WILLITON PAVILION PROJECT
PARISH ASSEMBLY 2015
1
WILLITON PAVILION PROJECT
MEMORIAL GROUND SITE PLAN
2
WILLITON PAVILION PROJECT
PAVILION GROUND FLOOR PLAN
3
WILLITON PAVILION PROJECT
MEMORIAL 1st FLOOR PLAN
4
WILLITON PAVILION PROJECT
PAVILION FRONT & SIDE ELEVATION
5
WILLITON PAVILION PROJECT
SITE PLAN (MUGA)
6
WILLITON PAVILION PROJECT
(MUGA) LIGHTING
7
WILLITON PAVILION PROJECT
REMODELLING OLD BUILDING
8
9
WILLITON PARISH COUNCIL
PROJECT UPDATE
FULL PLANNING APPROVAL - 4TH DECEMBER 2014
PLANNING CONDITIONS – COST IMPACT RAIN WATER ATTENUATION TANK BIN STORE LANDSCAPED EARTH BANK WITH INTEGRAL SEATING– MUGA ACOUSTIC DESIGN REQUIREMENTS GRASS CRETE SURFACING LANDSCAPING
FRAME WORK AGREEMENT IN PLACE WITH THE DOCTORS MONEY PAID FOR THE LAND – TO BE INVESTED IN IMPROVEMENTS TO THE
SURGERY PREMISES.
FUNDING – BID SUPPORT COMMUNITY COUNCIL FOR SOMERSET ENGAGE WEST SOMERSET ( LINKED TO SOMERSET ACTIVITY SPORTS
PARTNERSHIP)
10
WILLITON PARISH COUNCIL
PROJECT SUPPORT
ORGANISATIONS THAT HAVE EXPRESSED THEIR SUPPORT WEST SOMERSET COUNCIL WILLITON DOCTORS PRACTICE REMINISCENCE LEARNING (ARCHIE PROJECT) SOMERSET ACTIVITIES SPORTS PARTNERSHIP FOOTBALL FOUNDATION
LETTERS OF SUPPORT MEMBERS OF THE BUSINESS COMMUNITY THE POLICE MINEHEAD EYE WILLITON BOWLS CLUB WILLITON FOOTBALL CLUB WASPS VARIOUS OTHER LOCAL ORGANISATIONS, CLUBS AND INDIVIDUALS
11
WILLITON PARISH COUNCIL
PROJECT SUPPORT
POTENTIAL USAGE – ADDITIONS
WEST SOMERSET COUNCIL VENUE FOR HEALTH AND WELLBEING FAIR PUBLIC MEETINGS.
PHYSIO BASED ACTIVITIES – CURRENTLY HELD IN MINEHEAD AND WATCHET
LUNCHEON CLUB – ACTIVE LIVING ADDRESS GROWTH IN LONELINESS
HEALTH AND WELLBEING FAIR OUTPUT
ANNUAL FOOTBALL FESTIVAL REGULAR BOOKINGS
FILM CLUB
12
WILLITON PARISH COUNCIL
PROJECT CONTENT PLANNING BASELINE PROVIDES AN OPPORTUNITY TO BETTER
UNDERSTAND THE PROJECT CONTENT & COST.
PHASE 1 – PAVILION AND INFRASTRUCTURE ARCHITECT AND PROFESSIONAL FEES NEW BUILDING USER EQUIPMENT ACCESS & DISABLED PARKING NEW PEDESTRIAN LINKS, LIGHTING AND FENCING NEW HARD STANDING ASSEMBLY AREA REMEMBRANCE GARDEN
PHASE 2- MUGA MUGA & FLOODLIGHTING NEW EARTH BANK LANDSCAPING
PHASE 3 - REMODELLING OF THE OLD BUILDING NEW UNISEX DISABLED PUBLIC TOILET
13
WILLITON PARISH COUNCIL
PROJECT COST – PHASES 1,2 & 3
OUTSET PRICING BASED ON ARCHITECTS ESTIMATES OTHER LIKE PROJECTS.
NETHER STOWEY - MUGA LANGFORD BUDVILLE VH & MINEHEAD PAVILION
ESTIMATED PROJECT COST - £1.1M to £1.2M
FOLLOWING PLANNING APPROVAL INDICATIVE PRICING TO OBTAIN FUNDING - £1.5M UNDERLYING COST IS ESTIMATED AT £1.3M TO £1.4M
EXPECTED TENDERED PRICE - £1.2M TO £1.3M
14
WILLITON PARISH COUNCIL
PROJECT TIMETABLE
OBTAIN FUNDING – JUNE TO NOVEMBER 2015
COMMENCE CONSTRUCTION PHASE 1– 2ND QTR 2016
COMPLETE PHASE 1 PAVILION – 1ST QTR 2017
COMPLETE PHASE 2 MUGA – 4TH QTR 2017
COMPLETE PHASE 3 REMODELLING OLD BLD’G - 4TH QTR 2018