1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
-
Upload
anthony-dorsey -
Category
Documents
-
view
217 -
download
0
Transcript of 1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
![Page 1: 1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.](https://reader033.fdocuments.net/reader033/viewer/2022051517/56649f455503460f94c6609d/html5/thumbnails/1.jpg)
1
MICE Hall and Infrastructure- Progress since CM18
Chris NelsonMICE CM19 Oct 2007
![Page 2: 1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.](https://reader033.fdocuments.net/reader033/viewer/2022051517/56649f455503460f94c6609d/html5/thumbnails/2.jpg)
2
Contents
•What we’ve achieved…
•Current View/s of hall
•Status: – Q35 Refurb– Baseplates/Magnet stands– MLCR– Magnetic shielding walls– Hall Water supply – Platforms and Baseplates– Electrical
![Page 3: 1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.](https://reader033.fdocuments.net/reader033/viewer/2022051517/56649f455503460f94c6609d/html5/thumbnails/3.jpg)
3
What we’ve achieved… …CMS finished at last! -space used immediately.
![Page 4: 1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.](https://reader033.fdocuments.net/reader033/viewer/2022051517/56649f455503460f94c6609d/html5/thumbnails/4.jpg)
4
JUNE: North Wall start
![Page 5: 1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.](https://reader033.fdocuments.net/reader033/viewer/2022051517/56649f455503460f94c6609d/html5/thumbnails/5.jpg)
5
JUNE:Upstream shield
![Page 6: 1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.](https://reader033.fdocuments.net/reader033/viewer/2022051517/56649f455503460f94c6609d/html5/thumbnails/6.jpg)
6
JUNE:view of Hall
![Page 7: 1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.](https://reader033.fdocuments.net/reader033/viewer/2022051517/56649f455503460f94c6609d/html5/thumbnails/7.jpg)
7
What we’ve achieved… Solenoid plinth:First concrete pour: 26Jun07
![Page 8: 1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.](https://reader033.fdocuments.net/reader033/viewer/2022051517/56649f455503460f94c6609d/html5/thumbnails/8.jpg)
8
What we’ve achieved… D2 mounted in position
![Page 9: 1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.](https://reader033.fdocuments.net/reader033/viewer/2022051517/56649f455503460f94c6609d/html5/thumbnails/9.jpg)
9
What we’ve achieved… -Buffer tank and Platform-Enclosed Shielded area
![Page 10: 1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.](https://reader033.fdocuments.net/reader033/viewer/2022051517/56649f455503460f94c6609d/html5/thumbnails/10.jpg)
10
What we’ve achieved… Concrete shield wall
![Page 11: 1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.](https://reader033.fdocuments.net/reader033/viewer/2022051517/56649f455503460f94c6609d/html5/thumbnails/11.jpg)
11
Hall Progress Summary
Shielded area in use – waiting radiation Survey– Background refinements
– SW corner blocks on order– West wall replacement blocks at RAL– Extra wall near Door, and roof, subject to survey
Buffer tank and platform installed- Linde have startedElectrical work started in earnest (containment & cabling)Triplet build-up started, baseplatesNew full time Hall managerSignificantly more technician effort
![Page 12: 1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.](https://reader033.fdocuments.net/reader033/viewer/2022051517/56649f455503460f94c6609d/html5/thumbnails/12.jpg)
12
Current View/s of hall
![Page 13: 1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.](https://reader033.fdocuments.net/reader033/viewer/2022051517/56649f455503460f94c6609d/html5/thumbnails/13.jpg)
13
Current View/s of hall2
![Page 14: 1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.](https://reader033.fdocuments.net/reader033/viewer/2022051517/56649f455503460f94c6609d/html5/thumbnails/14.jpg)
14
Layout of hall 1
![Page 15: 1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.](https://reader033.fdocuments.net/reader033/viewer/2022051517/56649f455503460f94c6609d/html5/thumbnails/15.jpg)
15
Layout of hall 2
![Page 16: 1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.](https://reader033.fdocuments.net/reader033/viewer/2022051517/56649f455503460f94c6609d/html5/thumbnails/16.jpg)
16
Q35 RefurbishmentQ35 stands: Lower girder bases at RAL
![Page 17: 1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.](https://reader033.fdocuments.net/reader033/viewer/2022051517/56649f455503460f94c6609d/html5/thumbnails/17.jpg)
17
Q35s
Q35 Refurbishment– 2 complete– Program being accelerated with more technician
effort
Stands– Baseplates ready for grouting– Lower girder bases at RAL– Upper girder bases due this week– Remaining parts due end October– Accelerating trial build
![Page 18: 1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.](https://reader033.fdocuments.net/reader033/viewer/2022051517/56649f455503460f94c6609d/html5/thumbnails/18.jpg)
18
![Page 19: 1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.](https://reader033.fdocuments.net/reader033/viewer/2022051517/56649f455503460f94c6609d/html5/thumbnails/19.jpg)
19
located ready for levelling/aligning
![Page 20: 1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.](https://reader033.fdocuments.net/reader033/viewer/2022051517/56649f455503460f94c6609d/html5/thumbnails/20.jpg)
20
MLCR
Rack bases delivered beginning on this week.DPM for the floor completed by Friday.Network rack delivered next week.PPS rack, populated and tested delivered the week after (15th) Remaining racks the week of the 23rd.Walls delivered week of the 8th and installed by the end of the following week at the latest.Air con and power to start as soon as the walls are constructed and estimated to take three weeks so complete by 9th November.Construction of the roof to occur in parallel.Network connection to RAL site to start as soon as the racks have been Delivered. A wireless access point to be set up as soon as possible.Further wiring into the hall to follow. Too much civil still going on to start too early.
![Page 21: 1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.](https://reader033.fdocuments.net/reader033/viewer/2022051517/56649f455503460f94c6609d/html5/thumbnails/21.jpg)
21
Electrical Infra-structure
Drawings for distribution design complete– Final checks in progress, issue
next weekMICE Hall cable route design including LCR complete
– Busbar trunking removed– AC supply re-used as LCR feed
Cable schedule for magnet power converters complete
– Installation plan for DC and control cables to be agreed
Specification for power converters AC distribution scheme complete
– Installation in progress– Accelerator Dipole Power
Converter requires direct feed – Budget price received
Specification for RF System AC distribution scheme complete
– Awaiting price for installing distribution board
– Installation to commence within next 2 weeks
LCR tray work design complete– Rack support frames delivered– Tray work to be installed
• Sequence of installation to be agreed
– Raised floor to be installedCryogenic Soleniod
– Compressor supply installed– Distribution Board installed– AC temporary supply agreed for
testsPhase 2 electrical requirements under review
– Detailed information for all systems required
![Page 22: 1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.](https://reader033.fdocuments.net/reader033/viewer/2022051517/56649f455503460f94c6609d/html5/thumbnails/22.jpg)
22
Magnetic Shield
South Wall: Drgs completeSupport structure requote- Ready to buildMaterial identifiedPreparations to start procurement
North wall: Design being finished.Overall schedule to be prepared
![Page 23: 1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.](https://reader033.fdocuments.net/reader033/viewer/2022051517/56649f455503460f94c6609d/html5/thumbnails/23.jpg)
23
MICE – platforms and baseplates
CONCEPT – PLATFORM WITH AIR SKATES CLAMPED TO BASEPLATE IN INSTALLED LOCATION. WHEN ACCESS IS REQ’D THE CLAMPS ARE RELEASED AND THE TRACKER IS FLOATED TO A PARKED POSITION.
![Page 24: 1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.](https://reader033.fdocuments.net/reader033/viewer/2022051517/56649f455503460f94c6609d/html5/thumbnails/24.jpg)
24
Platform review
Design review last week:Supported mass up by 25% (7-9t)Clarification of cables esp. ‘live’
Not yet ready for productionClear issues before re-reviewing
![Page 25: 1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.](https://reader033.fdocuments.net/reader033/viewer/2022051517/56649f455503460f94c6609d/html5/thumbnails/25.jpg)
25
Mechanical Services
Water- Chiller order placed last Friday?
Other services/gases– Need for detector groups to request any
required services• Compressed air line for when Linde equipment in use• Nitrogen for CKOV (bottle/gas line)?
![Page 26: 1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.](https://reader033.fdocuments.net/reader033/viewer/2022051517/56649f455503460f94c6609d/html5/thumbnails/26.jpg)
26
Conclusion: Next High Priority!
-Concrete plinth for MICE Experiment
-False floor