Download - THE KENYA – UGANDA OIL PIPELINE PROJECT

Transcript
Page 1: THE KENYA – UGANDA OIL PIPELINE PROJECT

THE KENYA – UGANDA OIL PIPELINE PROJECT

byBen Twodo

MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA

Page 2: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

STRUCTURE1. Project Inception2. First Feasibility Study3. Complementary Study4. Highlights of the Report5. Ownership and Management6. Implementation7. Conclusion

Page 3: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

INCEPTION OF THE PROJECT

A Memorandum of Understanding (MOU) between Kenya and Uganda signed in May 1995

A Joint Coordination Commission (JCC) established

Page 4: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

INCEPTION cont’d …

The TOR of the JCC initially to coordinate the feasibility study for the pipeline extension.

TOR expanded in Oct 2000 to include implementation of the entire project.

Page 5: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

INCEPTION cont’d …

Agreed from start that the project be promoted and developed as a regional project.

Page 6: THE KENYA – UGANDA OIL PIPELINE PROJECT

THE FIRST FEASIBILITY STUDY

The European Investment Bank (EIB) financed the first feasibility study.

Page 7: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

FIRST STUDY cont’d …

An international consultancy firm contracted to undertake a feasibility study in 1997.

The consultant conducted the study in 1998 and presented its report in May 1999.

Page 8: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

FIRST STUDY cont’d …

The study concluded that the project is feasible and viable.

Page 9: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

THE SECOND/COMPLENTARY

STUDY

In 2001, a complementary study was commissioned to:oupdate the first study and reconfirm the pipeline as the least cost mode

oprepare documentation to invite bids from private sector investors

Page 10: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

COMPLEMENTARY STUDY cont’d …

Study financed by the two Governments under the auspices of the JCC.

Study carried out by another international firm.

Page 11: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

COMPLEMENTARY STUDY cont’d …

Report on Stage 1of the study submitted in Nov 2001.

Page 12: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

HIGHLIGHTS OF THE REPORT

Market demandoPresent demand is about 580,000 m3 p.a.

oDemand grows at 3.5% – 5% p.a

Page 13: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

HIGHLIGHTS cont’d …

Pipeline routeoPipeline to be extended from Eldoret in Kenya, through Malaba on the border (110 km), through Jinja (130 km from Malaba) then to Kampala (80 km)

Page 14: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

HIGHLIGHTS cont’d …

oTotal pipeline length approximately 320 km

Page 15: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

HIGHLIGHTS cont’d …

Pipeline sizeoAn 8 inch diameter pipeline recommended

Page 16: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

HIGHLIGHTS cont’d …

Pipeline capacityoPumping flow rate of 168 m3 per hour

oAnnual capacity is 1,200,000 m3

Page 17: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

HIGHLIGHTS cont’d …

No engineering design at this stage.

Page 18: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

KAMPALA TERMINAL

A common user terminal to be located in Kampala

Terminal to be located east of the city

Page 19: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

KAMPALA TERMINAL

Ministry prefers location west of the city to lessen truck traffic through city

Page 20: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

KAMPALA TERMINAL cont’d …

Kampala terminal capacity to be 72,000 m3 comprising:

o7 productso4 interface tanks

Page 21: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

KAMPALA TERMINAL cont’d …

Tanks Configuration o MPS - 2 tanks - 32,500 m3

o BIK - 2 tanks - 5,654 m3

o JET - 2 tanks - 10,544 m3

o AGO - 2 tanks - 22,570 m3

o Interface - 4 tanks 904 m3

Page 22: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

CAPITAL COST ESTIMATES

Cost estimates for basic development - $96.9 million

Page 23: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

CAPITAL COSTS cont’d …

oDesign, engineering, supervision - $7.2 m

oPreliminaries and general costs - $5.4 m

oPipe laying - $42.2 moEldoret terminal - $4.6 m

Page 24: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

CAPITAL COSTS cont’d …

oSindendet pump station - $3.4 m

o Intermediate pump station - $3.4 m

oKampala terminal cost - $30.7 m

Page 25: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

CAPITAL COSTS cont’d …Additional $12 million for:

o Improvement of pumping capacity at Burnt Forest in Kenya – $5.1 m

Page 26: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

CAPITAL COSTS cont’d …oT-off to government’s storage depot in Jinja; additional facilities - $2.1 m

oRe-locating terminal west of Kampala - $4.7 m

Page 27: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

ECONOMICS

Current truck transportation rates vary $38 - $42 per m3

Page 28: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

ECONOMICS

Viability of the project tested for various tariffs and investment configurations.

The IRR in all cases showed the project to be viable; 18% - 22%

Page 29: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

GOVERNMENTS POSITION

The complementary study report was accepted by JCC in 2001

The JCC recommended to the two Governments to implement the project.

Page 30: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

GOVERNMENTS POSITION cont’d …

Extension to be independent of existing Mombasa – Eldoret pipeline (owned and managed by GoK through the Kenya Pipeline Company).

Page 31: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

GOVERNMENTS’ POSITION cont’d …

A legal framework be developed immediately by the two governments:oBilateral/International agreements defining legal, commercial, financial arrangements.

Page 32: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

GOVERNMENTS’ POSITION cont’d …

oHost country laws on taxation, transportation, customs, etc.

oCommercial agreements – government/company or inter company.

Page 33: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

GOVERNMENTS’ POSITION cont’d …

Engineering design be undertaken parallel to identification of private sector investoroTOR for consultancy being drafted

Page 34: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

GOVERNMENTS’ POSITION cont’d …

Environment impact assessment study be carried out parallel to identification of private sector investor

oTOR being drafted

Page 35: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

OWNERSHIP AND MANAGEMENT

Ownership to be public-private partnership on boo terms

oPrivate investor51%oGovernments 49%

(24.5% each)

Page 36: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

OWNERSHIP & MANAGEMENT cont’d …

Private sector to manage and operate the pipeline

Page 37: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

OWNERSHIP/MANAGEMENT cont’d …

Governments’ shares to be offloaded to private investors in future

The two pipelines to be unified in future and operated as a single entity; Msa – Kla.

Page 38: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

PROJECT FINANCING

Project financing to be used based on future stream of revenues.

Oil marketing companies willing to sign agreements with promoters.

Page 39: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

WAY FORWARD

Prepare documentation to select private partner for the project

The selection will be through competitive process

Page 40: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

IMPLEMENTATION TIMETABLE

Prepare documentation for bidding - 2 months

Open invitation for bidding- 6 months

Evaluation, negotiations and contract signing - 6 months

Page 41: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

IMPLEMENTATION TIMETABLE

Legal framework - 3 monthsEngineering design - 4 monthsEIA - 4 months

These to run concurrent with investor selection

Page 42: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

IMPLEMENTATION TIMETABLE

Procure, Construction and Commissioning 27 – 32 months

Page 43: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

CONCLUSION

The Kenya – Uganda oil pipeline project is feasible and viable.

Ready market existsAttractive rates of return

assured.

Page 44: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

CONCLUSION

The project classified as high priority in both countries.

Page 45: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

CONCLUSION cont’d …

The project to be implemented as a regional project in the spirit of East African Community (EAC), the New Partnership for Africa (NEPAD), etc

Page 46: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

CONCLUSION cont’d …

Many financial institutions have indicated interest to support the projectoWorld Bank Group, EIB, AfDB, PTA Bank, EADB, etc.

oBilateral sources and finance houses, etc.

Page 47: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

CONCLUSION cont’d …

A number of investors have expressed interest in the project

Page 48: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

COME, LETS DO BUSINESS TOGETHER

THANK YOU!