Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4Q
Updated June 30, 2019
Capital Planning & DevelopmentFacilities Planning & Management
Find this document online at: www.cpd.fpm.wisc.edu/
Quarterly ReportFourth Quarter
University of Wisconsin-Madison
4Q
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 1
PAGEIntroduction 24th Quarter Highlights 3-6Current Major Projects 7-25Other Significant Projects 26-53Completed Projects 54-70Master Plans 71-74Studies 75-79Current Project Index 80-82Staff Directory 83-85Glossary of Construction Terms 86-88
The purpose of this report is to provide a volume of quarterly updates of current major projects on campus in a user friendly format to serve the needs of a diverse group of stakeholders. Please note that all completed projects are located in a document called ‘Completed Projects’ which is available on the Capital Planning & Development website at https://cpd.fpm.wisc.edu/projects/
INDEX
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 2
Planning: A/E SelectionPlanning
ProgrammingDesign: 10% Concept Report
25%-35% Design ReportConstruction Docs
Bid DateConstruction: ConstructionCompletion: Substantial Completion
Occupancy
INTRODUCTION
Projects can fall into three separate categories; Major Projects, Other Significant Projects, or Future Projects.
Regardless of which category a project is classified as, it will advance through the following phases throughout the duration of the project:
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 3
Current Projects in the 4th Quarter BudgetCurrent Projects in A/E Selection 3 projects $215,418,000Current Projects in Bidding 9 projects $38,713,600Current Projects in Design 11 projects $211,796,198Current Projects in Construction 17 projects $423,263,215Current Projects in Substantial Completion 4 projects $112,397,800Total 45 projects $1,001,588,813
Completed Projects (Since 2005) BudgetMajor Projects 88 $2,657,340,106Other Significant Projects 69 $81,249,120Total 143 $2,738,589,226
Current Master Plans & Studies BudgetCurrent Studies 1 project $156,000Previous Studies 3 projects $325,269Total 4 projects $481,269
TOTAL PROJECT BUDGETS
4TH QUARTER HIGHLIGHTS
The following tables provide highlights of activity during the fourth quarter of 2019. The total budgets below include only the Major projects, master plans, and studies featured in this report and do not include many campus activities that are smaller in scope and budget.
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 4
Project PageAthletics Facilities Renovations A/E Selection 28Camp Randall Stadium/Field House Repairs A/E Selection 9Gymnasium / Natatorium Replacement A/E Selection 12Kohl Center Addition & Renovation A/E Selection 15
NEW PROJECTS THIS QUARTER
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 5
CURRENT PROJECT PHASE BUDGETArmory & Gymnasium (Red Gym) Interior Remodel Design 2,000,000$ Athletics Facilities Renovations Design 2,995,000$ Babcock Hall Dairy Plant Renovation & CDR Addition Construction 46,920,000$ Bascom Hall / Van Vleck Classroom Itip Remodel Design 1,380,297$ Bascom Hall Room 165 Remodel Bidding 1,900,000$ Biochemistry Electron Microscopes Construction 2,250,000$ Biochemistry Instrument Facility Construction 2,700,000$ Biochemistry Loading Dock Renovation Construction 1,650,000$ Camp Randall Stadium Concourse Roof Replacement Construction 817,000$ Camp Randall Stadium/Field House Repairs A/E Selection 77,646,000$ Chemistry Instructional Addition & Renovation Construction 133,100,000$ Chemistry Laser Lab Design 617,746$ Cole & Phillips Hall Fire Alarm & Sprinkler Upgrade Bidding 2,530,600$ Curtis Pond Rehababilitation Bidding 1,124,000$ Ed Sciences Wcer Renovations Bidding 2,246,000$ Engineering Centers New Lab Renovation Bidding 2,000,000$ Engineering Hall Plaza Entrance Renovation Construction 1,425,815$ Engineering Hall Structures Lab Addition Substantial Completion 3,199,800$ Field House Exterior Restoration Design 2,995,000$ Field House South Plaza Redevelopment Design 1,826,000$ Gymnasium / Natatorium Replacement A/E Selection 95,000,000$ Hamel Music Center Construction 55,800,000$ Helen C. White Restroom Upgrades Construction 1,110,000$ Hoofers Boat Dock & Deck Replacement Substantial Completion 4,900,000$ Kohl Center Addition & Renovation A/E Selection 42,772,000$ Lathrop Drive/Bascom Hill Utility Repairs - Phase 1 Construction 32,656,000$ Limnology Lift Station & FM Construction 848,000$ Linden Drive Parking Garage Bidding 23,647,000$ Lot 76 Sanitary Lift Station Construction 2,396,000$ Lots 129 & 130 Reconstruction Construction 770,000$ Material Sciences Fume Hood Replacements Design 857,000$ McClimon Soccer Turf Replacement Construction 350,000$ Meat Science & Animal Biology Laboratory Substantial Completion 50,077,000$ Memorial Library UW Press Remodel Substantial Completion 1,424,000$ MSC Kinesiology Renovation Design 12,000,000$ MSC Remodel For Chemistry Learning Center Bidding 1,300,000$ Nancy Nicholas Hall/ Ember Hall Alteration Design 814,155$ Primate Center Backup Generator Bidding 1,200,000$ Sellery Hall Addition & Renovation Design 78,811,000$ South Campus Utility Improvements Construction 22,760,000$ Southeast Recreational Facility Replacement Construction 96,541,000$
4TH QUARTER HIGHLIGHTS
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 6
University Houses Roof Replacement & Repair Bidding 2,766,000$ Veterinary Medicine Addition & Renovation Design 107,500,000$ WIMR West Wedge Addition Construction 21,169,400$ Witte Hall Renovation Substantial Completion 52,797,000$ TOTAL 1,001,588,813$
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 7
Capital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin - Madison
Current Major ProjectsThese are projects that have been enumerated and are active
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 8
BABCOCK HALL DAIRY PLANT RENOVATION & CDR ADDITION 13A2U
BUDGET KEY STAKEHOLDERSTotal Soft Costs $5,356,400 Occupants Babcock Dairy Plant/CDRTotal Construction Costs $41,563,600 User Reps Doug SabatkeTotal Project Costs $46,920,000 UW PM Steve Richards
DFDM PM Kevin TrinasticFunding Sources: A/E Zimmerman Arch. StudiosGFSB $22,209,000 Design Arch. Zimmerman Arch. StudiosGift/Grant $18,461,000 Landscape Arch. Zimmerman Arch. StudiosCash $6,250,000 Structural Engr. Harwood Engineering
General Contractor CD SmithPlumbing Hooper Corp.Mechanical NAMI, Inc.Fire Protection J.F. Ahern Co.Electrical Morse Electric, Inc.
TIMELINE AREA DATAA/E Selection 11/2013 GSF-Babcock Remodel 29,700Design Report 02/2017 ASF-Babcock Remodel 23,575Bid Date 03/2018 Efficiency-Babcock Remodel 79.38%Start Construction 05/2018 GSF-CDR Addition 54,650Substantial Completion 11/2020 ASF-CDR Addition 33,145
Efficiency-CDR Addition 60.65%Construction $/GSF $493Construction $/GSF $733Total Project $/GSF $827
This project constructs a three-story addition to house the Center for Dairy Research (CDR), a milk intake facility with three storage silos, and a small addition to house a two-story dryer. Space on the basement, first, and second levels of the existing dairy plant will be renovated. The existing milk intake area, the existing drying tower, a mechanical space at the northwest corner of Babcock Hall, and a stair tower will be demolished to make room for the addition.
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 9
CAMP RANDALL STADIUM / FIELD HOUSE RENOVATION 19F2Y
BUDGET KEY STAKEHOLDERSTotal Soft Costs TBD Occupants Intercollegiate AthleticsTotal Construction Costs TBD User Reps Jason KingTotal Project Costs $77,646,000 UW PM Brandon Braithwaite
DFDM PM TBDFunding Sources: A/E TBDPRSB $68,046,000 Design Arch. TBDCash $6,600,000 Landscape Arch. TBDGift/Grant $3,000,000 Structural Engr. TBD
MEP Engr. TBDGeneral Contractor TBDPlumbing TBD
TIMELINE Mechanical TBDA/E Selection 08/2019 Fire Protection TBDDesign Report 10/2020 Electrical TBDBid Date 05/2021Start Construction 11/2021Substantial Completion 10/2023 AREA DATA
GSF TBDASF TBDEfficiency TBDConstruction $/GSF TBDTotal Project $/GSF TBD
This project renovates Camp Randall Stadium to provide enhanced fan amenities and opportunities for additional revenue that meet premium seating requests, repairs the Field House exterior envelope, upgrades finishes and technology in the press box, installs new mechanical, electrical/telecom, and plumbing systems, and replaces the synthetic field turf in the Stadium and the McClain Athletic Facility.
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 10
CHEMISTRY INSTRUCTIONAL ADDITION & RENOVATION 13B3G
BUDGET KEY STAKEHOLDERSTotal Soft Costs $27,600,350 Occupants Chemistry DepartmentTotal Construction Costs $105,499,650 User Reps Bob McMahonTotal Project Costs $133,100,000 UW PM Megan McBride
DFDM PM Russ Van GilderFunding Sources: A/E Strang, Inc.GIFT/GRANT $25,828,000 Design Arch. BallingerGFSB $91,200,000 Landscape Arch. GRAEF-USA Inc.CASH $5,000,000 Structural Engr. GRAEF-USA Inc.AGFO/Other $11,072,000 General Contractor Miron Construction Co., Inc.
Plumbing Hooper Mechanical NAMI
TIMELINE Fire Protection J.F. Ahern Co.A/E Selection 11/2013 Electrical Staff ElectricDesign Report 12/2015Bid Date 07/2018 AREA DATAStart Construction 09/2018 GSF 245,840Substantial Completion 03/2022 ASF 134,277
Efficiency 55.00%Construction $/GSF $511Total Project $/GSF $541
The project consists of the design and construction of a new undergraduate chemistry teaching tower, the renovation of existing undergraduate laboratories and offices in the Daniels portions of the existing Chemistry building, and the replacement of critical HVAC and exhaust systems serving the existing Daniels and Mathews research and teaching labs.
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 11
ENGINEERING HALL STRUCTURES LAB ADDITION 14J2I
BUDGET KEY STAKEHOLDERSTotal Soft Costs $435,350 Occupants College of EngineeringTotal Construction Costs $2,764,450 User Reps Barbara McPhersonTotal Project Costs $3,199,800 UW PM Peter Bloechl-Anderson
DFDM PM Kevin TrinasticFunding Sources: A/E BWBRGift/Grant $3,199,800 Design Arch. BWBR
Landscape Arch. N/AStructural Engr. GRAEF, AEIGeneral Contractor Vogel Bros.Plumbing H.J. PertzbornMechanical H & H Industries
TIMELINE Fire Protection H.J. PertzbornA/E Selection 03/2015 Electrical Forward ElectricDesign Report 06/2016Bid Date 04/2017Start Construction 05/2017 AREA DATASubstantial Completion 07/2019 GSF 2,200
ASF 2,000Efficiency 90.91%Construction $/GSF $1,372Total Project $/GSF $1,455
This $3,200,000 project is a 2,000 ASF / 2,200 GSF addition in the southwest corner of Engineering Hall for the Wisconsin Structures and Materials Testing Laboratory. The new lab room will provide a specially constructed high-strength floor and multi-story post-tensioned reaction wall with grid high-strength anchors, overhead crane, and access to the exterior that will allow for testing of structural components up to 40 feet in length. The overall height will match the existing building height. Behind schedule due to nonconforming work.
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 12
GYMNASIUM / NATATORIUM REPLACEMENT 18H3E
BUDGET KEY STAKEHOLDERSTotal Soft Costs $10,000,000 Occupants Recreational SportsTotal Construction Costs $85,000,000 User Reps John HornTotal Project Costs $95,000,000 UW PM Bo Muwahid
DFDM PM Wendy von BelowFunding Sources: A/E Kahler SlaterPRSB $60,600,000 Design Arch. HOKGift/Grant $34,400,000 Landscape Arch. GRAEF
Structural Engr. OTIEMEP Engr. Mead+HuntGeneral Contractor TBDPlumbing TBD
TIMELINE Mechanical TBDA/E Selection 04/2019 Fire Protection TBDDesign Report 10/2019 Electrical TBDBid Date 11/2020Start Construction 01/2021Substantial Completion 12/2022 AREA DATA
GSF 262,108ASF 170,200Efficiency 64.94%Construction $/GSF N/ATotal Project $/GSF N/A
This project will demolish the Gymnasium/Natatorium (Gym/Nat) facility that no longer adequately supports the space needs of Recreational Sports and construct a replacement facility on the same site. The project provides space for a wellness center, a new gift-funded ice arena, basketball courts, indoor track, fitness space and racquetball courts as well as enhanced activity areas that will generate additional revenue.
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 13
HAMEL MUSIC CENTER 10F2J
BUDGET KEY STAKEHOLDERSTotal Soft Costs $10,502,400 Occupants School of MusicTotal Construction Costs $45,297,600 User Reps Susan CookTotal Project Costs $55,800,000 UW PM Bo Muwahid
DFDM PM N/AFunding Sources: A/E Strang, Inc.Gift/Grant $55,800,000 Design Arch. Holzman Moss Bottino
Architecture, LLPLandscape Arch. Ken Saiki DesignStructural Engr. R.A. SmithGeneral Contractor JP CullenPlumbing Hooper Corp.
TIMELINE Mechanical General HeatingA/E Selection 11/2010 Fire Protection USA Fire ProtectionDesign Report 03/2015 Electrical NicklesBid Date 12/2016Start Construction 02/2017 AREA DATASubstantial Completion 08/2019 GSF 74,840
ASF 55,250Efficiency 73.82%Construction $/GSF $645Total Project $/GSF $746
This music performance facility project for the Mead Witter School of Music is a significant component of the University’s East Campus Development Plan. The project will provide a 650-seat concert hall, a 330-seat recital hall, and a large rehearsal room.
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 14
HOOFERS BOAT DOCK & DECK REPLACEMENT MSN #0008-1601
BUDGET KEY STAKEHOLDERSTotal Soft Costs $414,147 Occupants Memorial UnionTotal Construction Costs $4,485,853 User Reps Joel GerritsTotal Project Costs $4,900,000 UW PM Bo Muwahid
A/E SmithGroupJJRFunding Sources: Design Arch. N/AGift/Grant $4,900,000 Landscape Arch. SmithGroupJJR
Structural Engr. SmithGroupJJRGeneral Contractor MichelsPlumbing TBDMechanical TBDFire Protection TBD
TIMELINE Electrical Universal Power SystemA/E Selection 04/2017Design Report 02/2018Bid Date 08/2018Start Construction 10/2018 AREA DATASubstantial Completion 07/2019 GSF N/A
ASF N/AEfficiency N/AConstruction $/GSF N/ATotal Project $/GSF N/A
This project, located on the south shore of Lake Mendota immediately west of the Memorial Terrace, includes replacement of all components of the boat docks and storage decks including ramps, gangways, and anchoring systems, as well as shoreline restoration and other site amenities for the UW Hoofers Sailing Club.
UW-Managed
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 15
KOHL CENTER ADDITION & RENOVATION 18H2G
BUDGET KEY STAKEHOLDERSTotal Soft Costs $6,008,000 Occupants Intercollegiate AthleticsTotal Construction Costs $36,764,000 User Reps Jason KingTotal Project Costs $42,772,000 UW PM Brandon Braithwaite
DFDM PM Tim LuttrellFunding Sources: A/E Berners-Schober AssociatesPRSB $28,672,000 Structural Engr. TBDGift/Grant $10,000,000 General Contractor TBDCash $4,100,000 Plumbing TBD
Mechanical TBDFire Protection TBD
TIMELINE Electrical TBDA/E Selection 06/2019Design Report 03/2020 AREA DATABid Date 11/2020 GSF TBDStart Construction 03/2021 ASF TBDSubstantial Completion 07/2023 Efficiency TBD
Construction $/GSF TBDTotal Project $/GSF TBD
This project will construct an addition to the Kohl Center and renovate areas within the arena. The addition, over the existing loading dock, will serve and expand programs such as academics, a student-athlete hub, sports nutrition, strength and conditioning, sports medicine, and administrative functions. Additionally, there will be remodeling within the Kohl Center adjacent to the addition and on the service level for locker rooms, student-athlete dining, media room, club, and kitchen expansions.
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 16
LATHROP DRIVE/BASCOM HILL UTILITY REPAIRS - PHASE 1 17J2L
BUDGET KEY STAKEHOLDERSTotal Soft Costs $3,412,000 Occupants FP&M/Physical PlantTotal Construction Costs $29,244,000 User Reps Jeff PolleiTotal Project Costs $32,656,000 UW PM Brandon Braithwaite
DFDM PM Michael HansonFunding Sources: A/E Ring & DuChateau, LLPGFSB $23,839,000 Design Arch. N/APRSB $8,817,000 Landscape Arch. Saiki Design
Structural Engr. OTIEMEP Engr. TBDGeneral Contractor Terra EngineeringPlumbing TBD
TIMELINE Mechanical TBDA/E Selection 03/2019 Fire Protection TBDDesign Report 01/2019 Electrical Westphal ElectricBid Date 03/2019Start Construction 04/2019Substantial Completion 12/2021 AREA DATA
GSF TBDASF TBDEfficiency TBDConstruction $/GSF TBDTotal Project $/GSF TBD
The utility repair work consists of primary and signal duct bank installation, bored walkable steam tunnel, new steam box conduits, chilled water supply and return lines, and water and sewer utility upgrades.
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 17
LINDEN DRIVE PARKING GARAGE 17I1F
BUDGET KEY STAKEHOLDERSTotal Soft Costs $3,338,500 Occupants Transportation ServicesTotal Construction Costs $20,308,500 User Reps Patrick KassTotal Project Costs $23,647,000 UW PM Mike Zimmerman
DFDM PM Jake EhmkeFunding Sources: A/E Brian ReedAgency Cash $10,635,800 Structural Engr. Nik SwartzGFSB $13,011,200 General Contractor TBD
Plumbing TBDMechanical TBDFire Protection TBDElectrical TBD
TIMELINE AREA DATAA/E Selection 03/2017 GSF 190,200Design Report 04/2019 ASF 180,690Bid Date 07/2019 Efficiency 95.00%Start Construction 09/2019 Construction $/GSF $116Substantial Completion 12/2020 Total Project $/GSF $124
This project will design and construct a new 600+ stall parking garage in the existing Lot 62 parking lot to replace parking spaces lost from the expansion of the School of Veterinary Medicine addition and the new Meat Science and Animal Biologics Discovery Building.
Design-Bid-Build Single Prime
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 18
MEAT SCIENCE & ANIMAL BIOLOGICS DISCOVERY BUILDING 13I2Y
BUDGET KEY STAKEHOLDERSTotal Soft Costs $9,681,000 Occupants CALSTotal Construction Costs $40,396,000 User Reps Doug SabatkeTotal Project Costs $50,077,000 UW PM Peter Bloechl-Anderson
DFDM PMFunding Sources: A/E Gary McLeanGFSB $24,377,000 Design Arch. Potter LawsonGift/Grant $23,400,000 Landscape Arch. Saiki DesignCash $2,300,000 Structural Engr. GRAEF-USA Inc.
General Contractor JP CullenPlumbing MononaMechanical NAMI
TIMELINE Fire Protection MononaA/E Selection 04/2014 Electrical H&H ElectricalDesign Report 01/2015Bid Date 10/2016Start Construction 12/2016 AREA DATASubstantial Completion 07/2019 GSF 67,540
ASF 37,308Efficiency 55.24%Construction $/GSF $654Total Project $/GSF $741
This project will construct a two-story modern teaching, research, and outreach facility to support the meat industry of the State of Wisconsin. The new laboratory will facilitate the development of modern meat processing and research through the inclusion of lab general purpose benches for biochemical, chemical, and microbial studies as well as more specialized rooms for microscopy, tissue culture, instrumentation, and cold experiments. This project replaces the existing Meat and Muscle Biology Building built in three sections in 1930, 1959, and 1969.
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 19
MSC KINESIOLOGY RENOVATION MSN #0451-1803
BUDGET KEY STAKEHOLDERSTotal Soft Costs $2,971,000 Occupants Dept of KinesiologyTotal Construction Costs $9,029,000 User Reps Lindsey HoneyagerTotal Project Costs $12,000,000 UW PM Ashraf Sadek
DFDM PM TBDFunding Sources: A/E HGAGift/Grant $12,000,000 Design Arch. TBD
Landscape Arch. TBDStructural Engr. TBDMEP Engr. TBDGeneral Contractor TBDPlumbing TBD
TIMELINE Mechanical TBDA/E Selection 02/2019 Fire Protection TBDDesign Report 06/2019 Electrical TBDBid Date 10/2019Start Construction 12/2019Substantial Completion 05/2020 AREA DATA
GSF 59,685ASF 36,179Efficiency 60.62%Construction $/GSF $167Total Project $/GSF $201
This project will relocate the Department of Kinesiology to the Medical Sciences Center (MSC) building prior to the demolition of the Gymnasium/Natatorium (Gym/Nat) on Observatory Drive. Currently, the Department of Kinesiology occupies approximately 30,800 square feet in the Gym/Nat which is slated to start construction of the new facility in January 2021.
UW-Managed
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 20
SELLERY HALL ADDITION & RENOVATION 14E2O
BUDGET KEY STAKEHOLDERSTotal Soft Costs $9,631,000 Occupants University HousingTotal Construction Costs $69,180,000 User Reps Adam RittelTotal Project Costs $78,811,000 UW PM Bo Muwahid
DFDM PM Wendy von BelowFunding Sources: A/E UWRSPR Cash $19,703,000 Design Arch. Steve GrothPRSB $59,108,000 Landscape Arch. Smithgroup
Structural Engr. OTIEMEP Engr. IMEGGeneral Contractor CD SmithPlumbing Monona
TIMELINE Mechanical TBDA/E Selection 10/2014 Fire Protection TBDDesign Report 08/2019 Electrical TBDBid Date 05/2020Start Construction 07/2020Substantial Completion 08/2023 AREA DATA
GSF 330,931ASF 219,196Efficiency 66.24%Construction $/GSF 209Total Project $/GSF 238
As the campus continues to expand its academic offerings and enrollment, it needs to increase housing opportunities for incoming freshmen and returning students. By providing space within residence halls focused on the incoming freshman class program-based experience, students seek housing on campus to enhance their academic and social experience. The project will provide a full renovation of the space and add a new central core tower that will consolidate five new elevators, key mechanical equipment, accessible resident entry, and resident life space. Construction will also add two floors on top of the existing ten-story structure, allowing for approximately 250 new resident bed spaces.
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 21
SOUTH CAMPUS UTILITY IMPROVEMENTS 15K1F
BUDGET KEY STAKEHOLDERSTotal Soft Costs $2,316,000 Occupants FP&M/Physical PlantTotal Construction Costs $17,040,000 User Reps Jeff PolleiTotal Project Costs $22,760,000 UW PM Brandon Braithwaite
DFDM PM Michael HansonFunding Sources: A/E Affiliated Engineers, IncGFSB $11,306,000 Design Arch. N/APRSB $4,182,000 Landscape Arch. Ayres AssociatesCash $1,687,000 Structural Engr. Bloom Companies, LLC
MEP Engr. N/AGeneral Contractor Terra EngineeringPlumbing N/A
TIMELINE Mechanical Hooper CorperationA/E Selection N/A Fire Protection N/ADesign Report N/A Electrical Forward Electric, Inc.Bid Date 01/2019Start Construction 04/2019Substantial Completion 04/2020 AREA DATA
GSF TBDASF TBDEfficiency TBDConstruction $/GSF TBDTotal Project $/GSF TBD
The scope of work consists of replacement and construction of steam utilities along Dayton Street from Mills to Park Streets and primary electrical/signal communication utilities along Dayton Street from Charter to Park Street. Improvements include replacement of high-pressure steam, pumped condensate return, and compressed air piping. The City of Madison will also be upgrading water main, sewer, and storm sewer utilities.
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 22
SOUTHEAST RECREATIONAL FACILITY REPLACEMENT 14L2T
BUDGET KEY STAKEHOLDERSTotal Soft Costs $23,631,000 Occupants Rec SportsTotal Construction Costs $72,910,000 User Reps John HornTotal Project Costs $96,541,000 UW PM Ann Hayes
DFDM PM Wendy von BelowFunding Sources: A/E Workshop Architects, Inc.PRSB $53,872,600 Design Arch. HOKGift/Grant $42,080,000 Landscape Arch. Ken Saiki DesignCash $588,400 Structural Engr. GRAEF-USA Inc.
General Contractor Miron ConstructionPlumbing Hooper Corp.
TIMELINE Mechanical NAMIA/E Selection 09/2015 Fire Protection JF AhernDesign Report 02/2017 Electrical Staff ElectricBid Date 08/2008Start Construction 10/2017Substantial Completion 12/2019 AREA DATA
GSF 248,300ASF 170,800Efficiency 68.79%Construction $/GSF $354Total Project $/GSF $389
This replacement project demolishes the 125,118 ASF / 191,254 GSF Southeast Recreation Facility (SERF) and constructs a 181,830 ASF / 250,800 GSF facility which is a 31% expansion. It will include all the required utility improvements and house expanded spaces such as functional fitness areas, a nine-basketball court gymnasium, an indoor walking and jogging track, and several multi-purpose rooms. A 50-meter competition pool and separate diving well will be shared between Recreational Sports and the Division of Intercollegiate Athletics.
UW-Managed
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 23
VETERINARY MEDICINE ADDITION 18H2H
BUDGET KEY STAKEHOLDERSTotal Soft Costs $16,671,000 Occupants School of Vet MedTotal Construction Costs $90,829,000 User Reps Mark MarkelTotal Project Costs $107,500,000 UW PM Stu LaRose
DFDM PM Wendy von BelowFunding Sources: A/E N/AAGFO/Other $1,447,000.00 Structural Engr. N/AGFSB $68,053,000 General Contractor TBDGift/Grant $38,000,000 Plumbing TBD
Mechanical TBDTIMELINE Fire Protection TBDA/E Selection 04/2019 Electrical TBDDesign Report 04/2019Bid Date 07/2019Start Construction 08/2019 AREA DATASubstantial Completion 02/2020 GSF TBD
ASF TBDEfficiency TBDConstruction $/GSF TBDTotal Project $/GSF TBD
As the School of Veterinary Medicine continues to grow, so does its need for additional space to support enrollment, research, and outreach growth in patient care services. Consistently ranked within the top five veterinary medicine schools in the US, the facilities have reached capacity and no longer support current or future growth. This project will construct a three-story 139,000 GSF building on Lot 62 directly north of the current school, providing expanded space for the small animal clinic, collaborative spaces to support the teaching hospitals, research labs, and new BSL-3/ABSL-3/BSL-2 laboratories, offices, and conference rooms.
UW-Managed
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 24
WIMR WEST WEDGE ADDITION MSN #1485-1602
BUDGET KEY STAKEHOLDERSTotal Soft Costs $3,147,514 Occupants SMPHTotal Construction Costs $18,021,886 User Reps Mark WellsTotal Project Costs $21,169,400 UW PM Peter Bloechl-Anderson
A/E Flad ArchitectsFunding Sources: Design Arch. Flad ArchitectsGift/Grant $21,169,400 Landscape Arch. Flad Architects
Structural Engr. Flad Structural EngineersGeneral Contractor FindorffPlumbing H&H Industries
TIMELINE Mechanical J.F. AhernA/E Selection 05/2016 Fire Protection J.F. AhernDesign Report 07/2017 Electrical H&H ElectricBid Date 02/2018Start Construction 03/2018 AREA DATASubstantial Completion 09/2019 GSF 36,868
ASF 20,981Efficiency 56.91%Construction $/GSF $489Total Project $/GSF $574
This project designs and constructs two floors (20,981 ASF/ 36,868 GSF total) of new office and laboratory space above the existing single-story structure on the west side of the Wisconsin Institutes for Medical Research (WIMR) Building, 1111 Highland Avenue. The existing space contains the Surgical Pathology Department, which was constructed by the University of Wisconsin Hospital and Clinics (UWHC) and completed in the summer of 2014. The proposed two additional west wedge floors will be used to meet the growing demand for offices and laboratories on the clinical west campus.
UW-Managed
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 25
WITTE HALL RENOVATION 14E2O
BUDGET KEY STAKEHOLDERSTotal Soft Costs $5,466,460 Occupants University HousingTotal Construction Costs $47,330,540 User Reps Mike KindermanTotal Project Costs $52,797,000 Adam Rittel
UW PM Bo MuwahidFunding Sources: DFDM PM Wendy von BelowProgram Revenue $52,797,000 A/E UWRS
Design Arch. Steve GrothLandscape Arch. SmithGroupJJRStructural Engr. OTIEMEP Engr. IMEGGeneral Contractor CD Smith
TIMELINE Plumbing MononaA/E Selection 12/2014 Mechanical H&H IndustriesDesign Report 09/2015 Fire Protection H.J. PertzbornBid Date 12/2016 Electrical H&H ElectricStart Construction 03/2017Substantial Completion 08/2019 AREA DATA
GSF 287,324ASF 174,358Efficiency 60.68%Construction $/GSF $165Total Project $/GSF $184
Witte Hall’s core, first floor, and basement areas will be renovated and expanded to accommodate four new elevators, common space (floor lounge, study space, and kitchenette), and bathrooms. HVAC systems will be replaced/upgraded by adding individual heat controls in rooms and air conditioning throughout the halls. Windows will be replaced and resident rooms, hallways, and stairwells will be upgraded. There will be finish upgrades throughout. Construction began fall of 2017. Occupancy at the start of Fall 2019 is expected.
Design-Bid-Build Single Prime
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 26
Capital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin - Madison
Other Significant ProjectsProjects which are renovations and remodels with a budget range from $185,000 to $3 million and are either
overseen by a Capital Planning & Development Project Manager or have a significant impact throughout campus
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 27
ARMORY & GYMNASIUM (RED GYM) INTERIOR REMODEL MSN# 0020-1802
BUDGET KEY STAKEHOLDERSTotal Soft Costs $643,700 Occupants Space Management OfficeTotal Construction Costs $1,356,300 User Reps Brent LoydTotal Project Costs $2,000,000 UW PM Peter Bloechl-Anderson
DFDM PM N/AFunding Sources: A/E Aro EberleGift/Grant $2,000,000 Structural Engr. Aro Eberle
General Contractor TBDPlumbing TBDMechanical TBDFire Protection TBD
TIMELINE Electrical TBDA/E Selection 08/2018Design Report 05/2019 AREA DATABid Date 10/2019 GSF TBDStart Construction 11/2019 ASF TBDProject Close-Out 04/2020 Efficiency TBD
Construction $/GSF TBDTotal Project $/GSF TBD
This project will improve the space utilization of the current Red Gym tenants. Scope of the project will include: renovation of the Masley Media Room, converting it from a multi-purpose space to unit space specifically for the LGBT Campus Center; backfill of current LGBT Campus Center space with the IAP resource function; update the On Wisconsin Room; renovate the DDEEA Suite on second floor; address sound transfer in Multicultural Student Center space; convert South Mezzanine space to a lockable conference room that to accommodate additional staff and programs; convert the north mezzanine conference rooms to assignable space; update wayfinding for affected spaces; and provide a digital lobby information screen.
UW-Managed
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 28
ATHLETICS FACILITIES RENOVATIONS 19C1Y
BUDGET KEY STAKEHOLDERSTotal Soft Costs $296,000 Occupants UW AthleticsTotal Construction Costs $2,699,000 User Reps Barry FoxTotal Project Costs $2,995,000 UW PM Brandon Braithwaite
DFDM PM Tim LuttrellFunding Sources: A/E Berners-Schober AssociatesCash $2,995,000 Structural Engr. N/A
General Contractor TBDPlumbing TBDMechanical TBDFire Protection TBD
TIMELINE Electrical TBDA/E Selection 06/2019Design Report 10/2019 AREA DATABid Date 02/2020 GSF N/AStart Project 04/2020 ASF N/ASubstantial Completion 12/2021 Efficiency N/A
Construction $/GSF N/ATotal Project $/GSF N/A
This project will provide pre-design, and design services to renovate and maintain multiple athletic facilities to address safety, customer satisfaction, energy efficiency, and enhance the experience of patrons.
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 29
BASCOM HALL ROOM 165 REMODEL MSN #0050-1805
BUDGET KEY STAKEHOLDERSTotal Soft Costs $642,000 Occupants UW RelationsTotal Construction Costs $1,258,000 User Reps Jordan HansonTotal Project Costs $1,900,000 UW PM Megan McBride
A/E Boer ArchitectsFunding Sources: Design Arch. Boer ArchitectsGift/Grant $1,900,000 Structural Engr. TBD
General Contractor TBDPlumbing TBDMechanical TBDFire Protection TBDElectrical TBD
TIMELINE Fire Protection TBDA/E Selection 03/2014 Electrical TBDDesign Report 05/2018Bid Date 09/2019Start Construction 11/2019 AREA DATASubstantial Completion 05/2020 GSF 4,000
ASF 2,600Efficiency 65.00%Construction $/GSF $390Total Project $/GSF $475
UW-Managed
This project will re-purpose an existing lecture hall into office space for campus administration. The 4,000 GSF / 2,600 ASF project is completely gift-funded and will include a new reception area to support the Office of the Chancellor and a suite of private offices and workstations. The historic integrity of the original space will remain intact.
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 30
BASCOM HALL / VAN VLECK CLASSROOM ITIP REMODEL 18H1W
BUDGET KEY STAKEHOLDERSTotal Soft Costs $550,910 Occupants CampusTotal Construction Costs $829,387 User Reps Abe SchrumpTotal Project Costs $1,380,297 UW PM Megan McBride
DFDM PM Wendy von BelowFunding Sources: A/E Aro EberleGift/Grant $1,462,000 Structural Engr. N/A
General Contractor TBDPlumbing TBDMechanical TBDFire Protection TBD
TIMELINE Electrical TBDA/E Selection 09/2018Design Report 04/2019 AREA DATABid Date 08/2019 GSF 5,872Start Construction 11/2019 ASF 5,872Substantial Completion 05/2020 Efficiency TBD
Construction $/GSF $141Total Project $/GSF $235
The project will update the systems, finishes, and furnishings while preserving, restoring, and augmenting the historical integrity and beauty of the historic lecture hall in Bascom Hall. In addition, this project will provide an additional active learning classroom on campus in the 70-99 seat range by renovating three existing, underutilized spaces to create one large classroom in Van Vleck Hall.
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 31
BIOCHEMISTRY ELECTRON MICROSCOPES MSN# 0084-1802
BUDGET KEY STAKEHOLDERSTotal Soft Costs $341,000 Occupants BiochemistryTotal Construction Costs $1,909,000 User Reps Brian Fox / Liz WrightTotal Project Costs $2,250,000 UW PM Bo Muwahid
DFDM PM N/AFunding Sources: A/E Aro EberleGift/Grant $2,250,000 Structural Engr. OTIE
General Contractor TBDPlumbing TBDMechanical TBDFire Protection TBD
TIMELINE Electrical TBDA/E Selection 10/2018Design Report 12/2018 AREA DATABid Date 05/2019 GSF 1,562Start Construction 07/2019 ASF 1,274Substantial Completion 12/2019 Efficiency 81.00%
Construction $/GSF $1,033Total Project $/GSF $1,125
UW-Managed
This project will create a laboratory space for two cryo-electron microscopes. The laboratory space will be constructed to BSL-2 standards and will have areas for various sample prep.
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 32
BIOCHEMISTRY INSTRUMENT FACILITY 14E3R
BUDGET KEY STAKEHOLDERSTotal Soft Costs $566,000 Occupants BiochemistryTotal Construction Costs $2,134,000 User Reps Brian FoxTotal Project Costs $2,700,000 UW PM Bo Muwahid
DFDM PM N/AFunding Sources: A/E Flad ArchitectsGifts & Grants $2,999,000 Design Arch. Flad Architects
Landscape Arch. N/AStructural Engr. N/AGeneral Contractor J.H. Findorff & SonsPlumbing Monona PlumbingMechanical Illingworth-Kilgust
TIMELINE Fire Protection J.F. Ahern Co.A/E Selection 07/2014 Electrical WestphalDesign Report 01/2017Bid Date 11/2017Start Construction 03/2018 AREA DATASubstantial Completion 01/2020 GSF 3,690
ASF 2,320Efficiency 62.87%Construction $/GSF $621Total Project $/GSF $153
This project improves the shared 3,000 square feet research instrument facility in the basement of the Biochemical Sciences building (1985 wing.) Interior walls will be completely reconfigured to create a series of both large and small equipment rooms. Spaces will be electrically intensive, but wet-lab needs will be moderate.
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 33
BIOCHEMISTRY LOADING DOCK RENOVATION MSN # 0205-1704
BUDGET KEY STAKEHOLDERSTotal Soft Costs $200,000 Occupants BiochemistryTotal Construction Costs $1,450,000 User Reps Brian Fox / Doug SabatkeTotal Project Costs $1,650,000 UW PM Bo Muwahid
DFDM PM TBDFunding Sources: A/E Delta 3 EngineeringGifts & Grants $1,650,000 Design Arch. Delta 3 Engineering
Structural Engr. Delta 3 EngineeringGeneral Contractor Findorff
TIMELINE AREA DATAA/E Selection 09/2017 GSF N/ADesign Report 09/2018 ASF N/ABid Date 05/2019 Efficiency N/AStart Construction 06/2019 Construction $/GSF N/ASubstantial Completion 12/2019 Total Project $/GSF N/A
This project will add an addition to the Biochemistry Laboratories loading dock and raise the adjacent elevation roughly 30" to eliminate flooding that occurs frequently during heavy rain events. The existing storm sewers will also be increased in size at the Biochemistry Building as well as near the Bock Labs loading dock.
UW-Managed
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 34
CAMP RANDALL STADIUM CONCOURSE ROOF REPLACEMENT 18E1D
BUDGET KEY STAKEHOLDERSTotal Soft Costs $817,000 Occupants AthleticsTotal Construction Costs N/A User Reps Barry FoxTotal Project Costs $817,000 UW PM Peter Bloechl-Anderson
DFDM PM Tim LuttrellFunding Sources: A/E N/AGifts & Grants Structural Engr. TBDAGFO $817,000 General Contractor TBD
Plumbing TBDMechanical TBDFire Protection TBD
TIMELINE Electrical TBDA/E Selection 06/2019Design Report TBD AREA DATABid Date 02/2019 GSF TBDStart Construction 06/2019 ASF TBDSubstantial Completion 09/2019 Efficiency TBD
Construction $/GSF TBDTotal Project $/GSF TBD
UW-Managed
This project includes all design and construction for a complete replacement of the roofing system on the sixth level concourse roof of Camp Randall Stadium. The work will include complete removal of the existing asphalt roofing system down to bare concrete and all metal flashing.
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 35
CHEMISTRY LASER LAB MSN# 0047-1803
BUDGET KEY STAKEHOLDERSTotal Soft Costs $76,724 Occupants Chemistry DepartmentTotal Construction Costs $541,022 User Reps Jeff NielsonTotal Project Costs $617,746 UW PM Megan McBride
DFDM PM N/AFunding Sources: A/E Aro EberleGifts & Grants $617,000 Structural Engr. TBD
General Contractor TBDPlumbing TBDMechanical TBDFire Protection TBD
TIMELINE Electrical TBDA/E Selection 11/2018Design Report 04/2019 AREA DATABid Date 09/2019 GSF 675Start Construction 12/2019 ASF 550Substantial Completion 05/2020 Efficiency 81.48%
Construction $/GSF $606Total Project $/GSF $761
This project seeks to remodel two rooms on the fourth floor of the Chemistry building into a lab for three Class IV lasers. The lab needs to be a highly controlled space with tight temperature controls that lower airborne particulate counts for the laser microscopy work.
UW-Managed
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 36
COLE & PHILLIPS HALL FIRE ALARM & SPRINKLER UPGRADE 18A2B
BUDGET KEY STAKEHOLDERSTotal Soft Costs $333,200 Occupants UW HousingTotal Construction Costs $2,197,400 User Reps Mike KindermanTotal Project Costs $2,530,600 UW PM Bo Muwahid
DFDM PM Wendy von BelowFunding Sources: A/E Assemblage ArchitectsPRSB $2,530,600 Design Arch. Hamid Noughani
Landscape Arch. N/AStructural Engr. N/AGeneral Contractor TBDPlumbing TBDMechanical TBD
TIMELINE Fire Protection TBDA/E Selection 02/2018 Electrical TBDDesign Report 09/2019Bid Date 02/2019Start Construction 05/2020 AREA DATASubstantial Completion 08/2020 GSF N/A
ASF N/AEfficiency N/AConstruction $/GSF N/ATotal Project $/GSF N/A
Project work includes installation of a new, fully automated fire sprinkler systems per current code and replacing the fire alarm and smoke detection systems in both Cole Hall and Phillips Hall, and renovating the (75) 30 SF student restrooms in Phillips Hall.
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 37
CURTIS POND REHABILITATION 16H2U
BUDGET KEY STAKEHOLDERSTotal Soft Costs $165,000 Occupants N/ATotal Construction Costs $959,000 User Reps N/ATotal Project Costs $1,124,000 UW PM Brandon Braithwaite
DFDM PM Jim SchaeferFunding Sources: A/E Strand Associates, Inc.GFSB $550,450 Design Arch. N/APR Cash $203,590 Landscape Arch. N/AOthers $1,354,960 Structural Engr. N/A
General Contractor TBDPlumbing TBDMechanical TBD
TIMELINE Fire Protection TBDA/E Selection 11/2016 Electrical TBDDesign Report 10/2017Bid Date 11/2019Start Construction 12/2019 AREA DATAProject Close-Out 09/2020 GSF N/A
ASF N/AEfficiency N/AConstruction $/GSF N/ATotal Project $/GSF N/A
The existing UW Arboretum Curtis Storm Water Detention Pond must be rehabilitated to repair a failed flume and failing outlet structure, restoring the pond’s ability to control peak stormwater runoff flow rates and remove accumulated stormwater sediment. This project is funded in part through an Intergovernmental Agreement between the University of Wisconsin, the City of Madison, and the Town of Madison dated February 2009.
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 38
ED SCIENCES WCER RENOVATIONS MSN #0154-1705
BUDGET KEY STAKEHOLDERSTotal Soft Costs $617,981 Occupants School of EducationTotal Construction Costs $1,628,019 User Reps Lindsey HoneyagerTotal Project Costs $2,246,000 UW PM Ashraf Sadek
DFDM PM N/AFunding Sources: A/E Melissa DestreeGifts & Grants $2,267,000 Design Arch. N/A
Landscape Arch. N/AMEP Engineer Michael WimmerStructural Engr. N/AGeneral Contractor TBDPlumbing TBD
TIMELINE Mechanical TBDA/E Selection 06/2018 Fire Protection TBDDesign Report 02/2019 Electrical TBDBid Date 07/2019Start Construction 08/2019Substantial Completion 12/2019 AREA DATA
GSF 9,500ASF 7,050Efficiency 74.21%Construction $/GSF N/ATotal Project $/GSF N/A
UW-Managed
This project will renovate the entire fourth floor of the Educational Sciences Building, replacing an outdated layout and infrastructure with workspaces that meet the current needs of the Wisconsin Center for Education Research (WCER) with the goal of creating a mix of open work and activity areas, including conference rooms and private offices on the floor.
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 39
NANCY NICHOLAS HALL/EMBER HALL ALTERATION MSN# 0085-1804
BUDGET KEY STAKEHOLDERSTotal Soft Costs $181,155 Occupants School of Human EcologyTotal Construction Costs $633,000 User Reps Linda ZwickerTotal Project Costs $814,155 UW PM Angie Bollinger
DFDM PM N/AFunding Sources: A/E N/AGifts & Grants $814,155 Structural Engr. HGA
General Contractor TBDPlumbing TBDMechanical TBDFire Protection TBD
TIMELINE Electrical TBDA/E Selection 01/2019Design Report 06/2019 AREA DATABid Date 11/2019 GSF 2,100Start Construction 12/2019 ASF 2,100Substantial Completion 08/2020 Efficiency 100%
Construction $/GSF $301Total Project $/GSF $388
UW-Managed
This project will renovate approximately 2,100 SF on the second floor of the Nancy Nicholas Hall in the School of Human Ecology (SoHE) building. The project will create a new flexible multipurpose space for student innovation, collaboration, group ideation and design thinking replacing an under-utilized student organization/storage space and relocation a DoIT Print Shop area.
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 40
ENGINEERING CENTERS NEW LAB RENOVATION MSN# 0481-1809
BUDGET KEY STAKEHOLDERSTotal Soft Costs $246,000 Occupants College of EngineeringTotal Construction Costs $1,754,000 User Reps Peter NemmetzTotal Project Costs $2,000,000 UW PM Peter Bloechl-Anderson
DFDM PM TBDFunding Sources: A/E ContinuumGifts & Grants $2,301,000 Structural Engr. TBD
General Contractor TBDPlumbing TBDMechanical TBDFire Protection TBD
TIMELINE Electrical TBDA/E Selection 12/2018Design Report 04/2019 AREA DATABid Date 06/2019 GSF 3,916Start Construction 08/2019 ASF TBDSubstantial Completion 02/2020 Efficiency TBD
Construction $/GSF $400Total Project $/GSF TBD
This project seeks to renovate space within the Engineering Centers Building. Within ECB, laboratory space is greatly needed to support growth within the undergraduate majors. By creating a new Design Laboratory for Biological, Chemical Studies, and Biomedical Engineering, College of Engineering faculty will be able to increase their ability to enhance the learning experience for staff and students. Since all interior elements within the existing space have been removed, the new Design Laboratory will require infrastructure for sinks, fume hoods, biosafety cabinets, compressed air and nitrogen, and snorkel vents.
UW-Managed
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 41
ENGINEERING HALL PLAZA & ENTRANCE RENOVATION MSN # 0408-1704
BUDGET KEY STAKEHOLDERSTotal Soft Costs $50,815 Occupants College of EngineeringTotal Construction Costs $1,375,000 User Reps Barbara McPhersonTotal Project Costs $1,425,815 UW PM Peter Bloechl-Anderson
A/E AssemblageFunding Sources: Design Arch. TBDGifts & Grants $1,425,815 Landscape Arch. TBD
Structural Engr. TBDGeneral Contractor Fox ArnesonPlumbing TBDMechanical TBDFire Protection TBDElectrical TBD
TIMELINEA/E Selection 07/2018 AREA DATADesign Report 09/2018 GSF TBDBid Date 01/2019 ASF TBDStart Construction 06/2019 Efficiency TBDProject Close-Out 11/2019 Construction $/GSF TBD
Total Project $/GSF TBD
UW-Managed
This project creates a more prominent and accessible entrance on the north side of the building, creates a new vestibule and entrance into the center of the building, and enhances the exterior plaza space. This project will enhance building accessibility, functionality, and aesthetics.
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 42
FIELD HOUSE EXTERIOR RESTORATION 18L3F
BUDGET KEY STAKEHOLDERSTotal Soft Costs $308,000 Occupants Barry FoxTotal Construction Costs $2,687,000 User Reps TBDTotal Project Costs $2,995,000 UW PM Peter Bloechl-Anderson
DFDM PM Tim Luttrell Funding Sources: A/E BSAAGFO $1,232,127 Structural Engr. TBD
General Contractor TBDPlumbing TBDMechanical TBDFire Protection TBD
TIMELINE Electrical TBDA/E Selection 11/2015Design Report 10/2017 AREA DATABid Date 11/2019 GSF TBDStart Construction 02/2020 ASF TBDSubstantial Completion 08/2020 Efficiency TBD
Construction $/GSF TBDTotal Project $/GSF TBD
This project provides investigation and research, pre-design, and design services to rehabilitate or replace the Field House exterior windows. The exterior envelope will be evaluated to identify deficiencies, develop design solution alternatives, and recommend appropriate corrective measures. The design solution alternatives developed under this project will be in accordance with the State of Wisconsin Historical Society's guidelines for registered buildings in a historical district.
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 43
FIELD HOUSE SOUTH PLAZA REDEVELOPMENT 18E1C
BUDGET KEY STAKEHOLDERSTotal Soft Costs TBD Occupants Barry FoxTotal Construction Costs TBD User Reps TBDTotal Project Costs $1,826,000 UW PM Peter Bloechl-Anderson
DFDM PM Tim Luttrell Funding Sources: A/E BSAAGFO $188,000 Structural Engr. TBD
General Contractor TBDPlumbing TBDMechanical TBDFire Protection TBD
TIMELINE Electrical TBDA/E Selection 06/2018Design Report TBD AREA DATABid Date 11/2019 GSF TBDStart Construction 02/2020 ASF TBDSubstantial Completion 08/2020 Efficiency TBD
Construction $/GSF TBDTotal Project $/GSF TBD
The scope of work involves the removal and replacement of the retaining wall at the southeast corner of the Field House. The current wall requires repairs and will be rebuilt to have better drainage behind the wall, be more structurally sound and upgrade the aesthetics of the area. Paving to the east, south and at the southwest corner of the Field House, out to the back of curb along Monroe Street, Little Street and Regent Street will be removed and replaced. The entire area to the south of the Field House will be removed, including the stairs, and reconfigured to create a more functional space and upgrade the look and feel of the area to better celebrate the approach to the historic Field House.
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 44
HELEN C. WHITE RESTROOM UPGRADES MSN # 0018-1803
BUDGET KEY STAKEHOLDERSTotal Soft Costs $249,500 Occupants General Library SystemTotal Construction Costs $860,500 User Reps Carrie KruseTotal Project Costs $1,110,000 UW PM Megan McBride
DFDM PM N/AFunding Sources: A/E HGAGifts & Grants $1,110,000 Design Arch. N/A
Landscape Arch. N/AStructural Engr. N/AGeneral Contractor Advanced Building Corp.Plumbing HJ PertzbornMechanical Universal Power & Systems
TIMELINE Fire Protection N/AA/E Selection 03/2018 Electrical 1901, Inc.Design Report 09/2018Bid Date 01/2019Construction 02/2019 AREA DATASubstantial Completion 09/2019 GSF 3,750
ASF 3,000Efficiency 80.00%Construction $/GSF $297Total Project $/GSF $296
UW-Managed
This project will bring College Library restrooms up to current code requirements by providing toilet and lavatory counts that reflect current occupancy. The roughly 1500 SF of restrooms on the first three floors of Helen C. White Hall were constructed in 1968 and are no longer adequate for faculty, staff, students, and patrons that visit the library.
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 45
LIMNOLOGY LIFT STATION & FM 16B1C
BUDGET KEY STAKEHOLDERSTotal Soft Costs $115,000 Occupants UW PlumbingTotal Construction Costs $733,000 User Reps Marcella OtterTotal Project Costs $848,000 UW PM Brandon Braithwaite
DFDM PM Kris AndersonFunding Sources: A/E Ayres AssociatesGFSB $584,400 Design Arch. N/AAgency Cash $262,600 Landscape Arch. N/A
Structural Engr. N/AGeneral Contractor Terra EngineeringPlumbing TBDMechanical Hooper Corporation
TIMELINE Fire Protection TBDA/E Selection 03/2016 Electrical TBDDesign Report 12/2017Bid Date 04/2019 AREA DATAStart Construction 06/2019 GSF N/AProject Close-Out 12/2019 ASF N/A
Efficiency N/AConstruction $/GSF N/ATotal Project $/GSF N/A
This project will replace the existing sanitary sewer lift station in the lower level of the Limnology Building and replace the associated four-inch force main and the adjacent four-inch domestic water service to the building and the adjacent Water Science and Engineering Laboratory.
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 46
LOT 76 SANITARY LIFT STATION 12A1E
BUDGET KEY STAKEHOLDERSTotal Soft Costs $465,000 Occupants West CampusTotal Construction Costs $1,931,000 User Reps Marcella OtterTotal Project Costs $2,396,000 UW PM Brandon Braithwaite
DFDM PM Kathy KalscheurA/E Strand Associates
Funding Sources: Design Arch. Strand AssociatesGFSB $1,262,863 Landscape Arch. N/AAgency Cash $365,004 Structural Engr. Strand AssociatesAGFO/Other $768,133 General Contractor Miron Construction
Plumbing JCIMechanical 1901
TIMELINE Fire Protection N/AA/E Selection 03/2012 Electrical Forward ElectricDesign Report 03/2014Bid Date 06/2017 AREA DATAStart Construction 08/2017 GSF 850Substantial Completion 04/2020 ASF N/A
Efficiency N/AConstruction $/GSF $2,272Total Project $/GSF $2,818
This project is funded entirely by program revenue and consists of renovating the existing main sanitary lift station that serves buildings on the far west side of campus. This lift station has not seen a major renovation since its construction in 1966 and most of its major components are beyond their designed service life. The renovation work upgraded the entire station including the existing pumps, valves, and other mechanical and electrical components. The renovation also corrected the existing problems with rainwater seeping into the lift station. This project has been substantially completed.
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 47
LOTS 129 & 130 RECONSTRUCTION 17H2H
BUDGET KEY STAKEHOLDERSTotal Soft Costs $147,400 Occupants Transportation ServicesTotal Construction Costs $622,600 User Reps Patrick KassTotal Project Costs $770,000 UW PM Mike Zimmerman
DFDM PM Ed KeaslerFunding Sources: A/E Zach FreemanCash $770,000 Design Arch. N/A
Landscape Arch. Rebecca de BoerStructural Engr. N/AGeneral Contractor Cliff KoutnikPlumbing N/AMechanical N/A
TIMELINE Fire Protection N/AA/E Selection 10/2017 Electrical Brett ParpartDesign Report 09/2018Bid Date 04/2019Start Construction 07/2019 AREA DATASubstantial Completion 12/2019 GSF N/A
ASF N/AEfficiency N/AConstruction $/GSF N/ATotal Project $/GSF N/A
This project reconstructs and expands Lot 130 from 93 to 100 stalls and converts Lot 129 (28 stalls) into a vegetated area.
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 48
MATERIALS SCIENCE FUME HOOD REPLACEMENTS MSN# 0520-1805
BUDGET KEY STAKEHOLDERSTotal Soft Costs $138,000 Occupants College of EngineeringTotal Construction Costs $719,000 User Reps Peter NemmetzTotal Project Costs $857,000 UW PM Peter Bloechl-Anderson
DFDM PM TBDFunding Sources: A/E ContinuumGifts & Grants TBD Structural Engr. TBD
General Contractor TBDPlumbing TBDMechanical TBDFire Protection TBD
TIMELINE Electrical TBDA/E Selection 12/2018Design Report 04/2019 AREA DATABid Date 07/2019 GSF 1,401Start Construciton 08/2019 ASF TBDSubstantial Completion 02/2020 Efficiency TBD
Construction $/GSF $374Total Project $/GSF TBD
This project will remodel and add additional fume hoods to the 105 suite in the Materials Science & Engineering Building: remodel Room 105E as a research lab which requires the addition of four fume hoods, updated cabinetry, flooring, and supporting infrastructure; install an additional fume hood in Room 105D; and replace the existing, aging fume hood with a new model in Room 105C.
UW-Managed
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 49
MCCLIMON SOCCER TURF REPLACEMENT MSN# 0040-1801
BUDGET KEY STAKEHOLDERSTotal Soft Costs $39,000 Occupants AthleticsTotal Construction Costs $311,000 User Reps Barry FoxTotal Project Costs $350,000 UW PM Brandon Braithwaite
DFDM PM N/AFunding Sources: A/E SmithgroupGifts & Grants $350,000 Structural Engr. N/A
General Contractor TBDPlumbing TBDMechanical TBDFire Protection TBDElectrical TBD
TIMELINE Fire Protection N/AA/E Selection 12/2018Design Report 04/2019Bid Date 07/2019 AREA DATAStart Construction 08/2019 GSF TBDProject Close-Out 02/2020 ASF TBD
Efficiency TBDConstruction $/GSF TBDTotal Project $/GSF TBD
The project consisted of removing roughly 9,700 SY of existing turf grass field, laser fine grading and laying bluegrass sod at the Division of Intercollegiate Athletics’ soccer game field located inside McClimon complex. This project has been substantially completed.
UW-Managed
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 50
MEMORIAL LIBRARY UW PRESS REMODEL MSN #0015-1706
BUDGET KEY STAKEHOLDERSTotal Soft Costs $744,500 Occupants Vice Chan. for ResearchTotal Construction Costs $679,500 and Graduate EducationTotal Project Costs $1,424,000 General Library System
User Reps Alex JohnsonFunding Sources: UW PM Ann HayesGifts & Grants $1,424,000 DFDM PM N/A
A/E HGADesign Arch. Kevin AllebachLandscape Arch. N/AStructural Engr. N/A
TIMELINE General Contractor ABCA/E Selection 07/2018 Plumbing N/ADesign Report 08/2017 Mechanical 1901 Inc.Bid Date 01/2019 Fire Protection 1901 Inc.Start Construction 02/2019 Electrical Universal Power&SystemsSubstantial Completion 08/2019
AREA DATAGSF 29,508ASF 23,800Efficiency 80.66%Construction $/GSF $30Total Project $/GSF $48
UW-Managed
This project renovates portions of Memorial Library to consolidate current library staff which, in turn, provides renovated space for the staff of UW Press which is currently in off-campus leased space. The renovation will occur on portions of the third and fourth levels of the library and will be completed in three phases to minimize disruption to the library staff and patrons. The project will provide new finishes and workstations for staff, along with the required updates to mechanical, electrical, IT, fire alarm, and lighting systems.
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 51
MSC REMODEL FOR CHEMISTRY LEARNING CENTER MSN# 0450-1802
BUDGET KEY STAKEHOLDERSTotal Soft Costs $283,660 Occupants Chemistry Learning CenterTotal Construction Costs $1,016,340 User Reps Tony JacobTotal Project Costs $1,300,000 UW PM Bo Muwahid
DFDM PM N/AFunding Sources: A/E Aro EbeleGifts & Grants $1,300,000 Structural Engr. TBD
General Contractor TBDPlumbing TBDMechanical TBDFire Protection TBD
TIMELINE Electrical TBDA/E Selection 08/2018Design Report 02/2019 AREA DATABid Date 08/2019 GSF 4,900Start Construction 09/2019 ASF 4,600Substantial Completion 03/2020 Efficiency 93.88%
Construction $/GSF $232Total Project $/GSF $265
This project remodels space on the fourth floor of the Medical Sciences Center (MSC) building. Currently, the Chemistry Learning Center (CLC) is housed in the Daniels building on campus. The renovation of Daniels will begin in the Fall of 2020 and CLC will need to relocate prior to the start of that renovation. This project will create small flexible use classrooms and office space for CLC.
UW-Managed
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 52
PRIMATE CENTER BACKUP GENERATOR MSN #0526-1703
BUDGET KEY STAKEHOLDERSTotal Soft Costs $162,000 Occupants Graduate SchoolTotal Construction Costs $1,038,000 User Reps Bruce PapeTotal Project Costs $1,200,000 UW PM Bo Muwahid
DFDM PM N/AFunding Sources: A/E Mead & HuntGifts & Grants $1,200,000 Design Arch. Mead & Hunt
Landscape Arch. N/AStructural Engr. Mead & HuntGeneral Contractor TBDPlumbing TBD
TIMELINE Mechanical TBDA/E Selection 02/2018 Fire Protection TBDDesign Report 10/2018 Electrical TBDBid Date 09/2019Start Construction 11/2019 AREA DATASubstantial Completion 05/2020 GSF 500
ASF TBDEfficiency TBDConstruction $/GSF $2,266Total Project $/GSF $2,400
UW-Managed
This project, located at the Primate Center, will upgrade electrical systems and install a backup generator. A new electrical vault will be built over the existing electrical vault on the north side of the building.
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 53
UNIVERSITY HOUSES ROOF REPLACEMENT 18A2A
BUDGET KEY STAKEHOLDERSTotal Soft Costs $173,900 Occupants UW HousingTotal Construction Costs TBD User Reps Jeff KeatingTotal Project Costs TBD UW PM Peter Bloechl-Anderson
DFDM PM Evan Quilling Funding Sources: A/E Assemblage ArchitectsGifts & Grants TBD Structural Engr. TBDAGFO $173,900 General Contractor TBD
Plumbing TBDMechanical TBDFire Protection TBD
TIMELINE Electrical TBDA/E Selection 03/2018Design Report TBD AREA DATABid Date 09/2019 GSF TBDStart Construction 10/2019 ASF TBDProject Close-Out 10/2020 Efficiency TBD
Construction $/GSF TBDTotal Project $/GSF TBD
This project replaces damaged clay tile roofing and associated roofing components. Project work includes complete removal and disposal of damaged clay tile roofing system down to the structural deck; removal, replacement and re-use (where applicable) of metal gutter and fascia; and installation of the new roofing system and associated components.
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 54
Capital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin - Madison
Completed ProjectsProjects that have finished construction and reached occupancy during 2018 and 2019
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 55
445 HENRY MALL REMODEL FOR OSC MSN #0102-1706
BUDGET KEY STAKEHOLDERSTotal Soft Costs $205,000 Occupants Strategic Consulting OfficeTotal Construction Costs $605,000 User Reps Jenny FaustTotal Project Costs $810,000 UW PM Bo Muwahid
A/E Aro EberleFunding Sources: Structural Engr. N/AGifts & Grants $810,000 General Contractor Fox Arneson
Plumbing 1901Mechanical 1901Fire Protection TBDElectrical Electric Construction Inc.
TIMELINEA/E Selection 03/2018Design Report 04/2018 - 5/1/2018 AREA DATABid Date 07/2018-09/2018 GSF 4,030Construction 10/2018 ASF 3,801Substantial Completion 03/2019 Efficiency 94.32%
Construction $/GSF $164Total Project $/GSF $201
This project includes renovating 3,801 ASF / 4,030 GSF of the fourth floor of 445 Henry Mall for the Office of Strategic Consulting (OSC). OSC is currently housed in another building on campus and the new space will create a contiguous area for recently merged divisions. In addition to the office space, a shared common area will be created that includes a breakroom and a conference room.
UW-Managed
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 56
CHAMBERLIN 5TH FLOOR REMODEL FOR KOLKOWITZ LAB MSN #0055-1703
BUDGET KEY STAKEHOLDERSTotal Soft Costs $85,900 Occupants Physics DepartmentTotal Construction Costs $629,100 User Reps Shimon KolkowitzTotal Project Costs $715,000 UW PM Bo Muwahid
DFDM PM N/AFunding Sources: A/E Assemblage ArchitectsGifts & Grants $715,000 Design Arch. Assemblage Architects
Landscape Arch. N/AStructural Engr. N/AGeneral Contractor Advanced Building Corp.Plumbing Hooper Corp.Mechanical 1901
TIMELINE Fire Protection Hooper Corp.A/E Selection 08/2017 Electrical Universal Power SystemsDesign Report 09/2017Bid Date 04/2018Construction 06/2018 AREA DATASubstantial Completion 02/2019 GSF 1,300
ASF 1,200Efficiency 92.31%Construction $/GSF $528Total Project $/GSF $550
This project takes existing student office space and converts it into two laboratories for a new faculty member. The labs will implement a dedicated air handler, as the two new labs will have strict temperature and relative humidity controls.
UW-Managed
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 57
ELM DRIVE LIFT STATION 15B1Z
BUDGET KEY STAKEHOLDERSTotal Soft Costs $139,200.00 Occupants Bldgs in Elm Drive AreaTotal Construction Costs $883,300.00 User Reps Marcella OtterTotal Project Costs $1,022,500.00 UW PM Brandon Braithwaite
DFDM PM Sally ShumakerFunding Sources: A/E Strand AssociatesGFSB $1,022,500 Design Arch. Strand Associates
Landscape Arch. N/AStructural Engr. Strand AssociatesGeneral Contractor Speedway S&GPlumbing TBDMechanical TBD
TIMELINE Fire Protection TBDA/E Selection 04/2015 Electrical Pieper Electric Inc.Design Report 10/2016Bid Date 10/2017Construction 11/2017 AREA DATASubstantial Completion 11/2018 GSF N/A
ASF N/AEfficiency N/AConstruction $/GSF N/ATotal Project $/GSF N/A
The Elm Drive Lift Station Rehabilitation will create a new pumping station adjacent to the existing pumping station at Elm Drive. The project will include a steel drywell with cathodic protection, electrical controls, dual centrifugal pumps, new suction piping, new discharge piping to the existing force main, HVAC system meeting current controls, new power supply and backup power from Dejope Hall, a new wet well manhole, excavation, sheeting, dewatering, backfill, restoration, and landscaping. The construction of a new station allows the existing pumping station to stay online until the new station is tested; therefore, avoiding bypass pumping.
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 58
GRAINGER LEARNING COMMONS MSN #0140-1604
BUDGET KEY STAKEHOLDERSTotal $10,070,000 Occupants School of BusinessConstruction $6,700,000 User Reps Becky BarnesDesign $540,000 UW PM Megan McBrideMgt. $240,000 A/E Potter LawsonContingency $670,000 Design Arch. Meyer, Scherer & RockcastleEquipment $1,800,000 Landscape Arch. N/AOther Fees - Structural Engr. Henneman Engineering, Inc.
General Contractor MironFunding Sources: Plumbing HJ PertzbornGifts & Grants $10,070,000 Mechanical A&H
Fire Protection Automatic Fire SystemTIMELINE Electrical Staff ElectricA/E Selection 09/201610% Concept Report 12/201625% Design Report 02/2017 AREA DATAConstruction Documents 02/2017 GSF 34,700Bid Date 08/2017 ASF 28,000Construction 08/2017 Efficiency 80.69%Substantial Completion 05/2018 Construction $/GSF $193
Total Project $/GSF $290
UW-Managed
This project remodelled 34,700 GSF / 28,000 ASF across three floors of library, classroom, and computer lab space within the existing School of Business. The three-floor remodel updated the library to meet the needs of current students, faculty, staff, and the campus community; improve the functionality and visibility of the Business Learning Center (BLC); and add a technology-rich Special Projects Lab (SPL) within the first floor Huber Lab.
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 59
GOODMAN SOFTBALL LOCKER ROOM REMODEL MSN #0175-1701
BUDGET KEY STAKEHOLDERSTotal Soft Costs $253,720 Occupants UW AthleticsTotal Construction Costs $718,280 User Reps Barry FoxTotal Project Costs $972,000 UW PM Matt Collins
A/E Berners-SchoberFunding Sources: Design Arch. Berners-SchoberGifts & Grants $972,000 Landscape Arch. N/A
Structural Engr. N/AGeneral Contractor JP CullenPlumbing HJ PertzbornMechanical Prime Mechanical of WIFire Protection N/A
TIMELINE Electrical Staff ElectricA/E Selection 08/2017Design Report 09/2017 - 04/2018 AREA DATABid Date 06/2018 GSF 3,443Construction 08/2018 ASF 2,000Substantial Completion 01/2019 Efficiency 58.09%
Construction $/GSF $224Total Project $/GSF $282
This project will remodel and expand the home locker room, coaches’ locker room, and sports medicine areas. The existing women’s home locker room at the Goodman Softball Complex is very tight and the lockers are not sufficiently large enough to accommodate the players’ clothes and materials. The existing showers allow for only eight users at a time. In addition, the coaches share their locker and dressing space with the sports medicine area. The existing spaces have not been updated in many years except for routine painting.
UW-Managed
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 60
HSLC ACADEMIC AFFAIRS CURRICULUM ENHANCEMENT PROJECT MSN #1480-1604
BUDGET KEY STAKEHOLDERSTotal Soft Costs $6,141,955 Occupants SMPHTotal Construction Costs $9,883,309 User Reps Mark WellsTotal Project Costs $16,025,264 UW PM Peter Bloechl-Anderson
A/E OPNFunding Sources: Design Arch. SLAMGifts & Grants $16,025,264 Landscape Arch. N/A
Structural Engr. GRAEF-USA Inc.TIMELINE General Contractor JP CullenA/E Selection 10/2016 Plumbing Hooper Corp.Design Report 12/2016 Mechanical J.F. AhernBid Date 04/2017 Fire Protection H.J. PertzbornStart Construction 06/2017 Electrical WestphalSubstantial Completion 08/2018
AREA DATAGSF 140,000ASF 80,000Efficiency 57.14%Construction $/GSF $78Total Project $/GSF $114
The project renovated approximately 140,000 GSF / 80,000 ASF of floors 1, 2, 3 and 4 of Health Sciences Learning Center to enhance the Academic Affair’s teaching, administrative, and public space. All of the spaces were designed as one project with a cohesive aesthetic. The project also included space for a quiet student study lounge and renovation of strategic office spaces including Multicultural Affairs and the Native American Center for Health Professions, along with conference room upgrades.
UW-Managed
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 61
INGRAHAM 115-116 & 214-215 RENOVATION 16F2E
BUDGET KEY STAKEHOLDERSTotal Soft Costs $153,600 Occupants SMO General AssignmentTotal Construction Costs $668,400 User Reps N/ATotal Project Costs $822,000 UW PM Peter Bloechl-Anderson
DFDM PM Russ Van GilderFunding Sources: A/E AroEberleGFSB $412,000 Design Arch. Michael EberleAGFO $410,000 Landscape Arch. N/A
Structural Engr. N/AGeneral Contractor TBDPlumbing TBDMechanical Prime Mechanical of WIFire Protection TBD
TIMELINE Electrical Westphal & Co, Inc.A/E Selection 08/2017Design Report 10/2017 AREA DATABid Date 05/2018 GSF 2,603Construction 07/2018 ASF N/ASubstantial Completion 12/2018 Efficiency N/A
Construction $/GSF $279Total Project $/GSF $316
This project will plan, design and construct two general assignments, collaborative learning classrooms, creating it from four existing general assignment classrooms on the first floor of Ingraham Hall.
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 62
JOHNSON STREET STEAM/CONDENSATE RENOVATION 16E1D
BUDGET KEY STAKEHOLDERSTotal Soft Costs $1,071,000 Occupants FP&M Physical PlantTotal Construction Costs $3,740,000 UW PM Jeff PolleiTotal Project Costs $4,811,000 DFDM PM Michael Hanson
A/E Ring & DuChateau, LLPFunding Sources: Civil Engr. Ayres AssociatesGFSB $3,319,600 Structural Engr. Bloom Companies, LLCPRSB $1,491,400 General Contractor Terra Engineering
Mechanical 1901 Inc.Electrical Forward Electric, Inc.
TIMELINE AREA DATAA/E Selection 12/2016 GSF N/ADesign Report N/A ASF N/ABid Date 06/2018 Efficiency N/AStart Construction 07/2019 Construction $/GSF N/ASubstantial Completion 05/2019 Total Project $/GSF N/A
The work consists of replacing steam pits 17/11 and 120 LF of concrete box conduit with an accessible utility tunnel from steam pit 17/11 to the north terminating at a location suitable for connection to the Chemistry Building Addition and Renovation project currently under construction. The utility tunnel work includes replacement of the 18-inch HPS, 20-inch LPS, 8-inch PCR, and 3-inch CA piping, insulation, and supporting system. The 18-inch HPS will be increased in size to 20-inch HPS.
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 63
LELAH STARKS POTATO BUILDING 14L2V
BUDGET KEY STAKEHOLDERSTotal Soft Costs $49,000 Occupants CALSTotal Construction Costs $344,800 User Reps Doug SabatkeTotal Project Costs $393,800 UW PM Matt Collins
DFDM PM Evan QuillingFunding Sources: A/E Jewell Associates EngineersAgency Cash $393,800 Design Arch. N/A
Landscape Arch. N/AStructural Engr. N/AGeneral Contractor Altmann ConstructionPlumbing N/AMechanical Hengel Bros.
TIMELINE Fire Protection N/AA/E Selection 02/2015 Electrical Pieper Electric35% Design Report 04/2015Bid Date 01/2017 AREA DATAConstruction 04/2018 GSF 3,500Substantial Completion 08/2018 ASF 3,342
Efficiency 95.50%Construction $/GSF $107Total Project $/GSF $113
The project will construct a 3,500 SF addition to the existing potato building on the Lelah Starks Farm. The new addition will function as a potato grading and sorting area. The addition will be metal framed and sided with concrete foundations and flooring. A masonry fire separation wall will be constructed between the new and existing buildings. Three overhead doors will be provided for farm equipment access. The building is to be insulated and minimal heating will be provided. Electrical and plumbing work will be included to facilitate grading and sorting operations.
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 64
McCLIMON TRACK REPLACEMENT MSN #0040-1601
KEY STAKEHOLDERSTotal Soft Costs $62,600 Occupants Athletic DepartmentTotal Construction Costs $771,700 User Reps Barry FoxTotal Project Costs $834,300 UW PM Matt Collins
DFDM PM N/AFunding Sources: A/E Rettler AssociatesGift $834,300 Design Arch. John Kneer
Landscape Arch. TBDStructural Engr. TBDGeneral Contractor Beynon SportsPlumbing TBDMechanical TBD
TIMELINE Fire Protection TBDA/E Selection 10/2016 Electrical TBDDesign Report 01/2017Bid Date 05/2018 AREA DATAConstruction 06/2018 GSF N/ASubstantial Completion 07/2018 ASF N/A
Efficiency N/AConstruction $/GSF N/ATotal Project $/GSF N/A
UW-Managed
This project resurfaces the McClimon 400M outdoor track and adjacent field event areas, and surfaces the practice throw area and javelin runway.
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 65
NIELSEN TENNIS STADIUM INDOOR COURT RESURFACE MSN #0038-1601
BUDGET KEY STAKEHOLDERSTotal $2,136,120 Occupants UW AthleticsConstruction $1,729,445 User Reps Barry FoxDesign $174,920 UW PM Matt CollinsMgt. $67,200 DFDM PM N/AContingency $164,555 A/E Edge ConsultingEquipment - Design Arch. N/AOther Fees - Landscape Arch. N/AFunding Sources: Structural Engr. N/AGifts & Grants $2,136,120 GC Indoor Armstrong
GC Outdoor TBDTIMELINE Plumbing N/AIndoor Mechanical N/AA/E Selection 01/2017 Fire Protection N/AConstruction Documents 02/2017 - 05/2017 Electrical N/ABid Date 05/2017Construction 08/2017 - 09/2017 AREA DATAOccupancy 09/2017 GSF N/AOutdoor ASF N/A35% Design Report 10/2017 - 01/2018 Efficiency N/AConstruction Documents 02/2018 - 04/2018 Construction $/GSF N/ABid Date 04/2018 Total Project $/GSF N/AConstruction 5/2018 - 08/2018Substantial Completion 09/2018
This project resurfaces the indoor tennis courts and expands the outdoor space from six to eight courts on the north side of the stadium adjacent to the existing outdoor courts. It also improves spectator experience by adding a sound system, LED court lighting that meets NCAA standards, individual scoreboards for the center six courts, and spectator seating for about 600 people.
UW-Managed
30 North Mills St. ◦ Madison, WI 53715 ◦ (608) 263-3000 ◦ www.cpd.fpm.wisc.edu/
Current ReportCapital Planning & DevelopmentFacilities Planning & ManagementUniversity of Wisconsin-Madison
2019 4QPage 66
STERLING HALL RENOVATION FOR TREX PLASMA PHYSICS MSN #0057-1701
BUDGET KEY STAKEHOLDERSTotal Soft Costs $65,995 Occupants Physics DepartmentTotal Construction Costs $497,005 User Reps John WallaceTotal Project Costs $563,000 UW PM Bo Muwahid
DFDM PM N/AFunding Sources: A/E KEE ArchitectureGifts & Grants $563,000 Design Arch. KEE Architecture
Landscape Arch. N/AStructural Engr. RA Smith National, Inc.General Contractor Advanced Building Corp.Plumbing UW DDCMechanical Prime Mechanical
TIMELINE Fire Protection Hooper Corp.A/E Selection 06/2017 Electrical Electric Construction Inc.Design Report 02/2018Bid Date 06/2018Start Construction 07/2018 AREA DATAProject Close-Out 03/2019 GSF 3,000
ASF 2,900Efficiency 96.67%Construction $/GSF $166Total Project $/GSF $22
This project will make some building modifications to accommodate the Terrestrial Reconnection Experiment (TREX). Modifications include remodeling of the space on the second floor above the Plasma Dynamo Experiment (MPDX) to be used for assembly and storage of TREX equipment. An opening in the existing second-floor structure will be created to allow the TREX assembled components to be lowered into the MPDX. A crane will need to be hung from the ex