World Bank transport program in Vietnam

11
T T R R A A N N S S P P O O R R T T World Bank transport program in Vietnam Transport Sector World Bank, Hanoi, Vietnam

description

World Bank transport program in Vietnam. Transport Sector World Bank, Hanoi, Vietnam. Transport program in Vietnam. Overview Changing Program Objectives Present status of program Future directions. Overview. Why transport? - PowerPoint PPT Presentation

Transcript of World Bank transport program in Vietnam

Page 1: World Bank transport program in Vietnam

TTRRAANNSSPPOORRTT

World Bank transport program in Vietnam

Transport Sector

World Bank, Hanoi, Vietnam

Page 2: World Bank transport program in Vietnam

TTRRAANNSSPPOORRTT

Transport program in Vietnam

• Overview• Changing Program

Objectives• Present status of

program• Future directions

Page 3: World Bank transport program in Vietnam

TTRRAANNSSPPOORRTT

Overview

• Why transport? – Key issue for foreign investors: Poor Quality and Lack of Capacity of

Transport Infrastructure– Poverty Reduction: Improvements to rural infrastructure have directly

reduced poverty– Economic Growth: High levels of public investments required to

support rapid growth • The Program.

– Program is about $1 billion of projects under implementation and $ 1 billion of projects under preparation

– The program is growing and Vietnam is the only country in EAP where Bank budgets are increasing

– Vietnam is moving from IDA to IBRD status as a result the WB is increasing its support to large scale infrastructure projects

Page 4: World Bank transport program in Vietnam

TTRRAANNSSPPOORRTT

Changing Program Objectives

• Reconnection– In the ’90s projects supported the need to reinstate the

main transport links, particularly national roads. This work is largely completed.

• Integration– The focus of projects started to move beyond

‘emergency works’ towards building sustainable transport networks. This work is still ongoing.

• Expansion– With over 10 years of high growth, the capacity of the

transport network is inadequate.

Page 5: World Bank transport program in Vietnam

TTRRAANNSSPPOORRTT

5

Projects under Implementation

Project Approved Closing AgeIDA

approved (US$m)

Current Amount (US$m)

Disbursed to date [1]

(US$m)

Percentage disbursed

(%)

Mekong Transport & Flood Protection

FY01 12/10 8.5 110 132 117 86.22

MTFP Addit’l Financing

FY07 12/10 2 25 25 18.3 29.02

Road Network Improvement

FY04 09/10 5.5 225 241 105.8 42.91

Road Safety FY05 06/11 4.3 32 32 5.1 15.44

Rural Transport III FY06 12/11 3.5 106 114 27.8 23.85

Mekong Delta Transport Infrastructure Development

FY07 12/13 2.3 207 211 9.1 4.19

Hanoi Urban Transport

FY08 12/13 2.0 155 156 7.2 4.48

Northern Delta Transport Development Project

FY08 6/14 1.0 170 164 -- --

[1] AS of January15, 2010

Page 6: World Bank transport program in Vietnam

TTRRAANNSSPPOORRTT

Projects under implementation

• Issues:– WB program suffers from slow disbursement progress.– Disbursements are low for up to 2 years on approval.

There is a need for the identification of funding, and the timely preparation of projects.

– Provincial projects are increasingly decentralized which increases the complexity and capacity building is key

– According to WB guidelines we cannot use dependent SOE consultants and contractors. Therefore we need to work closely with the emerging private sector and capacity building is key.

– Most projects require substantial resettlement activity which is expensive and time consuming

Page 7: World Bank transport program in Vietnam

TTRRAANNSSPPOORRTT

Projects under preparation

• Road Network Improvement Project (Additional Financing) (FY11) – US$ 230m

• Da Nang-Quang Ngai Expressway (FY11) – IBRD US$500m/IDA US$70m: First transport IDA/IBRD blended operation.

• Haiphong Urban Transport (FY11) - US$150-175 m

• Third Rural Transport AF (FY11) – US$50m

• Project Preparation Facility (FY10) – US$75m

Page 8: World Bank transport program in Vietnam

TTRRAANNSSPPOORRTT

Projects under preparation

• Issues:– WB used to prepare projects using PHRD grant but

this is no longer available– All preparation work is government executed typically

using government and/or grant finance– Limitations of existing institutional and capacity terms

of identifying, planning, and implementing projects.– Institutional arrangements to bring together planning,

implementation, and operation of assets needs to be improved

– Need to widen sources of funding, possibilities for PPP type arrangements in transport projects

Page 9: World Bank transport program in Vietnam

TTRRAANNSSPPOORRTT

Policy and Strategy work

Bank Budget • Vietnam Expressway Investment Strategy – implementation to commence

in FY10• Infrastructure finance – Looks at different financing options, in particular

PPP, for infrastructure development

Infrastructure for Growth Trust Fund (AusAID) • State-Owned Enterprise and Construction Industry Review (US$125,000) • Preparation work for Danang to Quang Ngai Expressway (US$350,000)• Monitoring and evaluation study for two multi-modal transport projects

(US$100,000)• International Road Assessment Program (iRAP Vietnam) (US$ 400,000)• Urban Transport in Medium Cities (US$150,000)

Page 10: World Bank transport program in Vietnam

TTRRAANNSSPPOORRTT

Policy and strategy work

Infrastructure Policy & Sector Support Trust Fund (DFID)

• Rural Transport Support – US$250,000

• Transport Sector Support – US$300,000

• Infrastructure policy and research activities – US$275,000

Page 11: World Bank transport program in Vietnam

TTRRAANNSSPPOORRTT

Thank you!