THE KENYA – UGANDA OIL PIPELINE PROJECT

48
THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA

description

THE KENYA – UGANDA OIL PIPELINE PROJECT. by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA. STRUCTURE. Project Inception First Feasibility Study Complementary Study Highlights of the Report Ownership and Management Implementation Conclusion. INCEPTION OF THE PROJECT. - PowerPoint PPT Presentation

Transcript of THE KENYA – UGANDA OIL PIPELINE PROJECT

Page 1: THE KENYA – UGANDA OIL PIPELINE PROJECT

THE KENYA – UGANDA OIL PIPELINE PROJECT

byBen Twodo

MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA

Page 2: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

STRUCTURE1. Project Inception2. First Feasibility Study3. Complementary Study4. Highlights of the Report5. Ownership and Management6. Implementation7. Conclusion

Page 3: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

INCEPTION OF THE PROJECT

A Memorandum of Understanding (MOU) between Kenya and Uganda signed in May 1995

A Joint Coordination Commission (JCC) established

Page 4: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

INCEPTION cont’d …

The TOR of the JCC initially to coordinate the feasibility study for the pipeline extension.

TOR expanded in Oct 2000 to include implementation of the entire project.

Page 5: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

INCEPTION cont’d …

Agreed from start that the project be promoted and developed as a regional project.

Page 6: THE KENYA – UGANDA OIL PIPELINE PROJECT

THE FIRST FEASIBILITY STUDY

The European Investment Bank (EIB) financed the first feasibility study.

Page 7: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

FIRST STUDY cont’d …

An international consultancy firm contracted to undertake a feasibility study in 1997.

The consultant conducted the study in 1998 and presented its report in May 1999.

Page 8: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

FIRST STUDY cont’d …

The study concluded that the project is feasible and viable.

Page 9: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

THE SECOND/COMPLENTARY

STUDY

In 2001, a complementary study was commissioned to:oupdate the first study and reconfirm the pipeline as the least cost mode

oprepare documentation to invite bids from private sector investors

Page 10: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

COMPLEMENTARY STUDY cont’d …

Study financed by the two Governments under the auspices of the JCC.

Study carried out by another international firm.

Page 11: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

COMPLEMENTARY STUDY cont’d …

Report on Stage 1of the study submitted in Nov 2001.

Page 12: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

HIGHLIGHTS OF THE REPORT

Market demandoPresent demand is about 580,000 m3 p.a.

oDemand grows at 3.5% – 5% p.a

Page 13: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

HIGHLIGHTS cont’d …

Pipeline routeoPipeline to be extended from Eldoret in Kenya, through Malaba on the border (110 km), through Jinja (130 km from Malaba) then to Kampala (80 km)

Page 14: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

HIGHLIGHTS cont’d …

oTotal pipeline length approximately 320 km

Page 15: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

HIGHLIGHTS cont’d …

Pipeline sizeoAn 8 inch diameter pipeline recommended

Page 16: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

HIGHLIGHTS cont’d …

Pipeline capacityoPumping flow rate of 168 m3 per hour

oAnnual capacity is 1,200,000 m3

Page 17: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

HIGHLIGHTS cont’d …

No engineering design at this stage.

Page 18: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

KAMPALA TERMINAL

A common user terminal to be located in Kampala

Terminal to be located east of the city

Page 19: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

KAMPALA TERMINAL

Ministry prefers location west of the city to lessen truck traffic through city

Page 20: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

KAMPALA TERMINAL cont’d …

Kampala terminal capacity to be 72,000 m3 comprising:

o7 productso4 interface tanks

Page 21: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

KAMPALA TERMINAL cont’d …

Tanks Configuration o MPS - 2 tanks - 32,500 m3

o BIK - 2 tanks - 5,654 m3

o JET - 2 tanks - 10,544 m3

o AGO - 2 tanks - 22,570 m3

o Interface - 4 tanks 904 m3

Page 22: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

CAPITAL COST ESTIMATES

Cost estimates for basic development - $96.9 million

Page 23: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

CAPITAL COSTS cont’d …

oDesign, engineering, supervision - $7.2 m

oPreliminaries and general costs - $5.4 m

oPipe laying - $42.2 moEldoret terminal - $4.6 m

Page 24: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

CAPITAL COSTS cont’d …

oSindendet pump station - $3.4 m

o Intermediate pump station - $3.4 m

oKampala terminal cost - $30.7 m

Page 25: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

CAPITAL COSTS cont’d …Additional $12 million for:

o Improvement of pumping capacity at Burnt Forest in Kenya – $5.1 m

Page 26: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

CAPITAL COSTS cont’d …oT-off to government’s storage depot in Jinja; additional facilities - $2.1 m

oRe-locating terminal west of Kampala - $4.7 m

Page 27: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

ECONOMICS

Current truck transportation rates vary $38 - $42 per m3

Page 28: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

ECONOMICS

Viability of the project tested for various tariffs and investment configurations.

The IRR in all cases showed the project to be viable; 18% - 22%

Page 29: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

GOVERNMENTS POSITION

The complementary study report was accepted by JCC in 2001

The JCC recommended to the two Governments to implement the project.

Page 30: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

GOVERNMENTS POSITION cont’d …

Extension to be independent of existing Mombasa – Eldoret pipeline (owned and managed by GoK through the Kenya Pipeline Company).

Page 31: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

GOVERNMENTS’ POSITION cont’d …

A legal framework be developed immediately by the two governments:oBilateral/International agreements defining legal, commercial, financial arrangements.

Page 32: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

GOVERNMENTS’ POSITION cont’d …

oHost country laws on taxation, transportation, customs, etc.

oCommercial agreements – government/company or inter company.

Page 33: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

GOVERNMENTS’ POSITION cont’d …

Engineering design be undertaken parallel to identification of private sector investoroTOR for consultancy being drafted

Page 34: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

GOVERNMENTS’ POSITION cont’d …

Environment impact assessment study be carried out parallel to identification of private sector investor

oTOR being drafted

Page 35: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

OWNERSHIP AND MANAGEMENT

Ownership to be public-private partnership on boo terms

oPrivate investor51%oGovernments 49%

(24.5% each)

Page 36: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

OWNERSHIP & MANAGEMENT cont’d …

Private sector to manage and operate the pipeline

Page 37: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

OWNERSHIP/MANAGEMENT cont’d …

Governments’ shares to be offloaded to private investors in future

The two pipelines to be unified in future and operated as a single entity; Msa – Kla.

Page 38: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

PROJECT FINANCING

Project financing to be used based on future stream of revenues.

Oil marketing companies willing to sign agreements with promoters.

Page 39: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

WAY FORWARD

Prepare documentation to select private partner for the project

The selection will be through competitive process

Page 40: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

IMPLEMENTATION TIMETABLE

Prepare documentation for bidding - 2 months

Open invitation for bidding- 6 months

Evaluation, negotiations and contract signing - 6 months

Page 41: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

IMPLEMENTATION TIMETABLE

Legal framework - 3 monthsEngineering design - 4 monthsEIA - 4 months

These to run concurrent with investor selection

Page 42: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

IMPLEMENTATION TIMETABLE

Procure, Construction and Commissioning 27 – 32 months

Page 43: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

CONCLUSION

The Kenya – Uganda oil pipeline project is feasible and viable.

Ready market existsAttractive rates of return

assured.

Page 44: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

CONCLUSION

The project classified as high priority in both countries.

Page 45: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

CONCLUSION cont’d …

The project to be implemented as a regional project in the spirit of East African Community (EAC), the New Partnership for Africa (NEPAD), etc

Page 46: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

CONCLUSION cont’d …

Many financial institutions have indicated interest to support the projectoWorld Bank Group, EIB, AfDB, PTA Bank, EADB, etc.

oBilateral sources and finance houses, etc.

Page 47: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

CONCLUSION cont’d …

A number of investors have expressed interest in the project

Page 48: THE KENYA – UGANDA OIL PIPELINE PROJECT

Ministry of Energy and Mineral Development, UGANDA.

Kenya – Uganda Oil Pipeline Project

COME, LETS DO BUSINESS TOGETHER

THANK YOU!