Post on 11-Jun-2020
SINDH IRRIGATION AND DRAINAGE AUTHORITY
Procurement Plan For Additional
Financing Water Sector Improvement Project Phase-1
September 2014
This Procurement Plan for WSIP Additional Financing covers all the procurement activities from March 2015 to December 2017 under components A, B, C and E of the Project
SINDH IRRIGATION AND DRAINAGE AUTHORITY (SIDA)
WATER SECTOR IMPROVEMENT PROJECT PROCUREMENT PLAN
( Component A- Community Development and Capacity Building of SIDA) Sub Component A1 – Capacity Building of SIDA
Procurement Activities
Activity 01 Office Equipment 01 for
SIDA Secretariat Hyderabad.
Laptop (06 Nos.)
Computers (15 Nos.)
UPS for Computers Multi Media (16 Nos.)
Printers (08 Nos.)
Scanner (05 Nos.) Fax Machine multi-
purpose (04 Nos.)
Estimated Cost: Rs. 2.35 Millions
Procurement Method: Shopping / Post Review
Activity 02
Office Equipment 02 for
SIDA Secretariat
Hyderabad.
Networking (01 Nos.)
LCD 32" (01 No.)
DVD player (01 No.)
Stereo Tap Recorder (01 No.)
PABX System (01 No.)
GPS (04 Nos.)
Handy cam (02 Nos.)
Internet USB PTCL EVO (05 Nos.)
Movie Camera (01 No.)
Still Camera/Digital Camera (02 Nos.)
Digital Multi Media Screen (01 No.)
Estimated Cost: Rs. 1.63 Millions
Procurement Method: Shopping / Post Review
Activity 03 Office Furniture for
SIDA Secretariat Hyderabad.
Estimated Cost: Rs. 0.5 Millions
Procurement Method:
Shopping / Post
Activity 04
Survey Equipment
for SIDA Secretariat
Hyderabad.
Water Analysis Kit(s) As per latest specification (01 No.)
Noise level equipment (02 Nos.)
Air pollution meter (02 Nos.)
Estimated Cost: Rs. 0.60 Millions
Procurement Method:
Shopping / Post
Activity 05
Software & Accessories for SIDA Secretariat
Hyderabad.
MS. Windows (Desktop PC) (54 Nos.)
MS. Windows (Server Machine) (02 Nos.)
MS. Office (54 Nos.)
Anti-Virus (Desktop PC) (54 Nos.)
Anti-Virus (Server Machine) (02 Nos.)
HR Software & Bio-metric Machine (04 Nos.)
Abiana MIS Software (01 No.)
Oracle License (01 No.)
Public Address System (01 No.)
External Passport Hard Disk (02 Nos.)
External DVD/Blue Ray Rider (02 Nos.)
Service Level Agreement for Softwares (01 No)
Estimated Cost: Rs. 7.94 Millions
Procurement Method:
Shopping / Post
Procurement Process Planned Dates
Preparation of RFQ May 13, 2015 June 10, 2015 Apr 10, 2015 June 10, 2015 May 13, 2015
Submission of RFQ to WB (prior review cases only)
N/A N/A N/A N/A N/A
NoL on RFQ from WB (prior review cases only)
N/A N/A N/A N/A N/A
RFQ Notification May 15, 2015 June 14, 2015 Apr 12, 2015 June 14, 2015 May 15, 2015
Quotation Submission May 30, 2015 June 30, 2015 Apr 27, 2015 June 30, 2015 May 30, 2015
Evaluation of Quotations Jun 05, 2015 Jul 07, 2015 May 03, 2015 Jul 07, 2015 Jun 05, 2015
Evaluation Report (ER) Submitted to WB (for Prior Review cases) & PMCA for validation
Jun 06, 2015 Jul 08, 2015 May 04, 2015 Jul 08, 2015
Jun 06, 2015
NoL on ER from WB (for Prior Review cases) & PMCA
Jun 13, 20115 Jul 15, 2015 May 10, 2015 Jul 15, 2015 Jun 13, 20115
Contract/P.O. Award Jun 14, 2015 Jul 16, 2015 May 12, 2015 Jul 16, 2015 Jun 14, 2015
Completion/Delivery Jul 15, 2015 Aug 16, 2015 Jun 12, 2015 Aug 16, 2015 Jul 15, 2015
SINDH IRRIGATION AND DRAINAGER AUTHORITY (SIDA) WATER SECTOR IMPROVEMENT PROJECT
PROCUREMENT PLAN (Component A- Community Development and Capacity Building) Sub Component A2- Capacity Building of Area Water Boards
Procurement Activities
Activity 01 Office Equipment- 01
Multimedia with Screen (03 Nos.)
GPS system (03 Nos.)
Digital Still Camera (03 Nos.)
Handycam Video Camera (03 Nos.)
Networking (03 Nos.)
Server for LAN (03 Nos.)
Mini Telephone Exchange (05 Nos.)
Software (03 Nos.)
Estimated Cost: Rs. 6.72 Million
Procurement Method:
Shopping*/Post Review
Activity 02 Office Equipment- 02
Laptop Computers (01 No.)
Desktop Computers & UPS (15 Nos.)
Printers Laser Jet (11 Nos.)
Estimated Cost: Rs. 1.27 Million
Procurement Method:
Shopping*/Post Review
Activity 03 Office Equipment- 03
Fax Machine (05 Nos.)
Photocopier (03 Nos.)
Estimated Cost: Rs. 0.85 Million
Procurement Method:
Shopping*/Post Review
Activity 04
Air Conditioners (07 Nos.)
Estimated Cost: Rs. 0.53 Million
Procurement Method: Shopping/Post Review
Activity 05
Accounting Software (03 Nos.)
Estimated Cost: Rs. 9.00 Millions
Procurement Method:
Shopping / Post Review
Activity 06
Furniture Fixture
Estimated Cost: Rs. 1.4 Million
Procurement Method:
Shopping*/Post Review
Procurement Process Planned Dates
Preparation of RFQ Oct 8, 2015 Oct 25, 2015 Oct 25, 2015 Apr 10, 2015 May 13, 2015 Apr 10, 2015 Submission of RFQ to WB (prior review cases only)
N/A N/A N/A N/A N/A N/A
NoL from WB (prior review cases only) N/A N/A N/A N/A N/A N/A RFQ Notification Oct 10, 2015 Oct 27, 2015 Oct 27, 2015 Apr 12, 2015 May 15, 2015 Apr 12, 2015 Quotation Submission Oct 25, 2015 Nov 12, 2015 Nov 12, 2015 Apr 27, 2015 May 30, 2015 Apr 27, 2015 Evaluation of Quotations Nov 02, 2015 Nov 14, 2015 Nov 14, 2015 May 03, 2015 Jun 05, 2015 May 03, 2015 Evaluation Report (ER) Submitted to WB (for Prior Review cases) & PMCA (all cases)
Nov 04, 2015 Nov 16, 2015 Nov 16, 2015 May 04, 2015
Jun 06, 2015 May 04, 2015
NoL on ER from WB (for Prior Review cases) & PMCA (all cases)
Nov 10, 2015 Nov 21, 2015 Nov 21, 2015 May 10, 2015 Jun 13, 20115 May 10, 2015
Contract/ P.O. Award Nov 12, 2015 Nov 22, 2015 Nov 22, 2015 May 12, 2015 Jun 14, 2015 May 12, 2015 Completion/ Delivery Dec 12, 2015 Dec 22, 2015 Dec 22, 2015 Jun 12, 2015 Jul 15, 2015 Jun 12, 2015
SINDH IRRIGATION AND DRAINAGER AUTHORITY (SIDA)
WATER SECTOR IMPROVEMENT PROJECT PROCUREMENT PLAN
(Component A- Community Development and Capacity Building) Sub Component A3- Capacity Building of Farmer’s Organization
Procurement Activities
Activity 01 Vehicles
Motorcycles (70CC) (96 Nos.)
Bicycles (96 Nos.)
Estimated Cost: Rs. 6.24 Millions
Procurement Method:
NCB /Post Review
Activity 02 Survey Equipment-01
Gauge (96 Nos.)
Pigmy Current Meter (96 Nos.)
Estimated Cost: Rs. 2.59 Millions
Procurement Method:
NCB/ Post Review
Activity 03 Office Equipment
*Computers Desktop Qty: 96 Nos. *Laser Printer Qty: 96Nos. *Fax machine Qty: 96 Nos.
Digital Still Camera Qty: 96 Nos.
Estimated Cost: Rs. 12.96 Millions
Procurement Method: NCB /Post Review
Activity 04 Survey Equipment-02
Engineering Level Machine (01 No.)
Schmidt Hammer (01 No.)
Slump Cone (01 No.)
Dry Thermo Meter (01 No.)
FDT (01 No.)
Complete set of sieves (01 No.)
Estimated Cost: Rs. 0.302 Millions
Procurement Method: Shopping /Post Review
Procurement Process Planned Dates
Preparation of IFB / RFQ Apr 10, 2015 Jul 10, 2015 May 2, 2015 Jul 10, 2015
Submission of IFB / RFQ to WB (prior review cases only)
N/A N/A N/A N/A
NoL on IFB / RFQ from WB (prior review cases only)
N/A N/A N/A N/A
IFB / RFQ Notification Apr 12, 2015 Jul 14, 2015 May 5, 2015 Jul 14, 2015
IFB / RFQ Submission Apr 27, 2015 Jul 30, 2015 May 20, 2015 Jul 30, 2015
ER Completion May 03, 2015 Aug 07, 2015 May 26, 2015 Aug 07, 2015
ER Submitted to WB (prior review cases only) and PMCA for validation
May 04, 2015 Aug 08, 2015 May 27, 2015 Aug 08, 2015
NoL on ER from WB for (prior review cases) and PMCA
May 10, 2015 Aug 15, 2015 Jun 03, 2015 Aug 15, 2015
Contract/ P.O. Award May 12, 2015 Aug 16, 2015 Jun 05, 2015 Aug 16, 2015
Contract Completion Jun 12, 2015 Sep 16, 2015 Jul 05, 2015 Sep 16, 2015
SINDH IRRIGATION AND DRAINAGER AUTHORITY (SIDA) WATER SECTOR IMPROVEMENT PROJECT
PROCUREMENT PLAN (Component B- Improvement of Irrigation and Drainage System) Sub Component B.1-Improvement of Main and Branch Canals
Procurement Activities
Activity 01 Rehabilitation of Mithrao Canal
Contract Package WSIP/B1/NC/03
Estimated Cost: US$ 33 million
Procurement Method:
ICB/Prior Review
Activity 02 Capital works in Ghotki Feeder Canal and
Masu Wah
Contract Package WSIP/B1/GF/01
Estimated Cost: US$ 40 million
Procurement Method:
ICB/Prior Review
Activity 03 Capital works in Fulleli Canal
Contract Package WSIP/B1/LB/01
Estimated Cost: US$ 40 million
Procurement Method:
ICB/Prior Review
Procurement Process Actual/Planned Dates
Prequalification:
Submission of PQD to WB Nov 22, 2013 Nov 22, 2013 Nov 22, 2013
NoL on PQD Jan 30, 2014 Jan 30, 2014 Jan 30, 2014
Invitation for PQ Applications Feb 05, 2014 Feb 05, 2014 Feb 05, 2014
Submission date Mar 26, 2014 Mar 26, 2014 Mar 26, 2014
Submission of PQ Assessment Report to WB September 1, 2014 September 1, 2014 September 1, 2014
NoL on PQAR September 5, 2014 September 5, 2014 September 5, 2014
Notification of PQAR September 5, 2014 September 5, 2014 September 5, 2014
Bidding:
Preparation of BD Aug 25, 2014 Sep 05, 2014 Sep 20, 2014
Submission of BD to WB Aug 30, 2014 Sep 10, 2014 Sep 25, 2014
NoL on BD Sep 10, 2014 Sep 20, 2014 Oct 05, 2014
IFB Notification Oct 10, 2014 Oct 10, 2014 Oct 10, 2014
Bid Submission Dec 10, 2014 Dec 10, 2014 Dec 10, 2014
Award Recommendation Dec 17, 2014 Dec 17, 2014 Dec 17, 2014
NoL on Award Recommendation Dec 24, 2014 Dec 24, 2014 Dec 24, 2014
LOA Dec 27, 2014 Dec 27, 2014 Dec 27, 2014
Contract Award Jan 27, 2015 Jan 27, 2015 Jan 27, 2015
Contract Notification Feb 04, 2015 Feb 04, 2015 Feb 04, 2015
Contract Completion Feb 03, 2017 Feb 03, 2017 Feb 03, 2017
Revised Completion Date - - -
SINDH IRRIGATION AND DRAINAGER AUTHORITY (SIDA)
WATER SECTOR IMPROVEMENT PROJECT PROCUREMENT PLAN
(Component B- Improvement of Irrigation and Drainage System) Sub Component B.2- Improvement of Distributaries/Minor canals
Procurement Activities
Activity 01 Rehabilitation works in RD 145 l/S, RD 118 L/S, FO RD 116 L/S Minor
Contract Package WSIP/B2/NC/29
Estimated Cost: Rs. 73.99 million
Procurement Method: NCB/Post Review
Activity 02 Rehabilitation works in Santraho, Gaindaho and Faqeerabad Minor
Contract Package WSIP/B2/NC/29C
Estimated Cost: Rs. 83.20 million
Procurement Method: NCB/Post Review
Activity 03 Rehabilitation works in Sorah Minor RD 261, Akkan War, Shakh Dadu Minor and Jumma Minor
Contract Package WSIP/B2/NC/29A
Estimated Cost: Rs. 42.65 million
Procurement Method: NCB/Post Review
Activity 04 Rehabilitation works in Gaji
Upper, Pitafi Minor, Reti Minor
Contract Package WSIP/B2/GF/34
Estimated Cost: Rs. 146.10 million
Procurement Method: NCB/Post Review
Activity 05 Rehabilitation works in Shah
Minor, Jarwar
Contract Package WSIP/B2/GF/35A
Estimated Cost: Rs. 41.49 million
Procurement Method: NCB/Post Review
Procurement Process Planned Dates
Preparation of BD Aug 12, 2015 Aug 12, 2015 Aug 12, 2015 Jan 12, 2015 Jan 12, 2015
Submission of BD to WB (prior review cases only)
N/A N/A N/A N/A N/A
NoL on BD from WB (prior review cases only)
N/A N/A N/A N/A N/A
IFB Notification Aug 22, 2015 Aug 22, 2015 Aug 22, 2015 Jan 22, 2015 Jan 22, 2015
Bid Submission Sep 22, 2015 Sep 22, 2015 Sep 22, 2015 Feb 24, 2015 Feb 24, 2015
BER Completion Oct 10, 2015 Oct 10, 2015 Oct 10, 2015 Mar 10, 2015 Mar 10, 2015
BER Submitted to WB (prior review cases only)
N/A N/A N/A N/A N/A
NoL on BER from WB N/A N/A N/A N/A N/A
Contract Award Nov 15, 2015 Nov 15, 2015 Nov 15, 2015 Apr 19, 2015 Apr 19, 2015
Contract Completion Sep 14, 2016 Sep 14, 2016 Sep 14, 2016 Feb 18, 2016 Feb 18, 2016
Procurement Activities
Activity 06 Rehabilitation works in
Dilawaro and Jindo Minors
Contract Package WSIP/B2/GF/35B
Estimated Cost:
Rs. 31.05 million
Procurement Method: NCB/Post Review
Activity 07 Rehabilitation works in
That, Dingro and Lathwaro Minor
Contract Package WSIP/B2/GF/36
Estimated Cost:
Rs. 81.61 million
Procurement Method: NCB/Post Review
Activity 08 Rehabilitation works in
Maharo Distributary and Lundi and Bagho Wah
Contract Package WSIP/B2/GF/37
Estimated Cost:
Rs. 90.77 million
Procurement Method: NCB/Post Review
Activity 09 Rehabilitation works in
Kheraj Minor
Contract Package WSIP/B2/GF/38
Estimated Cost:
Rs. 19.44 million
Procurement Method: NCB/Post Review
Activity 10 Rehabilitation works in Karo Ali Bahar, Hadachar and Hamira Minors
Contract Package WSIP/B2/LB/43A
Estimated Cost:
Rs. 68.26 million
Procurement Method: NCB/Post Review
Procurement Process Planned Dates
Preparation of BD Jan 12, 2015 Jan 12, 2015 Jan 12, 2015 Jan 12, 2015 Aug 12, 2015
Submission of BD to WB (prior review cases only)
N/A N/A N/A N/A N/A
NoL on BD from WB (prior review cases only)
N/A N/A N/A N/A N/A
IFB Notification Jan 22, 2015 Jan 22, 2015 Jan 22, 2015 Jan 22, 2015 Aug 22, 2015
Bid Submission Feb 24, 2015 Feb 24, 2015 Feb 24, 2015 Feb 24, 2015 Sep 22, 2015
BER Completion Mar 10, 2015 Mar 10, 2015 Mar 10, 2015 Mar 10, 2015 Oct 10, 2015
BER Submitted to WB (prior review cases only)
N/A N/A N/A N/A N/A
NoL on BER from WB N/A N/A N/A N/A N/A
Contract Award Apr 19, 2015 Apr 19, 2015 Apr 19, 2015 Apr 19, 2015 Nov 15, 2015
Contract Completion Feb 18, 2016 Feb 18, 2016 Feb 18, 2016 Feb 18, 2016 Sep 14, 2016
Component E- WSIP Project Coordination and Monitoring Unit Cost) SINDH IRRIGATION AND DRAINAGER AUTHORITY (SIDA)
WATER SECTOR IMPROVEMENT PROJECT PROCUREMENT PLAN (Supervision Consultants)
Procurement Activities
Activity 01
Consultancy Services for Supervision of Civil Works under Additional Financing
Estimated Cost: USD$ 4.00 Million
Procurement Method:
QCBS/Prior Review
Procurement Process Actual/Planned Dates
Preparation of TORs/Cost Estimates/EOI 20-Aug-14
Bank's No-objection to TORs & EOI (for prior review cases) 25-Aug-14
Advertising for Expression of Interests in National Newspapers. Additionally advertising in UNDP required for contract above $200,000
28-Aug-14
Receipt of Interests from Firms 27-Sep-14
Preparation of Short List 7-Oct-14
Bank's No Objection to Short List (for prior review cases only) 12-Oct-14
Preparation of RFP 17-Oct-14
Bank's No-objection to RFP (for prior review cases only) 22-Oct-14
Issuance of RFP to Short-listed Firms 27-Oct-14
Receipt of Technical & Financial Proposals 11-Dec-14
Completion of Technical Evaluation 21-Dec-14
Bank's no-objection to Technical Evaluation (for prior review cases) 26-Dec-14
Opening of Financial Proposal 31-Dec-14
Completion of Combined/Final Evaluation 10-Jan-15
For Bank's clearance, Combined/Final Evaluation needs to be submitted along with draft negotiated contract (for prior review cases)
17-Jan-15
Negotiations/ Preparation of Draft Contract 22-Jan-15
Bank's No-objection to draft Contract (for prior review cases) 29-Jan-15
Contract Signing 3-Feb-15
Contract Completion 02-Feb-18
SINDH IRRIGATION AND DRAINAGER AUTHORITY (SIDA) WATER SECTOR IMPROVEMENT PROJECT
PROCUREMENT PLAN (Component C- Improvement of Irrigation and Drainage System) (Goods)
Sub Component C.1- Strengthening office of Secretary Irrigation Department
Procurement Activities
Activity 01 Office Equipment
Laptops (01 No.)
Desktop Computer (01 No.)
UPS (01 No.)
Printer Laser jet (01 No.)
Movie Camera (01 No.)
Digital Still Camera (01 No.)
Estimated Cost: Rs. 0.25 Millions
Procurement Method: Shopping /Post Review
Activity 02 Vehicle
1300 CC Car (01 No.)
Estimated Cost: Rs. 2.00 Millions
Procurement Method: Shopping /Post Review
Activity 03
Air Conditioner (01 No.)
Estimated Cost: Rs. 0.05 Millions
Procurement Method: Shopping /Post Review
Procurement Process Planned Dates
Preparation of RFQ Oct 10, 2015 June 10, 2015 Apr 10, 2015
Submission of RFQ to WB (prior review cases only) N/A N/A N/A
NoL on RFQ from WB (prior review cases only) N/A N/A N/A
RFQ Notification Oct 12, 2015 June 14, 2015 Apr 12, 2015
RFQ Submission Oct 27, 2015 June 30, 2015 Apr 27, 2015
ER Completion Nov 03, 2015 Jul 07, 2015 May 03, 2015
ER Submitted to WB (prior review cases only) and PMCA for validation
Nov 04, 2015 Jul 08, 2015 May 04, 2015
NoL on ER from WB for (prior review cases) and PMCA Nov 10, 2015 Jul 15, 2015 May 10, 2015
Contract/ P.O. Award Nov 12, 2015 Jul 16, 2015 May 12, 2015
Contract Completion Dec 12, 2015 Aug 16, 2015 Jun 12, 2015
SINDH IRRIGATION AND DRAINAGER AUTHORITY (SIDA) WATER SECTOR IMPROVEMENT PROJECT
PROCUREMENT PLAN (Component E- WSIP Project Coordination and Monitoring Unit) (Goods)
Procurement Activities
Activity 01 Vehicles
Car (1300CC – 1600CC) (03 Nos.)
Estimated Cost: Rs.6.00 Million
Procurement Method: Shopping/Post Review
Activity 02 Vehicles-02
Motor Cycle 125CC (02 Nos.)
Estimated Cost: Rs.0.20 Million
Procurement Method: Shopping/Post Review
Activity 03 Office Equipment-01
Air Conditioner (Split Type) (08 Nos.)
Refrigerator / Water Cooler (03 Nos.)
Estimated Cost: Rs.0.56 Million
Procurement Method:
Shopping/ Post Review
Activity 04 Office Equipment-02
Photocopier (01 No.)
Fax Machine (03 No.)
Estimated Cost: Rs. 0.36Million
Procurement Method:
Shopping/ Post Review
Activity 05 Publication of a book on Glories of Irrigation System in Sindh
Estimated Cost: Rs. 2.00 Million
Procurement Method:
Shopping /Post Review
Procurement Process Planned Dates
Preparation of RFQ Apr 07, 2015 Apr 07, 2015 Apr 07, 2015 Sep 07, 2015 Apr 07, 2015
Submission of RFQ to WB (prior review cases only)
N/A N/A N/A N/A N/A
NoL from WB (prior review cases only) N/A N/A N/A N/A N/A RFQ Notification Apr 08, 2015 Apr 08, 2015 Apr 08, 2015 Sep 08, 2015 Apr 08, 2015 Quotation Submission Apr 23, 2015 Apr 23, 2015 Apr 23, 2015 Sep 23, 2015 Apr 23, 2015 Evaluation of Quotations Apr 30, 2015 Apr 30, 2015 Apr 30, 2015 Sep 30, 2015 Apr 30, 2015 Evaluation Report (ER) Submitted to WB (for Prior Review cases) & PMCA (all cases)
May 02, 2015 May 02, 2015 May 02, 2015 Oct 02, 2015 May 02, 2015
NoL on ER from WB (for Prior Review cases) & PMCA (all cases)
May 09, 2015 May 09, 2015 May 09, 2015 Oct 09, 2015 May 09, 2015
Contract/ P.O. Award May 10, 2015 May 10, 2015 May 10, 2015 Oct 10, 2015 May 10, 2015 Delivery Date Jun 10, 2015 Jun 10, 2015 Jun 10, 2015 Nov 10, 2015 Jun 10, 2015
Procurement Activities
Activity 06 Office Equipment
Desktop Computers (06 Nos.)
Lap top Computer (11 Nos.)
Printers (11 Nos.)
UPS (11 Nos.)
Stablizers (05 Nos.)
Scanner (02 Nos.)
Computer Software (20 Nos.)
Estimated Cost: Rs.3.3 Million
Procurement Method: Shopping/Post Review
Activity 07 Office Furniture
Furniture (lump sum) Chairs, Tables, Books Shelf, Cupboards, Sofa set, Computer Tables etc.
Estimated Cost: Rs.2.50 Million
Procurement Method: Shopping/Post Review
Activity 08
Networking Installation (01 No.)
Digital Camera (03 Nos.)
Estimated Cost: Rs.0.11 Million
Procurement Method: Shopping/Post Review
Activity 09
Supply, Installation and Commissioning of Video Conferencing Equipments Including LED with Complete Setup Video Conferencing System (VCS) in the Office of Project Coordination & Monitoring Unit (PCMU) and CCTV Cameras / Time attendance Machine
Estimated Cost: Rs. 2.60 Million
Procurement Method: Shopping/Post Review
Procurement Process Planned Dates
Preparation of RFQ Apr 27, 2015 Apr 27, 2015 Apr 07, 2015 Apr 07, 2015
Submission of RFQ to WB (prior review cases only)
N/A N/A N/A N/A
NoL from WB (prior review cases only) N/A N/A N/A N/A RFQ Notification Apr 29, 2015 Apr 29, 2015 Apr 08, 2015 Apr 08, 2015 Quotation Submission May 14, 2015 May 14, 2015 Apr 23, 2015 Apr 23, 2015 Evaluation of Quotations May 21, 2015 May 21, 2015 Apr 30, 2015 Apr 30, 2015 Evaluation Report (ER) Submitted to WB (for Prior Review cases) & PMCA (all cases)
May 28, 2015 May 28, 2015 May 02, 2015 May 02, 2015
NoL on ER from WB (for Prior Review cases) & PMCA (all cases)
May 30, 2015 May 30, 2015 May 09, 2015 May 09, 2015
Contract/ P.O. Award Jun 01, 2015 Jun 01, 2015 May 10, 2015 May 10, 2015 Delivery Date Jul 01, 2015 Jul 01, 2015 Jun 10, 2015 Jun 10, 2015
SINDH IRRIGATION AND DRAINAGER AUTHORITY (SIDA)
WATER SECTOR IMPROVEMENT PROJECT PROCUREMENT PLAN
(Component E- WSIP Project Coordination and Monitoring Unit) (Works)
Procurement Activities
Activity 01
Renovation of Office Building
Flooring
White Wash
Electricity Switch Boards
Windows / Blind
Cables Channel Grips
Drainage Maintenance
Parking Area / Kitchen
Kitchen Renovation
VC / Training Room
Estimated Cost: Rs.2.5 Million
Procurement Method:
Shopping/ Post Review
Procurement Process Planned Dates
Preparation of RFQ Apr 07, 2015
Submission of RFQ to WB (prior review cases only) N/A NoL from WB (prior review cases only) N/A RFQ Notification Apr 08, 2015 Quotation Submission Apr 23, 2015 Evaluation of Quotations Apr 30, 2015 Evaluation Report (ER) Submitted to WB (for Prior Review cases) & PMCA (all cases) May 02, 2015 NoL on ER from WB (for Prior Review cases) & PMCA (all cases) May 09, 2015 Contract/ P.O. Award May 10, 2015 Delivery Date Jun 10, 2015
SINDH IRRIGATION AND DRAINAGER AUTHORITY (SIDA)
WATER SECTOR IMPROVEMENT PROJECT PROCUREMENT PLAN (Services)
(Component E- WSIP Project Coordination and Monitoring Unit) (Services)
Procurement Activities
Activity 9
Computerization of Abiana System on selected canal (any one of Fulleli or Nara Canal)
Estimated Cost: Rs. 8.00 Million
Procurement Method:
CQS/Post Review
Procurement Process Planned Dates
Preparation of the Terms of Reference of the assignment. 11 Aug, 2015
Preparation of the cost estimate or budget of the assignment. 15 Aug, 2015
Public advertisement of Request for Expression of Interest. 22 Aug, 2015
Short-listing of consultant. 10 Sep, 2015
Evaluation & Selection of best qualified and experienced firm. 15 Sep, 2015
Combined technical & financial proposal from selected firm. 22 Sep, 2015
Technical & Financial negotiations with the selected firm. 25 Sep, 2015
Award and signing of the contract between the procuring agency and the consultant. 26 Sep, 2015
Completion of the assignment. 25 Jan, 2016
WATER SECTOR IMPROVEMENT PROJECT PROCUREMENT PLAN
(Component E- WSIP Project Coordination and Monitoring Unit) (Services)
Procurement Activities
Activity 02 Provincial Strategy for Irrigated Agriculture in Sindh
Estimated Cost: Rs. 10 Million
Procurement Method:
Single Source Selection/Prior review
Procurement Process Planned Dates
Preparation of the Terms of Reference (TORs) Aug 11, 2015
NoL by the Bank on the ToRs Oct 20, 2015
preparation of the cost estimate or budget of the assignment) Sep 20, 2015
Public advertisement date of the Request for Expression of Interest (if any); Nov 05, 2015
receiving the CVs from individual consultant(s); Nov 09, 2015
evaluation of the received CVs; Nov 18, 2015
Contract negotiation (if any); Dec 18, 2015
NoL from Bank for award of individual consultancy; Jan 01, 2016
Award and signing of the contract between the procuring agency and the individual consultant(s);
Jan 08, 2016
Award notification Jan 11, 2016
Completion of the assignment
Feb 16, 2016