of 30 Sep 2019)
Loan 3601-PAK
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
62.31 59.19 51 0.00 0.43
Disbursements (Cumulative)
Un-disbursed Disbursement Performance %
Disbursements for 2019
Loan Balance EA’s Projections Actual
11.40 110.10 9 18.0 10.60
Loan 3602-PAK(COL)
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
17.44 1.06 94 0.00 0.00
Disbursements (Cumulative)
Un-disbursed Disbursement Performance %
Disbursements for 2019
Loan Balance EA’s Projections Actual
17.59 0.91 95 10.0 9.33
C. Project Description The proposed project will (i) rehabilitate 214 km of provincial roads in the Province of Khyber Pakhtunkhwa (KP); (ii) pilot two performance-based maintenance (PBM) contracts covering 104 km of provincial roads; and (iii) enhance road asset management.
143
Transport Sector
Loan 3601-Pak/L3602(COL): Khyber Pakhtunkhwa Provincial Roads Improvement Project
D. Project Monitoring Framework (Current Status)
Outputs Status with Key Activities
1. Provincial roads rehabilitated
Target Indicators Rehabilitation of approximately 214 km section of provincial road completed by 2023
Achievements/Status Civil works contracts and supervision consultant contract were signed and work has commenced.
2. PKHA’s institutional capacity on road maintenance strengthened
Two pilot PBM contracts with total length of 104 km completed by 2023
PBM will be financed by KP, but it has not been approved by PDWP and has not been included in the ADP. C&WD agreed to issue a letter to ADB after finalization of sections of roads to be included under PBM.
E. Cumulative Contract Award and Disbursement Performance Loan 3601-PAK
0.0 4.7
71.4
62.3
0.0 0.0 0.8
11.4
-
20
40
60
80
100
120
140
Jun-18 Dec-18 Jun-19 Dec-19 Jun-20 Dec-20 Jun-21 Dec-21 Jun-22 Dec-22 Jun-23 Dec-23
L 3601: Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Loan Amount: US$ 121.50 M
Clo
sin
g D
ate
: 3
0-J
un-2
02
3
144
Transport Sector
Loan 3601-Pak/L3602(COL): Khyber Pakhtunkhwa Provincial Roads Improvement Project
Loan 3602-PAK(COL)
F. Contract Award and Disbursement Targets and Achievements in 2019 Loan 3601-PAK
0.0 0.0
15.8
15.8
0.0 0.0
8.3
17.6
-
2
4
6
8
10
12
14
16
18
20
Jun-18 Dec-20 Dec-23
L 3602- Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Loan Amount: US$ 18.50 M
Clo
sin
g D
ate
: 30-J
un-2
023
0 0 0
3
7
1011
1213
1516
18
- 0.1 0.4 0.4 1.3
2.7
5.2
7.4
10.6
0.0
2.0
4.0
6.0
8.0
10.0
12.0
14.0
16.0
18.0
20.0
2019 Disbursements L3601($0.8 million through Dec 2018)
Projected Actual
0 0 0 0 0 0 0 0 0 0 0
- - - - - - -
0.4 0.4
0
0
0
0
0
0
0
0
0
0
2019 Contract Awards L3601($71.4 million through Dec 2018)
Projected Actual
145
Transport Sector
Loan 3601-Pak/L3602(COL): Khyber Pakhtunkhwa Provincial Roads Improvement Project
Loan 3602-PAK(COL)
G. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
Current Status
1. Shifting of utilities. To expedite the progress of
works, PKHA to ensure that the
utilities are relocated at the
earliest.
Immediate/PKHA Ongoing
H. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. Shifting of utilities. To expedite the progress of works, PKHA
to ensure that the utilities are relocated at
the earliest.
15 Nov / PMU
0 0 0
2
3
5
7
8
10 10 10 10
0.5 1.2
3.6
6.3
9.0 9.2
9.3 9.3
9.3
0.0
2.0
4.0
6.0
8.0
10.0
12.0
2019 Disbursements L3602($8.3 million through Dec 2018)
EA Projection Actual
0 0 0 0 0 0 0 0 0 0 0
- - - - - - - - -0
0
0
0
0
1
1
1
1
1
1
2019 Contract Awards L3602($15.8 million through Dec 2018)
EA Projection Actual
146
Transport Sector
Loan 3756-PAK: Khyber Pakhtunkhwa Provincial Roads Improvement Project- Additional Financing
Loan 3756-PAK: Khyber Pakhtunkhwa Provincial Roads Improvement Project- Additional Financing
A. Loan Basic Data $ Million
Approval Date
Signing Date Effective Date Closing
Date
Closing Date
(Revised)
Elapsed Time %
Project Rating as of
30 Sep 19 7-Dec-2018 26-Feb-2019 25-Jun-2019 30-Jun-24 - 15 Approved Amount
Net Loan Amount
Financing EA/IA Project Officer
Project Analyst
75.00
75.00
OCR
PHA J. Ning G. Jurado
Potential Problem
B. Loan Financial Progress (As of 30 Sep 2019)
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
40.83 34.17 54 40.0 40.83
Disbursements (Cumulative)
Un-disbursed Loan Balance
Disbursement Performance %
Disbursements for 2018
EA’s Projections Actual
1.96 73.04 3 7.0 1.96
C. Project Description The additional financing will widen the 42 km road section between Mardan and Swabi. The additional financing will further strengthen the capacity of the CWD by supporting the government to develop a Khyber Pakhtunkhwa road network master plan for the next 20 years, and by building a central laboratory for the PKHA and providing training to CWD staff. D. Project Monitoring Framework (Current Status)
Outputs Status with Key Activities
Reconstruction of 42 Km of provincial road to 4-lane between Mardan to Swabi, adopting relevant provincial highway standards, road safety improvements, and climate resilience features to withstand damage and disruption from natural disasters
2 civil works contracts under output (i) have been awarded. Work would commence after completion of joint survey.
C&WD’s institutional capacity on road management strengthened.
Ongoing
147
Transport Sector
Loan 3756-PAK: Khyber Pakhtunkhwa Provincial Roads Improvement Project- Additional Financing
E. Cumulative Contract Award and Disbursement Performance
F. Contract Award and Disbursement Targets and Achievements in 2019
40.8
2.0 -
10
20
30
40
50
60
70
80
Sep-19 Jun-22
L 3756- Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Loan Amount: US$ 75.00 M
Clo
sin
g D
ate
: 3
0-J
un
-20
24
0 0 0 0 0 0
2
3
56
6
7
- - - - - - - -
2.0
0.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
2019 Disbursements L3756($0.0 million through Dec 2018)
Projected Actual
0 0
13
27
40 40 40 40 40 40 40
- - - - - -
39.7 40.6 40.8
0
5
10
15
20
25
30
35
40
45
2019 Contract Awards L3756($0.0 million through Dec 2018)
Projected Actual
148
Transport Sector
Loan 3756-PAK: Khyber Pakhtunkhwa Provincial Roads Improvement Project- Additional Financing
G. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
Current Status
1. Relocation of utilities. PKHA to ensure that the
requisite funds to the line
departments are released at the
earliest for smooth and timely
relocation of utilization.
Immediate/PKHA Ongoing
H. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. Shifting of utilities. To expedite the progress of works, PKHA
to ensure that the utilities are relocated at
the earliest.
15 Nov / PMU
149
Transport Sector
TA 8990-PAK: Enabling Economic Corridors through Sustainable Transport Sector Development
TA 8990-PAK: Enabling Economic Corridors through Sustainable Transport Sector Development
A. TA Basic Data US$ (Thousand)
Approval Date
Signing Date
Closing Date
Closing Date (Revised)
Time Elapse
%
Contract Award
(Cumulative)
Disbursements (Cumulative)
17-Nov-15 16-Feb-16 31-Mar-20 - 89 10,183.54 5,627.00 Approved Amount
Net Amount
Financing Project Officer
Project Analyst
Counterpart Agencies
15,406.27 15,406.27 DPECP K. Sakamoto A.
Diamante MO P & D, MO Communications
B. TA Description 1. The TA is in line with the Country Partnership Strategy for Pakistan 2015-2019, which in turn is aligned with the Government of Pakistan's national strategy (Pakistan Vision 2025). One of seven pillars of the national strategy is modernization of transport infrastructure and greater regional connectivity, which this TA directly supports. 2. ADB has provided extensive support to Pakistan's transport sector which has in recent years focused on the upgrading of national highways and construction of new motorways. This is set to continue, with recently approved projects to support the construction of National Highways M-4, and planned projects to further develop CAREC Corridors through a Multitranche Financing Facility (MFF). In addition, projects have also been approved to develop provincial roads in Sindh province, and to improve infrastructure at key border crossing points with neighboring countries. The TA complements these efforts by enhancing the Governments capacity to manage the transport sector effectively, facilitate transport movement with neighboring countries, maintain road assets properly, and ensure safety on the roads being rehabilitated or reconstructed. 3. The TA strongly supports the implementation of the Central Asia Regional Economic Cooperation (CAREC) Transport and Trade Facilitation Strategy 2020, which places emphasis on the completion of six strategic multimodal corridors (two of which pass through Pakistan), and the shift of emphasis toward sustainability and quality of service of these corridors, addressed inter alia through (i) better maintenance of transport assets, (ii) road safety, (iii) transport and trade facilitation, and (iv) a multimodal approach to transport corridor development. These areas are directly supported through this TA.
150
Transport Sector
TA 8990-PAK: Enabling Economic Corridors through Sustainable Transport Sector Development
C. Project Monitoring Framework (Current Status)
Outputs Performance Indicators Status with Key Activities NTP transport policy and master plan developed
NTP and master plan adopted by Cabinet by 2019 (from none in 2015)
• National Transport Policy (NTP) has been approved by the Cabinet in May 2018. New Federal Minister for Planning, Development and Reforms (MPD&R) has also endorsed the policy in November 2018.
• The policy is required to made public and circulated among the relevant Ministries. o Work on Master plan has also commenced. o Preparation of sector-specific policies and
plans are ongoing. o Pakistan Railways Strategic Plan, NHA
Business plan has been completed and requires approval from the competent authority.
o Work on Seaports Development Plan in in progress.
Multimodal transport facilitated within Pakistan and with its neighboring countries
At least three new project pre-feasibility studies completed with multimodal features by 2019 (from none in 2015) At least three capacity building workshops are completed on the implementation of international transport agreements by 2019 (from none in 2015)
• Drafting of a scoping study on transport facilitation has been completed.
• A review of 58 UN conventions relevant to transport facilitation has been completed, and key conventions identified on which focused action may offer Pakistan improved transport competitiveness.
• Based on the above, practical support for the implementation of fundamental international conventions has commenced.
• Various capacity building workshops/trainings at national and international level have been conducted in consultation with the Ministry of Communications.
• On the basis of work to date, efforts are under way to further improve the policy and institutional environment to improve trade and logistics.
• Work on National Freight and Logistics Policy is in progress.
National road safety program implemented
An inter-ministerial body for coordination on road safety matters is operational by 2016 (from none in 2015) A national road safety action plan is adopted by MOC by 2017 (from none in 2015). A national awareness-raising campaign on road safety is completed by 2019 (from none in 2015)
• A road safety working group (RSWG) for TA implementation (facilitated by Ministry of Communications, and participated by National Highway Authority, National Highways and Motorways Police, National Transport Research Centre, Capital Development Authority, Islamabad Police and Ministry of Defense meeting monthly. TA activities aligned and guided by the work of the steering committee for Government of Pakistan’s National Road Safety Framework and Action Plan.
• On 15 November 2018, the Strategy was formally launched by the State Minister for Communications.
151
Transport Sector
TA 8990-PAK: Enabling Economic Corridors through Sustainable Transport Sector Development
By 2019, road standards for all classes of roads updated with road safety features (from none in 2015). National guidelines on vehicle standards and periodic testing, driver licensing and post-crash response are adopted by MOC by 2019 (from none in 2015)
• Design of comprehensive awareness-raising campaign completed, approved by the Federal Minister in October 2019 and is gradually being rolled out.
• Guidelines on vehicle and driver licensing, post-crash response, road crash data management and road safety engineering have also been completed and submitted to the Ministry of Communications for circulation to the federal and provincial authorities.
• Various workshops at federal and provincial level have been conducted to finalized the guidelines.
• Work on Road Safety Law has also commenced. Draft model law has been submitted to the Ministry of Communications for review.
National road asset management system made functional
At least 20 NHA staff trained on the use of new equipment and software for RAM by 2017 (from none in 2015) Financial restructuring plan of NHA’s balance sheet approved by relevant authorities by 2017 (from none in 2015)
• Diagnosis of NHA’s road asset management system (RAMS) has largely been concluded. Outlines of NHA’s business plan has been drafted and underlying analysis on technical, financial and human resources aspects completed.
• Diagnosis of provincial governments’ RAMS capacity is primarily concluded.
• A working group on RAM, led by Ministry of Communications (MoC) has been developed to further steer the work under Phase-2.
• 1st working group meeting has also taken place in October, 2019.
D. Cumulative Contract Award and Disbursement Performance
- -
7,225
8,416 8,625 8,748 9,108 9,177
10,184
10,184
0
8701,543
2,2282,731
3,433 3,697
5,0555,627
-
2,000
4,000
6,000
8,000
10,000
12,000
14,000
Dec-15 Jun-16 Dec-16 Jun-17 Dec-17 Jun-18 Dec-18 Jun-19 Dec-19 Jun-20
(Th -
$)
TA 8990- Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Clo
sin
g: 3
1 M
ar
20
20
Net TA amount: $ 15,406 (Th)
152
Transport Sector
TA 8990-PAK: Enabling Economic Corridors through Sustainable Transport Sector Development
E. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date / By Whom Current Status
1. Formal launch of
National Transport
Policy (NTP).
MPD&R to make the
NTP public and
circulate among the
relevant Ministries for
effective
implementation.
Immediate/MPD&R Pending
2. Notification of Cabinet
Committee on
Transport.
MPD&R to take this
issue with the
competent authority, so
that work on Master
Plan could be
progressed.
Immediate/MPD&R Pending
3. National Transport
Data Observatory
(NTDO).
MPD&R and MoC to
decide
operationalization of
NTDO.
Immediate/MPD&R/M
oC
Under discussion
with MoC and
MPD&R.
4. Notification of working
group on RAMS
MoC to notify the
RAMS working group
so that work could be
progressed.
Immediate/MoC Notified. 1st working
group meeting was
held on 1 October
2019.
5. Pending approval of
Pakistan Railways
Strategic Plan
(PRSP), NHA
Business Plan
Ministry of Railways
(MoR), MoC and NHA
to expedite the
approval of PRSP and
NHA business plan
respectively for its
effective
implementation.
Immediate/MoR/MoC/
NHA
Pending
6. Operationalization of
National Road Safety
Secretariat (NRSS).
MoC to formally make
the NRSS operational
to retain, coordinate
and progress the work
done under Road
Safety, Post Crash
Response, Vehicle and
Driving licensing.
Immediate/MoC. Executive Director
has been appointed
by MoC. However,
funds availability
and hiring of staff is
still pending.
153
Transport Sector
TA 8990-PAK: Enabling Economic Corridors through Sustainable Transport Sector Development
F. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. Formal launch of National
Transport Policy (NTP).
MPD&R to make the NTP public and
circulate among the relevant Ministries for
effective implementation.
Immediate
2. Notification of Cabinet
Committee on Transport.
MPD&R to take this issue with the
competent authority, so that work on
Master Plan could be progressed.
Immediate
3. Pending approval of
Pakistan Railways
Strategic Plan (PRSP),
NHA Business Plan
Ministry of Railways (MoR), MoC and NHA
to expedite the approval of PRSP and NHA
business plan respectively from the
competent authority for its effective
implementation.
Immediate
4. Operationalization of
National Road Safety
Secretariat (NRSS).
MoC to formally make the NRSS
operational to retain, coordinate and
progress the work done under Road
Safety, Post Crash Response, Vehicle and
Driving licensing.
Immediate
154
Transport Sector
TA-8912-Pak: Capacity Building of Institutions Handling Disasters
TA 8912-PAK: Capacity Building of Institutions Handling Disasters
A. TA Basic Data US$ (Thousand)
Approval Date
Signing Date
Closing Date
Closing Date
(Revised)
Time Elapse %
Contract Award
(Cumulative)
Disbursements (Cumulative)
30-Jun-15 4-Aug-15 30-Sep-
18 30-Dec-19 94 1,638.21 1,467.53
Approved Amount
Net Amount
Financing Project Officer
Project Analyst
Counterpart Agencies
2,000.00 2,000.00 TASF M. Shafi H. Ambreen C&W Dept. Punjab / AJK, Irrigation Dept. P&D AJK,
P&D Punjab, PDMA Punjab
B. TA Description 1. A late and concentrated monsoon, coupled with high flows in Pakistan’s eastern rivers resulted in flooding in the northern regions of Pakistan, Punjab and Sindh provinces in September 2014. The flood affected 44 districts across the country. It leads to the displacement of more than 2.5 million people, with major displacement and damage in central Punjab, which resulted in 367 deaths, and injured over 600 people. Nearly 110,000 houses were partially damaged or destroyed, over 1.1 million acres of agricultural land and 250,000 farmers were affected. This resulted in the loss of standing food, fodder or cash crops. Non-farm sources of livelihoods and services were also affected, including many small enterprises, manufacturing and processing businesses and losses of wage employment due to disruption of the economy. 2. In response to Government of Pakistan’s request to provide financial assistance for rehabilitating damaged infrastructure with improved resilience and strengthen its disaster management capacity in flood affected districts of Punjab and Azad Jammu and Kashmir, ADB approved the Flood Emergency Reconstruction and Resilience Project on 31 Dec 2015. ADB’s financial assistance includes a loan from its Ordinary Capital Resource for $218.04 million and a capacity development technical assistance (TA) grant for $2.0 million. The purpose of the TA is to ensure that the emergency assistance is implemented effectively, and efficiently. 3. The objective of the TA is to kick-start all essential project management functions, maintain a high level of dedicated due diligence capacity on all project operations to allow fast-track implementation, and shift the focus in DRM activities from post disaster responses towards disaster preparedness, mitigation and adaptation. The broad terms of reference for the TA include support for (i) establishing management systems in implementing agencies, including monitoring, procurement, financial, and reporting arrangements; (ii) augmenting the social safeguards, procurement, contract management, and technical due diligence capacity of the implementing agencies to fast-track implementation; and (iii) developing linkages to enhance DRM capacities, coordinate MHVRA and disaster mapping activities, and share DRM knowledge. The TA is to be implemented over 36 months starting from 1 July 2015 and cover the geographic area of the FERRP.
155
Transport Sector
TA-8912-Pak: Capacity Building of Institutions Handling Disasters
C. Project Monitoring Framework (Current Status)
Outputs Performance Indicators Status with Key Activities
Flood-damaged roads and bridges in Punjab Province and the districts of Haveli, Kotli, and Poonch reconstructed
By the end of 2018, 1,740 km of damaged provincial highways and district roads repaired, rehabilitated, and reconstructed. By 2018, 173 km of roads and bridges include safety measures that are friendly to women, children, the elderly, and persons with disabilities.
Refer to the relevant section of Summary Sheet of Loan 3264.
DRM strengthened 200 hectares of active slide area along major road corridors treated through bio-engineering interventions by 2018 Enhanced safety procedures for dams and flood protection structures institutionalized in PID by 2018 Land-slide risk mitigation measures include procurement of 30% of the forest nurseries owned by women Gender-disaggregated data and analysis of multi-hazard vulnerability and risk assessments available for 20 most vulnerable districts by 2018
Refer to the relevant section of Summary Sheet of Loan 3264.
Flood-resilient irrigation and flood management infrastructure in Punjab Province implemented
At least 90% of selected flood protection and irrigation structures damaged by 2014 floods reconstructed and made more resilient by 2018
Refer to the relevant section of Summary Sheet of Loan 3264.
156
Transport Sector
TA-8912-Pak: Capacity Building of Institutions Handling Disasters
D. Cumulative Contract Award and Disbursement Performance
E. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No issue related to TA.
F. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No issues
- -0 0
756.74
1,136
1,267 1,265
1,411
1,321
1,425
1,571 1,638
0
0
113.91
268
502
735
1,036 1,106
1,228
1,402 1,468
-
250
500
750
1,000
1,250
1,500
1,750
2,000
Jun-15 Dec-15 Jun-16 Dec-16 Jun-17 Dec-17 Jun-18 Dec-18 Jun-19 Dec-19
(Th -
$)
TA 8912- Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Clo
sin
g: 3
0 D
ec 2
01
9
Net TA amount: $ 2,000 (Th)
157
Transport Sector
TA-9153 Pak: Central Asia Regional Economic Cooperation Railway Connectivity Investment Program
TA 9153-PAK: Central Asia Regional Economic Cooperation Railway Connectivity Investment Program
A. TA Basic Data US$ (Thousand)
Approval Date
Signing Date
Closing Date
Closing Date
(Revised)
Time Elapse
%
Contract Award
(Cumulative)
Disbursements (Cumulative)
10-Aug-16 01-Sep-16 31-Aug-17 31-Aug-20 77 59.08 54.84
Approved Amount
Net TA Amount
Financing Project Officer
Project Analyst
Counterpart Agencies Agencies
1,000.00 1,000.00 TASF J. Sluijter A.
Diamante Ministry of Railways /
Pakistan Railways
B. TA Description
1. The PPTA will (i) develop an MFF and tranche projects bankable by ADB loan; (ii) conduct due diligence for technical, economic, financial, social, and environmental viability of the 1st tranche project and prepare required due diligence documents. 2. The PPTA will design an MFF to assist the government in improving the railway corridor from Lahore to Peshawar. The PPTA will also conduct a feasibility assessment for the 1st tranche project including preliminary engineering designs; cost estimating; technical, financial, economic, and socioeconomic analysis; environmental analysis; social impact assessment; a study for initial benchmark performance indicators; and preparation of project evaluation and monitoring framework. C. Project Monitoring Framework (Current Status)
Major Outputs and Activities Status with Key Activities Railway sector assessment and MFF packaging
ADB’s PPTA consultant team was mobilized in January-February 2017 and commenced the assignment that was to be completed by June 2017. Nonetheless, MoR has advised the Mission of government’s plan to cancel the MFF and shift the entire ML-1 under China-Pakistan Economic Corridor (CPEC) financing. Sensing the finality of the decision, the Mission has immediately instructed PPTA consultant team to demobilize so that no further unnecessary expense will be incurred. On 13 March 2017, ADB received Economic Affairs Division’s (EAD) letter formally advising ADB of the government’s decision. The PPTA consultant’s contract closed on 17 July 2017. The PPTA’s completion date has been extended to 31 August 2020 to implement a revised TA scope and outputs.
Technical feasibility assessment, cost estimation, engineering design, and procurement packaging Environment and social safeguards survey and analysis, validation of indigenous people Social poverty and gender Financial analysis and management assessment
158
Transport Sector
TA-9153 Pak: Central Asia Regional Economic Cooperation Railway Connectivity Investment Program
D. Cumulative Contract Award and Disbursement Performance
E. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No Issues
F. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No Issues
-43 43 43 59 59 59
- 43 43 43 55 55 55
-
200
400
600
800
1,000
Jan-17 Apr-17 Jul-17 Oct-17 Jan-18 Apr-18 Jul-18 Oct-18 Jan-19 Apr-19 Jul-19 Oct-19 Jan-20 Apr-20 Jul-20
(Mill
ion -
$)
TA 9153- Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Clo
sin
g: 3
1 A
ug
20
20
Net TA amount: $ 1,000 (Th)
159
IV. WATER AND OTHER URBAN INFRASTRUCTURE SERVICES
Loans
1. Loan 3543-PAK/Loan 8366(AFD)-Pak: Peshawar Sustainable Bus Rapid Transit Corridor Project
2. Loan 3799/Grant 0649/Loan 8367-PAK(GFC): Karachi Bus Rapid Transit Project
3. Loan 6008: Karachi Bus Rapid Transit Project - Project Design Advance (PDA)
4. Loan 3562-PAK: Punjab Intermediate Cities Improvement Program
5. Loan 6015 /6016-PAK: Khyber Pakhtunkhwa Cities Improvement Project - Project Readiness Financing
Technical Assistance (TAs)
1. TA 9223-PAK: Provincial Strategy for Inclusion and Sustainable Urban Growth
2. TA 9400-PAK: Khyber Pakhtunkhwa Intermediate Cities Improvement Project
3. TA 9465-PAK: Punjab Intermediate Cities Improvement Investment (Phase 2)
160
Water and Urban Infrastructure Services Sector
Loan 3543/8336(AFD)-PAK: Peshawar Sustainable Bus Rapid Transit Corridor Project
Loan 3543/8336(AFD)-PAK: Peshawar Sustainable Bus Rapid Transit Corridor Project
A. Loan Basic Data $ Million
Approval Date
Signing Date
Effective Date
Closing Date
Closing Date (Revised)
Elapsed Time % Project
Rating as of
30 Sep 2019
30-Jun-17 23-Nov-17
12-Sep-17 22-Jan-19
15-Nov-17 22-Jan-19
31-Dec-21 31-Dec-22
– 50 36
Approved Amount
Net Loan Amount
Financing EA/IA Project Officer Project Analyst
335.00 147.76
335.00 143.05
OCR AFD
PDA D. C.
Margonsztern L. Domingo On Track
B. Loan Financial Progress (As of 30 Sep 2019)
Loan 3543
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
302.13 32.87 90 10.00 0.00
Disbursements (Cumulative)
Un-disbursed Disbursement Performance %
Disbursements for 2019
Loan Balance EA’s Projections Actual
297.06 37.94 89 31.00 25.38
Loan 8336(AFD)
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
143.22 (0.17) 100 150.00 143.22
Disbursements (Cumulative)
Un-disbursed Disbursement Performance %
Disbursements for 2019
Loan Balance EA’s Projections Actual
57.75 85.30 40 100.00 57.75
C. Project Description The proposed project will help develop a sustainable urban transport system in Peshawar by delivering the city’s first integrated BRT corridor, directly benefiting 0.5 million people. The project will comprise two interlinked outputs: (i) the construction of a 26-kilometer (km) BRT corridor and associated facilities, and (ii) effective project management and sustainable BRT operations through institutional developments. The project is economically justified by major time savings for future BRT passengers, vehicle operating cost savings, better air quality, and carbon emissions savings, which will improve the health of Peshawar’s citizens and mitigate climate change. The project will also make Peshawar more livable and safer, boost private sector investment, and foster gender equity.
161
Water and Urban Infrastructure Services Sector
Loan 3543/8336(AFD)-PAK: Peshawar Sustainable Bus Rapid Transit Corridor Project
D. Project Monitoring Framework (Current Status) Outputs
Status with Key Activities
1a. 28 km BRT infrastructure, including 32 stations and dedicated lanes completed as per design and scored as “Gold” quality standard [baseline 2017: 0] 1b. Universal accessibility criteria scores maximum points, i.e. 100% of BRT stations achieve universal accessibility for women, children, and PWDs [baseline 2017: 0] 1c. Mixed traffic lane(s), sidewalks, green areas, on-street parking and street lights rebuilt over the whole length of the corridor [general improvement of 2017 baseline] 1d. Bicycle lanes built [baseline 2017: 0] 1e. 2 depots and 1 staging facility building including park-and-ride facilities and commercial areas [baseline 2017: 0] 1f. One office building built for KPUMA, TransPeshawar and BRT control center [baseline 2017: 0] 1g. 100 bus stops installed over 54-km of bus routes off the BRT corridor [baseline 2017: 0] 1h. One parking plaza built in Lady Reading Hospital [baseline 2017: 0] 1i. Number of safe (signalized at-grade, bridge or tunnel) pedestrian crossings of the BRT corridor increase to 78 [baseline 2016: 62 crossings, of which 50% are at-grade and unsafe] By 2020: 2a. 447 9-meter and 12-meter modern BRT buses procured [baseline 2017: 0] 2b. Distance-based fare collection system, BRT control center, and other ITS procured and installed by TransPeshawar to operate BRT services [baseline 2017: 0]
Design of the whole 28 km corridor completed based on Gold standard. All six major civil works contracts awarded, and construction works progressing at full speed. ITS contract will be awarded in December 2018 Universal access built into the design of all BRT station. The reconstruction of the whole corridor including footpaths, roads, street lights and bicycle lanes included in the project design that has been awarded for construction. Bicycle lanes included in the detailed design Park-and-ride facility and commercial areas included in the design of both depots and the staging facility, for which contracts have been awarded and construction is ongoing. The building housing KPUMA, TransPeshawar and Control center designed in Chamkani, contract has been awarded and building is currently under construction. The cost and design of 100 bus stops included in the tender documents for the three reaches of the BRT corridor which have been awarded. Still to be decided – no progress yet Safe crossing in most cases grade separated have been built in the operational model and system design that has been tendered. Contract for 220 hybrid electric plug in design buses (155 12-meter buses, and 65 18-meter buses) awarded. Prototypes have been tested and final design has been agreedManufacturing is in progress for first batch delivery in March 2091. Operational model has been developed to eliminate subsidy based on current demand projections. The ITS contract was awarded in December 2018.
162
Water and Urban Infrastructure Services Sector
Loan 3543/8336(AFD)-PAK: Peshawar Sustainable Bus Rapid Transit Corridor Project
Outputs
Status with Key Activities
2c. TransPeshawar and KPUMA are fully staffed (10% of female staff) and staff received trainings, as per their respective organizational development plans [baseline 2017: 0] 2d. 10% of operations and maintenance staff are women [baseline 2017: 0] 2e. Subsidy to BRT operations and maintenance cost is not required [baseline 2017: 0% subsidy to public transport] 2f. Average bus commercial speed on BRT corridor increased to 25 km/hour [baseline 2016: 12.2 km/hour] 2g. Multi-media behavior campaigns on the safety of all passengers including women, children, elderly, and PWDs, reached at least 480,000 riders [baseline 2017: 0]
About 50% of TransPeshawar hired (27 staff with 10% women) and in place. Hiring for remaining staff will continue as required. Training already started in some area like procurement. Hiring of KPUMA staff has not started is awaiting government approval. Hiring not yet due Operational model is being fine-tuned to ensure no or limited subsidy The system and operational model have been designed to increase average speed to around 26 Km per hour Currently being designed – yet to be started
E. Cumulative Contract Award and Disbursement Performance L3543-PAK
163
Water and Urban Infrastructure Services Sector
Loan 3543/8336(AFD)-PAK: Peshawar Sustainable Bus Rapid Transit Corridor Project
L8336-PAK(AFD)
F. Contract Award and Disbursement Targets and Achievements in 2019 L3543-PAK(AFD)
0.0
111.4
143.2
0.0
53.2
57.7
-
20
40
60
80
100
120
140
160
Dec-18 Jun-19 Dec-19 Jun-20 Dec-20 Jun-21 Dec-21 Jun-22 Dec-22 Jun-23
L 8336- Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Loan Amount: US$ 143.05 M
Clo
sin
g D
ate
: 31-D
ec-
0 0 0 0 0 0 0 0
3
7
10
0 00
0 0 0 0 0
0
2
4
6
8
10
12
2019 Contract Awards($335.0 million through Dec 2018)
EA Projection Actual
37
1013
17
2022
2426
2829
31
78
13 13
19 19
2325
0.0
5.0
10.0
15.0
20.0
25.0
30.0
35.0
2019 Disbursement($271.7 million through Dec 2018)
EA Projection Actual
164
Water and Urban Infrastructure Services Sector
Loan 3543/8336(AFD)-PAK: Peshawar Sustainable Bus Rapid Transit Corridor Project
L8336-PAK(AFD)
G. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
Current Status
1. Delay in KPUMA
establishment
Approval of the revised
organogram, position TORs and
budget
KPUMA Board by 15
Sep 2019
KPUMA Board
still awaited. No
progress on the
recruitments.
2. Delay in
implementation
of bus industry
restructuring
policy
- TransPeshawar is currently conducting verification of applications of Vehicles Scrapping. Scrutiny and Physical Verification Committee of the Government will be presented the findings for approval before disclosure. - Tender Document for Vehicle Scrapping has been finalized and is with BOD for review. Tender being planned for advertisement. - Compensation for Bus Owner
will commence in Sep 2019
subject to completion of main
corridor and inauguration of the
operations of buses on main
corridor.
TransPeshawar by 15 August 2019 TransPeshawar by September 2019 TransPeshawar in
December 2019 or
January 2020 on the
assumption that
works would have
completed and
operations will start
within this time frame
Bus Industry Restructuring Policy (BIRP) to be endorsed by ADB within October, upon which TPC will claim for the BIRP budget and will start implementing.
1020
3040
50
6068
7785
9095
100
0 0 0 0
5358 58 62
0.0
20.0
40.0
60.0
80.0
100.0
120.0
2019 Disbursements L8336($0.0 million through Dec 2018)
Projected Actual
100
150 150 150 150 150 150 150 150 150 150
41 43
120 116 111 113 114
143
0
20
40
60
80
100
120
140
160
2019 Contract Awards L8336($0.0 million through Dec 2018)
Projected Actual
165
Water and Urban Infrastructure Services Sector
Loan 3543/8336(AFD)-PAK: Peshawar Sustainable Bus Rapid Transit Corridor Project
H. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. Delay in KPUMA
establishment
Approval of the revised organogram,
position TORs and budget
Recruitments to be finalized.
KPUMA Board in Q4
2019
2. Delay in implementation of
bus industry restructuring
policy
- Bus Industry Restructuring Policy (BIRP) to be endorsed by ADB - TransPeshawar is conducting verification of applications of Vehicles Scrapping. Scrutiny and Physical Verification Committee of the Government will be presented the findings for approval before disclosure. - Compensation for Bus Owner will
commence in Q4 2019 subject to
completion of main corridor and
inauguration of the operations of buses on
main corridor.
ADB by October 2019 TransPeshawar by 15 August 2019 TransPeshawar in
December 2019 or
January 2020 on the
assumption that
works would have
completed and
operations will start
within this time
frame
166
Water and Urban Infrastructure Services Sector
Loan 3799/Grant 0649/Loan 8367-PAK(GFC): Karachi Bus Rapid Transit Project
Loan 3799/Grant 0649/Loan 8367-PAK(GFC): Karachi Bus Rapid Transit Project
A. Loan Basic Data $ Million
Approval Date
Signing Date Effective
Date Closing
Date Closing Date
(Revised) Elapsed Time %
Project Rating as of
30 Sep 19
05-Jul-19 - - 30-Jun-24 - 5 Approved Amount
Net Loan Amount
Financing EA/IA Project Officer Project Analyst
11.8 235.0 37.20
11.8 235.0 37.2
GCF OCR GCF
P&D Sindh
D. C. Margonsztern
L J. Domingo
N/A
B. Loan Financial Progress (As of 30 Sep 2019) Loan 3799
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
- 235.00 - 0.00 0.0
Disbursements (Cumulative)
Un-disbursed Loan Balance
Disbursement Performance %
Disbursements for 2019
EA’s Projections Actual
- 235.00 - 0.0 0.0
Grant 0649
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
- 11.80 - 0.00 0.0
Disbursements (Cumulative)
Un-disbursed Loan Balance
Disbursement Performance %
Disbursements for 2019
EA’s Projections Actual
- 11.80 - 0.0 0.0
Loan 8367
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
- 37.20 - 0.00 0.0
Disbursements (Cumulative)
Un-disbursed Loan Balance
Disbursement Performance %
Disbursements for 2019
EA’s Projections Actual
- 37.20 - 0.0 0.0
C. Project Description The proposed project will help increase the use of quality public transport in Karachi by delivering the 26.6-kilometer (km) Bus Rapid Transit (BRT) Red Line corridor and associated facilities, directly benefiting 1.5
167
Water and Urban Infrastructure Services Sector
Loan 3799/Grant 0649/Loan 8367-PAK(GFC): Karachi Bus Rapid Transit Project
million people. The project is economically justified by major time savings for BRT passengers; vehicle operating cost savings; and better air quality and reduced carbon emissions through an innovative waste-to-fuel scheme, which will improve the public health and mitigate climate change. It will also make Karachi safer, greener, and more inclusive and competitive. The project is aligned with the following impact: quality of life in Karachi improved. The project will have the following outcome: use of quality public transport in Karachi increased. D. Project Monitoring Framework (Current Status) Project is not yet effective. E. Cumulative Contract Award and Disbursement Performance
Project is not yet signed. F. Contract Award and Disbursement Targets and Achievements in 2019 Project is not yet signed. G. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. Pending status of co-
financing
Ongoing negotiation of the FAA with the
GCF. Signing is expected by the end of
2019.
ADB and GCF by
Dec 2019
168
Water and Urban Infrastructure Services Sector
Loan 6008: Karachi Bus Rapid Transit Project - PDA
Loan 6008-PAK: Karachi Bus Rapid Transit Project - Project Design Advance (PDA)
A. Loan Basic Data $ Million
Approval Date
Signing Date Effective
Date Closing
Date Closing Date
(Revised) Elapsed Time %
Project Rating as of
30 Sep 19
29-Sep-16 17-Nov-16 17-Nov-16 30-Oct-18 30-Oct-19 97 Approved Amount
Net Loan Amount
Financing EA/IA Project Officer Project Analyst
9.70 9.70
OCR
P&D Sindh
D. C. Margonsztern
L J. Domingo
Potential Problem
B. Loan Financial Progress (As of 30 Sep 2019)
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
9.01 0.69 93 0.00 0.0
Disbursements (Cumulative)
Un-disbursed Loan Balance
Disbursement Performance %
Disbursements for 2019
EA’s Projections Actual
6.67 3.03 69 5.0 3.17
C. Project Description The project will contribute to developing a sustainable urban transport system in Karachi through the delivery of a bus rapid transit (BRT) corridor, focusing on accessibility and people’s mobility needs. It will aim at organizing the urban growth and public space along the selected corridor through integration of land-use and transport planning (transit-oriented development), making the city more pleasant to live in, providing a holistic solution for integrated urban mobility, and bearing a demonstration value as no modern mass transit system exists in Karachi yet.
169
Water and Urban Infrastructure Services Sector
Loan 6008: Karachi Bus Rapid Transit Project - PDA
D. Cumulative Contract Award and Disbursement Performance
E. Contract Award and Disbursement Targets and Achievements in 2019
0.0
4.6
8.5 8.5 8.5 8.2 8.2
9.0
0.0 0.0
1.6
2.8 2.9
3.5
5.0
6.7
-
2
4
6
8
10
12
Dec-16 Apr-17 Aug-17 Dec-17 Apr-18 Aug-18 Dec-18 Apr-19 Aug-19 Dec-19 Apr-20
L 6008: Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Loan Amount: US$ 9.70 M
Clo
sin
g D
ate
: 3
0-O
ct-
20
19
Clo
sin
g D
ate
: 30-O
ct-
2019
0.0 0.0 0.00.5
1.01.5
2.2
2.8
3.54.0
4.5
5.0
0.8 0.8 0.8 0.8 1.3
1.5
2.6 2.6
3.2
0.0
1.0
2.0
3.0
4.0
5.0
6.0
2019 Disbursements L6008($3.5 million through Dec 2018)
EA Projection Actual
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
- - - - - - - - -0
0
0
0
0
1
1
1
1
1
1
2019 Contract Awards L6008($8.2 million through Dec 2018)
EA Projection Actual
170
Water and Urban Infrastructure Services Sector
Loan 6008: Karachi Bus Rapid Transit Project - PDA
F. Status of the Action Plan discussed in 2nd TPR
Sr. No
Issue Action to be Taken Due Date / By Whom
Current Status
1. Recruitment of TransKarachi’s core management team and PIU core staff, which is a condition to proceed to loan negotiations.
1. Summary of approval for 6-month budget to cater for the company’s OPEX need of PKR 80 million was submitted to CM for approval in Sepe 2019. CM approval is awaited. 2. GoS to facilitate clearances and administrative procedures to speed up PIU and TransKarachi recruitments. PMCCD has already shortlisting candidates. Interviews of key core staff expected were expected in third week of July 2019 that did not happen due to GoS concerns regarding the bard. The GOS to resolve the BOD issues of TransKarachi in consultation with ADB and complete the hiring of all staff by Q3 2019.
The Summary has been approved. MoF to release the funds to TransKarachi by 15 September 2019 PMCCB, Q3 2019
Slow progress in recruitments for TKC. Interviews for core management team scheduled from 15 to 18 October. Replacement of the Chairman of the Board required. This will delay loan signing to Q1 2020 and loan effectiveness to Q2 2020. Interim budget for TKC approved by GoS but not yet available as the BoD has not opened an advance account. Action expected to be taken by the end of November.
2. Delay in payments and approval of contract variations for on-going consulting contracts under PDA
1. SMTA and PIU to release withheld payments for ODBM and PMCCB, in light of resolution on the tax issue by ODBM which is still pending with FBR. However Interim 3 and 4 payments were partially released to the consultants. 2. SMTA and PIU to negotiate a contract variation with EPCM to cater for additional requirements / activities. Other possible solutions to outsource the additional activities through a VO in ODBM’s contract or hiring of new firm are also being deliberated.
All outstanding
payments of
OBDM already
released by
SMTA.
Payments worth
$0.5 million for
EPCM would be
released by Q3
2019
SMTA by Q3
2019
Further payments have
been made recently to
PMCCB and PIU staff.
Pending payments to
EPCM expected within
October 2019.
3. Advance Actions
GoS to finalize the utility re-location plan and modality which each utility, sign MOUs to on the scope, timelines and implementation modality based on which the cost of utility relocation should either be
PMU/SMTA/GOS
by 15 September
2019
Discussions are on-
going on the utility
relocation plan. Bidding
documents for civil
works still under
revisions and
171
Water and Urban Infrastructure Services Sector
Loan 6008: Karachi Bus Rapid Transit Project - PDA
Sr. No
Issue Action to be Taken Due Date / By Whom
Current Status
transferred to the utility or included in the scope of the respective civil works contracts of the BRT. SMTA to incorporate ADB comments in the bidding documents and re-submit for ADB approval so that the procurement process gets started.
SMTA by 5
September 2019
improvements are being
made in Section 6.
Further amendments
may be brought to
include a performance-
based maintenance
contract under the civil
works contract.
Updated and improved
bidding documents are
expected to be
resubmitted for OGC
and PPFD’s review
within November 2019.
Upon clearance by
ADB, advertisement is
expected in January
2020.
G. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. Recruitment of core staff Interviews for core management team
scheduled from 15 to 18 October.
Replacement of the Chairman of the
Board required which will delay loan
signing and effectiveness to Q1 2020 and
Q2 2020 respectvely.
SMTA and TKC to
complete
recruitment by Q4
2019
2. Advance account Advance account to be opened for
counterpart funds to be credited and made
available for utilization
GOS FD, TKC
Board by Nov 2019
3. EPCM Consultant
Payments
SMTA and PIU to negotiate a contract
variation with EPCM to cater for additional
requirements / activities and clear the
pending payments
SMTA, PIU, TKC by
October 2019
4. Civil works contracts Updated and improved bidding documents
are expected to be resubmitted for OGC
and PPFD’s review within November
2019. Upon clearance by ADB,
advertisement is expected in January
2020
TKC by November
2019
172
Water and Urban Infrastructure Services Sector
Loan 3562: Punjab Intermediate Cities Improvement Investment Project
Loan 3562-PAK: Punjab Intermediate Cities Improvement Investment Project
A. Loan Basic Data $ Million
Approval Date Signing Date Effective
Date Closing
Date Closing Date
(Revised) Elapsed Time % Project
Rating as of
30 Sep 19
19-Sep-2017 18-Dec-2017 16-Mar-2018 30-Jun-24 – 30 Approved Amount
Net Loan Amount
Financing EA/IA Project Officer
Project Analyst
200.00 200.00 OCR GoP M. Shafi M.A.
Sheikh Actual
Problem
B. Loan Financial Progress (As of 30 Sep 2019)
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2018
Projections Actual
2.30 197.70 1 38.00 0.00
Disbursements (Cumulative)
Un-disbursed Loan Balance
Disbursement Performance %
Disbursements for 2018
Projections Actual
11.16 188.84 6 7.15 0.00
C. Project Description The project will improve the quality of life of the residents in the two intermediate cities of Sahiwal and Sialkot in Punjab Province, making these cities more livable and sustainable. This will be achieved by improving urban infrastructure and services, and operations and maintenance capacity for urban service delivery. D. Project Monitoring Framework (Current Status)
Outputs Status with Key Activities
Output 1: Water Supply Systems Improved Rehabilitation of 114 Boreholes and tube wells [baseline: 0]
Feasibility Studies and preliminary designs were prepared in Q2 2017. Recruitment of Engineering, Procurement, Construction Supervision (EPCM) consultant was completed in April 2019 and mobilized in May 2019.
Construction of 22 Water reservoirs in Sahiwal and Sialkot.
EPCM consultant was mobilized in May 2018. The consultant will check the validity of preliminary designs and complete DEDs in 2019 (while the EPCM firm focused on other components)
173
Water and Urban Infrastructure Services Sector
Loan 3562: Punjab Intermediate Cities Improvement Investment Project
Outputs Status with Key Activities Rehabilitation and construction of 20 water pumping stations [baseline: 0]
EPCM firm was recruited in May 2018, had submitted the master plan of Sahiwal on 30 April 2019 and of Sialkot on 25 Sepe 2019. The master plan has been submitted to the technical committee and other decision-making authorities for approval and prioritization of the packages. This is currently ongoing and is expected to be completed by Q1 2020. ADB and EA have agreed to consolidate this component under Package [PICIIP03]
Rehabilitation of approx. 390 km of Water pipes [baseline: 0]
EPCM firm was recruited in May 2018, had submitted the master plan of Sahiwal on 30 April 2019 and of Sialkot on 25 Sepe 2019. The master plan has been submitted to the technical committee and other decision-making authorities for approval and prioritization of the packages. This is currently ongoing and is expected to be completed by Q1 2020. ADB and EA have agreed to consolidate this component under Package [PICIIP03]
Procurement and Installation of supervisory control and data administration (SCADA) [baseline: 0]
EPCM firm was recruited in May 2018, had submitted the master plan of Sahiwal on 30 April 2019 and of Sialkot on 25 Sepe 2019. The master plan has been submitted to the technical committee and other decision-making authorities for approval and prioritization of the packages. This is currently ongoing and is expected to be completed by Q1 2020. ADB and EA have agreed to consolidate this component under Package [PICIIP04]
Procurement and Installation of up to 16,600 Metered customer connections (1,400 pre-paid meter) [baseline: 0]
EPCM firm was recruited in May 2018, had submitted the master plan of Sahiwal on 30 April 2019 and of Sialkot on 25 Sepe 2019. The master plan has been submitted to the technical committee and other decision-making authorities for approval and prioritization of the packages. This is currently ongoing and is expected to be completed by Q1 2020. ADB and EA have agreed to consolidate this component under Package [PICIIP04]
Development of distribution Network Improvement (DNI) zones and Non-Revenue Water (NRW) program [baseline: 0]
EPCM firm was recruited in May 2018, had submitted the master plan of Sahiwal on 30 April 2019 and of Sialkot on 25 Sepe 2019. The master plan has been submitted to the technical committee and other decision-making authorities for approval and prioritization of the packages. This is currently ongoing and is expected to be completed by Q1 2020. ADB and EA have agreed to consolidate this component under Package [PICIIP04]
Output 2: Sanitation Systems Improved Construction of 18 Sewage pumping stations [baseline: 0]
EPCM firm was recruited in May 2018, had submitted the master plan of Sahiwal on 30 April 2019 and of Sialkot on 25 Sepe 2019. The master plan has been submitted to the technical committee and other decision-making authorities for approval and prioritization of the packages. This is currently ongoing and is expected to be completed by Q1 2020. Procurement package [PICPIIP08] will be tendered by Q4 2019.
Replacement of approx. 40 km Sewer pipes [baseline: 0]
EPCM firm was recruited in May 2018, had submitted the master plan of Sahiwal on 30 April 2019 and of Sialkot on 25 Sepe 2019. The master plan has been submitted to the technical committee and other decision-making authorities
174
Water and Urban Infrastructure Services Sector
Loan 3562: Punjab Intermediate Cities Improvement Investment Project
E. Cumulative Contract Award and Disbursement Performance
for approval and prioritization of the packages. This is currently ongoing and is expected to be completed by Q1 2020. Procurement package [PICPIIP08] will be tendered by Q4 2019.
Construction of centralized wastewater treatment plant [baseline: 0]
EPCM firm was recruited in May 2018, had submitted the master plan of Sahiwal on 30 April 2019 and of Sialkot on 25 Sepe 2019. The master plan has been submitted to the technical committee and other decision-making authorities for approval and prioritization of the packages. This is currently ongoing and is expected to be completed by Q1 2020. Procurement package [PICPIIP08] will be tendered by Q4 2019.
Output 3: Urban Public Spaces Improved Rehabilitation of 3 Bus terminals [baseline: 0]
Three bus terminals will be upgraded. However, there are certain land acquisition issues. Decision on pursuing bus terminals is yet to be decided.
Rehabilitation of 2.5 km Riverbank paths [baseline: 0]
EPCM consultant is mobilized in May 2018. Procurement is currently ongoing and contract is expected to be awarded in Q2 2020.
Development of 7 km Green belts [baseline: 0]
EPCM consultant is mobilized in May 2018. Procurement is currently ongoing and contract is expected to be awarded in Q2 2020..
2.7 2.7 2.5 2.5
11.2 11.2 11.2 11.2
-
50
100
150
200
250
Jun-18 Dec-20 Dec-23
L 3562- Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Loan Amount: US$ 200.00 M
Clo
sin
g D
ate
: 30-J
un-2
024
175
Water and Urban Infrastructure Services Sector
Loan 3562: Punjab Intermediate Cities Improvement Investment Project
F. Contract Award and Disbursement Targets and Achievements in 2019
G. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
Current Status
1. Project Scope Restructuring of the project
scope: Master plan for water
supply and sanitation has been
prepared which is under review
by concerned stakeholders for
scope finalization and
prioritization. In August 2019, the
master plan for Sahiwal was
approved by the government.
Q4 2019/P&DD
LG&CDD
Master plans
were approved
2. Hiring of OBDM
Consultants
Recruitment of operational design
& business model (ODBM)
consultants: EOI were floated in
July 2019 and interests are
expected by 9 September 2019.
Final proposal and recruitments
are expected before 31
December 2019.
Q4
2019/LG&CDD
Submission 1
was approved,
and RFP will be
issued
3. EPCM Consultants Variation order is pending to
incorporate additional scope of
work in Sialkot and Sahiwal for
the Engineering Procurement and
Construction Management
(EPCM) consultant. NESPAK and
PMU/LG&CDD need to agree on
Q3
2019/LG&CDD
Variation
pending
0.1 0.1 0.20.8
1.42.1
2.63.1
3.7
4.8
6.0
7.2
- - - - - - - - -
0.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
2019 Disbursements L3562($11.2 million through Dec 2018)
EA Projection Actual
0.0 0.0
4.3
8.7
13.015.3
17.720.0
26.0
32.0
38.0
- - - - - - - - -
0
5
10
15
20
25
30
35
40
2019 Contract Awards L3562($2.5 million through Dec 2018)
EA Projection Actual
176
Water and Urban Infrastructure Services Sector
Loan 3562: Punjab Intermediate Cities Improvement Investment Project
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
Current Status
the variation and communicate
the decision to ADB at the
earliest.
4. Procurement of
Phase 1 works and
goods packages
Complete procurement and
contract award of Phase 1 works
and goods contract in Sialkot and
Sahiwal amounting to USD 60
million. The status of the
procurement is as follows:
(i) Works package: process is
almost 90% complete as the price
bid evaluation report has been
approved and letter of award is
pending subject to PDWP
approval;
(ii) Goods package: process is
almost 50% complete as price
bids were opened and PBER is
pending submission; and
(iii) PLGA building: IFB for the
package will be published by 24
Aug 2019.
Sep
2019/LG&CDD
Oct
2019/LG&CDD
Dec
2019/LG&CDD
Procurement is
underway and
making progress.
Contract for
works has been
awarded and
goods will be
awarded in 3rd
week of October.
PLGA building
contract is on
schedule for
being awarded
by Dec 2019
H. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. Restructuring of the project
scope
In August 2019, the master plan for
Sahiwal was approved by the Government,
whereas the approval of the master plan for
Sialkot and scope finalization and
prioritization is still awaited. Prioritization of
key subprojects, and their procurement and
implementation schedule need to be
finalized, based on which the CAD
projections will be revised to make them
consistent with the revised procurement
and implementation schedule.
PMU / LGCCD by
November 2019
2. Land Acquisition Government of Punjab has to acquire 400 acres (3 Sites) identified for sewerage treatment plants (STP) in Sahiwal and Sialkot. Award of civil works contracts of $130 million (Water Supply and Sanitation component) schemes prioritized under master planning will remain subject to land acquisition of STP sites in both cities. The
PMU / LGCCD by
December 2019
177
Water and Urban Infrastructure Services Sector
Loan 3562: Punjab Intermediate Cities Improvement Investment Project
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
plan for land acquisition for STP as well as Land Fill Sites have to be finalized along with options of ADB financing the land acquisition.
3. Variation in Consultants’
Contract
A variation in the EPCM consultants’
contract is pending to incorporate additional
scope of work in Sialkot and Sahiwal. The
PMU and consultants need to agree on the
details of the variation and communicate
the decision to ADB. Revised PC-Il for
EPCM consultant also needs to be
submitted to PDWP for approval.
PMU and NESPAK
by Q4 2019
4. Hiring of Consultant
Firms/Individual
Consultants
Project scope initially included hiring of
Project Management, Coordination and
Capacity Building Consultant (Firm) under
the institutional support. The P&DD later
decided to hire individual consultants
instead of the firm to help the PMU for
required due diligence and capacity
development. PMU is to prepare PC-II for
the required inputs, process necessary
approvals and hire/mobilize required
individual consultants by Dec 2019.
Project also requires services of
Operational Design & Business Model
(ODBM) consultants. EOI were floated in
July 2019 and received by 18 September
2019. Submission 1 was approved in
October 2019 and RFP is yet to be issued.
PMU / LGCCD by
December 2019
PMU / LGCCD by
November 2019
5. Pending Withdrawal
Application
PMU to send WA to liquidate advance of
$10.9million which has not been turned
over since inception
PMU by 31 October
2019
178
Water and Urban Infrastructure Services Sector
Loan 6015-PAK/6016-PAK: Khyber Pakhtunkhwa Cities Improvement Project - PRF
Loan 6015 /6016-PAK: Khyber Pakhtunkhwa Cities Improvement Project - Project Readiness Financing
A. Loan Basic Data $ Million
Approval Date Signing Date Effective
Date Closing
Date Closing Date
(Revised) Elapsed Time % Project
Rating as of
30 Sep 19
15-Mar-2019 29-Mar-2019 30-Apr-2019 28-Aug-24 – 10 Approved Amount
Net Loan Amount
Financing EA/IA Project Officer
Project Analyst
7.00 2.00
7.00 2.00
OCR UCCRT
P&DD KPK
K. Nakamitsu
L. Buenavent
e
Actual Problem
B. Loan Financial Progress (As of 30 Sep 2019) Loan 6015
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
2.95 4.05 42 5.0 2.95
Disbursements (Cumulative)
Un-disbursed Loan Balance
Disbursement Performance %
Disbursements for 2018
EA’s Projections Actual
0.00 7.00 0 0.5 0.00
Loan 6016
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
0.91 1.09 45 1.00 0.91
Disbursements (Cumulative)
Un-disbursed Loan Balance
Disbursement Performance %
Disbursements for 2018
EA’s Projections Actual
0.00 2.00 0 0.5 0.00
C. Project Description The Khyber Pakhtunkhwa Cities Improvement Projects (KPCIP) will improve the quality of life of the residents of at least four cities, including Abbottabad, Kohat, Mardan, and Peshawar, directly benefitting about 3.5 million of urban population. The KPCIP will help selected cities improve their access to quality urban services through two interlinked outputs: (i) enhanced municipal infrastructure and public urban spaces, and (ii) strengthened institutional capacities and efficiency of provincial, municipal and city governments and urban service companies. The project readiness financing (PRF) will finance the preparation and engineering design of the KPCIP and possible future pipeline of urban projects in KPK. The PRF will ensure high project readiness of the KPCIP, thereby facilitating the timely and cost-effective achievement of the project outcomes.
179
Water and Urban Infrastructure Services Sector
Loan 6015-PAK/6016-PAK: Khyber Pakhtunkhwa Cities Improvement Project - PRF
D. Cumulative Contract Award and Disbursement Performance L6015-PAK
L6016-PAK
2.9 2.9
0.0 0.0
-
1
2
3
4
5
6
7
8
Jun-19 Dec-19 Jun-20 Dec-20 Jun-21 Dec-21 Jun-22 Dec-22 Jun-23 Dec-23 Jun-24 Dec-24 Jun-25
Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Loan Amount: US$ 7.00 M
Clo
sin
g D
ate
: 2
8-A
ug
-20
24
0.0
0.9
0.0 0.0
-
1
1
2
2
3
Jun-19 Dec-19 Jun-20 Dec-20 Jun-21 Dec-21 Jun-22 Dec-22 Jun-23 Dec-23 Jun-24 Dec-24 Jun-25
L 6016- Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Loan Amount: US$ 2.00 M
Clo
sin
g D
ate
: 2
8-A
ug
-20
24
180
Water and Urban Infrastructure Services Sector
Loan 6015-PAK/6016-PAK: Khyber Pakhtunkhwa Cities Improvement Project - PRF
E. Contract Award and Disbursement Targets and Achievements in 2019 L6015-PAK
L6016-PAK
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.2
0.3
0.5
- - - - - - - - -
0.0
0.1
0.2
0.3
0.4
0.5
0.6
2019 Disbursements L6015($0.0 million through Dec 2018)
EA Projection Actual
0.0 0.0 0.0 0.0 0.0
1.7
3.3
5.0 5.0 5.0 5.0
- - - - -
2.9 2.9 2.9 2.9
0
1
2
3
4
5
6
2019 Contract Awards L6015($0.0 million through Dec 2018)
EA Projection Actual
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.2
0.3
0.5
- - - - - - - - -
0.0
0.1
0.2
0.3
0.4
0.5
0.6
2019 Disbursements L6016($0.0 million through Dec 2018)
Projected Actual
0.0 0.0 0.0 0.0 0.0
0.0 0.0
0.3
0.7
1.0
- - - - - -
0.6 0.6
0.9
0
0
0
1
1
1
1
2019 Contract Awards L6016($0.0 million through Dec 2018)
Projected Actual
181
Water and Urban Infrastructure Services Sector
Loan 6015-PAK/6016-PAK: Khyber Pakhtunkhwa Cities Improvement Project - PRF
F. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
Current Status
1 No disbursements
are made due to
delay in opening
project bank
account. PMU
agreed to achieve
this goal by May
2019 but still not
yet achieved.
PRM team is requested to
work with PMU-KPCIP to
support the opening of the
account. The first WA
application, submitted in
July, will be processed as
soon as the account is
opened.
End of August. Advance account of
$0.6m disbursed on
7 October. Payment
for inception report
milestone of EDCM
firm ($.3m) by end
October 2019
2 Delay in PMU
consultants
3 out of 9 core PMU staff
positions have been
recruited. Shortlisting of
remining 4 positions is
ongoing while 2 positions
will be advertised.
Activity expected to
be completed by 10
September 2019.
8 PMU consultants
have been engaged.
Three third party
review consultants to
be engaged by close
of 2019.
3 DED Consultants Delays in DED
Consultants were
mobilized. The inception
report of the consultants to
define the scope of the
first phase and its
timelines is due.
Inception report will
be submitted by 10
September 2019
Inception report
submitted
4 Incomplete
planning in the 5
cities
To ensure that that
identified investments are
in line with broader growth
and development pattern
of each city, land use plan
and sector master plans
are needed for each city. A
broad status of where
each city in terms of
planning and the additional
work required to produce
these plans has been
identified. This additional
work needs to be included
in the scope of the existing
ADB or included in the
scope of the EPCM
contract through a
variation
UPU in consultation
with ADB to decide
the scope of the
variation to include
planning work in the
contract of EPCM
and issue the
required variation by
30 Sep 2019
Pending
182
Water and Urban Infrastructure Services Sector
Loan 6015-PAK/6016-PAK: Khyber Pakhtunkhwa Cities Improvement Project - PRF
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
Current Status
5 Institutional
Development and
Capacity Building
Consultants (IDCB)
that will develop the
operational plans,
conceptual design
and business plans
have still not been
hired.
The work of the IDCB
consultant is crucial to
ensure quality selection of
investments that are within
the operational resources
and capability of the
respective cities
(sustainable operation). 8
EOIs have been submitted
and shortlisting for IFP is
ongoing. TORs will be
updated by HQs in
coordination with PRM
UPU/PMU/ADB to
complete the hiring
process of IDCB
consultants before
30 November 2019.
Pending
G. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. Payment to EDCM Firm Payment to EDCM Firm of $0.3 million
against inception report.
End of October
2019.
2. Delay in PMU consultants Three third party review consultants to be
engaged by close of 2019.
UPU/PMU by Dec
2019
3. Incomplete planning in the
5 cities
To ensure that that identified investments
are in line with broader growth and
development pattern of each city, land use
plan and sector master plans are needed
for each city. A broad status of where
each city in terms of planning and the
additional work required to produce these
plans has been identified. This additional
work needs to be included in the scope of
the existing ADB or included in the scope
of the EPCM contract through a variation
UPU in consultation
with ADB to decide
the scope of the
variation to include
planning work in the
contract of EPCM
and issue the
required variation in
Q4 2019
4. Institutional Development
and Capacity Building
Consultants (IDCB) that
will develop the
operational plans,
conceptual design and
business plans have still
not been hired.
The work of the IDCB consultant is crucial
to ensure quality selection of investments
that are within the operational resources
and capability of the respective cities
(sustainable operation). 8 EOIs have been
submitted and shortlisting for IFP is
ongoing. TORs will be updated by HQs in
coordination with PRM
UPU/PMU/ADB to
complete the hiring
process of IDCB
consultants before
30 November 2019.
183
Water and Urban Infrastructure Services Sector
TA 9223-PAK: Provincial Strategy for Inclusion and Sustainable Urban Growth
TA 9223-PAK: Provincial Strategy for Inclusive and Sustainable Urban Growth
A. TA Basic Data US$ (Thousand)
Approval Date
Signing Date
Closing Date
Closing Date
(Revised)
Time Elapse
%
Contract Award (Cumulative)
Disbursements (Cumulative)
07-Nov-16 02-Dec-16 31-Dec-18 31 Dec 2019
92 JFPR: 1,103.01
TASF: 49.02 713.42 35.10
Approved Amount
Net Amount
Financing Project Officer
Project Analyst
Implementation Agencies
2,000.00 400.00
2,000.00 400.00
JFPR TASF
K. Nakamitsu
L. Dimayuga
P & D Dept. GoKPK Local Gov't, Elections and Rural
Dev. Dept, GoKPK
B. TA Description The PATA's impact is aligned with renewed focus on inclusive and sustainable urban development in provincial policies and allocations. The outcome will be improved urban inclusivity, sustainability, and resilience in investment programming in Khyber Pakhtunkhwa. The TA outputs include: (i) sector road map for inclusive and sustainable urban growth endorsed; (ii) Regional Development Plans prepared by provincial and local governments; (iii) institutional capacity for implementation agencies built; and (iv) lessons from pilots on accredited trainings and municipal business planning mainstreamed within the urban sector. The outputs will be implemented through a participatory process to ensure stakeholder consultations across the political spectrum and all income levels. Four themes run across all TA outputs: poverty alleviation, gender inclusivity, enabling small and medium-sized enterprises, and building resilience to disasters and climate change. The TA has recently been approved and ADB is currently in the process of selecting one consulting firm. The TA inception mission is proposed in early March 2017. TA consultants are currently updating the draft regional development plans. Contract variations will be issued in September 2019. KP government officials will also join capacity development program on institutional reforms and financial sustainability.
C. Project Monitoring Framework (Current Status)
Outputs Performance Indicators Status with Key Activities Sector road map for inclusive and sustainable urban growth endorsed
A sector road map for inclusive and sustainable urban growth that is gender-inclusive and focuses on small and medium-sized enterprises, the poor, and climate change endorsed. At least 200 citizens and decision makers, of whom 30% will be women and poor persons, participated in consultations on the sector road map.
The TA consulting firm was mobilized on 26 February 2018. Draft report was finalized in August 2018. The final draft report will be ready in Q3 2019. Extensive consultation already completed and the scope of investment in three cities already agreed. The draft pre-feasibility report on the priority infrastructure and the CRVA have been circulated for comments
184
Water and Urban Infrastructure Services Sector
TA 9223-PAK: Provincial Strategy for Inclusion and Sustainable Urban Growth
Outputs Performance Indicators Status with Key Activities Regional Development Plans prepared by provincial and local governments
RDPs, including a 10–15-year urban investment plan that is gender-inclusive and focuses on small and medium-sized enterprises, the urban poor, and climate change, endorsed. Fifty professionals from the region, of whom 20% will be women, trained on the job on the process and principles of formulating RDPs. RDP guidelines and manuals with a focus on the participation of small and medium-sized enterprises, the poor, women, and climate change issued by the provincial government.
The TA consulting firm was mobilized on 26 February 2018. Draft report was finalized in August 2018. The final draft report will be ready in Q3 2019.
Institutional capacity for implementation agencies built
Organizational improvement plan developed including legal set-up and allocation of human resources (with an increased number of women employees), and financial resources endorsed by the provincial government.
UN Habitat who is leading this sector has completed preparatory work. CA development work has started in January 2018 and the final draft will be ready in Q3 2019.
Lessons from pilots on accredited trainings and municipal business planning mainstreamed within the urban sector
More than 100 people (25% women) trained, and at least 50% of the total participants received certificates for trainings on planning, implementation, or maintenance. Municipal business plan prepared based on a financial management and life cycle cost pilot. Urban sector professions from Khyber Pakhtunkhwa participated in the urban forum. Three knowledge products produced, with at least one on integrating urban climate change resilience principles into urban planning and one on gender mainstreaming.
The TA consulting firm was mobilized on 26 February-2018. One training event was conducted in December 2018.
185
Water and Urban Infrastructure Services Sector
TA 9223-PAK: Provincial Strategy for Inclusion and Sustainable Urban Growth
D. Cumulative Contract Award and Disbursement Performance
E. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No issues
F. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No issues
-0 0
181
1103 11031142 1152 1152
0 0 42
299
454527
737 749
-
250
500
750
1,000
1,250
1,500
1,750
2,000
2,250
2,500
Dec/16 Jun/17 Dec/17 Jun/18 Dec/18 Jun/19 Dec/19 Jun/20
(Th -
$)
TA 9223- Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Clo
sin
g: 3
1D
ec 2
01
9
Net TA amount: $ 2,400 (Th)
186
Water and Urban Infrastructure Services Sector
TA 9400-PAK: Khyber Pakhtunkhwa Intermediate Cities Improvement Project
TA 9400-PAK: Khyber Pakhtunkhwa Intermediate Cities Improvement Project
A. TA Basic Data US$ (Thousand)
Approval Date
Signing Date
Closing Date
Closing Date (Revised)
Time Elapse
%
Contract Award
(Cumulative)
Disbursements (Cumulative)
5-Oct-17 - 31-Dec-18 30 Nov 2019 92 123.57 89.03 Approved Amount
Net Loan Amount
Financing Project Officer
Project Analyst
Counterpart Agencies
225.00 135.37 TASF K.Nakamitsu L.
Dimayuga -
B. TA Description The TA will finance the (i) preparation of project design advance documents, (ii) preparation of due diligence assessments, and (iii) project preparatory coordination for the ensuing loan for Khyber Pakhtunkhwa Intermediate Cities Improvement Investment Project. The TA will support project readiness and minimize possible start-up delays for the project. This TA will be closed in September 2019 as all activities envisaged are completed. C. Cumulative Contract Award and Disbursement Performance
- - -
184 188
216
116 124
-
49 56
76 86 89
-
25
50
75
100
125
150
175
200
225
250
Oct-17 Apr-18 Oct-18 Apr-19 Oct-19
(Th -
$)
TA 9400- Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Clo
sin
g: 3
0 N
ov
20
19
Net TA amount: $ 225 (Th)
187
Water and Urban Infrastructure Services Sector
TA 9400-PAK: Khyber Pakhtunkhwa Intermediate Cities Improvement Project
D. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No issues
E. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No issues
188
Water and Urban Infrastructure Services Sector
TA 9465-PAK: Punjab Intermediate Cities Improvement Investment (Phase 2)
TA 9465-PAK: Punjab Intermediate Cities Improvement Investment (Phase 2)
A. TA Basic Data US$ (Thousand)
Approval Date
Signing Date
Closing Date
Closing Date (Revised)
Time Elapse
%
Contract Award
(Cumulative)
Disbursements (Cumulative)
15-Dec-17 - 10-Jul-19 10-Jan-20 87 115.53 72.88 Approved Amount
Net TA Amount
Financing Project Officer
Project Analyst
Counterpart Agencies
225.00 225.00 TASF J. Kohlhase L.
Buenavente
B. TA Description 1. Pakistan’s rate of urbanization is unprecedented, where cumulatively the population of its cities has expanded by over 70% during the past 2 decades alone. As a result, its cities have and continue to experience relentless urban densification and expansion, resulting in ever-increasing demand for urban services and growing pressures on urban service institutions to deliver. This situation has become acute in many cities, and especially Pakistan’s intermediate cities, where urban delivery institutions are increasingly unable to cope, resulting in significant environmental degradation, unhealthy public spaces, and a severe shortage of civic amenities. The classic hallmarks of strained urban development are apparent in many cities, including unplanned and overcrowded settlements and residential areas, traffic-clogged streets and arterials, irregular and poor-quality water supplies, and serious environmental and public health impacts caused by poorly functioning liquid and solid waste management systems. 2. Fully recognizing livable cities as engines of economic growth and centers of culture and knowledge, the government has now placed urban sector development as a key priority of its national strategic development agenda. It has also amended the constitution to decentralize urban services, paving the way to build stronger institutional capacity in municipal governments so that they can respond more rapidly and effectively to the growing needs of individual cities as they evolve. So far, urban sector reforms have included selected cities of Punjab, which is Pakistan’s most populous province and generates half of the nation’s gross domestic product. In this context, the Government of Punjab (GOP) Urban Unit, has and continues to implement key urban sector reform initiatives in selected areas throughout the province, working closely with international development partners to upgrade and expand urban infrastructure, and reform and build capacity in infrastructure service delivery institutions. This has notably included support from the World Bank, which has provided assistance to five large cities of Punjab, and more recently from the Asian Development Bank (ADB) through PICIIP (Phase 1).
189
Water and Urban Infrastructure Services Sector
TA 9465-PAK: Punjab Intermediate Cities Improvement Investment (Phase 2)
C. Cumulative Contract Award and Disbursement Performance
D. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
Current Status
1. PC-2 Submission PMU monitoring status of PWDG
approval and report back.
30 August 2019 Completed. On
4 October 2019
the PWDP
approved PC-2.
2. International
Engineer recruitment.
Evaluation 45 applications. 28 August 2019. Completed.
Notice to
proceed was
issued on 4
October 2019.
Awaiting Visa
clearance to
mobilize the
consultant to
the field.
-- - - -
14
176
116
- -
-
14
35
73
-
25
50
75
100
125
150
175
200
225
250
Dec-17 Jun-18 Dec-18 Jun-19 Dec-19
(Th -
$)
TA 9465- Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Clo
sin
g: 1
0 J
an
20
20
Net TA amount: $ 225 (Th)
190
Water and Urban Infrastructure Services Sector
TA 9465-PAK: Punjab Intermediate Cities Improvement Investment (Phase 2)
E. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1 PC-2 Submission PMU monitoring status of CWDP approval
and report back.
25 October 2019
2 Field work – technical due
diligence
Engineer to mobilize and carry our
technical assessment for Rawalpindi and
Multan WASAs.
25 October 2019
3 Processing the PRF loan
documentation
Issue draft PRF Report for interdepartmental circulation.
25 October 2019
191
V. PUBLIC SECTOR MANAGEMENT Loans
1. Loan 3049-PAK(COL): Social Protection Development Project
2. Loan 3469-PAK/Grant 0518-PAK: Supporting Public–Private Partnership Investments in Sindh Province
3. Loan 3473/3474/Grant 0519-PAK: National Disaster Risk Management Fund
4. Loan 0639-PAK: National Disaster Risk Management Fund – Additional Financing
5. Loan 3636-PAK/Grant 0562-PAK: Enhancing Public-Private Partnerships in Punjab
Technical Assistance (TAs)
1. TA 9239-PAK: Enhancing Public Private Partnership in Pakistan
2. TA 9246-PAK: National Disaster Risk Management Fund
3. TA 9410-PAK: Sindh Secondary Education Improvement Project
4. TA 9392-PAK: Preparing Health Sector Assessment
5. TA 9467-PAK: Strengthening the Federal Public-Private Partnership Framework and Enabling Reforms for Infrastructure Financing Support
6. TA 9469-PAK: Enhancing Public-Private Partnerships in Punjab
7. TA 9488-PAK: Supporting Economic Corridor Development through Strategic Planning Frameworks
8. TA 9580-PAK: Preparing the Trade and Competitiveness Program
9. TA 9588-PAK: Promoting Investments and Economic Growth through International Trade
10. TA 9688-PAK: Economic Management Support
11. TA 9730-PAK: Improving Workforce Readiness in Punjab
12. TA 9676-PAK: Capacity Building for Structural Transformation, Country Programming,
and Portfolio Management
13. TA 9788-PAK: Supporting Development of Additional Financing for Social Protection
Development Project
14. TA 9789-PAK: Financial Markets Development Program
192
Public Sector Management
Loan 3049-PAK(COL): Social Protection Development Project
Loan 3049-PAK (COL): Social Protection Development Project
A. Loan Basic Data $ Million
Approval Date
Signing Date
Effective Date
Closing Date
Closing Date (Revised)
Elapsed Time %
Project Rating as of
30 Sep 19
22-Oct-13 25-Nov-13 24-Jun-14 30-Jun-19 30-Jun-22 68 Approved Amount
Net Loan Amount
Financing EA/IA Project Officer Project Analyst
430.00 394.43 COL BISP O. Bin Zia H. Ambreen On Track
B. Loan Financial Progress – (As of 30 Sep 19)
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
325.88 68.55 83 39.2 9.58
Disbursements (Cumulative)
Un-disbursed Loan Balance
Disbursement Performance %
Disbursements for 2019
EA’s Projections Actual
383.98 10.45 97 7.6 7.35
C. Project Description 1. The project will support the Government of Pakistan’s national social safety net program, the Benazir Income Support Program (BISP). The project will enable the expansion of the cash transfer program (paid to the female head of targeted poor families) by registering an additional 2.4 million eligible families and financing the first few quarters of their cash transfers. In addition, it will support activities aimed at graduating BISP beneficiaries out of poverty and providing them sustainable livelihood and access to health services. The substantial fiduciary risk of the project will be mitigated through the strengthening of BISP financial management systems and capacity. 2. The outcome will be increased resilience for BISP female beneficiaries and their families. D. Project Monitoring Framework (Current Status)
Outputs Performance Indicators Status with Key Activities 1. Cash transfer program coverage expanded
Enrollment of eligible female heads of families with the CNIC increased Baseline: 70% in 2013, target: 95% in 2018
As of 31 Mar 2019, 855,052 beneficiaries have been enrolled under ADB loan out of total 5.4 million eligible beneficiaries receiving the cash transfers. The ADB beneficiaries are 16% of total eligible beneficiaries. BISP’s national socio-economic registry (NSER) was planned to be updated every 5 years. The poverty scorecard survey was completed in 2010. Data collection for the NSER Phase 2 is currently ongoing through implementing partners. The country has been divided into 8 clusters for the
193
Public Sector Management
Loan 3049-PAK(COL): Social Protection Development Project
Outputs Performance Indicators Status with Key Activities purpose. The new database is expected to be completed by Sep 2020.
Regular cash transfers received in time by all eligible beneficiaries (baseline 0 in 2013; target 2.5 million in 2020)
Q3 2014 – Q1 2019 cash transfer payments to new beneficiaries have so far been paid from project resources. The payments are being released to BISP beneficiaries on quarterly basis. However, the Q4 2018 and Q1 2019 instalments were reportedly not disbursed to the beneficiaries on time.
2. Graduation components (implementation between 2018 and 2020)
Income poverty sustainably reduced in the project area (baseline 0 in 2014, target 50,000 households by 2020) and social protection in health for BISP poor enhanced (baseline: 0 in 2014, target 20,000 households in 2020)
Pursuant to BISP Board’s decision and ADB’s amendment to the LA and the PA, a BISP Graduation Program (BGP) was designed for implementation in select districts on pilot basis. Two approaches, namely, Business Incubation for Self Employment (BISE), Inclusive Business (IB) and Direct Cash will be piloted under the Project using ADB’s $40 million (approx.) allocated for the BGP. On 17 November 2017, the Design Committee of BISP Board endorsed a program for graduation to be implemented in 2018 through June 2020. The fourth component of the BGP, the public works program, has been put on hold by the BISP Board.
2.1 Business incubation sub-component
Comprehensive business incubation provided to BISP and other poor and vulnerable beneficiaries (baseline: 0, target: 50,000 of which 30% women by June 2020
Poor households provided with BI will move out of poverty (Baseline: 0 in 2014, 50% of beneficiaries receiving comprehensive coaching and asset transfers in 2020)
Health insurance introduced and scaled to those receiving assets transfer (baseline: 0, target: 30,000)
Compulsory saving scheme introduced and scaled to those who receive assets (baseline: 0, target: 30,000)
For implementing BISE-IB component
the 5 districts selected are; Upper Dir
(Khyber Pakhtunkhwa), Awaran and
Harnai (Balochistan), Rajanpur
(Punjab), and Tharparkar (Sindh).
These have been selected on the basis
of UNDP districts ranking on the basis
of HDI.
The hiring of implementing partner for BISE-IB component is currently ongoing. The request for EOI was advertised on 15 June 2019 and then re-advertised on 18 October 2019 due to the change in scope, budget variance and inability of the NGOs in providing the Sales Tax Registration number, a mandatory requirement.
2.2 Inclusive business sub-component
Poor and vulnerable people in the value chain of Inclusive Business companies and Social Enterprises come out of poverty. (Baseline: 0 in 2014, targets:
The hiring of implementing partner for BISE-IB component is currently ongoing. The request for EOI was advertised on 15 June 2019.
194
Public Sector Management
Loan 3049-PAK(COL): Social Protection Development Project
Outputs Performance Indicators Status with Key Activities 85% BISP beneficiaries employed by IB
companies, of which 20% women).
2.3 Public works sub-component
Public work schemes create temporary income opportunities for poor and vulnerable people. (Baseline: 0 on 2014, 30,000 jobs in 2020, of which 35% for women)
Some of the people receiving public work income move out of poverty (Baseline: 0 in 2014, target: 15% in 2020).
The public work programs generate community-based infrastructure that help rural people adapting to climate change and addressing environmental poverty. (Baseline: 0 in 2014, target: 30,000 people2 in 2020).
Schemes endorsed by provincial government and approved by BISP (baseline: 0, target: 4)
BISP refinanced costs to LGUs (baseline: 0, target: 4) Impact monitoring established and implemented (baseline: 0, target: 4)
Pursuant to BISP Board’s decision, the public works component has been shelved for the time being. A possibility to implement this component will be explored in consultation with the provincial governments.
2.4 Direct cash component
A reasonable share (45%) of BISP beneficiary households graduate out of poverty (Baseline: 0; target: 9,000 households by 2020)
BISP beneficiaries receive new health insurance that reduces their vulnerability to fall back into poverty. (Baseline: 0 in 2014; 20,000 in 2020),
The MOA has been signed between BISP, MHL consortium and Research Consultants. The timeline and workplan for the project has been developed for implementation in two districts. NOC for field activities has been provided by the Government of Punjab. Payment mechanism of the beneficiaries is being discussed with National Bank of Pakistan.
22 Calculated as number of places (10 places each for 10 districts) where PW programs are implemented times 3,000
people each.
195
Public Sector Management
Loan 3049-PAK(COL): Social Protection Development Project
E. Cumulative Contract Award and Disbursement Performance
F. Contract Award and Disbursement Targets and Achievements in 2019
18 18
78 78
232 232
303 303 303 316
326
326
0
68 69
115122
297 298
356 359363377 380
384
-
50
100
150
200
250
300
350
400
450
L 3049- Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Loan Amount: US$ 394.43 M
Clo
sin
g D
ate
: 30-J
un-2
022
1.3
2.5
3.8 3.8 3.8 3.8
5.1
6.3
7.6 7.6 7.6 7.6
3.6 3.6 3.6 3.6 3.6 3.6
7.3 7.3 7.3
0.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
2019 Disbursements L3049($376.6 million through Dec 2018)
EA Projection Actual
0.0 0.01.7
3.35.0 5.0 5.0 5.0
16.4
27.8
39.2
- - -
7.4 9.6 9.6 9.6 9.6 9.6
0
5
10
15
20
25
30
35
40
45
2019 Contract Awards L3049($316.5 million through Dec 2018)
EA Projection Actual
196
Public Sector Management
Loan 3049-PAK(COL): Social Protection Development Project
G. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
Current Status
1. PMU Consultants for graduation
The PMU consultants need to be on board asap specially the procurement expert, team leader, as the hiring of implementing partner is currently in process and the experts should effectively support the process.
15 September 2019
1 out of 6 consultants is on board. The rest of the consultants are expected to be on board within Nov 2019.
2. Submission of pending AFS for FY 2017 and 2018; and hiring of firm for the FY2019 and FY2020 audit
The submission is already overdue for the FY2017 and FY2018. In addition, BISP need to expedite the hiring of firm for the FY2019 and FY2020 audit.
FY2017&FY2018- Audit Completed, report expected by 31 August 019
Pending
3. Submission of RFP for BISE-IB implementing partner (IP) to ADB
The detailed revised TORs in RFP are to be incorporated as discussed with BISP to ensure clarity in the tasks to be delivered by the IP.
To be re-advertised by 4 September 2019
Re-advertised on 18 October 2019
H. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. Setting up of the PMU On-boarding of all PMU Consultants and
provision of office space to the BGP
Consultants
BISP/ First week
Dec 2019
2. Submission of pending
AFS for FY 2017 and
2018; and hiring of firm for
the FY2019 and FY2020
audit
The submission is already overdue for the
FY2017 and FY2018.
In addition, BISP need to expedite the
hiring of firm for the FY2019 and FY2020
audit.
BISP / 31 October
2019
BISP / 15 November
2019
3. Opening of Imprest
Account for the additional
financing
Timely opening of the account is important
for the disbursements within this year
BISP / 10 November
2019
4. Delays in hiring of
Implementing Partner for
BISP Graduation Program
The Re-Request for EOI has been
advertised on 19 October with deadline for
submission of EOIs as 19 November
2019. BISP to develop a CRAM for the
hiring of IP and ensure following of
timelines.
BISP / 6 Nov 2019
197
Public Sector Management
Loan 3469-PAK/Grant 0518-PAK: Supporting Public Private Sector Partnership in Sindh Province
Loan 3469-PAK/Grant 0518-PAK: Supporting Public Private Sector Partnership in Sindh Province
A. Loan Basic Data $ Million
Approval Date
Signing Date
Effective Date
Closing Date Closing Date
(Revised) Elapsed Time %
Project Rating as of
30 Sep 19
24-Nov-16 12-Sep-17 31 Mar 18 31-Dec-22 – 47 Approved Amount
Net Loan Amount
Financing EA/IA Project Officer
Project Analyst
100.00 19.20
100.00 19.23
OCR DFID Grant
Dept. of Finance, GOS S. Masood Z.Hamid
Actual Problem
B. Loan / Grant Financial Progress – (As of 30 Sep 19) Loan 3469-PAK
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
0.00 100.00 0 18.8 0.00
Disbursements (Cumulative)
Un-disbursed Loan Balance
Disbursement Performance %
Disbursements for 2019
EA’s Projections Actual
0.21 99.79 0 13.0 0.08
Grant 0518-PAK
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
0.43 18.81 2 3.5 0.43
Disbursements (Cumulative)
Un-disbursed Disbursement Performance %
Disbursements for 2019
Loan Balance EA’s Projections Actual
1.08 18.15 6 4.7 1.08
C. Project Description 1. The project will support the development policies of GoS for sustainable infrastructure provision through PPPs. It is aligned with Midterm Review of Strategy 2020, in which PPPs are a key driver of change, and the Country Partnership Strategy 2015-2019. The project builds on ADBs partnership with GoS to develop the PPP framework under a program cluster in 2009, using lessons learned from this program and the Country Assistance Program Evaluation for Pakistan. 2. The expected impact of the project is aligned with the number of infrastructure investments and services in Sindh improved. The expected outcome is fiscally-responsible private sector participation and investment in infrastructure increased in Sindh.
198
Public Sector Management
Loan 3469-PAK/Grant 0518-PAK: Supporting Public Private Sector Partnership in Sindh Province
D. Project Monitoring Framework (Current Status)
Outputs Performance Indicators Status with Key Activities Government of Sindh capacity to select and develop PPP projects strengthened
• Standardized project selection criteria for PDF in place by January 2017 (Baseline: Different sets of criteria used for each project in 2014)
• At least one staff member of 4 PPP nodes trained in proper application of selection criteria by April 2017, 7 PPP nodes by December 2018 (Baseline: No standardized criteria in 2014)
• PDF replenished by $3 million upfront by January 2017 (Baseline: No PDF replenishment plan in 2014)
Eleven consultants are on board.
PPP project-related fiscal risk effectively managed by PSF
• PSF established by December 2016 • Established criteria for VGF utilization and
management by PSF from Sepe 2017 onwards (Baseline: Criteria incomplete and not used systematically in 2014)
• Risk management measures applied by PSF to all PPP transactions from September 2017 onwards (Baseline: No criteria in 2014)
• At least 6 PPP projects supported by PSF by March 2022 (Baseline: 0 in 2014)
• Quarterly risk management reports submitted by PSF to the PPP Policy Board from July 2017 onwards (Baseline: PPP policy and project decisions not linked with contingent liability management in 2014)
PSF incorporated in Dec 2017. Interim management is in place.
PPP project selection and subsequent management capacity of line departments, finance, and planning and development departments strengthened
• Screening criteria adopted for all proposed development projects by July 2017 and utilized with respect to projects in all government departments by January 2018
• 50% of PPP proposals to the PPP Policy Board contain standardized selection criteria by Sepe 2017, 100% by Sepe 2019 (2014 baseline: no standardized selection criteria)
• Annual status reports issued by the departments implementing PPP projects for 50% of projects by December 2017 and 100% by December 2018 (2014 baseline: no status reports)
• All PPP node staff in the energy, planning and development, transport, works, and services departments trained on contract and project management by December 2017; and in education and health departments by Sepe 2022 (2014 baseline: 0)
Project selection criteria prepared and approved by the PPP Policy Board in Nov 2017.
199
Public Sector Management
Loan 3469-PAK/Grant 0518-PAK: Supporting Public Private Sector Partnership in Sindh Province
E. Cumulative Contract Award and Disbursement Performance
F. Contract Award and Disbursement Targets and Achievements in 2019
0.0 0.0 0.0 0.0 0.4
0.1 0.1 0.1 1.2 1.2 -
20
40
60
80
100
120
140
Jun-18 Jun-20 Jun-23
L 3469-G0518 :Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Loan Amount: US$ 119.20 M
Clo
sin
g D
ate
: 31-D
ec-2
022
0.0 0.0 0.0
1.73.3
5.0 5.0 5.0 5.0
9.2
13.5
17.7
- - - 0.1 0.1 1.2 1.2 1.2 1.2
0.0
2.0
4.0
6.0
8.0
10.0
12.0
14.0
16.0
18.0
20.0
2019 Disbursements L3469($0.1 million through Dec 2018)
EA Projection Actual
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
7.4
14.9
22.3
- - - - - - - 0.4 0.4 0
5
10
15
20
25
2019 Contract Awards L3469($0.0 million through Dec 2018)
EA Projection Actual
200
Public Sector Management
Loan 3469-PAK/Grant 0518-PAK: Supporting Public Private Sector Partnership in Sindh Province
G. Status of the Action Plan discussed in 2nd TPR
Sr. No
Issue Action to be Taken Due Date / By Whom
Current Status
1 Pending Withdrawal Applications for VGF (Advance) and PDF (Reimbursement)
FD to submit Withdrawal Applications for VGF (Advance) and PDF (Reimbursement)
30 August 2019
Pending
2 Disbursement and Contract Award Projections
Project-wise disbursement projections (along with reverse clock with key milestones) to be provided by the PPP Unit
30 August 2019
Under preparation by PPP Unit
3 Project Pipeline
(a) Safeguard Requirements
Category A Projects: GOS to prepare draft IEE or EIAs (as applicable) and LARPs of all Category A projects in the pipeline through transaction advisors, including Malir Expressway. PPP Unit to initiate draft EIA for Malir Expressway through existing transaction technical advisors. GOS to share the TORs of the consultant that will be appointed by the concessionaire to conduct the EIA for Ghotki Kandhkot Bridge project. EIA consultant for Ghotki Kandhkot concessionaire to meet with ADB safeguards staff and consultants to work in close coordination.
30 August 2019 30 August 2019
PPP Unit is in the process of procuring approvals for engaging a separate firm through PDF for conducting EIA and LARPs for three projects (Malir Expressway, GKT and Link Road). Procurement of consultants to be initiated by end October 2019.
(b) Submission of project appraisal reports for other projects listed below:
PSF to submit project appraisal reports for other projects listed below:
Education Management Outsourcing – RFP 3- 4 Teachers Training Institute (TTI)
Project Appraisal Reports to be finalized by PSF, in collaboration with the PPP Unit and SELD.
30 August 2019
PSF board approval for EMO 1&2 and signed safeguards checklist received.
Regional Blood Centers (RBC)
Project Appraisal Reports of Sindh and Indus to be finalized by PSF, in collaboration with the Health Department
30 August 2019 Pending. Information awaited from the Health Department.
201
Public Sector Management
Loan 3469-PAK/Grant 0518-PAK: Supporting Public Private Sector Partnership in Sindh Province
Ongoing PPP projects Existing PPP projects to be reviewed, for PSF funding, starting from Karachi Thatta Dual Carriageway. ADB to provide list of information required for due diligence (esp safeguards due diligence). PPP Unit to provide relevant information to facilitate the due diligence process.
Done 30 August 2019
Done ADB to revert back on ESMS mitigating measures/follow up actions on LA/social safeguards to further the due diligence process of KTDC.
Wastewater Treatment (TP-1):
PPP Policy Board approval for engaging ADB transaction advisory services obtained. Mandate letter to be signed.
TP1 mandate letter signed on 8 August 2019
Kick off mission held in September
(c) PDF Support PPP Unit to appoint focal staff for potential projects requiring PDF to expedite the applications, especially for Works and Services PPP project pipeline. Project Concept notes to be finalized and submitted by Works and Services Department to the PPP Unit for 3 projects:
1. O&M for Khyber-Sanghar 2. O&M for Tando M. Khan –
Badin 3. Dualization of Sukkur –
Larkana Road Substantial completion for the roads will not be required for launching the RFP for O&M of these roads.
30 August 2019 A PDF list of 10 projects have been identified to work further on.
Others: 1. Operationalization of PMU to streamline WA and reporting process. It is important to have a focal
person in Finance Department and PPP Unit
30 August 2019 PMU has been re-notified.
202
Public Sector Management
Loan 3469-PAK/Grant 0518-PAK: Supporting Public Private Sector Partnership in Sindh Province
to manage all the reporting requirements and withdrawals and liquidations.
2. Arrange formal handing
over to full-time management of PSF.
We understand this has been done by PSF.
H. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. Pending Withdrawal
Applications for VGF
(Advance) and PDF
(Reimbursement)
FD to submit Withdrawal Applications for
VGF (Advance) and PDF
(Reimbursement)
15 Nov/Finance
Department (FD)
2. Disbursement and Contract Award Projections
Project-wise revised disbursement
projections (along with reverse clock with
key milestones) to be provided by the PPP
Unit
15 Nov/ PPP Unit,
Finance Department
(FD)
3. Recruitment of PDF consultants for draft EIA and LARPs of selected projects
CSC to be notified and recruitment of firms
to be expedited.
Dec 2019/ PPP Unit,
Finance Department
(FD)
4. Submission of project appraisal reports for other projects listed below:
- EMO 3 and 4
- TTI
- NICH
- RBC 1 and 2
- HMOs
- Ghotki-Kandhkot
- Malir Expressway
- Link Road
- KTDC
Target dates for submission to be decided;
all PARs to be submitted within the next
quarter.
Nov 2019- Mar 2020
PSF in collaboration
with PPP Unit and
relevant line
department
5. PDF Support PPP Unit to appoint focal staff for potential
projects requiring PDF to expedite the
applications.
Nov 2019- Mar 2020
PPP Unit in
collaboration with
relevant line
department
6. Hiring for PSF Second tier hiring for PPP Support Facility
to be expedited.
Dec 2019 – Mar
2020
PSF
203
Public Sector Management
Loan 3473/3474-PAK: Grant 0591-PAK: National Disaster Risk Management Fund
Loan 3473/3474-PAK: Grant 0519-PAK: National Disaster Risk Management Fund
A. Loan Basic Data $ Million
Approval Date
Signing Date Effective
Date Closing Date
Closing Date (Revised)
Elapsed Time % Project
Rating as of
30 Sep 19
23-Nov-16 02-Dec-16 27-Dec-16 L: 17-May-20 G: 17-May-20
L: 30-Nov-21 L: 57 G: 82
Approved Amount
Net Loan Amount
Financing EA/IA Project Officer
Project Analyst
75.00 121.11
3.36
75.00 121.11
3.36
OCR COL
AUSG
Ministry of Finance
S. Shafi M. Sheikh On Track
B. Loan Financial Progress (As of 30 Sep 2019)
Loan 3473-PAK
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
6.88 68.12 9 16.6 6.88
Disbursements (Cumulative)
Un-disbursed Disbursement Performance %
Disbursements for 2018
Loan Balance EA’s Projections Actual
21.61 53.39 29 2.85 0.38
Loan 3474-PAK (COL)
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
99.12 22.66 81 12.1 2.44
Disbursements (Cumulative)
Un-disbursed Disbursement Performance %
Disbursements for 2019
Loan Balance EA’s Projections Actual
109.68 12.11 90 6.0 1.05
AUSG 0519-PAK (Grant)
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
0.20 3.16 6 3.2 0.00
Disbursements (Cumulative)
Un-disbursed Disbursement Performance %
Disbursements for 2019
Loan Balance EA’s Projections Actual
0.55 2.81 16 0.25 0.00
204
Public Sector Management
Loan 3473/3474-PAK: Grant 0591-PAK: National Disaster Risk Management Fund
C. Project Description 1. Pakistan faces significant disaster risk and requires substantial financing to tackle it. The country and its population and assets are increasingly exposed and vulnerable to various types of natural hazards. It features in the list of the ten most vulnerable countries impacted by extreme weather events from 1995 to 2014. Increasing natural hazard events over the last 15 years have resulted in significant loss of life, economic damage, and the undoing of development gains. Floods occur frequently and have caused the greatest physical damage. More than 30 million people were affected by just three major floods in 2010, 2011 and 2014, resulting in damage and losses exceeding $14.0 billion. A major earthquake in 2005 caused more than 73,000 deaths and $5.0 billion in losses. The country faces tropical cyclone risk and droughts, including a drought in 2014-2015 which affected more than 3 million people. These events severely impact livelihoods of the poor and vulnerable, result in mass migration, and disrupt trade and commerce, and destabilize markets. Such events negatively impact government budgets, periodically placing significant additional demands on limited public resources for humanitarian relief, early recovery and reconstruction. 2. The Project will provide financial and technical support to the National Disaster Risk Management Fund (NDRMF), which is being established as a government-owned non-bank financial intermediary with a corporate structure. The NDRMF will reduce the socio-economic and fiscal vulnerability of the country and its population to natural hazards by prioritizing and financing investments in disaster risk reduction and preparedness that have high economic benefits, taking into account climate change, as well as disaster risks and their impacts. The government will pass on ADB loan funds to the NDRMF as a grant, for on-granting by NDRMF to eligible implementing partners. The NDRMF will finance up to 70% of the cost of eligible subprojects that will enhance Pakistan’s resilience to extreme weather events and other natural hazards. The NDRMF will also enter into insurance arrangements to develop markets for the transfer of residual risks that cannot be mitigated. D. Project Monitoring Framework (Current Status)
Outputs Performance Indicators with Baseline
Status with Key Activities
NDRMF established and made operational
(i) Requisite governance, operational, fiduciary and safeguard (including gender) procedures, polices and systems are in place by Dec 2016. (Baseline = 0) (ii) The NDRMF fully staffed (with at least 20% women), with fully established offices by Mar 2017. (Baseline = 0)
(i) Requisite governance and fiduciary activities for effectiveness and disbursement have been met. Policies and guidelines for HR, Risk Management, Accounting, Safeguards and Procurement have been approved by the NDRMF Board. (ii) Hiring process is substantially complete and NDRMF office fully established – female staff percentage is 21%.
205
Public Sector Management
Loan 3473/3474-PAK: Grant 0591-PAK: National Disaster Risk Management Fund
Outputs Performance Indicators with Baseline
Status with Key Activities
(iii) Endowment fund invested in appropriate vehicles by Mar 2017. (Baseline = 0)
(iv) Communication, disclosure and public relation strategy of the NDRMF developed by June 2017. (Baseline = 0) (v) By 2018, a comprehensive ERP for the Fund is developed, and deployed. (Baseline = 0) (vi) First request for proposals to FIPs issued by June 2017, with periodic requests for proposals issued every year up to 2019. (Baseline = 0) (vii) By Q2 of each year until 2019, annual operational plan prepared and periodically rolling three-year business plans updated. (Baseline =0) (viii) By 2019, income from endowment fund financed 100% of the operating expenses of the NDRMF. (Baseline = 0)
(iii) Endowment fund has been established. Government has also released its share of the endowment fund. Basic policy for operations has been developed and the endowment Funds investment in conservative (low risk and less return) vehicles according to this policy. An Investment guideline for the endowment fund was approved by BOD in March 2018, based on which current investments are being made. (iv) Communication strategy has been developed for NDREMF and is currently with their board for approval. (v) Party complied. One aspects of the ERP have been deployed and operational, using off the shelf solution for financial resource management. To implement the complete solution in which this aspect will also be integrated, RFQ were floated in August 2019 and proposals are expected in September 2019. Revised deadline for the start of deployment of full ERP is Q4 2019. (vi) Revised to Sep. 2019. The first batch was approved in March 2019, and the second batch was approved in September 2019. The evaluation and approval of the final batch is expected by first quarter of 2020. (vii) Partly Complied. Strategic business plan 2018-2020 approved. Annual operational plan approved up to June 2019. (viii) Revised to June 2020.
Increased investment to reduce vulnerability to disasters.
(i) National and subnational emergency response plans developed by Q4 2017 (Baseline = 0)
(i) Revised the deadline to Q4 2021.
206
Public Sector Management
Loan 3473/3474-PAK: Grant 0591-PAK: National Disaster Risk Management Fund
Outputs Performance Indicators with Baseline
Status with Key Activities
(ii) National level MHVRA (including climate change and gender related vulnerabilities) completed by Q4 2018 and 20 subnational level MHVRAs completed by Q3 2019.
(iii) CBDRM plans completed in 50 vulnerable union councils or urban centers by Q2 2019 (Baseline = 0)
(iv) At least 300 kilometers new or retrofitted flood protection infrastructure financed by the NDRMF constructed (compared to 2016 baseline) by Q3 2019.
(v) Additional 500 public building (compared to 2016 data) financed from NDRMF (in social sector) safe and multi-hazard resistant by 2019.
(vi) The geographic coverage area of the early warning system increased by 10% above the 2016 base line by 2019.
(ii) Revised to Q4 2020. (iii) Revised to Q2 2021. (iv) Revised to Q3 2021. (v) Revised to Q4 2021. (vi) Revised to Q4 2021.
Analytical work and products to improve fiscal management of disaster risks.
(i) Develop a gender sensitive national DRF strategy by Q4, 2018. (ii) At least two gender inclusive DRF instruments developed (with targeted interventions for poor and vulnerable population segments), and one piloted by Q4 2019. (Baseline = 0)
(i) Revised to Q4 2020. Hiring process of the individual consultants to undertake this work is in advance stages. One international DRF consultant has been hired with ADB’s approval. (ii) Revised to Q2 2021.
207
Public Sector Management
Loan 3473/3474-PAK: Grant 0591-PAK: National Disaster Risk Management Fund
E. Cumulative Contract Award and Disbursement Performance Loan 3473-PAK
Loan 3474-PAK (COL)
0.0 0.0 0.0 0.0 0.0 0.0
6.9
0.0 0.0 0.1
21.0 21.0 21.2 21.6
-
10
20
30
40
50
60
70
80
Dec-16 Jun-17 Dec-17 Jun-18 Dec-18 Jun-19 Dec-19 Jun-20 Dec-20 Jun-21 Dec-21 Jun-22
L 3473- Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Loan Amount: US$ 75.00 M
Clo
sing
Da
te:
30
-No
v-2
02
1
96.7 96.7 96.7 96.7 96.7 96.7 99.1
96.7 97.2
106.4 107.5107.5108.6 109.7
-
20
40
60
80
100
120
140
Dec-16 Jun-17 Dec-17 Jun-18 Dec-18 Jun-19 Dec-19 Jun-20 Dec-20 Jun-21 Dec-21 Jun-22
L 3474- Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Loan Amount: US$ 121.78 M
Clo
sing
Da
te:
30
-No
v-2
02
1
208
Public Sector Management
Loan 3473/3474-PAK: Grant 0591-PAK: National Disaster Risk Management Fund
G 0519-PAK
F. Contract Award and Disbursement Targets and Achievements in 2019 Loan 3473-PAK
0.2 0.2 0.2 0.2
0.0 0.0 0.0
0.6 0.6 0.6 0.6
-
1
1
2
2
3
3
4
4
Dec-16 Jun-17 Dec-17 Jun-18 Dec-18 Jun-19 Dec-19 Jun-20 Dec-20
G 0519- Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Loan Amount: US$ 3.36 M
Clo
sin
g D
ate
: 1
7-M
ay-2
02
0
0.0 0.1 0.1 0.2 0.3 0.40.5 0.6
0.7
1.4
2.1
2.9
- - -
0.4 0.4 0.4 0.4 0.4 0.4
0.0
0.5
1.0
1.5
2.0
2.5
3.0
2019 Disbursements L3473($21.2 million through Dec 2018)
EA Projection Actual
1.1 1.6 1.8 2.0 2.2 2.2 2.2 2.2
7.0
11.8
16.6
- - - - -
3.1 3.0
6.8 6.9
0
2
4
6
8
10
12
14
16
18
2019 Contract Awards L3473($0.0 million through Dec 2018)
EA Projection Actual
209
Public Sector Management
Loan 3473/3474-PAK: Grant 0591-PAK: National Disaster Risk Management Fund
Loan 3474-PAK
G 0519-PAK
0.2 0.4 0.60.9
1.21.5
2.1
2.8
3.4
4.3
5.1
6.0
- - -
1.1 1.1 1.1 1.1 1.1 1.1 0.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
2019 Disbursements L3474($108.6 million through Dec 2018)
EA Projection Actual
2.5
3.7 3.9 4.1 4.35.1
5.86.6
8.5
10.3
12.1
- - - -
1.8
2.4 2.4 2.4
2.4
0
2
4
6
8
10
12
14
2019 Contract Awards L3474($96.7 million through Dec 2018)
EA Projection Actual
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.1
0.2
0.3
- - - - - - - - -
0.0
0.1
0.1
0.2
0.2
0.3
0.3
2019 Disbursements G0519($0.6 million through Dec 2018)
EA Projection Actual
0.0 0.0 0.0 0.0 0.0
0.5
1.1
1.6
2.1
2.6
3.2
- - - - - - - - -
0
1
1
2
2
3
3
4
2019 Contract Awards G0519($0.2 million through Dec 2018)
EA Projection Actual
210
Public Sector Management
Loan 3473/3474-PAK: Grant 0591-PAK: National Disaster Risk Management Fund
G. Status of the Action Plan discussed in 2nd TPR
Sr. No Issue Action to be Taken Due Date / By Whom
Current Status
1. Appointment of Full Board and General Body
Government to approve nomination of the BOD members already submitted by NDRMF through EAD. Government also need to expand General Body membership to the required level.
Still not completed. New date 30 September 2019
Not yet completed.
2. Grant Awards to FIPs
NDRMF to sign the contracts for the remaining approved grant proposals from batch 1.
15 September 2019
Completed.
3. Recruitment of Consultants
Complete single sourcing of SUPPARCO for risk modeling
30 September 2019
Hiring at final stage of contract negotiations expected by end October 2019.
Signing of contact with audit firm 31 July 2019 – Completed
Completed.
Complete hiring of Individual consultants
10 September 2019 – the immediate need of individual consultants supporting DRR operations has been met. The 4 DRF consultants will be hired by 20 September 2019
Partly completed. One DRF consultant has been hried.
Finalize TORs and Publish EOIs for the DRF Instrument development and piloting
Not completed by 10 August 2019 – Revised date is 31 August 2019.
Not completed.
Complete hiring of Baseline and perception survey consultants
EOI received, evaluation awaited. Deadline for hiring is 31 October 2019.
Still on going.
4. ERP Development
Request for Quotations to be Floated
31 Jul 2019 - Completed
RfQ was floated but very poor response was received.
5. Procurement of Equipment for NDMA
Bidding document to ADB for approval.
10 August 2019. Not completed – revised date 15 September 2019.
Not completed.
211
Public Sector Management
Loan 3473/3474-PAK: Grant 0591-PAK: National Disaster Risk Management Fund
H. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. Appointment of Full Board
and General Body
Government to approve nomination of the BOD members already submitted by NDRMF through EAD. Government also need to expand General
Body membership to the required level.
GOP/ 31 December 2019.
2. Procurement of Equipment
for NDMA
Bidding document to ADB for approval. NDRMF/
16 November 2019.
3. ERP Development Shopping of ERP to be completed within
2019.
NDRMF/
31 December 2019
4. Complete Hiring of
SUPARCO
NDRMF will complete the negotiations and
sign contract will SUPARCO for NatCat
modeling.
NDRMF/
10 November 2019.
5. Signing of Grant
Implementation
Agreements for Batch 2.
All grant subprojects of batch two, will be
signed with the respective fund
implementation partners.
Respective
Provincial
Governments, and
FIPs/
NDRMF/
31 December 2019
6. Award of Final Batch of
grant subprojects
NDRMF to ensure that the third batch of
grant subprojects is approved
expeditiously.
NDRMF/
Respective FIPs/
Q1, 2020.
7. Hiring of individual
consultants
Complete hiring of the remaining individual
consultants.
NDRMF/
31 December 2019
8. Procurement of Equipment
for NDMA
Bidding document to ADB for approval. NDRMF/
15 November 2019
9. Review of accreditation
and proposal
review/approval process
NDRMF to revisit the process,
documentation and workflow for
accreditation of FiPs, proposal guidelines
and review and approval mechanism.
NDRMF/
ADB/
31 March 2019.
10. Submission of Audited
Project Financial
Statement for FY 2017
NO APFS was received for FY 2017 with
the pretext that there was no expenditure
during the FY. However, since ADB
disbursed $96 million in endowment fund
in December 2016, for which ADB needs
auditor’s opinion on the use of the
disbursed amount. The EA needs to
provide the APFS for FY 2017 latest by 31
December 2019
EAD/
AGP/
31 December 2019
212
Public Sector Management
Loan 0639-PAK: National Disaster Risk Management Fund – Additional Financing
Loan 0639-PAK: National Disaster Risk Management Fund – Additional Financing
A. Loan Basic Data $ Million
Approval Date
Signing Date Effective
Date Closing Date
Closing Date (Revised)
Elapsed Time %
Project Rating as of
30 Sep 19
18-Jan-19 22-Mar-19 28-Jun-19 17-May-20 - 53 Approved Amount
Net Loan Amount
Financing EA/IA Project Officer
Project Analyst
1.50 - SWG Ministry of Finance
S. Shafi M. A.
Sheikh Actual Problem
B. Loan Financial Progress (As of 30 Sep 2019)
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
0.08 1.43 5 0.00 0.08
Disbursements (Cumulative)
Un-disbursed Loan Balance
Disbursement Performance %
Disbursements for 2018
EA’s Projections Actual
0.00 1.50 0 0.00 0.00
C. Project Description The Project will provide financial and technical support to the National Disaster Risk Management Fund (NDRMF), which is being established as a government-owned non-bank financial intermediary with a corporate structure. The NDRMF will reduce the socio-economic and fiscal vulnerability of the country and its population to natural hazards by prioritizing and financing investments in disaster risk reduction and preparedness that have high economic benefits, taking into account climate change, as well as disaster risks and their impacts. The government will pass on ADB loan funds to the NDRMF as a grant, for on-granting by NDRMF to eligible implementing partners. The NDRMF will finance up to 70% of the cost of eligible subprojects that will enhance Pakistan’s resilience to extreme weather events and other natural hazards. The NDRMF will also enter into insurance arrangements to develop markets for the transfer of residual risks that cannot be mitigated.
D. Project Monitoring Framework (Current Status)
Please refer to the loan DMF
213
Public Sector Management
Loan 0639-PAK: National Disaster Risk Management Fund – Additional Financing
E. Cumulative Contract Award and Disbursement Performance
F. Contract Award and Disbursement Targets and Achievements in 2019
0.0 0.0
-
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
Jun-19 Dec-19 Jun-20
G 0639- Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Loan Amount: US$ 1.50 M
Clo
sin
g D
ate
: 17-M
ay-2
020
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
- - - - - - - - -
0.0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1.0
2019 Disbursements G0639($0.0 million through Dec 2018)
Projected Actual
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0- - - - - -
0.1 0.1 0.1
0
0
0
0
0
0
0
0
0
2019 Contract Awards G0639($0.0 million through Dec 2018)
Projected Actual
214
Public Sector Management
Loan 0639-PAK: National Disaster Risk Management Fund – Additional Financing
G. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. Please refer to the loan action plan
215
Public Sector Management
Loan3636/G0562-PAK: Enhancing Public-Private Partnerships in Punjab
Loan 3636-PAK/Grant 0562-PAK: Enhancing Public-Private Partnerships in Punjab
A. Loan Basic Data $ Million
Approval Date
Signing Date Effective Date Closing
Date Closing Date
(Revised) Elapsed Time % Project
Rating as of
30 Sep 19
15-Dec-2017 13 Apr 18 17 May 18 30-Jun-23 – 32
Approved Amount
Net Loan Amount
Financing EA/IA Project Officer
Project Analyst
L: 100 G: 19.61
L: 100 G: 19.61
OCR DFID Grant
P&D, GoP S. Masood Z. Hamid Actual
Problem
B. Loan Financial Progress (As of 30 Sep 2019)
Loan 3636-PAK
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
0.00 100.00 0 6.00 0.00
Disbursements (Cumulative)
Un-disbursed Disbursement Performance %
Disbursements for 2019
Loan Balance EA’s Projections Actual
0.18 99.82 0 5.1 0.15
Grant 0562-PAK
Contract Award (Cumulative)
Un-contracted Loan Balance
Contract Award Performance %
Contract Award for 2019
EA’s Projections Actual
0.00 19.62 0 4.3 0.00
Disbursements (Cumulative)
Un-disbursed Disbursement Performance %
Disbursements for 2019
Loan Balance EA’s Projections Actual
0.00 19.62 0 3.7 0.00
C. Project Description The project is expected to improve and strengthen the development and delivery of public-private partnership (PPP) projects in the Punjab province. The loan from ADB will be used to finance a viability gap fund window which will enhance the commercial viability of projects and help attract private sector participation in PPPs. The project will support institutional capacity building by engaging procurement and safeguards specialists and project finance experts in the province that will further improve the government’s ability to review, develop, and implement sustainable PPP projects.
216
Public Sector Management
Loan3636/G0562-PAK: Enhancing Public-Private Partnerships in Punjab
D. Project Monitoring Framework (Current Status)
Outputs Performance Indicators with Baseline Status with Key Activities
PDF and VGF resources for PPP projects augmented
1a. Twelve PPP project proposals with PDF support submitted and reviewed by the RMU and the PPPC by 2022, with at least one social project approved with direct benefits to vulnerable groups such as the poor, women, girls, elderly, and persons with disabilities (2017 baseline: 0) 1b. Five PPP projects awarded with VGF support by 2022 (2017 baseline: 1)
PDF request for PKR 371 million for 13 projects received. Please see updates below on VGF.
PPP institutional capacity enhanced and strengthened
2a. VGF guidelines approved by steering committee and adopted and made operational by March 2018 (2016 baseline: Not applicable) 2b. ESMS, with social and gender indicators, established and adopted by March 2018 and prior to first disbursement. (2016 baseline: No ESMS) 2c. At least three PPP training programs delivered to relevant government agencies, with women accounting for 20% of participants from at least one department, by 2022. (2017 baseline: No PPP training arrangements in place) 2d. At least three locally held PPP investment conferences delivered to increase awareness from prospective private investors by 2022 (2017 baseline: No local conference held in Punjab)
VGF guidelines approved. ESMS established with 2 out of 3 hiring completed. Training programs / conferences need to be sequenced in conjunction with progress on various VGF projects in pipeline.
E. Cumulative Contract Award and Disbursement Performance
0.0 0.0 0.0 0.0
0.0 0.0 0.0 0.2 -
20
40
60
80
100
120
140
Jun-18 Dec-18 Jun-19 Dec-19 Jun-20 Dec-20 Jun-21 Dec-21 Jun-22 Dec-22 Jun-23 Dec-23
Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Loan Amount: US$ 119.60 M
Clo
sing
Dat
e: 3
0-J
un-2
023
217
Public Sector Management
Loan3636/G0562-PAK: Enhancing Public-Private Partnerships in Punjab
F. Contract Award and Disbursement Targets and Achievements in 2019
G. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
Current Status
1. Advance
(Imprest)
Account
(i) Accounts to be opened without further delay.
(ii) Submission of withdrawal applications (WA) for PDF advance to be submitted once advance accounts have been established.
30 August 2019/PPP Cell/Finance
i) PDF Account Opened ii) VGF Account Opening in process Withdrawal request for PRs 371 M for PDF of 13 projects has been sent on October 11. Formal signed application awaited.
2. Risk
Management
Unit (RMU) to
have
adequate
staffing for
VGF
monitoring
and
safeguards
oversight
For strengthening of RMU, hiring to be expedited by Finance Department.
30 August
2019/Finance
Vacant positions have
been advertised.
Committee to shortlist
the applicants and
interviews are expected
by end October.
3. ESMS to be
established
for PPPs.
Proper staffing to be completed for establishment of the ESMS.
30 August
2019/PPP
Cell
The Environment
Specialist and Social
Safeguard Specialist
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
2.9
5.9
8.8
- 0.1 0.1 0.1 0.1 0.1 0.1 0.2 0.2 0.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
10.0
2019 Disbursements L3636($0.0 million through Dec 2018)
EA Projection Actual
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
3.4
6.9
10.3
- - - - - - - - -0
2
4
6
8
10
12
2019 Contract Awards L3636($0.0 million through Dec 2018)
EA Projection Actual
218
Public Sector Management
Loan3636/G0562-PAK: Enhancing Public-Private Partnerships in Punjab
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
Current Status
have joined. The
Gender Specialist post
will be advertised again
due to lack of qualified
applicants.
4. Project
Pipeline
(i) To fast track VGF disbursements; it was agreed by GoPb that ADB may simultaneously evaluate already completed projects for VGF eligibility, including Lahore Waste Management Company, Punjab Education Foundation, Lahore Transport Company, Lahore & Islamabad Metro Bus Projects.
(ii) Share details of remaining
2 new projects.
For due
diligence;
Office of
Advisor to CM
to assist in
setting up
meetings with
the concerned
authorities for
the identified
projects.
09 August
2019
30 August
2019/PPP
Cell
i) To jumpstart VGF, 2 existing projects have been identified that are under PPP mode and their contract is up for renewal by end of 2019. These projects include Lahore Transport Company & Lahore Waste Management Company. PPP Cell has shared feasibility studies of 3 out of 5 projects envisaged. These include Safe City Project Rawalpindi, Water Meters & Faisalabad Affluent Treatment plants. ADB had shared its comments. Feasibilities of
remaining 2 projects still
under preparation.
5. Disbursement
projections to
be completed.
Revised projections in line with the updated project pipeline is to be shared by PPP Cell.
30 August
2019
6. Development
of PPP
Punjab
Authority Act
(i) Point wise response to
ADB comments have now been
shared post TPR.
(i) ADB to provide technical
assistance for
implementation of PPP
Authority.
Done. Government has
requested ADB
assistance for
operationalization of the
Authority.
7. Framework
Agreement
Summary for the Chief Minister shall be initiated
30 September
2019
Government has
proposed to ADB to
219
Public Sector Management
Loan3636/G0562-PAK: Enhancing Public-Private Partnerships in Punjab
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
Current Status
for
Transaction
Advisory
Services by
ADB
through Punjab Procurement Regulatory Authority (PPRA), Finance Department & Law Department and a decision shall be taken after approval/ orders of the chief Minister
consider aligning the
framework agreement
draft in line with already
executed IFC
agreement.
H. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. Development of PPP
Punjab Authority Act
Operationalization of PPP Authority.
To take forward LTC and LWMC projects, key is operationalization of PPP Authority that will need to approve initiation of transaction advisory and subsequent sign off on project proposals before RFPs can be triggered.
7 November 2019
2. VGF Project Pipeline Revised feasibilities for 3 new projects to be shared post ADB comments. Details of remaining 2 new projects
awaited.
30 November
2019/PPP Authority
3. Risk Management Unit
(RMU) to have adequate
staffing for VGF monitoring
and safeguards oversight
For strengthening of RMU, hiring to be
expedited by Finance Department.
30 November
2019/Finance
Department
4. Outstanding hiring for
ESMS.
Gender Specialist to be staffed. 30 November
2019/PPP Cell
220
Public Sector Management
TA 9239-PAK: Enhancing Public Private Partnership in Pakistan
TA 9239-PAK: Enhancing Public Private Partnership in Pakistan
A. TA Basic Data US$ (Thousand)
Approval Date
Signing Date
Closing Date
Closing Date
(Revised)
Time Elapse
%
Contract Award
(Cumulative)
Disbursements (Cumulative)
24-Nov-16 20-Dec-16 30-Jun-22 - 51 1,291.88 880.32 Approved Amount
Net TA Amount
Financing Project Officer
Project Analyst
Counterpart Agencies
4,750.53 4,750.53 DPECP S.
Masood M. Sheikh Finance Department, GoSindh
B. TA Description 1. The project will support the development policies of GoS for sustainable infrastructure provision through PPPs. It is aligned with Midterm Review of Strategy 2020, in which PPPs are a key driver of change, and the Country Partnership Strategy 2015-2019. The project builds on ADBs partnership with GoS to develop the PPP framework under a program cluster in 2009, using lessons learned from this program and the Country Assistance Program Evaluation for Pakistan. 2. The expected impact of the project is aligned with the number of infrastructure investments and services in Sindh improved. The expected outcome is fiscally-responsible private sector participation and investment in infrastructure increased in Sindh. 3. The outputs are (i) GoS capacity to select and develop PPP projects strengthened; (ii) PPP project-related fiscal risk effectively managed by the PPP Support Facility (PSF); and (iii) PPP project selection and subsequent management capacity of line departments, finance, and planning and development departments strengthened.
C. Project Monitoring Framework (Current Status)
Outputs Performance Indicators Status with Key Activities Government of Sindh capacity to select and develop PPP projects strengthened
Standardized project selection criteria for PDF in place by January 2017 (Baseline: Different sets of criteria used for each project in 2014) At least one staff member of 4 PPP nodes trained in proper application of selection criteria by April 2017, 7 PPP nodes by December 2018 (Baseline: No standardized criteria in 2014) PDF replenished by $3 million upfront by January 2017
Consultants engaged
221
Public Sector Management
TA 9239-PAK: Enhancing Public Private Partnership in Pakistan
(Baseline: No PDF replenishment plan in 2014)
Outputs Performance Indicators Status with Key
Activities Government of Sindh capacity to select and develop PPP projects strengthened
Standardized project selection criteria for PDF in place by January 2017 (Baseline: Different sets of criteria used for each project in 2014) At least one staff member of 4 PPP nodes trained in proper application of selection criteria by April 2017, 7 PPP nodes by December 2018 (Baseline: No standardized criteria in 2014) PDF replenished by $3 million upfront by January 2017 (Baseline: No PDF replenishment plan in 2014)
Consultants engaged
PPP project-related fiscal risk effectively managed by PSF
PSF established by December 2016 Established criteria for VGF utilization and management by PSF from Sepe 2017 onwards Risk management measures applied by PSF to all PPP transactions from September 2017 onwards At least 6 PPP projects supported by PSF by March 2022 Quarterly risk management reports submitted by PSF to the PPP Policy Board from July 2017 onwards
Consultants engaged
PPP project selection and subsequent management capacity of line departments, finance, and planning and development departments strengthened
Screening criteria adopted for all proposed development projects by July 2017 and utilized with respect to projects in all government departments by January 2018 50% of PPP proposals to the PPP Policy Board contain standardized selection criteria by Sepe 2017, 100% by Sepe 2019 Annual status reports issued by the departments implementing PPP projects for 50% of projects by December 2017 and 100% by December 2018 All PPP node staff in the energy, planning and development, transport, works, and services departments trained on contract and project management by December 2017; and in education and health departments by Sepe 2022
Consultants engaged
222
Public Sector Management
TA 9239-PAK: Enhancing Public Private Partnership in Pakistan
D. Cumulative Contract Award and Disbursement Performance
E. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No issues
F. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No issues
430
697872
974 1,0461,234
1,292
-0 34
264
495 568 642
846 880
-
500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
4,500
Dec/16 Jun/17 Dec/17 Jun/18 Dec/18 Jun/19 Dec/19 Jun/20 Dec/20 Jun/21 Dec/21 Jun/22
(Th -
$)
TA 9239- Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Clo
sin
g: 3
0 J
un
e 2
02
2
Net TA amount: $ 4,750 (Th)
223
Public Sector Management
TA 9246-PAK: National Disaster Risk Management Fund
TA 9246-PAK: National Disaster Risk Management Fund
A. TA Basic Data $ (Thousand)
Approval Date
Signing Date
Closing Date
Closing Date
(Revised)
Time Elapse
%
Contract Award
(Cumulative)
Disbursements (Cumulative)
23-Nov-16 17-Mar-16 01-Dec-19 - 94 778.43 672.78 Approved Amount
Net TA Amount
Financing Project Officer
Project Analyst
Executing Agency
1,000.00 1,000.00 TASF S. Shafi M. A.
Sheikh Mo Finance
B. TA Description 1. The National Disaster Risk Management Fund Project has an attached capacity development technical assistance (CDTA) to ensure that (i) the NDRMF’s core functions are established effectively and quickly, (ii) DRM mainstreaming is supported at the country level, (iii) FIPs begin their activities expeditiously; and (iv) an independent third-party oversight of the NDRMF’s activities is made available to ADB and other sponsors. The CDTA will enable the NDRMF and the FIP’s to expedite their operationalization and development of procedures. 2. The core outputs of the CDTA include (i) fast-tracking the operationalization and quality control of the National Disaster Risk Management Fund, (ii) strengthening disaster risk management due diligence capacity; and (iii) mainstreaming disaster risk management in development planning. 3. The CDTA will be implemented over 36 months from the signing of the letter of effectiveness. C . Project Monitoring Framework (Current Status)
Please refer to the DMF of the National Disaster Risk Management Fund Project
224
Public Sector Management
TA 9246-PAK: National Disaster Risk Management Fund
D. Cumulative Contract Award and Disbursement Performance
E. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No issues
F. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No issues
166
539
632
783 774 778
28
129
209
357
582
673
-
250
500
750
1,000
Jun-16 Dec-16 Jun-17 Dec-17 Jun-18 Dec-18 Jun-19 Dec-19
(Th -
$)
TA 9246- Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Clo
sin
g: 1
De
c 2
01
9
Net TA amount: $ 1,000 (Th)
225
Public Sector Management
TA 9410-PAK: Sindh Secondary Education Improvement Project
TA 9410-PAK: Sindh Secondary Education Improvement Project
A. TA Basic Data US$ (Thousand)
Approval Date Signing
Date Closing
Date
Closing Date
(Revised)
Time Elapse
%
Contract Award
(Cumulative)
Disbursements (Cumulative)
27-Oct-17 21-Nov-17 31-Dec-19 - 88 808.067 463.09 Approved Amount
Net TA Amount
Financing Project Officer
Project Analyst
Counterpart Agencies
1,000.00 1,000.00 TASF N.
LaRocque M. Martin
School Education and Literacy Department
B. TA Description The proposed Sindh Secondary Education Improvement Project (SSEIP) will support investments, institutional capacity building, and reforms in secondary education. The project is aligned with, and will support the implementation of, the SESP 2014-2018 (and subsequent SESP 2019-2023). C. Project Monitoring Framework (Current Status)
Outputs Performance Indicators
Status with Key Activities
Detailed project design developed and costed
• Project design and costing completed • SRM held in August 2018 • School architectural prototypes
completed and list of 160 project school sites identified
• PC-1 approved by CDWP and ECNEC • ADB board consideration on 25 October
2019 Project due diligence undertaken
• Safeguard categorization forms completed and submitted
• Procurement and financial management assessments completed
• Provisional list of 160 schools identified, subject to confirmation during early implementation
• Initial environmental and social assessment undertaken in one district
Project processing and implementation startup facilitated
• Advance actions and retroactive financing agreed
• Project Director appointed • Planning Commission and Sindh P&D
have authorized advance actions. Additional provincial authorizations and Federal endorsement required before advance actions can begin
• TORs have been prepared and updated and are awaiting authorization of the advance actions
226
Public Sector Management
TA 9410-PAK: Sindh Secondary Education Improvement Project
D. Cumulative Contract Award and Disbursement Performance
E. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to
be Taken
Due Date
/ By Whom
Current Status
1. Approval of the PC-1 by CDWP and ECNEC is
expected within the month. We need for
CDWP to quickly give final approval to PC 1 to
allow loan negotiations to take place within 2
weeks and advance actions, such as
advertisement of PIU key positions,
advertisement of the 2 firm-based contracts,
allow the safeguards team to visit the school
sites, to proceed.
Approval
of PC1
GoP
ECNEC
Approval: 29
July 2019
Loan
Negotiations: 2
September
2019
Final CDWP
and ECNEC
approval
obtained.
Loan
negotiations
held on 4
September
2019
Safeguards
teams have
- - -
517
589
711
788 808
-
188
276
350
451 463
-
250
500
750
1,000
Sep-17 Dec-17 Mar-18 Jun-18 Sep-18 Dec-18 Mar-19 Jun-19 Sep-19 Dec-19
(Th -
$)
TA 9410- Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Clo
sin
g: 3
1 D
ec 2
01
9
Net TA amount: $ 1,000 (Th)
227
Public Sector Management
TA 9410-PAK: Sindh Secondary Education Improvement Project
Sr.
No
Issue Action to
be Taken
Due Date
/ By Whom
Current Status
begun school
site visits
F. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. Authorization of advance
actions by GOS and GOP
SELD and Finance Department must authorize project and Federal Government must endorse project so that advance actions can begin
SELD and Sindh
Finance Department
by 25 October 2019
Federal Government
2. Loan signing Loan must be signed before the end of 2019 to secure concessional funding
Federal Government/
ADB by 15 November
2019
228
Public Sector Management
TA 9392-PAK: Preparing Health Sector Assessment
TA 9392-PAK: Preparing Health Sector Assessment
A. TA Basic Data US$ (Thousand)
Approval Date Signing
Date Closing
Date
Closing Date
(Revised)
Time Elapse
%
Contract Award
(Cumulative)
Disbursements (Cumulative)
27-Sep-17 27-Sep-17 30-Jun-18 30-Jun-20 73 173.94 167.71 Approved Amount
Net TA Amount
Financing Project Officer
Project Analyst
Counterpart Agencies
225.00 225.00 TASF R. Lavdo M. Dizon Department of Health, KP
B. TA Description In line with the authority delegated to country directors or heads of divisions to approve small-scale technical assistance (TA), a small-scale transaction TA amounting to $225,000 was mobilized to be financed on a grant basis by ADB’s Technical Assistance Special Fund (TASF 6). This TA became effective upon approval; and such approval will be reported to the Board in the Quarterly Summary Report on Small-Scale and Supplementary Technical Assistance Projects not exceeding $225,000. ADB will finance the SSTA to carry out an assessment that will examine delivery of health services particularly hospital sector, focusing on quality of health care, public financial management of the health sector, and health seeking behavior of the population. With all the ongoing initiatives, there is need for a consistent policy framework to coordinate and align all the reform initiatives and prevent system fragmentation by reforms implemented in silos. The sector assessment will inform the new Health Strategy for the province and will distill the policy matrix for an upcoming policy-based loan. C. Project Monitoring Framework (Current Status)
Outputs Performance Indicators Status with Key Activities Health sector assessment undertaken
Final report endorsed by ADB by Feb 2018 A series of consultation workshop with relevant government agencies, key civil society, and private sector representatives and development held in country by Feb 2018
Review existing national and regional policies, legislation, data and progress implementation reports, and past work undertaken by development partners on health sector focusing on adequacy of health services, quality of care, health financing, governance and public financial management (Oct 2017-Feb 2018) - Completed
Final report endorsed by ADB on Feb 2019
229
Public Sector Management
TA 9392-PAK: Preparing Health Sector Assessment
Outputs Performance Indicators Status with Key Activities Status:
International and national consultants were mobilized to conduct assessment. Findings were presented on February 2018. Timing of release of final report is scheduled to be delivered after the elections. - Completed Consult with relevant government agencies and stakeholders (October 2017 – February 2018) - Completed Status: Consultations were conducted from October 2017 to February 2018. - Completed Conduct workshop to discuss findings, lessons learned and recommendation of the assessment (February 2018) - Completed Status: A workshop was conducted in February 2018 to present findings of the assessment. - Completed
Priority policy reforms identified
Proposed priorities and strategies in line with the health sector assessment, endorsed by the Government by February 2018
Based on health sector assessment, prioritize policies in consultation with stakeholders (February 2018) - Completed Status: Priorities were identified as of February 2018 - Completed As of July 2019, priorities were changed, and assistance was requested. SSTA is being extended until Sepe 2020 to respond to this request.
230
Public Sector Management
TA 9392-PAK: Preparing Health Sector Assessment
D. Cumulative Contract Award and Disbursement Performance
E. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
Current Status
1. Need MOF decision
regarding future
engagement with KP
MOH
Discuss with MOF During the TPR
/ By PRM
TA was not
discussed in the
TPR
F. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No issues
- -
129
199 199 199
178 174
-
35
120
141
154
168 168
-
25
50
75
100
125
150
175
200
225
250
Sep-17 Mar-18 Sep-18 Mar-19 Sep-19 Mar-20 Sep-20
(Th -
$)
TA 9392- Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Clo
sin
g: 3
0 J
un
20
20
Net TA amount: $ 225 (Th)
231
Public Sector Management
TA 9467-PAK: Strengthening the Federal Public-Private Partnership Framework and Enabling Reforms for Infrastructure Financing Support
TA 9467-PAK: Strengthening the Federal Public-Private Partnership Framework and Enabling Reforms for Infrastructure Financing Support
A. TA Basic Data US$ (Thousand)
Approval Date Signing
Date Closing
Date
Closing Date
(Revised)
Time Elapse
%
Contract Award
(Cumulative)
Disbursements (Cumulative)
13-Dec-17 8-Jan-18 31-Dec-20 59 634.68 301.38 Approved Amount
Net TA Amount
Financing Project Officer
Project Analyst
Counterpart Agencies
3,266.21 3,266.21 DPECP S. Masood Z. Hamid Ministry of Finance
B. TA Description 1. The proposed knowledge and support technical assistance (TA) will support the enabling environment for infrastructure financing in Pakistan through capacity development, and research and policy advice for supporting the legal and institutional framework of infrastructure financing, public private partnerships (PPPs), and public debt management. The proposed TA will also fund the preparation of a target infrastructure project to be delivered as a PPP project. 2. The TA is included in the current COBP 2017-19 for Pakistan. Outputs of the TA will also support the policy lending reforms for program loans in public financial management. C. Project Monitoring Framework (Current Status)
Outputs Performance Indicators Status with Key Activities
1. Support to develop institutional, legal, and regulatory frameworks for PPPs provided
1a. By 2018: Report on the gap analysis of the government’s existing (i) legal, institutional, and regulatory frameworks; and (ii) financial support mechanisms submitted to the MOF (2017 baseline: not applicable) 1b. By 2019: Report on sectors that are well suited for mobilizing private sector investments through PPPs submitted to the MOF and the Ministry of Planning (2017 baseline: not applicable) 1c. By 2019: Draft rules or guidelines for federal VGF and PDF submitted to the MOF (2017 baseline: not adopted)
Ongoing
2. Issues for operationalization of the PDFL determined and support to operationalize the PDFL provided
2a. By 2018: PDFL mandate and strategy agreed with government stakeholders (2017 baseline: not adopted) 2b. By 2019: Business and financing plan, including policies, manuals, environmental and social safeguard management system, and standard
Ongoing
232
Public Sector Management
TA 9467-PAK: Strengthening the Federal Public-Private Partnership Framework and Enabling Reforms for Infrastructure Financing Support
documentation templates for the PDFL developed (2017 baseline: not developed) 2c. By 2020: At least one target infrastructure project to be delivered as a PPP project prepared (2017 baseline: not applicable)
3. Infrastructure finance and PPP capacity of the Finance Division, the Planning Commission, and key line ministries enhanced
3a. By 2018: At least 12 senior staff members in identified divisions and/or agencies received training (2017 baseline: not applicable) 3b. By 2019: Terms of reference for specific positions or nodes created in at least three identified divisions and/or agencies (2017 baseline: not created) 3c. By 2020: PPP policy document drafts for reforms prepared in at least three identified divisions and/or agencies (2017 baseline: not prepared) 3d. By 2020: PPP advisory committee created with cross-ministerial representation from the Finance Division, Planning Commission, key line ministries, and provincial PPP units (2017 baseline: not created)
Ongoing
4. Potential reform areas for the development of long-term debt capital markets identified
4a. By 2019: Report on participation in public debt and availability of a secondary market for government bonds and other sovereign instruments, and recommendations for reform with focus on (i) fund mobilization from retail investors through potential sukukc issuances, and (ii) role and framework of the Central Directorate of National Savings with respect to debt market development in Pakistan provided (2017 baseline: not applicable) 4b. By 2019: Report identifying the impact of public debt policy and management on the mobilization of long-term financing from domestic commercial banks and other financiers (including retail investors), and recommendations for reform provided (2017 baseline: not applicable)
233
Public Sector Management
TA 9467-PAK: Strengthening the Federal Public-Private Partnership Framework and Enabling Reforms for Infrastructure Financing Support
D. Cumulative Contract Award and Disbursement Performance
E. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
Current Status
1 Full time CEOs for PPP Authority and PDFL to be engaged.
Recruitment to be expedited. 30 Sep 2019 Yet to be completed
2 A review of PPP Authority Act and drafting of related rules and guidelines, where required.
Drafts of the VGF rules, PDF rules, Procurement rules and Conduct of Business rules have been shared with MOF on 21 Sepe 2019. Feedback on the drafts to be provided by the committee nominated for the review and finalization of the drafts.
Revised draft submitted in August 2019
Yet to be completed
-- - 35 138
285
450
635
- 17 61 93
217 301
-
500
1,000
1,500
2,000
2,500
3,000
3,500
Jun-17 Dec-17 Jun-18 Dec-18 Jun-19 Dec-19 Jun-20 Dec-20
(Th -
$)
TA 9467- Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Clo
sin
g: 3
1 D
ec 2
02
0
Net TA amount: $ 3,266 (Th)
234
Public Sector Management
TA 9467-PAK: Strengthening the Federal Public-Private Partnership Framework and Enabling Reforms for Infrastructure Financing Support
F. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No issues
235
Public Sector Management
TA 9469-PAK: Enhancing Public-Private Partnerships in Punjab
TA 9469-PAK: Enhancing Public-Private Partnerships in Punjab
A. TA Basic Data US$ (Thousand)
Approval Date Signing
Date Closing
Date
Closing Date
(Revised)
Time Elapse
%
Contract Award
(Cumulative)
Disbursements (Cumulative)
15-Dec-17 9-Jan-18 31-Dec-22 - 36 369.39 233.07 Approved Amount
Net TA Amount
Financing Project Officer
Project Analyst
Counterpart Agencies
4,008.72 4,008.72 DPECP S. Masood M. Sheikh P&D, Government of Punjab
B. TA Description The transaction TA will help improve government capacity to (i) review PPP project proposals that require VGF support, (ii) provide recommendations to the PPP steering committee, and (iii) monitor project performance. The TA will also help improve the capacity of the government in evaluating PPP project proposals from selected line departments, and in monitoring projects in accordance with the environmental and social management system and other relevant regulations. The TA will also support information sessions on PPPs to identify and navigate impediments to private sector participation, which will promote the sustainability of and knowledge sharing about PPPs in Punjab. C. Project Monitoring Framework (Current Status)
Outputs Performance Indicators Status with Key Activities ECD policy and operational framework developed in line with best practice.
By 2020: Framework is adopted by at least one stakeholder
Complete draft reports on ECD, SEZs and improving Pakistan’s competitiveness including the strategic policy frameworks and SEZs assessment analytical tool have been shared with government and other key stakeholders such as DFID for consultations, institutionalisation and adoption. The ECD, SEZs and improving competitiveness strategic policy frameworks have been transformed into national policies, as part of the Ministry of Commerce’s upcoming Strategic Trade Policy Framework 2018-2023.
236
Public Sector Management
TA 9469-PAK: Enhancing Public-Private Partnerships in Punjab
D. Cumulative Contract Award and Disbursement Performance
E. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. Please refer to Loan 3636-
PAK
F. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. Please refer to Loan 3636-
PAK
---
217 254 343 369 369
- 47 67 115 216 233 -
500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
4,500
Jun-17 Dec-17 Jun-18 Dec-18 Jun-19 Dec-19 Jun-20 Dec-20 Jun-21 Dec-21 Jun-22 Dec-22
(Th -
$)
TA 9469- Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Clo
sin
g: 3
1 D
ec 2
02
2
Net TA amount: $ 4,009 (Th)
237
Public Sector Management
TA 9488-PAK: Supporting Economic Corridor Development through Strategic Planning Frameworks
TA 9488-PAK: Supporting Economic Corridor Development through Strategic Planning Frameworks
A. TA Basic Data US$ (Thousand)
Approval Date Signing
Date Closing
Date
Closing Date
(Revised)
Time Elapse
%
Contract Award
(Cumulative)
Disbursements (Cumulative)
15-Dec-17 29-Jan-18 30-Jun-20 - 70 1,526.51 1,128.02 Approved Amount
Net TA Amount
Financing Project Officer
Project Analyst
Counterpart Agencies
2,418.08 2,418.08 DPECP G.
Sugiyarto K. Ali
Ministry of Planning, Development and Reform
B. TA Description 1. The TA aims to assist Pakistan to realize the potential of economic corridor development (ECD) to boost industrial productivity, exports, and job creation and thereby contribute to sustained, increased and equitable economic growth. The key focus of the TA is to (i) further study the corridors to be included in the TA scope; (ii) enhance the value chain development program along the corridors; and (iii) strengthen strategies, policies, institutions, and coordination, including by promoting the role of the private sector, strengthening capacity, and learning from best practices. 2. This knowledge and support TA (KSTA) will build upon the preceding small-scale policy and advisory technical assistance (S-PATA) to enable the development of the strategic policy frameworks for better planned ECD in Pakistan. In particular, it will facilitate the development of (i) the strategic policy framework for ECD; (ii) strategic policy framework for improving Pakistan’s trade competitiveness coupled with supporting the feasibility studies on various ECD related critical issues such as specialized economic zones (SEZs) to identify the international best practices and benchmarks for informed policy making; (iii) analytical tools as part of decision support system, and; (iv) ECD Hub to facilitate professional networking along key stakeholders, both nationally and internationally. The outcome will be a well-planned ECD resulting in increased investment, competitiveness, productivity, connectivity, exports and economic activity.
C. Project Monitoring Framework (Current Status)
Outputs Performance Indicators Status with Key Activities ECD policy and operational framework developed in line with best practice.
By 2020: Framework is adopted by at least one stakeholder
The complete draft reports on ECD and SEZ development including the strategic policy frameworks have been developed and shared with government and other key stakeholders including DFID for consultations, adoption and institutionalization. ECD and SEZ frameworks are highly likely to be included as the national policies in the Ministry of Commerce's Strategic Trade Policy Framework (STPF) 2019–2023. The draft STPF has been prepared and submitted to the DG Trade Policy of Ministry of Commerce. Feedback on the draft is
238
Public Sector Management
TA 9488-PAK: Supporting Economic Corridor Development through Strategic Planning Frameworks
Outputs Performance Indicators Status with Key Activities positive, though Ministry would like to present to Cabinet only after the approval of the National Tariff Policy. A knowledge report titled “Economic Corridor Development in Pakistan” is expected to be published by January 2020.
ECD analytical tools developed
Main study result and tools are adopted by at least two stakeholders
ECD Decision Support System (ECD-DSS) including 5 analytical tools are at various stages of development, including: 1. District development monitor: the first draft of
the monitor has been developed and tool coverage is being extended to inform the revenue sharing formula of the National Finance Commission (NFC);
2. Tariff monitor: the conceptual framework has been developed and knowledge report titled “tariff structure and reforms” is expected to be published by March 2020.
3. Energy tariff monitor: conceptual framework has been established and work has commenced;
4. ECD-DSS: the first draft of the model has been developed and presented to BOI to receive valuable feedback for further strengthening; and
5. CPEC financial monitor: the excel based monitor has been developed and knowledge report titled “CPEC: Fiscal and External Implications” is expected to be published by February 2020.
Pakistan ECD hub developed
ECD hub is established in partnerships with at least four think tanks
Moving forward, the development of an ECD hub based on global best practice is a top priority, which was delayed due to administrative changes. The hub will also house the first round of knowledge products developed under the KSTA. Concept note and TORs have been developed and consultant recruitment process is in process.
Strategic policy framework for improving trade competitiveness developed
Framework is adopted by the government
The complete draft report on improving competitiveness including the strategic policy framework has been prepared and shared with government and other key stakeholders for consultations, adoption and institutionalization. Improving competitiveness framework is highly likely to be adopted as the national policy under the Ministry of Commerce's STPF 2019–2023, which has been prepared and submitted to the DG Trade Policy of Ministry of Commerce. Feedback on the draft is positive, though Ministry would like to present to Cabinet only after the approval of the National Tariff Policy.
239
Public Sector Management
TA 9488-PAK: Supporting Economic Corridor Development through Strategic Planning Frameworks
D. Cumulative Contract Award and Disbursement Performance
E. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No Issues
F. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. Timely adoption of
strategic policy
frameworks.
Approval of National Strategic Trade
Policy Framework (STPF) 2019–2023 by
the government, incorporating elements of
strategic policy frameworks drafted under
the TA on trade competitiveness and
economic corridor development.
TBD / Ministry of
Commerce
-- -
154
378
514
1,302
1527
-54
188
426
855
1128
-
500
1,000
1,500
2,000
2,500
Jun-17 Dec-17 Jun-18 Dec-18 Jun-19 Dec-19 Jun-20
(Th -
$)
TA 9488 - Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Clo
sin
g: 3
0 J
un
20
20
Net TA amount: $ 2,418 (Th)
240
Public Sector Management
TA 9580-PAK: Preparing the Trade and Competitiveness Program
TA 9580-PAK: Preparing the Trade and Competitiveness Program
A. TA Basic Data US$ (Thousand)
Approval Date
Signing Date
Closing Date
Closing Date
(Revised)
Time Elapse
%
Contract Award
(Cumulative)
Disbursements (Cumulative)
5-Sep-18 3-Oct-18 31-Jul-20 - 56 214.50 94.31 Approved Amount
Net Amount Financing Project Officer
Project Analyst
Counterpart Agencies
750.00 750.00 TASF H. Mukhopadhyay
L. Raquipiso
Ministry of Finance, Revenue and Economic Affairs
B. TA Description The proposed PPTA will help in processing the program loan which is aimed to help in the recovery of the current account deficit and promote macroeconomic stability and sustained high growth by facilitating improved competitiveness and exports. The proposed program will (i) introduce important tariff and tax policy reforms to support Pakistan’s exporting industries and improve their competitiveness internationally; and (ii) strengthen key institutions involved in facilitating trade, including accreditation bodies and operationalization of the EXIM Bank of Pakistan (EXIMBP) and the National Single Window (NSW). C. Cumulative Contract Award and Disbursement Performance
- -- -
215 215
0
-
94 94
-
100
200
300
400
500
600
700
800
Sep-18 Mar-19 Sep-19 Mar-20 Sep-20
(Th -
$)
TA 9580- Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Clo
sin
g: 3
1 J
ul 2
02
0
Net TA amount: $ 750 (Th)
241
Public Sector Management
TA 9580-PAK: Preparing the Trade and Competitiveness Program
D. Action Plan discussed in 2nd TPR
Sr. No Issue Action to be Taken Due Date / By Whom
1. No issues
E. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No issues
242
Public Sector Management
TA 9588-PAK: Promoting Investments and Economic Growth through International Trade
TA 9588-PAK: Promoting Investments and Economic Growth through International Trade
A. TA Basic Data US$ (Thousand)
Approval Date
Signing Date
Closing Date
Closing Date
(Revised)
Time Elapse
%
Contract Award
(Cumulative)
Disbursements (Cumulative)
14-Sep-18 12-Oct-18 31-Dec-19 - 81 383.52 95.88 Approved Amount
Net Amount Financing Project Officer
Project Analyst
Counterpart Agencies
500.00 500.00 TASF S. Masood
L.Isabel Ministry of Finance, Revenue
and Economic Affairs
B. TA Description The proposed knowledge and support technical assistance (TA) from Asian Development Bank (ADB) will support the operationalization of the EXIM Bank of Pakistan (EXIMBP) which will provide trade financing facilities to help local exporters get access to much needed financing to competitively trade internationally. Overtime, this will help the economy increase and diversify its export base and promote long-term economic growth. The TA will build on the outputs by International Financial Consulting under TA-8832 which produced a draft operational roadmap for EXIMBP.
C. Project Monitoring Framework (Current Status)
Outputs Performance Indicators Status with Key Activities
1. EXIMBP operational and institutional structure reviewed
1. Recommendations on operational and institutional structure adopted by EXIMBP (2018 baseline: Not reviewed)
In process
2. Operational road map and business plan updated
2a. Updated operational road map and business plan adopted by EXIMBP. (2018 baseline: Not updated) 2b. Product suite offering for exporters and banks developed (2018 baseline: Not developed) 2c. Operational policies and manuals established by EXIMBP. (2018 baseline: Not established) 2d. Management information system established by EXIMBP. (2018 baseline: Not established)
In process
243
Public Sector Management
TA 9588-PAK: Promoting Investments and Economic Growth through International Trade
Outputs Performance Indicators Status with Key Activities
3. Legal and regulatory framework and other institutional arrangements required for EXIM
BP’s operation
3a. Relevant government legal act enacted, or legal framework established (2018 baseline: Not established) 3b. Board charter and manual developed (2018 baseline: Not developed) 3c. Mode of government financial backing finalized for EXIMBP and national interest account established (2018 baseline: Not established)
Draft Act submitted to the government. Feedback received. Awaiting confirmation on Steering Committee meeting.
4. Economic, financial, and safeguards assessment performed
4a. EXIMBP capital structure and forecast financial model established by EXIMBP. (2018 baseline: Not established) 4b. Financial management assessment recommendation adopted by EXIMBP (2018 baseline: Not assessed) 4c. ESMS established by EXIMBP (2018 baseline: Not established)
Yet to be initiated
D. Cumulative Contract Award and Disbursement Performance
- - - -
384 384
0
-
96 96
-
100
200
300
400
500
Sep-18 Mar-19 Sep-19 Mar-20
(Th -
$)
TA 9588- Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Clo
sin
g: 3
1 D
ec 2
01
9
Net TA amount: $ 500 (Th)
244
Public Sector Management
TA 9588-PAK: Promoting Investments and Economic Growth through International Trade
E. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No issues
F. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No issues
245
Public Sector Management
TA 9688-PAK: Economic Management Support
TA 9688-PAK: Economic Management Support
A. TA Basic Data US$ (Thousand)
Approval Date
Signing Date
Closing Date
Closing Date
(Revised)
Time Elapse
%
Contract Award
(Cumulative)
Disbursements (Cumulative)
18-Dec-18 18-Dec-18 30-Jun-20 51 103.30 42.90 Approved Amount
Net Amount Financing Project Officer
Project Analyst
Counterpart Agencies
225.00 225.00 TASF K. Rosbach
C. Espina Ministry of Finance, Revenue
and Economic Affairs
B. TA Description This TA is supporting evidence-based decision making on the seven outlined most binding constraints to Pakistan’s economic recovery. The proposed TA is mobilizing quick initial support while the economic policies are being shaped. To support the Pakistan Government in developing sustainable economic reforms, the TA will finance the preparation of policy papers, briefs and road maps for the following binding constraints to inclusive and sustainable economic growth in Pakistan: (i) diversification of the economy and export sophistication; (ii) energy sector reforms to reduce subsidies, substantially clear the circular debt in the sector, and move to multi-year cost recovery tariffs; (iii) rule-based fiscal policies that help limit expenditure and broaden the tax base; (iv) agricultural policies to reduce output fluctuations; (v) corporatization and privatization of public sector enterprises; (vi) strengthening the independence of the State Bank of Pakistan (Central Bank); and (vii) social policies and targeted transfers for the poor.
C. Project Monitoring Framework (Current Status)
Outputs Performance Indicators Status with Key Activities Policy notes and roadmaps on important economic policy reforms completed
At least 8 policy notes/roadmaps produced by 2020
Two policy notes on public finance gaps and needs, and tax policy unit proposal completed.
Preparation of concept notes and identification of key reforms to be supported under ADB’s policy-based lending to Pakistan finalized
At least 2 budget support and policy-based operations supported by 2020
Support for the formulation of the inclusive and sustainable growth analysis.
Knowledge sharing activities completed
At least 30 government staff with increased awareness of trade-offs in key economic policy decisions
246
Public Sector Management
TA 9688-PAK: Economic Management Support
D. Cumulative Contract Award and Disbursement Performance
E. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No issues
F. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No issues
- -- -
103 103
0
-
14
43
-
50
100
150
200
250
Sep-18 Mar-19 Sep-19 Mar-20 Sep-20
(Th -
$)
TA 9688- Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Clo
sin
g: 3
0 J
un
20
20
Net TA amount: $ 225 (Th)
247
Public Sector Management
TA 9730-PAK: Improving Workforce Readiness in Punjab
TA 9730-PAK: Improving Workforce Readiness in Punjab
A. TA Basic Data US$ (Thousand)
Approval Date
Signing Date
Closing Date
Closing Date
(Revised)
Time Elapse
%
Contract Award
(Cumulative)
Disbursements (Cumulative)
17-Apr-18 28-May-19 30-Apr-21 - 22 582.16 28.90 Approved Amount
Net Amount Financing Project Officer
Project Analyst
Counterpart Agencies
800.00 800.00 TASF N. LaRocque
M. Isabel Industries, Commerce and
Investment Department
B. TA Description This PPTA will support processing the proposed Improving Workforce Development in Punjab (IWRP) Project is estimated to cost $110 million, of which the ADB will finance $100 million from ordinary capital resources (regular loan). The Government of Punjab will contribute in-kind assistance of $10 million. The IWRP Project will strengthen the technical and vocational education and training (TVET) sectors ability to support economic growth and job creation in priority economic sectors, including export-oriented sectors. The IWRP Project will expand use of competency-based training and assessment (CBTA), reform the TVET institutional framework, and develop TVET centers of excellence (COEs) and sector skills councils. It will also expand work-based training, strengthen of industry-TVET linkages, address the lack of female participation in TVET, expand entrepreneurship programs for TVET graduates, and introduce the private management of public TVET institutes.
C. Project Monitoring Framework (Current Status)
Outputs Performance Indicators Status with Key Activities
Detailed project design developed
(i) Design of the project; (ii) preparation of detailed project costings; (iii) preparation of a project design and monitoring framework; (iv) identification of sector capacity building requirements; (v) identification of project TVET institutes; (vi) identification of priority economic sectors; (vii) initial architectural designs for project institutes, as required; (viii) development of the project procurement plan; and (ix) specification of project implementation plan
Inception Mission and one additional project preparation mission fielded so far
Project due diligence undertaken
(i) TVET sector assessment, (ii) environmental assessment, (iii) economic and financial analysis, (iv) gender, poverty and social analysis, (v) financial management assessment of the executing and implementing agencies, (vi) procurement capacity and financial management assessments of the executing and implementing agencies; (vii) procurement risk assessment and procurement classification; (viii) social safeguards assessments; and (ix) risk assessment and management plan
Inception Mission and one additional project preparation mission fielded so far
248
Public Sector Management
TA 9730-PAK: Improving Workforce Readiness in Punjab
D. Cumulative Contract Award and Disbursement Performance
E. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No issues
F. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No issues
Project processing and implementation startup facilitated
(i) RRRP and linked documents, (ii) project administration manual; and (iii) project startup and implementation support, including establishment of project implementation unit
Inception Mission and one additional project preparation mission fielded so far
- - -
58
582
0
2
29
-
250
500
750
Dec-18 Mar-19 Jun-19 Sep-19 Dec-19 Mar-20 Jun-20 Sep-20 Dec-20 Mar-21 Jun-21
(Th -
$)
TA 9730- Contract Award and Disbursement Performance to Date
Contract Awards DisbursementsC
losin
g: 3
0 A
pr
20
21
Net TA amount: $ 800 (Th)
249
Public Sector Management
TA 9788-PAK: Supporting Development of Additional Financing for Social Protection Development Project
TA 9676-PAK: Capacity Building for Structural Transformation, Country Programming, and Portfolio Management
A. TA Basic Data US$ (Thousand)
Approval Date
Signing Date
Closing Date
Closing Date
(Revised)
Time Elapse
%
Contract Award
(Cumulative)
Disbursements (Cumulative)
6-Dec-18 17-Dec-18 31-Dec-21 - 27 673.30 138.56
321.31 104.76
Approved Amount
Net Amount Financing Project Officer
Project Analyst
Counterpart Agencies
750.00 2000.00
750.00 2000.00
CEF TASF
Z. Wu L.Domingo
M. A. Sheikh
Ministry of Finance, Revenue and Economic Affairs
B. TA Description The knowledge and support technical assistance (TA) will support capacity building of Pakistan’s federal and provincial governments on the structural transformation, programming, and management of the Asian Development Bank (ADB) portfolio in Pakistan. Initiated at the request of the Government of Pakistan, the TA will (i) facilitate the effective and efficient delivery of the development impacts of new structural reform initiatives; and (ii) deepen the anchoring of ADB’s country partnership strategy, country programming, and portfolio management in the government’s policies and strategies.
C. Project Monitoring Framework (Current Status)
Outputs Performance Indicators Status with Key Activities Operational guidelines developed, and capacity of key government agencies enhanced.
1a. By 2021: at least three operational knowledge training manuals or guidelines developed, including curricula and modules on technical aspects of development projects for judicial and oversight bodies. (2018 baseline: 0) 1b. By 2021: at least 450 participants, at least 20% of whom are female, and at least 70% of government officials trained improved their skills on procurement, safeguards, gender mainstreaming, contract management, financial management, and other aspects of programming and project implementation. (2018 baseline: 0) 1c. By 2021: ADB Pakistan alumni network established. (2018 baseline: not established) 1d. Annual capacity development reports that track progress against established baselines published. (2018 baseline: 0)
15 consultants have been recruited either individually or through a firm under the TA. They have provided advisory support and/or knowledge products in a multitude of fields including biogas, financial and economic analysis, contract management, procurement, social safeguards, environment, gender, communications and knowledge management.
Advisory support for the government’s structural reforms and policy
2a. By 2019: working groups supported by technical advisors in key ministries set up. (2018 baseline: not established)
250
Public Sector Management
TA 9788-PAK: Supporting Development of Additional Financing for Social Protection Development Project
development provided and knowledge on relevant sectoral and thematic issues enhanced.
2b. By 2021: at least three knowledge products related to policy and reform produced. (2018 baseline: 0) 2c. By 2021: at least three knowledge events in emerging areas, such as urbanization, climate resilience, and information and communications technology, conducted (with at least 20% female participants), and at least 70% of participants improved their knowledge of the relevant sectoral and thematic areas. (2018 baseline: 0)
D. Cumulative Contract Award and Disbursement Performance
- - -
747 812
-
216 426
-
500
1,000
1,500
2,000
2,500
3,000
Dec-18 Jun-19 Dec-19 Jun-20 Dec-20 Jun-21 Dec-21
(Th -
$)
TA 9676- Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Clo
sin
g: 3
1 D
ec 2
02
1
Net TA amount: $ 2,750 (Th)
251
Public Sector Management
TA 9788-PAK: Supporting Development of Additional Financing for Social Protection Development Project
E. Status of the Action Plan discussed in 2nd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No issues
F. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No issues
252
Public Sector Management
TA 9788-PAK: Supporting Development of Additional Financing for Social Protection Development Project
TA 9788-PAK: Supporting Development of Additional Financing for Social Protection Development Project
A. TA Basic Data US$ (Thousand)
Approval Date
Signing Date
Closing Date
Closing Date
(Revised)
Time Elapse
%
Contract Award
(Cumulative)
Disbursements (Cumulative)
13-Aug-19 - 31-Aug-20 - 13 - -
Approved Amount
Net Amount Financing Project Officer
Project Analyst
Counterpart Agencies
225.00 225.00 TASF L.Tora O.B.Zia
H.Ambreen Benazir Income Support
Program
B. TA Description The knowledge and support TA will primarily help with the setting up of the proposed Policy and Research Unit (PRU), in line with the envisaged institutional strengthening of the Benazir Income Support Program (BISP). This KSTA is expected to help operationalize the concept of the PRU and assist in key factors such as staffing model, contract design, terms of reference, recruitment process, reporting lines, performance evaluations mechanisms, monitoring and evaluation plan, and budgeting. Subsequently, this KSTA will ensure BISP-additional financing project readiness and minimize possible start-up delays in its implementation.
C. Project Monitoring Framework (Current Status)
Outputs Performance Indicators Status with Key Activities 1. Strategic Business Plan for
BISP prepared. The TA consultants will assist BISP in developing a strategic business plan and in setting up and operationalizing a PRU. The PRU will (i) develop a policy framework for BISP and support policy and legislative development; (ii) help monitor and improve performance of ongoing programs while developing new evidence-based initiatives to effectively address intergenerational poverty; (iii) study cost-effectiveness, financial feasibility, and scalability of new interventions; and (iv) serve as a knowledge management and data analytics hub for BISP.
1.1 Consultant recruitment. 1.2 Stakeholder consultations
within BISP. 1.3 Preparation of Strategic
Business Plan 1.4 Dissemination of Business Plan to key stakeholders.
Consultants recruitment is ongoing
2. PRU plan fully developed. The TA consultants well help BISP (i) set up and operationalize a PRU, with a
2.1 Consultant recruitment. 2.2 Staffing plan developed
(including number and skill mix of staff; staffing contracts;
Consultants recruitment is ongoing
253
Public Sector Management
TA 9788-PAK: Supporting Development of Additional Financing for Social Protection Development Project
work plan for year one and a mechanism for developing annual plans for policy research. The consultant will ensure that this preparatory work for the additional financing and will assist the component on PRU to be launched immediately as the loan becomes effective
TORs; reporting lines; performance evaluation standards).
2.3 Fully developed budget and workplan (with M&E plan).
2.4 Development of collaborating institutions network.
2.5 Recruitment of key PRU staff and orientation.
3. Priority actions and plan for strengthening fiduciary systems and EFC framework developed.
The TA consultants will conduct a desk review of the relevant manuals, assessments of beneficiary identification, payment, case management, monitoring and evaluation, finance and audit, and procurement systems and processes of BISP and its development partners.
3.1 Consultant recruitment. 3.2 Review of existing systems
and assessment of gaps in financial management and internal controls.
3.3 Review progress on EFC framework action plan in collaboration of DFID and WB.
3.4 Development of action plans for implementing EFC action plan in collaboration with DFID and WB.
Development of TORs.
Yet to be initiated
D. Cumulative Contract Award and Disbursement Performance
- - 0 0 0
0 00
-
50
100
150
200
250
300
Dec-18 Jun-19 Dec-19 Jun-20 Dec-20
(Th -
$)
TA 9788- Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Clo
sin
g: 3
1 A
ug
20
20
Net TA amount: $ 225 (Th)
254
Public Sector Management
TA 9788-PAK: Supporting Development of Additional Financing for Social Protection Development Project
E. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No issues
255
Public Sector Management
TA 9789-PAK: Financial Markets Development Program
TA 9789-PAK: Financial Markets Development Program
A. TA Basic Data
US$ (Thousand)
Approval Date
Signing Date
Closing Date
Closing Date
(Revised)
Time Elapse
%
Contract Award
(Cumulative)
Disbursements (Cumulative)
15-Aug-19 6-Sep-19 31-Aug-20 - 12 - -
Approved Amount
Net Amount Financing Project Officer
Project Analyst
Counterpart Agencies
500.00 500.00 TASF S.A.Shah M.T.
Bartolome Ministry of Finance
B. TA Description The transaction TA will support diagnostic studies, policy dialogue, and the preparation of the proposed Financial Markets Development Program. It will also help the Pakistan Government formulate a national capital market development master plan. The reforms under the program will serve to remove the binding constraints to the achievement of a vibrant capital market, such as (i) ad hoc government debt management practices and absence of a clear capital market development strategy for debt issuances; (ii) shallow and illiquid corporate bond and equity markets, and ineffective market facilitation; and (iii) fragile market stability. The TA will also explore the measures required to encourage broader participation of institutional investors in Pakistans securities markets, and to lay the groundwork for introducing alternative financing instruments, such as derivatives, as the financial markets develop.
C. Project Monitoring Framework (Current Status)
Outputs Status with Key Activities
Long-term national capital market development strategy and implementation plan formulated and implemented.
Ongoing
Legal, regulatory, and institutional framework streamlined Ongoing
Development of debt and equity markets supported by broad demand and supply measures
Ongoing
256
Public Sector Management
TA 9789-PAK: Financial Markets Development Program
D. Cumulative Contract Award and Disbursement Performance
E. Action Plan to be discussed in 3rd TPR
Sr.
No
Issue Action to be Taken Due Date
/ By Whom
1. No Issues
- - 0 0 0
0 00
-
100
200
300
400
500
600
Dec-18 Jun-19 Dec-19 Jun-20 Dec-20
(Th -
$)
TA 9789- Contract Award and Disbursement Performance to Date
Contract Awards Disbursements
Clo
sin
g: 3
1 A
ug
20
20
Net TA amount: $ 500 (Th)