Download - Pentridge Coburg - Building 15 (Jul-17) · Pentridge Coburg Building 15 development: Economic implications for total project i Executive summary • Shayher Properties Pty Ltd (Shayher)

Transcript
Page 1: Pentridge Coburg - Building 15 (Jul-17) · Pentridge Coburg Building 15 development: Economic implications for total project i Executive summary • Shayher Properties Pty Ltd (Shayher)

 

 

 

Pentridge Coburg 

Building  15 development:  Economic  implications  for total  project  

 

 

Ju ly  2017   

 

  

Page 2: Pentridge Coburg - Building 15 (Jul-17) · Pentridge Coburg Building 15 development: Economic implications for total project i Executive summary • Shayher Properties Pty Ltd (Shayher)

MacroPlan Dimasi 

 

MELBOURNE 

Level 16 

330 Collins Street 

Melbourne  VIC 3000 

(03) 9600 0500 

SYDNEY

Level 6 

39 Martin Place 

Sydney  NSW 2000 

(02) 9221 5211 

BRISBANE 

Level 15 

111 Eagle Street 

Brisbane  QLD 4000 

(07) 3221 8166 

GOLD COAST

Level 2 

89 – 91 Surf Parade 

Broadbeach  QLD 4218 

(07) 3221 8166 

ADELAIDE 

Ground Floor 

89 King William Street 

Adelaide  SA 5000 

(08) 8221 6332 

PERTH

Level 1 

89 St Georges Terrace 

Perth  WA 6000 

(08) 9225 7200 

 

 

 

 

 

 

 

Prepared for: Shayher Group 

 

 

MacroPlan Dimasi staff responsible for this report: 

Ellis Davies, Manager – Retail 

 

 

Page 3: Pentridge Coburg - Building 15 (Jul-17) · Pentridge Coburg Building 15 development: Economic implications for total project i Executive summary • Shayher Properties Pty Ltd (Shayher)

 

 

Table of contents

 

Executive summary  i 

Introduction  iv 

Section 1:  Site ownership history and approval process  1 

Section 2:  Approved Masterplan  2 

2.1  Masterplan Vision and key elements  2 

2.2  Heritage and public realm considerations  7 

Section 3:  Overview of Building 15  14 

Section 4:  Economic feasibility of Masterplan  18 

4.1  Development components of Masterplan  18 

4.2  Financial/economic feasibility of Masterplan  20 

4.3  Significance of Building 15  24 

4.4  Net community benefit  25 

Appendix 1  28 

 

 

 

Page 4: Pentridge Coburg - Building 15 (Jul-17) · Pentridge Coburg Building 15 development: Economic implications for total project i Executive summary • Shayher Properties Pty Ltd (Shayher)

 

Pentridge Coburg Building 15 development: Economic implications for total project 

i

Executive summary 

• Shayher  Properties  Pty  Ltd  (Shayher)  has  submitted  a  permit  application  to 

Heritage Victoria for the development of the proposed Building 15 and the restoration of 

the  southern  part  of  the  Administration  building  in  the  south‐western  part  of  the 

Pentridge Coburg site. This  independent report provides an assessment of the economic 

implications if the permit application is refused. 

• Preserving the heritage value of the former Pentridge Prison  is of great  importance, and 

provides the overarching identity for Pentridge Coburg. The approved Masterplan details 

the  overall  planning/urban  design  principles  for  redevelopment  of  the  Pentridge  site, 

which include: 

‘Achieving  a  density  of  development  that  is  sustainable  having  regard  to 

physical, social and economic considerations,  including ensuring the  long term 

retention of important heritage assets.’ 

• The preservation of its heritage value and the public realm objectives for the site go hand 

in  hand  with  the  joint  objectives  of  creating  a  vibrant  and  sustainable  urban  hub, 

facilitating a major urban renewal project, and enabling the community at  large to both 

appreciate and respect the heritage value of the site. 

• One of  the  significant opportunity costs of  the  site  remaining undeveloped, and having 

been undeveloped for more than a decade, is the fact that the community at large is not 

able to enjoy these benefits. While this opportunity cost is not a direct economic cost for 

Shayher  per  se,  it  should  nonetheless  be  regarded  as  an  additional  factor  which  is 

impeding  the  reasonable  or  economic use of  the  Pentridge  site,  i.e.  any unreasonable 

delay  in  the  development  of  the  site,  in  line with  community  expectations  as  already 

expressed  in  the approved Masterplan,  is  imposing  further economic costs, and making 

the viability of the adaptive re‐use of the site more difficult to achieve. 

 

Page 5: Pentridge Coburg - Building 15 (Jul-17) · Pentridge Coburg Building 15 development: Economic implications for total project i Executive summary • Shayher Properties Pty Ltd (Shayher)

Executive summary 

Pentridge Coburg Building 15 development: Economic implications for total project 

ii

• The analysis outlined in this report demonstrates that restricting or significantly delaying 

the development of Building 15 and the restoration and reuse of the southern part of the 

Administration  heritage  building  will  pose  risks  to  the  economic  feasibility  of  the 

Masterplan. Because of the constraints of the site, not  least those  imposed by the need 

and  desire  to  protect  its  heritage  value,   

 

 and  if this permit application  is refused  it would clearly affect the reasonable 

or economic use of the registered place. 

• This  conclusion  is  supportable  by  a  number  of  key  reasons which  are  set  out  in  this 

report, in particular the following: 

-  

 

 

-  

- The  development  requires  significant  investment, much  of  it  already  expended  by 

Shayher,  relating  specifically  to  the  heritage  value  of  the  site  and  public  realm 

requirements, many of those in turn also associated with the heritage value. 

-  

 

 

- The restoration of the Administration building, together with Building 15, will provide 

an  important  feature  at  the  main  pedestrian  entrance  to  Pentridge  Coburg  from 

Champ  Street.  The  development  is  expected  to  generate  an  estimated  of 

revenue each year over the life of the project,  . 

   

Page 6: Pentridge Coburg - Building 15 (Jul-17) · Pentridge Coburg Building 15 development: Economic implications for total project i Executive summary • Shayher Properties Pty Ltd (Shayher)

Executive summary 

Pentridge Coburg Building 15 development: Economic implications for total project 

iii

• In addition though, it should not be ignored that such refusal can also result in significant 

net community disbenefit, for a number of reasons. The site has sat undeveloped for well 

over a decade, and  thus  its heritage value, as well as  its broader potential  to deliver a 

major urban renewal project, remains untapped. More directly, there will be community 

disbenefits suffered as a result of employment opportunities foregone  in the event that 

the approved Masterplan is unable to be implemented, or is significantly delayed. 

• Overall,  the  project  is  estimated  to  create  almost  8,000  jobs,  of which  approximately 

3,600  will  constitute  direct  employment  on  the  site,  with  4,270  jobs  attributable  to 

multiplier induced indirect employment. Therefore, there will be a very large community 

disbenefit,  in  the  form  of  such  employment  opportunities  foregone,  if  the  approved 

Masterplan is unnecessarily delayed or, worse, is unable to be implemented. 

 

 

Page 7: Pentridge Coburg - Building 15 (Jul-17) · Pentridge Coburg Building 15 development: Economic implications for total project i Executive summary • Shayher Properties Pty Ltd (Shayher)

 

Pentridge Coburg Building 15 development: Economic implications for total project 

iv

Introduction 

Shayher Properties Pty Ltd (Shayher) has submitted a permit application to Heritage Victoria 

for  works  in  relation  to  Building  15  and  the  restoration  of  the  southern  part  of  the 

Administration building, which are located in the south‐western part of the Pentridge Coburg 

site. 

 

This  independent  report provides an assessment of  the extent  to which  the application,  if 

refused, would adversely affect the reasonable or economic use of the Pentridge site which 

is  owned  by  Shayher  and  for which  an  approved  development Masterplan  is  in  place.  In 

particular,  it  provides  information  in  accordance  with  s.73(2)  of  the  Heritage  Act  1995, 

namely,  in  relation  to  s.73(1)(b) of  the Heritage Act 1995,  consideration of  ‘the extent  to 

which  the  application,  if  refused,  would  affect  the  reasonable  or  economic  use  of  the 

registered place….’ 

 

The report is presented in four sections as follows: 

 

• Section 1 provides an overview of the recent history of the site, since it was first acquired 

for  development  in  1999,  as well  as  discussing  the  approval  process  for  the  proposed 

development. 

• Section 2 details the latest Masterplan for the site which was prepared in February 2014 

and approved in July 2014 as part of Amendment C154 to the Moreland Planning Scheme. 

• Section 3 provides an overview of the plans for Building 15 and the southern part of the 

heritage Administration building. 

• Section 4 outlines  the economic  feasibility of  the Masterplan, and sets out  the  reasons 

why the subject permit application, if refused, would significantly affect the reasonable or 

economic use of  the  subject  site, as well as drawing  conclusions as  to  the  consequent 

implications of such refusal. 

Page 8: Pentridge Coburg - Building 15 (Jul-17) · Pentridge Coburg Building 15 development: Economic implications for total project i Executive summary • Shayher Properties Pty Ltd (Shayher)

 

Pentridge Coburg Building 15 development: Economic implications for total project 

1

Section 1:  Site  ownership  history  and  approval process 

Pentridge Prison operated from 1851 to May 1997, when it was officially closed. In 1999 the 

Victorian  State  Government  sold  the  former  jail  and  around  30  hectares  of  adjacent 

Crown Land to two developers – Pentridge Piazza (Crema) and Pentridge Village – with the 

site planned to be developed for residential and mixed‐use accommodation.  

 

Due to a number of reasons, development of the site was delayed, such as in 2002 when an 

impasse between  the  local Council  and developers over heritage protection  saw planning 

work  for  the site cease  for a period of  time. The only developments on  the northern  land 

parcel of Pentridge completed by Pentridge Piazza were the QM building and Industry Lane.  

 

Valad Property Group (Valad) purchased 6.7 hectare of land in the northern part of the site 

from  Pentridge  Piazza  in  June  2007, which  covered  the majority  of  the  decommissioned 

prison.  Valad  prepared  a Masterplan  for  the  site, which was  endorsed  by Moreland City 

Council  in  August  2009  and  given  formal  approval  in  December  2009  with  the 

C125 Amendment  to  the  Moreland  Planning  Scheme.  However,  for  various  reasons, 

including the onset of the Global Financial Crisis (GFC), Valad did not proceed. 

 

Shayher Group acquired the northern 6.7 hectare site from Valad in May 2013 and prepared 

an amendment to the Masterplan. This amendment was approved by the Victorian Minister 

for Planning in February 2014 and is reflected in the Pentridge Coburg Design Guidelines and 

Masterplan as it currently stands. The 2014 Masterplan sets the framework for the ongoing 

development  of  the  Pentridge  site  over  the  next  decade.  It  supersedes  the  previous 

Masterplan for the site, and now forms part of the Moreland Planning Scheme through the 

incorporation of Planning Scheme Amendment C154 in July 2014. 

 

Page 9: Pentridge Coburg - Building 15 (Jul-17) · Pentridge Coburg Building 15 development: Economic implications for total project i Executive summary • Shayher Properties Pty Ltd (Shayher)

 

Pentridge Coburg Building 15 development: Economic implications for total project 

2

Section 2:  Approved Masterplan 

The Pentridge Coburg Design Guidelines and Masterplan (the Masterplan) of February 2014 

was  incorporated  into  the Moreland Planning Scheme  in  July 2014 under Planning Scheme 

Amendment C154. The Masterplan sets the framework for the development of the Pentridge 

Coburg  site. The  subject  site  covers an area of 6.7 hectares,  located  in  the north‐western 

part of the former Coburg Prison Complex, generally to the north of Pentridge Boulevard and 

west of Stockade Avenue. 

 

2.1  Masterplan Vision and key elements 

The Masterplan outlines  the plan  to develop  the site  into a vibrant and sustainable mix of 

residential,  retail,  commercial,  entertainment  and  leisure/tourism  uses. On  page  2  of  the 

Masterplan the vision for the Pentridge site is stated:  

“The Masterplan is seeking to create a vibrant and sustainable urban hub, a place 

for the shared use of  its residents and workers, the neighbouring community and 

tourists.  To  ensure  the  ongoing  success  of  Pentridge  and  its  broad  convenience 

function, a diverse range of commercial and community uses are anticipated. The 

renewed  life within the prison will be expressed through the careful placement of 

contemporary  architecture  adjacent  to  historically  significant  Pentonville  prison 

model buildings. These old and new elements will  combine  to  facilitate a major 

urban renewal project that will complement other development contemplated by 

the Central Coburg 2020 Structure Plan.  

The public realm will be enlivened through the active  integration of the proposed 

uses, within both new buildings and restored heritage prison buildings. The range 

of activities  expected  in  and adjacent  to  the  public  realm,  both permanent and 

temporary, will generate one of Melbourne’s memorable urban experiences.” 

 A number of heritage listed buildings are located throughout the subject site, with the main 

heritage buildings including the Division B and B Annexe buildings (which is to be integrated 

with Building 16), Division A (located in the northern part of the site), Division E (central), the 

former Wardens Residence (Building 14) and the Administration building in the western part 

of Pentridge Coburg (refer Figure 2.1).   

Page 10: Pentridge Coburg - Building 15 (Jul-17) · Pentridge Coburg Building 15 development: Economic implications for total project i Executive summary • Shayher Properties Pty Ltd (Shayher)

Section 2: Approved Masterplan 

Pentridge Coburg Building 15 development: Economic implications for total project 

3

 

  

   

Figure 2.1 

Page 11: Pentridge Coburg - Building 15 (Jul-17) · Pentridge Coburg Building 15 development: Economic implications for total project i Executive summary • Shayher Properties Pty Ltd (Shayher)

Section 2: Approved Masterplan 

Pentridge Coburg Building 15 development: Economic implications for total project 

4

One  of  the major  land  uses  under  the  approved Masterplan will  be  residential, with  the 

project to provide some 1,300 dwellings in a number of medium and high density buildings, 

housing a projected population of around 3,000. A majority of the residential housing will be 

provided  in  the northern part of  the  site  in  the Coburg  Lake precinct  along Murray Road 

(Buildings 3 – 8) and in the southern Sentinel precinct. The project is planned to deliver high 

quality homes for the community, and will provide a range of housing choices such as 1, 2, 

and  3 bedroom  apartments,  terrace  homes  and  home‐offices.  Pentridge  Coburg will  also 

seek partners  to deliver affordable housing options, and will  target various groups such as 

first‐time buyers, low income workers and older residents. 

 

A  large  piazza  will  be  at  the  heart  of  the  project,  located  between  the  Division  B  and 

Division E heritage buildings, within the Piazza precinct of the development. The Piazza will 

be  the primary public open  space of Pentridge Coburg and  is designed  to be an engaging 

place and a meeting point  for  the community.  It  is planned  to host a  range of community 

events and functions. Retail and associated uses will surround the Piazza and will be critical 

in ensuring the piazza can be activated and be a vibrant place to visit. A large component to 

be provided  in  the multi‐level Building 9, and a  total of  some 12,000 – 14,000 sq.m  retail 

floorspace to be provided throughout the site. 

 

The retail facilities to be provided within Pentridge Coburg will be distinctive, and will be a 

critical  element  of  the  iconic,  historic  and  heritage  listed  site.  The  retail  component will 

include a range of food and drink premises, while a supermarket, non‐food specialities and 

non‐retail  shopfront  specialties  are  also  likely  to  be  provided  to  serve  local workers  and 

residents, as well as visitors to the site. A childcare centre, a medical centre and community 

services may also be provided within the Piazza precinct of the development. 

 

Between  15,000  –  20,000  sq.m  of  commercial  floorspace  is  also  planned  to  be  provided 

under the Masterplan. The majority of the commercial floorspace will be located within the 

central Mixed Use precinct, which fronts Champ Street and  includes the heritage Division A 

building.   

Page 12: Pentridge Coburg - Building 15 (Jul-17) · Pentridge Coburg Building 15 development: Economic implications for total project i Executive summary • Shayher Properties Pty Ltd (Shayher)

Section 2: Approved Masterplan 

Pentridge Coburg Building 15 development: Economic implications for total project 

5

The buildings to be developed at Pentridge Coburg, as detailed  in the Masterplan, range  in 

height.  Figure  2.2  outlines  the Masterplan  Building  Envelope,  which  details  the  planned 

building footprints and heights across the site (page 26 of the Masterplan). As set out in the 

Masterplan, Building  15, which  is  the  subject of  this  report,  is  to be  2  levels  and  located 

adjacent to the Administration building. 

 

The overall land use vision for the site is summarised on page 40 of the Masterplan. It details 

the importance of rejuvenating the former prison complex and creating a sense of place for 

residents,  workers  and  other  visitors.  The  plan  is  for  a  vibrant, mixed‐use  environment 

providing a diverse range of uses which are well integrated. The piazza will form the central 

community  meeting  place,  which  will  be  surrounded  by  a  range  of  functions  including 

residential, retail, a hotel, offices, as well as tourism, leisure and community facilities. All the 

facilities,  though  particularly  retail, will  contribute  to  the  life  and  activation  of  the  public 

realm throughout Pentridge Coburg.  

 

The retail, hotel and commercial facilities will also provide on‐site  job opportunities for the 

local community and will provide a substantial daytime population at the site, creating the 

much needed activation. 

 

Page 13: Pentridge Coburg - Building 15 (Jul-17) · Pentridge Coburg Building 15 development: Economic implications for total project i Executive summary • Shayher Properties Pty Ltd (Shayher)

Section 2: Approved Masterplan 

Pentridge Coburg Building 15 development: Economic implications for total project 

6

Figure 2.2

Page 14: Pentridge Coburg - Building 15 (Jul-17) · Pentridge Coburg Building 15 development: Economic implications for total project i Executive summary • Shayher Properties Pty Ltd (Shayher)

Section 2: Approved Masterplan 

Pentridge Coburg Building 15 development: Economic implications for total project 

7

2.2  Heritage and public realm considerations 

The Pentridge Prison site  is  listed as a place of State significance on  the Victorian Heritage 

Register  (H1551).  In  accordance  with  these  heritage  listings  the  key  heritage  buildings 

throughout the site will be retained and maintained, together with the perimeter bluestone 

walls. Through adaptive re‐use, the heritage buildings are planned to accommodate a mix of 

retail, office and community uses, while the historic significance of the site will be preserved. 

Figure 2.3, which  is a  replication of  Figure 4.1a on page 21 of  the Masterplan,  shows  the 

primary heritage elements within the Pentridge Coburg site, including the bluestone walls.  

    

Figure 2.3 

Page 15: Pentridge Coburg - Building 15 (Jul-17) · Pentridge Coburg Building 15 development: Economic implications for total project i Executive summary • Shayher Properties Pty Ltd (Shayher)

Section 2: Approved Masterplan 

Pentridge Coburg Building 15 development: Economic implications for total project 

8

Preserving  the  heritage  value  of  the  former  Pentridge  Prison  is  of  great  importance,  and 

provides the overarching  identity for Pentridge Coburg. Section 4.1 Heritage and Built Form 

of the Masterplan details the overall planning/urban design principles for redevelopment of 

the Pentridge site, which include: 

 “Achieving a density of development that is sustainable having regard to physical, 

social and economic considerations, including ensuring the long term retention of 

important heritage assets.” 

 

The preservation of its heritage value and the public realm objectives for the site go hand in 

hand, with the joint objectives of creating a vibrant and sustainable urban hub, facilitating a 

major urban renewal project, and enabling the community at  large to both appreciate and 

respect the heritage value of the site. 

 

One of the significant opportunity costs of the site remaining undeveloped, and having been 

undeveloped for more than a decade,  is the fact that the community at  large  is not able to 

enjoy these benefits. While this opportunity cost  is not a direct economic cost  for Shayher 

per  se,  it  should  nonetheless  be  regarded  as  an  additional  factor which  is  impeding  the 

reasonable  or  economic  use  of  the  Pentridge  site,  i.e.  any  unreasonable  delay  in  the 

development of  the  site,  in  line with  community expectations as already expressed  in  the 

approved Masterplan,  is  imposing  further economic  costs, and making  the  viability of  the 

adaptive re‐use of the site more difficult to achieve. 

 

Some of the key urban design principles include: 

 - maintaining the significance of the recognised heritage elements of the site; 

- creating a high quality civic urban space; 

- creating opportunities for the viable re‐use of the heritage buildings; and 

- creating a functional, high quality built form and public realm. 

   

Page 16: Pentridge Coburg - Building 15 (Jul-17) · Pentridge Coburg Building 15 development: Economic implications for total project i Executive summary • Shayher Properties Pty Ltd (Shayher)

Section 2: Approved Masterplan 

Pentridge Coburg Building 15 development: Economic implications for total project 

9

The  Central  Coburg  2020  Structure  Plan  outlines  a  vision  for  sustainable  development  in 

Coburg.  Section  3.1.6  Sustainability Analysis  of  the Masterplan  details  the  environmental, 

economic and social sustainability nature of the proposed development, and the opportunity 

to create a neighbourhood that: 

 

• Encourages social interaction and improves social cohesion; 

• Is based around an interconnected street network that reduces dependence on 

cars, improves connection and viability of public transport, and specifically aims 

to attract a high level of use by pedestrians and cyclists by creating safe and vital 

spaces; 

• Provides on‐site employment opportunities through a combination of uses; 

• Builds upon the heritage assets to generate a sense of place through design; and 

• Creates a safe and secure public realm by creating streets and footpaths that are 

well used and under constant neighbourhood surveillance. 

A  key  component  of  the  development  to  ensure  that  it  is  environmentally  and  socially 

sustainable  is  the  inclusion  of  a  significant  amount  of  public  realm  and  open  space.  The 

Masterplan details that the public realm should complement the existing heritage buildings; 

link  a  network  of  open  spaces;  be  inviting  and  easily  navigated  to  encourage  visitors  to 

explore the spaces; and be attractive and comfortable with high levels of amenity. 

 

Figure 2.4, which  is  a  replication of  Figure 4.5a  at Page 51 of  the Masterplan,  shows  the 

extensive  areas  of open  space  to  be  provided  in  the  development. As  highlighted  in  red, 

there is planned to be 16,889 sq.m of primary public open space within the site, more than 

one‐quarter  of  the  6.7  hectare  site.  The  primary  public  open  space will  be  open  to  the 

broader community, and will  include areas for passive recreation.  It will  include the piazza, 

two  local parks  adjacent  to  the Division A building  and other public  areas.  The  areas will 

include public seating, picnic tables, and lawn areas, and landscaping will be integrated into 

these spaces. 

 

   

Page 17: Pentridge Coburg - Building 15 (Jul-17) · Pentridge Coburg Building 15 development: Economic implications for total project i Executive summary • Shayher Properties Pty Ltd (Shayher)

Section 2: Approved Masterplan 

Pentridge Coburg Building 15 development: Economic implications for total project 

10

 

 

   

Figure 2.4

Page 18: Pentridge Coburg - Building 15 (Jul-17) · Pentridge Coburg Building 15 development: Economic implications for total project i Executive summary • Shayher Properties Pty Ltd (Shayher)

Section 2: Approved Masterplan 

Pentridge Coburg Building 15 development: Economic implications for total project 

11

A  further  3,989  sq.m  of  secondary  public  open  space  is  contemplated  within  the  site, 

highlighted  orange  in  Figure  2.4.  The  secondary  public  open  space  includes  the  future 

laneways between buildings and other areas surrounding some buildings. In total, therefore, 

approximately one‐third of the total site will be devoted to open space. 

 

Shayher Group has invested considerably in the restoration of the heritage buildings and the 

public realm throughout the Pentridge Coburg site. Since acquiring the site  in May 2013 to 

June  2016,  Shayher  Group  spent  a  total  of    on  public  realm  and  heritage 

maintenance. A  further    is budgeted  to be  spent on public  realm and heritage 

maintenance  as  the  project  is  delivered,  taking  the  total  to    at  completion.  In 

addition, approximately   will be spent on restoring the exterior and interior of the 

heritage buildings located throughout the site in order for them to be opened to the public 

and  accommodate  commercial  and  community  uses.  This  takes  the  total  investment  in 

public realm, heritage maintenance and heritage restoration to some  . 

 

Figures 2.5 and 2.6 are artist’s impressions showing the overall vision for the development at 

Pentridge Coburg, described as follows: 

 

• Figure 2.5 shows the future piazza together with the heritage Division E building (central) 

and the heritage Administration building on the left; and 

• Figure  2.6  is  a  point  of  view  between  the  future  retail  buildings  12  and  9  toward  the 

south, showing Division E building on the right and Division B building in the distance. 

 

 

Page 19: Pentridge Coburg - Building 15 (Jul-17) · Pentridge Coburg Building 15 development: Economic implications for total project i Executive summary • Shayher Properties Pty Ltd (Shayher)

Section 2: Approved Masterplan 

Pentridge Coburg Building 15 development: Economic implications for total project 

12

 

 

Figure 2.5

Page 20: Pentridge Coburg - Building 15 (Jul-17) · Pentridge Coburg Building 15 development: Economic implications for total project i Executive summary • Shayher Properties Pty Ltd (Shayher)

Section 2: Approved Masterplan 

Pentridge Coburg Building 15 development: Economic implications for total project 

13

 

Figure 2.6

Page 21: Pentridge Coburg - Building 15 (Jul-17) · Pentridge Coburg Building 15 development: Economic implications for total project i Executive summary • Shayher Properties Pty Ltd (Shayher)

 

Pentridge Coburg Building 15 development: Economic implications for total project 

14

Section 3:  Overview of Building 15 

Building 15  is proposed  to be developed near  the main  entrance  to Pentridge Coburg on 

Champ Street, in the south‐western part of the site. The building will be integrated with the 

southern part of  the heritage Administration building, ensuring  that  the historic building  is 

activated  and open  to  the public. Building 15 will be  surrounded by  a number of historic 

bluestone walls, which will be restored as part of the development. 

 

Building  15,  together  with  the  Administration  building,  will  provide  a  high  quality  and 

engaging  entrance  point  to  the  Pentridge  Coburg  development.  The  main  pedestrian 

entrance to Pentridge Coburg  is  located on Champ Street, and visitors to the complex need 

to walk through the Administration building to access the site from Champ Street. The new 

Building 15 will occupy a strategic site at this entrance.  

 

Building  15 will  front  a  courtyard  to  its  north, while  a  key  pedestrian  thoroughfare  runs 

between the subject site and the courtyard. The main piazza of Pentridge Coburg, which will 

form a key meeting/focal point  in  the overall development,  is  located  immediately  to  the 

east  of  the  site  for  Building  15.  The  piazza  will  provide  the main  public  open  space  at 

Pentridge  Coburg,  and  is  to  be  surrounded  by  retail  uses  to  ensure  it  is  a  vibrant  and 

engaging place for the local community.  

 

The  restoration and  reuse of  the southern part of  the historic Administration building also 

forms part of the Building 15 development. It is important to find appropriate uses to active 

the  existing  heritage  building  throughout  Pentridge  Coburg,  to  ensure  that  they  can  be 

accessed by the public and their historic context appreciated.       

 

Building  15  and  the  southern  part  of  the  Administration  Building  is  planned  to  include 

around 613 sq.m of gross leasable floorspace. Zero 95 Wood Fire Pizza is to be the tenant of 

the building, and will provide residents of Pentridge Coburg and other visitors with a popular 

restaurant and meeting place. An attractive and lively entrance is considered critical for the 

project,  to  ensure  that  local  residents,  visitors  and  tourists  are  attracted  into  Pentridge 

Page 22: Pentridge Coburg - Building 15 (Jul-17) · Pentridge Coburg Building 15 development: Economic implications for total project i Executive summary • Shayher Properties Pty Ltd (Shayher)

Section 3: Overview of Building 16 

Pentridge Coburg Building 15 development: Economic implications for total project 

15

Coburg.  A  wood  fire  pizza  outlet  at  Building  15  will  provide  an  important  anchor  for 

Pentridge Coburg and will clearly mark the entrance to the site.   

 

The  following  images provide an artist’s  impression  for Building 15, prepared by PRO‐ARK 

Architects, and described as follows: 

 • Figure 3.1  illustrates the vision for the northern front of Building 15 (i.e.  looking south). 

The  Administration  building  and  the  key  pedestrian  entrance  to  Pentridge  Coburg  is 

located to the right of Building 15 in the image; and 

• Figure  3.2  provides  an  indicative  view  from  the  west,  looking  towards  the  internal 

bluestone wall.   

The images illustrate the indicative plan and impression for Building 15, and how the building 

will fit within the historic context of the overall development of Pentridge Coburg. 

 

 

Page 23: Pentridge Coburg - Building 15 (Jul-17) · Pentridge Coburg Building 15 development: Economic implications for total project i Executive summary • Shayher Properties Pty Ltd (Shayher)

 

 

 

 

Figure 3.1 

Page 24: Pentridge Coburg - Building 15 (Jul-17) · Pentridge Coburg Building 15 development: Economic implications for total project i Executive summary • Shayher Properties Pty Ltd (Shayher)

 

 

 

 

Figure 3.2 

Page 25: Pentridge Coburg - Building 15 (Jul-17) · Pentridge Coburg Building 15 development: Economic implications for total project i Executive summary • Shayher Properties Pty Ltd (Shayher)

 

Pentridge Coburg Building 15 development: Economic implications for total project 

18

Section 4:  Economic feasibility of Masterplan 

The  final  section  of  this  report  commences with  an  analysis  of  the  various  development 

components  of  the  approved  Masterplan  before  setting  out  the  financial/economic 

feasibility of the Masterplan and then considering the economic implications if the permit for 

Building 15 and the restoration and reuse of the Administration building is refused. 

 

4.1  Development components of Masterplan 

Table 4.1 below sets out the income generating components of the Masterplan, comprising: 

 •  of  retail  floorspace  (GLA),  to be distributed across  the  six  retail 

buildings.    is planned within Building  15  (which  is  the  subject of  this  report), 

while the majority is to be provided in Building 9. A further   of retail floorspace 

to be provided within the mixed‐use Building 12. 

• A total of some  apartments provided across nine residential buildings (AIR and B1‐

B8), with a further   apartments provided in the mixed‐use buildings 12, 13 and 16. 

• A  range  of  residential,  retail  and  commercial  uses,  as  well  as  a  hotel,  to  be 

accommodated within  the mixed‐use  buildings  12,  13  and  16.  Building  16 will  be  the 

largest mixed‐use building, and together with the restoration and reuse of the Division B 

and B Annexe buildings, is to deliver a 114 room hotel and 52 residential apartments. 

• A  total of   of “Heritage”  floorspace, which  is  to be provided  in  the  range of 

heritage  buildings  located  throughout  the  site  including  the  Administration  building 

(which  is the subject of  this report), Division A, Division B, B Annexe, Division E and  the 

former Wardens Residence (Building 14). The adaptive re‐use of these buildings will pose 

considerable challenges and the final uses of some of the buildings are still to be finalised, 

though are expected to include commercial, hospitality and retail uses.  

 

 

Page 26: Pentridge Coburg - Building 15 (Jul-17) · Pentridge Coburg Building 15 development: Economic implications for total project i Executive summary • Shayher Properties Pty Ltd (Shayher)

Section 4: Economic feasibility of Masterplan 

Pentridge Coburg Building 15 development: Economic implications for total project 

19

  Residential Gross leasable Net leasable % of usage % of total

Building Usage units (approx.) area (sq.m) area (sq.m) NLA NLA

Retail buildings

B15 Retail

B9 Retail

B11 Retail

B14 Retail

B17 Retail

B18 Retail

Total retail buildings

Residential buildings

AIR Residential 190

B1 Residential

B2 Residential

B3 & 4 Residential

B5 Residential

B6 Residential

B7 Residential 53

B8 Residential

Total residential buildings

Mixed-use buildings

Total B12

• B12 Residential

• B12 Commercial

• B12 Retail

Total B13

• B13 Residential

• B13 Commercial

Total B16

• B16 Hotel (114 rooms)

• B16 Residential

Total mixed-use buildings

Heritage buildings

Div. A Heritage

Div. E Heritage

Div. B Heritage

B Annex Heritage

Admin Heritage

Total heritage buildings

Total

Source: Shayher Group; MacroPlan Dimasi

Table 4.1

Pentridge Coburg - Planned usages and indicative floorspace

Page 27: Pentridge Coburg - Building 15 (Jul-17) · Pentridge Coburg Building 15 development: Economic implications for total project i Executive summary • Shayher Properties Pty Ltd (Shayher)

Section 4: Economic feasibility of Masterplan 

Pentridge Coburg Building 15 development: Economic implications for total project 

20

4.2  Financial/economic feasibility of Masterplan 

MacroPlan Dimasi has modelled the feasibility of the approved Masterplan, having regard to 

all  available  information,  and  utilising  estimates  of  costs  for  each  component  of  the 

Masterplan provided by Shayher Properties Pty Ltd. 

 

The key  information and estimates/assumptions utilised  for  the purposes of  this  feasibility 

assessment are set out below: 

 

1. Expenditure to date 

In the  first three  financial years to  June 2016, Shayher spent a  total of  on 

the project, comprising the following elements: 

• Site acquisition    

• Acquisition costs   

• Finance costs   

• Holding costs   

• Heritage & public realm maintenance   

• Other costs   

Total costs   

Therefore, Shayher has already  invested a significant amount on the Pentridge site, and 

has borne these costs over a period of more than three years, having acquired the site in 

May 2013. This  is a significant cost burden which Shayher has carried  to date, as  it has 

worked within the parameters of the approved Masterplan to develop the site  in a way 

that  is  both  acceptable  to  approval  authorities  and  the  community  at  large  and 

economically/financially feasible to a reasonable developer/investor. 

   

Page 28: Pentridge Coburg - Building 15 (Jul-17) · Pentridge Coburg Building 15 development: Economic implications for total project i Executive summary • Shayher Properties Pty Ltd (Shayher)

Section 4: Economic feasibility of Masterplan 

Pentridge Coburg Building 15 development: Economic implications for total project 

21

2. Development costs 

Detailed development  costs have been made available by Shayher  for each element of 

the  Masterplan.  These  estimates  show  a  total  eventual  development  costs  of 

 including the   spent to mid 2016. The key elements of this total 

development cost (in constant 2015/16 dollars) are the following: 

• Building costs of   for the development of Building 15 and the restoration 

and reuse of the southern part of the Administration building (subject site); 

• Total costs of   for the development of the Air Apartments building; 

• Total costs of   for the B7 (Horizon) residential building; 

• A total project cost of  for Building 16, with a further   for the 

Division B, B Annexe heritage buildings;  

• Combined costs of   for the other heritage buildings – Division A, Division E, 

and Administration (northern part); 

• A cost of   for the B9 Retail building, and a further  for the other 

retail buildings; 

• Total costs of   for the B12 and B13 mixed‐use buildings; 

• Costs of   for the B1 and B2 residential buildings; 

•  for the apartments to be delivered in the B3 and B4 buildings; and 

• Combined costs of   for the B5, B6 and B8 residential buildings; 

3. Period of development 

We have  adopted  a  14  year  timeframe  for delivery of  the Masterplan  from  2013. We 

consider  this  is  a  reasonable,  although  arguably optimistic,  timeframe within which  all 

elements of the Masterplan are likely to be completed, having regard to the complexities 

of the development as well as likely market conditions. 

 

Page 29: Pentridge Coburg - Building 15 (Jul-17) · Pentridge Coburg Building 15 development: Economic implications for total project i Executive summary • Shayher Properties Pty Ltd (Shayher)

Section 4: Economic feasibility of Masterplan 

Pentridge Coburg Building 15 development: Economic implications for total project 

22

4. Estimated revenues 

Revenues  have  been  estimated  by  MacroPlan  Dimasi  for  each  component  of  the 

Masterplan, having regard to current and expected market conditions, and to the quality 

and location of the total project. The key elements of the estimated revenue streams are 

the following: 

• Year 1 revenue of   for the sale of the residential apartments; 

• Year 1 revenue of   for the proposed retail floorspace; 

• Year 1  revenue of    for  the  future  leasing of  the  refurbished heritage 

buildings;  

•  per room in the first year for the hotel (Building 16), increasing to   for 

year 2 and   for year 3; and 

• Year 1 revenue of   for the future office floorspace. 

Allowances have also been made for escalation  in future revenues at the annual rate of 

for the apartment revenues and   for the retail floorspace and the other uses on the 

site. 

5. Other assumptions regarding revenue 

Other key assumptions made regarding the generation of revenue for the project are as 

follows: 

• Each apartment building  is assumed  to be  sold out  in  full within a period of around 

one year from its date of completion. 

• For the purposes of calculating an  internal rate of return, the various non‐residential 

elements of  the Masterplan are  valued, at period end  (i.e. at  the  conclusion of  the 

development period), adopting a capitalisation rate which is applied to the net income 

being earned at that date. The capitalisation rates adopted, which are considered to 

be reasonable having regard to all relevant factors, are   for retail floorspace, and 

 for all other uses such as the commercial and heritage buildings. 

Page 30: Pentridge Coburg - Building 15 (Jul-17) · Pentridge Coburg Building 15 development: Economic implications for total project i Executive summary • Shayher Properties Pty Ltd (Shayher)

Section 4: Economic feasibility of Masterplan 

Pentridge Coburg Building 15 development: Economic implications for total project 

23

Details of the feasibility modelling are provided at Appendix 1 to the report. 

The  outcome  of  our  feasibility modelling  shows  an  anticipated  net  rate  of  return  for  the 

project, over a 14‐year period including the 4 years elapsed since site acquisition by Shayher, 

of   The following comments are made in relation to this estimate:  

• This internal rate of return should be considered against the fact that the site owner has 

already spent in excess of   in relation to the site in the first three years. 

• The  total estimated development  cost  is  in excess of  , while  the period of 

exposure, for the developer, is 14 years, if not longer. These factors represent   

  and  an  internal  rate  of  return  of    under  these 

circumstances,   

 

 

•  

 

 

 

• There are other large financial risks, for the developer, associated with the development, 

relating  to  the  site  itself  and  the  various  constraints  which  it  imposes,  not  least  the 

heritage and public realm considerations, as well as market conditions. The fact that the 

subject site still remains essentially undeveloped some 17 years after its initial acquisition 

by Crema and then subsequently Valad and some three years after Shayher, which is now 

the third owner of the site, has acquired  it, highlights the difficulties associated with  its 

timely development.   

Page 31: Pentridge Coburg - Building 15 (Jul-17) · Pentridge Coburg Building 15 development: Economic implications for total project i Executive summary • Shayher Properties Pty Ltd (Shayher)

Section 4: Economic feasibility of Masterplan 

Pentridge Coburg Building 15 development: Economic implications for total project 

24

4.3  Significance of Building 15 

Building 15  is  important  to provide a  feature building at  the main pedestrian entrance  to 

Pentridge Coburg. It will also provide a suitable commercial use for the southern part of the 

heritage Administration building, enabling  the historic building  to be  restored and open  to 

the public. 

 

Given the project analysis outlined above, it is evident that any obstacle to the development 

of  this project  represents a  threat  to  the economic  feasibility of  the Masterplan,   

 

  Therefore,  the  permit  application  for  Building  15  and  the 

southern part of the Administration building, if refused, would clearly affect the reasonable 

or economic use of the total project. 

 

This conclusion  is supportable by a number of key reasons, which have been set out  in this 

report and include the following: 

 

• The total development will require an investment, over the development period, of some 

   

 

•  

• The  development  requires  significant  investment,  much  of  it  already  expended  by 

Shayher,  relating  specifically  to  the  heritage  value  of  the  site  and  public  realm 

requirements, many of those associated with the heritage value. 

•  

 

 

• Building 15, together with the southern part of the Administration building, is expected to 

generate an estimated  of revenue each year over the life of the project, which 

is   

Page 32: Pentridge Coburg - Building 15 (Jul-17) · Pentridge Coburg Building 15 development: Economic implications for total project i Executive summary • Shayher Properties Pty Ltd (Shayher)

Section 4: Economic feasibility of Masterplan 

Pentridge Coburg Building 15 development: Economic implications for total project 

25

If Building 15 is unable to proceed, it would greatly restrict the ability of the Administration 

building  to  be  activated  and  made  available  to  the  general  public  and  would  put  the 

economic feasibility of the total Masterplan at serious risk. 

 

Those risks will include: 

 

•  

 

 

• A significant extension  in  the period of delay before  implementation of  the Masterplan 

can proceed further,  imposing additional costs and additional risks on the project, again 

potentially putting the entire project at risk of not proceeding; and 

• Setting a pattern of further obstacles to the reasonable completion of other elements of 

the Masterplan,  thereby again potentially  imposing  further delays and  further  costs on 

the project, and imperilling its future delivery. 

 

4.4  Net community benefit 

Refusal  of  the  permit  required  to  build  Building  15  and  restore  the  southern  part  of  the 

Administration building at Pentridge Coburg will affect  the  reasonable or economic use of 

the  registered place,  as detailed  above.  In  addition  though,  it  should not be  ignored  that 

such refusal can also result in significant net community disbenefit, for a number of reasons. 

 

First, as discussed previously  in this report, there  is a significant opportunity cost, borne by 

the  community,  due  to  the  site  remaining  undeveloped,  or  remaining  undeveloped  for  a 

longer period of time. As already noted, the site has sat undeveloped for well over a decade, 

and thus its heritage value as well as its broader potential to deliver a major urban renewal 

project remain untapped. In particular, the development of Building 15 is critical in providing 

a  feature  building  near  the  main  pedestrian  entrance  to  Pentridge  Coburg,  as  well  as 

delivering a suitable use for the southern part of the Administration building.   

Page 33: Pentridge Coburg - Building 15 (Jul-17) · Pentridge Coburg Building 15 development: Economic implications for total project i Executive summary • Shayher Properties Pty Ltd (Shayher)

Section 4: Economic feasibility of Masterplan 

Pentridge Coburg Building 15 development: Economic implications for total project 

26

More  directly,  there  will  be  community  disbenefits  suffered  as  a  result  of  employment 

opportunities  foregone  in  the  event  that  the  current  masterplan  is  unable  to  be 

implemented, or is significantly delayed. 

 

Table  4.2  details  the  estimated  on‐site  employment  that  would  be  created  by  the 

development, which would be in excess of 1,200 jobs. 

 

 

 

Table 4.3 shows the total employment generating potential of the development, including: 

 • Long term on‐site employment to be accommodated  in the retail, hotel and commercial 

uses. 

• Construction employment during the period of construction of the project. 

• Induced employment due to economic multiplier effects. 

Estimated Pentridge CoburgType of use employment GLA Employment

per '000 sq.m (sq.m) (persons)

Retail 739

Commercial 63

Heritage 455

Hotel 78

Total 1,335

Net increase* 1,268

* Net increase includes an allowance for reduced employment levels at impacted centres, estimated at 5% of the total increaseSource: Shayher Group; MacroPlan Dimasi

Table 4.2

Pentridge Coburg - Estimated ongoing employment levels

Page 34: Pentridge Coburg - Building 15 (Jul-17) · Pentridge Coburg Building 15 development: Economic implications for total project i Executive summary • Shayher Properties Pty Ltd (Shayher)

Section 4: Economic feasibility of Masterplan 

Pentridge Coburg Building 15 development: Economic implications for total project 

27

 

 

Overall, the project  is estimated to create almost 8,000  jobs, of which approximately 3,600 

will  constitute  direct  employment  on  the  site,  with  4,270  jobs  attributable  to multiplier 

induced indirect employment. 

 

Therefore,  there will  be  a  very  large  community  disbenefit,  in  the  form  of  employment 

opportunities  foregone,  if  the  approved Masterplan  is unnecessarily delayed or, worse,  is 

unable to be implemented. 

 

Original stimulus Direct Direct Supplier Totalemployment employment employment (long-term) (const'n period) multiplier effects

Ongoing employment1 1,268 507 1,776

Construction of project 2,349 3,764 6,113 Job years2

Total 1,268 2,349 4,271 7,889

* Employment totals include both full-time and part-time work1. Indicates the estimated number of net additional ongoing jobs as a result of the proposed development2. Indicates the estimated number of jobs over the life of the construction project, for the equivalent of one yearSource: Shayher Group; MacroPlan Dimasi

Table 4.3

Pentridge Coburg - Estimated future employment levels*

Page 35: Pentridge Coburg - Building 15 (Jul-17) · Pentridge Coburg Building 15 development: Economic implications for total project i Executive summary • Shayher Properties Pty Ltd (Shayher)

 

 

 

 

 

 

 

 

 

Appendix 1 

 

 

Page 36: Pentridge Coburg - Building 15 (Jul-17) · Pentridge Coburg Building 15 development: Economic implications for total project i Executive summary • Shayher Properties Pty Ltd (Shayher)
Page 37: Pentridge Coburg - Building 15 (Jul-17) · Pentridge Coburg Building 15 development: Economic implications for total project i Executive summary • Shayher Properties Pty Ltd (Shayher)
Page 38: Pentridge Coburg - Building 15 (Jul-17) · Pentridge Coburg Building 15 development: Economic implications for total project i Executive summary • Shayher Properties Pty Ltd (Shayher)