000.265.1004
Transcript of 000.265.1004
7/28/2019 000.265.1004
http://slidepdf.com/reader/full/0002651004 1/3
Guideline 000 265 1004Date 06Nov2009
Page 1 of 3
PLOTPLAN SPACE REQUIREMENTS
Copyright ©2009, Fluor Corporation. All Rights Reserved. Electrical
PURPOSE
This document establishes guidelines to define the space requirements for Electricalequipment during plotplan development by Piping.
SCOPE
The guideline describes the items to be addressed, in order to have an optimal plantlayout, which is based on:
• Health, Safety and Environmental (HSE)• Authority/local requirements• Economics• Ergonomics• Practicality• Cost saving aspects• Specific client requirements
APPLICATION
All projects.
RESPONSIBILITY
The Project Lead Electrical should assign a task force member as originator, who isresponsible to provide the input to Piping with regard to electrical equipment and itemsrequiring space.
GENERAL GUIDELINES
Substation/Transformer Yard
Assess substation/transformer yard dimension, based on equipment information derivedfrom the key single line diagram, and locate facility adjacent and as central as possible tothe plant.
Possible locations are:
• outside the roads surrounding the plant,• Inside the roads surrounding the plant, provided that any impact caused by the
explosion hazardous area classification and fire hazard classification is observed• close to piperacks to easy overhead cable installations
Observe facility location with regard to prevailing wind.
Allow for safety-, working clearance and future facility extension.
7/28/2019 000.265.1004
http://slidepdf.com/reader/full/0002651004 2/3
Guideline 000 265 1004Date 06Nov2009
Page 2 of 3
PLOTPLAN SPACE REQUIREMENTS
Copyright ©2009, Fluor Corporation. All Rights Reserved. Electrical
Ensure free space around building entry for unloading and access for heavy equipmentthrough ramps, alleys, doors and neighboring structures.
Observe interference of major cable trenches interfacing with the facility or plantequipment.
Buildings General
Allow for safety and easy building access.
Note:
Dimensions of major equipment shall be based on vendor catalogue information andshall be used to define building sizes. Include clearance distances and future space tocome to a preliminary building size. Examples of major equipment and requirements thatmay have major space impacts are:
• MCC/SWGR's/Transformers/UPS/VSDS systems• Allow for safety and operation clearances around equipment• Allow for maintenance areas around equipment were required, include space to open
doors
Equipment in Plant Areas
Assess dimensions of major electrical and control system equipment associated with
process/mechanical equipment, based on vendor catalogue information and outlineestimated space requirement on layout. Examples of major equipment that may havespace impacts are:
• MW drives having auxiliary equipment such as captive or unit transformers, VSDS,local panels, etc.
• Allow for safety, working clearance and maintenance area around equipment,include space to open doors
• Consider adequate space for large size cable bends or sleeves requiring a large radiusto connect MW drives
• Corridors for high tension conductors and its interface / clearance with otherfacilities
• Space for busducts / supports• Requirement of batteries / acid storage rooms• Storage space for spares / warehousing• Operator's room.
Assess underground trench or cable tray dimensions, outline and locate trench corridorsor cable tray space requirements plant wide, based on (preliminary) required number of HV/MV/LV feeders, motor-, and associated control cables. Preferred location of maincable trenches onplot are under pipe racks, offplot along roads.
Asses space for main cable tray riser racks in front of substations.
7/28/2019 000.265.1004
http://slidepdf.com/reader/full/0002651004 3/3
Guideline 000 265 1004Date 06Nov2009
Page 3 of 3
PLOTPLAN SPACE REQUIREMENTS
Copyright ©2009, Fluor Corporation. All Rights Reserved. Electrical
REFERENCES
Checklist: Plot Plan Review 000 200 F0916
ATTACHMENTS
None